39
© 2015 Electric Power Research Institute, Inc. All rights reserved. Richard Reid, PhD Program Manager 2015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI Decommissioning Program Pre-Planning and Early Decommissioning Tasks

Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

  • Upload
    dodieu

  • View
    218

  • Download
    3

Embed Size (px)

Citation preview

Page 1: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

© 2015 Electric Power Research Institute, Inc. All rights reserved.

Richard Reid, PhD

Program Manager

2015 Workshop on Nuclear Power Plant

Decommissioning

2015 March 18

Lessons Learned from

EPRI

Decommissioning

ProgramPre-Planning and Early

Decommissioning Tasks

Page 2: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

2© 2015 Electric Power Research Institute, Inc. All rights reserved.

Discussion Topics

Decommissioning Strategy and Decisions

Transition from Operation to Decommissioning

Ten Key Decommissioning Questions

Page 3: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

3© 2015 Electric Power Research Institute, Inc. All rights reserved.

Decommissioning Options

US Regulation: Decommissioning

(license termination) must be completed

within 60 years of permanent plant

shutdown

The NRC defines three approaches to

decommissioning*:

– DECON: Prompt dismantlement

– SAFSTOR: Plant defueled and

maintained in a safe condition

– ENTOMB: Plant permanently

enclosed within a robust structure

Similar options outside of the US

– Time to complete decommissioning

varies

* http://www.nrc.gov/reading-rm/doc-collections/fact-sheets/decommissioning.html

Page 4: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

4© 2015 Electric Power Research Institute, Inc. All rights reserved.

Decommissioning Decisions for

the Future Use of the Site

Setting the end goal of decommissioning impacts key decommissioning strategies, site release limits and costs

Site End State Decisions:

– Utility retains ownership or site released to public?

– Site released with buildings demolished or standing?

– Future use of the site:

Unrestricted Release:

– Residential (Resident Farmer)

– Industrial

Restricted Release : Institutional controls enforce land use restrictions and allow higher release limits

Trojan Plant - Unrestricted Release

Yankee Rowe Plant - Unrestricted

Release

Page 5: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

5© 2015 Electric Power Research Institute, Inc. All rights reserved.

Decommissioning Strategy and Decisions

Future Use of the Site

Important to decided on decommissioning end state early in the planning process.

Involves/Requires discussions with regulators

Site Release Criteria and Limits:

– Concentration set by regulator or dose based (i.e., 0.25 mSv/yr dose limit in U.S.)

– Resident Farmer Scenario – Relatively lower radionuclide concentration limits allowed

– Industrial Use Scenario – Relatively higher concentrations allowed

EPRI Report 1015500 “Final Status Survey and Site Release Experience Report” (2008)

Page 6: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

6© 2015 Electric Power Research Institute, Inc. All rights reserved.

Decommissioning Strategies and Decisions

Management and Disposition of Spent Fuel

Plant Shutdown

Spent Fuel Pool Isolated

ONSITE - Interim Spent Fuel Storage Installation (ISFSI)

OFFSITE – Final Disposal or Storage

ONSITE – Fuel Transfer Casks

OFFSITE – Final Disposal or Storage

In United States, Federal

Government is responsible for

final disposal of spent fuel

Disposal site not yet identified

Spent fuel is stored on-site in

ISFSIs until disposal site is

operational.

Plants have decommissioned and

terminated original license while

maintaining a different license to

manage ISFSIs.

Page 7: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

7© 2015 Electric Power Research Institute, Inc. All rights reserved.

Future Use of the Site & Spent Fuel Storage

Connecticut Yankee – Resident Farmer Scenario

Dry Fuel

Storage

Facility

Page 8: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

8© 2015 Electric Power Research Institute, Inc. All rights reserved.

Future Use of the Site & Spent Fuel Storage

Rancho Seco – Industrial Use Scenario

Intermediate

Level Waste

Storage Facility

Page 9: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

9© 2015 Electric Power Research Institute, Inc. All rights reserved.

