Upload
all-round-supplies
View
226
Download
0
Embed Size (px)
DESCRIPTION
The notes from the Level 1 and 3 ASP seminar at Liverpool Catholic Club, Dec 2015.
Citation preview
Level 1 & 3
ASP Seminar
Liverpool Catholic Club
3 December 2015
AGENDA
1. Introduction
– Paul Hardman
2. Code of Conduct/Statement of Business Ethics & Safety
– Paul Hardman
HVNL Presentation
– Shannon Kyle
3. GIS CAD Update &
WAE Data Capture SAD0004
– Daryl Skene
4. Contestable Network – Key Performance Report
– Han Phan
5. Electrical Safety & Authorisations
– Terry Niemeier
6. ASP Investigation Procedure
– Fred Kaft
7. Network Mains Update
– David Shepherd
8. Contractor Operations Changes
– Ivan Mendonsa
9. LV Restoration Awareness
– Chris Srbinovski
10. Earthing Construction Refresher
– Simon Lewis/ Kris Shankar
11. ASP Activity Report
– Paul Hardman
12. Response to Issues from Last
Seminar
– Paul Hardman
13. General Business
– Paul Hardman
2
Paul Hardman
Introduction
3
01
4
WELCOME
• Thanks for your attendance.
• Presentations will proceed – questions on presentation material
will be addressed during or after the presentation.
• Individual/personal issues can be addressed after the seminar –
NOT during.
• Working papers will be on the ASP Website within 2 weeks of
the final seminar.
Paul Hardman
Code of Conduct/Statement of Business Ethics & Safety
5
02
Code of Conduct
• Values
– Safety Excellence
– Respect for People
– Customer and Community Focus
– Continuous Improvement
– Act with Integrity
6
Code of Conduct
• Ladder Of Escalation:
– 1. Speak Up
– 2. Escalate the issue / Make a disclosure
– 3. Seek external advice or report to an Authority
7
Code of Conduct
• Ethics Checklist
– I know the behaviour I need to adhere to that supports Endeavour
Energy’s Code Of Conduct
– I know what to do if I suspect I have a conflict of interest
– I know how to report issues if I see something that might be out of
step with our values
– If I see colleagues behaving inappropriately, I am prepared to
speak up
8
Code Of Conduct
• Corporate Statement:
– “For us, Ethics is about applying the principles and values in the
Code Of Conduct and our policies and procedures to help us make
the right choice”
9
Statement of Business Ethics
• Values – as shown in the Code Of Conduct
• Guiding Principles
– Safety
– Value for Money
– Open, Fair and Honest
• EE Procurement Process
• What you can expect from us
10
Statement of Business Ethics
• What we expect of you
– Be committed to Safety
– Adhere to our corporate values
– Comply with NSW Government lobbying protocol
– Comply with the ‘Competition and Consumer ACT 2010’
– Comply with NSW Government Procurement Guidelines
– Consequences for not complying
11
Statement of Business Ethics
• Guidance Notes:
– Gifts and Benefits
– Communication between parties
– Endeavour Energy’s employees and assets
– Conflicts of interest
– Confidentiality
– Contractors
– Intellectual property rights
12
Statement of Business Ethics
• Who to Contact
– Questions about “Business Ethics”
• 02 9853 6433
– Reporting possible wrongdoing
• Phone – 1800 ETHICS (1800 384 427)
• Email – [email protected]
• Letter – Group Head Of Audit
Endeavour Energy
PO Box 811
Seven Hills NSW 1730
13
14
Safety
• Safety Presentaton– HVNL – Chain of Responsibility (CoR)
Project, Fleet Services.
HVNL– Chain of
Responsibility
(CoR) Project,
Fleet Services
Prepared by: Shannon Kyle
HVNL Project Manager
ASP Presentation
December 2015
16
WHAT IS THE CHAIN OF RESPONSIBILITY?
• If you consign, pack, load or receive goods as part of your
business, you could be held legally liable for breaches of the
Heavy Vehicle National Law (HVNL) even though you have no
direct role in driving or operating a heavy vehicle. In addition,
corporate entities, directors, partners and managers are
accountable for the actions of people under their control. This is
the ‘chain of responsibility’ (CoR).
17
CoR BACKGROUND – PARTIES IN THE CHAIN
18
CoR BACKGROUND
• The aim of CoR is to make sure everyone in the supply chain
shares equal responsibility for ensuring breaches of the HVNL
do not occur. Under CoR laws if you exercise (or have the
capability of exercising) control or influence over any transport
task, you are part of the supply chain and therefore have a
responsibility to ensure the HVNL is complied with.
• The law recognises that multiple parties may be responsible for
offences committed by the drivers and operators of heavy
vehicles. A person may be a party in the supply chain in more
than one way. For example they may have duties as the
employer, the operator and the consigner of goods.
• Legal liability applies to all parties for their actions or inactions.
19
HOW DOES IT WORK?
• Offences in mass, dimension, load restraint, and driver fatigue
have been placed in risk based categories.
• Breaches of these laws are classed as minor, substantial,
severe or critical. This recognises that not all offences have the
same impact on safety or infrastructure.
• A range of penalties (for example, warnings, improvement
notices and prohibition orders) give courts greater enforcement
measures for penalising offences. They also help to prevent,
persuade and target the causes of breaches to ensure a culture
of compliance within the heavy vehicle industry.
20
RESPONSIBLE PARTIES
• The ‘responsible person’ concept makes the laws applicable to
a wide category of relevant persons responsible for the
transport of goods. For example:
– Heavy vehicle drivers must drive safely and within speed and
work/rest hour limits
– Loaders must load a vehicle safely and within mass and load
restraint requirements to ensure the load is safe for transport
– Consignors must ensure the delivery of goods does not require the
driver to exceed the permitted number of driving hours, fail to have
minimum rest periods or exceed the speed limits.
