188
Level 1 & 3 ASP Seminar Liverpool Catholic Club 3 December 2015

Level 1 and 3 ASP Seminar Dec 2015

Embed Size (px)

DESCRIPTION

The notes from the Level 1 and 3 ASP seminar at Liverpool Catholic Club, Dec 2015.

Citation preview

Page 1: Level 1 and 3 ASP Seminar Dec 2015

Level 1 & 3

ASP Seminar

Liverpool Catholic Club

3 December 2015

Page 2: Level 1 and 3 ASP Seminar Dec 2015

AGENDA

1. Introduction

– Paul Hardman

2. Code of Conduct/Statement of Business Ethics & Safety

– Paul Hardman

HVNL Presentation

– Shannon Kyle

3. GIS CAD Update &

WAE Data Capture SAD0004

– Daryl Skene

4. Contestable Network – Key Performance Report

– Han Phan

5. Electrical Safety & Authorisations

– Terry Niemeier

6. ASP Investigation Procedure

– Fred Kaft

7. Network Mains Update

– David Shepherd

8. Contractor Operations Changes

– Ivan Mendonsa

9. LV Restoration Awareness

– Chris Srbinovski

10. Earthing Construction Refresher

– Simon Lewis/ Kris Shankar

11. ASP Activity Report

– Paul Hardman

12. Response to Issues from Last

Seminar

– Paul Hardman

13. General Business

– Paul Hardman

2

Page 3: Level 1 and 3 ASP Seminar Dec 2015

Paul Hardman

Introduction

3

01

Page 4: Level 1 and 3 ASP Seminar Dec 2015

4

WELCOME

• Thanks for your attendance.

• Presentations will proceed – questions on presentation material

will be addressed during or after the presentation.

• Individual/personal issues can be addressed after the seminar –

NOT during.

• Working papers will be on the ASP Website within 2 weeks of

the final seminar.

Page 5: Level 1 and 3 ASP Seminar Dec 2015

Paul Hardman

Code of Conduct/Statement of Business Ethics & Safety

5

02

Page 6: Level 1 and 3 ASP Seminar Dec 2015

Code of Conduct

• Values

– Safety Excellence

– Respect for People

– Customer and Community Focus

– Continuous Improvement

– Act with Integrity

6

Page 7: Level 1 and 3 ASP Seminar Dec 2015

Code of Conduct

• Ladder Of Escalation:

– 1. Speak Up

– 2. Escalate the issue / Make a disclosure

– 3. Seek external advice or report to an Authority

7

Page 8: Level 1 and 3 ASP Seminar Dec 2015

Code of Conduct

• Ethics Checklist

– I know the behaviour I need to adhere to that supports Endeavour

Energy’s Code Of Conduct

– I know what to do if I suspect I have a conflict of interest

– I know how to report issues if I see something that might be out of

step with our values

– If I see colleagues behaving inappropriately, I am prepared to

speak up

8

Page 9: Level 1 and 3 ASP Seminar Dec 2015

Code Of Conduct

• Corporate Statement:

– “For us, Ethics is about applying the principles and values in the

Code Of Conduct and our policies and procedures to help us make

the right choice”

9

Page 10: Level 1 and 3 ASP Seminar Dec 2015

Statement of Business Ethics

• Values – as shown in the Code Of Conduct

• Guiding Principles

– Safety

– Value for Money

– Open, Fair and Honest

• EE Procurement Process

• What you can expect from us

10

Page 11: Level 1 and 3 ASP Seminar Dec 2015

Statement of Business Ethics

• What we expect of you

– Be committed to Safety

– Adhere to our corporate values

– Comply with NSW Government lobbying protocol

– Comply with the ‘Competition and Consumer ACT 2010’

– Comply with NSW Government Procurement Guidelines

– Consequences for not complying

11

Page 12: Level 1 and 3 ASP Seminar Dec 2015

Statement of Business Ethics

• Guidance Notes:

– Gifts and Benefits

– Communication between parties

– Endeavour Energy’s employees and assets

– Conflicts of interest

– Confidentiality

– Contractors

– Intellectual property rights

12

Page 13: Level 1 and 3 ASP Seminar Dec 2015

Statement of Business Ethics

• Who to Contact

– Questions about “Business Ethics”

• 02 9853 6433

– Reporting possible wrongdoing

• Phone – 1800 ETHICS (1800 384 427)

• Email – [email protected]

• Letter – Group Head Of Audit

Endeavour Energy

PO Box 811

Seven Hills NSW 1730

13

Page 14: Level 1 and 3 ASP Seminar Dec 2015

14

Safety

• Safety Presentaton– HVNL – Chain of Responsibility (CoR)

Project, Fleet Services.

Page 15: Level 1 and 3 ASP Seminar Dec 2015

HVNL– Chain of

Responsibility

(CoR) Project,

Fleet Services

Prepared by: Shannon Kyle

HVNL Project Manager

ASP Presentation

December 2015

Page 16: Level 1 and 3 ASP Seminar Dec 2015

16

WHAT IS THE CHAIN OF RESPONSIBILITY?

• If you consign, pack, load or receive goods as part of your

business, you could be held legally liable for breaches of the

Heavy Vehicle National Law (HVNL) even though you have no

direct role in driving or operating a heavy vehicle. In addition,

corporate entities, directors, partners and managers are

accountable for the actions of people under their control. This is

the ‘chain of responsibility’ (CoR).

Page 17: Level 1 and 3 ASP Seminar Dec 2015

17

CoR BACKGROUND – PARTIES IN THE CHAIN

Page 18: Level 1 and 3 ASP Seminar Dec 2015

18

CoR BACKGROUND

• The aim of CoR is to make sure everyone in the supply chain

shares equal responsibility for ensuring breaches of the HVNL

do not occur. Under CoR laws if you exercise (or have the

capability of exercising) control or influence over any transport

task, you are part of the supply chain and therefore have a

responsibility to ensure the HVNL is complied with.

• The law recognises that multiple parties may be responsible for

offences committed by the drivers and operators of heavy

vehicles. A person may be a party in the supply chain in more

than one way. For example they may have duties as the

employer, the operator and the consigner of goods.

• Legal liability applies to all parties for their actions or inactions.

Page 19: Level 1 and 3 ASP Seminar Dec 2015

19

HOW DOES IT WORK?

• Offences in mass, dimension, load restraint, and driver fatigue

have been placed in risk based categories.

• Breaches of these laws are classed as minor, substantial,

severe or critical. This recognises that not all offences have the

same impact on safety or infrastructure.

• A range of penalties (for example, warnings, improvement

notices and prohibition orders) give courts greater enforcement

measures for penalising offences. They also help to prevent,

persuade and target the causes of breaches to ensure a culture

of compliance within the heavy vehicle industry.

Page 20: Level 1 and 3 ASP Seminar Dec 2015

20

RESPONSIBLE PARTIES

• The ‘responsible person’ concept makes the laws applicable to

a wide category of relevant persons responsible for the

transport of goods. For example:

– Heavy vehicle drivers must drive safely and within speed and

work/rest hour limits

– Loaders must load a vehicle safely and within mass and load

restraint requirements to ensure the load is safe for transport

– Consignors must ensure the delivery of goods does not require the

driver to exceed the permitted number of driving hours, fail to have

minimum rest periods or exceed the speed limits.

Page 21: Level 1 and 3 ASP Seminar Dec 2015

21

WHAT ARE THE CoR PENALTIES?

• Breaches of CoR can be both administrative and court imposed

and can be tailored to address specific types of offences.

