Upload
dodieu
View
218
Download
3
Embed Size (px)
Citation preview
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Richard Reid, PhD
Program Manager
2015 Workshop on Nuclear Power Plant
Decommissioning
2015 March 18
Lessons Learned from
EPRI
Decommissioning
ProgramPre-Planning and Early
Decommissioning Tasks
2© 2015 Electric Power Research Institute, Inc. All rights reserved.
Discussion Topics
Decommissioning Strategy and Decisions
Transition from Operation to Decommissioning
Ten Key Decommissioning Questions
3© 2015 Electric Power Research Institute, Inc. All rights reserved.
Decommissioning Options
US Regulation: Decommissioning
(license termination) must be completed
within 60 years of permanent plant
shutdown
The NRC defines three approaches to
decommissioning*:
– DECON: Prompt dismantlement
– SAFSTOR: Plant defueled and
maintained in a safe condition
– ENTOMB: Plant permanently
enclosed within a robust structure
Similar options outside of the US
– Time to complete decommissioning
varies
* http://www.nrc.gov/reading-rm/doc-collections/fact-sheets/decommissioning.html
4© 2015 Electric Power Research Institute, Inc. All rights reserved.
Decommissioning Decisions for
the Future Use of the Site
Setting the end goal of decommissioning impacts key decommissioning strategies, site release limits and costs
Site End State Decisions:
– Utility retains ownership or site released to public?
– Site released with buildings demolished or standing?
– Future use of the site:
Unrestricted Release:
– Residential (Resident Farmer)
– Industrial
Restricted Release : Institutional controls enforce land use restrictions and allow higher release limits
Trojan Plant - Unrestricted Release
Yankee Rowe Plant - Unrestricted
Release
5© 2015 Electric Power Research Institute, Inc. All rights reserved.
Decommissioning Strategy and Decisions
Future Use of the Site
Important to decided on decommissioning end state early in the planning process.
Involves/Requires discussions with regulators
Site Release Criteria and Limits:
– Concentration set by regulator or dose based (i.e., 0.25 mSv/yr dose limit in U.S.)
– Resident Farmer Scenario – Relatively lower radionuclide concentration limits allowed
– Industrial Use Scenario – Relatively higher concentrations allowed
EPRI Report 1015500 “Final Status Survey and Site Release Experience Report” (2008)
6© 2015 Electric Power Research Institute, Inc. All rights reserved.
Decommissioning Strategies and Decisions
Management and Disposition of Spent Fuel
Plant Shutdown
Spent Fuel Pool Isolated
ONSITE - Interim Spent Fuel Storage Installation (ISFSI)
OFFSITE – Final Disposal or Storage
ONSITE – Fuel Transfer Casks
OFFSITE – Final Disposal or Storage
In United States, Federal
Government is responsible for
final disposal of spent fuel
Disposal site not yet identified
Spent fuel is stored on-site in
ISFSIs until disposal site is
operational.
Plants have decommissioned and
terminated original license while
maintaining a different license to
manage ISFSIs.
7© 2015 Electric Power Research Institute, Inc. All rights reserved.
Future Use of the Site & Spent Fuel Storage
Connecticut Yankee – Resident Farmer Scenario
Dry Fuel
Storage
Facility
8© 2015 Electric Power Research Institute, Inc. All rights reserved.
Future Use of the Site & Spent Fuel Storage
Rancho Seco – Industrial Use Scenario
Intermediate
Level Waste
Storage Facility
9© 2015 Electric Power Research Institute, Inc. All rights reserved.
Decommissioning Strategy and Decisions -
Full System Decontamination
Conducted before major plant systems are retired (e.g. reactor coolant pumps)
Facilitates Decommissioning
– Reduces contamination within plant systems
– Reduces dose rates to workers during decommissioning
Industry Experiences: Connecticut Yankee (US), Jose Cabrera (Spain), Barsebäck (Sweden), Unterwesser (Germany) and others
EPRI Decontamination for Decommissioning (DfD) Process Available
10© 2015 Electric Power Research Institute, Inc. All rights reserved.
Other Decommissioning Strategies and Decisions
Reactor Vessel and Internals Disposition
– Dispose whole/intact (e.g. grouted)
– Dispose with segmented internals (intact vessel)
– Dispose segmented vessel and internals
– Technology
Waste Management and Disposal
– Availability of radioactive waste disposal site
– Availability of very low level waste category and clearance level
– Availability of industrial waste sites
11© 2015 Electric Power Research Institute, Inc. All rights reserved.