Decommissioning Strategy and Decisions -

Full System Decontamination

Conducted before major plant systems are retired (e.g. reactor coolant pumps)

Facilitates Decommissioning

– Reduces contamination within plant systems

– Reduces dose rates to workers during decommissioning

Industry Experiences: Connecticut Yankee (US), Jose Cabrera (Spain), Barsebäck (Sweden), Unterwesser (Germany) and others

EPRI Decontamination for Decommissioning (DfD) Process Available

Page 10: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

10© 2015 Electric Power Research Institute, Inc. All rights reserved.

Other Decommissioning Strategies and Decisions

Reactor Vessel and Internals Disposition

– Dispose whole/intact (e.g. grouted)

– Dispose with segmented internals (intact vessel)

– Dispose segmented vessel and internals

– Technology

Waste Management and Disposal

– Availability of radioactive waste disposal site

– Availability of very low level waste category and clearance level

– Availability of industrial waste sites

Page 11: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

11© 2015 Electric Power Research Institute, Inc. All rights reserved.

Decommissioning Process

Typical Decommissioning Sequences During Phases

– Pre-Decommissioning (Transition) Phase

– Phase 1: Moving Fuel to Dry Fuel Storage

– Phase 2: Highly Contaminated Systems Removal

– Phase 3: Remaining Systems Being Removed

– Phase 4: Buildings Being Decontaminated

– Phase 5: Final Remediation and Site Release

Page 12: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

12© 2015 Electric Power Research Institute, Inc. All rights reserved.

Pre-Decommissioning (Transition) Phase

Large volume of Licensing and Engineering work need to

change the Design Basis of the plant to Permanently

Defueled

– Safety Analysis Report

– Downgrade of Systems

– Technical Specifications

– Program and Procedures

Create a Decommissioning Plan

– Exposure and Waste Estimates

– Dismantlement and Decontamination Methods to be used

– Site Release Criteria Development and Final Status Survey Methods

Page 13: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

13© 2015 Electric Power Research Institute, Inc. All rights reserved.

Decommissioning Planning (Oyster Creek Plan)*

1. Cost Estimate

& Funding

Assurance

2. Summary

Level Schedule

3. Management

Issues

4. Pre-Shutdown

Operations

Practices

5. Organization &

Staffing Planning

6. Community

Relations &

Stakeholder

Communications

7. Certifications,

Exemptions,

Requests & Fee

Relief

8. Exposure

Estimate

9. Environment

Assessment

(Environment

Report)

10. Post

Shutdown Report

Preparation

11. Spent Fuel

Storage

12. Accident

Analysis & SFP

Heatup

Calculation

13. Defueled

Technical

Specifications

14. Occupational

Safety

15. Vendor

Assessment &

Selection

Recommend-

ations

16. Project

Controls

17. Historical Site

Assessment

18. Site

Characterization

19. Federal /

State / Local

Regulatory

Compliance

20. Safety

Analysis Update

Plan

21. License

Termination Plan

22. System ID &

Reclassification

23. Programmatic

Revisions

24. QA Program

Plam

25. Work

Processes &

Procedures

Reviews

26. Systems &

Structures

Decontamination

27. RPV & Large

Components

Removal &

Shipping

28. Deconstruc-

tion Power Study

29. Area Based

Work Plan &

Integrated

Schedule

30. Dismantle-

ment Major Task

Sequence

31. LLW Liquids,

Solids, & Mixed

Radioactive

Waste

32. Hazardous

Waste Disposal

(Non-Rad)

IN SEQUENCE

IN P

AR

AL

LE

L

ENGINEERING

LICENSING / OPERATIONS / TRAINING / QA

ENVIRONMENTAL MANAGEMENT

MANAGEMENT / FINANCE / HUMAN RESOURCES

LEGEND

*Reference: EPRI Report # 1000093, Preparing for Decommissioning – The Oyster Creek

Experience, Jun. 00

Page 14: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

14© 2015 Electric Power Research Institute, Inc. All rights reserved.