21
WHAT ARE THE CoR PENALTIES?
• Breaches of CoR can be both administrative and court imposed
and can be tailored to address specific types of offences.
• Examples of administrative penalties Roads and Maritime may
issue include:
– Improvement notices – identifies areas of risk and requires a
responsible person to address non-compliance
– Warnings – puts a responsible person on notice to address non-
compliance where a minor breach is detected
– Infringement notices – can be an alternative to court proceedings
for a less serious offence.
WHAT ARE THE CoR PENALTIES?
• Examples of court imposed penalties may include:
• Courts may issue fines as well as having the ability to impose:
– Supervisory intervention orders
– Licensing and registration sanctions
– Prohibition orders
– Commercial benefits penalties.
• In addition, body corporates may have a five times multiplier
imposed on their penalty.
22
WHAT IS INVOLVED IN A CoR INVESTIGATION?
• A specialist Compliance Investigation unit manages CoR
investigations.
• A CoR investigation may involve any of the following:
– Inspecting and searching appropriate business premises or
vehicles
– Requesting compliance related information, documentation or
contract records and names, and contact details of other
responsible people in the logistics chain
– Requiring reasonable assistance of relevant parties, including the
interpretation of data and other information
– Seizing of relevant electronic equipment.
23
WHAT IS A HEAVY VEHICLE?
24
WHAT IS A HEAVY VEHICLE?
• All of the vehicles above have a >12t GVM, and are Fatigue
Regulated Heavy Vehicles under the HVNL.
• The HVNL Project to date has focused on the fatigue related
obligations relating to these vehicle types
25
WHAT IS A HEAVY VEHICLE?
26
RAISING AWARENESS
• A factsheet on CoR and the associated reasonable steps for
each element of the HVNL legislation (Mass, Dimension, Load
Restraint, Speed & Fatigue) has been distributed to raise
awareness of CoR and help in the development of a current
training needs analysis based on responsible parties duties
under the legislation.
27
28
PROJECT OVERVIEW
• Heavy Vehicle National Law (HVNL) Project – Chain of
Responsibility (CoR)
– Project Statement:
Develop and implement a Chain of Responsibility (CoR) framework
across Endeavour Energy that will ensure transport safety risks are
managed and will limit the businesses exposure to any road transport
law prosecution. This will enable Endeavour Energy to adopt best
practice and provide suitable objective evidence to demonstrate that
reasonable steps have been taken to comply with heavy vehicle fatigue,
mass, dimension, load restraint and speed laws - keeping our drivers and
community safe.
More Information on CoR can be found at the above road regulator links
PROPOSED PROJECT WORKFLOW
Stage 3 - Implementation (Training & Compliance verification)
Modulated training package developed
Audit Tool and KPI’s developed
Audit function Transition to HSE Assurance
Transport provider accreditation programme
Stage 2 – CoR Commitment & Guidance Material developed
EE CoR policy/Code of Practice developed
CoR Handbook developed
IT solution developed Heavy Vehicle
Operators Manual updated
Compliance tools developed (forms,
factsheets, etc)
Stage 1 – Project Review & Gap/Training needs Analysis
HVNL Work Group Meetings Project Plans Training requirements identified
29
TRANSPORT SAFETY STRUCTURE(PROPOSED)
30
What changes will you see
• Driver declarations
• Sample weighing
• Load restraint
compliance checks
• Updated product mass
information
• Current tare weight
evidence available
(printed docket, no
more than 12 months
old)
31
Driver declaration: Circle
Are you fit for duty, free from the effects of drugs and
alcohol?
Y / N
Do you hold a current license for the class of vehicle you
are driving?
Y / N
Do you have available work time within regulated driving
hour’s requirements?
Y / N
Have you verified the load weight was gross and axle
mass compliant for your vehicle?
Y / N
Was the load restrained in accordance with Load Restraint
Guidelines?
Y / N
Driver Name:
(person
delivering)
Received by:
(Driver/on site
rep)
32
WATCH THIS SPACE – NTC REVIEW OF HVNL
• To better align with Australia’s national safety laws, improve
compliance and simplify enforcement, Australia’s transport
ministers have agreed the Heavy Vehicle National Law chain
of responsibility obligations should be reformed to provide a
more outcomes based approach, focussed on primary duties.
• These proposed reforms are limited to the existing regulatory
framework of the Heavy Vehicle National Law and to current
chain of responsibility parties, including executive officers.
• The intention of these reforms is not to extend the scope of
duties but to restructure and consolidate existing obligations
to ensure current parties in the chain of responsibility take a
performance based approach to their responsibilities.
• Detailed policy recommendations arising from this discussion
paper and the Roadworthiness Review will be considered by
ministers in November 2015.
QUESTIONS?
Thankyou for your time
IMPORTANT NOTICE
IN 051/15
Brian Berrell
Important Notice IN 051/15
35
Safety Bulletins
Paul Hardman
Safety Bulletins
37
• SB 16/15 – Cable jointing cut hand Lvl 1
• SB 15/14 – Temporary earthing connection All ASP’s
• SB 17/16 – Reverse polarity connection customer installation All ASP’s
• SB 18/15 – Failure of defective cable terminations All ASP’s
• SA 05/15 – Worker injury due to rope breaking during augmentation work All ASP’s
• SB 21/15 – Snakes and Wasps Notice All ASP’s
• SB 20/15 – Pole fell due to loading chance Lvl 1 & 2
• SB 19/15 – EWP – Fall from height Lvl 1 & 2
• SB 22/15 – Contractor working without Access Authority All ASP’s
• SB 23/15 – High Voltage Cable damage at Padmount Substation Lvl 1
• SB 24/15 – Stepping On and Off A Pole Platform Lvl 1 & 2
• SB 25/15 – Hazards of Making generator Connections to the LV Network Lvl 1
• SB 26/15 – High Voltage Cable Strike Lvl 1
GIS CAD Update & WAE Data Capture SAD0004
38
03 Daryl Skene
Network Data
Update
For ASPs
Current Situation
40
Versions currently available: GISCAD
2014 • Help Desk has been made available for GISCAD to all ASP Users
• New application delivery system has been developed with
Vendor
• Drawing Mgmt Project (DIS V2.0) Phase 1 FY Implemented
• Enhanced Validator to resolve trending issues FY Q1
41
Disturbing Trends
• We still have problems with Geomedia Webmap
42
Currently in Development
• GISCAD 2016 available FY Q3
• Webmap replacement project FY Q4
• GISCAD enhanced integration with Ellipse FY Q4
• Drawing Mgmt Project (DIS V2.0) Phase 2 FY Q4
• Ability to view designs (DIS V2.0) Phase 2 FY Q4
• SAD0001 and SAD0002 Standards updated Q3 or Q4
43
Questions or Suggestions???
