Upload
others
View
16
Download
0
Embed Size (px)
Citation preview
LIVE OAK COUNTYTRANSMISSION PROJECT
AEP Texas plans power grid upgrades to increase electric reliability
in Live Oak and Bee counties. The Live Oak County Transmission
Project involves building a 138-kilovolt power line and an electrical
substation to strengthen the local transmission system and add a
new power delivery source to the area.
PROJECT SCHEDULE
OPEN HOUSES IN THREE RIVERS AND BEEVILLEMay 22 - 23, 2017
CCN* APPLICATION FILED WITH PUCT*Spring 2019
PUCT EXPECTED TO DECIDE ON CCNSpring 2020
ROW* COMMUNICATIONS AND FIELD ACTIVITIES BEGINSpring 2020
FACILITIES PLACED IN SERVICELate 2022
CONSTRUCTION BEGINSSummer 2021
2017 2018 2020 20212019 20232022
The project, also known as the Three Rivers - Borglum - Tuleta Transmission Line Project, involves building a 138-kilovolt electric transmission line* to connect three AEP Texas substations:• The existing Three Rivers Substation located northeast of Three Rivers off of Highway 72 • A new Borglum Substation the company plans to build south of Beeville• The existing Tuleta Substation located near Highway 181 between Tuleta and Pettus
*AEP Texas hosted public open houses for the project in May 2017 to gather landowner input on potential route links for the power line. The Public Utility Commission of Texas (PUCT) determines a final route for the line.
The Electric Reliability Council of Texas (ERCOT), which monitors the regional transmis-sion system, endorsed this project in 2015 to address the need for better service reliability in the area.
AEP Texas submitted a Certificate of Conve-nience and Necessity application to the PUCT on April 5, 2019 to ask for approval to build the power line and new substation. The company expects to receive a decision from the PUCT by April 2020.
Following this approval:• AEP Texas notifies landowners who own property along the approved power line route. • Right-of-way agents begin contacting landowners to acquire necessary easements for the safe construction, operation and maintenance of the power line. • Construction begins in Summer 2021 and concludes in late 2022.
WHAT/WHERE WHY WHEN
*CCN: Certificate of Convenience and Necessity*CCN: Certificate of Convenience and Necessity*PUCT: Public Utility Commission of Texas*PUCT: Public Utility Commission of Texas*ROW: Right-of-Way*ROW: Right-of-Way
37
59
59
281
72
72
181
239
359
2441
798
SKIDMORESKIDMORE
THREE RIVERSTHREE RIVERS
PETTUSPETTUS
CHOKE CANYON RESERVOIRCHOKE CANYON RESERVOIR
LAKE CORPUS CHRISTILAKE CORPUS CHRISTI
BEEVILLEBEEVILLE
GOLIADGOLIAD
PAWNEEPAWNEE
REFU
GIO
COUN
TY
REFU
GIO
COUN
TY
BEE
COUN
TY
BEE
COUN
TY
LIVE
OAK
CO
UN
TYLI
VE O
AK C
OU
NTY
MC
MU
LLEN
CO
UN
TYM
CM
ULL
EN C
OU
NTY
LIVE OAK COUNTY
LIVE OAK COUNTY
BEE COUNTY
BEE COUNTY
BEE COUNTY
BEE COUNTY
GOLIAD COUNTY
GOLIAD COUNTY
*Exact structure, height and right-of-way requirements may vary
Typical Height: Approximately 90 - 110 feetTypical Distance between Structures: 600 feetTypical Right-of-Way Width: 100 feet
TYPICAL STRUCTURES
LIVE OAK COUNTY TRANSMISSION PROJECT
POTENTIAL ROUTE LINKSEXISTING TRANSMISSION LINE
EXISTING SUBSTATIONS
PROPOSED BORGLUM SUBSTATION
N
FOR MORE INFORMATION CONTACT:
04/04/201904/04/2019
PROJECT TEAM844-629-4296AEPTexas.com/LiveOak
BEEVILLEBEEVILLE
GOLIADGOLIAD
PAWNEEPAWNEE
THREE RIVERSTHREE RIVERS
CHOKE CANYON RESERVOIRCHOKE CANYON RESERVOIR
LAKE CORPUS CHRISTILAKE CORPUS CHRISTI
The route links are preliminary line segmentsdeveloped following a field review and initialreview of environmental and social constraints.The input gathered from the presentation of these route links at the open house provides acomprehensive review for the PUCT in the CCNapplication. Not all route links will beconstructed. Rather, one route will be determined by the PUCT.
WHAT ARE ROUTE LINKS?