LHCb and its upgrade - Reducing further the UX85/1 beam pipe diameter? A major upgrade of LHCb is scheduled for 2018 (LS2) to run at up to 2*10 33 cm -2 s -1 with a data taking at 40MHz. On the detector side, mainly the tracking devices will be replaced. This gives the possibility to think about increasing the acceptance region for the tracking station in front of the magnet - closer to the beam line. -> will improve considerably the tracking between the VeLo and the Tracking Station after the magnet, having another tracking segment between both!

LHCb and its upgrade - Reducing further the UX85/1 beam pipe diameter?

  • Upload
    caspar

  • View
    50

  • Download
    0

Embed Size (px)

DESCRIPTION

LHCb and its upgrade - Reducing further the UX85/1 beam pipe diameter?. A major upgrade of LHCb is scheduled for 2018 (LS2) to run at up to 2*10 33 cm -2 s -1 with a data taking at 40MHz. On the detector side, mainly the tracking devices will be replaced. - PowerPoint PPT Presentation

Citation preview

Page 1: LHCb  and its upgrade -  Reducing further the UX85/1 beam pipe diameter?

LHCb and its upgrade - Reducing further the UX85/1 beam pipe diameter?

A major upgrade of LHCb is scheduled for 2018 (LS2) to run at up to 2*1033 cm-2s-1 with a data taking at 40MHz. On the detector side, mainly the tracking devices will be replaced.

This gives the possibility to think about increasing the acceptance region for the tracking station in front of the magnet - closer to the beam line.

-> will improve considerably the tracking between the VeLo and the Tracking Station after the magnet, having another tracking segment between both!

Page 2: LHCb  and its upgrade -  Reducing further the UX85/1 beam pipe diameter?

1 2 3 4

54 mm Ø50 mm Ø

60 mm Ø

381 mm Ø262 mm Ø

25 mrad10 mrad

142 mm Ø

1940 mm 3648 mm

420 mm 145 mm

6050 mm

1290 mm

5330 mm

Trigger Turicensis (TT)

Page 3: LHCb  and its upgrade -  Reducing further the UX85/1 beam pipe diameter?

Two track segment in the tracking after the magnetNo track element in the TT -> not possible to link the segment with the one in the VELO!

Page 4: LHCb  and its upgrade -  Reducing further the UX85/1 beam pipe diameter?
Page 5: LHCb  and its upgrade -  Reducing further the UX85/1 beam pipe diameter?

UX85/1 before welding to the VELO exit window.

Page 6: LHCb  and its upgrade -  Reducing further the UX85/1 beam pipe diameter?

TT

UX85/1

RICH 1Magnet

Page 7: LHCb  and its upgrade -  Reducing further the UX85/1 beam pipe diameter?

Is there any possibility reducing the beam pipe diameter close to the TT station?

Although …• already down at 50mm in diameter• close to on of the LHC injection• HL-LHC• …• Aperture for LHCb were presented 3/2/2009 (M.

Giovannozzi: “These values might be too pessimistic!”)