Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Appendix, Linked Document 6
1
LINKED DOCUMENT 6: STAKEHOLDERS’ PERCEPTIONS
A. Survey Objective and Methodology
1. The evaluation of the Asian Development Bank’s (ADB) results-based lending (RBL) pilot program
entailed a survey that aimed to gather feedback from government counterparts in relevant developing
member country (DMC) governments and ADB staff on the design and implementation of the RBL
modality, its added value, and the achievement of expected results and benefits. The survey results,
together with the analyses of data and information from other sources such as key informant interviews,
documents review, and portfolio analyses, were intended to contribute to the formulation of
recommendations to improve ongoing RBL programs and give directions for future portfolio.
2. The structured survey questionnaires were administered online1
to three groups of target
respondents with known email addresses: (i) officers and staff of national and central government
agencies in nine countries implementing RBL operations; (ii) officers and staff of executing and
implementing agencies of RBL programs; and (iii) ADB staff and RBL program officers or team leaders
(PTLs). The names of target respondents and their email addresses were mostly compiled from the
Independent Evaluation Department (IED) missions undertaken for this evaluation.
3. The survey was conducted from 16 August to 10 September 2017. A follow-up email was sent
to each target respondent.
B. Survey Response Rates and Respondents’ Profiles
1. Response rates
4. The survey questionnaire was sent to 21 central government officers and 49 executing or
implementing agency officers and staff (70 staff). A total of 40 government staff responded, a response
rate of 57% (Table A6.1). The survey questionnaire was sent to 26 ADB RBL program officers, of which
18 or 69% responded.
Table A6.1. Number of Stakeholders and Response Rates, by Type of Respondent
Stakeholders Sent to No. responded Response rate Margin of error a
Central government 21 9 43% 25%
Executing or
implementing agencies
49 31 63% 11%
Total DMC clients 70 40 57% 10%
PTLs 26 18 69% 13%
Total 96 58 60 8%
DMC = developing member country., PTLs=project or program team leaders
a At 95% confidence interval.
Source: Independent Evaluation Department.
2. Number of Respondents, by Country
5. Table A6.2 shows the distribution of survey respondents by country of RBL operations. Except for
Solomon Islands where the survey team was not able to discover e-mail addresses of DMC government
contacts, countries with ADB-supported RBL projects were represented by at least one respondent
government officer. The 18 PTLs cover all countries but one, the Philippines.
1 Survey Monkey online tool (www.surveymonkey.com).
Appendix, Linked Document 6
2
Table A6.2. Number of Respondents, by Country of RBL Program
Central Government
Executing and
Implementing
Agencies
Total DMC
Clients PTLs
Armenia 1 2 3 3
China, People’s Republic 0 3 3 4
Indiaa - 1 1 3
Indonesia 1 1 2 3
Nepal 0 3 3 1
Pakistan 1 4 5 1
Philippines 1 5 6 0
Solomon Islandsa - - - 1
Sri Lanka 2 6 8 4
Total 6 25 31 18
No answerb 3 6 9
DMC = developing member country, PTL = program team leader.
a No email addresses of contacts.
b Since the survey is anonymous, the respondent can opt not to indicate their country of operations.
Source: Independent Evaluation Department.
3. Length of involvement in ADB-supported RBL Program
6. One of every five DMC client respondents (particularly the executing or implementing agency
officers) and one of every three PTLs had been involved with RBL program since it started 3 years ago.
More DMC clients (33%) than PTLs (11%) were relatively new in the RBL program (Table A6.3).
Table A6.3. Years of RBL Project Involvement
Central Government
Executing and
Implementing
Agencies Total DMC Clients PTLs
No. % No. % No. % No. %
One (1) year or less 4 44.4 9 29.0 13 32.5 2 11.1
More than 1 year to 2
years 4 44.4 10 32.3 14 35.0 5 27.8
More than 2 years to 3
years 0 0.0 5 16.1 5 12.5 5 27.8
More than 3 years 1 11.1 7 22.6 8 20.0 6 33.3
Total 9 100.0 31 100.0 40 100.0 18 100.0
DMC = developing member country, PTL = program team leader.
Source: Independent Evaluation Department.
4. Activity Involvement, Roles, and Responsibilities in the RBL Program
7. DMC central government officers who participated in the survey had been involved in
(i) identifying the program to be supported by RBL (44%), (ii) policy dialogues (33%), and (iii) verification
of results and disbursements against disbursement-linked indicators (DLIs) (33%). Most executing and
implementing agency respondents were involved in (i) verification of results and disbursements against
DLIs (64%), (ii) implementation and monitoring of the program action plan, PAP (64%), and
(iii) assessment of program systems (45%)—Table A6.4.
8. Conversely, most PTL respondents (at least two-thirds) had been involved in: (i) assessment of
program soundness, expenditure and financing framework, results and links with disbursements (89%);
(ii) support to government in identifying and designing the country’s RBL program (89%); (iii) assessment
of programs systems (83%); (iv) assessment of the RBL program (83%); (v) supervision of RBL program
implementation (72%); (vi) monitoring of RBL program performance and risks (67%); and (vii) working
with development partners to support the country in implementing measures to improve the RBL
program (Table A6.5).
Appendix, Linked Document 6
3
Table A6.4. Activity Involvement of DMC Client Respondents
Central Government
Executing and
Implementing
Agencies All DMC Clients
No. % No. % No. %
Identification of program to be supported ADB
through the results-based lending modality 4 44.4 12 38.7 16 40.0
Assessment of program soundness, expenditure and
financing frameworks, and/or results and links with
disbursements
1 11.1 13 41.9 14 35.0
Assessment of monitoring and evaluation system,
fiduciary system, safeguards system, and/or other
program systems
1 11.1 14 45.2 15 37.5
Design of the RBL program 1 11.1 7 22.6 8 20.0
Development of the program action plan 1 11.1 16 51.6 17 42.5
Implementation and monitoring of the program
action plan 2 22.2 20 64.5 22 55.0
Monitoring and managing fiduciary and safeguard
issues and other risks 0 0.0 6 19.4 6 15.0
Addressing performance problems and ensuring
effective feedback loops 0 0.0 7 22.6 7 17.5
Participation in policy dialogues 3 33.3 12 38.7 15 37.5
Verification of results and disbursements against
disbursement-linked indicators 3 33.3 20 64.5 23 57.5
Othersa 1 11.1 1 3.2 2 5.0
Total 9 100.0 31 100.0 40 100.0
DMC = developing member country.
a Others include: for central government: overall coordination of the program, mainly financial aspects; for the executing or implementing agencies:
(i) program management, (ii) facilitation of the submission of the ADB required financial reports available at the Department of Education Accounting
Division, coordinate with the Department of Education Budget Division regarding financial reports prepared by their office, coordinate with the
Commission on Audit and Department of Education Project Management Staff regarding ADB financial requirements; attend selected meetings
regarding ADB loan; (iii) implementation of the RBL program.