• Examples of administrative penalties Roads and Maritime may

issue include:

– Improvement notices – identifies areas of risk and requires a

responsible person to address non-compliance

– Warnings – puts a responsible person on notice to address non-

compliance where a minor breach is detected

– Infringement notices – can be an alternative to court proceedings

for a less serious offence.

Page 22: Level 1 and 3 ASP Seminar Dec 2015

WHAT ARE THE CoR PENALTIES?

• Examples of court imposed penalties may include:

• Courts may issue fines as well as having the ability to impose:

– Supervisory intervention orders

– Licensing and registration sanctions

– Prohibition orders

– Commercial benefits penalties.

• In addition, body corporates may have a five times multiplier

imposed on their penalty.

22

Page 23: Level 1 and 3 ASP Seminar Dec 2015

WHAT IS INVOLVED IN A CoR INVESTIGATION?

• A specialist Compliance Investigation unit manages CoR

investigations.

• A CoR investigation may involve any of the following:

– Inspecting and searching appropriate business premises or

vehicles

– Requesting compliance related information, documentation or

contract records and names, and contact details of other

responsible people in the logistics chain

– Requiring reasonable assistance of relevant parties, including the

interpretation of data and other information

– Seizing of relevant electronic equipment.

23

Page 24: Level 1 and 3 ASP Seminar Dec 2015

WHAT IS A HEAVY VEHICLE?

24

Page 25: Level 1 and 3 ASP Seminar Dec 2015

WHAT IS A HEAVY VEHICLE?

• All of the vehicles above have a >12t GVM, and are Fatigue

Regulated Heavy Vehicles under the HVNL.

• The HVNL Project to date has focused on the fatigue related

obligations relating to these vehicle types

25

Page 26: Level 1 and 3 ASP Seminar Dec 2015

WHAT IS A HEAVY VEHICLE?

26

Page 27: Level 1 and 3 ASP Seminar Dec 2015

RAISING AWARENESS

• A factsheet on CoR and the associated reasonable steps for

each element of the HVNL legislation (Mass, Dimension, Load

Restraint, Speed & Fatigue) has been distributed to raise

awareness of CoR and help in the development of a current

training needs analysis based on responsible parties duties

under the legislation.

27

Page 28: Level 1 and 3 ASP Seminar Dec 2015

28

PROJECT OVERVIEW

• Heavy Vehicle National Law (HVNL) Project – Chain of

Responsibility (CoR)

– Project Statement:

Develop and implement a Chain of Responsibility (CoR) framework

across Endeavour Energy that will ensure transport safety risks are

managed and will limit the businesses exposure to any road transport

law prosecution. This will enable Endeavour Energy to adopt best

practice and provide suitable objective evidence to demonstrate that

reasonable steps have been taken to comply with heavy vehicle fatigue,

mass, dimension, load restraint and speed laws - keeping our drivers and

community safe.

More Information on CoR can be found at the above road regulator links

Page 29: Level 1 and 3 ASP Seminar Dec 2015

PROPOSED PROJECT WORKFLOW

Stage 3 - Implementation (Training & Compliance verification)

Modulated training package developed

Audit Tool and KPI’s developed

Audit function Transition to HSE Assurance

Transport provider accreditation programme

Stage 2 – CoR Commitment & Guidance Material developed

EE CoR policy/Code of Practice developed

CoR Handbook developed

IT solution developed Heavy Vehicle

Operators Manual updated

Compliance tools developed (forms,

factsheets, etc)

Stage 1 – Project Review & Gap/Training needs Analysis

HVNL Work Group Meetings Project Plans Training requirements identified

29

Page 30: Level 1 and 3 ASP Seminar Dec 2015

TRANSPORT SAFETY STRUCTURE(PROPOSED)

30

Page 31: Level 1 and 3 ASP Seminar Dec 2015

What changes will you see

• Driver declarations

• Sample weighing

• Load restraint

compliance checks

• Updated product mass

information

• Current tare weight

evidence available

(printed docket, no

more than 12 months

old)

31

Driver declaration: Circle

Are you fit for duty, free from the effects of drugs and

alcohol?

Y / N

Do you hold a current license for the class of vehicle you

are driving?

Y / N

Do you have available work time within regulated driving

hour’s requirements?

Y / N

Have you verified the load weight was gross and axle

mass compliant for your vehicle?

Y / N

Was the load restrained in accordance with Load Restraint

Guidelines?

Y / N

Driver Name:

(person

delivering)

Received by:

(Driver/on site

rep)

Page 32: Level 1 and 3 ASP Seminar Dec 2015

32

WATCH THIS SPACE – NTC REVIEW OF HVNL

• To better align with Australia’s national safety laws, improve

compliance and simplify enforcement, Australia’s transport

ministers have agreed the Heavy Vehicle National Law chain

of responsibility obligations should be reformed to provide a

more outcomes based approach, focussed on primary duties.

• These proposed reforms are limited to the existing regulatory

framework of the Heavy Vehicle National Law and to current

chain of responsibility parties, including executive officers.

• The intention of these reforms is not to extend the scope of

duties but to restructure and consolidate existing obligations

to ensure current parties in the chain of responsibility take a

performance based approach to their responsibilities.

• Detailed policy recommendations arising from this discussion

paper and the Roadworthiness Review will be considered by

ministers in November 2015.

Page 33: Level 1 and 3 ASP Seminar Dec 2015

QUESTIONS?

Thankyou for your time

Page 34: Level 1 and 3 ASP Seminar Dec 2015

IMPORTANT NOTICE

IN 051/15

Brian Berrell

Page 35: Level 1 and 3 ASP Seminar Dec 2015

Important Notice IN 051/15

35

Page 36: Level 1 and 3 ASP Seminar Dec 2015

Safety Bulletins

Paul Hardman

Page 37: Level 1 and 3 ASP Seminar Dec 2015

Safety Bulletins

37

• SB 16/15 – Cable jointing cut hand Lvl 1

• SB 15/14 – Temporary earthing connection All ASP’s

• SB 17/16 – Reverse polarity connection customer installation All ASP’s

• SB 18/15 – Failure of defective cable terminations All ASP’s

• SA 05/15 – Worker injury due to rope breaking during augmentation work All ASP’s

• SB 21/15 – Snakes and Wasps Notice All ASP’s

• SB 20/15 – Pole fell due to loading chance Lvl 1 & 2

• SB 19/15 – EWP – Fall from height Lvl 1 & 2

• SB 22/15 – Contractor working without Access Authority All ASP’s

• SB 23/15 – High Voltage Cable damage at Padmount Substation Lvl 1

• SB 24/15 – Stepping On and Off A Pole Platform Lvl 1 & 2

• SB 25/15 – Hazards of Making generator Connections to the LV Network Lvl 1

• SB 26/15 – High Voltage Cable Strike Lvl 1

Page 38: Level 1 and 3 ASP Seminar Dec 2015

GIS CAD Update & WAE Data Capture SAD0004

38

03 Daryl Skene

Page 39: Level 1 and 3 ASP Seminar Dec 2015

Network Data

Update

For ASPs

Page 40: Level 1 and 3 ASP Seminar Dec 2015

Current Situation

40

Versions currently available: GISCAD

2014 • Help Desk has been made available for GISCAD to all ASP Users

• New application delivery system has been developed with

Vendor

• Drawing Mgmt Project (DIS V2.0) Phase 1 FY Implemented

• Enhanced Validator to resolve trending issues FY Q1

Page 41: Level 1 and 3 ASP Seminar Dec 2015

41

Disturbing Trends

• We still have problems with Geomedia Webmap

Page 42: Level 1 and 3 ASP Seminar Dec 2015

42

Currently in Development

• GISCAD 2016 available FY Q3

• Webmap replacement project FY Q4

• GISCAD enhanced integration with Ellipse FY Q4

• Drawing Mgmt Project (DIS V2.0) Phase 2 FY Q4

• Ability to view designs (DIS V2.0) Phase 2 FY Q4

• SAD0001 and SAD0002 Standards updated Q3 or Q4

Page 43: Level 1 and 3 ASP Seminar Dec 2015

43

Questions or Suggestions???

