81
LOGAN WATER ALLIANCE ONLINE WATER QUALITY MONITORING SITES: DETAILED PLANNING TASK NUMBER: 90-12-38 FEBRUARY 2014

LOGAN WATER ALLIANCE ONLINE WATER … · ONLINE WATER QUALITY MONITORING SITES: DETAILED PLANNING ... 4.5 First Principle Cost Estimate ... Capital Works Cost Summary

  • Upload
    docong

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

LOGAN WATER ALLIANCE

ONLINE WATER QUALITY MONITORING SITES: DETAILED PLANNING

TASK NUMBER: 90-12-38

FEBRUARY 2014

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 2 of 55 Rev: 1

Approval Register

Date

Project Manager Submitted

Planning & Project Management Team Review

Program Review

Controlled Document – Change Register

Revision Section

Changed Change Description Initial Date

A All Draft Report SH 28/01/2014

B All Draft Report format SS 04/02/2014

C All Incorporate review comments SH 20/02/2014

1 All Format Final Report SS 24/02/2014

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 3 of 55 Rev: 1

TABLE OF CONTENTS

EXECUTIVE SUMMARY ................................................................................................................................. 8

1. INTRODUCTION ............................................................................................................................... 11

1.1 Objectives ...................................................................................................................................... 11

1.2 Scope ............................................................................................................................................. 11

1.3 Business Drivers ............................................................................................................................ 12

1.4 Stakeholder engagement ............................................................................................................... 12

2. PLANNING CONTEXT ...................................................................................................................... 13

2.1 Existing Situation ........................................................................................................................... 13

2.2 Previous Studies ............................................................................................................................ 14

2.3 Selection of Water Quality Monitoring sites ................................................................................... 16

3. METHODOLOGY .............................................................................................................................. 18

3.1 Risk Assessment for disposal of instrumentation water ................................................................ 19

4. ASSUMPTIONS ................................................................................................................................ 20

4.1 Water Quality Monitoring Parameters ........................................................................................... 20

4.2 Location of Water Quality Cabinets ............................................................................................... 21

4.3 Water Quality Instrumentation ....................................................................................................... 21

4.4 RTU Site Audits ............................................................................................................................. 21

4.5 First Principle Cost Estimate .......................................................................................................... 22

5. DETAILED PLANNING ..................................................................................................................... 23

5.1 WQI 03 - Spring Mountain Reservoir ............................................................................................. 23

5.1.1 Site Description .......................................................................................................................... 23

5.1.2 Risks and Opportunities ............................................................................................................. 24

5.1.3 Cost Estimate............................................................................................................................. 25

5.2 WQI 04 - Woodhill Reservoir ......................................................................................................... 26

5.2.1 Site Description .......................................................................................................................... 26

5.2.2 Risks and Opportunities ............................................................................................................. 27

5.2.3 Cost Estimate............................................................................................................................. 28

5.3 WQI 05 - Jimboomba Reticulation ................................................................................................. 29

5.3.1 Site Description .......................................................................................................................... 29

5.3.2 Risks and Opportunities ............................................................................................................. 30

5.3.3 Cost Estimate............................................................................................................................. 30

5.4 WQI 06 - Flagstone Reticulation .................................................................................................... 31

5.4.1 Site Description .......................................................................................................................... 31

5.4.2 Risks and Opportunities ............................................................................................................. 31

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 4 of 55 Rev: 1

5.4.3 Cost Estimate............................................................................................................................. 32

5.5 WQI 07 - Mundoolun Pump Station ............................................................................................... 33

5.5.1 Site Description .......................................................................................................................... 33

5.5.2 Risks and Opportunities ............................................................................................................. 34

5.5.3 Cost Estimate............................................................................................................................. 34

5.6 WQI 08 - Bethania Reticulation ..................................................................................................... 35

5.6.1 Site Description .......................................................................................................................... 35

5.6.2 Risks and Opportunities ............................................................................................................. 35

5.6.3 Cost Estimate............................................................................................................................. 36

5.7 WQI 09 - Springwood High Level Water Supply zone ................................................................... 37

5.7.1 Site Description .......................................................................................................................... 37

5.7.2 Risks and Opportunities ............................................................................................................. 37

5.7.3 Cost Estimate............................................................................................................................. 38

5.8 WQI 10 - Logan Village Reticulation .............................................................................................. 39

5.8.1 Site Description .......................................................................................................................... 39

5.8.2 Risks and Opportunities ............................................................................................................. 40

5.8.3 Cost Estimate............................................................................................................................. 41

5.9 WQI 11 - Windaroo Reticulation .................................................................................................... 42

5.9.1 Site Description .......................................................................................................................... 42

5.9.2 Risks and Opportunities ............................................................................................................. 42

5.9.3 Cost Estimate............................................................................................................................. 43

5.10 WQI 12 - Springwood Low Level Reservoir ................................................................................... 44

5.10.1 Site Description ...................................................................................................................... 44

5.10.2 Risks and Opportunities ......................................................................................................... 45

5.10.3 Cost Estimate......................................................................................................................... 46

6. CONCLUSION ................................................................................................................................... 47

6.1 Capital Works Program Implication ............................................................................................... 48

7. RECOMMENDATIONS ..................................................................................................................... 49

8. REFERENCES .................................................................................................................................. 50

FIGURES

Figure 2-1: Current Sites Remotely Monitored by LCC ................................................................................. 13

Figure 2-2: Proposed Sites to be Remotely Monitored by LCC ...................................................................... 15

Figure 3-1: Methodology ................................................................................................................................ 18

Figure 5-1: Proposed WQI 03 monitoring point at Spring Mountain Reservoir ............................................. 23

Figure 5-2: Future dosing arrangement ......................................................................................................... 24

Figure 5-3: WQI 04 at Woodhill Reservoir ..................................................................................................... 26

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 5 of 55 Rev: 1

Figure 5-4: WQI 05 sample point at Jimboomba ........................................................................................... 29

Figure 5-5: WQI 06 cabinet location at Flagstone 1 (SPS 78) Pump Station ................................................ 31

Figure 5-6: WQI 07 Cabinet Location, Mundoolun Pump Station ................................................................. 33

Figure 5-7: PRV/WQI 08 Cabinet location at Bethania ................................................................................. 35

Figure 5-8: WQI 09 cabinet location at Parfrey Road, Rochedale ................................................................ 37

Figure 5-9: WQI 10 sample point at Logan Village 1 Pump Station .............................................................. 39

Figure 5-10: WQI 11 cabinet location at Belivah ........................................................................................... 42

Figure 5-11: WQI 12 cabinet location at Springwood Low Level Reservoir ................................................... 44

TABLES

Table E-1: Capital Works Cost Summary ........................................................................................................ 9

Table 1-1: Key stakeholders .......................................................................................................................... 12

Table 2-1: Proposed Water Quality Monitoring Sites .................................................................................... 15

Table 2-2: Assessment of site criticality ....................................................................................................... 17

Table 5-1: WQI 03 Environmental Assessment ............................................................................................ 24

Table 5-2: Capital Cost estimate for WQI 03 ................................................................................................. 25

Table 5-3: Capital Cost estimate for WQI 04 ................................................................................................. 28

Table 5-4: WQI 05 Environmental Assessment ............................................................................................ 30

Table 5-5: Capital Cost estimate for WQI 05 ................................................................................................. 30

Table 5-6: WQI 06 Environmental Assessment ............................................................................................ 32

Table 5-7: Capital Cost estimate for WQI 06 ................................................................................................. 32

Table 5-8: Capital Cost estimate for WQI 07 ................................................................................................. 34

Table 5-9: WQI 08 Environmental Assessment ............................................................................................ 36

Table 5-10: Capital Cost estimate for WQI 08 ............................................................................................... 36

Table 5-11: WQI 09 Environmental Assessment .......................................................................................... 37

Table 5-12: Capital Cost estimate for WQI 09 ............................................................................................... 38

Table 5-13: WQI 10 Environmental Assessment .......................................................................................... 40

Table 5-14: Capital Cost estimate for WQI 10 ............................................................................................... 41

Table 5-15: WQI 11 Environmental Assessment .......................................................................................... 43

Table 5-16: Capital Cost estimate for WQI 11 ............................................................................................... 43

Table 5-17: WQI 11 Environmental Assessment .......................................................................................... 45

Table 5-18: Capital Cost estimate for WQI 12 ............................................................................................... 46

Table 6-1: Proposed sites for alternative release of instrumentation water .................................................. 47

Table 6-2: Capital Works Cost Summary ...................................................................................................... 48

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 6 of 55 Rev: 1

APPENDICES

Appendix A Risk Assessment

Appendix B Preliminary Design Drawings

Appendix C Environmental Assessment

Appendix D Cost Estimate

Appendix E POAR Meeting Minutes

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 7 of 55 Rev: 1

ABBREVIATIONS

ARMP Approved Risk Management Plan

CCP Critical Control Point

DBYD Dial Before You Dig

DN Nominal Diameter

DMA District Metered Area

HACCP Hazard Analysis and Critical Control Points

HV High Voltage

IDM Infrastructure Demand Model

I/O Input/Output

LCC Logan City Council

LV Low Voltage

LWA Logan Water Alliance

POAR Planning, Opportunity And Risk

PS Pump Station

QCP Quality Control Point

RTU Remote Telemetry Unit

SCADA Supervisory Control and Data Acquisition

SRWP Southern Regional Water Pipeline

WQ Water Quality

WTP Water Treatment Plant

WSZ Water Supply Zone

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 8 of 55 Rev: 1

EXECUTIVE SUMMARY

The Online Water Quality Monitoring Strategy (LWA, 2013) identified 12 sites where real-time water quality

monitoring could further enhance Logan City Council’s ability to monitor network water quality. Detailed

planning for ten of these sites has been addressed as part of this current detailed planning study, while two

sites are already being delivered by LWA as part of Work Package WP7635 - Travis Road Reservoir outlet

main.

There are 11 existing online water quality instruments within Logan North and Logan East; however, there is

only one instrument installed within the Logan South network. LCC currently relies upon manual sample

collection and laboratory testing to identify issues with water quality within Logan South, which typically takes

up to one week to identify and respond to any issues. This process limits Council’s ability to respond in a

timely manner to potentially critical events in the water supply network.

The Online Water Quality Management Strategy (LWA Task 90-11-48) identified beneficial locations for

sampling within the LCC water supply area to improve the real time collection of water quality data, and also

reviewed parameters for monitoring. The parameters to be monitored at the proposed sites include:

pH

Temperature

Free Chlorine

Total Chlorine

Nitrate (3 sites).

A review of instrumentation suppliers was undertaken in this current study to determine equipment

availability and cost based on formal quotes from suppliers and has refined instrumentation costs and

specific equipment requirements for the proposed monitoring sites. Detailed planning has been undertaken

for each site by examining constraints and opportunities to determine the preferred location of the water

quality (WQ) cabinet. An environmental, town planning, cultural heritage assessment and a first principles

cost estimate were also undertaken for the sites.

