8/13/2019 Line Sizing (Liquid)
1/22
Calculation number
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_2\[208857486.xls.ms_office.xls]new
Line number 01-210-0-CO-010-8"-BC210-E38
Line destination Crude Oil Outlet of 1st Stage Separator
SIZE CASE 4 6 8 10 12
PIPE DATA Nom.size (inches) 4 6 8 10 12
PIPE RATING # 300 300 300 300 300
PIPE SCH NO. 40 40 40 40 40
PIPE INTERNAL DIA in 4.026 6.066 7.982 10.022 11.94
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 8.50 8.50 8.50 8.50 8.50
psia 123.25 123.25 123.25 123.25 123.25
TEMPERATURE deg C 60.0 60.0 60.00 60.00 60.00
deg F 140.00 140.00 140.00 140.00 140.00deg R 600.00 600.00 600.00 600.00 600.00
LIQUID FLOWRATE m3/hr 264.971 264.971 264.971 264.971 264.971
bpd 40000.00 40000.00 40000.00 40000.00 40000.00
LIQUID VISCOCITY cP 5.580 5.580 5.580 5.580 5.580
LIQUID DENSITY kg/m3 833.00 833.00 833.00 833.00 833.00
lb/ft3 51.98 51.98 51.98 51.98 51.98
CALCULATION
NRe (Reynold Number) 137716.05 91402.04 69461.89 55322.77 46435.91
Relative Roughness 4.76900E-04 3.17E-04 2.41E-04 1.92E-04 1.61E-04
A (Fric. Factor Constant) 7.88E+20 6.95E+20 5.53E+20 4.26E+20 3.36E+20
B (Fric. Factor Constant) 9.2535E-10 6.5277E-07 5.2737E-05 2.0118E-03 3.3143E-02
Moody Friction Factor 0.01955 0.01986 0.02044 0.02111 0.02175
RESULT
LIQUID VELOCITY m/s 9.032 3.979 2.298 1.458 1.027
ft/s 29.614 13.045 7.534 4.779 3.367
psi/100ft 28.33 3.71 0.97 0.32 1.37E-01
kPa/100m 640.999 83.856 21.874 7.242 3.108
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100m
SELECTION CRITERION
NOTE
1 Flowrate based on design capacity of oil production (40000blpd).
EXCO-00 29/10/2008 FO AJ HHRev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
ISSUED AS FINALDescription
8/13/2019 Line Sizing (Liquid)
2/22
Calculation number
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1002
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_ 2\[208857486.xls.ms_office.xls]newLine number 01-210-0-CO-012-12"-AC210-E38
