Lighting Voltage Supprestion in Gis

Embed Size (px)

Citation preview

  • 7/28/2019 Lighting Voltage Supprestion in Gis

    1/5

    Approaches for Suppressing of Lightning

    Overvoltage in the Gas-Insulated Substation (GIS)

    AbstractGas-insulated substations (GIS) have different

    specifications in proportion to air-insulated substations. Due to

    space limitation in the field of the gas-insulated substation (GIS),

    it is difficult to install extra arresters near the power

    transformers. Voltage magnification is due to reflections oftransient waves in various junctions, low surge impedance and

    decrease in the length of conductors in the GIS. These problems

    cause to increase the propagation of transmitted and reflected

    waves within the conductors in proportion to air-insulated

    substation; thereby overvoltages in GIS are more important than

    air-insulated substation. In air-insulated substations, probability

    of failures across insulator strings or bushings is acceptable since

    air insulation is self restoring. In GIS, the entire gas insulated

    assembly must be protected because the gas insulated system

    must be considered as non-self-restoring. According to

    aforementioned reasons, it follows that insulation coordination

    design of the GIS has been critically important. This paper

    presents practicable and beneficial approaches to the industry to

    look for the optimum approaches for lightning incoming surge

    mitigation. These approaches are included effects of number of

    surge arrester in the each feeder, system configuration and

    decreasing of number of surge arrester and as costs, location of

    surge arrester and cable, and terminal components. Lightning

    overvoltages due to direct lightning stroke with varying intensity

    current have been investigated. For accurate calculations,

    ATP/EMTP software has been used.

    Keywords- Insulation Coordination; lightning; gas insulated

    substation (GIS); surge arrester; cable; the terminal component;

    switchgear arrangement

    I. INTRODUCTIONGas Insulated Substation (GIS) has been developed for

    wide range, because of their benefits. These benefits are suchas compactness, protection from pollution, high reliability, a

    few maintenance, etc [1]. Gas-Insulated Substations (GIS) are

    exposed to the same variety of overvoltages as air-insulated

    substations (i.e., lightning. switching, and temporary

    overvoltages) [2].

    However, in air-insulated stations, primary concern is placed

    on the protection of transformers and some risk of failures

    across insulator strings or bushings is accepted since air

    Insulation is self restoring. In GIS on the other hand, theentire gas insulated assembly (including enclosures, circuit

    breakers, disconnect and grounding switches) must be

    protected because the gas insulated system must be viewed as

    non-self-restoring. In the insulation coordination design of the

    GIS, lightning overvoltages are found to be critically

    important. Voltage magnification due to reflections of suchlightning surges at various junctions within the GIS is often

    the determining criteria for selection of surge arrester rating

    and locations [2].Though lightning surges have been reduced to an acceptable

    level in modern substation insulation coordination, still

    transformer failures related to lightning are often reported.

    Two possible transformer failure modes may happen if a

    lightning surge appears at the transformer terminals. The

    transformer main insulation (the insulation between HV

    winding and LV winding, HV winding and core, or HV

    windings) will be threatened because of the large magnitude of

    the lightning surge. On the other hand, the insulation between

    turns at the beginning of the HV winding is oftendisproportionally more stressed because of the large potential

    gradient appearing in the initial voltage distribution. Similar to

    switching overvoltages and VFT, it is possible that lightning

    overvoltage may excite partial winding resonance in the

    transformer windings. The distance between the arrester and

    the transformer will determine the overvoltage magnitude at

    the transformer HV terminals [3],[4].Several factors may contribute to a transformer failure due to

    lightning strokes including: 1) very high magnitude of the

    overvoltage; 2) nonlinear voltage distribution along the

    winding, which could result in high voltage between turns; 3)

    Resonance or partial-winding resonance in the HV winding if

    they coincide with the excitation frequencies [4],[5].This paper presents beneficial approaches to the industry to

    look for the optimum approaches for lightning incoming surge

    mitigation, including number of surge arrester, location of

    surge arrester/cable, system configuration and decrease

    number of surge arrester, the terminal component.