Concept layout plans showing cabinet and conduit locations have been prepared for each of the sites based

on a detailed assessment of the known risks and constraints.

The key findings of this study are:

In general there was minimal constraint for the installation of the water quality monitoring cabinets at

each of the proposed sites. There were no environmental or town planning approval issues which

would prevent installation of the WQ cabinets at any of the sites. Audits of existing remote telemetry

units (RTU) should be undertaken to confirm spare I/O capacity in the RTU.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 9 of 55 Rev: 1

A key constraint pertains to the release of the instrumentation water generated, where this water

cannot be disposed of to a sewer asset. Release of water for irrigation was preferred where no

sewer disposal exists, and a site specific risk assessment will be undertaken for sites where release

to a stormwater asset is proposed.

There is the potential to realise cost savings in the delivery of two of the proposed sites (WQI 08 and

WQI 11) by combining the delivery of the WQ cabinets in conjunction with works to be undertaken as

part of the Logan East DMA work package, WP 7634.

Table E-1 provides a summary of the capital works for the proposed monitoring sites.

Table E-1: Capital Works Cost Summary

CWP ID Site Name Cost Estimate ($2013)

WQI 03 Spring Mountain Reservoir $49,000

WQI 04 Woodhill Reservoir $43,900

WQI 05 Jimboomba Reticulation $49,100

WQI 06 Flagstone Reticulation $42,100

WQI 07 Mundoolun Pump Station $43,200

WQI 08 Bethania Reticulation $47,9001

WQI 09 Rochedale South Reticulation $55,400

WQI 10 Logan Village Reticulation $47,800

WQI 11 Windaroo Reticulation $47,1001

WQI 12 Springwood Low Level Reservoir $81,500

DELIVERY Sub total $507,000

Design and Work Package Project Management $83,0002

Project Fee and Contingency $104,400

TOTAL $694,400

1. Sites can be delivered through WP7634

2. Includes LCC costs

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 10 of 55 Rev: 1

Based on the outcomes of this study LWA recommends:

1. LCC proceed with detailed design and delivery of the following sites:

WQI 03 – Spring Mountain

WQI 05 – Jimboomba Reticulation

WQI 06 – Flagstone Reticulation

WQI 07 – Mundoolun Reticulation

WQI 09 – Rochedale Reticulation

WQI 10 – Logan Village Reticulation

WQI 12 – Springwood Low Level Reservoir

2. WQI 08 and WQI 11 are delivered through the Logan East DMA work package WP7634 to realise the

potential delivery savings

3. The delivery of WQI 04 is investigated in conjunction with installation of a new chlorine booster station

at the site to realise potential delivery savings

4. The Project Brief for “Logan South Disinfection Project (W003)” is updated to reflect the current

capital cost estimates

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 11 of 55 Rev: 1

1. INTRODUCTION

Water utilities must not only respond to regulatory requirements, but also satisfy consumer demand for

drinking water of a consistently high quality. A water quality strategy that includes remote monitoring of the

network can provide water utilities with the ability to proactively manage the risks associated with the supply

of potable water and meet both of these business needs.

Since 2010, Logan City Council (LCC) has invested significantly in active management projects targeting

improvements in water quality. One aspect which has been identified is the significant gap in the availability

of real-time water quality data at critical points within the network. Currently, LCC relies on manual sample

collection and laboratory testing which typically takes up to a week to identify issues. This method does not

achieve appropriate response times to potentially critical events in the water network which may adversely

impact customer health, and limits the ability of operations staff to make real time adjustments to the

network.

Remote water quality monitoring can address some of these issues and provide additional benefits,

including:

early warning of changes in source water quality by monitoring specific or surrogate parameters

enhanced ability to meet increasingly strict regulatory requirements

reducing chemical dosing costs by optimizing and continuously monitoring and regulating the chemical

dosing and operational performance of the network

maintaining customer confidence by transparent reporting on the water quality within the network

1.1 Objectives

The objective of this current Task is to undertake a detailed planning investigation for the installation of

online water quality monitoring instrumentation at ten sites within the Logan water supply network.

1.2 Scope

The scope of this Task is as follows:

Undertake site visits to identify constraints/opportunities for proposed monitoring sites

Review existing infrastructure, operational feasibility (such as power and radio telemetry), site

constraints, approvals, environment, community and constructability issues

Undertake a first principles cost estimate

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 12 of 55 Rev: 1

1.3 Business Drivers

The main Business Drivers for this study are:

improving the Levels of Service by improving the identification and response times to water quality

issues in the network (Improvement)

informing discussions with Seqwater regarding bulk water quality and treatment optimisation

(Improvement)

to assist with achieving compliance with regulatory requirements outlined in Australian Drinking Water

Guidelines (Compliance)

1.4 Stakeholder engagement

The stakeholder engagement process for this study includes:

A start-up meeting with all stakeholders held on 13th September 2013

A Planning, Opportunity and Risk (POAR) workshop held on 2nd

December 2013

An 80% completion Task presentation with all stakeholders held on 22nd

January 2013

Program review of the draft deliverables

Informal and ongoing consultation with various stakeholders, as required

Table 1-1 lists the key stakeholders for this project and their respective areas of interest.

Table 1-1: Key stakeholders

Section Stakeholder Areas of Interest

Infrastructure Planning

Sandy Stewart Impacts on capital works program

Interaction with other planning tasks Tracey Leslie

Water Product Quality

Chris Pipe-Martin Understanding potential impacts on customers

Understanding potential water quality improvement activities Natasha Georgius

Operations Branch Darshan Udayaratna Impacts on the operation of the disinfection assets

Understanding potential water quality improvement activities

Capital Program Development

Maria Thomsen Impacts on the capital works program

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 13 of 55 Rev: 1

2. PLANNING CONTEXT

Since 2010, LCC has invested significantly in active management projects targeting improvements in water

quality. This strategy has identified a significant gap in the availability of real-time water quality data at critical

points within the network. In addition, the time-consuming nature of manual sample collection and laboratory

testing does not facilitate an appropriate response time to potentially critical events in the water network that

may adversely impact customer health, and limits the ability of operations staff to make real time adjustments

to the network.

2.1 Existing Situation

Figure 2-1 illustrates the Water Quality sampling locations currently monitored by LCC.

Figure 2-1: Current Sites Remotely Monitored by LCC

Figure 2-1 shows that the existing sites are predominantly located throughout Logan North. Monitoring sites

within Logan East at the Logan River Pump Station and Wuraga reservoir are both new monitoring sites

installed in 2013 as part of Emergent Task WP7709. Logan South, with the exception of Pub Lane Reservoir

site, has historically been monitored with manual sample collection and laboratory analysis. This manual

sampling, in conjunction future network operating arrangements, was used to identify priority locations for

online monitoring.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 14 of 55 Rev: 1

2.2 Previous Studies

The Logan Water Alliance (LWA) recently completed an Online Water Quality Monitoring Strategy (LWA,

2013). This report identified the need for:

Two (2) monitoring sites to control the process loop of an existing disinfectant dosing facility located

at:

o WQI03 - Spring Mountain reservoir

o WQI04 - Woodhill reservoir

Eight (8) monitoring sites to monitor areas with historical water quality issues located at:

o WQI05 - St Jude Circuit, Jimboomba

o WQI06 - Homestead Drive, Flagstone

o WQI07 - Mundoolun pump station

o WQI08 - Black Diamond Crescent, Bethania

o WQI09 - Parfrey Road, Rochedale South

o WQI010 - Logan Village

o WQI011 - Bannockburn Road, Windaroo

o WQI012 - Springwood low level reservoir.

Two further monitoring points (WQI 01 and WQI 02) were identified in the Online Water Quality Monitoring

Strategy at Travis Road Reservoir. The design of these two sampling locations was included with planned

works at the reservoir associated with construction of a new outlet main. This monitoring equipment is

currently being delivered by LWA under work package (WP) 7635 and is not included in the scope of the

current study.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 15 of 55 Rev: 1

Figure 2-2 illustrates the proposed online WQ sampling sites.

Figure 2-2: Proposed Sites to be Remotely Monitored by LCC

The monitoring objective for each of the proposed sites was determined through consultation with key LCC

stakeholders for the Online Water Quality Monitoring Strategy, and is outlined in Table 2-1.

Table 2-1: Proposed Water Quality Monitoring Sites

CWP ID Monitoring Site Sampling Location Business Case

WQI03 Spring Mountain Reservoir

Reservoir Inlet / Outlet Will monitor the performance of the existing dosing facility.

WQI04 Woodhill Reservoir Reservoir Outlet Will provide control signals for the onsite dosing equipment.

WQI05 Cerina Circuit, Jimboomba

Reticulation Monitoring only of water quality at the western extent of the Travis Road Reservoir WSZ

WQI06 Blueberry Ash Court, Flagstone

Reticulation Will monitor the water quality coming from the Round Mountain reservoir supply.

WQI07 Mundoolun pump station Reticulation Will monitor the water quality in the southern areas of the Logan South water supply zone.

WQI08 Black Diamond Crescent, Bethania

Reticulation - Co-locate with DMA58 PRV

Will monitor the water quality in the western areas of the Logan East water supply zone.

WQI09 Parfrey Rd, Rochedale South

Reticulation - Co-located at either DMA 14 Inlet 2 or DMA 15 Inlet 2

Will monitor the water quality in the northern areas of the Springwood High water supply zone.

WQI10 Logan Village Reticulation Will monitor the water quality in the Logan Village area.

WQI11 Bannockburn Rd, Windaroo

Reticulation – Co-locate with DMA62 PRV

Will monitor the water quality in the southern areas of the Logan east water supply zone.

WQI12 Springwood Low Level Reservoir

Reservoir Outlet Will monitor the water quality in the central areas of the Springwood Low water supply zone near the Springwood Low Level Reservoir.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 16 of 55 Rev: 1

The Online Water Quality Monitoring Strategy identified that the capital expenditure for these sites is

estimated at $500,000. These costs have been developed using the results of market surveys and

construction costs from recently-undertaken projects of a similar nature.

The LCC Capital Works Program includes $600,000 allocated for the proposed monitoring sites under CWP

item W0003.

2.3 Selection of Water Quality Monitoring sites

Water Quality throughout a water supply zone can vary depending on a number of factors, including

seasonal demand changes, flow reversals, storage size and distance from the supply source. To be able to

capture the changes in water quality that can occur within a zone, sampling locations can include the

following general locations:

within a reservoir

inlet and outlets of reservoirs

within the reticulation or at network extremities

within a trunk main or at a pump station

upstream and downstream of chemical dosing locations

points in the zone with a historical record of water quality incidents

The selection of a site for online monitoring was based on a combination of historical grab sample data,

consultation with operations staff, existing site infrastructure, cost and using hydraulic modelling to assist in

the decision making process where necessary.

Sites were classified either as a Critical Control Point (CCP) or Quality Control Point (QCP) in accordance

with Hazard Analysis and Critical Control Point (HACCP) categorisation of each selected site.