Contestable Network – Key Performance Report
44
04 Han Phan
Contestable network activities and key performance
reports
• Application volume
• Acknowledgment letter KPI
• Supply offer KPI
• Design brief KPI
• Design certification KPI
• Design certification amendment quantities
• Gifted asset value
• Average Lead Time between:
– Application to Design Certification for Connection of Load Projects
– Application to Design Certification for Subdivision Projects
– L3 ASP on-board to Design Certification for Connection of Load Projects
– L3 ASP on-board to Design Certification for Subdivision Projects
45
Application volume
46
Acknowledgment letter KPI
47
Supply offer KPI
48
Design brief KPI
49
Design certification KPI
50
Gifted asset value
51
Design certification amendment quantities
52
Study period – 1 Oct 2014 to 31 Oct 2015 (13 months)
COL SUB COL SUB
A 403 437 312 343
B 88 120 61 103
C 15 19 4 11
D 2 3 1 1
E 0 1 0 0
Totals 508 580 378 458
Application to certification L3 on-board to certification
Amendment
Average Lead Time – Application to Design Certification for COL Projects
53
Notes:
• Amendment A of the design only
• Average lead time is 265 days or 8.83 months
Average Lead Time – Application to Design Certification for Sub Projects
54
Notes:
• Amendment A of the design only
• Average lead time is 251 days or 8.37 months
Average Lead Time – L3 ASP on-board to Certification for COL Projects
55
Notes:
• Amendment A of the design only
• Average lead time is 158 days or 5.27 months
Average Lead Time – L3 ASP on-board to Certification for Sub Projects
56
Notes:
• Amendment A of the design only
• Average lead time is 148 days or 4.93 months
Electrical Safety & Authorisations
57
05 Terry Niemeier
OVERVIEW
Authorisations
• Authorisations fees
• ID Photos
• Trade authorisations
• Safety Management systems
Training
• Close approach training
• ESR amendments
• Accredited RTOs
Electrical Safety
• Arc rated clothing
• Polarity testing
• ESR amendments
58
Authorisations
59
AUTHORISATIONS FEES
• From July 1 the AER has determined that this fee will increase
to;
– $428.38 (inc. GST) per year for renewed authorisations
– $477.27 (inc. GST) for new authorisations
• The increase was to ensure that connected or existing
customers do not pay for the administration of the authorisation
process
– The fee is cost reflective and removes cross subsidisation
60
AUTHORISATIONS FEES
• ASP companies that hold more than one level of accreditation
– Workers who are authorised under more than one level of
accreditation will only be charged once per year
– This can only apply where the worker holds authorisation under
multiple levels shown on the same renewal application form
• New authorisation or upgrade authorisation training
– If a worker attends training provided by Endeavour Energy within a
calendar year either for initial electrical safety rules training, or to
upgrade an authorisation, they will be charged the fee for a new
authorisation
61
“TRADE BASED AUTHORISATIONS”
• Currently authorisations cards show the worker’s qualification
– Cable jointer, Line worker, EFM etc
• This will begin to change over the next 12 months
• An authorisation card will show the type of work that can be
carried out
62
Line worker Construct & Maintain OH mains – Distribution
Cable Jointer Construct & Maintain UG Mains – Distribution
EFM Construct & Maintain Distribution Substation Equipment
“TRADE BASED AUTHORISATIONS”
• Non-qualified workers, and electrically qualified non-trade
workers will be broken into overhead workers and ground level
workers
• If a non-electrically qualified worker is required to work aloft or
act as a rescue assistant for overhead work they must hold the
overhead authorisation
– This requires annual refresher training (UETTDREL14A)
63
Trades assistant Carry out non-
electrical work – ground work
Carry out non-electrical work – overhead work
Engineer (or similar)
Carry out non-trade electrical work –
ground work
Carry out non-trade electrical work – overhead work
“TRADE BASED AUTHORISATIONS”
• If you the ASP is transmission pre-qualified, then transmission
level authorisations may be requested
64
Line worker Construct & Maintain OH mains – Transmission
Cable Jointer Construct & Maintain UG Mains – Transmission
“TRADE BASED AUTHORISATIONS”
• From the time this change is approved there will be a 12 month
transition period
• During this time;
– Existing authorisations will be transitioned to the new notation
– We will confirm that all training and qualification information is up
to date
• Once this change is approved, more information will be
sent out to all ASPs impacted by the change
• These authorisations are only to confirm that the worker can
perform the tasks safely, and in accordance with the Electrical
Safety Rules
65
“TRADE BASED AUTHORISATIONS”
Impact:
• All authorised workers will need to annually complete “Provide
first aid in an ESI environment” (UETTDRRF10B)
• All trade qualified workers will need to annually complete
– Testing of LV connections (UETTDRRF11A )
– Pole top rescue (UETTDRRF02B)
• Line workers will be specifically authorised to operate an EWP
near live mains
– All other workers will continue to need explicit authorisation
• Non-qualified workers who work aloft will need to initially
complete UETTDREL14A
66
AUTHORISATIONS CARDS - PHOTOS
• We have a small number of ASPs with no photo on their
authorisation card
• You must have a photo on your card
• Make sure you email a passport sized photo with your renewal
– If you don’t currently have a photo,
– If your photo needs updating
67
SAFETY MANAGEMENT SYSTEMS
• Your company must maintain a safety management system to
meet the requirements for accreditation
• You will now need to sign a form when you renew your
accreditation confirming that you have a system in place
68
NSW WIDE TEMPORARY SUSPENSION OF
AUTHORISATIONS
• Given the unique nature of ASP work there is the potential for
safety risks to shift from one Network Operator to another
• For this reason a NSW wide authorisation suspension process
has been established for ASP workers.
• If your authorisation to work on Endeavour Energy’s network is
suspended this will be mirrored on Ausgrid and Essential
Energy’s network
• A comparable process to that detailed below has been
established within both Ausgrid and Essential Energy, so if you
are suspended from work on their networks, you will be
suspended from Endeavour Energy’s network
69
Training Requirements
70
AUTHORISATION TO OPERATE OR OBSERVE PLANT
NEAR OH MAINS
• Previously, non-electrically qualified workers who were
authorised to operate plant or equipment near OH mains, were
require to annually complete “close approach training” or
UETTDREL14A
• The required content of this course will be moved into
Endeavour Energy’s ESR refresher from the 16th of December
• You will no longer need to annually complete this training
course to maintain authorisation
– You will however need to confirm that you have operated plant or
machinery near OH mains on at least 10 occasions within the year
• UETTDREL14A will still be required to initially gain authorisation
71
RTO ACCREDITATION
• Endeavour Energy now accredits RTOs to deliver training
• Only accredited RTOs can provide any training specific to
Endeavour Energy, including;
– Electrical Safety Rules
– Excavation in a public place
• Confirm with the RTO that they are accredited prior to
undertaking training
72
Electrical Safety Rules refreshers other than specific Endeavour Energy ESR from an Accredited RTO
Will not be accepted
COMBINED ESR REFRESHER TRAINING
• Endeavour Energy has created an assessment specification
that will allow RTO’s to develop a common NSW ESR refresher
training delivery program subject to network operator approval.
• Currently it is a requirement that RTO’s deliver and assess to a
specific tailored assessment schedule however; in light of
industry feedback it has been decided to allow RTO’s to
streamline this process.
• RTO’s shall be required to submit any common ESR refresher
assessment process to the relevant network operators for
approval.
• Provided the assessment satisfies each network operator’s
requirements, a common streamlined ESR refresher may be
undertaken in the near future.
73
Electrical Safety
74
ELECTRICAL SAFETY RULE AMENDMENTS
• There will not be an amendment to the Electrical Safety Rules
released in 2015
• The next amendment to the electrical safety rules is likely to be
2016
• The delivery method and process is currently being determined
75
ARC RATED CLOTHING
• From 1 July 2016, all workers will need to wear a minimum of
4 cal/cm2 ATPV Arc Rated clothing
when working on or near Endeavour Energy’s network
– This requirement is consistent with the ENA NENS 09 (2014)
minimum recommendation for base garments
– ASPs may decide to procure clothing rated above this rating
• This requirement will be consistent across Networks NSW
– At this stage you don’t need to change anything unless you are
working in Ausgrid’s area
• Clothing meeting these requirements should be available from
commercial clothing suppliers
76
POLARITY TESTING PROCEDURES
• We are currently reviewing our polarity testing procedures and
requirements
• It is proposed that from the 2016 rules amendment, ASPs will
be required to perform service polarity testing, phasing and
neutral integrity testing in accordance with Australian Standard
4741
– ASPs will not be required to follow Endeavour Energy’s specific
procedure for polarity testing (WSY0037)
– ASP companies will need to develop, and document their own
polarity testing, and neutral integrity testing procedure
• This would align with the nationally recognised annual training
in testing of connections that you currently do
77
NEW SUBSTATION KEY ISSUES
• Our security group have rolled our a new locking system at
Endeavour Energy
• Existing padmount substation locks will only be changed where
the cubicle is replaced
• New installed substations will have the new locks
78
NEW SUBSTATION KEY ISSUES
• Security have made the decision that the new keys will not be
available for loan
• The only option currently available for ASPs to access
substations with new locks is to request accompanied access
with Endeavour Energy staff
• We have requested that security resolve this issue
79
QUESTIONS?
I’m happy to try to answer any of your questions now,
but if you think of anything later our contact details are:
80
• Electrical safety enquiries
• Interpretations of Electrical Safety Rules
• Authorisations enquiries
• Required training courses and RTOs
• Submit application forms and evidence of training
Authorisations@endeavourenergy. com.au
or; 9853 6946
or; 9853 5043
Fred Kaft
ASP Investigation Procedure
81
06
OVERVIEW
Incident Types
• Level 1 - 2
• Level 3 - 4 Serious Incidents
Examples
• Past 12 months of ASP incidents
Process
• EE ICAM
• ASP investigations – ESR and Standards
Next Steps
• Framework development
• Further communication
82
Incident Types
83
NNSW (Endeavour Energy) Incident Management
Framework
Level 1 – ASP Process
• Incidents that are of a minor and localised nature. Controlled
across the site and supervisor manages the incident
Level 2 – ASP Process
• Incidents that are more complex but still are localised in nature.
These may require a full investigation by the ASP based on
their processes
84 ASP Forum – Incident Investigations, November 2015
Level 3 – ASP and EE investigation:
• Incidents that are high consequence or high potential (near
misses). Incidents that require notification to a regulatory
authority.
Level 4 – ASP and EE investigation:
• Incidents that result in very high consequences are very
complex and have network wide implications.
85 ASP Forum – Incident Investigations, November 2015
NNSW (Endeavour Energy) Incident Management
Framework
Examples
86
Past 12 Months of Level 3 ASP incidents
• Unauthorised work on the Endeavour Energy Network.
• Reverse polarity
• Pole fall over
• Conductor fall
• Cut live HV Cable
87 ASP Forum – Incident Investigations, November 2015
Process
88
Endeavour Energy ICAM/ ASP Investigation
89
EE investigation against ESR and standards
ASP Investigation from ASP perspective – ICAM or other
ASP Forum – Incident Investigations, November 2015
Next Steps
90
Next Steps
91
Review Roles of EE and ASP
Develop framework
Communicate
ASP Forum – Incident Investigations, November 2015
QUESTIONS?
92
• Investigation enquiries
or; 9853 6781
or; 9853 6713
ASP Forum – Incident Investigations, November 2015
David Shepherd
Network Mains Updates
93
07
94
NETWORK MAINS - UPDATES
Standard Updates Technical Bulletins Upcoming
Amendments
95
MDI 0026 - Location of Isolation points on the high
voltage distribution network
96
MDI 0026 - KEY CHANGES
• Urban overhead isolation point requirements reduced to every second
pole substation.
URBAN AREAS
• Simplified classifications for non-urban areas
• Removal of the 20 customer limit between isolation points, now only
250kVA limit used.
NON-URBAN AREAS
HVC
LBLB
63kVA100kVA63kVA150kVA63kVA400kVA
97
MDI 0026 - KEY CHANGES
GENERAL
• Isolation points either side of a HVC removed and isolation at the point
of demarcation added.
• Endorsement for additional switches can be given by planning when
reliability is justified
98
TB 207 - Pole loading assessment for communication
cables
99
TB 207 - Pole loading assessment for communication
cables
100
TB 207 - Pole loading assessment for communication
cables
101
TB 207 - Pole loading assessment for communication
cables
Applicable to MCI 00002 Attachment of communication cables to
Endeavour Energy poles
• If a communication cable is
added to the pole;
– Full pole loading calculation
required
– Load shall not exceed pole
rating (pole disc)
– Can exclude customer
service drops/lead-ins
• If a communication cable is
added to the pole;
– Full pole loading calculation
required
– Load shall not exceed pole
rating (pole disc)
– Shall include customer
service drops/lead ins
Previous Requirement New Requirement
102
Upcoming Amendments
MCI 0006 - Underground distribution: Construction standards
manual
• Endeavour Energy and RMS have an MoU for trench configurations
103
Upcoming Amendments
MCI 0006 - Underground distribution: Construction standards
manual
• Endeavour Energy and RMS have an MoU for trench configurations
Scenario
Concrete
protection
layer
Concrete
encase
Existing road 1200mm 1000mm
Proposed
road
(energised
before road
completed)
1800mm 1500mm
Proposed
road
(energised
after road
completed)
1500mm 1200mm
104
Upcoming Amendments
MDI 0045 - Cable sheath bonding design
SVL
Cable Sheath
Major Section
Minor section 1 Minor section 2 Minor section 3
Link BoxLinks
Footing
Resistance
Cable details
Maximum
prospective
fault current
(kA)
Maximum
minor
section
length (m)
Voltage
(kV)
CSA
(mm2)
33
300
31.5 XX 630
800
1200
66 630 31.5 XX
132
400
31.5 XX 630
800
1200
400
40 XX 630
800
1200
• Include design requirements for cross bonding
105
Upcoming Amendments
MDI 0031 - Overhead distribution: Design standards manual
MDI 00XX - Underground transmission mains design
MDI 0028 - Underground distribution network design
Ivan Mendonsa
Contractor Operations Changes
106
08
Quality Assurance Forms – Contestable Transmission
Construction Works
107
• Forms are developed to address the gap in the process
• Forms have been circulated within Endeavour Energy for input
from Subject Matter Experts
• Planned to implement the forms from 1 Feb 2016
• Commissioning testing and reports will be carried out by the
Endeavour Energy testing group and funded by the ASP.
Quality Assurance Forms – Contestable Transmission
Construction Works
108
• Forms will be published in the ASP website for your input & your
Input required by the end of Dec 2015
• All input to be provided to Ivan Mendonsa:
• Note the attached forms below:
– ASP Transmission Forms
– CI Transmission Forms
Chris Srbinovski
LV Restoration Awareness
109
09
110
What is the hazard
Multiple houses were energised with a reversed polarity due to an incorrect
LV mains connection.
The connection was made with the distributor de energised when a new
bay of LV ABC was installed. Connections at one side of the LV cable were
correct, but at the other connection C phase and neutral were reversed.
What has been done
Staff noticed the reverse polarity immediately and reinstated the isolation.
There was no personal or property damage caused at any of the customer
installations.
111
Endeavour Energy Electrical Safety Rules
7.2.5 Low voltage customers' service connection and identification of service neutral
Reverse polarities and incorrect phase rotations
can create life threatening situations and equipment damage.
If there is any doubt the service shall be left disconnected
until the neutral has been identified.
It is the connecting person’s responsibility to ensure that all
connections are correct.
LV Isolation Guide
112
L2 ASP to note customer installation phase rotation
Switching officer to Test N/O points (phasing & volts)
L2 ASP to disconnect affected service mains including neutral (isolate & insulate)
Isolate circuit, apply PB’s as required & Issue ATW as per ESR
Commence Work
Complete works & Surrender ATW
Switching officer to Remove PB’s and cancel ATW
Begin LV Restoration
LV Restoration Guide
113
Identify possible incorrect connections points & Prepare Restoration Plan
Scenario 1 All services isolated from
LV circuit
Perform IR & Continuity tests
Energise LV circuit & perform commission tests
L2 ASP reconnect services as per
WSY0037 & submit NOSW’s
Scenario 2 Existing Parallel supply
available
Circuit left un-bonded & LV energised from
both directions
Test and make final connections live
L2 ASP reconnect services as per
WSY0037 & submit NOSW’s
Scenario 3 Spur LV circuit
Disco all services affected by possible incorrect connection
Energise & perform polarity test
L2 ASP reconnect services as per
WSY0037 & submit NOSW’s
Augment of Existing Overhead Mains
114
Possible Incorrect Connections
115
All Services Isolated For Restoration
116
• Perform IR & Continuity tests on
isolated circuit
• Energise & perform polarity tests.
• L2 ASP to restore services
New Installation With Parallel Points Available
117
• Circuit left un-bonded &
energised from both
directions.
• Test polarity and make
connections live.
• L2 ASP to restore
services
New Installation on Spur LV Circuit
118
• Disco all services, affected
by possible incorrect
connections downstream of
new installation.
• Energise & perform polarity
tests.
• L2 ASP to restore services
ASP Requirements
Include LV restoration in project plan
Provide restoration resources
L2 ASP requirements
• NOSW / FPJ 4672
• CAT 2 Underground service
• CAT 3 Overhead services
119
120
Kris Shankar
Earthing Construction Refresher
121
10
EARTHING
CONSTRUCTION
REFRESHER
Earthing and Power Quality
Kris Shankar
Electrical Engineer - Earthing
WHERE IS THE EARTHING INFORMATION ON A
DESIGN??
123
Something doesn’t seem right
• If you feel the design appears to be unfit for the location
question the designer
124
How do we construct
an earthing system?
125
EDI100
126
127
128
COMMON EARTHED POLE SUB
Both the HV earth and
the LV earth are bonded
together and connected
to earth.
HV earth connection to
Tx frame
LV earth is bonded to neutral
129
PADMOUNT SUB – COMMON EARTH
130
Only bond where
designed to
PADMOUNT SUB – COMMON EARTH
131
UGOH – COMMON EARTH
132
Only bond where
designed to
KEY ISSUES (CONSTRUCT)
• Not achieving standard resistance:
– Follow design rather than standard resistance (limit impact on
nearby homes, pits etc.)
– Question with the designer if target resistance does not line up
with design target
133
SPECIAL EARTHING CONDITIONS
• First Cables out of a Zone Sub are not to be connected to the Distribution earth bar, only earthed back at the ZS (unless the design specifies it)
• Handles which operate HV Switchgear such as ABS, LBS, Regulators, etc maybe connected to earth (in limited situations)
134
UGOH – FIRST POLE OUT
• CMEN:
– Zone substations that are
deliberately bonded into the
distribution earthing environment
(HV earths and/or LVN)
– CMEN terminology is not common
use in the industry
– First sub out or first UGOH out
135
CRIMP CONNECTIONS
136
ROD INSTALLATION
137
RECAP
• Build to the design
• If you are not sure
contact designer
• Follow standard
drawings provided by
EDI 100
138
EARTHING DESIGN
REFRESHER
Earthing and Power Quality
EXISTING SUPPORT
• Standards, e.g. EDI100
• 3E handbook
• Webinars
• Contestable work
◦ If the team require they will contact earthing
140
COMMON EARTHED EXAMPLE 1:
141
Common earthed (with series impedance)
• A common earthed asset is being installed where there maybe low
amount of MEN customers, but joined to a larger MEN pocket.
• The series impedance must be taken into account, sometimes it can
be the limiting factor in the design
• In some cases the secondary MEN can be in lower soil resistivity or
the same as the designed MEN.
• The following is examples shows how this is entered into 3E
• When 3E is used in conjunction with additional calculations, a small
report with the calculations and assumptions should be produced (1-2
pages is sufficient or as required by designer)
COMMON EARTHED EXAMPLE 1:
142
MEN 2 1500 customers
20Ωm
MEN 1 67 customers
200Ωm200m Neutral connection
COMMON EARTHED EXAMPLE 1:
143
Series
impedance of
neutral
= 0.063Ω
COMMON EARTHED EXAMPLE 1:
144
200m Neutral connection = 0.063Ω
1500 customers MEN = 0.035Ω
67 customers MEN = 3.135Ω
COMMON EARTHED EXAMPLE 1:
145
SEPARATELY EARTHED EXAMPLE 1:
146
Separately earthed (interconnected cable screens)
• A separately earthed asset is being installed in a separately earthed
area
• Soil resistivity is 700Ωm
• The following is examples shows how to incorporate a less
conservative analysis
• When 3E is used in conjunction with additional calculations, a small
report with the calculations and assumptions should be produced (1-2
pages is sufficient or as required by designer)
SEPARATELY EARTHED EXAMPLE 1:
147
UGOH
Padmount 2 Padmount 3
Padmount 1
Asset under design
Measured resistance = 45.18Ω
Measured resistance = 35.15Ω
Measured resistance = 20.23Ω
SEPARATELY EARTHED EXAMPLE 1: STANDARD
148
SEPARATELY EARTHED EXAMPLE 1:
149
ScreenResistance
Padmount 1
Padmount 2
ScreenResistance
Padmount 3 Screen
Resistance
UGOH0.041 Ω Design Ω
20.23 Ω
0.027 Ω
45.18 Ω0.044 Ω
35.15 Ω
SEPARATELY EARTHED EXAMPLE 1:
150
SEPARATELY EARTHED EXAMPLE 1:
151
SEPARATELY EARTHED EXAMPLE 1:
152
QUESTIONS?
153
• Thank you for your attention and time.
Paul Hardman
ASP Activity Report
154
11
Non Conformance Summary – Last 6 Months
155
ASP Level Major Minor Safety Total
1 15 23 1 39
• Level 1 ASP
156
Non Conformance Summary Details – Last 6 Months
Non Conformance Description Major Minor Safety Total
Assets not constructed to design specifications 5 5
Damage to assets (Investigation) 2 2
Failure to notify customers of outage 5 5
Inadequate project management 7 7
Inadequate supervision of pre-qualification works 1 1
Incorrect phasing 5 5
Low insulation resistance 1 1
Non compliance with ESR rescue kits requirements 1 1
Non compliance with MCI0005 2 2
Non compliance with substation design – earthing
(EDI100) 1 1
Non compliance with Worksite Audit (FPJ4660) 3 3
Unsatisfactory workmanship 5 5
Use of unapproved materials 1 1
Total 15 23 1 39
157
Level 1 Major Non Conformances
• Assets not constructed to design specifications
• Damage to assets (Investigation)
– Incorrect disconnection of pilot cable
• Inadequate supervision of pre-qualification works
– Using non pre-qualified staff for transmission works.
• Incorrect phasing
– Phasing information not communicated to staff.
– Pillar connections terminated incorrectly.
– Overhead conductor phases inadequately traced x 3.
Level 1 Major Non Conformances
• Low insulation resistance
– IR test not conducted on installed LV cable prior to commissioning.
• Use of unapproved materials
– Used unapproved materials without seeking dispensation from EE
Engineering Group.
158
159
Level 1 Safety Non Conformance
• Non compliance with ESR rescue kits requirements
– Damaged Rubber Gloves, no touch and trauma dressing
Non Conformance Summary – Last 6 Months
160
ASP Level Major Minor Safety Total
3 0 479 0 479
• Level 3 Non Conformances
161
Non Conformance Summary Details – Last 6 Months
Non Conformance Description Major Minor Safety Total
ADM - Failure to provide required administrative information 116 116
MDI - Non compliance with Mains Design Instruction 55 55
EDI100 - Non Compliance with Earthing Design Standards 52 52
LDI - Non compliance with Lighting Design Instruction LDI0001 50 50
IPS - Incomplete Proposed method of Supply 42 42
ICP - Incomplete Design Certification Package 39 39
NPS - Non compliance with Network Property Standard 39 39
SAD - Non Conformance to drawing Standard SAD0001 33 33
FEE - Failure to pay fees 25 25
AVS - Incorrect Asset Valuation Sheet 10 10
FDB - Failure to comply with design brief 8 8
MC5 - Non-Compliance with MCI0005 6 6
LVD - Incorrect voltage drop calculations 3 3
MC6 - Non-Compliance with MCI0006 1 1
Total 479 479
162
Level 3 Minor Non Conformances
• Failure to provide required administrative information
– Incorrect information provided on connection forms, method of
supply, design certification packages & etc.
• Non compliance with Mains Design Instructions
– MDI 0026: Underground distribution network design
– MDI 0031: Overhead distribution: Design standards manual
• Non Compliance with Earthing Design Standards EDI100
– Incorrect substation earthing layout – incorrect cable terminations.
– Inadequate earthing arrangement for UGOH poles, substation.
– EPR exceeded allowable touch/ step voltage limits.
Paul Hardman
Response to Issues from Last Seminar
163
12
Questions raised from Last Seminar
164
• Information on Earthing (Seminar Topic)
• Lease of Poles and Wires – Impacts on ASP’s
• Design issues – How to (Seminar Topic)
• Need to be able to locate forms
• Where is the link to the ASP website on the Endeavour Energy
website
• What’s going on with GIS and current performance/ (Seminar
Topic)
• Sending fees to the correct party
165
• Interactive reporting of job progress
• What are the time frames for each stage of the design process?
• What is required at each stage of the design/ construct
process?
• Cost share reimbursement scheme more information
Questions raised from Last Seminar
166
• Lease of Poles and Wires – Impact on ASP’s
– Legislation prepared;
• Electricity Network Assets (Authorised Transactions) Bill 2015
• Electricity Retained Interest Corporations Bill 2015
– Bills have been introduced to state parliament and have
progressed through the 2nd reading – now with the Upper House
for review.
– Select committee have convened and presented their report
“Leasing of Electricity Infrastructure” Printed 2nd June 2015.
Lease of Poles and Wires – Impacts on ASP’s
167
– The Plan;
• Long term lease Transgrid has been completed.
– $10.258 Billion lease
– ‘NSW Electricity Networks’ – New Owner
– Foreign Investment Review Board approval has been
given.
– Regular information being provided to staff by NSW Treasury
through a document “NSW Government Lease Transaction
Employee Question and Answers” Most recent 27/10/15.
– Impact on ASP’s
• Little or none with Transgrid lease
Lease of Poles and Wires – Impacts on ASP’s
168
– Current legislation in NSW supports the ASP scheme:
• Electricity Supply Act 1995
• Electricity Supply (Safety and Network Management)
Regulation 2014
• Scheme for Accreditation of Service Providers (March 2015)
– Legislative change needed if there is a change planned for the
Scheme
– The legislation covering the planned lease of Ausgrid and then
Endeavour do not refer to the ASP Scheme or the ongoing
interaction of the new entity with ASP’s.
– “Customer Funded Contestable Work” is a cost effective and
efficient means of connecting customers to the network.
Lease of Poles and Wires – Impacts on ASP’s
169
• Locating Forms on the ASP Website
– The Plan
• Standards move to the Endeavour Energy website.
• Standards tab on ASP Website is available for forms.
– The Result
• Standards and associated documents are on the Endeavour
Energy website.
• New Endeavour Energy website has additional facility and
includes a number of updated documents and forms.
• No forms page!
Locating Forms on the ASP Website
170
– Why?
• The old ASP website is incapable of being updated.
• A new ASP Website is being developed which will include
features identified by ASP’s.
– Expected delivery 2nd quarter 2016.
Locating Forms on the ASP Website
171
The Link to the ASP Website on the EE Website Page
• Where is the link to the ASP website on the EE website page?
– The old webpage required that a number of pages were opened to
gain access to the ASP website login page.
– The new website is very simple
• Select ASP’s from the top banner line
• The ASP Website login is immediately available.
172
The Link to the ASP Website on the EE Website Page
173
The Link to the ASP Website on the EE Website Page
174
The Link to the ASP Website on the EE Website Page
• For ASPs who want access to the ASP website;
– Click on [email protected] on the ASP
website page.
– Rachel will respond with a login within a couple of days if all data is
provided on the email form.
175
Sending Fees to the Correct Party
• Sending fees to the correct party
– Notice of Advice letter issued by Endeavour Energy –
• Applicant advises ASP Level 3 and who is responsible for fees
• Around 25 – 30% of jobs the company responsible for fees is
not the Level 3 ASP.
• Current process is manual – requires CWO/ CWE to identify
the different parties and send the appropriate correspondence.
• Investigating option of CAMS change to capture both sets of
data and have the required documents correctly addressed.
176
Sending Fees to the Correct Party
– Letter of intent letter issued by Endeavour Energy -
• Response provided lists all participants and their roles.
• All details updated in CAMS and used for the remainder of
activity on the project.
– Where the developer changes Level 1 after initial notification
• Revised Letter of Intent required.
• Statement also from Developer indicating that all contractual
responsibilities to original Level 1 have been met.
177
Interactive Reporting of Job Progress
• Interactive reporting of job progress
Drivers:
– AER Decision
– Lease imminent
– No corporate appetite for change
Result:
– Company will not proceed with interactive online reporting.
178
Interactive Reporting of Job Progress
• Customer self service
– This initiative will proceed.
– Online application / validation for basic connection offer.
– Issue PTC if all criteria are met.
179
Time Frames for Each Stage of the Design Certification
Process
• What are the time frames for each stage of the design certification
process?
Process Action by
EE ASP
Days KPI
1. Receive Completed Application
2. Application Acknowledgement
14 Days 3. Supply Offer
- Level 3 ASP required
- Pay up and connect
4. Notice of Advice (NOA)
5. Proposed MOS
6. Design Brief Issued 14 Days
7. Design Package Received
8. Design Certification 14 Days
180
What is Required at Each Stage of the Design Process
1. Completed Application
– All requirements in the application form fully completed
4. Notice of Advice
– The notification of advice form is completed with all required
information
5. Proposed MOS
– WPJ 4120 clause 4.7
“The proposed Method of Supply must included sufficient relevant
information to enable the CWE/ CWO to carry out the appropriate
assessment”
(Numbering From Process Steps on Previous Slide)
181
What is Required at Each Stage of the Design Process
– The documentation provided by the Level 3 ASP shall comprise of:
• Branch Form FPJ 4103 – Method of Supply Proposal
• Related sketches / GIS mark ups
• Voltage Drop Calculations
• Network equipment locations including coordination with
building structures
• Site inspection photographs
– Reference shall be made to all relevant Australian Standards,
Company policies and standards necessary to prepare a
complying document.
182
What is Required at Each Stage of the Design Process
7. Design Package Received.
─ WPJ 4130
From Annexure B of WPJ 4130 the following items are to be provided
by the Level 3 ASP.
– Drawing complying with SAD 0001
– Complete Asset Valuation Sheet (FPJ 4160)
– Complete Environmental Assessment with Photographs (FAT
0038)
– Complete Audit Check List
– Design Safety Report
183
What is Required at Each Stage of the Design Process
─ Completed Voltage Drop Calculations (MDI 0030)
─ Property Tenure Documentation
─ Signed Agreement to Enter and Create Easement (when required)
─ Agreement Document from Other Authorities (Telstra, Sydney Water etc)
─ GIS/ CAD Validation Report – Indicating “No P1 or P2 errors”
Additionally;
─ All fees paid
• CWO/E will check all documents have been provided – where documents are
missing a non-conformance will be issued and the ASP requested to submit
additional documents.
184
Cost Share Reimbursement Scheme – More Information
• Cost share reimbursement scheme originally introduced by
IPART in their Determination No.1 – 2002.
– Applied by Endeavour Energy as a rural reimbursement scheme
• Change to the National Electricity Rules (NER) Part E of
Chapter (5A) defined a broad outline and intent for a cost
sharing scheme.
• Endeavour Energy have interpreted these requirements into the
following documents;
– Connection Policy (May 2014) clause 5.0.
– Pioneer Reimbursement Scheme Principles (June 2014)
Both Documents available on the Endeavour Energy website
185
Cost Share Reimbursement Scheme – More Information
• Seminar presentation for Level 3 ASPs on 9/12/2014
− Section 6 – Cost Share Reimbursement Scheme: Han Phan
• Seminar material on the ASP website
− IN 046/14 Dated: 15/12/2014
• ASP Actions
− Complete assessment
− Include appropriate label (55(A)) on the design
− Scheme activated based on your information
Paul Hardman
General Business
186
13
Important Notices
• IN 036/15 – Substation Order Form Lvl 1
• IN 037/15 – Website Availability All ASP’s
• IN 038/15 – Accellion Upgrade Lvl 3
• IN 039/15 – Approved RTO for ASP’s All ASP’s
• IN 042/15 – V4 Revision to Fees Schedule All ASP’s
• IN 041/15 – GIS Update Lvl 1 & 3
• IN 040/15 – Meter Issue Hoxton Park – Field Safety Day Lvl 2
• IN 038A/15 – Accellion Update Lvl 3
• IN 038B/15 – Accellion Update Lvl 3
• IN 044/15 – Availiability of Outage Informaiton Mobile Application All ASP’s
• IN 043/15 – Tariff Structure Statement (Request for Comment) All ASP’s
• IN 045/15 – IT System Changes All ASP’s
• IN 046/15 – GIS – GNET Viewer Availability Lvl 1 & 3
• IN 051/15 –Transformer Workshop Update Lvl 1
187
General Business
• Questions or Discussion
• Please complete feedback forms.
188