Phase 1

Moving Fuel to Dry Fuel Storage or Off-site

– Necessary Systems Repowered

– Plan/Contract for Major Projects (i.e. Chemical Decon, Reactor Removal)

– Reason Done First:

Allows Reduction in Secure Area

Allows Downgrading and Removal of Unnecessary Systems

Page 15: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

15© 2015 Electric Power Research Institute, Inc. All rights reserved.

Phases 2 and 3

Phase 2: Highly Contaminated Systems Removal

– Primary Component Removal and Shipment for Disposal

– Fuel Pool Drained and Decontaminated

– Reason Done Second:

By Reducing Radiation Sources remainder of removals facilitated

Installed Plant Ventilation System Needed for Airborne Contamination Control

Phase 3: Remaining (Lower Activity) Systems Removed

– Reason Performed Third:

Systems Need to be Removed to Allow Building Decontamination

Less Building Ventilation Needed for Airborne Control (Use Portable Equipment)

Page 16: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

16© 2015 Electric Power Research Institute, Inc. All rights reserved.

Phases 4 and 5

• Phase 4: Building Decontamination to Site Release Limits

– Separation of contaminated and non-contaminated materials (e.g.

concrete)

– Waste management and optimization

– Outlying areas of the site may be released from the license

Phase 5: Final Remediation

and Site Release

– Building Demolition (if performed)

– Remediation of Soil and

Groundwater

– Final Site Survey Complete,

License Terminated

Page 17: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

17© 2015 Electric Power Research Institute, Inc. All rights reserved.

Ten Key Decommissioning Questions

1. What are the waste disposal options available?

2. What is the required form/packaging of the waste for disposal?

3. What are the disposition options for the spent fuel?

4. What is the end state of the site going to be?

5. What is the site release criteria set by the regulator?

6. What options to I have in setting the site release limits (i.e., residential, industrial, other scenarios)?

7. Do clearance and/or recycle regulatory criteria exist?

8. Do I promptly decommission or wait for the remaining plants on site to permanently shutdown?

9. Do I perform a full system chemical decontamination?

10. Does the regulator have a required schedule for preparation of decommissioning documents and/or completion of the decommissioning?

Page 18: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

18© 2015 Electric Power Research Institute, Inc. All rights reserved.

Comparison of Connecticut Yankee and Rancho Seco

Aspect of

Decommissioning

Connecticut

Yankee (CY)

Rancho Seco Result of Difference for

Rancho Seco

Future Use Resident Farmer IndustrialHigher Release Limits, Less

Decontamination and Waste

Buildings Surveyed for

ReleaseNo Yes

Higher Survey Cost, Much

Less Waste

Radiological Status of

Buildings & Land

Contamination

High incl. Alpha

Little

Contamination

Lower Decontamination Costs

and Much Less Waste

Activity in Reactor

InternalsVery High

Approximately

1/10th of CY

Easier, Less Costly Internal

Segmentation

Materials Surveyed for

ReleaseGenerally No

Yes if Likely to be

Successful

Less Waste and Disposal

Costs

Reactor Segmented No Yes Lower Disposal Costs

Groundwater

ContaminationYes No

No Waste, Very Low Survey

Costs

Final Survey

Instrumentation

Generally Hand

Held

Portable Gamma

SpectroscopySaved Time and Labor Costs

Total Decom. Cost $850 Million $424 Million Result of Factors Above

Page 19: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

19© 2015 Electric Power Research Institute, Inc. All rights reserved.

Early Decommissioning Tasks

Historical Site Assessment

Documentation of Changes to the Plant Design Basis

Early Regulatory Submittals

Planning for Major Decommissioning Projects

Page 20: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

20© 2015 Electric Power Research Institute, Inc. All rights reserved.

Historical Site Assessments

Review of plant events to identify areas of the site that may be contaminated with radioactive and/or hazardous materials

Historical Site Assessments include:

– Review of plant documentation (in the U.S. per NRC regulation 10CFR50.75(g)) requires documentation of leaks and spills; modifications of buildings and structures where radiological materials may be used or stored

– Interviews of plant personnel

The first step of site characterization and remediation decision making process (site characterization to be discussed this afternoon)

Page 21: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

21© 2015 Electric Power Research Institute, Inc. All rights reserved.