    II. LIGHTNINGLightning overvoltage is a phase-to-ground or phase-to-phaseovervoltage produced by one specific lightning discharge. The

    Ahmad Tavakoli

    Iran University of Science and

    Technology, Center of Excellence for

    Power System Automation and

    Operation, Tehran, Iran

    [email protected]

    Ahmad Gholami

    Iran University of Science and

    Technology, Center of Excellence for

    Power System Automation and

    Operation, Tehran, Iran

    [email protected]

    Ali Parizad

    Iran University of Science and

    Technology, Center of Excellence for

    Power System Automation and

    Operation, Tehran, [email protected]

    978-1-4244-4813-5/10/$25.00 2010 IEEE

  • 7/28/2019 Lighting Voltage Supprestion in Gis

    2/5

    lightning overvoltages have duration bet

    microseconds and a wave front between 1 anThe wave shape of the lightning current is

    voltage produced at the point of contact

    stroke. The lightning condition and

    specifications are shown in the table. I. Th

    stroke current and its rate of decay were de

    the guide lines given in References [2].

    TABLE . THE LIGHTNING CONDITION AND THE APP

    Peak Current (kA) 50 75 100

    Time to Crest (s) 1.5 1.75 2.0

    III. MODELING OF GIS COMTo model GIS components, lumped elemeparameters can be used, that is defined by

    wave velocity and lengths of GIS section.

    The surge arresters model recommended b

    (IEEE Working Group 3.4.11, 1992) is sho

    model the non-linear V-I characteristic is rep

    sections of non-linear resistances designate

    two non-linear resistances A0 and A1 are s

    filter. For currents discharge in arrester witthe influence of the filter is negligible; th

    essentially in parallel and characterize the

    the MOSA. For the fast rising of su

    impedance of the filter becomes more signi

    inductance L1 derives more current into the

    A0. Since A0 has a higher voltage for a givethe model generates a higher voltage b

    terminals, what matches the dynamic

    MOSAs. The inductance L0 represents

    associated with the magnetic fields in the i

    of the arrester. The resistor R0 is used tooscillations when running the model with

    The capacitance C0 represents the ext

    associated to the height of the arrester [8], [9

    Figure 1. The IEEE Frequency-Dependant

    Table.II shows the electrical equivalent circof GIS component [6]. Fig.2 shows the sing

    a 420 kV GIS. Characteristics of the trans

    and the electric power line and the ground

    the table.III and Fig.3.

    een 1 and 100

    d 5 microseconds.different from the

    of the lightning

    the apparatus

    e steepness of the

    ermined based on

    RATUS SPECIFICATION

    150 200

    2.25 2.5

    ONENTS

    ts and distributedurge impedances,

    IEEE W.G3.4.11

    n in Fig.1. In this

    resented with two

    d A0 and A1. The

    parated by a R-L

    slow rising time,s A0 and A1 are

    static behavior of

    ge currents, the

    ficant, indeed the

    non-linear branch

    n current than A1,etween its input

    characteristics of

    the inductance

    mmediate vicinity

    avoid numericaldigital program.

    rnal capacitance

    ], [10].

    Model [8]

    uits for mode lingle-line diagram of

    ission line tower

    ire are shown in

    Figure 2. Single-line d

    Figure 3. Transmissi

    TABLE I. ELECTRICAL

    Component

    GIS Bus Bar

    CB, DS, and Earthing Switch

    Potential Transformer (PT)

    Current Transformer (CT)

    Capacitive Voltage Transformer

    (CCVT)

    Bushing

    Power Transformer

    Arrester

    cable

    CT

    LA

    T1

    LA

    PT

    PT

    CT

    CT

    PT

    Transmi

    Ca

    iagram of a 420 kV GIS

    n Line and Substation

    QUIVALENT CIRCUIT[5],[6],[7]