Decommissioning Process
Typical Decommissioning Sequences During Phases
– Pre-Decommissioning (Transition) Phase
– Phase 1: Moving Fuel to Dry Fuel Storage
– Phase 2: Highly Contaminated Systems Removal
– Phase 3: Remaining Systems Being Removed
– Phase 4: Buildings Being Decontaminated
– Phase 5: Final Remediation and Site Release
12© 2015 Electric Power Research Institute, Inc. All rights reserved.
Pre-Decommissioning (Transition) Phase
Large volume of Licensing and Engineering work need to
change the Design Basis of the plant to Permanently
Defueled
– Safety Analysis Report
– Downgrade of Systems
– Technical Specifications
– Program and Procedures
Create a Decommissioning Plan
– Exposure and Waste Estimates
– Dismantlement and Decontamination Methods to be used
– Site Release Criteria Development and Final Status Survey Methods
13© 2015 Electric Power Research Institute, Inc. All rights reserved.
Decommissioning Planning (Oyster Creek Plan)*
1. Cost Estimate
& Funding
Assurance
2. Summary
Level Schedule
3. Management
Issues
4. Pre-Shutdown
Operations
Practices
5. Organization &
Staffing Planning
6. Community
Relations &
Stakeholder
Communications
7. Certifications,
Exemptions,
Requests & Fee
Relief
8. Exposure
Estimate
9. Environment
Assessment
(Environment
Report)
10. Post
Shutdown Report
Preparation
11. Spent Fuel
Storage
12. Accident
Analysis & SFP
Heatup
Calculation
13. Defueled
Technical
Specifications
14. Occupational
Safety
15. Vendor
Assessment &
Selection
Recommend-
ations
16. Project
Controls
17. Historical Site
Assessment
18. Site
Characterization
19. Federal /
State / Local
Regulatory
Compliance
20. Safety
Analysis Update
Plan
21. License
Termination Plan
22. System ID &
Reclassification
23. Programmatic
Revisions
24. QA Program
Plam
25. Work
Processes &
Procedures
Reviews
26. Systems &
Structures
Decontamination
27. RPV & Large
Components
Removal &
Shipping
28. Deconstruc-
tion Power Study
29. Area Based
Work Plan &
Integrated
Schedule
30. Dismantle-
ment Major Task
Sequence
31. LLW Liquids,
Solids, & Mixed
Radioactive
Waste
32. Hazardous
Waste Disposal
(Non-Rad)
IN SEQUENCE
IN P
AR
AL
LE
L
ENGINEERING
LICENSING / OPERATIONS / TRAINING / QA
ENVIRONMENTAL MANAGEMENT
MANAGEMENT / FINANCE / HUMAN RESOURCES
LEGEND
*Reference: EPRI Report # 1000093, Preparing for Decommissioning – The Oyster Creek
Experience, Jun. 00
14© 2015 Electric Power Research Institute, Inc. All rights reserved.
Phase 1
Moving Fuel to Dry Fuel Storage or Off-site
– Necessary Systems Repowered
– Plan/Contract for Major Projects (i.e. Chemical Decon, Reactor Removal)
– Reason Done First:
Allows Reduction in Secure Area
Allows Downgrading and Removal of Unnecessary Systems
15© 2015 Electric Power Research Institute, Inc. All rights reserved.
Phases 2 and 3
Phase 2: Highly Contaminated Systems Removal
– Primary Component Removal and Shipment for Disposal
– Fuel Pool Drained and Decontaminated
– Reason Done Second:
By Reducing Radiation Sources remainder of removals facilitated
Installed Plant Ventilation System Needed for Airborne Contamination Control
Phase 3: Remaining (Lower Activity) Systems Removed
– Reason Performed Third:
Systems Need to be Removed to Allow Building Decontamination
Less Building Ventilation Needed for Airborne Control (Use Portable Equipment)
16© 2015 Electric Power Research Institute, Inc. All rights reserved.
Phases 4 and 5
• Phase 4: Building Decontamination to Site Release Limits
– Separation of contaminated and non-contaminated materials (e.g.
concrete)
– Waste management and optimization
– Outlying areas of the site may be released from the license
Phase 5: Final Remediation
and Site Release
– Building Demolition (if performed)
– Remediation of Soil and
Groundwater
– Final Site Survey Complete,
License Terminated
17© 2015 Electric Power Research Institute, Inc. All rights reserved.