Source: Independent Evaluation Department.
Table A6.5. Activity Involvement of ADB Staff and/or PTL Client Respondents
PTLs
No. %
Assessment of program soundness, expenditure and financing
frameworks, and/or results and links with disbursements 16 88.9
Assessment of monitoring and evaluation system, fiduciary
system, safeguards system, and/or other program systems 15 83.3
Assessment of the results-based lending (RBL) program in
coordination with the government 15 83.3
Support to the government in identifying and designing
measures to improve the RBL Program, its systems, and risk-
mitigating measures
16 88.9
Working with development partners as appropriate to support
the country in implementing improvement measures 12 66.7
Monitoring of RBL program performance and risks 12 66.7
Supervision of RBL program implementation 13 72.2
Provision of technical advice in support of RBL implementation
including resolution of issues 10 55.6
Others a 3 16.7
Total 18 100.0
PTL = program team leader.
a Others include: (i) program team leader and (ii) support the mission leader in processing the RBL.
Source: Independent Evaluation Department.
Appendix, Linked Document 6
4
C. Summary of Stakeholders’ Perceptions
1. Identifying sector priorities to be supported by RBL and defining program boundaries
9. Most DMC clients (87%) find their engagement with the ADB in identifying sector priorities to be
supported by RBL, “extremely/very useful” (Table A6.6).
Table A6.6. Usefulness of ADB’s Engagement with the Government in
Identifying Sector Priorities for RBL
Central Government
Executing and
Implementing
Agencies Total DMC Clients
No. % No. % No. %
Extremely/very usefula 8 88.9 25 86.2 33 86.8
Moderately useful 1 11.1 4 13.8 5 13.2
Slightly/not at all useful 0 0.0 0 0.0 0 0.0
Don’t know 0 0.0 0 0.0 0 0.0
Total 9 100.0 29 100.0 38 100.0
DMC = developing member country.
a Executing or implementing agency comments: (i) ADB has given the most priority to the development of the education sector
plan and its implementation through the technical and financial support; (ii) conducting research and publication of insightful
reports have contributed to the establishment of accurate policies; (iii) especially ADB's RBL support for distribution systems,
staff training and certification programs.
Source: Independent Evaluation Department.
10. Identifying country sector priorities to be supported by RBL is “not difficult” for two-thirds (67%)
of PTL respondents. It seems that PTLs find it slightly more difficult to define the boundaries of the RBL
program as distinct from the government program; 50% of PTLs rated defining boundaries as
“moderately difficult” (Table A6.7).
Table A6.7. PTLs’ Level of Difficulty in Identifying Sector Priorities and
In Defining RBL Boundaries
PTLs’ Level of Difficulty
Identifying Sector Prioritiesa Defining Boundaries
b
No. of PTLs % No. of PTLs %
Extremely/very
difficult 1 5.6 1 5.6
Moderately difficult 5 27.8 9 50.0
Slightly/not at all
difficult 12 66.7 8 44.4
Don’t know 0 0.0 0 0.0
Total 18 100.0 18 100.0
PTL = program team leader.
a Comments: (i) “Not difficult”—The first RBL financed by ADB in Sri Lanka was in the education sector and the first RBL in
PRC was in the same sector. Expanding RBL to other sectors, such as transport and energy is much more difficult because
of safeguard requirements; (ii) “Difficult” —Difficult due to the breadth and range of sector priorities; some priorities were
selected but the enabling policy environment was not considered.
b Comments: (i) This largely depended on the mission leader, his/her knowledge and familiarity with the RBL. (ii) Negotiating
boundaries was intense but not really difficult. Government expected more from ADB.
Source: Independent Evaluation Department.
2. Technical Assistance Capacity Building Support for Clients and Staff
11. Not all DMC clients and PTLs think that the identification of the country’s needs for capacity
building or TA related to the RBL program has been accurate. Only 18% of DMC client respondents and
28% of PTLs think that the identification of RBL-related capacity building or TA needs of the country has
been “highly accurate” (Table A6.8). The majority of DMC government respondents (82%) and of PTLs
(72%) indicated that TA needs identification was less than “highly accurate” with the majority (about
Appendix, Linked Document 6
5
two-thirds) of both groups of respondents saying it has been “moderately accurate.” About 13% of DMC
respondents considered the TA needs identification “slightly accurate” and 6% of PTLs found it to be
“not accurate.”
Table A6.8. Accuracy of Identification of Country’s TA Capacity Building Needs
Central Government
Executing and
Implementing
Agencies Total DMC Clients PTLs
No. % No. % No. % No. %
Highly accurate 2 22.2 5 17.2 7 18.4 5 27.8
Moderately accurate 4 44.4 20 69.0 24 63.2 12 66.7
Slightly accurate 2 22.2 3 10.3 5 13.2 0 0.0
Not accurate a 0 0.0 0 0.0 0 0.0 1
a 5.6
a
Don’t know 1 11.1 1 3.4 2 5.3 0 0.0
Total 9 100.0 29 100.0 38 100.0 18 100.0
DMC = developing member country, PTL = program team leader.
a PTL’s comment: TA was discouraged by ADB and reduced to focus on risk mitigation of ADB funds. Government wanted
more assistance with policy reforms.
Source: Independent Evaluation Department.
12. For two-thirds of DMC clients (68%), the project preparatory technical assistance (PPTA) provided
by ADB in the preparation of the country's RBL Program had been “extremely/very important” (Table
A6.9). A respondent cited the case of the preparatory TA for Nepal’s School Sector Development Plan
provided by ADB, which he/she said was so useful that the government was able to use it as the strategic
plan for the development of the sector.
Table A6.9. Importance of the PPTA for the RBL Program
Central Government
Executing and
Implementing
Agenciesa Total DMC Clients
No. % No. % No. %
Extremely/very important 7 77.8 18 64.3 25 67.6
Moderately important 1 11.1 5 17.9 6 16.2
Slightly/not at all
important 0 0.0 1 3.6 1 2.7
No PPTA was provided 0 0.0 0 0.0 0 0.0
Don’t know 1 11.1 4 14.3 5 13.5
Total 9 100.0 28 100.0 37 100.0
DMC = developing member country.
a Comment: During the preparation of the School Sector Development Plan in Nepal, the TA provided by ADB was so
useful that it was used as the strategic plan for the development of school education sector through the joint efforts
made by Government of Nepal and financing partners.
Source: Independent Evaluation Department.
13. Like the PPTA, the capacity development technical assistance (CDTA) provided by ADB in building
the country’s capacity and institutional strengthening related to RBL was considered important by 66%
of DMC clients (Table A6.10). However, 26% of government clients indicated that the CDTA was
“moderately or slightly important”, which could mean that RBL capacity building efforts so far may not
have been enough.