A CCP is a point where control can be applied that prevents, eliminates or reduces exceedances of a critical

water quality parameter incident in a timely manner; whereas a QCP is a site where only limited or no real-

time action can take place to reduce or prevent a water quality issue from occurring.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 17 of 55 Rev: 1

Table 2-2 outlines the HACCP classification of criticality for the monitoring sites.

Table 2-2: Assessment of site criticality

CWP ID Site Name CCP/QCP

WQI 03 Spring Mountain Reservoir QCP*

WQI 04 Woodhill Reservoir QCP*

WQI 05 Jimboomba Reticulation QCP

WQI 06 Flagstone Reticulation QCP

WQI 07 Mundoolun Pump Station QCP

WQI 08 Bethania Reticulation QCP

WQI 09 Rochedale South Reticulation QCP

WQI 10 Logan Village Reticulation QCP

WQI 11 Windaroo Reticulation QCP

WQI 12 Springwood Low Level Reservoir QCP

Note: WQI 03 and WQI 04 will be considered a CCP where dosing equipment is installed in future

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 18 of 55 Rev: 1

3. METHODOLOGY

The methodology adopted for this Task is outlined in Figure 3-1:

Figure 3-1: Methodology

Review and familiarisation

• Review the background data and information

• Hold a start-up workshop with key stakeholders

• Confirm business drivers

• Confirm the parameters to be monitored at each site

• Develop layout of each site

• Undertake site visit to identify constraints/opportunities with LCC

Operations to determine preferred monitoring location

Options development

• Formulate option through consultation LCC Water Quality and LCC

Operations

• Review critical factors affecting the project including town planning,

environmental, cultural heritage and land acquisition

• Undertake first principles estimate of cost for all sites

• Undertake a risk assessment for the disposal of instrumentation water

Option evaluation and reporting

• Undertake Planning Opportunity and Risk (POAR) workshop with LCC

Water Quality, LCC Asset Management and LCC Operations

• Finalise drawings based on outcomes of POAR workshop

• Prepare draft and final reports

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 19 of 55 Rev: 1

3.1 Risk Assessment for disposal of instrumentation water

Potable water release to the stormwater network was highlighted as a restricted activity and is regulated by

the Environmental Protection Act 1994 (EP Act, the Act).

Section 319 of the EP Act, subsection (1) prescribes that:

'A person must not carry out any activity that causes, or is likely to cause, environmental harm unless the

person takes all reasonable and practicable measures to prevent or minimise the harm (the general

environmental duty).'

Subsection (2) outlines the measures which must be regarded as part of a persons' general environmental

duty. This includes consideration of the following:

a) the nature of the harm or potential harm

b) the sensitivity of the receiving environment

c) the current state of technical knowledge for the activity

d) the likelihood of successful application of the different measures that might be taken

e) the financial implications of the different measures as they would relate to the type of activity

A preliminary risk assessment was undertaken for the release of potable water at sites where release to

sewer was not possible. The risk assessment for the release of potable water to the stormwater network as

part of this current study considers:

the likelihood and impact to the receiving environment/s

the alternative measures that can be taken to avoid release to stormwater

the cost of these alternatives

The risk assessment is provided in Appendix A.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 20 of 55 Rev: 1

4. ASSUMPTIONS

This chapter outlines the various assumptions used in this study, such as the monitoring parameters, basis

for site location, site requirements and assumptions used for developing first principles cost estimates.

4.1 Water Quality Monitoring Parameters

The water quality instrumentation required for each of the priority sites was outlined in the Online Water

Quality Management Strategy. At the start up meeting for this current Task, an additional requirement to

monitor free chlorine and total chlorine at all sites was added in anticipation of the conversion of water

supplies to chlorinated supply for all of South East Queensland (currently under consideration by Seqwater

(Bulk water supply authority)). The allocation of space within the new water quality monitoring cabinets (at a

minimum) will ensure the easy integration of future instrumentation for monitoring free chlorine residual.

Additionally, this will ensure online monitoring is available to control operational and disinfection

management activities, ie breakpoint chlorination.

The adopted parameters to be measured at each site are as follows:

pH

Temperature

Free Chlorine

Total Chlorine

In addition to these four parameters, Nitrate measurement was identified as an indicator for monitoring for

nitrification episodes in the distribution network. Nitrification in chloraminated water systems can lead to

depleted disinfectant levels and consequently increased biological contamination, as a result of improved

conditions for biofilm growth within water mains. Nitrate measurement was added to two sites within Logan

North and one site in Logan South, namely:

Springwood Low Level reservoir outlet (WQI 12)

within Springwood High level water supply zone (WSZ) (WQI 09)

within Travis Road (Jimboomba) WSZ (WQI 06)

These sites will provide monitoring of nitrification levels in the bulk water supply entering the network from

Kuraby reservoir and at a point in the supply zone.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 21 of 55 Rev: 1

4.2 Location of Water Quality Cabinets

The location of the proposed water quality sampling cabinets was determined by assessing locations:

near existing LCC Remote Terminal Unit (RTU) sites for ease of connection to Telemetry and mains

power supply

near existing wastewater assets for ease of discharge of instrumentation water

in part of the network that is able to meet the location objectives outlined in the Online Water Quality

Management Strategy.

4.3 Water Quality Instrumentation

The selection criteria for water quality instrumentation were based upon minimising operator maintenance

and chemical reagent requirements. It was agreed among the POAR workshop attendees that where

possible, monitoring equipment not requiring reagents be preferentially adopted, as this will minimise

ongoing costs, and reduce disposal requirement and OHS handling concerns that may otherwise be

associated with reagent handling and use.

The key criteria considered for selecting the preferred equipment supplier was based on:

Cost

Ability of supplier to provide instrumentation required to monitor the designated parameters

Equipment required and resulting layout of instrumentation within cabinet

Sensor/Equipment life

Maintenance and calibration requirements

Amount of water generated requiring release.

Other criteria included the availability of a turnkey supplied cabinet that would enable installation by Logan

City Council Operations staff. A supplier shortlist was developed to meet these needs.

4.4 RTU Site Audits

Audit of the proposed sites was identified at the POAR workshop to be undertaken during detailed design, in

order to determine availability of spare I/O for connection of the WQ instrumentation to existing RTUs and

ensure that incorporation of the proposed instrumentation can be achieved at the existing site.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 22 of 55 Rev: 1

4.5 First Principle Cost Estimate

The following assumptions were used to develop the cost estimates for the proposed monitoring sites.

Project Management costs were developed based on the following:

o Project Duration - 5 Weeks (for the construction works and installation of eight sites)

o Project Manager, Project Engineer - 2 hour/day

o Site Supervision - 4 hours/day

Instrumentation costs were developed based on formal quote requests from instrumentation

suppliers. The instrumentation costs reflected the specific instrumentation requirements for each site

Commissioning costs have been estimated based on costs provided for similar projects

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 23 of 55 Rev: 1

5. DETAILED PLANNING

The following section outlines specific requirements for the individual monitoring sites. A description of each

site is provided outlining specific site constraints, risks and opportunities. A cost estimate has also been

compiled for each site based on first principle cost estimates for the civil component of works, supplier

quotes, installation and commissioning of the proposed monitoring cabinets.

5.1 WQI 03 - Spring Mountain Reservoir

5.1.1 Site Description

This location was selected as a Quality Control Point at the extremity of the network and will monitor any

decline of disinfection residual within Spring Mountain reservoir. Approximately 26% of existing monthly

sample readings indicate inadequate disinfection levels (below 0.2 mg/L) as reported in laboratory sampling

data from the site (LWA, 2012). This site will be considered a Critical Control Point (CCP) should a new

chlorine booster station be installed; however, the decision to implement a booster station will be informed by

the proposed online monitoring at Spring Mountain.

The proposed monitoring point is on the combined inlet-outlet main to the reservoir. There is an existing

tapping on the main which was previously used as a rechlorination point - this tapping can be reused,

minimising the installation requirements for the sampling line. The WQ cabinet can be located adjacent to a

disused dosing building, and a conduit can be installed to provide connection to the RTU for the site, which is

located adjacent to the reservoir. Figure 5-1 shows the proposed location of the WQ cabinet while the

concept layout plan for the site is provided in Drawing 90-12-38-S-DWG-CI-2002 of Appendix B.

Figure 5-1: Proposed WQI 03 monitoring point at Spring Mountain Reservoir

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 24 of 55 Rev: 1

5.1.2 Risks and Opportunities

Environmental/Approval constraints

A review of environmental factors has highlighted some risks for this site, as summarised in Table 5-1, while

the complete Environmental Risk Assessment in provided in Appendix C. As the site for the proposed WQ

cabinet is on already cleared land, there is no risk of disturbance to native vegetation.

Table 5-1: WQI 03 Environmental Assessment

Issue Comment Action

Presence of Fire Ants Site is mapped within a high risk fire ant area

Movement of restricted items in compliance with approved risk management plan (ARMP)

Bush fire Site mapped as a Medium Risk bushfire hazard area

Management required during construction

Discharge of Instrumentation Water

There is no nearby wastewater infrastructure to allow disposal of the instrumentation water. It was agreed in

discussion with LCC representatives that the preferred means of discharging the instrumentation water is via

irrigation. Section 3.1 outlines the risk assessment process undertaken for sites where no opportunity exists

to discharge the instrumentation water to a wastewater asset.

Integration with Dosing control

As the proposed monitoring site is likely to be integrated with a future dosing facility, provision should be

made for incorporating the monitoring equipment to provide a feedback control loop with the dosing system

as outlined in Figure 5-2.

Figure 5-2: Future dosing arrangement

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 25 of 55 Rev: 1

5.1.3 Cost Estimate

Table 5-2 outlines the cost estimate for instrumentation supply, construction and integration into the existing

SCADA system by a sub-contractor. The detailed first principle cost estimate is provided in Appendix D. A

provisional sum has been designated for the installation of a sprinkler/sub-surface irrigation system should

stormwater release via soak away be deemed environmentally unacceptable. This will be subject to a risk

assessment undertaken during detailed design in conjunction with LCC prior to construction.

Table 5-2: Capital Cost estimate for WQI 03

Item Capital Cost ($2013)

Water Quality Instrumentation $12,000

Civil construction items $25,400

SCADA integration and commissioning $1,000

Sprinkler System for irrigation of discharge water (provisional sum) $6,000

Indirect costs* $4,600

Total $49,000

*Includes Design and Environmental Group project management and defects liability allowance

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 26 of 55 Rev: 1

5.2 WQI 04 - Woodhill Reservoir

5.2.1 Site Description

This location was selected as a quality control point at the network extremity, where low disinfection levels

have previously been observed. Approximately 30% of analysed lab samples were observed to have

disinfection levels less than 0.2 mg/L (LWA, 2012). This site will be considered a Critical Control Point upon

completion of a new chlorine booster station, which is currently being installed. The proposed monitoring

equipment must be capable of integrating with future dosing equipment to provide feedback control for future

dosing.