    Notes

    z0 = 90 ohm

    v = 270 m/us

    In the closed position: impedance

    (42 ohm)

    In the open position: capacitance

    (4pF)

    300pF

    300pF

    5 nF

    100pF

    2 nF

    Discharge Voltage (10kA):870kV

    R0 = 0.0010679 ohm/m

    z0 = 30 ohmv = 165m/us

    CT

    LA

    LA

    CT

    T2

    PT

    PT

    sion Line

    ble

  • 7/28/2019 Lighting Voltage Supprestion in Gis

    3/5

    TABLE II. SPECIFICATION OF TRANS

    Conductor resistance at DC (with skin

    effect) ohm/km

    Power

    Ground

    Outer radius of one conductor

    Power

    Ground

    Inner radius of one conductor. Only

    available with skin effect

    Power

    Ground

    Vertical bundle height at tower PowerGround

    Vertical bundle height at mid-spanPower

    Ground

    Distance between conductors in a

    bundle

    Power

    Ground

    Angular position of one of the

    conductors in a bundle

    Power

    Ground

    Number of conductors in a bundlePower

    Ground

    The time step for simulation is 2.5 ns and

    100s. Computer simulation has been

    alternative transients program (ATP), a wide

    EMTP. For simulation of surge arrester c

    exponential current-dependent resistor

    ATP/EMTP.

    IV. EFFECT OF VARIOUS FACTDIRECT LIGHTNING S

    In this section, lightning overvoltages

    lightning that directly striking the transmissi

    is corresponding to the situation where

    opened and lightning is struck on the tower

    (Fig. 3). Also, in order to simulation

    condition, it is considered that lightning waphase A in tower No.2 and at the crest of

    Table.IV describes the lightning overvoltage

    intensity current at the power transformer,

    near the lightning struck.

    TABLE V. LIGHTNING OVERVOLT

    Peak Current

    (kA)

    Transformer

    (MV)

    Tower

    (kV)

    50 1.1221 67.17

    75 1.1401 101.19

    100 1.2841 142.98

    150 1.3573 208.61200 1.3635 274.96

    These factors are included effects of the

    arrester in the each feeder, system c

    decreasing of number of surge arrester and

    surge arrester and cable, terminal compon

    resistance of tower. The impact of various

    discussed above, were investigated undcurrent levels.

    ISSION LINE

    ine 0.069

    Wire 0.44

    ine 1.45cm

    Wire 0.77cm

    ine 0.7cm

    Wire 0.5cm

    ine 25.1mWire 39.7m

    ine 10.1m

    Wire 24.7m

    ine 60cm

    Wire 0cm

    ine 45deg

    Wire 0deg

    ine 4

    Wire 1

    alculating time is

    done using the

    ly used version of

    n be using ZnO-

    (TYPE 92) in

    ORS UNDER

    ROKE

    re simulated for

    on line. This part

    bus coupler was

    o.2 from the GIS

    under the worst

    s happened on thenegative polarity.

    s with the various

    T, PT and tower

    AGES

    CT

    (MV)

    PT

    (MV)

    1.1361 1.3044

    1.1584 1.3731

    1.3208 1.4442

    1.3544 1.56851.4049 1.6158

    number of surge

    onfiguration and

    costs, location of

    nt and grounding

    odeling details as

    r various stroke

    A.Effect of Number of SurgeThis part is corresponding towas opened and lightning stru

    the GIS (Fig. 3).The lightning

    six cases.

    Case(A-1): the arreste Case(A-2): the arr

    transformer feeder, Case (A-3) : original

    as Shown in Fig. 2

    Case (A-4): an extrtransformer feeder ba

    Case (A-5): an extrafeeder based on case (

    Case (A-6): an extrtransformer feeder a

    case (A-3).