Appendix, Linked Document 6
6
Table A6.10. Importance of Capacity Building Technical Assistance
Central Governments
Executing and
Implementing
Agencies Total DMC Clients
No. % No. % No. %
Extremely/very importanta 7 77.8 18 62.1 25 65.8
Moderately important 0 0.0 9 31.0 9 23.7
Slightly/not at all
importantb 1 11.1 0 0.0 1 2.6
No CDTA was provided 0 0.0 1 3.4 1 2.6
Don’t know 1 11.1 1 3.4 2 5.3
Total 9 100.0 29 100.0 38 100.0
DMC = developing member country.
a Comment: Technical assistance given by ADB in different sectors to strengthen the education system of
Nepal has also enhanced the institutional capacity of the ministry system.
b Comments: (i) CDTA has a memorandum of understanding but the intended CDTA assistance is not
provided to concerned offices. (ii) Focus must be sensitive to project and project implementer's needs.
Source: Independent Evaluation Department.
3. ADB’s due diligence efforts in terms of pre-design diagnostics and assessments
14. The DMC clients were asked to rate the quality of RBL program pre-design diagnostics and
assessments done by the ADB staff, as follows: (i) program soundness, (ii) expenditure frameworks and
financing plans, (iii) results and links with disbursements, (iv) monitoring and evaluation systems, (v)
fiduciary systems, (vi) procurement systems, and (vii) environment and social safeguard systems. It can
be noted from Table A6.11 that the majority of the respondents (at least 60%) consider the quality of
each of these efforts as “very good or good”. The biggest proportion of government respondents (86%)
that gave “very good/good” rating referred to ADB’s efforts in ensuring “program soundness.” Fewer
government respondents (60%) gave the highest rating for the quality of ADB’s assessment of monitoring
and evaluation (M&E) system for the RBL program (Table A6.11).
Table A6.11. DMC Clients’ Rating of the Quality of ADB’s Due Diligence Efforts
Very Good/
Good Acceptable
Poor/Very
Poor
Don't
know Total
No. % No. % No. % No. % No. %
Central Governments
Program soundness 8 100.0 0 0.0 0 0.0 0 0.0 8 100.0
Expenditure frameworks and
financing plans 6 75.0 2 25.0 0 0.0 0 0.0 8 100.0
Results and links with disbursements 5 62.5 3 37.5 0 0.0 0 0.0 8 100.0
Monitoring and evaluation systems 6 75.0 2 25.0 0 0.0 0 0.0 8 100.0
Fiduciary systems 7 87.5 1 12.5 0 0.0 0 0.0 8 100.0
Procurement systems 7 87.5 1 12.5 0 0.0 0 0.0 8 100.0
Environment and social safeguard
systems 7 87.5 1 12.5 0 0.0 0 0.0 8 100.0
Executing and Implementing Agencies
Program soundness 22 81.5 4 14.8 0 0.0 1 3.7 27 100.0
Expenditure frameworks and
financing plans 16 59.3 8 29.6 1 3.7 2 7.4 27 100.0
Results and links with disbursements 17 63.0 7 25.9 2 7.4 1 3.7 27 100.0
Monitoring and evaluation systems 15 55.6 8 29.6 3 11.1 1 3.7 27 100.0
Fiduciary systems 15 55.6 8 29.6 0 0.0 4 14.8 27 100.0
Procurement systems 15 55.6 9 33.3 1 3.7 2 7.4 27 100.0
Environment and social safeguard
systems 16 59.3 8 29.6 1 3.7 2 7.4 27 100.0
Total DMC Clients
Program soundness 30 85.7 4 11.4 0 0.0 1 2.9 35 100.0
Appendix, Linked Document 6
7
Very Good/
Good Acceptable
Poor/Very
Poor
Don't
know Total
No. % No. % No. % No. % No. %
Expenditure frameworks and
financing plans 22 62.9 10 28.6 1 2.9 2 5.7 35 100.0
Results and links with disbursements 22 62.9 10 28.6 2 5.7 1 2.9 35 100.0
Monitoring and evaluation systems 21 60.0 10 28.6 3 8.6 1 2.9 35 100.0
Fiduciary systems 22 62.9 9 25.7 0 0.0 4 11.4 35 100.0
Procurement systems 22 62.9 10 28.6 1 2.9 2 5.7 35 100.0
Environment and social safeguard
systems 23 65.7 9 25.7 1 2.9 2 5.7 35 100.0
DMC = developing member country.
Executing or implementing agency comment: Consider introduction of monitoring and evaluation software tool in order to ensure
efficiency and accuracy of monitoring.
Source: Independent Evaluation Department.
15. On the other hand, the PTLs’ rating of their level of difficulty in doing pre-design diagnostics and
assessments was somewhat mixed. As is shown in Table A6.12, the majority of the PTLs (56%) find
assessment of program soundness slightly or not at all difficult. Moderately difficult for at least half of
the PTLs are the pre-diagnostics of the environmental and social safeguard systems (61%), fiduciary
systems (56%), and procurement systems (50%).
Table A6.12. Project Team Leaders’ Level of Difficulty in Pre-Design Diagnostics and Assessments
Extremely/Very
Difficult
Moderately
Difficult
Slightly/Not at
all Difficult Total
No. % No. % No. % No. %
Program soundness 3 16.7 5 27.8 10 55.6 18 100.0
Expenditure frameworks and financing
plans 5 27.8 8 44.4 5 27.8 18 100.0
Results and links with disbursementsa 6 33.3 6 33.3 6 33.3 18 100.0
Monitoring and evaluation systems 4 22.2 8 44.4 6 33.3 18 100.0
Fiduciary systems 2 11.1 10 55.6 6 33.3 18 100.0
Procurement systems 3 16.7 9 50.0 6 33.3 18 100.0
Environment and social safeguard
systems 1 5.6 11 61.1 6 33.3 18 100.0
a Comment: design of disbursement-linked indicators for the second results-based lending program in the People’s Republic of
China (also in the education sector) was extremely difficult due to anticipated high expectation from the Board.
Source: Independent Evaluation Department.
16. With regard to the sufficiency of resources, particularly the amount of time to complete pre-
design diagnostics and assessments for the RBL program, 61% of PTL respondents though that resources
are sufficient, but 56% feel that time available is inadequate (Table A6.13).
Appendix, Linked Document 6
8
Table A6.13. Sufficiency of Resources and Adequacy of Time to Complete
Pre-Design Diagnostics and Assessments
Resources Timea
No. of PTLs % No. of PTLs %
More than
sufficient/adequate 2 11.1 1 6.3
Sufficient/adequate 9 50.0 6 37.5
Less than sufficient/adequate 7 38.9 5 31.3
Not at all sufficient/adequate 0 0.0 4 25.0
Don’t know 0 0.0 0 0.0
Total 18 100.0 16 100.0
PTL = program team leader.
a Comments: (1) “Not adequate”—Everything is always rushed at ADB due to artificial deadlines linked to
bunching season; (2) “Adequate”—The program design used a lot of assessments completed by other
development partners and ADB, which are available to the program team.