Page 44: Level 1 and 3 ASP Seminar Dec 2015

Contestable Network – Key Performance Report

44

04 Han Phan

Page 45: Level 1 and 3 ASP Seminar Dec 2015

Contestable network activities and key performance

reports

• Application volume

• Acknowledgment letter KPI

• Supply offer KPI

• Design brief KPI

• Design certification KPI

• Design certification amendment quantities

• Gifted asset value

• Average Lead Time between:

– Application to Design Certification for Connection of Load Projects

– Application to Design Certification for Subdivision Projects

– L3 ASP on-board to Design Certification for Connection of Load Projects

– L3 ASP on-board to Design Certification for Subdivision Projects

45

Page 46: Level 1 and 3 ASP Seminar Dec 2015

Application volume

46

Page 47: Level 1 and 3 ASP Seminar Dec 2015

Acknowledgment letter KPI

47

Page 48: Level 1 and 3 ASP Seminar Dec 2015

Supply offer KPI

48

Page 49: Level 1 and 3 ASP Seminar Dec 2015

Design brief KPI

49

Page 50: Level 1 and 3 ASP Seminar Dec 2015

Design certification KPI

50

Page 51: Level 1 and 3 ASP Seminar Dec 2015

Gifted asset value

51

Page 52: Level 1 and 3 ASP Seminar Dec 2015

Design certification amendment quantities

52

Study period – 1 Oct 2014 to 31 Oct 2015 (13 months)

COL SUB COL SUB

A 403 437 312 343

B 88 120 61 103

C 15 19 4 11

D 2 3 1 1

E 0 1 0 0

Totals 508 580 378 458

Application to certification L3 on-board to certification

Amendment

Page 53: Level 1 and 3 ASP Seminar Dec 2015

Average Lead Time – Application to Design Certification for COL Projects

53

Notes:

• Amendment A of the design only

• Average lead time is 265 days or 8.83 months

Page 54: Level 1 and 3 ASP Seminar Dec 2015

Average Lead Time – Application to Design Certification for Sub Projects

54

Notes:

• Amendment A of the design only

• Average lead time is 251 days or 8.37 months

Page 55: Level 1 and 3 ASP Seminar Dec 2015

Average Lead Time – L3 ASP on-board to Certification for COL Projects

55

Notes:

• Amendment A of the design only

• Average lead time is 158 days or 5.27 months

Page 56: Level 1 and 3 ASP Seminar Dec 2015

Average Lead Time – L3 ASP on-board to Certification for Sub Projects

56

Notes:

• Amendment A of the design only

• Average lead time is 148 days or 4.93 months

Page 57: Level 1 and 3 ASP Seminar Dec 2015

Electrical Safety & Authorisations

57

05 Terry Niemeier

Page 58: Level 1 and 3 ASP Seminar Dec 2015

OVERVIEW

Authorisations

• Authorisations fees

• ID Photos

• Trade authorisations

• Safety Management systems

Training

• Close approach training

• ESR amendments

• Accredited RTOs

Electrical Safety

• Arc rated clothing

• Polarity testing

• ESR amendments

58

Page 59: Level 1 and 3 ASP Seminar Dec 2015

Authorisations

59

Page 60: Level 1 and 3 ASP Seminar Dec 2015

AUTHORISATIONS FEES

• From July 1 the AER has determined that this fee will increase

to;

– $428.38 (inc. GST) per year for renewed authorisations

– $477.27 (inc. GST) for new authorisations

• The increase was to ensure that connected or existing

customers do not pay for the administration of the authorisation

process

– The fee is cost reflective and removes cross subsidisation

60

Page 61: Level 1 and 3 ASP Seminar Dec 2015

AUTHORISATIONS FEES

• ASP companies that hold more than one level of accreditation

– Workers who are authorised under more than one level of

accreditation will only be charged once per year

– This can only apply where the worker holds authorisation under

multiple levels shown on the same renewal application form

• New authorisation or upgrade authorisation training

– If a worker attends training provided by Endeavour Energy within a

calendar year either for initial electrical safety rules training, or to

upgrade an authorisation, they will be charged the fee for a new

authorisation

61

Page 62: Level 1 and 3 ASP Seminar Dec 2015

“TRADE BASED AUTHORISATIONS”

• Currently authorisations cards show the worker’s qualification

– Cable jointer, Line worker, EFM etc

• This will begin to change over the next 12 months

• An authorisation card will show the type of work that can be

carried out

62

Line worker Construct & Maintain OH mains – Distribution

Cable Jointer Construct & Maintain UG Mains – Distribution

EFM Construct & Maintain Distribution Substation Equipment

Page 63: Level 1 and 3 ASP Seminar Dec 2015

“TRADE BASED AUTHORISATIONS”

• Non-qualified workers, and electrically qualified non-trade

workers will be broken into overhead workers and ground level

workers

• If a non-electrically qualified worker is required to work aloft or

act as a rescue assistant for overhead work they must hold the

overhead authorisation

– This requires annual refresher training (UETTDREL14A)

63

Trades assistant Carry out non-

electrical work – ground work

Carry out non-electrical work – overhead work

Engineer (or similar)

Carry out non-trade electrical work –

ground work

Carry out non-trade electrical work – overhead work

Page 64: Level 1 and 3 ASP Seminar Dec 2015

“TRADE BASED AUTHORISATIONS”

• If you the ASP is transmission pre-qualified, then transmission

level authorisations may be requested

64

Line worker Construct & Maintain OH mains – Transmission

Cable Jointer Construct & Maintain UG Mains – Transmission

Page 65: Level 1 and 3 ASP Seminar Dec 2015

“TRADE BASED AUTHORISATIONS”

• From the time this change is approved there will be a 12 month

transition period

• During this time;

– Existing authorisations will be transitioned to the new notation

– We will confirm that all training and qualification information is up

to date

• Once this change is approved, more information will be

sent out to all ASPs impacted by the change

• These authorisations are only to confirm that the worker can

perform the tasks safely, and in accordance with the Electrical

Safety Rules

65

Page 66: Level 1 and 3 ASP Seminar Dec 2015

“TRADE BASED AUTHORISATIONS”

Impact:

• All authorised workers will need to annually complete “Provide

first aid in an ESI environment” (UETTDRRF10B)

• All trade qualified workers will need to annually complete

– Testing of LV connections (UETTDRRF11A )

– Pole top rescue (UETTDRRF02B)

• Line workers will be specifically authorised to operate an EWP

near live mains

– All other workers will continue to need explicit authorisation

• Non-qualified workers who work aloft will need to initially

complete UETTDREL14A

66

Page 67: Level 1 and 3 ASP Seminar Dec 2015

AUTHORISATIONS CARDS - PHOTOS

• We have a small number of ASPs with no photo on their

authorisation card

• You must have a photo on your card

• Make sure you email a passport sized photo with your renewal

– If you don’t currently have a photo,

– If your photo needs updating

67

Page 68: Level 1 and 3 ASP Seminar Dec 2015

SAFETY MANAGEMENT SYSTEMS

• Your company must maintain a safety management system to

meet the requirements for accreditation

• You will now need to sign a form when you renew your

accreditation confirming that you have a system in place

68

Page 69: Level 1 and 3 ASP Seminar Dec 2015

NSW WIDE TEMPORARY SUSPENSION OF

AUTHORISATIONS

• Given the unique nature of ASP work there is the potential for

safety risks to shift from one Network Operator to another

• For this reason a NSW wide authorisation suspension process

has been established for ASP workers.