Line destination Crude Oil to Booster Pump
SIZE CASE 6 8 10 12
PIPE DATA Nom.size (inches) 6 8 10 12
PIPE RATING # 150 150 150 150
PIPE SCH NO. 40 40 40 40
PIPE INTERNAL DIA in 6.066 7.982 10.022 11.940
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 1.21 1.21 1.21 1.21
psia 17.55 17.55 17.55 17.55
TEMPERATURE deg C 65.00 65.00 65.00 65.00
deg F 149.00 149.00 149.00 149.00deg R 609.00 609.00 609.00 609.00
LIQUID FLOWRATE m3/hr 322.100 322.100 322.100 322.100
bpd 48624.22 48624.22 48624.22 48624.22
LIQUID VISCOCITY cP 4.434 4.434 4.434 4.434
LIQUID DENSITY kg/m3 821.79 821.79 821.79 821.79
lb/ft3 51.28 51.28 51.28 51.28
CALCULATION
NRe (Reynold Number) 137944.53 104832.31 83493.46 70081.37
Relative Roughness 3.16518E-04 2.41E-04 1.92E-04 1.61E-04
A (Fric. Factor Constant) 1.11E+21 9.60E+20 7.84E+20 6.44E+20
B (Fric. Factor Constant) 9.0113E-10 7.2801E-08 2.7773E-06 4.5753E-05
Moody Friction Factor 0.01873 0.01907 0.01956 0.02005
RESULT
LIQUID VELOCITY m/s 4.836 2.793 1.772 1.248
ft/s 15.857 9.158 5.809 4.093
psi/100ft 5.09 1.32 0.43 0.18
kPa/100m 115.274 29.761 9.782 4.177
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100m
SELECTION CRITERION
NOTE
1 Flowrate based on crude booster pump's capacity of 322.10m3/hr.
EXCO-00 29/10/2008 FO AJ HH
Rev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
ISSUED AS FINAL
Description
8/13/2019 Line Sizing (Liquid)
3/22
Calculation number
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_ 2\[208857486.xls.ms_office.xls]newLine number 01-210-0-CO-014-8"-AC210-E38
Line destination Crude Oil to Electrostatic Coalescer
SIZE CASE 4 5 6 8
PIPE DATA Nom.size (inches) 4 5 6 8
PIPE RATING # 150 150 150 150
PIPE SCH NO. 40 40 40 40
PIPE INTERNAL DIA in 4.026 5.047 6.066 7.982
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 4.50 4.50 4.50 4.50
psia 65.25 65.25 65.25 65.25
TEMPERATURE deg C 65.00 65.00 65.00 65.00
deg F 149.00 149.00 149.00 149.00deg R 609.00 609.00 609.00 609.00
LIQUID FLOWRATE m3/hr 322.100 322.100 322.100 322.100
bpd 48624.22 48624.22 48624.22 48624.22
LIQUID VISCOCITY cP 4.434 4.434 4.434 4.434
LIQUID DENSITY kg/m3 822.16 822.16 822.16 822.16
lb/ft3 51.30 51.30 51.30 51.30
CALCULATION
NRe (Reynold Number) 207935.73 165870.67 138006.80 104879.64
Relative Roughness 4.76900E-04 3.80E-04 3.17E-04 2.41E-04
A (Fric. Factor Constant) 1.10E+21 1.15E+21 1.11E+21 9.61E+20
B (Fric. Factor Constant) 1.2682E-12 4.7178E-11 8.9464E-10 7.2277E-08
Moody Friction Factor 0.01875 0.01865 0.01872 0.01907
RESULT
LIQUID VELOCITY m/s 10.980 6.987 4.836 2.793
ft/s 35.999 22.907 15.857 9.158
psi/100ft 39.63 12.73 5.10 1.32
kPa/100m 896.641 288.129 115.320 29.773
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100m
SELECTION CRITERION
NOTE
1 Flowrate based on crude booster pump's capacity of 322.10m3/hr.
EXCO-00 29/10/2008 FO AJ HH
Rev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
ISSUED AS FINAL
Description
8/13/2019 Line Sizing (Liquid)
4/22
Calculation number
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_2\[208857486.xls.ms_office.xls]newLine number 01-210-0-CO-017-8"-AC210-E38
Line destination Oil to Coolers
SIZE CASE 4 5 6 8
PIPE DATA Nom.size (inches) 4 5 6 8
PIPE RATING # 150 150 150 150
PIPE SCH NO. 40 40 40 40
PIPE INTERNAL DIA in 4.026 5.047 6.066 7.982
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 4.51 4.51 4.51 4.51
psia 65.40 65.40 65.40 65.40
TEMPERATURE deg C 64.28 64.28 64.28 64.28
deg F 147.70 147.70 147.70 147.70deg R 607.70 607.70 607.70 607.70
LIQUID FLOWRATE m3/hr 264.971 100.000 100.000 100.000
bpd 40000.00 40000.00 40000.00 40000.00
LIQUID VISCOCITY cP 3.744 3.744 3.744 3.744
LIQUID DENSITY kg/m3 814.49 814.49 814.49 814.49
lb/ft3 50.82 50.82 50.82 50.82
CALCULATION
NRe (Reynold Number) 200689.04 160089.97 133197.18 101224.52
Relative Roughness 4.76900E-04 3.80E-04 3.17E-04 2.41E-04
A (Fric. Factor Constant) 1.07E+21 1.11E+21 1.07E+21 9.18E+20
B (Fric. Factor Constant) 2.2371E-12 8.3221E-11 1.5781E-09 1.2749E-07
Moody Friction Factor 0.01881 0.01873 0.01881 0.01918
RESULT
LIQUID VELOCITY m/s 9.032 5.747 3.979 2.298
ft/s 29.614 18.844 13.045 7.534
psi/100ft 26.65 8.57 3.43 0.89
kPa/100m 603.071 193.948 77.676 20.072
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100m
SELECTION CRITERION
NOTE
1 Flowrate based on design capacity of oil production (40000blpd).
EXCO-00 29/10/2008 FO AJ HH
Rev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
ISSUED AS FINAL
Description
8/13/2019 Line Sizing (Liquid)
5/22
Calculation number
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_2\[208857486.xls.ms_office.xls]newLine number 01-210-0-CO-029-8"-AC210-E38