Typical Goals During Early Portions of Decommissioning –

US Experience

Reduction in Technical Specifications

Reduction in Operating Systems

Reduction/Modification of Necessary Programs

Eliminate Need for Off-site Emergency Plan

Perform Early Decommissioning Projects– Full System Chemical Decontamination

– Asbestos Insulation Removal

– Modify Building Containing Fuel Pool to Spent Fuel Pool Island (SFPI)

– Move Control Room

– Collapse Security Boundary to SFPI

Begin Planning for Long Lead Time Decommissioning Projects– Dry Fuel Storage

– Reactor and Reactor Internal Segmentation

Page 22: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

22© 2015 Electric Power Research Institute, Inc. All rights reserved.

NRC Regulation Important to Decommissioning

10 CFR 50.82: Termination of License

10 CFR 20: Standards of Protection Against Radiation

– Radiation Protection of Workers and Public

– Subpart E: Radiological Criteria for Release of the Site

10 CFR 61: License Requirement for Land Disposal of Radioactive

Waste

10 CFR 71: Packaging and Transportation of Radioactive Material

10 CFR 100: Radiological Consequences of Accidents

10 CFR 50, Appendix I: Radioactive Effluents

40 CFR 190: Environmental Radiation Protection Standards for

Nuclear Power Plants (US Environmental Protection Agency)

Bolded Items Contain Decommissioning Specific Requirements

Page 23: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

23© 2015 Electric Power Research Institute, Inc. All rights reserved.

Basis Documents Prepared During Early

Decommissioning in US

Submittals Made in Accordance with NRC Reg. 10 CFR 50.82:

– Certification to NRC of Permanent Defueled Status

– Post Shutdown Decommissioning Activities Report (PSDAR):

General description of plan for the decommissioning

Includes estimate of personnel dose and RadWaste quantities expected

Revise Licensing Design Basis to Reflect Permanently Defueled Condition in Defueled Safety Analysis Report:

– Deletes abandoned systems

– Revises design basis accidents to those relevant during decommissioning

– Defines necessary Systems, Structures and Components (SSCs)

Revised Technical Specifications

Revised Emergency Plan

All of the documents could be prepared before plant shutdown to facilitate the transition to decommissioning

Page 24: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

24© 2015 Electric Power Research Institute, Inc. All rights reserved.

Typical Accident Analysis Calculations

Define Accidents Applicable During Decommissioning:

– Some Accidents Analyzed at US Sites:

Chemical Decontamination Resin Fire

Drop of Spent Fuel Assembly

Fire in Dry Active Waste Box

Vacuum Filter Bag Rupture

Liquid Propane Gas Explosion

Contamination Control Tent Rupture

Oxyacetylene Explosion

Filter Damage from Blast Surge

Page 25: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

25© 2015 Electric Power Research Institute, Inc. All rights reserved.

Key Aspects of US Decommissioning Requirements that

Differ from Other Countries (1/2)

United States:

– NRC approval not required to start plant dismantlement – Active

decommissioning can begin 90 days after submitting the PSDAR

– NRC does not approve “Means and Methods” used for dismantlement.

Can be changed as long as task is bounded by the “Decommissioning

Accidents”

– NRC is primarily concerned with Site Release Limits and the Final Status

Survey used to show compliance with these limits. License Termination

Plan (LTP) needs to be submitted at least 2 years before license

termination.

– NRC periodically inspects decommissioning activities primarily for

ALARA, excessive RadWaste quantities and accuracy of the Final

Status Survey

– Large Components can be disposed of in one piece

Page 26: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

26© 2015 Electric Power Research Institute, Inc. All rights reserved.

Key Aspects of US Decommissioning Requirements that

Differ from Other Countries (2/2)

Other Countries (Primarily European Experience)

– Detailed plan (with Means and Methods) needs to be submitted to the

regulator and a Special License granted before dismantlement can

begin

– Changes to the Means and Methods likely trigger a new review cycle

– Little clear regulatory guidance on Site Release Limits – Need to start

discussions with the regulator early to define the Decommissioning

End Point

– Some countries require Active Decommissioning to begin promptly

– Large Components generally need to be segmented prior to disposal

Page 27: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

27© 2015 Electric Power Research Institute, Inc. All rights reserved.