• If your authorisation to work on Endeavour Energy’s network is

suspended this will be mirrored on Ausgrid and Essential

Energy’s network

• A comparable process to that detailed below has been

established within both Ausgrid and Essential Energy, so if you

are suspended from work on their networks, you will be

suspended from Endeavour Energy’s network

69

Page 70: Level 1 and 3 ASP Seminar Dec 2015

Training Requirements

70

Page 71: Level 1 and 3 ASP Seminar Dec 2015

AUTHORISATION TO OPERATE OR OBSERVE PLANT

NEAR OH MAINS

• Previously, non-electrically qualified workers who were

authorised to operate plant or equipment near OH mains, were

require to annually complete “close approach training” or

UETTDREL14A

• The required content of this course will be moved into

Endeavour Energy’s ESR refresher from the 16th of December

• You will no longer need to annually complete this training

course to maintain authorisation

– You will however need to confirm that you have operated plant or

machinery near OH mains on at least 10 occasions within the year

• UETTDREL14A will still be required to initially gain authorisation

71

Page 72: Level 1 and 3 ASP Seminar Dec 2015

RTO ACCREDITATION

• Endeavour Energy now accredits RTOs to deliver training

• Only accredited RTOs can provide any training specific to

Endeavour Energy, including;

– Electrical Safety Rules

– Excavation in a public place

• Confirm with the RTO that they are accredited prior to

undertaking training

72

Electrical Safety Rules refreshers other than specific Endeavour Energy ESR from an Accredited RTO

Will not be accepted

Page 73: Level 1 and 3 ASP Seminar Dec 2015

COMBINED ESR REFRESHER TRAINING

• Endeavour Energy has created an assessment specification

that will allow RTO’s to develop a common NSW ESR refresher

training delivery program subject to network operator approval.

• Currently it is a requirement that RTO’s deliver and assess to a

specific tailored assessment schedule however; in light of

industry feedback it has been decided to allow RTO’s to

streamline this process.

• RTO’s shall be required to submit any common ESR refresher

assessment process to the relevant network operators for

approval.

• Provided the assessment satisfies each network operator’s

requirements, a common streamlined ESR refresher may be

undertaken in the near future.

73

Page 74: Level 1 and 3 ASP Seminar Dec 2015

Electrical Safety

74

Page 75: Level 1 and 3 ASP Seminar Dec 2015

ELECTRICAL SAFETY RULE AMENDMENTS

• There will not be an amendment to the Electrical Safety Rules

released in 2015

• The next amendment to the electrical safety rules is likely to be

2016

• The delivery method and process is currently being determined

75

Page 76: Level 1 and 3 ASP Seminar Dec 2015

ARC RATED CLOTHING

• From 1 July 2016, all workers will need to wear a minimum of

4 cal/cm2 ATPV Arc Rated clothing

when working on or near Endeavour Energy’s network

– This requirement is consistent with the ENA NENS 09 (2014)

minimum recommendation for base garments

– ASPs may decide to procure clothing rated above this rating

• This requirement will be consistent across Networks NSW

– At this stage you don’t need to change anything unless you are

working in Ausgrid’s area

• Clothing meeting these requirements should be available from

commercial clothing suppliers

76

Page 77: Level 1 and 3 ASP Seminar Dec 2015

POLARITY TESTING PROCEDURES

• We are currently reviewing our polarity testing procedures and

requirements

• It is proposed that from the 2016 rules amendment, ASPs will

be required to perform service polarity testing, phasing and

neutral integrity testing in accordance with Australian Standard

4741

– ASPs will not be required to follow Endeavour Energy’s specific

procedure for polarity testing (WSY0037)

– ASP companies will need to develop, and document their own

polarity testing, and neutral integrity testing procedure

• This would align with the nationally recognised annual training

in testing of connections that you currently do

77

Page 78: Level 1 and 3 ASP Seminar Dec 2015

NEW SUBSTATION KEY ISSUES

• Our security group have rolled our a new locking system at

Endeavour Energy

• Existing padmount substation locks will only be changed where

the cubicle is replaced

• New installed substations will have the new locks

78

Page 79: Level 1 and 3 ASP Seminar Dec 2015

NEW SUBSTATION KEY ISSUES

• Security have made the decision that the new keys will not be

available for loan

• The only option currently available for ASPs to access

substations with new locks is to request accompanied access

with Endeavour Energy staff

• We have requested that security resolve this issue

79

Page 80: Level 1 and 3 ASP Seminar Dec 2015

QUESTIONS?

I’m happy to try to answer any of your questions now,

but if you think of anything later our contact details are:

80

• Electrical safety enquiries

• Interpretations of Electrical Safety Rules

[email protected]

• Authorisations enquiries

• Required training courses and RTOs

• Submit application forms and evidence of training

Authorisations@endeavourenergy. com.au

or; 9853 6946

or; 9853 5043

Page 81: Level 1 and 3 ASP Seminar Dec 2015

Fred Kaft

ASP Investigation Procedure

81

06

Page 82: Level 1 and 3 ASP Seminar Dec 2015

OVERVIEW

Incident Types

• Level 1 - 2

• Level 3 - 4 Serious Incidents

Examples

• Past 12 months of ASP incidents

Process

• EE ICAM

• ASP investigations – ESR and Standards

Next Steps

• Framework development

• Further communication

82

Page 83: Level 1 and 3 ASP Seminar Dec 2015

Incident Types

83

Page 84: Level 1 and 3 ASP Seminar Dec 2015

NNSW (Endeavour Energy) Incident Management

Framework

Level 1 – ASP Process

• Incidents that are of a minor and localised nature. Controlled

across the site and supervisor manages the incident

Level 2 – ASP Process

• Incidents that are more complex but still are localised in nature.

These may require a full investigation by the ASP based on

their processes

84 ASP Forum – Incident Investigations, November 2015

Page 85: Level 1 and 3 ASP Seminar Dec 2015

Level 3 – ASP and EE investigation:

• Incidents that are high consequence or high potential (near

misses). Incidents that require notification to a regulatory

authority.

Level 4 – ASP and EE investigation:

• Incidents that result in very high consequences are very

complex and have network wide implications.

85 ASP Forum – Incident Investigations, November 2015

NNSW (Endeavour Energy) Incident Management

Framework

Page 86: Level 1 and 3 ASP Seminar Dec 2015

Examples

86

Page 87: Level 1 and 3 ASP Seminar Dec 2015

Past 12 Months of Level 3 ASP incidents

• Unauthorised work on the Endeavour Energy Network.