    Fig.4 shows the effect of nu

    overvoltage at the power tran

    lightning stroke. Its clear that

    cause decreasing of the overvobserved that peak magnitude

    power transformer terminal

    current is fixed. Fig.5 shows cthe lightning overvoltage at t

    The observed overvoltage at

    can reach up much more than t

    when the arresters are disabl

    feeder. But disabled arresters

    than disabled arresters in thexistence of arrester at the i

    Fig.5, case (A-3) shows clearl

    transformer terminal is still v

    and can be up to 4.21 Pu. It isarrester installed, the lightnin

    transformer terminal is still hithe studied case. Hence, ins

    necessary for suppressing har

    Figure 4. Effects of number of surge

    transformer due to direct lightning stro

    the line feeder, case (A-2): the arrestercase (A-3): original arrester configura

    (A-4): an extra arrester is installed in t

    3), case (A-5: an extra arrester is insta3) and case (A-6) is that an extra arres

    and in the line feeder based on case (A

    Arrester

    he situation where bus couplerk on the tower No.2 away from

    overvoltages are investigated in

    rs are disabled in the line feeder

    sters are disabled in the

    arrester configuration is applied

    a arrester is installed in the

    ed on case (A-3),

    arrester is installed in the line

    A-3)

    a arrester is installed in the

    d in the line feeder based on

    mber of surge arrester on the

    sformer terminal due to direct

    existence of extra arrester can

    oltage. In the cases 4, 5, 6 areof overvoltage variation at the

    with increasing of lightning

    learly effect of extra arrester one power transformer terminal.

    he power transformer terminal

    he transformer BIL of 1230 kV,

    ed in the line and transformer

    in the line feeder can be worse

    transformer feeder. Howevercoming feeder is emphasized.

    y that the voltage at the power

    ery high because of reflection,

    orth noting, that even with theovervoltage seen at the power

    her than the transformer BIL inalling extra surge arresters is

    ful lightning overvoltages.

    rrester on the overvoltage at the power

    ke. Case (A-1): arresters are disabled in

    s are disabled in the transformer feeder,ion is applied as Shown in Fig. 2, case

    e transformer feeder based on case (A-

    led in the line feeder based on case (A-ter is installed in the transformer feeder

    -3).

  • 7/28/2019 Lighting Voltage Supprestion in Gis

    4/5

    Figure 5. Effects of extra arrester on the lightni

    B.Effect of System ConfigurationInstalling extra surge arresters is necessar

    harmful lightning overvoltages. But it is

    extra arresters near transformers due to spac

    site.

    In order to suppressing harmful lightning otransformer terminals, it can be used an

    installation of extra arresters. In this waycircuit breaker of bus coupler; on the other h

    associated with together and more tran

    connected to the substation. In this sectovervoltages are investigated in three cases.

    Case (B-1): the arresters are disfeeder and bus coupler is closed

    Case (B-2): the arresters aretransformer feeder and bus coupler

    Case (B-3): original arrester conand bus coupler is closed.

    Fig.6 shows effect of system configuration

    at the power transformer terminal when bus

    If bus coupler is closed, the lightnintransformer terminals can be reduced to a le

    in the studied case. Fig.7 compares effects onew configuration (bus coupler is closed

    associated with together). Its clear that c

    than case (A-4) and case (A-5). H

    configuration is better than even extra arrest

    With more transformers connected to tharresters must be also connected to the GI

    absorbing more lightning energy by the a

    cause to reduce the maximum overv

    transformer terminal.

    g overvoltage.

    for suppressing

    ifficult to install

    e limitation in the

    vervoltages at theapproach without

    ne can be closedand, all of feeders

    sformers can be

    ion the lightning

    abled in the line

    disabled in the

    is closed

    iguration applied

    nthe overvoltagecoupler is closed.

    overvoltage atel below the BIL

    extra arrester andor all of feeders

    se (B-3) is lower

    nce, appropriate

    r in the feeder.

    e network, more, it is helpful for

    rresters; hence, it

    oltages at each

    Figure 6. Effects of System Configutransformer terminal when bus couple

    disabled in the line feeder and bus co

    are disabled in the transformer feederoriginal arrester configuration is appl

    (A-3) is that original arrester configura

    Figure 7. Compares etween effect

    configuration (bus coupler is closed or

    C.Effect of Location of SurgeDue to absorbing more lightni

    negative reflection of cable,ef

    and cable is imported. This

    situation where bus coupler

    on the tower No.2 away fro

    arrester configuration is app

    lightning overvoltages are inve

    Case(C-1): the surgincoming cable

    Case(C-2): the surgeincoming cable.