Source: Independent Evaluation Department.
17. According to 75% of PTL respondents, at least equal, if not greater efforts, are required to
complete the preparation and processing of RBL program compared with those needed for other lending
modalities (Table A6.14). About 38% indicated that RBL requires greater effort while 19% said that it
requires less effort than other modalities. One PTL who claimed greater effort was required by RBL
explained that much more work was required in developing the results chain and DLIs as RBL requires a
much more holistic appreciation of constraints, policy context, budget allocation to sequence DLI and
implementation arrangements. Moreover, he/she noted that closer engagement with government was
required under RBL.
Table A6.14. Effort Required in the Preparation and Processing of RBL Compared with Other Lending
Modalities
PTL
No. %
RBL requires greater effort than other modalities 6 37.5
RBL requires equal effort than other modalities 6 37.5
RBL requires less effort than other modalities 3 18.8
Don’t know 1 6.3
Total 16 100.0
PTL = program team leader.
Comments: (i) Much more work is required in developing the results chain and DLIs—much more
holistic appreciation of constraints, policy context, budget allocation is required to sequence the
disbursement-linked indicators and implementation arrangements. Closer engagement with
government is required which is really good; (ii) It depends on how much assessment has been done
on the sector and country systems. Nevertheless, efforts to complete the preparation and processing
of the RBL program should reduce over time, with more assessments done for the sector and country
systems.
Source: Independent Evaluation Department.
4. Disbursement-Linked Indicators (DLIs)
18. Quality of DLIs. The majority of DMC stakeholders (at least 85%) and PTLs (at least 78%) have
encouraging views on the DLIs of the country’s RBL program (Table A6.15). They generally agree that:
(i) DLIs were effectively formulated and their achievement would ensure attainment of the RBL program’s
intended outcomes, (ii) DLIs are sufficiently ambitious, yet realistic, (iii) the DLI verification protocols are
clear in terms of defining how their achievement will be measured and verified, and (iv) the DLIs and the
PAP complement each other. However, it should be noted that PTLs had slightly less positive views than
DMC government clients on the quality of DLIs.
19. Most DMC stakeholder respondents (94%) agreed that “The DLI verification protocols are clear
in terms of defining how their achievement will be measured and verified” while most PTLs (89%) believed
Appendix, Linked Document 6
9
that “The DLIs and the PAP complement each other.” Both, however, seem to be less than fully convinced
that the “DLIs are sufficiently ambitious, yet realistic” as this statement had the least agreement from
DMC clients (79%) and PTLs (78%).
Table A6.15. Agreement or Disagreement with Statements on the Quality of DLIs
Strongly
Agree/ Agree
Neutral/ No
Opinion
Disagree/Strongly
Disagree Total
No. % No. % No. % No. %
DMC Clients
The disbursement-linked indicators (DLIs) were
effectively formulated such that their achievement
ensures attainment of the Program’s intended
outcomes.
31 91.2 1 2.9 2 5.9 34 100.0
The DLIs are sufficiently ambitious, yet realistic. 27 79.4 4 11.8 3 8.8 34 100.0
The DLI verification protocols are clear in terms of
defining how their achievement will be measured
and verified.
32 94.1 1 2.9 1 2.9 34 100.0
The DLIs and the Program Action Plan (PAP)
complement each other. 29 85.3 2 5.9 3 8.8 34 100.0
PTLs
The DLIs were effectively formulated such that their
achievement ensures attainment of the Program’s
intended outcomes.
14 77.8 2 11.1 2 11.1 18 100.0
The DLIs are sufficiently ambitious, yet realistic. 14 77.8 1 5.6 3 16.7 18 100.0
The DLI verification protocols are clear in terms of
defining how their achievement will be measured
and verified.
14 77.8 1 5.6 3 16.7 18 100.0
The DLIs and the PAP complement each other. 16 88.9 2 11.1 0 0.0 18 100.0
DMC = developing member country, PTL = program team leader.
Comments: (1) Executing or implementing agency comment: There must be an established system of revising, refining, or polishing indicators,
so they remain relevant to both the program and the department; (ii) PTL comment: Of the three programs I am involved with, DLIs for one of
them were not very effective.
Source: Independent Evaluation Department.
20. Independent verification of DLIs. About 76% of DMC stakeholder respondents thought that the
independent verification of DLIs was “extremely/very important” in ensuring the achievement of the
intended results of the RBL Program. By contrast, only 9% believed otherwise (Table A6.16). A respondent
commented that independent verification of DLIs would ensure whether progress was achievable or not,
and suggest necessary action for on-time completion of each and every activity.
Table A6.16. Importance of Independent Verification of DLIs
Central Government
Executing and
Implementing
Agencies Total DMC Clients
No. % No. % No. %
Extremely/very important 7 87.5 18 72.0 25 75.8
Moderately important 1 12.5 4 16.0 5 15.2
Slightly/not at all
important 0 0.0 3 12.0 3 9.1
Don’t know 0 0.0 0 0.0 0 0.0
Total 8 100.0 25 100.0 33 100.0
DMC = developing member country.
Comments: (i) Independent verification of DLIs will ensure whether progress is achievable or not, and suggest necessary action
for on-time completion of each and every activity. (ii) Independent verification will need more achievement data to prove the
result of the RBL program.
Source: Independent Evaluation Department.
Appendix, Linked Document 6
10
21. Management of the DLI results verification process. About 64% of executing agency or
implementing agency respondents against only 27% of PTLs rated the management of the DLI results
verification process “extremely/very effective”. The rest, 24% of government stakeholders and 60% of
PTLs, gave a lower rating of “moderately effective.” Some 12% of the respondents replied with “don’t
know,” which indicates that it is too early to say (Table A6.17).
Table A6.17. Effectiveness of the Management of the DLI Results Verification Process
Executing and
Implementing Agencies PTLs Total
No. % No. % No. %
Extremely/very effective 16 64.0 4 26.7 20 50.0
Moderately effective 6 24.0 9 60.0 15 37.5
Slightly/not at all effective 0 0.0 0 0.0 0 0.0
Don’t know 3 12.0 2 13.3 5 12.5
Total 25 100.0 15 100.0 40 100.0
PTL = program team leader.
Executing or implementing agency comments: (i) We have not raised any withdrawal application. Hence could not answer this
question at this point of time. (ii) It is still early to give the decision on this questionnaire. It could be answered once independent
verification agencies' output is seen.