Line destination Oil to Storage
SIZE CASE 4 5 6 8
PIPE DATA Nom.size (inches) 4 5 6 8
PIPE RATING # 150 150 150 150
PIPE SCH NO. 40 40 40 40
PIPE INTERNAL DIA in 4.026 5.047 6.066 7.982
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 2.00 2.00 2.00 2.00
psia 29.00 29.00 29.00 29.00
TEMPERATURE deg C 45.00 45.00 45.00 45.00
deg F 113.00 113.00 113.00 113.00deg R 573.00 573.00 573.00 573.00
LIQUID FLOWRATE m3/hr 264.971 155.698 155.698 155.698
bpd 40000.00 40000.00 40000.00 40000.00
LIQUID VISCOCITY cP 5.427 5.427 5.427 5.427
LIQUID DENSITY kg/m3 828.53 828.53 828.53 828.53
lb/ft3 51.70 51.70 51.70 51.70
CALCULATION
NRe (Reynold Number) 140837.90 112346.62 93474.02 71036.50
Relative Roughness 4.76900E-04 3.80E-04 3.17E-04 2.41E-04
A (Fric. Factor Constant) 8.04E+20 7.80E+20 7.14E+20 5.71E+20
B (Fric. Factor Constant) 6.4646E-10 2.4049E-08 4.5604E-07 3.6843E-05
Moody Friction Factor 0.01950 0.01957 0.01979 0.02035
RESULT
LIQUID VELOCITY m/s 9.032 5.747 3.979 2.298
ft/s 29.614 18.844 13.045 7.534
psi/100ft 28.11 9.11 3.67 0.96
kPa/100m 635.959 206.199 83.120 21.670
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100m
SELECTION CRITERION
NOTE
1 Flowrate based on design capacity of oil production (40000blpd).
EXCO-00 29/10/2008 FO AJ HH
Rev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
ISSUED AS FINAL
Description
8/13/2019 Line Sizing (Liquid)
6/22
Calculation number
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_2\[208857486.xls.ms_office.xls]new
Line number 01-555-0-PW-021-4"-AC210-V
Line destination Produced Water Outlet from Flotation Cell
SIZE CASE 3 4 5 6 8 10
PIPE DATA Nom.size (inches) 3 4 5 6 8 10
PIPE RATING # 150 150 150 150 150 150
PIPE SCH NO. 40 40 40 40 40 40
PIPE INTERNAL DIA in 3.068 4.026 5.046 6.066 7.982 10.022
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 3.00 3.00 3.00 3.00 3.00 3.00
psia 43.50 43.50 43.50 43.50 43.50 43.50
TEMPERATURE deg C 65.0 65.0 65.00 65.00 65.00 65.00
deg F 149.00 149.00 149.00 149.00 149.00 149.00deg R 609.00 609.00 609.00 609.00 609.00 609.00
LIQUID FLOWRATE m3/hr 59.618 59.618 59.618 59.618 59.618 59.618
bpd 9000.00 9000.00 9000.00 9000.00 9000.00 9000.00
LIQUID VISCOCITY cP 0.440 0.440 0.440 0.440 0.440 0.440
LIQUID DENSITY kg/m3 978.30 978.30 978.30 978.30 978.30 978.30
lb/ft3 61.05 61.05 61.05 61.05 61.05 61.05
CALCULATION
NRe (Reynold Number) 605611.41 461504.18 368215.58 306300.00 232775.72 185393.72
Relative Roughness 6.25815E-04 4.77E-04 3.80E-04 3.17E-04 2.41E-04 1.92E-04
A (Fric. Factor Constant) 1.29E+21 1.74E+21 2.07E+21 2.25E+21 2.30E+21 2.14E+21
B (Fric. Factor Constant) 4.7310E-20 3.6580E-18 1.3565E-16 2.5805E-15 2.0848E-13 7.9531E-12
Moody Friction Factor 0.01838 0.01771 0.01733 0.01715 0.01710 0.01726
RESULT
LIQUID VELOCITY m/s 3.500 2.032 1.294 0.895 0.517 0.328
ft/s 11.474 6.663 4.242 2.935 1.695 1.075
psi/100ft 6.16 1.53 0.48 0.19 4.81E-02 1.56E-02
kPa/100m 139.421 34.520 10.923 4.306 1.088 0.352
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15 3 - 15 4 - 15
m/s
Pressure drop psi/100ft
kpa/100m
SELECTION CRITERION
Fraude Number 4.003 2.029 1.154 0.728 0.367 0.208
NOTE
1 Flowrate based on design flowrate of produced water which is 9000blpd.
EXCO-00 29/10/2008 FO AJ HH
Rev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
ISSUED AS FINAL
Description
8/13/2019 Line Sizing (Liquid)
7/22
Calculation number
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_2\[208857486.xls.ms_office.xls]new
Line number 01-590-0-CW-003-8"-AN140-N
Line destination Cooling Water Discharge from Crude Coolers
SIZE CASE 8 10 12 14 16 18
PIPE DATA Nom.size (inches) 8 10 12 14 16 18
PIPE RATING # 300 300 300 300 300 300
PIPE SCH NO. 40 40 40 40 40 40
PIPE INTERNAL DIA in 7.982 10.022 11.940 13.124 15.2496 16.8687
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 4.70 4.70 4.70 4.70 4.70 4.70
psia 68.15 68.15 68.15 68.15 68.15 14.69
TEMPERATURE deg C 45.0 45.0 45.00 45.00 45.00 45.00
deg F 113.00 113.00 113.00 113.00 113.00 113.00deg R 573.00 573.00 573.00 573.00 573.00 573.00
LIQUID FLOWRATE m3/hr 262.200 262.200 262.200 262.200 262.200 262.200
bpd 39581.71 39581.71 39581.71 39581.71 39581.71 39581.71
LIQUID VISCOCITY cP 1.000 1.000 1.000 1.000 1.000 1.000
LIQUID DENSITY kg/m3 1030.00 1030.00 1030.00 1030.00 1030.00 1030.00
lb/ft3 64.27 64.27 64.27 64.27 64.27 64.27
CALCULATION
NRe (Reynold Number) 474256.22 377715.60 317038.03 288447.21 248233.77 224407.67
Relative Roughness 2.40544E-04 1.92E-04 1.61E-04 1.46E-04 1.26E-04 1.14E-04
A (Fric. Factor Constant) 4.02E+21 4.22E+21 4.14E+21 4.02E+21 3.74E+21 3.50E+21
B (Fric. Factor Constant) 2.3651E-18 9.0244E-17 1.4869E-15 6.7452E-15 7.4522E-14 3.7450E-13