• Reverse polarity

• Pole fall over

• Conductor fall

• Cut live HV Cable

87 ASP Forum – Incident Investigations, November 2015

Page 88: Level 1 and 3 ASP Seminar Dec 2015

Process

88

Page 89: Level 1 and 3 ASP Seminar Dec 2015

Endeavour Energy ICAM/ ASP Investigation

89

EE investigation against ESR and standards

ASP Investigation from ASP perspective – ICAM or other

ASP Forum – Incident Investigations, November 2015

Page 90: Level 1 and 3 ASP Seminar Dec 2015

Next Steps

90

Page 91: Level 1 and 3 ASP Seminar Dec 2015

Next Steps

91

Review Roles of EE and ASP

Develop framework

Communicate

ASP Forum – Incident Investigations, November 2015

Page 92: Level 1 and 3 ASP Seminar Dec 2015

QUESTIONS?

92

• Investigation enquiries

[email protected]

or; 9853 6781

or; 9853 6713

ASP Forum – Incident Investigations, November 2015

Page 93: Level 1 and 3 ASP Seminar Dec 2015

David Shepherd

Network Mains Updates

93

07

Page 94: Level 1 and 3 ASP Seminar Dec 2015

94

NETWORK MAINS - UPDATES

Standard Updates Technical Bulletins Upcoming

Amendments

Page 95: Level 1 and 3 ASP Seminar Dec 2015

95

MDI 0026 - Location of Isolation points on the high

voltage distribution network

Page 96: Level 1 and 3 ASP Seminar Dec 2015

96

MDI 0026 - KEY CHANGES

• Urban overhead isolation point requirements reduced to every second

pole substation.

URBAN AREAS

• Simplified classifications for non-urban areas

• Removal of the 20 customer limit between isolation points, now only

250kVA limit used.

NON-URBAN AREAS

HVC

LBLB

63kVA100kVA63kVA150kVA63kVA400kVA

Page 97: Level 1 and 3 ASP Seminar Dec 2015

97

MDI 0026 - KEY CHANGES

GENERAL

• Isolation points either side of a HVC removed and isolation at the point

of demarcation added.

• Endorsement for additional switches can be given by planning when

reliability is justified

Page 98: Level 1 and 3 ASP Seminar Dec 2015

98

TB 207 - Pole loading assessment for communication

cables

Page 99: Level 1 and 3 ASP Seminar Dec 2015

99

TB 207 - Pole loading assessment for communication

cables

Page 100: Level 1 and 3 ASP Seminar Dec 2015

100

TB 207 - Pole loading assessment for communication

cables

Page 101: Level 1 and 3 ASP Seminar Dec 2015

101

TB 207 - Pole loading assessment for communication

cables

Applicable to MCI 00002 Attachment of communication cables to

Endeavour Energy poles

• If a communication cable is

added to the pole;

– Full pole loading calculation

required

– Load shall not exceed pole

rating (pole disc)

– Can exclude customer

service drops/lead-ins

• If a communication cable is

added to the pole;

– Full pole loading calculation

required

– Load shall not exceed pole

rating (pole disc)

– Shall include customer

service drops/lead ins

Previous Requirement New Requirement

Page 102: Level 1 and 3 ASP Seminar Dec 2015

102

Upcoming Amendments

MCI 0006 - Underground distribution: Construction standards

manual

• Endeavour Energy and RMS have an MoU for trench configurations

Page 103: Level 1 and 3 ASP Seminar Dec 2015

103

Upcoming Amendments

MCI 0006 - Underground distribution: Construction standards

manual

• Endeavour Energy and RMS have an MoU for trench configurations

Scenario

Concrete

protection

layer

Concrete

encase

Existing road 1200mm 1000mm

Proposed

road

(energised

before road

completed)

1800mm 1500mm

Proposed

road

(energised

after road

completed)

1500mm 1200mm

Page 104: Level 1 and 3 ASP Seminar Dec 2015

104

Upcoming Amendments

MDI 0045 - Cable sheath bonding design

SVL

Cable Sheath

Major Section

Minor section 1 Minor section 2 Minor section 3

Link BoxLinks

Footing

Resistance

Cable details

Maximum

prospective

fault current

(kA)

Maximum

minor

section

length (m)

Voltage

(kV)

CSA

(mm2)

33

300

31.5 XX 630

800

1200

66 630 31.5 XX

132

400

31.5 XX 630

800

1200

400

40 XX 630

800

1200

• Include design requirements for cross bonding

Page 105: Level 1 and 3 ASP Seminar Dec 2015

105

Upcoming Amendments

MDI 0031 - Overhead distribution: Design standards manual

MDI 00XX - Underground transmission mains design

MDI 0028 - Underground distribution network design

Page 106: Level 1 and 3 ASP Seminar Dec 2015

Ivan Mendonsa

Contractor Operations Changes

106

08

Page 107: Level 1 and 3 ASP Seminar Dec 2015

Quality Assurance Forms – Contestable Transmission

Construction Works

107

• Forms are developed to address the gap in the process

• Forms have been circulated within Endeavour Energy for input

from Subject Matter Experts

• Planned to implement the forms from 1 Feb 2016

• Commissioning testing and reports will be carried out by the

Endeavour Energy testing group and funded by the ASP.

Page 108: Level 1 and 3 ASP Seminar Dec 2015

Quality Assurance Forms – Contestable Transmission

Construction Works

108

• Forms will be published in the ASP website for your input & your

Input required by the end of Dec 2015

• All input to be provided to Ivan Mendonsa:

[email protected]

• Note the attached forms below:

– ASP Transmission Forms

– CI Transmission Forms

Page 109: Level 1 and 3 ASP Seminar Dec 2015

Chris Srbinovski

LV Restoration Awareness

109

09

Page 110: Level 1 and 3 ASP Seminar Dec 2015

110

What is the hazard

Multiple houses were energised with a reversed polarity due to an incorrect

LV mains connection.

The connection was made with the distributor de energised when a new

bay of LV ABC was installed. Connections at one side of the LV cable were

correct, but at the other connection C phase and neutral were reversed.

What has been done

Staff noticed the reverse polarity immediately and reinstated the isolation.

There was no personal or property damage caused at any of the customer

installations.

Page 111: Level 1 and 3 ASP Seminar Dec 2015

111

Endeavour Energy Electrical Safety Rules

7.2.5 Low voltage customers' service connection and identification of service neutral

Reverse polarities and incorrect phase rotations

can create life threatening situations and equipment damage.

If there is any doubt the service shall be left disconnected

until the neutral has been identified.

It is the connecting person’s responsibility to ensure that all

connections are correct.

Page 112: Level 1 and 3 ASP Seminar Dec 2015

LV Isolation Guide

112

L2 ASP to note customer installation phase rotation

Switching officer to Test N/O points (phasing & volts)

L2 ASP to disconnect affected service mains including neutral (isolate & insulate)

Isolate circuit, apply PB’s as required & Issue ATW as per ESR

Commence Work

Complete works & Surrender ATW

Switching officer to Remove PB’s and cancel ATW

Begin LV Restoration

Page 113: Level 1 and 3 ASP Seminar Dec 2015

LV Restoration Guide

113

Identify possible incorrect connections points & Prepare Restoration Plan

Scenario 1 All services isolated from

LV circuit

Perform IR & Continuity tests

Energise LV circuit & perform commission tests

L2 ASP reconnect services as per

WSY0037 & submit NOSW’s

Scenario 2 Existing Parallel supply

available

Circuit left un-bonded & LV energised from

both directions

Test and make final connections live

L2 ASP reconnect services as per

WSY0037 & submit NOSW’s

Scenario 3 Spur LV circuit

Disco all services affected by possible incorrect connection

Energise & perform polarity test

L2 ASP reconnect services as per

WSY0037 & submit NOSW’s

Page 114: Level 1 and 3 ASP Seminar Dec 2015

Augment of Existing Overhead Mains

114

Page 115: Level 1 and 3 ASP Seminar Dec 2015

Possible Incorrect Connections

115

Page 116: Level 1 and 3 ASP Seminar Dec 2015

All Services Isolated For Restoration

116

• Perform IR & Continuity tests on

isolated circuit

• Energise & perform polarity tests.