This location will monitor chlorine residual on the outlet of Woodhill reservoir. The instrumentation cabinet

can be installed in the new pump station building. During the site investigations, the new pump set was not

installed, later being commissioned on the 17th January 20141. A new tapping is proposed at the existing

sampling location, and discharge is proposed to connect to the stormwater outlet from the reservoir site. This

will be subject to a risk assessment undertaken during detailed design in conjunction with LCC prior to

construction. Should a risk assessment determine the proposed stormwater disposal is untenable, a

subsurface irrigation system will be installed to water the grassed area at the reservoir site.

Figure 5-3 shows the existing pump station building, while the concept layout plan for the site is provided in

Drawing 90-12-38-S-DWG-CI-2004 of Appendix B. As noted, further field verification is required to determine

the WQ cabinet location within the pump station building.

Figure 5-3: WQI 04 at Woodhill Reservoir

1 Advice provided by LCC Water Operations

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 27 of 55 Rev: 1

5.2.2 Risks and Opportunities

Environmental/Approval constraints

As the water quality monitoring cabinet is proposed within the existing pump station building there is no risk

of disturbance to native vegetation or public amenity with the proposed installation.

Discharge of Instrumentation Water

There is no nearby wastewater infrastructure to allow disposal of the instrumentation water. It was agreed

that the preferred means of discharging the instrumentation water is via the existing stormwater drain for the

reservoir site, which flow toward a stormwater drain in a nearby property. The alternative means of discharge

is subsurface or sprinkler system irrigation. Section 3.1 outlines the risk assessment process undertaken for

sites where no opportunity exists to discharge the instrumentation water to a wastewater asset.

Integration with Dosing control

As the proposed monitoring site will be integrated with a future dosing facility, provision should be made for

incorporating the monitoring equipment to provide a feedback control loop with the dosing system as outlined

in Figure 5-2. Equipment selection should specify these requirements between monitoring and future dosing

equipment.

Installation with future dosing unit

There is potential to realise cost savings by incorporating the installation of an online water quality monitoring

cabinet within the future chlorine booster station to be installed at the site.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 28 of 55 Rev: 1

5.2.3 Cost Estimate

Table 5-3 outlines the cost estimate for instrumentation supply, construction and integration into the existing

SCADA system by a sub-contractor. The detailed first principle cost estimate is provided in Appendix D. A

provisional sum has been designated for the installation of a sprinkler/sub-surface irrigation system should

stormwater release via soak away be deemed environmentally unacceptable. This will be subject to a risk

assessment undertaken during detailed design in conjunction with LCC prior to construction.

Table 5-3: Capital Cost estimate for WQI 04

Item Capital Cost ($2013)

Water Quality Instrumentation $12,000

Civil construction items $20,300

SCADA integration and commissioning $1,000

Sprinkler System for irrigation of discharge water $6,000

Indirect costs* $4,600

Total $43,900

*Includes Design and Environmental Group project management and defects liability allowance

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 29 of 55 Rev: 1

5.3 WQI 05 - Jimboomba Reticulation

5.3.1 Site Description

This location was selected as a quality control point within the Travis Road WSZ and will monitor disinfection

residual at the extents of this zone subject to high water age. Water sampling in the Jimboomba area of

Travis Road WSZ includes disinfection levels below 0.2 mg/L in approximately 20% of historical data from

July 2010 to December 2011 (LWA, 2012).

The proposed instrumentation cabinet will be located at the Jimboomba 6 (SPS 80) wastewater pump station

at Cerina Circuit, Jimboomba. There is an existing potable supply to the pump station from which a sample

tapping point can be installed, while discharge of the instrumentation water is to the adjacent pump station

wet well.

Figure 5-4 shows the proposed location of the WQ cabinet and existing RTU, while the concept layout plan

for the site is provided in Drawing 90-12-38-S-DWG-CI-2003 of Appendix B.

Figure 5-4: WQI 05 sample point at Jimboomba

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 30 of 55 Rev: 1

5.3.2 Risks and Opportunities

A review of environmental factors has highlighted some risks for this site, as summarised in Table 5-4, while

the complete Environmental Risk Assessment is provided in Appendix C. As the site for the proposed WQ

cabinet is on already cleared land within the pump station area, there is no risk of disturbance to native

vegetation.

Table 5-4: WQI 05 Environmental Assessment

Issue Comment Action

Presence of Fire Ants Site is mapped within a high risk fire ant area

Movement of restricted items in compliance with approved risk management plan (ARMP)

Public Amenity Site is adjacent to residential properties

Adequate odour, noise and visual impact mitigation measures must be implemented during design, construction and operation.

Land Protection (Pest and Stock Route Management) Act

Presence of declared pest plants within alignment

A field investigation is required prior to construction to identify declared pest plants and define mitigation

Potable water supply

The potable water sampling point may be sourced from the backflow prevention device pipework installed

adjacent to the RTU at the pump station, rather than from the potable water main in front of the pump station,

which will minimise pipework requirements for connection. This connection should be confirmed in

conjunction with Logan City Council Water Operations representatives.

5.3.3 Cost Estimate

Table 5-5 outlines the cost estimate for instrumentation supply, construction and integration into the network.

The detailed first principle cost estimate is provided in Appendix D.

Table 5-5: Capital Cost estimate for WQI 05

Item Capital Cost ($2013)

Water Quality Instrumentation $19,000

Civil construction items $24,500

SCADA integration and commissioning $1,000

Indirect costs* $4,600

Total $49,100

*Includes Design and Environmental Group project management and defects liability allowance

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 31 of 55 Rev: 1

5.4 WQI 06 - Flagstone Reticulation

5.4.1 Site Description

This location was selected as a quality control point for monitoring the outgoing water quality from Round

Mountain reservoir within Flagstone. The water age through Round Mountain reservoir from the proposed

New Beith Road SRWP offtake will likely increase in the early years of supply to lower Logan South,

compared to the existing supply arrangement. Funds were allocated under Capital Works item W0003 -

Logan South Disinfection Project for a future dosing station at Round Mountain reservoir which will utilise

readings from the proposed water quality instrumentation in Flagstone for trim dosing purposes.

Figure 5-5 shows the proposed location of the WQ cabinet at the Flagstone 1 wastewater pump station at

Blueberry Ash Court (SPS 78), while the concept layout plan for the site is provided in Drawing 90-12-38-S-

DWG-CI-2005 of Appendix B.

Figure 5-5: WQI 06 cabinet location at Flagstone 1 (SPS 78) Pump Station

5.4.2 Risks and Opportunities

Environmental/Approval constraints

A review of environmental factors has highlighted some risks for this site, as summarised in Table 5-6, while

the complete Environmental Risk Assessment is provided in Appendix C. As the site for the proposed WQ

cabinet is on already cleared land, there is no risk of disturbance to native vegetation.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 32 of 55 Rev: 1

Table 5-6: WQI 06 Environmental Assessment

Issue Comment Action

Presence of Fire Ants Site is mapped within a high risk fire ant area

Movement of restricted items in compliance with approved risk management plan (ARMP)

Nature Conservation Act Clearing/trimming of any native regrowth adjacent works

Further assessment required once scope defined to determine the presence/absence of any threatened species or breeding places

Land Protection (Pest and Stock Route Management) Act

Presence of declared pest plants within alignment

A field investigation is required prior to construction to identify declared pest plants and define mitigation

Public Amenity Site is adjacent to residential properties

Adequate odour, noise and visual impact mitigation measures must be implemented during design, construction and operation.

Potable Water Supply

The potable water sampling point may be sourced from the backflow prevention device pipework installed

adjacent to the RTU at the pump station, rather than from the potable water main which runs in front of the

pump station, which will minimise pipework requirements for connection. This connection should be

confirmed in conjunction with Logan City Council Water Operations representatives.

Switchboard Capacity

An audit of the existing RTU should be undertaken during detailed design to confirm RTU capacity or

determine whether expansion of I/O capacity for the RTU is required.

5.4.3 Cost Estimate

Table 5-7 outlines the cost estimate for instrumentation supply, construction and integration into the existing

water supply network. The detailed first principle cost estimate is provided in Appendix D.

Table 5-7: Capital Cost estimate for WQI 06

Item Capital Cost ($2013)

Water Quality Instrumentation $12,000

Civil construction items $24,500

SCADA integration and commissioning $1,000

Indirect costs* $4,600

Total $42,100

*Includes Design and Environmental Group project management and defects liability allowance

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 33 of 55 Rev: 1

5.5 WQI 07 - Mundoolun Pump Station

5.5.1 Site Description

This location was selected as a quality control point within the Razorback/Mundoolun WSZ. Supply to the

zone is from the South Maclean clear water tanks. Historical sample data in the July 2010 to December 2011

sample period indicates that approximately 60% of samples contained inadequate disinfection levels (LWA,

2012).

The water quality instrumentation can be installed within the Mundoolun water pump station building, utilising

a spare tapping point on the common suction main. There is sufficient space available to mount an

instrumentation cabinet on the wall adjacent to the pump set and utilise underfloor conduits back to the

switchboard and RTU for connection of power and telemetry.

Discharge of water from the instrumentation cabinet is proposed by irrigation. The land adjacent to the pump

station is currently under an infrastructure agreement between LCC and a developer - this may provide for

discharge of the instrumentation water to an adjacent public recreation space. This arrangement should be

facilitated with Logan City Council Development Assessment Services. A decision will also be required in

determining asset maintenance responsibilities within Council.

Figure 5-6 shows the proposed location of the WQ cabinet and existing RTU, while the concept layout plan

for the site is provided in Drawing 90-12-38-S-DWG-CI-2007 of Appendix B. Note that the discharge line

shown in this figure is based on the assumption that a tank for storing water for irrigation purposes is

installed in front of the pump station, between the vehicle roller door and entry door on the western side of

the building. The exact siting and feasibility of tank location can only be determined following further

negotiation with the developer at a later date.

Figure 5-6: WQI 07 Cabinet Location, Mundoolun Pump Station

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 34 of 55 Rev: 1

5.5.2 Risks and Opportunities

A review of environmental factors has highlighted that the site is located within a high risk fire ant area, with

the appropriate measures for notification of Biosecurity Queensland to be undertaken in conjunction with the

subcontractors' Approved Risk Management Plan (ARMP). The complete Environmental Risk Assessment in

provided in Appendix C.

Discharge of Instrumentation Water

There is no nearby wastewater infrastructure to allow disposal of the instrumentation water. The only location

available for discharging this instrumentation water is the adjacent developer held land. There may be

opportunity for further negotiation with the developer to allow for discharge to the adjacent land for

irrigation/watering purposes. Should no arrangement be forthcoming, investigation must be made into the

release to a sub-surface soak away pit, as there is no planted vegetation at the site which can be irrigated.

This will be subject to a risk assessment undertaken during detailed design in conjunction with LCC prior to

construction.

Connection of sampling point with suction pipework

It was assumed that the water sampling point can be connected to a blanked off tapping on the common

suction main of the pump sets. Detailed design should confirm that no excess positive/negative pressures

are imparted on the sensor equipment, which are limited to 0.5 bar (50 kPa). Pressure head is typically

broken within the flow assembly which houses the sensor; however, the proposed arrangement should be

confirmed with the equipment manufacturer at detailed design.