PTL comments: (i) As far as the verification protocol is clear and fully understood by the executing and implementing agencies, and
verification sources (e.g., independent verification) are available, it could be very effective. (ii) External third-party verification is
really required. Must be transparent and reported. (iii) Verification protocols are sometimes intentionally kept general, not very
detailed, as we cannot anticipate everything upfront and design the verification protocol very rigidly. Therefore, during
implementation, the verification protocol needs to be further refined. Also, executing agencies need to be guided on the
preparation of evidence or documentation of evidence.
Source: Independent Evaluation Department.
5. RBL Program Action Plan
22. Usefulness of the PAP. The majority of both DMC clients (88%) and PTLs (61%) found the PAP
useful in supporting RBL implementation. However, they differed in their opinion of the PAP’s usefulness
in capacity building, strengthening program systems, and in mitigating risks (Table A6.18).
23. In capacity building, only 44% of PTLs compared with 67% of DMC clients indicated that the PAP
was useful. Some 11% of PTLs even said that the PAP was not useful at all for the purpose of capacity
building. For the strengthening of program systems, 88% of DMC respondents versus 44% of PTL
respondents thought that the PAP was useful. Likewise, 73% of DMC clients against 33% of PTLs believed
that the PAP was useful.
Table A6.18. Usefulness of the RBL Program Action Plan
Extremely/
Very Useful
Moderately
Useful
Slightly/Not
At All Useful
Don't
Know Total
No. % No. % No. % No. % No. %
DMC Clients
In capacity building 22 66.7 10 30.3 1 3.0 0 0.0 33 100.0
In strengthening program systems 29 87.9 3 9.1 1 3.0 0 0.0 33 100.0
In mitigating risks 24 72.7 4 12.1 4 12.1 1 3.0 33 100.0
In supporting implementation 29 87.9 4 12.1 0 0.0 0 0.0 33 100.0
ADB Staff PTLs
In capacity building 8 44.4 7 38.9 2 11.1 1 5.6 18 100.0
In strengthening program systems 8 44.4 6 33.3 3 16.7 1 5.6 18 100.0
In mitigating risks 6 33.3 9 50.0 2 11.1 1 5.6 18 100.0
In supporting implementation 11 61.1 6 33.3 0 0.0 1 5.6 18 100.0
DMC = developing member country, PTL = program team leader.
PTL comment: The PAP is useful but is not prioritized by government as it tends to focus on DLIs, especially those that can be
addressed quickly. Policy reforms have been overlooked a little, which undermines the effectiveness and achievement of intended
results.
Source: Independent Evaluation Department.
Appendix, Linked Document 6
11
24. Completion of PAP activities. According to 76% of DMC client respondents, most or more than
half of the activities of the RBL program specified in the PAP had been completed on time, with 12%
saying that all activities in fact have been completed as scheduled (Table A6.19).
Table A6.19. Proportion of PAP Activities Completed as Scheduled
Central Government
Executing and
Implementing
Agencies
Total DMC Clients
No. % No. % No. %
All activities are being completed as scheduled 0 0.0 4 16.0 4 12.1
Most/More than half of activities are being completed as
scheduled 4 50.0 17 68.0 21 63.6
Half of the activities are being completed as scheduled 2 25.0 2 8.0 4 12.1
Less than half of the activities are being completed as
scheduled 0 0.0 1 4.0 1 3.0
No activity is being completed as scheduled 0 0.0 0 0.0 0 0.0
Don’t know 2 25.0 1 4.0 3 9.1
Total 8 100.0 25 100.0 33 100.0
DMC = developing-member country
Source: Independent Evaluation Department.
25. Effectiveness of PAP implementation. The implementation of the PAP has been “extremely/very
effective” as noted by 60% of executing or implementing agency respondents but only 27% of PTLs (Table
A6.20). Of the PTL respondents, 20% even indicated that PAP implementation was “slightly/not effective”.
Table A6.20. Effectiveness of PAP Implementation
Executing and
Implementing
Agencies PTLs Total
No. % No. % No. %
Extremely/very effective 15 60.0 4 26.7 19 47.5
Moderately effective 9 36.0 7 46.7 16 40.0
Slightly/not effective 0 0.0 3 20.0 3 7.5
Don’t know 1 4.0 1 6.7 2 5.0
Total 25 100.0 15 100.0 40 100.0
PTL = program team leader.
Executing or implementing agency comments: (i) RBL PAP is very useful for the implementation of secondary
school programs, it drives the program and makes the team accountable for the result through in-time
implementation of the programs. (ii) Some PAPs need a time schedule and process to be completed in
Perusahaan Listrik Negara (State Electricity Company)—PLN.
PTL comments: (i) PAP requirements or recommendations were too often overlooked or avoided. (ii) There are
differences between different RBL programs. In one RBL, PAP implementation is very good while in the other
one, PAP is not very much followed up by the executing agency.
Source: Independent Evaluation Department.
6. Technical Advice Provided by ADB in Support of RBL Program Implementation
26. Most DMC client respondents (80%) considered the technical advice provided by ADB in support
of the implementation of the country's RBL program to be adequate (Table A6.21).
Appendix, Linked Document 6
12
Table A6.21. Adequacy of ADB Technical Advice
Central Government
Executing and
Implementing
Agencies Total DMC Clients
No. % No. % No. %
More than adequate 1 12.5 2 8.0 3 9.1
Adequate 6 75.0 18 72.0 24 72.7
Less than adequate a 0 0.0 3 12.0 3 9.1
Not adequate 0 0.0 1 4.0 1 3.0
Don’t know 1 12.5 1 4.0 2 6.1
Total 8 100.0 25 100.0 33 100.0
DMC = developing member country
a Executing or implementing agency comment: in some areas, the technical assistance needed to be
expanded for the successful implementation of all program activities within a given time.
Source: Independent Evaluation Department.
27. According to 60% of PTLs, ADB’s technical advice during RBL program implementation had been
adopted by the executing or implementing agencies “to a somewhat high degree” (Table A6.22). But
13% of PTLs indicated that adoption of the technical advice was “to a somewhat low degree.” No
respondents thought that there was a “very high degree” of acceptance of ADB’s technical advice.
Table A6.22. Extent of the Country’s Adoption of ADB’s Technical Advice
PTL
No. %
To a very high degree 0 0.0
To a somewhat high degree a 9 60.0
To a somewhat low degree a 2 13.3
To a very low degree 0 0.0
Don’t know 4 26.7
Total 15 100.0
PTL = program team leader.
a Comments: (1) ADB needs to put more effort into the provision of technical advice. (2) I
have a mixed case. One executing agency is very receptive while the other is not so much.
Source: Independent Evaluation Department.
7. Monitoring of critical risks
28. Risks critical to the implementation of the RBL program are monitored to a “high degree” as
indicated by 72% of executing and implementing agencies and 60% of PTLs. However, there are cases
where apparently risks are monitored to a “low degree” according to 24% of executing agency and
implementing agency respondents and 20% of PTLs (Table A6.23).