Example of Regulatory Approach in Countries Outside

the US – Spanish Experience

Page 28: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

28© 2015 Electric Power Research Institute, Inc. All rights reserved.

Preparation of Regulatory Documents Prior to Shutdown

(Spanish Experience)

Perform

Accident

Analyzes

Determine Safety

Related SSCs

Based on

Accident Analyzes

Revise FSAR to

Describe Transition

Period Activities,

Accident Analyses and

Safety Related SSCs

Determine

Transition

Period

Waste

Management

Activities

Estimate

Transition

Period

Waste

Types and

Volumes

Prepare Transition

Period Waste

Management Plan

Preparation of Regulatory Documents Prior to Shutdown

Define Transition

Period Accidents

and Assumptions

Revise Tech Specs

To Reflect Transition

Period SSCs and

Administrative

RequirementsSubmit

to

Regulator

Potential Submittals:

Decom. Cost Est.,

Quality Assurance Plan.

Revised Operator Quals

Emergency Plan,

Security and

Insurance Exemptions,

Dry Fuel Storage SARTwo Years

Before

Shutdown

One Year

Before

ShutdownPreparation Schedule

Page 29: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

29© 2015 Electric Power Research Institute, Inc. All rights reserved.

Critical Activities and Regulatory Document Preparation

During the Transition Period (Spanish Experience)

Package Operational

Waste and

Ship to Disposal Site

Build ISFSI, Dry Fuel Storage

Canisters and Other Equipment

Revise FSAR to Describe Dismantlement

Period Activities, Accident Analyses and

Safety Related SSCs

Estimate

Dismantlement

Period

Waste

Types and

Volumes

Prepare

Dismantlement

Period

Waste

Management

Plan

Critical Activities and Regulatory Document Preparation During Transition Period

Obtain Approval of

Dry Fuel Storage

SAR

Revise Tech

Specs to Reflect

Dismantlement

Period

Requirements

Submit

to

Regulator

Potential

Submittals:

Radiological

Site Release

Criteria, Any

Revisions to

Regulatory

Submittals

Transfer Fuel to ISFSI

Plant

Shutdown Task Schedule

One Year

Before End

Of Transition

Period

End of

Transition

Period

Page 30: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

30© 2015 Electric Power Research Institute, Inc. All rights reserved.

Transition Period Activities Needed to Reduce Overall

Decommissioning Cost & Schedule (Spanish Experience)

Perform Full System Chemical Decontamination

Award Contract for Reactor

Internals Segmentation

Perform Historical Site Assessment and Initial Site Characterization

Perform Building Modifications Needed

for Reactor and Reactor Internals

Segmentation Projects

Characterize

Reactor Vessel

and Internals

Major Transition Period Activities Needed to Reduce

Overall Decommissioning Cost and Schedule

Dispose of Irradiated Hardware

Acceptable at Disposal Site

Plant

Shutdown

End of

Transition

Period

Task Schedule

Page 31: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

31© 2015 Electric Power Research Institute, Inc. All rights reserved.

United States Experience with Technical Specification

Reduction

Page 32: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

32© 2015 Electric Power Research Institute, Inc. All rights reserved.

US Experience – Examples of Technical Specification

Reductions Shortly After Permanent Shutdown

Technical Specifications Removed– Reactor Reactivity Control Systems

– Instrumentation – Reactor Protection, Fire Protection, Safeguard Activation

– Auxiliary Building Emergency Filter System

– Electric Power Supply Systems

– Special Test Exceptions

– Gaseous Waste Treatment System

– Spent Fuel Pool Storage and Cooling System – Instrumentation

Page 33: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

33© 2015 Electric Power Research Institute, Inc. All rights reserved.