    Case(C-3): the surgeincoming cable

    Case(C-4): the surgeincoming cable

    Case (C-5): the surincoming cable.

    Fig.8 shows effect of location

    the overvoltage at the powerwhen the surge arrester is pl

    lightning overvoltages are

    reflection.

    Figure 8. Effects of location of surge

    power transformer terminal. Case (C-

    incoming cable, Case (C-2): the surge

    ation on the overvoltage at the poweris closed. Case (B-1): the arresters are

    pler is closed, Case (B-2): the arresters

    and bus coupler is closed, Case (B-3):ed and bus coupler is closed and case

    tion applied as Shown in Fig.2.

    of extra arrester and effect of new

    all of feeders associated with together)

    Arrester and Cable

    ng energy by the arresters and

    fect of location of surge arrester

    ection is corresponding to the

    as opened and lightning struck

    m the GIS (Fig. 3). Original

    lied as shown in Fig.2. The

    stigated in five following cases.

    arrester situated in next of

    arrester situated in 3/4 after

    arrester situated in 2/4 after

    arrester situated in 1/4 after

    ge arrester situated in before

    of surge arrester and cable ontransformer terminal. Its clearced before of incoming cable,

    decreased due to negative

    rrester and cable onovervoltage at the): the surge arrester situated innext ofarrester situated in3/4 after incoming

  • 7/28/2019 Lighting Voltage Supprestion in Gis

    5/5

    cable Case (C-3): the surge arrester situated in2/4 afte(C-4): the surge arrester situated in1/4 after incomingsurge arrester situated inafter incoming cable.

    D.Effect of the Terminal ComponentThe peak magnitude of lightning overvolta

    terminals depends on the terminal compone

    GIS. The terminal component can be an

    overhead transmission line or a gas-insulate

    (GITL). To understand the effect of differe

    the peak magnitude of the lightning ovesubstation layouts have been considered and

    V. The attenuation of the lightning overv

    with time is found to depend on the switc

    and the terminal component connected to the

    Fig.9 shows variation in peak magnitudes

    overvoltages for various substation layouts.

    The attenuation rate is high if the GIS is teimpedance systems, such as XLPE cable, a

    rate is low if the GIS is terminated with hig

    elements such as an overhead line. Similar

    terminated with a long length of GITL, ther

    the transient currents for longer time durati

    be noted that effect of the cable is more effeovervoltage peak than adding more arresters.

    Figure 9. variation in peak magnitudes of the lightvarious substation layouts.

    TABLE V. VARIOUSSUBSTATIONLAYOUTSFOR

    Substation

    Layouts

    The Terminal Co

    D-1 Overhead Li

    D-2 GITL

    D-3 XLPE Cab

    D-4 Two XLPE Cable i

    IV. CONCLUSION

    Installing extra surge arresters isuppressing harmful lightning overv

    difficult to install extra arresters near t

    space limitation in the site.