Moody Friction Factor 0.01595 0.01585 0.01589 0.01595 0.01609 0.01623
RESULT
LIQUID VELOCITY m/s 2.274 1.442 1.016 0.841 0.623 0.509
ft/s 7.455 4.729 3.332 2.758 2.042 1.669
psi/100ft 0.91 0.29 0.12 0.08 3.62E-02 2.20E-02
kPa/100m 20.671 6.584 2.749 1.720 0.819 0.499
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100m
SELECTION CRITERION
Fraude Number 1.612 0.913 0.589 0.465 0.320 0.248
NOTE
1 Flowrate based on design flowrate of produced water which is 9000blpd.
EXCO-00 29/10/2008 FO AJ HH
Rev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
ISSUED AS FINAL
Description
8/13/2019 Line Sizing (Liquid)
8/22
Calculation number
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_2\[208857486.xls.ms_office.xls]new
Line number 01-130-0-TW-046-6"-FC200-V
Line destination Water Injection Line From Water Injection Pump Discharge
SIZE CASE 6 8 10 12 14 16
PIPE DATA Nom.size (inches) 6 8 10 12 14 16
PIPE RATING # 2500 2500 2500 2500 2500 2500
PIPE SCH NO. 40 40 40 40 40 40
PIPE INTERNAL DIA in 6.066 7.982 10.022 11.940 13.124 15.2496
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 210.00 210.00 210.00 210.00 210.00 210.00
psia 3045.00 3045.00 3045.00 3045.00 3045.00 14.69
TEMPERATURE deg C 30.0 30.0 30.00 30.00 30.00 30.00
deg F 86.00 86.00 86.00 86.00 86.00 86.00deg R 546.00 546.00 546.00 546.00 546.00 546.00
LIQUID FLOWRATE m3/hr 99.364 99.364 99.364 99.364 99.364 99.364
bpd 15000.00 15000.00 15000.00 15000.00 15000.00 15000.00
LIQUID VISCOCITY cP 1.000 1.000 1.000 1.000 1.000 1.000
LIQUID DENSITY kg/m3 1030.00 1030.00 1030.00 1030.00 1030.00 1030.00
lb/ft3 64.27 64.27 64.27 64.27 64.27 64.27
CALCULATION
NRe (Reynold Number) 236490.45 179723.26 143140.20 120146.65 109307.46 94071.39
Relative Roughness 3.16518E-04 2.41E-04 1.92E-04 1.61E-04 1.46E-04 1.26E-04
A (Fric. Factor Constant) 1.84E+21 1.78E+21 1.59E+21 1.38E+21 1.26E+21 1.07E+21
B (Fric. Factor Constant) 1.6182E-13 1.3073E-11 4.9874E-10 8.2162E-09 3.7296E-08 4.1185E-07
Moody Friction Factor 0.01758 0.01765 0.01791 0.01823 0.01844 0.01882
RESULT
LIQUID VELOCITY m/s 1.492 0.862 0.547 0.385 0.319 0.236
ft/s 4.892 2.825 1.792 1.263 1.045 0.774
psi/100ft 0.57 0.15 0.05 0.02 1.26E-02 6.08E-03
kPa/100m 12.909 3.286 1.068 0.453 0.286 0.138
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100m
SELECTION CRITERION
Fraude Number 1.214 0.611 0.346 0.223 0.176 0.121
NOTE
1 Flowrate based on design flowrate of water injection system.
EXCO-00 29/10/2008 FO AJ HH
Rev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
ISSUED AS FINAL
Description
8/13/2019 Line Sizing (Liquid)
9/22
Calculation number
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_2\[208857486.xls.ms_office.xls]newLine number 01-210-0-CO-026-6"-BC210-V