Technical Specification/Emergency Plan Requirements

During Wet Fuel Storage

Technical Specifications Reduced To the Following Once

Plant Declared in “Permanently Defueled”:

– Certified Fuel Handler/Administrative Controls

– Seismic Monitoring Instrumentation

– Crane Travel/Load Limitations

– Pool Water Level/Temperature Limitations

– Reactivity Controls/Burnup Requirements

– Fuel Pool Boron Concentration

– Effluent/Meteorological Instrumentation/Reporting

Emergency Plan Changes (Site with no Operating Plants)

– Reduced Radiological Consequences of Accidents

– Less Personnel On-Call, Reporting Time Requirements

Page 34: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

34© 2015 Electric Power Research Institute, Inc. All rights reserved.

Technical Specification/Emergency Plan Requirements

During Dry Fuel Storage

Technical Specifications Reduced Further to the Following:

– Most Apply During Loading of the Dry Storage Canisters

Drying Time/Vacuum Pressure

Canister Leak Testing

Canister Contamination/Dose Rate Limitations

– Only Tech Specs Applicable After Fuel Loading Complete:

Cask Heat Removal System Operable (Passive System)

Surveillance After Natural Phenomena (i.e. Earthquake)

Further Emergency Plan Changes

– No Credible Accidents, No Effluents

– No On-Call Requirements

– Security Response Available

– Any need for Clean-up Personnel arranged after the event

Page 35: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

35© 2015 Electric Power Research Institute, Inc. All rights reserved.

Other Potential Document Changes During Pre-

Shutdown Period – US Experience

Regulatory Required in the US:– Plant Procedures

– Plant Program Descriptions

– Technical Requirement Manual

– 10 CFR 50.59 screenings/determinations,

– Safety classification change documentation, as required.

– Radiological Effluent Monitoring/Off-Site Dose Calculation Manual

Documents to Optimize Efficiency of the Decommissioning: – Prepare Strategic Plans for the Decommissioning

– Define the Decommissioning Organization/Human Resources Plan

– Perform Historical Site Assessment (Precursor to Site Characterization)

– Prepare Site Characterization Plan

– Prepare Communication Plan

– Redesign Work Control Process

– Evaluate Chemical Decontamination Process and Award Contract, if applicable

Page 36: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

36© 2015 Electric Power Research Institute, Inc. All rights reserved.

Summary of Early Decommissioning Tasks and

Regulatory Submittals

Performance of certain tasks (i.e., Historical Site Assessment) and the planning and preparation for early decommissioning projects before shutdown can facilitate decommissioning and reduce overall costs

Preparation of regulatory documents needed prior to and during the early periods of a decommissioning is a major effort

The early periods of the decommissioning can proceed more efficiently if preparation of regulatory documents begins 2 or 3 years prior to plant shutdown

Preparations of other (non-regulatory) studies and plans can reduce cost during the early periods of a decommissioning

Page 37: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

37© 2015 Electric Power Research Institute, Inc. All rights reserved.

Conclusions

Decommissioning is a step by step process

Experience shows that knowing the end state of

decommissioning is important in making key

decommissioning decisions

Preparing Transition Period Document early can facilitate

decommissioning

Experiences and lessons learned for completing specific

tasks and entire decommissioning projects are valuable

Page 38: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

38© 2015 Electric Power Research Institute, Inc. All rights reserved.

Additional Information in EPRI Reports

Recent United States and International Experiences in

Reactor Vessel and Internals Segmentation. (1023024,

2011)

Decommissioning Experiences and Lessons Learned:

Decommissioning Costs. (1023025, 2011)

Power Reactor Decommissioning Experience. (1023456,

2011)

U.S. Nuclear Plant Decommissioning Lessons Learned.

(1021107, 2010)

Final Status Survey and Site Release Experience Report

(1015500, 2008)

Page 39: Lessons Learned from EPRI Decommissioning Program …€¦ ·  · 2015-03-182015 Workshop on Nuclear Power Plant Decommissioning 2015 March 18 Lessons Learned from EPRI ... (i.e

39© 2015 Electric Power Research Institute, Inc. All rights reserved.

Together…Shaping the Future of Electricity