5.5.3 Cost Estimate

Table 5-8 outlines the cost estimate for instrumentation supply, construction and integration into the existing

water supply network. The detailed first principle cost estimate is provided in Appendix D.

Table 5-8: Capital Cost estimate for WQI 07

Item Capital Cost ($2013)

Water Quality Instrumentation $12,000

Civil construction items $19,600

SCADA integration and commissioning $1,000

Sprinkler System for irrigation of discharge water $6,000

Indirect costs* $4,600

Total $43,200

*Includes Design and Environmental Group project management and defects liability allowance

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 35 of 55 Rev: 1

5.6 WQI 08 - Bethania Reticulation

5.6.1 Site Description

This location was selected as a quality control point at the extent of the Logan East WSZ. This location will

monitor chlorine residual downstream of Woodhill reservoir. This site will be established in conjunction with a

proposed District Metered Area (DMA 58), which is part of LWA Work Package 7634 - Logan East Water

Supply DMA Management and Fire Flow Augmentations. This work package is currently in detail design with

construction scheduled to commence in January 2014.

The water quality instrumentation is proposed to be installed in a combined control cabinet with the PRV

instrumentation. The cabinet location will be confirmed as part of the design for work package 7634. A

sample line is proposed from within the PRV pit, and there is an adjacent sewer manhole for discharging the

instrumentation water. Mains power supply will be sourced from a street pole in Black Diamond Crescent.

Figure 5-7 shows the proposed location of the WQ cabinet, PRV pit and RTU, while Drawing 7634-004-W-

DWG-CI-2050 REV D in Appendix B shows the concept layout plan for this site.

Figure 5-7: PRV/WQI 08 Cabinet location at Bethania

5.6.2 Risks and Opportunities

An Environmental and Approval assessment has identified minimal risks for construction. The proposed

installation is in already cleared land. The identified risks are outlined in Table 5-9.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 36 of 55 Rev: 1

Table 5-9: WQI 08 Environmental Assessment

Issue Comment Action

Presence of Groundwater The site is at low elevation (10m AHD) and is located near Logan River

Groundwater is to be captured and tested prior to disposal

Presence of Fire Ants Site is mapped within a low risk fire ant area

Movement of restricted items in compliance with approved risk management plan (ARMP)

Public Amenity Site is adjacent to residential properties

Adequate odour, noise and visual impact mitigation measures must be implemented during design, construction and operation.

PRV pit and Cabinet location

Detailed design should ensure that the PRV pit location is such that conduit lengths can be minimised where

possible. In addition, the adjacent property contains a pool and the cabinet should be located in a position

such that the cabinet cannot be used to gain access to the fenced pool area. Discussions should also be

progressed with the property owner regarding the final location of the cabinet.

5.6.3 Cost Estimate

Table 5-10 outlines the cost estimate for supplier instrumentation and supply, construction and integration

into the existing water supply network. Cost efficiencies can be obtained if the WQ equipment is installed in

conjunction with the PRV site, given there will be minimal additional cost for the installation of WQ equipment

(the only additional scope item being the discharge line for instrumentation water).

As such, costing for this item is presented with and without project delivery in conjunction with work package

WP7634 (Logan East DMA sites), demonstrating the potential cost savings if delivered under the TOC

budget for work package 7634. Note that there would be a minor variation to the WP7634 TOC to

accommodate this additional scope.

The detailed first principle cost estimate is provided in Appendix D.

Table 5-10: Capital Cost estimate for WQI 08

Item Capital Cost ($2013) Capital Cost ($2013)*

- WP7634 delivery

Water Quality Instrumentation $12,000 $12,000

Civil construction cost (additional scope to WP7634) $30,300 $8,000

SCADA integration and commissioning* $1,000 $0

Indirect costs* $4,600 $0

Total $47,900

$20,000

* Cost efficiencies assumed under combined delivery with WP 7634

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 37 of 55 Rev: 1

5.7 WQI 09 - Springwood High Level Water Supply Zone

5.7.1 Site Description

This location was selected as a quality control point within the Springwood High Level Water Supply Zone to

monitor the decay in disinfection residual between this location and water supplied from Springwood Low

Level Reservoir. This location will monitor disinfection residual as well as Nitrate, which will serve as an

indicator for nitrification occurring in the network.

The proposed cabinet location is alongside the existing PRV installation at Parfrey Road, Rochedale

(opposite Gills Close). A sample point tapping is proposed on the DN250 supply main to the PRV zones

(DMA14 and DMA15), while power and telemetry can be supplied from the PRV cabinets. A stormwater gully

inlet pit is available to discharge the instrumentation water; however, if this arrangement is untenable the

discharge line can be directed across the road into the nearest sewer manhole (at front of 23 Parfrey Road).

Figure 5-8 shows the proposed location of the WQ cabinet and existing RTU, while the concept layout plan

for the site is provided in Drawing 90-12-38-S-DWG-CI-2000 of Appendix B.

Figure 5-8: WQI 09 cabinet location at Parfrey Road, Rochedale

5.7.2 Risks and Opportunities

Environmental and Approvals Assessment

The risk assessment undertaken for the site has identified the following risks, as outlined in Table 5-11.

Table 5-11: WQI 09 Environmental Assessment

Issue Comment Action

Presence of Fire Ants Site is mapped within a high risk fire ant area

Movement of restricted items in compliance with approved risk management plan (ARMP)

Public Amenity Site is adjacent to residential properties

Adequate odour, noise and visual impact mitigation measures must be implemented during design, construction and operation.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 38 of 55 Rev: 1

Discharge of Instrumentation Water

There is no adjacent sewerage infrastructure to allow disposal of the instrumentation water. It was agreed in

discussion with LCC representatives that the preferred means of discharging the instrumentation water is to

the stormwater drain, which will minimise site installation costs resulting from traffic management and road

crossings. If this is not tenable, the discharge line can be directed to the sewer manhole at the front of the

opposite property at 23 Parfrey Road.

5.7.3 Cost Estimate

Table 5-12 outlines the summary cost estimate for instrumentation supply, construction and integration into

the existing water supply network. The detailed first principle cost estimate is provided in Appendix D.

Table 5-12: Capital Cost estimate for WQI 09

Item Capital Cost ($2013)

Water Quality Instrumentation $19,000

Civil construction items $30,800

SCADA integration and commissioning $1,000

Indirect costs* $4,600

Total $55,400

*Includes Design and Environmental Group project management and defects liability allowance

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 39 of 55 Rev: 1

5.8 WQI 10 - Logan Village Reticulation

5.8.1 Site Description

This location was selected as a quality control point at the extent of the Travis Road Reservoir WSZ in Logan

Village. Disinfection residuals within the Logan Village area were found to be the worst in Logan South, with

approximately 74% of monthly disinfection grab samples in the July 2010 - December 2011 sample period

containing inadequate levels of disinfection (levels below 0.2 mg/L). A new dosing facility is currently being

designed as part of the Work Package 7635 Travis Road Reservoir outlet main which will see an

improvement in the disinfection residuals in Logan Village.

The proposed water quality monitoring instrumentation location is adjacent to the Logan Village 1 (SPS 70)

wastewater pump station. A new potable supply is required at the pump station (none currently available),

which will improve facilities at the pump station for cleaning/pump maintenance, and will also provide a

sample water source.

The existing RTU is installed on a raised platform above the Q100 flood level, hence the WQ cabinet has

been proposed on the existing platform. A preliminary assessment of the platform has confirmed the WQ

cabinet can be located on the platform in at least two locations adjacent to the existing RTU; however,

should be confirmed during detailed design when exact cabinet dimensions and constraints are known.

Figure 5-9 shows the proposed location of the WQ cabinet and existing RTU, while the concept layout plan

for the site is provided in Drawing 90-12-38-S-DWG-CI-2008 of Appendix B.

Figure 5-9: WQI 10 sample point at Logan Village 1 Pump Station

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 40 of 55 Rev: 1

5.8.2 Risks and Opportunities

The environmental risk assessment undertaken for the site has identified the following risks, as outlined in

Table 5-13.

Table 5-13: WQI 10 Environmental Assessment

Issue Comment Action

Presence of Fire Ants Site is mapped within a low risk fire ant area

Movement of restricted items in compliance with approved risk management plan (ARMP)

Public Amenity Site is adjacent to residential properties

Adequate odour, noise and visual impact mitigation measures must be implemented during design, construction and operation.

Installation of Cabinet on existing raised RTU platform

A preliminary assessment of the raised platform suggests that sufficient space is available for the installation

of the WQ cabinet. Provision has been made in the cost estimate for the modification (if necessary) of the

raised platform should there be insufficient space; alternatively, the WQ cabinet could be located adjacent to

the existing platform on a new cabinet stand if the cabinet cannot be co-located on the existing platform.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 41 of 55 Rev: 1

5.8.3 Cost Estimate

Table 5-14 outlines the summary cost estimate for instrumentation supply, construction and integration into

the existing water supply network. The detailed first principle cost estimate is provided in Appendix D.

Table 5-14: Capital Cost estimate for WQI 10

Item Capital Cost ($2013)

Water Quality Instrumentation $12,000

Civil construction items $30,200

SCADA integration and commissioning $1,000

Indirect costs* $4,600

Total $47,800

*Includes Design and Environmental Group project management and defects liability allowance

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 42 of 55 Rev: 1

5.9 WQI 11 - Windaroo Reticulation

5.9.1 Site Description

This location was selected as a quality control point at the extremity of the Logan East network. The site is

proposed as part of a new DMA installation (DMA 62) at Bannockburn Road, Belivah. A combined PRV and

WQ cabinet is proposed for the site in the road reserve in Bannockburn Road. Power supply will be subject

to Energex approval, while new telemetry will be installed for the PRV.

Instrumentation water can be released into the gravity sewer main which runs parallel to the proposed PRV

installation. Figure 5-10 shows the proposed location of the WQ cabinet and existing RTU, while the concept

layout plan for the site is provided in Drawing 7634-005-W-DWG-CI-2020-REV G of Appendix B.

Figure 5-10: WQI 11 cabinet location at Belivah

5.9.2 Risks and Opportunities

A review of environmental factors has highlighted some risks for this site, as presented in Table 5-15, while

the complete Environmental Risk Assessment in provided in Appendix C. As the site for the proposed WQ

cabinet is on already cleared land, there is no risk of disturbance to native vegetation.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 43 of 55 Rev: 1

Table 5-15: WQI 11 Environmental Assessment

Issue Comment Action

Nature Conservation Act Clearing/trimming of any native regrowth adjacent works

Further assessment required once scope defined to determine the presence/absence of any threatened species or breeding places

Land Protection (Pest and Stock Route Management) Act

Presence of declared pest plants within alignment

A field investigation is required prior to construction to identify declared pest plants and define mitigation

Public Amenity Site is adjacent to residential properties

Adequate odour, noise and visual impact mitigation measures must be implemented during design, construction and operation.

Risk of Vehicular Collision

The PRV installation is located adjacent to the roadway, and is therefore at risk of collision from vehicles.