• L2 ASP to restore services

Page 117: Level 1 and 3 ASP Seminar Dec 2015

New Installation With Parallel Points Available

117

• Circuit left un-bonded &

energised from both

directions.

• Test polarity and make

connections live.

• L2 ASP to restore

services

Page 118: Level 1 and 3 ASP Seminar Dec 2015

New Installation on Spur LV Circuit

118

• Disco all services, affected

by possible incorrect

connections downstream of

new installation.

• Energise & perform polarity

tests.

• L2 ASP to restore services

Page 119: Level 1 and 3 ASP Seminar Dec 2015

ASP Requirements

Include LV restoration in project plan

Provide restoration resources

L2 ASP requirements

• NOSW / FPJ 4672

• CAT 2 Underground service

• CAT 3 Overhead services

119

Page 120: Level 1 and 3 ASP Seminar Dec 2015

120

Page 121: Level 1 and 3 ASP Seminar Dec 2015

Kris Shankar

Earthing Construction Refresher

121

10

Page 122: Level 1 and 3 ASP Seminar Dec 2015

EARTHING

CONSTRUCTION

REFRESHER

Earthing and Power Quality

Kris Shankar

Electrical Engineer - Earthing

Page 123: Level 1 and 3 ASP Seminar Dec 2015

WHERE IS THE EARTHING INFORMATION ON A

DESIGN??

123

Page 124: Level 1 and 3 ASP Seminar Dec 2015

Something doesn’t seem right

• If you feel the design appears to be unfit for the location

question the designer

124

Page 125: Level 1 and 3 ASP Seminar Dec 2015

How do we construct

an earthing system?

125

Page 126: Level 1 and 3 ASP Seminar Dec 2015

EDI100

126

Page 127: Level 1 and 3 ASP Seminar Dec 2015

127

Page 128: Level 1 and 3 ASP Seminar Dec 2015

128

Page 129: Level 1 and 3 ASP Seminar Dec 2015

COMMON EARTHED POLE SUB

Both the HV earth and

the LV earth are bonded

together and connected

to earth.

HV earth connection to

Tx frame

LV earth is bonded to neutral

129

Page 130: Level 1 and 3 ASP Seminar Dec 2015

PADMOUNT SUB – COMMON EARTH

130

Only bond where

designed to

Page 131: Level 1 and 3 ASP Seminar Dec 2015

PADMOUNT SUB – COMMON EARTH

131

Page 132: Level 1 and 3 ASP Seminar Dec 2015

UGOH – COMMON EARTH

132

Only bond where

designed to

Page 133: Level 1 and 3 ASP Seminar Dec 2015

KEY ISSUES (CONSTRUCT)

• Not achieving standard resistance:

– Follow design rather than standard resistance (limit impact on

nearby homes, pits etc.)

– Question with the designer if target resistance does not line up

with design target

133

Page 134: Level 1 and 3 ASP Seminar Dec 2015

SPECIAL EARTHING CONDITIONS

• First Cables out of a Zone Sub are not to be connected to the Distribution earth bar, only earthed back at the ZS (unless the design specifies it)

• Handles which operate HV Switchgear such as ABS, LBS, Regulators, etc maybe connected to earth (in limited situations)

134

Page 135: Level 1 and 3 ASP Seminar Dec 2015

UGOH – FIRST POLE OUT

• CMEN:

– Zone substations that are

deliberately bonded into the

distribution earthing environment

(HV earths and/or LVN)

– CMEN terminology is not common

use in the industry

– First sub out or first UGOH out

135

Page 136: Level 1 and 3 ASP Seminar Dec 2015

CRIMP CONNECTIONS

136

Page 137: Level 1 and 3 ASP Seminar Dec 2015

ROD INSTALLATION

137

Page 138: Level 1 and 3 ASP Seminar Dec 2015

RECAP

• Build to the design

• If you are not sure

contact designer

• Follow standard

drawings provided by

EDI 100

138

Page 139: Level 1 and 3 ASP Seminar Dec 2015

EARTHING DESIGN

REFRESHER

Earthing and Power Quality

Page 140: Level 1 and 3 ASP Seminar Dec 2015

EXISTING SUPPORT

• Standards, e.g. EDI100

• 3E handbook

• Webinars

• Contestable work

◦ If the team require they will contact earthing

140

Page 141: Level 1 and 3 ASP Seminar Dec 2015

COMMON EARTHED EXAMPLE 1:

141

Common earthed (with series impedance)

• A common earthed asset is being installed where there maybe low

amount of MEN customers, but joined to a larger MEN pocket.

• The series impedance must be taken into account, sometimes it can

be the limiting factor in the design

• In some cases the secondary MEN can be in lower soil resistivity or

the same as the designed MEN.

• The following is examples shows how this is entered into 3E

• When 3E is used in conjunction with additional calculations, a small

report with the calculations and assumptions should be produced (1-2

pages is sufficient or as required by designer)

Page 142: Level 1 and 3 ASP Seminar Dec 2015

COMMON EARTHED EXAMPLE 1:

142

MEN 2 1500 customers

20Ωm

MEN 1 67 customers

200Ωm200m Neutral connection

Page 143: Level 1 and 3 ASP Seminar Dec 2015

COMMON EARTHED EXAMPLE 1:

143

Series

impedance of

neutral

= 0.063Ω

Page 144: Level 1 and 3 ASP Seminar Dec 2015

COMMON EARTHED EXAMPLE 1:

144

200m Neutral connection = 0.063Ω

1500 customers MEN = 0.035Ω

67 customers MEN = 3.135Ω

Page 145: Level 1 and 3 ASP Seminar Dec 2015

COMMON EARTHED EXAMPLE 1:

145

Page 146: Level 1 and 3 ASP Seminar Dec 2015

SEPARATELY EARTHED EXAMPLE 1:

146

Separately earthed (interconnected cable screens)

• A separately earthed asset is being installed in a separately earthed

area

• Soil resistivity is 700Ωm

• The following is examples shows how to incorporate a less

conservative analysis

• When 3E is used in conjunction with additional calculations, a small

report with the calculations and assumptions should be produced (1-2

pages is sufficient or as required by designer)

Page 147: Level 1 and 3 ASP Seminar Dec 2015

SEPARATELY EARTHED EXAMPLE 1:

147

UGOH

Padmount 2 Padmount 3

Padmount 1

Asset under design

Measured resistance = 45.18Ω

Measured resistance = 35.15Ω

Measured resistance = 20.23Ω

Page 148: Level 1 and 3 ASP Seminar Dec 2015

SEPARATELY EARTHED EXAMPLE 1: STANDARD

148

Page 149: Level 1 and 3 ASP Seminar Dec 2015

SEPARATELY EARTHED EXAMPLE 1:

149

ScreenResistance

Padmount 1

Padmount 2

ScreenResistance

Padmount 3 Screen

Resistance

UGOH0.041 Ω Design Ω

20.23 Ω

0.027 Ω

45.18 Ω0.044 Ω

35.15 Ω

Page 150: Level 1 and 3 ASP Seminar Dec 2015

SEPARATELY EARTHED EXAMPLE 1:

150

Page 151: Level 1 and 3 ASP Seminar Dec 2015

SEPARATELY EARTHED EXAMPLE 1:

151

Page 152: Level 1 and 3 ASP Seminar Dec 2015

SEPARATELY EARTHED EXAMPLE 1:

152

Page 153: Level 1 and 3 ASP Seminar Dec 2015

QUESTIONS?