Table A6.23. Extent of Monitoring of Critical Risks
Executing and Implementing
Agencies a PTLs
No. % No. %
To a very high degree 5 20.0 3 20.0
To a somewhat high degree 13 52.0 6 40.0
To a somewhat low degree 6 24.0 1 6.7
To a very low degree 0 0.0 2 13.3
Don’t know 1 4.0 3 20.0
Total 25 100.0 15 100.0
PTL = program team leader.
a Comment: It appears as high-risk because of the set disbursement-linked indicators (targets and protocol) and political
transition of the country.
Source: Independent Evaluation Department.
Appendix, Linked Document 6
13
29. Risks that may arise during RBL program implementation seemed to have been anticipated. Two-
thirds (67%) of PTL respondents estimated that the number of risks that materialized during
implementation were the same or fewer than those identified during the risk assessment (Table A6.24).
However, one PTL noted that more risks arose in the course of implementation than were identified
during risk assessment.
Table A6.24. Number of Risks during Implementation Compared with Risk Assessment
PTLs
No. %
Greater number of risks during implementation than in risk
assessment 1 6.7
Same number of risks during implementation as in risk assessment 7 46.7
Fewer risks during implementation than in risk assessment 3 20.0
Don’t know 4 26.7
Total 15 100.0
PTL = program team leader.
Source: Independent Evaluation Department.
8. Implementation of the country’s RBL-supported program
30. About 85% of DMC government stakeholders, but only 67% of PTLs were satisfied with the
implementation of the RBL-supported program. No DMC client was not satisfied with how the program
had implemented, but 13% of PTLs are somewhat dissatisfied (Table A6.25).
Table A6.25. Satisfaction or Dissatisfaction with RBL Implementation
Central
Governments
Executing and
Implementing
Agencies All DMC Clients PTLs Total
No. % No. % No. % No. % No. %
Very/somewhat satisfied 7 87.5 21 84.0 28 84.8 10 66.7 38 79.2
Neither satisfied nor
dissatisfied 1 12.5 3 12.0 4 12.1 1 6.7 5 10.4
Somewhat/Very dissatisfied 0 0.0 0 0.0 0 0.0 2 13.3 2 4.2
Don’t know 0 0.0 1 4.0 1 3.0 2 13.3 3 6.3
Total 8 100.0 25 100.0 33 100.0 15 100.0 48 100.0
DMC = developing-member country, PTL = program team leader.
Source: Independent Evaluation Department.
31. While the majority (70%) of DMC clients considered ADB’s support and supervision of the
country’s RBL implementation to have been “extremely/very effective”, some 9% thought that ADB’s
support and supervision had been “slightly/not effective” (Table A6.26).
Table A6.26. Effectiveness of ADB's Support and Supervision of RBL Implementation
Central Government
Executing and
Implementing
Agencies All DMC Clients
No. % No. % No. %
Extremely/very
effective 5 62.5 18 72.0 23 69.7
Moderately effective 1 12.5 4 16.0 5 15.2
Slightly/not effective 1 12.5 2 8.0 3 9.1
Don’t know 1 12.5 1 4.0 2 6.1
Total 8 100.0 25 100.0 33 100.0
DMC = developing-member country
Source: Independent Evaluation Department.
Appendix, Linked Document 6
14
9. Extent to Which RBL Programs Strengthen the Country’s Program Systems
32. For the majority (77%) of stakeholders (85% of DMC clients and 60% of PTLs), the extent to which
RBL programs strengthen program systems is “high” (Table A6.27). However, a significant proportion of
PTLs (33%) responded “don’t know,” which could mean that there is still no evidence yet of this expected
value added of RBL.
Table A6.27. Extent to Which RBL Programs Strengthened DMC Program Systems
Central Government
Executing and
Implementing
Agencies All DMC Clients PTLs Total
No. % No. % No. % No. % No. %
To a very high degree 2 25.0 9 36.0 11 33.3 4 26.7 15 31.3
To a somewhat high
degree 6 75.0 11 44.0 17 51.5 5 33.3 22 45.8
To a somewhat low
degree 0 0.0 3 12.0 3 9.1 1 6.7 4 8.3
To a very low degree 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0
Don’t know 0 0.0 2 8.0 2 6.1 5 33.3 7 14.6
Total 8 100.0 25 100.0 33 100.0 15 100.0 48 100.0
DMC = developing-member country, PTL = program team leader.
Comments: DMC Clients: (i) The Government of Indonesia still needs adjustments to some regulations related to the implementation of RBL. (ii)
In some areas, government departments have been reluctant or lethargic in adapting the recommendations or requirements of the RBL program
which reduced the effectiveness of the program. PTLs: (i) Too early to assess. (ii) This supports government efforts to move toward performance-
based contracting and better performance management of staff and contractors.
Source: Independent Evaluation Department.
10. Extent to which RBL has led to Greater Country Ownership of ADB-Supported
Operations
33. Close to 85% of DMC government respondents and 60% of PTLs perceived that the RBL modality
had to a “high extent” led to greater country ownership of programs supported by ADB (Table A6.28).
On the other hand, 9% of DMC clients and 33% of PTLs may have not yet felt or observed this result of
RBL based on their “don’t know” responses.
Table A6.28. Extent RBL has Led to Greater Country Ownership of ADB-supported Operations
Central Government
Executing and
Implementing
Agencies
All DMC
Clients PTLs Total
No. % No. % No. % No. % No. %
To a very high degree 3 37.5 6 24.0 9 27.3 4 26.7 13 27.1
To a somewhat high
degree 5 62.5 14 56.0 19 57.6 5 33.3 24 50.0
To a somewhat low
degree 0 0.0 2 8.0 2 6.1 1 6.7 3 6.3
To a very low degree 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0
Don’t know 0 0.0 3 12.0 3 9.1 5 33.3 8 16.7
Total 8 100.0 25 100.0 33 100.0 15 100.0 48 100.0
DMC = developing-member country, PTL = program team leader.
Comments: Executing and implementing agencies: For example, the RBL program was extended to PLN region of Sulawesi, following the PLN
region of Sumatera. PTL: The agenda remains the responsibility of the government and they are becoming more realistic and clear in what
they want to achieve.
Source: Independent Evaluation Department.
Appendix, Linked Document 6
15
11. Effectiveness of RBL in Promoting Partnerships among Other Donors
34. Two–thirds of PTLs (67%) confirm the effectiveness of the RBL modality in promoting partnerships
among other donors, including cofinancing (Table A6.29).