Detailed design should seek to maximise the distance from the roadway. It may be feasible to locate the

PRV/WQ RTU cabinet behind the adjacent power pole. This will be determined in conjunction with necessary

clearances as required by the electricity provider. In addition bollards can also be considered in the cabinet

design to reduce damage from collision.

5.9.3 Cost Estimate

Table 5-16 outlines the cost estimate for supplier instrumentation and supply, construction and integration

into the existing water supply network. Cost efficiencies can be obtained if the WQ equipment is installed in

conjunction with the PRV site, given there will be minimal additional cost for the installation of WQ

equipment.

As such, costing for this item is presented with and without project delivery in conjunction with work package

WP7634 (Logan East DMA sites), demonstrating the potential cost savings if delivered under the TOC

budget for work package 7634. Note that there would be a minor variation to the WP7634 TOC to

accommodate this additional scope.

The detailed first principle cost estimate is provided in Appendix D.

Table 5-16: Capital Cost estimate for WQI 11

Item Capital Cost ($2013)* Capital Cost ($2013)*

- Delivery via WP 7634

Water Quality Instrumentation $12,000 $12,000

Civil construction items* $29,500 $8,000

SCADA integration and

commissioning* $1,000 $0

Indirect costs* $4,600 $0

Total $47,100 $20,000

* Cost efficiencies assumed under combined delivery with WP 7634

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 44 of 55 Rev: 1

5.10 WQI 12 - Springwood Low Level Reservoir

5.10.1 Site Description

This location was selected as a quality control point at the outlet from Springwood Low Level Reservoir. This

site will be monitored in conjunction with the WQI 09 site in Rochedale, specifically monitoring for residual

decay in the Springwood High Level Zone (HLZ). The proposed sampling point is on the DN600 outlet of the

reservoir, which, in addition to comparing residual decay between Springwood Low Level zone and

Springwood HLZ, will also enable comparison with the upstream monitoring point at Compton Road.

There is existing telemetry at the reservoir site located within the Springwood Low Level Pump Station. The

WQ cabinet should be located near the outlet main as indicated in Figure 5-11 to minimise sample line

length. This will require laying approximately 60-70m of buried conduit to provide power and telemetry to the

cabinet.

Figure 5-11 shows the proposed location of the WQ cabinet, while the concept layout plan for the site is

provided in Drawing 90-12-38-S-DWG-CI-2001 of Appendix B.

Figure 5-11: WQI 12 cabinet location at Springwood Low Level Reservoir

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 45 of 55 Rev: 1

5.10.2 Risks and Opportunities

The review of environmental factors has highlighted some risks for this site, as presented in Table 5-17,

while the complete Environmental Risk Assessment is provided in Appendix C. As the site for the proposed

WQ cabinet is on already cleared land, there is no risk of disturbance to native vegetation.

Table 5-17: WQI 11 Environmental Assessment

Issue Comment Action

Presence of Fire Ants Site is mapped within a high risk fire ant area

Movement of restricted items in compliance with approved risk management plan (ARMP)

Bush fire Site mapped as a Medium Risk bushfire hazard area

Management required during construction

Steep Slopes Site is adjacent to a steep slope area To be considered and managed during design and construction

Discharge of Instrumentation Water

There is no nearby wastewater infrastructure to allow disposal of the instrumentation water. It was agreed in

discussion with LCC representatives that the preferred means of discharge is via the existing stormwater

outlet from the reservoir site. Section 3.1 outlines the risk assessment process undertaken for sites where no

opportunity exists to discharge the instrumentation water to a wastewater asset. This arrangement will be

subject to a risk assessment required during detailed design in conjunction with LCC prior to construction.

Bushfire Hazard

The site is directly adjacent to a medium hazard bushfire area. The proposed location of the WQ cabinet

exposes the cabinet to risk of equipment loss in the event of bushfire. Remedial measures include providing

additional fire protection for the cabinet, and where possible locating the cabinet closer to the reservoir wall.

This should be further investigated during detailed design.

Future Reservoir integration

The Springwood Low Level Reservoir is comprised of two separate sections, one of which is currently offline.

The location of the proposed sampling point should ensure (where feasible) that provision is made for

sampling the second reservoir compartment when brought back online in the future.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 46 of 55 Rev: 1

5.10.3 Cost Estimate

Table 5-18 outlines the cost estimate for instrumentation supply, construction and integration into the existing

water supply network. First principle cost estimates for this site are higher compared to other sites as a result

of the length of trenching required for installation of power/telemetry conduits.

The detailed first principle cost estimate is provided in Appendix D.

Table 5-18: Capital Cost estimate for WQI 12

Item Capital Cost ($2013)

Water Quality Instrumentation $19,000

Civil construction items $56,900

SCADA integration and commissioning $1,000

Indirect costs* $4,600

Total $81,500

*Includes Design & Environmental Group project management and defects liability allowance

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 47 of 55 Rev: 1

6. CONCLUSION

This detailed planning study outlines the site specific requirements for the installation of ten additional water

quality sites throughout the Logan District. The requirements are based on a preliminary site assessment for

the proposed cabinet locations, and an assessment of the environmental, cultural heritage and approvals

requirements for each of the sites. An estimated cost to install the monitoring equipment at each site has

been developed from first principle cost estimates.

The proposed monitoring sites will serve to improve the real time management of the water supply network,

further enabling a proactive response to issues related to changes in water quality, rather than relying on

manual sampling and laboratory testing. The real-time monitoring will also enhance LCC's ability to respond

rapidly to events which may adversely affect customer health.

This detailed planning study has determined that:

There are minimal constraints for the installation of the water quality monitoring cabinets at each of

the proposed sites. There are no environmental ‘show stoppers’ or town planning approval issues

which would prevent installation of the WQ cabinets at any of the sites.

Audits of existing RTUs should be undertaken to confirm spare I/O capacity in each existing RTU

The release of the instrumentation water cannot be disposed of to a sewer asset at all proposed

sites. Release of water for irrigation was preferred where no sewer disposal exists, and a site

specific risk assessment will need to be undertaken during detailed design for sites where release to

a stormwater asset is proposed. Where the residual risk of disposal to stormwater is considered low

with no risk to the receiving environment as a result of chlorine residual, and the cost of alternative

release is prohibitive, it is recommended that disposal to the stormwater assets should proceed as

outlined in Table 6-1.

Table 6-1: Proposed sites for alternative release of instrumentation water

ID Site Name Proposed Release Mechanism

WQI 03 Spring Mountain Reservoir Irrigation

WQI 04 Woodhill Reservoir Irrigation

WQI 07 Mundoolun Water Pump Station Irrigation

WQI 09 DMA 14/15 PRV site Stormwater drain

WQI 12 Springwood Low Level Reservoir Stormwater drain

There is the potential to realise cost savings in the delivery of two of the proposed sites (WQI 08 and

WQI 11) by combining the delivery of the WQ cabinets in conjunction with works to be undertaken as

part of the Logan East DMA work package, WP 7634.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 48 of 55 Rev: 1

6.1 Capital Works Program Implication

Table 6-2 provides a summary of the capital costs for delivery of this project. These costs have been

developed from first principle cost estimates. A detailed breakdown of these costs is provided in Appendix D.

Table 6-2: Capital Works Cost Summary

CWP ID Site Name Cost Estimate ($2013)

WQI 03 Spring Mountain Reservoir $49,000

WQI 04 Woodhill Reservoir $43,900

WQI 05 Jimboomba Reticulation $49,100

WQI 06 Flagstone Reticulation $42,100

WQI 07 Mundoolun Pump Station $43,200

WQI 08 Bethania Reticulation $47,9001

WQI 09 Rochedale South Reticulation $55,400

WQI 10 Logan Village Reticulation $47,800

WQI 11 Windaroo Reticulation $47,1001

WQI 12 Springwood Low Level Reservoir $81,500

DELIVERY Sub total $507,000

Design and Work Package Project Management $83,0002

Project Fee and Contingency $104,400

TOTAL $694,400

1. Potential cost savings can be realised with combined delivery with Logan East DMA project, Work Package 7634 2. Includes LCC costs

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 49 of 55 Rev: 1

7. RECOMMENDATIONS

The Logan Water Alliance recommends that:

1. LCC proceed with detailed design and delivery of the following sites:

WQI 03 – Spring Mountain

WQI 05 – Jimboomba Reticulation

WQI 06 – Flagstone Reticulation

WQI 07 – Mundoolun Reticulation

WQI 09 – Rochedale Reticulation

WQI 10 – Logan Village Reticulation

WQI 12 – Springwood Low Level Reservoir

2. WQI08 and WQI11 are delivered in conjunction with the Logan East DMA work package WP7634 to

realise the potential delivery savings

3. The delivery of WQI 04 is investigated in conjunction with installation of a new chlorine booster station

at the site to realise potential delivery savings

4. The Project Brief for “Logan South Disinfection Project (W003)” is updated to reflect the current

capital cost estimates.

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 50 of 55 Rev: 1

8. REFERENCES

Logan City Council, 2012, LCC Docs #8063117 COM-56-2008 Infrastructure Agreement for Jimboomba

Woods estate water supply infrastructure

Logan Water Alliance 2012, Logan South Disinfection Project Scoping - Planning Report (Task 90-11-43)

Logan Water Alliance 2013a, Online Water Quality Monitoring Strategy - Planning Report (Task 90-11-48)

Logan Water Alliance 2013b, Logan East Water Supply DMA Management and Fire Flow Augmentations

Detailed Planning - Planning Report (Task 90-11-92)

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 51 of 55 Rev: 1

Appendix A Risk Assessment

Logan Water Alliance Risk Register90-12-38

PROJECT: 90-12-38 Online Water Quality Priority 1 and 2 sites 1-4: Low Risk DATE: 30/01/2014

PREPARED BY: Simon Hawkes 5-9: Medium Risk

RISK AREA: Environment 10-14: Significant Risk

REVISION: Revision A 15-25: High Risk

OPTION DESCRIPTION: Risks associated with alternative release options

Likelihood Consequence Risk Score (L x C) Risk Rating Likelihood

(1-5)Consequence

(1-5)Risk Score

(L x C) Risk Rating

WQI 03 Spring Mountain Reservoir IrrigationInstrumentation water will run off to the natural environment adjacent to the reservoir site if no control measures are provided.

2 - Unlikely 2 - Minor 4 Low

- Overland flow would most likely be absorbed to subsurface within a short distance of the release point. Typical disinfectant concentration levels anecdotally have little impact to turf, elevated levels (up to 5 mg/l) would likely have negligible effect.

1. Proposed release at Spring Mountain is to sub surface irrigation. There is approximately 300m2 of adjacent grassed area which could receive irrigation.

Irrigation system - provisional sum

of $5000. 1 - Rare 1 -

Insignificant 1 Low

WQI 07 Mundoolun Water Pump Station Irrigation

Instrumentation water will ultimately drain to the upper reaches of Henderson Creek, linked by a series of manmade and natural dams which presumably join up via ephemeral streams during rainfall. Otherwise runoff will be absorbed into the subsurface. Distance to first manmade channel is approximately 130 m.