Line destination Oil from Test Separator
SIZE CASE 3 4 5 6 8
PIPE DATA Nom.size (inches) 3 4 5 6 8
PIPE RATING # 300 300 300 300 300
PIPE SCH NO. 40 40 40 40 40
PIPE INTERNAL DIA in 3.068 4.026 5.047 6.066 7.982
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 8.50 8.50 8.50 8.50 8.50
psia 123.25 123.25 123.25 123.25 123.25
TEMPERATURE deg C 60.0 60.0 60.00 60.00 60.00
deg F 140.00 140.00 140.00 140.00 140.00deg R 600.00 600.00 600.00 600.00 600.00
LIQUID FLOWRATE m3/hr 99.364 99.364 99.364 99.364 99.364
bpd 15000.00 15000.00 15000.00 15000.00 15000.00
LIQUID VISCOCITY cP 5.580 5.580 5.580 5.580 5.580
LIQUID DENSITY kg/m3 833.00 833.00 833.00 833.00 833.00
lb/ft3 51.98 51.98 51.98 51.98 51.98
CALCULATION
NRe (Reynold Number) 67769.49 51643.52 41196.12 34275.77 26048.21
Relative Roughness 6.25815E-04 4.77E-04 3.80E-04 3.17E-04 2.41E-04
A (Fric. Factor Constant) 3.03E+20 2.62E+20 2.12E+20 1.70E+20 1.14E+20
B (Fric. Factor Constant) 7.8255E-05 6.0507E-03 2.2509E-01 4.2684E+00 3.4483E+02
Moody Friction Factor 0.02203 0.02244 0.02303 0.02368 0.02488
RESULT
LIQUID VELOCITY m/s 5.833 3.387 2.155 1.492 0.862
ft/s 19.123 11.105 7.067 4.892 2.825
psi/100ft 17.47 4.57 1.52 0.62 1.66E-01
kPa/100m 395.223 103.451 34.304 14.060 3.745
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100m
SELECTION CRITERION
NOTE
1 Flowrate based on oil f lowrate of 15000blpd.
EXCO-00 29/10/2008 FO AJ HH
Rev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
ISSUED AS FINAL
Description
8/13/2019 Line Sizing (Liquid)
10/22
8/13/2019 Line Sizing (Liquid)
11/22
8/13/2019 Line Sizing (Liquid)
12/22
8/13/2019 Line Sizing (Liquid)
13/22
8/13/2019 Line Sizing (Liquid)
14/22
Calculation number
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_2\[208857486.xls.ms_office.xls]newLine number 01-210-0-CO-060-4"-AC210-V
Line destination Condensate return to 2nd Stage Separator (Header)
SIZE CASE 2 3 4 6 8
PIPE DATA Nom.size (inches) 2 3 4 6 8
PIPE RATING # 150 150 150 300 300
PIPE SCH NO. 40 40 40 40 40
PIPE INTERNAL DIA in 2.066 3.068 4.026 6.066 7.982
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 8.30 8.30 8.30 8.30 8.30
psia 120.35 120.35 120.35 120.35 120.35
TEMPERATURE deg C 44.8 44.8 44.81 44.81 44.81
deg F 112.66 112.66 112.66 112.66 112.66deg R 572.66 572.66 572.66 572.66 572.66
LIQUID FLOWRATE (Note 1) m3/hr 1.600 1.600 1.600 0.500 0.500
bpd 241.54 241.54 241.54 241.54 241.54
LIQUID VISCOCITY cP 0.596 0.596 0.596 0.596 0.596
LIQUID DENSITY kg/m3 837.80 837.80 837.80 837.80 837.80
lb/ft3 52.28 52.28 52.28 52.28 52.28
CALCULATION
NRe (Reynold Number) 15261.81 10277.35 7831.82 5197.97 3950.25
Relative Roughness 9.29332E-04 6.26E-04 4.77E-04 3.17E-04 2.41E-04
A (Fric. Factor Constant) 2.86E+19 1.58E+19 9.54E+18 3.98E+18 2.09E+18
B (Fric. Factor Constant) 1.7880E+06 9.9991E+08 7.7314E+10 5.4540E+13 4.4062E+15
Moody Friction Factor 0.02959 0.03186 0.03394 0.03786 0.04103
RESULT
LIQUID VELOCITY m/s 0.207 0.094 0.055 0.024 0.014
ft/s 0.679 0.308 0.179 0.079 0.045
psi/100ft 0.04 0.01 0.00 0.00 7.12E-05
kPa/100m 1.000 0.149 0.041 0.006 0.002
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100mSELECTION CRITERION
NOTE
1 Flowrate is based on 'Line Sizing Calculation' document 08055E-801-FI-02 and Hysys simulation Design Case
EXCO-00 29/10/2008 FO AJ HH
Rev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
ISSUED AS FINAL
Description
8/13/2019 Line Sizing (Liquid)
15/22
Calculation number BAE 00 C0701-EC-PR003
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_2\[208857486.xls.ms_office.xls]newLine number 01-210-0-CO-059-3"-BC210-V
Line destination Condensate return to 1st Stage Separator (Header)
SIZE CASE 2 3 4 6 8
PIPE DATA Nom.size (inches) 2 3 4 6 8
PIPE RATING # 300 300 300 300 300
PIPE SCH NO. 40 40 40 40 40
PIPE INTERNAL DIA in 2.066 3.068 4.026 6.066 7.982
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 122.69 122.69 122.69 122.69 122.69