153

• Thank you for your attention and time.

Page 154: Level 1 and 3 ASP Seminar Dec 2015

Paul Hardman

ASP Activity Report

154

11

Page 155: Level 1 and 3 ASP Seminar Dec 2015

Non Conformance Summary – Last 6 Months

155

ASP Level Major Minor Safety Total

1 15 23 1 39

• Level 1 ASP

Page 156: Level 1 and 3 ASP Seminar Dec 2015

156

Non Conformance Summary Details – Last 6 Months

Non Conformance Description Major Minor Safety Total

Assets not constructed to design specifications 5 5

Damage to assets (Investigation) 2 2

Failure to notify customers of outage 5 5

Inadequate project management 7 7

Inadequate supervision of pre-qualification works 1 1

Incorrect phasing 5 5

Low insulation resistance 1 1

Non compliance with ESR rescue kits requirements 1 1

Non compliance with MCI0005 2 2

Non compliance with substation design – earthing

(EDI100) 1 1

Non compliance with Worksite Audit (FPJ4660) 3 3

Unsatisfactory workmanship 5 5

Use of unapproved materials 1 1

Total 15 23 1 39

Page 157: Level 1 and 3 ASP Seminar Dec 2015

157

Level 1 Major Non Conformances

• Assets not constructed to design specifications

• Damage to assets (Investigation)

– Incorrect disconnection of pilot cable

• Inadequate supervision of pre-qualification works

– Using non pre-qualified staff for transmission works.

• Incorrect phasing

– Phasing information not communicated to staff.

– Pillar connections terminated incorrectly.

– Overhead conductor phases inadequately traced x 3.

Page 158: Level 1 and 3 ASP Seminar Dec 2015

Level 1 Major Non Conformances

• Low insulation resistance

– IR test not conducted on installed LV cable prior to commissioning.

• Use of unapproved materials

– Used unapproved materials without seeking dispensation from EE

Engineering Group.

158

Page 159: Level 1 and 3 ASP Seminar Dec 2015

159

Level 1 Safety Non Conformance

• Non compliance with ESR rescue kits requirements

– Damaged Rubber Gloves, no touch and trauma dressing

Page 160: Level 1 and 3 ASP Seminar Dec 2015

Non Conformance Summary – Last 6 Months

160

ASP Level Major Minor Safety Total

3 0 479 0 479

• Level 3 Non Conformances

Page 161: Level 1 and 3 ASP Seminar Dec 2015

161

Non Conformance Summary Details – Last 6 Months

Non Conformance Description Major Minor Safety Total

ADM - Failure to provide required administrative information 116 116

MDI - Non compliance with Mains Design Instruction 55 55

EDI100 - Non Compliance with Earthing Design Standards 52 52

LDI - Non compliance with Lighting Design Instruction LDI0001 50 50

IPS - Incomplete Proposed method of Supply 42 42

ICP - Incomplete Design Certification Package 39 39

NPS - Non compliance with Network Property Standard 39 39

SAD - Non Conformance to drawing Standard SAD0001 33 33

FEE - Failure to pay fees 25 25

AVS - Incorrect Asset Valuation Sheet 10 10

FDB - Failure to comply with design brief 8 8

MC5 - Non-Compliance with MCI0005 6 6

LVD - Incorrect voltage drop calculations 3 3

MC6 - Non-Compliance with MCI0006 1 1

Total 479 479

Page 162: Level 1 and 3 ASP Seminar Dec 2015

162

Level 3 Minor Non Conformances

• Failure to provide required administrative information

– Incorrect information provided on connection forms, method of

supply, design certification packages & etc.

• Non compliance with Mains Design Instructions

– MDI 0026: Underground distribution network design

– MDI 0031: Overhead distribution: Design standards manual

• Non Compliance with Earthing Design Standards EDI100

– Incorrect substation earthing layout – incorrect cable terminations.

– Inadequate earthing arrangement for UGOH poles, substation.

– EPR exceeded allowable touch/ step voltage limits.

Page 163: Level 1 and 3 ASP Seminar Dec 2015

Paul Hardman

Response to Issues from Last Seminar

163

12

Page 164: Level 1 and 3 ASP Seminar Dec 2015

Questions raised from Last Seminar

164

• Information on Earthing (Seminar Topic)

• Lease of Poles and Wires – Impacts on ASP’s

• Design issues – How to (Seminar Topic)

• Need to be able to locate forms

• Where is the link to the ASP website on the Endeavour Energy

website

• What’s going on with GIS and current performance/ (Seminar

Topic)

• Sending fees to the correct party

Page 165: Level 1 and 3 ASP Seminar Dec 2015

165

• Interactive reporting of job progress

• What are the time frames for each stage of the design process?

• What is required at each stage of the design/ construct

process?

• Cost share reimbursement scheme more information

Questions raised from Last Seminar

Page 166: Level 1 and 3 ASP Seminar Dec 2015

166

• Lease of Poles and Wires – Impact on ASP’s

– Legislation prepared;

• Electricity Network Assets (Authorised Transactions) Bill 2015

• Electricity Retained Interest Corporations Bill 2015

– Bills have been introduced to state parliament and have

progressed through the 2nd reading – now with the Upper House

for review.

– Select committee have convened and presented their report

“Leasing of Electricity Infrastructure” Printed 2nd June 2015.

Lease of Poles and Wires – Impacts on ASP’s

Page 167: Level 1 and 3 ASP Seminar Dec 2015

167

– The Plan;

• Long term lease Transgrid has been completed.

– $10.258 Billion lease

– ‘NSW Electricity Networks’ – New Owner

– Foreign Investment Review Board approval has been

given.

– Regular information being provided to staff by NSW Treasury

through a document “NSW Government Lease Transaction

Employee Question and Answers” Most recent 27/10/15.

– Impact on ASP’s

• Little or none with Transgrid lease

Lease of Poles and Wires – Impacts on ASP’s

Page 168: Level 1 and 3 ASP Seminar Dec 2015

168

– Current legislation in NSW supports the ASP scheme:

• Electricity Supply Act 1995

• Electricity Supply (Safety and Network Management)

Regulation 2014

• Scheme for Accreditation of Service Providers (March 2015)

– Legislative change needed if there is a change planned for the

Scheme

– The legislation covering the planned lease of Ausgrid and then

Endeavour do not refer to the ASP Scheme or the ongoing

interaction of the new entity with ASP’s.

– “Customer Funded Contestable Work” is a cost effective and

efficient means of connecting customers to the network.

Lease of Poles and Wires – Impacts on ASP’s

Page 169: Level 1 and 3 ASP Seminar Dec 2015

169

• Locating Forms on the ASP Website

– The Plan

• Standards move to the Endeavour Energy website.

• Standards tab on ASP Website is available for forms.

– The Result

• Standards and associated documents are on the Endeavour

Energy website.

• New Endeavour Energy website has additional facility and

includes a number of updated documents and forms.

• No forms page!

Locating Forms on the ASP Website

Page 170: Level 1 and 3 ASP Seminar Dec 2015

170

– Why?