2 - Unlikely 2 - Minor 4 Low

- Overland flow will most likely be absorbed to subsurface within a short distance of the release point. - Instrumentation water may not be absorbed if the ground is saturated.- The impact of disinfectant concentration levels on any native fauna is unknown.

1. The pump station is adjacent to future development. There may be potential to release water from the instrumentation for irrigation of open space in the future development estate.

Irrigation system - provisional sum

of $5000. 1 - Rare 1 -

Insignificant 1 Low

WQI 12 Springwood Low Level Reservoir Stormwater drain

The preferred release is to the stormwater drain at the reservoir. This drains to a stormwater headwall at the bottom of the adjacent embankment, approx. 150m away.This stormwater drains to Slacks Creek approximately 1.5 km away

2 - Unlikely 2 - Minor 4 Low

- The existing stormwater drain discharges to a energy dissipating device on the adjacent slope, upstream of the connection with the stormwater headwall at the top of the stormwater network. This would serve to increase turbulence and provide significant air stipping action to free chlorine residual, which in turn would serve to reduce or elimate disinfection residual.

1. Dechlorination mats (need to confirm suitability) could be used at the release point to the stormwater drain.2.There is a proxy location for this site on the outlet main downstream of the site, where release to sewer is possible. This site however would require a new RTU installation, and has not been assessed for radio signal at this location.

1. Alternative site - approx. $15-

20K 2. Dechlorination

mats - ??

1 - Rare 1 - Insignificant 1 Low

WQI 04 Woodhill Reservoir IrrigationThe reservoir scour/stormwater drains to an adjacent property (however the ultimate fate of this water in unknown)

2 - Unlikely 2 - Minor 4 Low

- The ultimate fate of discharge from the reservoir scour drain on the adjacent property is unknown. It is noteworthy that the existing scour valve leaks at a rate which appears greater than the proposed instrumentation water release.

1. This site is suitable for subsurface irrigation with sufficient grassed area in the reservoir site for irrigation

Irrigation system - provisional sum

of $5000. 1 - Rare 1 -

Insignificant 1 Low

WQI 09 DMA 14/15 PRV site Stormwater drainThe site drains via the stormwater network (approx. 1.5 km) to the upper reaches of the Tingalpa Creek catchment.

2 - Unlikely 2 - Minor 4 Low- There is a signficant length of stormwater drain which will likely decay the disinfection residual as a result of the organic demand in the stormwater drain/grass swale.

1. Dechlorination mats (need to confirm suitability) could be used at the release point to the stormwater drain.

Dechlorination mats ?? 1 - Rare 1 -

Insignificant 1 Low

WQI 11 DMA 62 PRV Site Stormwater drain

The site drains via stormwater pipes and open swales to a series of manmade lakes adjacent Windaroo golf course, approx. 400m away. These manmade lakes ultimately drain to Logan River.

2 - Unlikely 2 - Minor 4 Low

- Instrumentation water will likely absorb to the sub surface within a short distance.- Instrumentation water may not be absorbed if the ground is saturated.- There will likely be decay of the disinfection residual as a result of the organic demand in stormwater drain/grass swale.

1. Dechlorination mats (need to confirm suitability) could be used at the release point to the stormwater drain.

Dechlorination mats ?? 1 - Rare 1 -

Insignificant 1 Low

Status

Project Risk Register

Reference Site Description of release Receiving Environment

Existing Risk Score (Untreated/Unmitigated)Comments on existing status with NO mitigation New mitigation/contingency measures

(describe activities ) OwnerCost of

Mitigation/ Contingency

Risk Scoring after treatment/mitigation

Priority

Project Risk RegisterSite Risk Assessment 30/01/2014 Page 1 of 1

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 52 of 55 Rev: 1

Appendix B Preliminary Design Drawings

PRELIMINARY

PRELIMINARY

PRELIMINARY

PRELIMINARY

PRELIMINARY

FOR TENDER

PRELIMINARY

PRELIMINARY

energex

FOR TENDER

PRELIMINARY

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 53 of 55 Rev: 1

Appendix C Environmental Assessment

TRIGGER/IMPACT ACTION

Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)

Significant impact on any Matter of National Environmental Significance (MNES) as defined by the EPBC Act.

Proposed works not likely to result in a significant impact on any MNES.

Vegetation Management Act 1999 (VM Act)

Clearance of remnant vegetation on any land tenure or clearance of non‐remnant vegetation on state land, unless an exemption applies.

The site is surrounded by remnant Least Concern RE12.9‐10.19, however there is no remnant RE likely to be cleared for the proposed works as they are generally located 

within cleared land adjacent to the existing reservoir. 

Due to recent exemptions in relation to clearing of native vegetation under the VM Act, no formal permits would be required under the VM Act for clearance of native vegetation for the works. The project is not expected to require clearance 

of native vegetation.

Nature Conservation Act 1992 (NC Act)

Clearing of native plants where assessable under the VM Act. Clearing or pruning of threatened plants listed under the provisions of the NC Act on any land tenure. Tampering with animal breeding places protected under the provisions of the NC 

Act.The works are located adjacent the existing reservoir and associated buildings within 

cleared land. 

This project is not expected to require any clearing of native plants. Should any clearing be required, further assessment would be required to verify the 

presence/absence of threatened species and identify any breeding places to be impacted by the works and advise on requirements. 

Land Protection (Pest and Stock Route Management) Act 2002

Presence of declared pest plants within the proposed alignment.

The works are located adjacent the existing reservoir and associated buildings within cleared land that is unlikely to support declared pest plants. Should pest plants be identified within or adjacent to the works area at a later stage, then measures to prevent spread shall be implemented in accordance with the EMP. 

South East Queensland Koala Conservation State Planning Regulatory Provisions (SPRP)

Clearing of non‐juvenile koala habitat trees within koala assessable development areas.

No action required ‐ site is not located within a koala assessable development area

Water Act 2000Works interfering with a waterway pursuant to the Water Act 2000 . Works will not interfere with surface water.

No action required ‐ works will not be in the bed or banks of the waterway

Fisheries Act 1994Works which will affect marine plants, waterways or declared Fish Habitat Areas relevant to the act. Works does not interfere  with waterways identified in the spatial data layer for Queensland waterways for waterway barrier works  (2013)

No action required ‐ work does not interfere with waterways. No marine plants are expected to be impacted by the works.

Coastal Protection and Management Act 1995 (Coastal Act)

Works requiring assessment and permit/s under the Queensland Coastal Plan. A search was undertaken on 19 December 2013 and the site is not  identified in the coastal management district or coastal hazard area. 

No action required ‐ site is not in coastal management district or coastal zone

Flood Regulated Area (planning scheme)Works within Flood and Inundation Area. A search of the LCC Flood Regulated Area Mapping was undertaken on 19 December 2013. The site is not in flood regulated area

No action required ‐ Site is not in the flood regulated area

Aboriginal Cultural Heritage Act 2003

The site is allocated a Category 4 ‐ (previously been subject to significant ground disturbance) under the Duty of Care Guidelines, given the installation of underground and aboveground services and disturbance due to the infrastructure on site, and the removal of vegetation, including the root ball. A search request was submitted on 19 December 2013 and no items were found on the register. The registered party is Jagera People #2

No items identified on the register. No consultation will be required prior to commencement of works within Category 4 areas . If any potential items are found during construction a 'stop work' will be required and consultation will need to be undertaken with the nominated Aboriginal parties of the area.

Non-indigenous cultural heritage (Queensland Heritage Act 1992 , planning scheme)

Works within an area with non‐Indigenous cultural heritage items. No non‐indigenous cultural heritage was recorded on the council's planning scheme map, Queensland Heritage Register or Australia Heritage database cited 19 December 2013. 

No action required ‐ stop works and consultation with the relevant party/ies if a potential cultural heritage item is discovered.

Acid sulphate soilsDisturbance/potential disturbance of acid sulphate soils (ASS). It is unlikely for ASS to be present onsite given that the area is at contours are 140m AHD.  No action required ‐ site not mapped as ASS area

WQI 03 - Spring Mountain Reservoir, Greenbank

Legislation/Issue

Groundwater (dewatering)Contamination to groundwater. Geotechnical investigation are not undertaken for the site. Limited information available. 

Limited information available. If found, groundwater to be captured and tested prior to  release into the environment (i.e. irrigation to grasslands). Further 

assessment required during design and construction.

Environmental Protection Act 1994 - contaminated land

Contamination offsite or health impacts. A search of the environmental management register (EMR) and contaminated land register (CLR) was undertaken on 20 November 2013. None of the lots are on EMR/CLR

No action required ‐ None of the lots are on EMR/CLR

Fire ants (Plant Protection Act 1989 )Movement of restricted items within and out of a high or low risk area. A search of the restricted area map was undertaken on 19 December 2013. The site is within high risk area

Movement of restricted items outside the restricted area must be in compliance with the subcontractors ARMP. Stop works and inform LWA and Biosecurity QLD 

of any potential Fire Ant citings.

Public amenity (odour, noise, visual impacts)

Works within public areas. Works not adjacent to residential area.No action required ‐ due to high vegetation surrounding the reservoir and the 

nature of the works. 

BushfireWorks causing or impacted by bushfires. The site is located within a Medium bushfire hazard area as shown in BSC  OV 3.1D. 

Site is mapped as Medium bushfire hazard area. Management required during construction 

Steep SlopesWorks within a steep slopes area. The site is  shown as a  Landslide hazard investigation area in Beaudesert shire council planning scheme mapping OV 3.2D.

Site mapped as investigation area. However due to the nature of the work this is unlikely to have any impact on the works

Unexploded ordnance (UXO's)Working within an area known or suspected of having been used for military activity and assessed as having potential UXO contamination. A search of the UXO database on 12 December 2013 indicated that the site is categorised as "Other" 

No action required ‐ Department of defence makes no recommendation in regards to this category. This is for information purpose only.  Stop works if a 

suspicious UXO item is found. Do not touch or disturb the item. Contact LWA and the Police.

The project works are located adjacent the existing reservoir and associated buildings within cleared land and are considered unlikely to require clearance of native plants. Nonetheless, the site is surrounded by remnant RE12.9‐10.19 which is considered to comprise significant ecological values to the broader area, including habitat for threatened species. Any design changes should be undertaken in a manner that avoids impacting on this vegetation and mitigation measures shall be employed during construction to ensure that this vegetation is adequately protected (i.e. all access and laydown areas shall avoid impacts on surrounding vegetation and an arborist shall be consulted for any works within the Tree Protection zone of adjacent vegetation).

Environmental summary (Ecological perspective)

Remnant vegetation surrounding the site

The site is considered to be in environmentally low risk area. The items that will need further assessment and management are Fire Ant, Bushfire hazard and potential groundwater

Environmental Summary (non ecological perspective)

TRIGGER/IMPACT ACTION

Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)

Significant impact on any Matter of National Environmental Significance (MNES) as defined by the EPBC Act.

Proposed works not likely to result in a significant impact on any MNES.