psia 1779.01 1779.01 1779.01 1779.01 1779.01
TEMPERATURE deg C 49.8 49.8 49.80 49.80 49.80
deg F 121.64 121.64 121.64 121.64 121.64deg R 581.64 581.64 581.64 581.64 581.64
LIQUID FLOWRATE (Note 1) m3/hr 5.600 5.600 5.600 1.820 1.820
bpd 845.38 845.38 845.38 845.38 845.38
LIQUID VISCOCITY cP 6.324 6.324 6.324 6.324 6.324
LIQUID DENSITY kg/m3 421.60 421.60 421.60 421.60 421.60
lb/ft3 26.31 26.31 26.31 26.31 26.31
CALCULATION
NRe (Reynold Number) 2532.89 1705.65 1299.79 862.67 655.59
Relative Roughness 9.29332E-04 6.26E-04 4.77E-04 3.17E-04 2.41E-04
A (Fric. Factor Constant) 5.93E+17 2.10E+17 9.59E+16 2.66E+16 1.05E+16
B (Fric. Factor Constant) 5.3976E+18 3.0186E+21 2.3340E+23 1.6465E+26 1.3302E+28
Moody Friction Factor 0.03602 0.03753 0.04925 0.07420 0.09764
RESULT
LIQUID VELOCITY m/s 0.725 0.329 0.191 0.084 0.049
ft/s 2.377 1.078 0.626 0.276 0.159
psi/100ft 0.33 0.05 0.02 0.00 1.04E-03
kPa/100m 7.502 1.083 0.365 0.071 0.024
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100mSELECTION CRITERION
NOTE
1 Flowrate is based on 'Line Sizing Calculation' document 08055E-801-FI-02 and Hysys simulation Design Case.
EXCO-00 29/10/2008 FO AJ HH
Rev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
ISSUED AS FINAL
Description
8/13/2019 Line Sizing (Liquid)
16/22
Calculation number BAE 00 C0701-EC-PR003
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_2\[208857486.xls.ms_office.xls]new
Line number 01-555-0-CO-101-2"-AC210-E25
Line destination Oil Return from Flotation Cell
SIZE CASE 1 2 3 4
PIPE DATA Nom.size (inches) 1 2 3 4
PIPE RATING # 150 150 150 150
PIPE SCH NO. 40 40 40 40
PIPE INTERNAL DIA in 1.049 2.066 3.068 4.026
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 3.00 3.00 3.00 3.00
psia 43.50 43.50 43.50 43.50
TEMPERATURE deg C 65.00 65.00 65.00 65.00
deg F 149.00 149.00 149.00 149.00deg R 609.00 609.00 609.00 609.00
LIQUID FLOWRATE (Note 1)m3/hr 3.000 3.000 3.000 3.000
bpd 452.88 452.88 452.88 452.88
LIQUID VISCOCITY cP 4.434 4.434 4.434 4.434
LIQUID DENSITY kg/m3 822.16 822.16 822.16 822.16
lb/ft3 51.30 51.30 51.30 51.30
CALCULATION
NRe (Reynold Number) 7432.89 3774.01 2541.43 1936.69
Relative Roughness 1.83031E-03 9.29E-04 6.26E-04 4.77E-04
A (Fric. Factor Constant) 5.52E+18 1.61E+18 6.28E+17 3.06E+17
B (Fric. Factor Constant) 1.7846E+11 9.1455E+15 5.1146E+18 3.9546E+20
Moody Friction Factor 0.03635 0.04237 0.03620 0.03307
RESULT
LIQUID VELOCITY m/s 1.506 0.388 0.176 0.102
ft/s 4.939 1.273 0.577 0.335
psi/100ft 5.55 0.22 0.03 0.01
kPa/100m 125.564 4.939 0.584 0.137
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100m
SELECTION CRITERION
NOTE
1 Oil outlet from the flotation cell is based on 5% of total flowrate into the flotation cell which is at 60m3/hr.
EXCO-00 29/10/2008 FO AJ HH
Rev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
Issued for design
Description
8/13/2019 Line Sizing (Liquid)
17/22
Calculation number BAE 00 C0701-EC-PR003
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_2\[208857486.xls.ms_office.xls]new
Line number
Line destination Oil from Test Separator
SIZE CASE 8 3 6 4 5
PIPE DATA Nom.size (inches) 8 3 6 4 5
PIPE RATING # 300 300 300 300 300
PIPE SCH NO. 40 40 40 40 40
PIPE INTERNAL DIA in 7.982 3.068 6.066 4.026 5.047
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 8.50 8.50 8.50 8.50 8.50
psia 123.25 123.25 123.25 123.25 123.25
TEMPERATURE deg C 60.0 60.0 60.00 60.00 60.00
deg F 140.00 140.00 140.00 140.00 140.00
deg R 600.00 600.00 600.00 600.00 600.00LIQUID FLOWRATE (Note 1) m3/hr 99.364 53.000 53.000 53.000 53.000
bpd 15000.00 15000.00 15000.00 15000.00 15000.00
LIQUID VISCOCITY cP 4.581 4.581 4.581 4.581 4.581
LIQUID DENSITY kg/m3 823.27 823.27 823.27 823.27 823.27
lb/ft3 51.37 51.37 51.37 51.37 51.37
CALCULATION
NRe (Reynold Number) 31358.33 81583.68 41261.60 62170.82 49593.57
Relative Roughness 2.40545E-04 6.26E-04 3.17E-04 4.77E-04 3.80E-04