Ten Key Decommissioning Questions
1. What are the waste disposal options available?
2. What is the required form/packaging of the waste for disposal?
3. What are the disposition options for the spent fuel?
4. What is the end state of the site going to be?
5. What is the site release criteria set by the regulator?
6. What options to I have in setting the site release limits (i.e., residential, industrial, other scenarios)?
7. Do clearance and/or recycle regulatory criteria exist?
8. Do I promptly decommission or wait for the remaining plants on site to permanently shutdown?
9. Do I perform a full system chemical decontamination?
10. Does the regulator have a required schedule for preparation of decommissioning documents and/or completion of the decommissioning?
18© 2015 Electric Power Research Institute, Inc. All rights reserved.
Comparison of Connecticut Yankee and Rancho Seco
Aspect of
Decommissioning
Connecticut
Yankee (CY)
Rancho Seco Result of Difference for
Rancho Seco
Future Use Resident Farmer IndustrialHigher Release Limits, Less
Decontamination and Waste
Buildings Surveyed for
ReleaseNo Yes
Higher Survey Cost, Much
Less Waste
Radiological Status of
Buildings & Land
Contamination
High incl. Alpha
Little
Contamination
Lower Decontamination Costs
and Much Less Waste
Activity in Reactor
InternalsVery High
Approximately
1/10th of CY
Easier, Less Costly Internal
Segmentation
Materials Surveyed for
ReleaseGenerally No
Yes if Likely to be
Successful
Less Waste and Disposal
Costs
Reactor Segmented No Yes Lower Disposal Costs
Groundwater
ContaminationYes No
No Waste, Very Low Survey
Costs
Final Survey
Instrumentation
Generally Hand
Held
Portable Gamma
SpectroscopySaved Time and Labor Costs
Total Decom. Cost $850 Million $424 Million Result of Factors Above
19© 2015 Electric Power Research Institute, Inc. All rights reserved.
Early Decommissioning Tasks
Historical Site Assessment
Documentation of Changes to the Plant Design Basis
Early Regulatory Submittals
Planning for Major Decommissioning Projects
20© 2015 Electric Power Research Institute, Inc. All rights reserved.
Historical Site Assessments
Review of plant events to identify areas of the site that may be contaminated with radioactive and/or hazardous materials
Historical Site Assessments include:
– Review of plant documentation (in the U.S. per NRC regulation 10CFR50.75(g)) requires documentation of leaks and spills; modifications of buildings and structures where radiological materials may be used or stored
– Interviews of plant personnel
The first step of site characterization and remediation decision making process (site characterization to be discussed this afternoon)
21© 2015 Electric Power Research Institute, Inc. All rights reserved.
Typical Goals During Early Portions of Decommissioning –
US Experience
Reduction in Technical Specifications
Reduction in Operating Systems
Reduction/Modification of Necessary Programs
Eliminate Need for Off-site Emergency Plan
Perform Early Decommissioning Projects– Full System Chemical Decontamination
– Asbestos Insulation Removal
– Modify Building Containing Fuel Pool to Spent Fuel Pool Island (SFPI)
– Move Control Room
– Collapse Security Boundary to SFPI
Begin Planning for Long Lead Time Decommissioning Projects– Dry Fuel Storage
– Reactor and Reactor Internal Segmentation
22© 2015 Electric Power Research Institute, Inc. All rights reserved.
NRC Regulation Important to Decommissioning
10 CFR 50.82: Termination of License
10 CFR 20: Standards of Protection Against Radiation
– Radiation Protection of Workers and Public
– Subpart E: Radiological Criteria for Release of the Site
10 CFR 61: License Requirement for Land Disposal of Radioactive
Waste
10 CFR 71: Packaging and Transportation of Radioactive Material
10 CFR 100: Radiological Consequences of Accidents
10 CFR 50, Appendix I: Radioactive Effluents
40 CFR 190: Environmental Radiation Protection Standards for
Nuclear Power Plants (US Environmental Protection Agency)
Bolded Items Contain Decommissioning Specific Requirements
23© 2015 Electric Power Research Institute, Inc. All rights reserved.
Basis Documents Prepared During Early
Decommissioning in US
Submittals Made in Accordance with NRC Reg. 10 CFR 50.82:
– Certification to NRC of Permanent Defueled Status
– Post Shutdown Decommissioning Activities Report (PSDAR):
General description of plan for the decommissioning
Includes estimate of personnel dose and RadWaste quantities expected
Revise Licensing Design Basis to Reflect Permanently Defueled Condition in Defueled Safety Analysis Report:
– Deletes abandoned systems
– Revises design basis accidents to those relevant during decommissioning
– Defines necessary Systems, Structures and Components (SSCs)
Revised Technical Specifications
Revised Emergency Plan
All of the documents could be prepared before plant shutdown to facilitate the transition to decommissioning
24© 2015 Electric Power Research Institute, Inc. All rights reserved.