Table A6.29. Effectiveness of RBL in Promoting Partnerships
Central Government a PTL
b Total
No. % No. % No. %
Extremely/very effective 3 37.5 10 66.7 13 56.5
Moderately effective 2 25.0 3 20.0 5 21.7
Slightly/not effective 0 0.0 1 6.7 1 4.3
Don’t know 3 37.5 1 6.7 4 17.4
Total 8 100.0 15 100.0 23 100.0
PTL = program team leader.
a Comment: There has been no learning for the results of RBL implementation in Indonesia. Still in progress.
b Comments: (i) The cofinancing with KFW under the second proposed results-based lending program is very effective. (ii) This
will improve once donors see improvements in delivery and more serious attention directed towards achievement of specified
results. It is building credibility currently. Donors are watching carefully and are likely to support future reforms now that they
see ADB and World Bank investing wisely and are more serious in supporting government to achieve specified results.
Source: Independent Evaluation Department.
12. Extent to Which RBL Complements other ADB Lending Modalities
35. About 67% of PTL respondents confirmed that the RBL modality complemented other ADB
lending modalities to a “high degree,” while 20% observed that they were complementary only to a low
degree (Table A6.30).
Table A6.30. Extent to Which RBL Complements Other ADB Lending Modalities
PTLs
No. %
To a very high degree 1 6.7
To a somewhat high degree 9 60.0
To a somewhat low degree 2 13.3
To a very low degree 1 6.7
Don’t know 2 13.3
Total 15 100.0
PTL = program team leader.
Comment: There have been few RBL programs in a limited number of sectors so far.
RBL should be able to complement other modalities more if more RBLs in more
sectors are processed.
Source: Independent Evaluation Department.
13. Usefulness of RBL in Reducing Transaction Costs
36. More than half of PTLs (60%) affirmed the usefulness of RBL in reducing transaction costs (Table
A6.31). One PTL commented that the lower cost may be attributed to the use of government systems.
Appendix, Linked Document 6
16
Table A6.31. Usefulness of RBL in Reducing Transaction Costs
PTLs
No. %
Extremely/very useful 9 60.0
Moderately useful 4 26.7
Slightly/not useful 1 6.7
Don’t know 1 6.7
Total 15 100.0
PTL = program team leader.
Comments: (i) It may take more time from both ADB and government at the
beginning of implementation to fully understand the requirements of the DLI
verification process; (ii) RBL is using more government systems.
Source: Independent Evaluation Department.
14. Extent to Which RBL’s Intended Benefits are Being Achieved in the Country
37. At least 88% of DMC stakeholders and 71% of ADB PTLs believe that the intended benefits of
RBL are being achieved in countries, namely: (i) greater responsiveness to the needs of the country,
(ii) supporting good governance, (iii) increased accountability and incentives for development results,
and (iv) enhanced development and aid effectiveness (Table A6.32).
38. RBL would be able to achieve enhanced development effectiveness to a “high degree” according
to 94% of DMC clients and greater responsiveness to the needs of the country (91%). The high extent of
achievement of RBL in terms of greater responsiveness to the needs of the country and increased
accountability and incentives for development results were acknowledged by 86% of PTLs.
Table A6.32. Extent of Achieving RBL Program’s Intended Benefits
To a Very
High
Degree
To a Somewhat
High Degree
To a Somewhat
Low Degree
To a very
Low
degree
Don't
know Total
No. % No. % No. % No. % No. % No. %
DMC Clients
Greater responsiveness to the
needs of the country 6 18.2 24 72.7 1 3.0 0 0.0 2 6.1 33 100.0
Supporting good governance 10 30.3 19 57.6 3 9.1 0 0.0 1 3.0 33 100.0
Increased accountability and
incentives for development results 7 21.2 22 66.7 2 6.1 1 3.0 1 3.0 33 100.0
Enhanced development / aid
effectiveness 5 15.2 26 78.8 1 3.0 0 0.0 1 3.0 33 100.0
ADB Staff PTLs
Greater responsiveness to the
needs of the country 4 28.6 8 57.1 1 7.1 0 0.0 1 7.1 14 100.0
Supporting good governance 2 14.3 8 57.1 2 14.3 0 0.0 2 14.
3 14 100.0
Increased accountability and
incentives for development results 6 42.9 6 42.9 1 7.1 0 0.0 1 7.1 14 100.0
Enhanced development / aid
effectiveness 3 21.4 8 57.1 1 7.1 0 0.0 2
14.
3 14 100.0
DMC = developing member country, PTL = program team leader.
Source: Independent Evaluation Department.
15. Two Greatest Strengths of the RBL modality
39. The responses of DMC clients and PTLs when asked to choose two strengths of the RBL modality
are summarized in Table A6.33. It can be noted that “focus on results” was the top strength of cited by
all three groups of respondents: DMC central government (75%), executing and implementing agencies
(80%), and PTLs (86%).
Appendix, Linked Document 6
17
40. The second most-frequently cited strength of RBL by both executing and implementing agencies
(24%) and PTLs (43%) is the “use of government program systems” (Table A6.33).
Table A6.33. Two Greatest Strengths of the RBL Modality
Central Government
Executing
and
Implementing
Agencies
All DMC
Clients PTLs Total
No. % No. % No. % No. % No. %
Efficiency in processing the
preparation of the operation 3 37.5 4 16.0 7 21.2 1 7.1 8 17.0
Use of government program
systems 2 25.0 6 24.0 8 24.2 6 42.9 14 29.8
Focus on results 6 75.0 20 80.0 26 78.8 12 85.7 38 80.9
Focus on program institutional
strengthening 0 0.0 6 24.0 6 18.2 1 7.1 7 14.9
Ability to include capacity-building
measures and focus on incentives 1 12.5 3 12.0 4 12.1 3 21.4 7 14.9
Enhanced ADB staff support to
government in identifying and
addressing key issues
1 12.5 2 8.0 3 9.1 4 28.6 7 14.9
Usefulness of ADB assessments in
designing the results-based
lending program
1 12.5 2 8.0 3 9.1 1 7.1 4 8.5
Other (Control of funding for a
designated-results oriented task) 0 0.0 1 4.0 1 3.0 0 0.0 1 2.1
Total 8 100.0 25 100.0 33 100.0 14 100.0 47 100.0
DMC = developing member country, PTL = program team leader.
Source: Independent Evaluation Department.
16. Two Greatest Challenges of the RBL Modality
41. The greatest challenge of RBL is “the novelty of RBL and issues related to its newness” according
to 76% of DMC clients and governments and 57% of PTLs. The second greatest challenge for 39% of
DMC government respondents is “delays in processing the preparation of the operation,” which to PTLs
seem to be less of a problem as only 7% marked this as a top challenge. For 29% of PTLs, the greater
problems are “exclusions of high-value contracts” and “heaviness in conducting ADB assessments” (Table
A6.34).