A (Fric. Factor Constant) 1.58E+20 3.71E+20 2.29E+20 3.34E+20 2.79E+20
B (Fric. Factor Constant) 1.7718E+01 4.0216E-06 2.1944E-01 3.1094E-04 1.1568E-02
Moody Friction Factor 0.02389 0.02148 0.02282 0.02177 0.02226
RESULT
LIQUID VELOCITY m/s 0.862 5.833 1.492 3.387 2.155
ft/s 2.825 19.123 4.892 11.105 7.067
psi/100ft 0.16 16.84 0.59 4.38 1.45E+00
kPa/100m 3.555 380.956 13.389 99.194 32.764
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100m
SELECTION CRITERION
NOTE
Rev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
Description
8/13/2019 Line Sizing (Liquid)
18/22
Calculation number BAE 00 C0701-EC-PR003
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_2\[208857486.xls.ms_office.xls]new
Line number 01-500-0-SW-508-14"-AN140-V
Line destination SW LIFT PUMP LINE
SIZE CASE 12 14 8 10 12
PIPE DATA Nom.size (inches) 12 14 8 10 12
PIPE RATING # 300 300 300 300 300
PIPE SCH NO. 40 40 40 40 40
PIPE INTERNAL DIA in 12.350 13.290 7.982 10.022 11.94
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 7.70 7.70 7.70 7.70 7.70
psia 111.65 111.65 111.65 111.65 111.65
TEMPERATURE deg C 30.0 30.0 30.00 30.00 30.00
deg F 86.00 86.00 86.00 86.00 86.00deg R 546.00 546.00 546.00 546.00 546.00
LIQUID FLOWRATE m3/hr 800.000 800.000 264.971 264.971 264.971
bpd 120768.00 120768.00 120768.00 120768.00 120768.00
LIQUID VISCOCITY cP 1.000 1.000 1.000 1.000 1.000
LIQUID DENSITY kg/m3 1030.00 1030.00 1030.00 1030.00 1030.00
lb/ft3 64.27 64.27 64.27 64.27 64.27
CALCULATION
NRe (Reynold Number) 935211.12 869063.76 1446987.89 1152450.34 967324.73
Relative Roughness 1.55466E-04 1.44E-04 2.41E-04 1.92E-04 1.61E-04
A (Fric. Factor Constant) 9.50E+21 9.82E+21 6.74E+21 8.30E+21 9.33E+21
B (Fric. Factor Constant) 4.5238E-23 1.4630E-22 4.1939E-26 1.5999E-24 2.6357E-23
Moody Friction Factor 0.01432 0.01426 0.01495 0.01456 0.01435
RESULT
LIQUID VELOCITY m/s 2.898 2.503 6.938 4.401 3.100
ft/s 9.502 8.205 22.746 14.429 10.165
psi/100ft 0.86 0.59 7.97 2.49 1.02E+00
kPa/100m 19.486 13.447 180.367 56.311 23.120
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100m
SELECTION CRITERION
NOTE
1 Flowrate based on operating flowrate from the seawater lift pump.
EXCO-00 29/10/2008 FO AJ HHRev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
Issued for designDescription
8/13/2019 Line Sizing (Liquid)
19/22
Calculation number BAE 00 C0701-EC-PR003
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_2\[208857486.xls.ms_office.xls]new
Line number
Line destination Condensate return to 2nd Stage Separator from HP Compressor
SIZE CASE 2 3 4 6 8
PIPE DATA Nom.size (inches) 2 3 4 6 8
PIPE RATING # 300 300 300 300 300
PIPE SCH NO. 40 40 40 40 40
PIPE INTERNAL DIA in 2.066 3.068 4.026 6.066 7.982
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 8.30 8.30 8.30 8.30 8.30
psia 120.35 120.35 120.35 120.35 120.35
TEMPERATURE deg C 44.8 44.8 44.81 44.81 44.81
deg F 112.66 112.66 112.66 112.66 112.66deg R 572.66 572.66 572.66 572.66 572.66
LIQUID FLOWRATE (Note 1) m3/hr 0.500 0.500 0.500 0.500 0.500
bpd 75.48 75.48 75.48 75.48 75.48
LIQUID VISCOCITY cP 0.596 0.596 0.596 0.596 0.596
LIQUID DENSITY kg/m3 837.80 837.80 837.80 837.80 837.80
lb/ft3 52.28 52.28 52.28 52.28 52.28
CALCULATION
NRe (Reynold Number) 4769.32 3211.67 2447.44 1624.37 1234.45
Relative Roughness 9.29332E-04 6.26E-04 4.77E-04 3.17E-04 2.41E-04
A (Fric. Factor Constant) 2.79E+18 1.15E+18 5.81E+17 1.89E+17 8.38E+16
B (Fric. Factor Constant) 2.1615E+14 1.2088E+17 9.3466E+18 6.5935E+21 5.3268E+23
Moody Friction Factor 0.03959 0.04367 0.03390 0.03941 0.05186
RESULT
LIQUID VELOCITY m/s 0.065 0.029 0.017 0.008 0.004
ft/s 0.212 0.096 0.056 0.025 0.014
psi/100ft 0.01 0.00 0.00 0.00 8.78E-06
kPa/100m 0.131 0.020 0.004 0.001 0.000
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100m
SELECTION CRITERION
NOTE
1 Flowrate is based on 'Line Sizing Calculation' document 08055E-801-FI-02
EXCO-00 29/10/2008 FO AJ HH
Rev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
Issued for design
Description
8/13/2019 Line Sizing (Liquid)
20/22
Calculation number BAE 00 C0701-EC-PR003
DESCRIPTION
Project OYO FIELD DEVELOP MENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_2\[208857486.xls.ms_office.xls]new
Line number 01-210-0-CO-059-3"-BC210-V
Line destination Condensate return to 1st Stage Separator from HP Compressor
SIZE CASE 2 4 6 6 8
PIPE DATA Nom.size (inches) 2 4 6 6 8
PIPE RATING # 300 300 300 300 300
PIPE SCH NO. 40 40 40 40 40
PIPE INTERNAL DIA in 2.066 4.026 6.066 6.066 7.982
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0 .00192 0.00192
PROCESS DATA
PRESSURE bara 122.69 122.69 122.69 122.69 122.69
psia 1779.01 1779.01 1779.01 1779.01 1779.01
TEMPERATURE deg C 49.8 49.8 49.80 49.80 49.80
deg F 121.64 121.64 121.64 121.64 121.64
deg R 581.64 581.64 581.64 581.64 581.64
LIQUID FLOWRATE (Note 1) m3/hr 1.820 1.820 1.820 1.820 1.820
bpd 274.75 274.75 274.75 274.75 274.75LIQUID VISCOCITY cP 6.324 6.324 6.324 6.324 6.324
LIQUID DENSITY kg/m3 421.60 421.60 421.60 421.60 421.60
lb/ft3 26.31 26.31 26.31 26.31 26.31
CALCULATION
NRe (Reynold Number) 823.19 422.43 280.37 280.37 213.07
Relative Roughness 9.29332E-04 4.77E-04 3.17E-04 3.17E-04 2.41E-04
A (Fric. Factor Constant) 2.17E+16 2.04E+15 3.82E+14 3.82E+14 1.11E+14
B (Fric. Factor Constant) 3.4839E+26 1.5065E+31 1.0627E+34 1.0627E+34 8.5856E+35
Moody Friction Factor 0.07776 0.15153 0.22830 0.22830 0.30041
RESULT
LIQUID VELOCITY m/s 0.236 0.062 0.027 0.027 0.016
ft/s 0.772 0.203 0.090 0.090 0.052
psi/100ft 0.08 0.01 0.00 0.00 3.39E-04
kPa/100m 1.711 0.119 0.023 0.023 0.008
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100m
SELECTION CRITERION
NOTE
1 Flowrate is based on 'Line Sizing Calculation' document 08055E-801-FI-02
EXCO-00 29/10/2008 FO AJ HHRev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
Issued for designDescription
8/13/2019 Line Sizing (Liquid)
21/22
Calculation number BAE 00 C0701-EC-PR003
DESCRIPTION
Project OYO FIELD DEVELOPMENT
Project number BAB 002 1004
Client ENI
File name \\vboxsrv\conversion_tmp\scratch_2\[208857486.xls.ms_office.xls]new
Line number 01-230-0-CO-062-2"-AC210-E25 and 01-230-0-CO-061-2"-AC210-E25
Line destination Recycle line from the condensate return pump back to LP Flare KOD.
SIZE CASE 2 3 4 5 6
PIPE DATA Nom.size (inches) 2 3 4 5 6
PIPE RATING # 300 300 300 300 300
PIPE SCH NO. 40 40 40 40 40
PIPE INTERNAL DIA in 2.066 3.068 4.026 5.046 6.066
ABSOLUTE ROUGHNESS in 0.00192 0.00192 0.00192 0.00192 0.00192
PROCESS DATA
PRESSURE bara 4.00 4.00 4.00 4.00 4.00
psia 58.00 58.00 58.00 58.00 58.00
TEMPERATURE deg C 45.0 45.0 45.00 45.00 45.00
deg F 113.00 113.00 113.00 113.00 113.00deg R 573.00 573.00 573.00 573.00 573.00
LIQUID FLOWRATE m3/hr 20.000 20.000 20.000 20.000 20.000
bpd 3019.20 3019.20 3019.20 3019.20 3019.20
LIQUID VISCOCITY cP 4.581 4.581 4.581 4.581 4.581
LIQUID DENSITY kg/m3 823.27 823.27 823.27 823.27 823.27
lb/ft3 51.37 51.37 51.37 51.37 51.37
CALCULATION
NRe (Reynold Number) 24385.35 16421.16 12513.69 9984.17 8305.33
Relative Roughness 9.29332E-04 6.26E-04 4.77E-04 3.80E-04 3.17E-04
A (Fric. Factor Constant) 6.04E+19 3.84E+19 2.50E+19 1.66E+19 1.15E+19
B (Fric. Factor Constant) 9.9082E+02 5.5411E+05 4.2844E+07 1.5888E+09 3.0224E+10
Moody Friction Factor 0.02695 0.02852 0.03010 0.03168 0.03316
RESULT
LIQUID VELOCITY m/s 2.589 1.174 0.682 0.434 0.300
ft/s 8.488 3.849 2.235 1.423 0.985
psi/100ft 6.18 0.91 0.25 0.08 3.48E-02
kPa/100m 139.810 20.493 5.556 1.891 0.788
SELECTION CRITERIA
Liquid velocity ft/s 3 - 15 3 - 15 3 - 15 3 - 15 3 - 15
m/s
Pressure drop psi/100ft
kpa/100m
SELECTION CRITERION
NOTE
1 Flowrate based condensate return pump's capacity.
EXCO-00 29/10/2008 FO AJ HH
Rev Date Prep Chkd App
BUMI ARMADA ENGINEERING SDN BHD
LIQUID PIPE SIZING CALCULATION
Issued for design
Description
8/13/2019 Line Sizing (Liquid)
22/22