Typical Accident Analysis Calculations
Define Accidents Applicable During Decommissioning:
– Some Accidents Analyzed at US Sites:
Chemical Decontamination Resin Fire
Drop of Spent Fuel Assembly
Fire in Dry Active Waste Box
Vacuum Filter Bag Rupture
Liquid Propane Gas Explosion
Contamination Control Tent Rupture
Oxyacetylene Explosion
Filter Damage from Blast Surge
25© 2015 Electric Power Research Institute, Inc. All rights reserved.
Key Aspects of US Decommissioning Requirements that
Differ from Other Countries (1/2)
United States:
– NRC approval not required to start plant dismantlement – Active
decommissioning can begin 90 days after submitting the PSDAR
– NRC does not approve “Means and Methods” used for dismantlement.
Can be changed as long as task is bounded by the “Decommissioning
Accidents”
– NRC is primarily concerned with Site Release Limits and the Final Status
Survey used to show compliance with these limits. License Termination
Plan (LTP) needs to be submitted at least 2 years before license
termination.
– NRC periodically inspects decommissioning activities primarily for
ALARA, excessive RadWaste quantities and accuracy of the Final
Status Survey
– Large Components can be disposed of in one piece
26© 2015 Electric Power Research Institute, Inc. All rights reserved.
Key Aspects of US Decommissioning Requirements that
Differ from Other Countries (2/2)
Other Countries (Primarily European Experience)
– Detailed plan (with Means and Methods) needs to be submitted to the
regulator and a Special License granted before dismantlement can
begin
– Changes to the Means and Methods likely trigger a new review cycle
– Little clear regulatory guidance on Site Release Limits – Need to start
discussions with the regulator early to define the Decommissioning
End Point
– Some countries require Active Decommissioning to begin promptly
– Large Components generally need to be segmented prior to disposal
27© 2015 Electric Power Research Institute, Inc. All rights reserved.
Example of Regulatory Approach in Countries Outside
the US – Spanish Experience
28© 2015 Electric Power Research Institute, Inc. All rights reserved.
Preparation of Regulatory Documents Prior to Shutdown
(Spanish Experience)
Perform
Accident
Analyzes
Determine Safety
Related SSCs
Based on
Accident Analyzes
Revise FSAR to
Describe Transition
Period Activities,
Accident Analyses and
Safety Related SSCs
Determine
Transition
Period
Waste
Management
Activities
Estimate
Transition
Period
Waste
Types and
Volumes
Prepare Transition
Period Waste
Management Plan
Preparation of Regulatory Documents Prior to Shutdown
Define Transition
Period Accidents
and Assumptions
Revise Tech Specs
To Reflect Transition
Period SSCs and
Administrative
RequirementsSubmit
to
Regulator
Potential Submittals:
Decom. Cost Est.,
Quality Assurance Plan.
Revised Operator Quals
Emergency Plan,
Security and
Insurance Exemptions,
Dry Fuel Storage SARTwo Years
Before
Shutdown
One Year
Before
ShutdownPreparation Schedule
29© 2015 Electric Power Research Institute, Inc. All rights reserved.
Critical Activities and Regulatory Document Preparation
During the Transition Period (Spanish Experience)
Package Operational
Waste and
Ship to Disposal Site
Build ISFSI, Dry Fuel Storage
Canisters and Other Equipment
Revise FSAR to Describe Dismantlement
Period Activities, Accident Analyses and
Safety Related SSCs
Estimate
Dismantlement
Period
Waste
Types and
Volumes
Prepare
Dismantlement
Period
Waste
Management
Plan
Critical Activities and Regulatory Document Preparation During Transition Period
Obtain Approval of
Dry Fuel Storage
SAR
Revise Tech
Specs to Reflect
Dismantlement
Period
Requirements
Submit
to
Regulator
Potential
Submittals:
Radiological
Site Release
Criteria, Any
Revisions to
Regulatory
Submittals
Transfer Fuel to ISFSI
Plant
Shutdown Task Schedule
One Year
Before End
Of Transition
Period
End of
Transition
Period
30© 2015 Electric Power Research Institute, Inc. All rights reserved.
Transition Period Activities Needed to Reduce Overall
Decommissioning Cost & Schedule (Spanish Experience)
Perform Full System Chemical Decontamination
Award Contract for Reactor
Internals Segmentation
Perform Historical Site Assessment and Initial Site Characterization
Perform Building Modifications Needed
for Reactor and Reactor Internals
Segmentation Projects
Characterize
Reactor Vessel
and Internals
Major Transition Period Activities Needed to Reduce
Overall Decommissioning Cost and Schedule
Dispose of Irradiated Hardware
Acceptable at Disposal Site
Plant
Shutdown
End of
Transition
Period
Task Schedule
31© 2015 Electric Power Research Institute, Inc. All rights reserved.