42. Other challenges identified by the respondents include: (i) difficulty in revising unrealistic targets
identified at the implementation process (executing and implementing agencies); (ii) lack of
understanding of RBL among ADB Management and the Board (PTL); (iii) pressure to put higher amount
of disbursement on outcome-level indicators (PTL); (iv) burden on project officer in verifying the results
and addressing issues arising from bottlenecks to the result achievement, which can be beyond one
person's capacity or the program scope (PTL).
Appendix, Linked Document 6
18
Table A6.34. Two Main Greatest Challenges of the RBL Modality
Central
Government
Executing and
Implementing
Agencies All DMC Clients PTLs Total
No. % No. % No. % No. % No. %
The novelty of RBL and issues related to
its newness 7 87.5 18 72.0 25 75.8 8 57.1 33 70.2
Delays in processing the preparation of
the operation 3 37.5 10 40.0 13 39.4 1 7.1 14 29.8
Exclusions of high-value contracts and
activities due to their potential adverse
impact on the environment and/or
affected people
0 0.0 1 4.0 1 3.0 4 28.6 5 10.6
Heaviness in conducting ADB assessments 1 12.5 5 20.0 6 18.2 4 28.6 10 21.3
Ability to include capacity-building
measures and focus on incentives a
0 0.0 3 21.4 3 6.4
Difficulties in applying ADB's Results-
based Lending Anti-Corruption Guidelines 1 12.5 1 4.0 2 6.1 2 14.3 4 8.5
Other b 0 0.0 1 4.0 1 3.0 2 14.3 3 6.4
Total 8 100.0 25 100.0 33 100.0 14 100.0 47 100.0
DMC = developing member country, PTL = program team leader.
a Not included in the choices of challenges for central governments and executing and implementing agencies.
b Other challenges specified are: (i) difficulty in revising unrealistic targets identified at the implementation process (executing and implementing
agencies); (ii) lack of understanding of RBL among management and board (PTL); (iii) pressure to put a higher amount of disbursement on
outcome-level indicators (PTL); (iv) burden on project officer in verifying the results and addressing issues arising from bottlenecks to the result
achievement, which can be beyond one person's capacity or the program scope (PTL).
Source: Independent Evaluation Department.
17. Appropriateness of the RBL Modality in Supporting the Country’s Sector Program
43. While a significant proportion of government respondents (64%) think that the RBL modality is
appropriate in supporting their country’s sector program, there are a few (18%) who think otherwise
(Table A6.35). On the other hand, 93% of PTLs believe that the RBL modality is suited for the country’s
sector program.
Table A6.35. Appropriateness of the RBL Modality for the Country’s Sector Program
Central
Government
Executing and
Implementing
Agencies All DMC Clients PTLs Total
No. % No. % No. % No. % No. %
More than
appropriate 1 12.5 5 20.0 6 18.2 4 28.6 10 21.3
Appropriate 7 87.5 14 56.0 21 63.6 9 64.3 30 63.8
Less than appropriate 0 0.0 4 16.0 4 12.1 1 7.1 5 10.6
Not at all appropriate 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0
Don't know 0 0.0 2 8.0 2 6.1 0 0.0 2 4.3
Total 8 100.0 25 100.0 33 100.0 14 100.0 47 100.0
DMC = developing member country, PTL = program team leader.
PTL comment: Things are really changing as a result of RBL. After years of policy stagnation government is now addressing challenges.
Source: Independent Evaluation Department.
18. Satisfaction Rating of the RBL Program
44. Overall, 85% of DMC clients are satisfied with the outcomes and benefits so far of the RBL
Program. Likewise, 79% of PTLs expressed overall satisfaction with the RBL program.
Appendix, Linked Document 6
19
19. DMC Clients’ Satisfaction Rating of ADB’s Efforts and Performance
45. All DMC government respondents rated ADB’s RBL-related efforts and performance in providing
support to the country’s RBL Program, “satisfactory,” of which more than half (58%) gave a rating of
“very satisfactory” (Table A6.37).
Table A6.36. Satisfaction or Dissatisfaction of the RBL Program
Central Governments
Executing and
Implementing
Agencies
All DMC
Clients PTLs Total
No. % No. % No. % No. % No. %
Very satisfied 2 25.0 8 32.0 10 30.3 4 28.6 14 29.8
Somewhat satisfied 6 75.0 12 48.0 18 54.5 7 50.0 25 53.2
Neither satisfied nor
dissatisfied 0 0.0 3 12.0 3 9.1 1 7.1 4 8.5
Somewhat dissatisfied 0 0.0 0 0.0 0 0.0 1 7.1 1 2.1
Very dissatisfied 0 0.0 0 0.0 0 0.0 0 0.0 0 0.0
Don’t know 0 0.0 2 8.0 2 6.1 1 7.1 3 6.4
Total 8 100.0 25 100.0 33 100.0 14 100.0 47 100.0
DMC = developing member country, PTL = program team leader.
PTL Comment: “Somewhat dissatisfied”—There is no accountability, there is no buying in by the borrower, unless there are dedicated and
assigned individuals, the expected results can’t be achieved through the system.
Source: Independent Evaluation Department.
Table A6.37. DMC Clients’ Satisfaction Rating of ADB’s RBL Efforts and Performance
Central Governments
Executing and
Implementing Agencies All DMC Clients
No. % No. % No. %
Very satisfactory 4 50.0 15 60.0 19 57.6
Somewhat satisfactory 4 50.0 8 32.0 12 36.4
Neither satisfactory nor
unsatisfactory 0 0.0 2 8.0 2 6.1
Somewhat unsatisfactory 0 0.0 0 0.0 0 0.0
Very unsatisfactory 0 0.0 0 0.0 0 0.0
Don't know 0 0.0 0 0.0 0 0.0
Total 8 100.0 25 100.0 33 100.0
DMC = developing member country.
Executing and implementing Agency comment: The efforts and performance of ADB in providing our country's RBL is very good indeed.
Thank you for these kind efforts.
Source: Independent Evaluation Department.
20. Effectiveness of ADB support and Strengthening of its Own Capacity to Design and
Implement RBL programs
46. In strengthening its own capacity to design and implement RBL programs, only a few PTLs (14%)
believe that ADB has provided “extremely/very effective” support (Table A6.38). On the other hand, 21%
of PTL respondents consider ADB support to be “slightly/not effective” and more than half (64%) as
“moderately effective” indicating there is a need for improvement in building ADB staff capacity in terms
of designing and implementing RBL programs.
Appendix, Linked Document 6
20
Table A6.38. Effectiveness of ADB Support and Strengthening of its Own Capacity
PTL
No. %
Extremely/very effective a 2 14.3
Moderately effective 9 64.3
Slightly/not effective 3 21.4
Don’t know 0 0.0
Total 14 100.0
PTL = program team leader.
a Comment: ADB is supporting staff well in this area.
Source: Independent Evaluation Department.