    In order to suppressing harmful lightnithe transformer terminals, it can be

    without installation of extra arresters. I

    be closed circuit breaker of bus co

    incoming cable, Casecable, Case (C-5): the

    es at transformer

    t connected to the

    LPE cable or an

    transmission line

    t terminations on

    voltages, variousare listed in table

    oltages amplitude

    ing configuration

    GIS.

    of the lightning

    minated with lownd the attenuation

    surge impedance

    ly, if the GIS are

    is a possibility of

    on [11]. It should

    ctive to reduce the

    ning overvoltages for

    IFFERENTTERMINALS

    mponent

    ne

    le

    n Parallel

    necessary for

    ltages. But it is

    ansformers due to

    g overvoltages at

    sed an approach

    this way one can

    pler; With more

    transformers connected

    must be also connectedabsorbing more lightning

    it reduce to a level below

    When the surge arrestercable, lightning overvo

    negative reflection.

    It should be noted thateffective to reduce the

    more arresters. When

    impedance becomes sm

    overvoltage appearing a

    reduced dramatically due

    The attenuation rate is hilow impedance systems,

    attenuation rate is low if

    surge impedance eleme

    Similarly, if the GIS are t

    GITL, there is a possibil

    longer time duration.

    REFE

    [1] C.Y. Lui J. Hiley Computatiowith special reference to effecovervoltage amplitude IEEETr1994.

    [2] H. Elahi, M. Sublich, M.E.overvoltage protection of thesubstation, IEEE Transactions50, Jan. 1990.

    [3] A. Greenwood, Electrical TransYork: Wiley, 1991, pp. 548554.

    [4] Xuzhu Dong,Sebastian RosadoLine, Tzong-Yih Guo, "StudyEffects on GSU Transformers"vol. 18, NO. 3, JULY 2003

    [5] J. P. Bickford and A. G. Heatsystems, Proc. Inst. Elect. En1986.

    [6] Task Force on Very Fast Transifor very fast transients, IEEEpp.20282035, Oct. 1996.

    [7] Z. Haznadar, S.CarSimamoviModeling of Gas Insulated Substof Very Fast ElectromagneticDelivery, Vol. 7 No.1, January 1

    [8] IEEE working group 3.4.11, MIEEE Trans. Power Delivery, vol

    [9] F. Fernndez, R. Daz, Metatransient simulations paper 14system transients, IPST01, 20 -2

    [10] A. BAYADI1, N. HARID 2, K.of metal oxide surge arrester dThe international Conference onin New Orleans, USA

    [11] M. Mohana Rao, M. Joy TCharacteristics of Very Fast TraTransactions on Power Delivery,

    o the network, more arresters

    to the GIS, it is helpful forenergy by the arresters; hence,

    the BIL in the studied case.

    is placed before of incoming

    ltages are decreased due to

    effect of the cable is moreovervoltage peak than adding

    the equivalent cable surge

    aller, the peak value of the

    t the transformer terminals is

    to negative reflection.

    h if the GIS is terminated with

    such as XLPE cable, and the

    the GIS is terminated with high

    ts such as an overhead line.

    erminated with a long length of

    ity of the transient currents for

    ENCES

    al study of very fast transients in GISts of trapped charge and risetime onns. Distrib, Vol. 141, No. 5, September

    Anderson, B.D. Nelson, LightningPaddock 362-145 kV gas-insulated

    n Power Delivery, vol.5, no.1, pp.144-

    ients in Power Systems, 2nd ed. New

    , Yilu Liu,Nien-Chung Wang,E-Lenyof Abnormal Electrical Phenomena

    EEE Transactions on Power Delivery,

    n, Transients overvoltages on power., pt. C, vol. 133, pp. 201225, May

    nts, Modeling and analysis guidelinesTrans. Power Delivery, vol. 11, no. 4,

    , R. Mahmutkehajif ,"More Accurateation Component in Digital Simulations

    Transients" Transactions on Power92.

    odeling of metal oxide surge arresters,. 7, pp. 302309, Jan. 1992.

    l-oxide surge arrester model for fast4, International conference on power4 June 2001.

    EHAR 1, S. BELKHIAT, Simulationnamic behavior under fast transientsPower Systems Transients - IPST 2003

    omas, and B. P. Singh Frequencysient Currents in a 245-kV GIS IEEEvol. 20, NO. 4, OCTOBER 2005.