United States Experience with Technical Specification
Reduction
32© 2015 Electric Power Research Institute, Inc. All rights reserved.
US Experience – Examples of Technical Specification
Reductions Shortly After Permanent Shutdown
Technical Specifications Removed– Reactor Reactivity Control Systems
– Instrumentation – Reactor Protection, Fire Protection, Safeguard Activation
– Auxiliary Building Emergency Filter System
– Electric Power Supply Systems
– Special Test Exceptions
– Gaseous Waste Treatment System
– Spent Fuel Pool Storage and Cooling System – Instrumentation
33© 2015 Electric Power Research Institute, Inc. All rights reserved.
Technical Specification/Emergency Plan Requirements
During Wet Fuel Storage
Technical Specifications Reduced To the Following Once
Plant Declared in “Permanently Defueled”:
– Certified Fuel Handler/Administrative Controls
– Seismic Monitoring Instrumentation
– Crane Travel/Load Limitations
– Pool Water Level/Temperature Limitations
– Reactivity Controls/Burnup Requirements
– Fuel Pool Boron Concentration
– Effluent/Meteorological Instrumentation/Reporting
Emergency Plan Changes (Site with no Operating Plants)
– Reduced Radiological Consequences of Accidents
– Less Personnel On-Call, Reporting Time Requirements
34© 2015 Electric Power Research Institute, Inc. All rights reserved.
Technical Specification/Emergency Plan Requirements
During Dry Fuel Storage
Technical Specifications Reduced Further to the Following:
– Most Apply During Loading of the Dry Storage Canisters
Drying Time/Vacuum Pressure
Canister Leak Testing
Canister Contamination/Dose Rate Limitations
– Only Tech Specs Applicable After Fuel Loading Complete:
Cask Heat Removal System Operable (Passive System)
Surveillance After Natural Phenomena (i.e. Earthquake)
Further Emergency Plan Changes
– No Credible Accidents, No Effluents
– No On-Call Requirements
– Security Response Available
– Any need for Clean-up Personnel arranged after the event
35© 2015 Electric Power Research Institute, Inc. All rights reserved.
Other Potential Document Changes During Pre-
Shutdown Period – US Experience
Regulatory Required in the US:– Plant Procedures
– Plant Program Descriptions
– Technical Requirement Manual
– 10 CFR 50.59 screenings/determinations,
– Safety classification change documentation, as required.
– Radiological Effluent Monitoring/Off-Site Dose Calculation Manual
Documents to Optimize Efficiency of the Decommissioning: – Prepare Strategic Plans for the Decommissioning
– Define the Decommissioning Organization/Human Resources Plan
– Perform Historical Site Assessment (Precursor to Site Characterization)
– Prepare Site Characterization Plan
– Prepare Communication Plan
– Redesign Work Control Process
– Evaluate Chemical Decontamination Process and Award Contract, if applicable
36© 2015 Electric Power Research Institute, Inc. All rights reserved.
Summary of Early Decommissioning Tasks and
Regulatory Submittals
Performance of certain tasks (i.e., Historical Site Assessment) and the planning and preparation for early decommissioning projects before shutdown can facilitate decommissioning and reduce overall costs
Preparation of regulatory documents needed prior to and during the early periods of a decommissioning is a major effort
The early periods of the decommissioning can proceed more efficiently if preparation of regulatory documents begins 2 or 3 years prior to plant shutdown
Preparations of other (non-regulatory) studies and plans can reduce cost during the early periods of a decommissioning
37© 2015 Electric Power Research Institute, Inc. All rights reserved.
Conclusions
Decommissioning is a step by step process
Experience shows that knowing the end state of
decommissioning is important in making key
decommissioning decisions
Preparing Transition Period Document early can facilitate
decommissioning
Experiences and lessons learned for completing specific
tasks and entire decommissioning projects are valuable
38© 2015 Electric Power Research Institute, Inc. All rights reserved.
Additional Information in EPRI Reports
Recent United States and International Experiences in
Reactor Vessel and Internals Segmentation. (1023024,
2011)
Decommissioning Experiences and Lessons Learned:
Decommissioning Costs. (1023025, 2011)
Power Reactor Decommissioning Experience. (1023456,
2011)
U.S. Nuclear Plant Decommissioning Lessons Learned.
(1021107, 2010)
Final Status Survey and Site Release Experience Report
(1015500, 2008)
39© 2015 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity