Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
For Public Use
Leveraging trading through energy exchange
Rajesh K MedirattaDirector (Business Development)
• 25-year PPA - Tariff on cost-plus or competitive bidLong-term
• 3 Month- 3 Years • Tariff covers : Fixed Cost + Variable Cost+ Mark Up
(< long term) Medium Term
• Intraday- 3 Months to be procured through competitive bidding only
• Single tariff covering Tariff covers Fixed Cost+Short Term (OTC)
• Highly liquid and transparent marketplace• More accurate load management
Day-Ahead Market
• Last-minute adjustments (Gate closure 4 hours)• Less liquid
Intra-day
Discom’s Options For Power Procurement 2
India Power Sector I Present Market Segments
Source: CERC MMC Report
Long Term Short Term
Long-term Power Purchase Agreements
(PPA)
Over the Counter Bilateral Trade
Agreements (OTC)Effected by Licensed
traders
Deviation settlement/Unscheduled Interchange
89.7% 4.8% 3.5% 2.0%
Exchanges (Only up to 11 days) Day Ahead Contingency DailyWeekly Day Ahead Market
Short Term Power market is at ~10%, Power Exchange volume in the segment have been growing significantly
Up to 25 years OTC:Intraday to 1 year
Exchanges: Intraday – 11 days Real Time
1,157,938 MU
1,038,708 MU 55,980 MU 40,032 MU 23,218 MU
All values for FY17
3
Share of Short Term Market in Total Generation
25 21 19 21 23
1517
16
2421
24
31 29
35
41
36 35 35 3534
0
5
10
15
20
25
30
35
40
45
FY12-13 FY13-14 FY14-15 FY15-16 FY 16-17
Volu
me
(BU
)
UI/DSM Direct Exchange Bilateral (trader)
Share in TotalGeneration 10.9% 10.4% 10.3%10.9% 9.5%
Source: CERC MMC Reports
• Short term market grew at a rate with a CAGR of 9% (FY-10 to FY 17).• Power Exchanges witnessed growth at a CAGR of 28% (FY-10 to FY 17).
4
PRICE AND VOLUME TREND IN THE POWER MARKET
5
IEX Market Segments
Day-Ahead Marketsince June,08
• Delivery for next day• Price discovery: Closed , Double-sided Auction
Term-Ahead Contracts since Sep’09
• For delivery up to 11 days• Daily Contracts, Weekly Contracts
Renewable Energy Certificatessince Feb’11
Energy Saving Certificatessince 27th Sept’17
Intraday Market & Day-Ahead ContingencyRound the clock since Jul’15
• Intraday: For Delivery within the same day• Day Ahead Contingency: Another window for next day• Gate closure : 3 hours
• Green Attributes as Certificates• Sellers : RE generators not under feed in tariffs• Buyers: Obligated entities; 1MWh equivalent to 1 REC
• 1 ESCert = 1 mtoe (metric Tonne of Oil Equivalent)• Trading Session on every Tuesday of the Week• Trading time 1300 hrs to 1500 hrs
Auction Continuous
6
Price Comparison of a typical day
0.00
1.00
2.00
3.00
4.00
5.00
6.00
1 6 11 16 21 26 31 36 41 46 51 56 61 66 71 76 81 86 91 96
Pric
e (R
s/kW
h)
15 min time block
Winter Summer
7
Winter: 18/12/2016 | Summer: 15/04/2017
High Liquidity in Volume at IEX(Avg. Hourly Volume in MW)
1,13
0
1,33
4
1,91
9
2,84
2
4,45
6
4,73
7
4,94
2
4,90
7
5,44
5
698
1,30
2
2,37
1
2,53
9
3,95
6
5,74
1
4,68
9
6,43
4
8,80
6
394
704
1,34
7
1,57
1
2,55
4
3,30
2
3,21
2
3,87
8
4,54
1
7.23
5.19
3.56 3.54 3.49
2.80
3.51
2.732.41
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17
MCP
(Rs.
/kW
h)
Avg.
Hou
rly V
olum
e (M
W)
Purchase Bid (MW) Sell Bid (MW) Cleared Volume (MW) MCP (Rs/kWh)
Data as on 31st Mar’ 2017
8
Monthly Market Snapshot (DAM)- Average hourly MW
2.772.92
2.59 2.49
3.13
4.09 4.08
3.55
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
0.00
2000.00
4000.00
6000.00
8000.00
10000.00
12000.00
April May June July August September October November
MCP
(Rs/
kWh)
Aver
age
Hou
rely
Vol
ume
(MW
)
Purchase Bid (MW) Sell Bid (MW) Cleared Volume (MW) Price (Rs./kWh)
9
Daily Purchase and Sell bid trend November
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
5.00
0.00
50.00
100.00
150.00
200.00
250.00
300.00
350.00
1/11
/201
7
2/11
/201
7
3/11
/201
7
4/11
/201
7
5/11
/201
7
6/11
/201
7
7/11
/201
7
8/11
/201
7
9/11
/201
7
10/1
1/20
17
11/1
1/20
17
12/1
1/20
17
13/1
1/20
17
14/1
1/20
17
15/1
1/20
17
16/1
1/20
17
17/1
1/20
17
18/1
1/20
17
19/1
1/20
17
20/1
1/20
17
21/1
1/20
17
22/1
1/20
17
23/1
1/20
17
24/1
1/20
17
25/1
1/20
17
26/1
1/20
17
27/1
1/20
17
28/1
1/20
17
29/1
1/20
17
30/1
1/20
17
Pric
e pe
r uni
t
Mill
ion
Uni
ts
Purchase Bid Sell Bid Cleared Volume Price
10
0.00
1.00
2.00
3.00
4.00
5.00
6.00
0.00
50.00
100.00
150.00
200.00
250.00
300.00
350.00
Pric
e pe
r uni
t
Mill
ion
Uni
ts
Purchase Bid Sell Bid Cleared Volume Price
Daily Purchase and Sell bid trend October
11
Monthly Average Market Clearing Price (Rs/kWh)
2.68
2.62 2.562.74 2.82
3.68
3.03
2.67 2.56 2.52
2.30
2.612.91
2.32 2.312.16 2.17
2.43 2.462.32 2.32
2.50
2.54
2.56
2.772.92 2.59
2.49
3.13
4.09 4.08
3.55
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Avg. MCP FY15-16: Rs 2.73/kWhAvg. MCP FY16-17: Rs 2.42/kWhAvg. MCP FY17-18: Rs 3.20/kWh
Data as on 30th Sept 2017
12
15 min price trend on 11th December 2017 (Monday)
Even within the day, prices @ night are much lower, providing opportunities to the Discomsto utilize the market
0.00
0.50
1.00
1.50
2.00
2.50
3.00
3.50
4.00
4.50
5.00
5.50
00:0
0 - 0
0:15
00:4
5 - 0
1:00
01:3
0 - 0
1:45
02:1
5 - 0
2:30
03:0
0 - 0
3:15
03:4
5 - 0
4:00
04:3
0 - 0
4:45
05:1
5 - 0
5:30
06:0
0 - 0
6:15
06:4
5 - 0
7:00
07:3
0 - 0
7:45
08:1
5 - 0
8:30
09:0
0 - 0
9:15
09:4
5 - 1
0:00
10:3
0 - 1
0:45
11:1
5 - 1
1:30
12:0
0 - 1
2:15
12:4
5 - 1
3:00
13:3
0 - 1
3:45
14:1
5 - 1
4:30
15:0
0 - 1
5:15
15:4
5 - 1
6:00
16:3
0 - 1
6:45
17:1
5 - 1
7:30
18:0
0 - 1
8:15
18:4
5 - 1
9:00
19:3
0 - 1
9:45
20:1
5 - 2
0:30
21:0
0 - 2
1:15
21:4
5 - 2
2:00
22:3
0 - 2
2:45
23:1
5 - 2
3:30
Market Clearing Price 11-12-17
MCP
Power in night hours available below Rs 2.5/unit
13
‘SMART’ Options with Distribution Companies
SMART CONTRACTING
SMART PROCUREMENT
Ensuring ideal mix of long term and short term power purchase
arrangements to manage fixed cost and manage availability of supply
On a day to day basis- managing demand of the area by utilizing cheaper short term
sources by replacing power from high variable cost plants and ensuring MERIT
order based dispatch
Commercial decision-making
14
1. SMART Procurement• Under long term & medium term PPA : two part tariff
• Capacity charges (commitment charges): paid irrespective of whether discompurchase power from these plants or not
• Energy charges : Paid corresponding to the number of units of power purchasedfrom that particular plant
• Discoms can replace costlier long term power by procurement from IEX, if,• Energy charge of power plant is greater than IEX rates• During night hours prices at IEX are further low and savings can be enhanced
• Discoms can replace ISGS first, keeping import constraint in consideration
• Discoms can continue paying fixed charge to Long Term PPAs and substitutewhere energy charge is higher than IEX price
15
PPA 1 I 3.70
PPA 2 I 4.06
Long Term Contracts
Bilateral Contracts Exchange
Capacity Tied up by Discom
IEX Price I 2.45
Merit Order Baseline
PPA 3 I 3.00
PPA 4 I 1.99
PPA 5 I 2.00
PPA I Variable Cost
Must Run Plants(includes all hydro, nuclear or
other ‘take or pay’ type contractual plants)
Contract 1 I 4.70
Contract 2 I 3.50
Contract 3 I 2.10
Merit order dispatch schedule to be prepared based on Variable cost and considering Exchange Prices
16
PPA 1 I 3.70
PPA 2 I 4.06
IEX Price I 2.45
PPA 3 I 3.00
PPA 4 I 1.99
PPA 5 I 2.00
Must Run Plants(includes all hydro, nuclear or
other ‘take or pay’ type contractual plants)
Contract 1 I 4.70
Contract 2 I 3.50
Contract 3 I 2.10
Increasing Variable Cost
To be dispatched in this Order based on Energy
Demand of the Discom
Merit Order Baseline
17
SMART Procurement
Gen 1 : 100 Gen 2 :80 Gen 3: 120Avl Gen in MW
Variable cost Rs 1/unit Rs 3/unit Rs 4/unit
Possible Backdown /Surrender (MW) 20 5 25
Replacement cost/ Exchange Bid Rs 0.5/unit Rs 2.5 /unit Rs 3.5/unit
Exchange Price
Rs 2.1/unit 5MW 25 MW
Rs 2.6/unit 25MW
Opt
imiz
atio
n /R
epla
cem
ent
Bid
Smart Buy
18
SMART Procurement
• Assess Generation availability and Demand Forecast for next day (15 min block) • Generation data for Long Term (LT) I Medium Term (MT) I Short Term (ST)• Calculate Surplus and Shortage to prepare “Regular Bid”
• Prepare schedule with maximum back down possible for LT & MT • For every plant identify maximum back down possible considering all constraints
• Technical I Must Run status I Contractual I Transmission ( Intra / Inter-state)• Give technical minimum schedule to these plants and identify “Replacement Bid” quantum
• Submit Bid at Exchange (1000 Hrs-1200 hrs)• Regular Bid: For Regular Shortage/Surplus depending on the demand and Generation cost • Replacement Bid: Price sensitive bids ( based on Variable cost) for every plant• Two Bid Options
• Single Bid: For every 15 min time block separately. May lead to non uniform back down schedule • Block Bid: All or none principle for clubbed time blocks. Will ensure uniform back down schedule
• Post IEX result- finalize schedule ( after 1500 Hrs)• If Replacement bid not selected: Revise the schedule from the plants whose bid is not selected• If Replacement bid selected: No change and retain the earlier schedule (max possible back down)
19
Timeline for Bidding and BackdownIEX
Bidding
D - 1
12 PM10 AM00 3 PM
DAM Biding periodResults declared
ISGS Scheduling
3 PM9 AM00One hour
before delivery
Declared Capacity Requisition for Scheduling
D
If Bid Selected
No Need for giving Requisition
If Bid Not Selected
Requisition can be given one hour before Delivery time
20
Merit Order
Power Plant Variable Cost (Rs/kWh) IEX Price (Rs/kWh)
KAWAS LF/RF 7.46/4.51
RTC: Rs 2.23/kWh(July’17)
GANDHAR LF 4.49MAUDA (MSTPS-II) 3.00MAUDA (MSTPS-IV) 2.87NTPC RSTPS 1&2 2.42KAWAS NAPM/APM 2.05/1.83GANDHAR NAPM/APM 2.04/1.77VSTPS-STG-I 1.51VSTPS-STG-II 1.42VSTPS-V 1.42VSTPS-STG-III 1.41VSTPS-STG-IV 1.41SIPAT-II 1.37SIPAT I 1.33KSTPS 1.30
Source: www.vidyutmode.in*Landed price including POC loss and POC charges as belowPOC Loss: 2.52% & POC Charges : Rs 0.27/kWh
21
CASE STUDY: Cost Optimization by Bihar
• Bihar has initiated the process of Cost Optimization• The costlier power from Barh & Dadri stations is replaced by
the cheaper power from IEX.• The Energy Charges of these power plants are greater than the
IEX rates.
• Bihar has made a saving of over 11 crores in 21 days
Due to low prices at the Exchange there was further potential toincrease savings
22
Bihar Savings
Delivery Day Savings(in Rs. Lacs)
Further Savings(in Rs. Lacs) Total
6th June'15 19 83 102 7th June'15 55 38 93 8th June'15 51 17 68 9th June'15 31 43 74 10th June'15 37 27 64 11th June'15 60 9 69 12th June'15 46 15 61 13th June'15 75 30 105 14th June'15 12 80 92 15th June'15 18 70 88 16th June'15 31 53 83 17th June'15 181 0 181 18th June'15 71 20 92 19th June'15 102 0 102 20th June'15 103 8 111 21st June'15 78 30 108 22nd June'15 29 67 96 TOTAL 997 487 1,274
*A min of 200 MW power purchase is
considered in each block
with replacement
of Dadri & Barh power
23
0
5
10
15
Savings in Rs Crore, FY17
Mar-17
7
Apr-17
15
3.57 3.23
5.71 5.98
33.9 52.9
Wtd. Avg IEX
Price (Rs/unit)Wtd. avg
Bilateral Price
(Rs/unit)Volumes (MU)
Telangana example:Procurement on exchange in March-April ’17 increased by 45% yoy
Better utilization of exchange has generated significant savings for TL DISCOM
Note: Savings estimated by assuming that scheduled vol. from exchange would otherwise be procured from bilateral contracts. Exchange prices includes POC Charge of Rs. 0.2134/Unit, POC Loss of 1.62% of clearing price, and Rs 0.02/unit transaction charge; Wtd. Avg Bilateral Price calculated on bids placed on DEEP Platform; April prices based on bids in 1-15 April periodSource: Power exchange, DEEP Platform
Total ~Rs. 22 Cr
TL PURCHASED HIGHER VOLUMES IN FY17 WITH BETTER SCHEDULING %
TOTAL SAVINGS OF ~ RS 22 CR TO TL DISCOMS FROM PURCHASES ON PX IN MARCH-APRIL 2017
Date Total Bid(MU)
Total Sched.(MU) Sched. %
Apr-17 54.0 52.9 98%
Apr-16 54.6 46.5 85%
Mar-17 43.8 33.9 77%
Mar-16 23.5 13.5 57%
Total (Mar-Apr 17) 97.8 86.8 89%
Total (Mar-Apr 16) 78.0 59.9 77%
24
Some states have not utilized Short Term power sources (e.g. exchange) as well as other States
Note: % bought on IEX is calculated on the total energy availability; Power purchased from IEX is calculated assuming that energy is scheduled from IEX on RTC basis; MH data is based on procurement by MSEDCLSource: IEX data; CEA Reports
0
2
4
6
8
10%
UTT
ARAKH
AN
D
10.0%J&
K
4.7%
WES
T BEN
GAL
4.2%
DEL
HI
2.7%ASSAM
2.7%
CH
AN
DIG
ARH
2.6%
KER
ALA
2.0%
HP
2.0%
AP
1.6%
CH
HATT
ISG
ARH
1.4%
PUN
JAB
1.2%
TELA
NG
AN
A
0.9%
UP
0.8%
RAJA
STH
AN
0.7%
MAH
ARASH
TRA
0.5%
KARN
ATA
KA
0.5%
MP
0.0%
HARYA
NA
0.0%
469638672 1,984 234 81442 1741,295 462 298805 6 0472334 733835Volume bought on
IEX (FY17) (MU)
535314 47 9 502 913 23 61106 66 496724 13931Total Energy
availability (BU)
547377 226 27 935 20148 53 3492 1 05438 8495Power Purchased
from IEX (MW)
Share of energy bought on exchange, FY17 (%)
25
Smart Procurement : Saving Potential
Rs. 3200 crore from Smart Procurement
State
DISCOM
losses(in INR
cr, FY17E)
Smart Procurem
ent savings
(in INR cr,FY17)
Average power to
be bought (MW)
Uttar P 5012 800 1350Tamil Nadu 2224 490 660
Punjab 1681 190 400Haryana 2911 270 400
Andhra P. 1032 170 350Telangana 4380 150 300
Maharashtr 2639 110 390Rajasthan 2195 80 190
Bihar 2275 60 125MP 2278 20 70
Other states** -1955 820 1450
Total 25000 3200 5700
26
Key factors considered for Smart Power Procurement• Demand Forecast - Forecast on 15 min time block basis
• Generation Data• Plant wise DC /Entitlement of various ISGS and SGS on Day ahead basis• Variable cost of all generators (ISGS,SGS, Bilateral etc)• Applicable losses and charges Import/Export (banking etc)• Generator outage period
• Optimization potential assessment• Must run plants• Back down potential in each plant considering
• Technical minimum• Contractual minimum• Network constraints• Ramp-up/Ramp down
27
2. Smart Contracting
i. Discoms should tie-up PPA only to manage their basedemand
ii. Many Discoms have tied PPAs to meet their peakdemand as well. The Discoms have to pay the capacitycharge for this quantum even in the off peak time.
iii. So for optimum utilisation, Long Term PPA should beonly for base demand and remaining energy (for peakand variations in forecast) should be bought throughother available market options.
28
Monthly Demand Curve for Delhi
Monthly Peak -Source : CEA
4,1763,849
3,618
4,799
6,308 6,261 6,342
5,7075,305 5,442
3,5103,857
0
1000
2000
3000
4000
5000
6000
7000
Jan'16 Feb'16 Mar'16 Apr'16 May'16 Jun'16 Jul'16 Aug'16 Sep'16 Oct'16 Nov'16 Dec'16
Dem
and
(MW
)
Month wise Delhi Demand (MW)
Base
De
man
d
29
Monthly Demand Curve for Punjab
Monthly Peak -Source : CEA
6,283
7,997
10,99711,408 11,204
10,543
8,408
5,5486,266 5,954
6,475 6,536
0
2000
4000
6000
8000
10000
12000
April'16 May'16 June'16 July'16 Aug'16 Sep'16 Oct'16 Nov'16 Dec'16 Jan'17 Feb'17 Mar'17
Dem
and
(MW
)
Month wise Punjab Demand (MW)
Base
De
man
d
8500 MW
11,500 MW
5500 MW
30
6642 6561 6815 6556 6668
74637780
89129539 9671
9215
7860
0
2000
4000
6000
8000
10000
12000
Nov'16 Dec'16 Jan'17 Feb'17 Mar'17 Apr'17 May'17 Jun'17 Jul'17 Aug'17 Sep'17 Oct'17
Dem
and
(MW
)
Base
Dem
and
Monthly Demand Curve for Haryana
Monthly Peak -Source : CEA
31
Surpluses/Deficits - Balance physical supply and demand
Meeting Shortages/Surplus through Short Term MarketMaximizing efficiency – Ideal Scenario (Monthly)
0
1000
2000
3000
4000
5000
6000
7000
1 2 3 4 5 6 7 8 9 10 11 12
Base (MW) Short Term (MW) Load (MW)
PPA (Base Load Contract)
Short Term/Exchange for peak load
Month
Surpluses/Deficits - Balance physical supply and demand
Meeting Shortages/Surplus through STMMaximizing efficiency – Ideal Scenario (Hourly)
0
500
1000
1500
2000
2500
3000
3500
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Base (MW) Short Term (MW) Load (MW)
PPA (Base Load Contract)
Short Term/Exchange for peak load
Smart Contracting-Ideal mix LT
Methodology 2 -Long term PPA for 80% of total energy demand
• Draw load curve for a state (indicating demand met in MW for each hour of the year), • Estimate the demand met in MW that corresponds to meeting 80% of total energy demand
over the year• Estimate total capacity required to meet baseload demand by applying an average Plant Load
Factor (PLF) to the baseload demand met (in MW).
Commercial decision-making
34
Key considerations – for long-term • Demand projections for next few years (say 3)• Extent of Renewable growth• Solar Rooftop potential• Hydro potential in the State
35
Procurement Strategy for Renewable Energy
• Purchase of bundled green power to be benchmarked with marketdetermined prices of power & REC
• Discom can purchase Power @ 2.41 (IEX Avg. Price for FY17)REC @ 1.00
3.41
• Deficit state should procure renewable power only if the power is available atPrice less than Rs 3.41/kWh.
• Flexibility in procurement as Discom can purchase power when they actuallyneed.
Flexible Purchase at most competitive price
36
Power Exchange across Globe:Enormous potential to grow for India compared to international benchmarks
INDIA TRADES ~3% OF ITS OVERALL CONSUMPTION ON EXCHANGE MARKETS COMPARED TO 15-91% GLOBALLY GLOBAL BENCHMARKS ON PENETRATION OF ST MARKETS
0
20
40
60
80
100
Exchange traded ( % total
consumption)
India
France
UK
Netherlands
Germany
Italy
Nordic
2004 05 06 07 08 09 10 11 12 13 14 15
Indian markets still at a nascent stage and high potential for growth for the Indian Power Exchanges
VOLUME IN BU (Billion Units)
37
IEX SMART POWER PROCUREMENT TOOLUNDER PILOT TESTING PHASE
38
Generation Master39
Replacement Potential Assessment40
Bid Preparation41
Suggestions for development of competitive power market
Power Purchase cost optimisation by Discoms• Follow merit order dispatch
• Discom to ensure that the principle of economic dispatch/ merit order dispatch(National Tariff Policy), is followed while preparing day-ahead power procurementplan. The merit order should include energy charge of all available power plants,power exchange prices and prices of other short term arrangements
Policy push for promoting short term market• Prices discovered on Short term market, particularly Exchanges is very competitive,
therefore policy initiatives for short-term transactions be encouraged.• Allow coal linkages for merchant power plants also.
Long term PPAs by Discoms should be limited to 10-12 years• Discoms in past contracted long term power on the basis of peak demand, as a result,
many of the states landed up having surplus capacity during 6-7 months in a year, payingcapacity charge without utilizing the power.
• PPAs should not be more than 10-12 years to give comfort to the bankers.• PPAs which expire after 25 year period should not be renewed and be allowed to sell
power in market on competitive basis
42
Register for IEX Monthly Bulletin
Register for Daily SMS alerts
Use IEX Mobile Application to track prices
Follow us @IEXLtd
Thank Youwww.iexindia.com
43