• The old ASP website is incapable of being updated.

• A new ASP Website is being developed which will include

features identified by ASP’s.

– Expected delivery 2nd quarter 2016.

Locating Forms on the ASP Website

Page 171: Level 1 and 3 ASP Seminar Dec 2015

171

The Link to the ASP Website on the EE Website Page

• Where is the link to the ASP website on the EE website page?

– The old webpage required that a number of pages were opened to

gain access to the ASP website login page.

– The new website is very simple

• Select ASP’s from the top banner line

• The ASP Website login is immediately available.

Page 172: Level 1 and 3 ASP Seminar Dec 2015

172

The Link to the ASP Website on the EE Website Page

Page 173: Level 1 and 3 ASP Seminar Dec 2015

173

The Link to the ASP Website on the EE Website Page

Page 174: Level 1 and 3 ASP Seminar Dec 2015

174

The Link to the ASP Website on the EE Website Page

• For ASPs who want access to the ASP website;

– Click on [email protected] on the ASP

website page.

– Rachel will respond with a login within a couple of days if all data is

provided on the email form.

Page 175: Level 1 and 3 ASP Seminar Dec 2015

175

Sending Fees to the Correct Party

• Sending fees to the correct party

– Notice of Advice letter issued by Endeavour Energy –

• Applicant advises ASP Level 3 and who is responsible for fees

• Around 25 – 30% of jobs the company responsible for fees is

not the Level 3 ASP.

• Current process is manual – requires CWO/ CWE to identify

the different parties and send the appropriate correspondence.

• Investigating option of CAMS change to capture both sets of

data and have the required documents correctly addressed.

Page 176: Level 1 and 3 ASP Seminar Dec 2015

176

Sending Fees to the Correct Party

– Letter of intent letter issued by Endeavour Energy -

• Response provided lists all participants and their roles.

• All details updated in CAMS and used for the remainder of

activity on the project.

– Where the developer changes Level 1 after initial notification

• Revised Letter of Intent required.

• Statement also from Developer indicating that all contractual

responsibilities to original Level 1 have been met.

Page 177: Level 1 and 3 ASP Seminar Dec 2015

177

Interactive Reporting of Job Progress

• Interactive reporting of job progress

Drivers:

– AER Decision

– Lease imminent

– No corporate appetite for change

Result:

– Company will not proceed with interactive online reporting.

Page 178: Level 1 and 3 ASP Seminar Dec 2015

178

Interactive Reporting of Job Progress

• Customer self service

– This initiative will proceed.

– Online application / validation for basic connection offer.

– Issue PTC if all criteria are met.

Page 179: Level 1 and 3 ASP Seminar Dec 2015

179

Time Frames for Each Stage of the Design Certification

Process

• What are the time frames for each stage of the design certification

process?

Process Action by

EE ASP

Days KPI

1. Receive Completed Application

2. Application Acknowledgement

14 Days 3. Supply Offer

- Level 3 ASP required

- Pay up and connect

4. Notice of Advice (NOA)

5. Proposed MOS

6. Design Brief Issued 14 Days

7. Design Package Received

8. Design Certification 14 Days

Page 180: Level 1 and 3 ASP Seminar Dec 2015

180

What is Required at Each Stage of the Design Process

1. Completed Application

– All requirements in the application form fully completed

4. Notice of Advice

– The notification of advice form is completed with all required

information

5. Proposed MOS

– WPJ 4120 clause 4.7

“The proposed Method of Supply must included sufficient relevant

information to enable the CWE/ CWO to carry out the appropriate

assessment”

(Numbering From Process Steps on Previous Slide)

Page 181: Level 1 and 3 ASP Seminar Dec 2015

181

What is Required at Each Stage of the Design Process

– The documentation provided by the Level 3 ASP shall comprise of:

• Branch Form FPJ 4103 – Method of Supply Proposal

• Related sketches / GIS mark ups

• Voltage Drop Calculations

• Network equipment locations including coordination with

building structures

• Site inspection photographs

– Reference shall be made to all relevant Australian Standards,

Company policies and standards necessary to prepare a

complying document.

Page 182: Level 1 and 3 ASP Seminar Dec 2015

182

What is Required at Each Stage of the Design Process

7. Design Package Received.

─ WPJ 4130

From Annexure B of WPJ 4130 the following items are to be provided

by the Level 3 ASP.

– Drawing complying with SAD 0001

– Complete Asset Valuation Sheet (FPJ 4160)

– Complete Environmental Assessment with Photographs (FAT

0038)

– Complete Audit Check List

– Design Safety Report

Page 183: Level 1 and 3 ASP Seminar Dec 2015

183

What is Required at Each Stage of the Design Process

─ Completed Voltage Drop Calculations (MDI 0030)

─ Property Tenure Documentation

─ Signed Agreement to Enter and Create Easement (when required)

─ Agreement Document from Other Authorities (Telstra, Sydney Water etc)

─ GIS/ CAD Validation Report – Indicating “No P1 or P2 errors”

Additionally;

─ All fees paid

• CWO/E will check all documents have been provided – where documents are

missing a non-conformance will be issued and the ASP requested to submit

additional documents.

Page 184: Level 1 and 3 ASP Seminar Dec 2015

184

Cost Share Reimbursement Scheme – More Information

• Cost share reimbursement scheme originally introduced by

IPART in their Determination No.1 – 2002.

– Applied by Endeavour Energy as a rural reimbursement scheme

• Change to the National Electricity Rules (NER) Part E of

Chapter (5A) defined a broad outline and intent for a cost

sharing scheme.

• Endeavour Energy have interpreted these requirements into the

following documents;

– Connection Policy (May 2014) clause 5.0.

– Pioneer Reimbursement Scheme Principles (June 2014)

Both Documents available on the Endeavour Energy website

Page 185: Level 1 and 3 ASP Seminar Dec 2015

185

Cost Share Reimbursement Scheme – More Information

• Seminar presentation for Level 3 ASPs on 9/12/2014

− Section 6 – Cost Share Reimbursement Scheme: Han Phan

• Seminar material on the ASP website

− IN 046/14 Dated: 15/12/2014

• ASP Actions

− Complete assessment

− Include appropriate label (55(A)) on the design

− Scheme activated based on your information

Page 186: Level 1 and 3 ASP Seminar Dec 2015

Paul Hardman

General Business

186

13

Page 187: Level 1 and 3 ASP Seminar Dec 2015

Important Notices

• IN 036/15 – Substation Order Form Lvl 1

• IN 037/15 – Website Availability All ASP’s

• IN 038/15 – Accellion Upgrade Lvl 3

• IN 039/15 – Approved RTO for ASP’s All ASP’s

• IN 042/15 – V4 Revision to Fees Schedule All ASP’s

• IN 041/15 – GIS Update Lvl 1 & 3

• IN 040/15 – Meter Issue Hoxton Park – Field Safety Day Lvl 2

• IN 038A/15 – Accellion Update Lvl 3

• IN 038B/15 – Accellion Update Lvl 3

• IN 044/15 – Availiability of Outage Informaiton Mobile Application All ASP’s

• IN 043/15 – Tariff Structure Statement (Request for Comment) All ASP’s

• IN 045/15 – IT System Changes All ASP’s

• IN 046/15 – GIS – GNET Viewer Availability Lvl 1 & 3

• IN 051/15 –Transformer Workshop Update Lvl 1

187

Page 188: Level 1 and 3 ASP Seminar Dec 2015

General Business

• Questions or Discussion

• Please complete feedback forms.

188