Vegetation Management Act 1999 (VM Act)Clearance of remnant vegetation on any land tenure or clearance of non‐remnant 

vegetation on state land, unless an exemption applies.There is no remnant RE located within or adjacent to the proposed works. 

Due to recent exemptions in relation to clearing of native vegetation under the VM Act, no formal permits would be required under the VM Act for clearance of native vegetation for the works. The project is not expected to require 

clearance of native vegetation.

Nature Conservation Act 1992 (NC Act)

Clearing of native plants where assessable under the VM Act. Clearing or pruning of threatened plants listed under the provisions of the NC Act on any land tenure. Tampering with animal breeding places protected under the provisions of the NC 

Act.The works are located adjacent the existing reservoir and associated buildings 

within cleared land. 

This project is not expected to require any clearing of native plants. Should any clearing be required, further assessment would be required to verify the 

presence/absence of threatened species and identify any breeding places to be impacted by the works and advise on requirements. 

Land Protection (Pest and Stock Route Management) Act 2002

Presence of declared pest plants within the proposed alignment.

The works are located adjacent the existing reservoir and associated buildings within cleared land that is unlikely to support declared pest plants. Should pest plants be identified within or adjacent to the works area at a later stage, then measures to prevent spread shall be implemented in accordance with the EMP. 

South East Queensland Koala Conservation State Planning Regulatory Provisions (SPRP)

Clearing of non‐juvenile koala habitat trees within koala assessable development areas.

No action required ‐ site is not located within a koala assessable development area

Water Act 2000Works interfering with a waterway pursuant to the Water Act 2000 . Works will not interfere with surface water.

No action required ‐ works will not be in the bed or banks of the waterway

Fisheries Act 1994Works which will affect marine plants, waterways or declared Fish Habitat Areas relevant to the act. Works does not interfere  with waterways identified in the spatial data layer for Queensland waterways for waterway barrier works  (2013)

No action required ‐ work does not interfere with waterways. No marine plants are expected to be impacted by the works.

Coastal Protection and Management Act 1995 (Coastal Act)

Works requiring assessment and permit/s under the Queensland Coastal Plan. A search was undertaken on 19 December 2013 and the site is not  identified in the coastal management district or coastal hazard area. 

No action required ‐ site is not in coastal management district or coastal zone

Flood Regulated Area (planning scheme)Works within Flood and Inundation Area. A search of the LCC Flood Regulated Area Mapping was undertaken on 19 December 2013. The site is not in flood regulated area

No action required ‐ Site is not in the flood regulated area

Aboriginal Cultural Heritage Act 2003

The site is allocated a Category 4 ‐ (previously been subject to significant ground disturbance) under the Duty of Care Guidelines, given the installation of underground and aboveground services and disturbance due to the infrastructure on site, and the removal of vegetation, including the root ball. A search request was submitted on 19 December 2013. The results did not identify any items on the register. This is no registered party or body for this site. 

 No consultation will be required prior to commencement of works (if no items are found on the register) within Category 4 areas . If any potential items are found during construction a 'stop work' will be required and consultation will 

need to be undertaken with the DATSIMA

Non-indigenous cultural heritage (Queensland Heritage Act 1992 , planning scheme)

Works within an area with non‐Indigenous cultural heritage items. No non‐indigenous cultural heritage was recorded on the council's planning scheme map, Queensland Heritage Register or Australia Heritage database cited 19 December 2013

No action required ‐ stop works and consultation with the relevant party/ies if a potential cultural heritage item is discovered.

Legislation/Issue

WQI 04 - Woodhill Reservoir

)2013. 

Acid sulphate soilsDisturbance/potential disturbance of acid sulphate soils (ASS). It is unlikely for ASS to be present onsite given that the area is at contours are 90m AHD.  No action required ‐ site not mapped as ASS area

Groundwater (dewatering)Contamination to groundwater. Geotechnical investigation are not undertaken for the site. Limited information available. 

Limited information available. If found, groundwater to be captured and tested prior to  release into the environment (i.e. irrigation to grasslands). Further 

assessment required during design and construction.

Environmental Protection Act 1994 - contaminated land

Contamination offsite or health impacts. A search of the environmental management register (EMR) and contaminated land register (CLR) was undertaken on 20 November 2013. None of the lots are on EMR/CLR

No action required ‐ None of the lots are on EMR/CLR

Fire ants (Plant Protection Act 1989 )Movement of restricted items within and out of a high or low risk area. A search of the restricted area map was undertaken on 19 December 2013. The site is outside the restricted area

No Action required. Site is not within fire ant restricted area

Public amenity (odour, noise, visual impacts)

Works within public areas. Works are adjacent to residential  premises. Adequate odour, noise and visual impact mitigation measures must be 

implemented during design, construction and operation.

BushfireWorks causing or impacted by bushfires. The site is not located within a bushfire hazard area as shown in BSC OV 3.1A. 

No action required ‐ site is not located within a bushfire hazard area.

Steep SlopesWorks within a steep slopes area. The site is not  shown as a  Landslide hazard investigation area in Beaudesert shire council planning scheme mapping OV 3.2A.

No action required ‐ site not shown in an area of  potential landslip hazard .

Unexploded ordnance (UXO's)

Working within an area known or suspected of having been used for military activity and assessed as having potential UXO contamination. A search of the UXO database on 12 December 2013 indicated that the site does not contain a known UXO contaminated area.

No action required ‐ site not shown to contain any known UXO. Stop works if a suspicious UXO item is found. Do not touch or disturb the item. Contact LWA 

and the Police.

Site mapped as non‐remnant vegetation

Environmental summary (Ecological perspective)

The project works are located adjacent the existing reservoir and associated buildings within cleared land and are considered unlikely to require clearance of native plants. Nonetheless, there are a number of mature trees within and adjacent to the broader site. Any design changes should be undertaken in a manner that avoids impacting on this vegetation and mitigation measures shall be employed during construction to ensure that this vegetation is adequately protected (i.e. all access and laydown areas shall avoid impacts on surrounding vegetation and an arborist shall be consulted for any works within the Tree Protection zone of adjacent vegetation).

pp g

Environmental Summary (non ecological perspective)

The site is considered to be in environmentally low risk area. The items that will need further assessment and management are Public Amenity and potential groundwater

TRIGGER/IMPACT ACTION

Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)

Significant impact on any Matter of National Environmental Significance (MNES) as defined by the EPBC Act.

Proposed works not likely to result in a significant impact on any MNES.

Vegetation Management Act 1999 (VM Act)Clearance of remnant vegetation on any land tenure or clearance of non‐remnant 

vegetation on state land, unless an exemption applies.There is no remnant RE located within or adjacent to the proposed works. 

Due to recent exemptions in relation to clearing of native vegetation under the VM Act, no formal permits would be required under the VM Act for clearance of native vegetation for the works. The project is not expected to require clearance 

of native vegetation.

Nature Conservation Act 1992 (NC Act)

Clearing of native plants where assessable under the VM Act. Clearing or pruning of threatened plants listed under the provisions of the NC Act on any land tenure. Tampering with animal breeding places protected under the provisions of the NC 

Act.The works are located adjacent the existing pump station within cleared land with a 

weedy groundcover. 

This project is not expected to require any clearing of native plants. Should any clearing be required, further assessment would be required to verify the 

presence/absence of threatened species and identify any breeding places to be impacted by the works and advise on requirements. 

Land Protection (Pest and Stock Route Management) Act 2002

Presence of declared pest plants within the proposed alignment.Prior to construction, a field investigation is required to identify any declared 

pest plants within the proposed works area and define mitigation requirements.

South East Queensland Koala Conservation State Planning Regulatory Provisions (SPRP)

Clearing of non‐juvenile koala habitat trees within koala assessable development areas.

No action required ‐ site is not located within a koala assessable development area

Water Act 2000Works interfering with a waterway pursuant to the Water Act 2000 . Works will not interfere with surface water.

No action required ‐ works will not be in the bed or banks of the waterway

Fisheries Act 1994Works which will affect marine plants, waterways or declared Fish Habitat Areas relevant to the act. Works does not interfere  with waterways identified in the spatial data layer for Queensland waterways for waterway barrier works  (2013)

No action required ‐ work does not interfere with waterways. No marine plants are expected to be impacted by the works.

Coastal Protection and Management Act 1995 (Coastal Act)

Works requiring assessment and permit/s under the Queensland Coastal Plan. A search was undertaken on 19 December 2013 and the site is not  identified in the coastal management district or coastal hazard area. 

No action required ‐ site is not in coastal management district or coastal zone

Flood Regulated Area (planning scheme)Works within Flood and Inundation Area. A search of the LCC Flood Regulated Area Mapping was undertaken on 19 December 2013. The site is not in flood regulated area

No action required ‐ Site is not in the flood regulated area

Aboriginal Cultural Heritage Act 2003

The site is allocated a Category 4 ‐ (previously been subject to significant ground disturbance) under the Duty of Care Guidelines, given the installation of underground and aboveground services and disturbance due to the infrastructure on site, and the removal of vegetation, including the root ball. A search request was submitted on 19 December 2013. The results did not identify any items on the register. This is no registered party or body for this site. 

 No consultation will be required prior to commencement of works (if no items are found on the register) within Category 4 areas . If any potential items are found during construction a 'stop work' will be required and consultation will 

need to be undertaken with the DATSIMA

Non-indigenous cultural heritage (Queensland Heritage Act 1992 , planning scheme)

Works within an area with non‐Indigenous cultural heritage items. No non‐indigenous cultural heritage was recorded on the council's planning scheme map, Queensland Heritage Register or Australia Heritage database cited 19 December 2013

No action required ‐ stop works and consultation with the relevant party/ies if a potential cultural heritage item is discovered.

Legislation/Issue

WQI 05 - Cerina Circuit, Jimboomba

2013. 

Acid sulphate soilsDisturbance/potential disturbance of acid sulphate soils (ASS). It is unlikely for ASS to be present onsite given that the area is at contours are 30m AHD.  No action required ‐ site not mapped as ASS area

Groundwater (dewatering)Contamination to groundwater. Geotechnical investigation are not undertaken for the site. Limited information available. 

Limited information available. If found, groundwater to be captured and tested prior to  release into the environment (i.e. irrigation to grasslands). Further 

assessment required during design and construction.

Environmental Protection Act 1994 - contaminated land

Contamination offsite or health impacts. A search of the environmental management register (EMR) and contaminated land register (CLR) was undertaken on 20 November 2013. None of the lots are on EMR/CLR

No action required ‐ None of the lots are on EMR/CLR

Fire ants (Plant Protection Act 1989 )Movement of restricted items within and out of a high or low risk area. A search of the restricted area map was undertaken on 19 December 2013. The site is within high risk area

Movement of restricted items outside the restricted area must be in compliance with the subcontractors ARMP. Stop works and inform LWA and Biosecurity QLD 

of any potential Fire Ant citings.

Public amenity (odour, noise, visual impacts)

Works within public areas. Works are adjacent to residential  premises. Adequate odour, noise and visual impact mitigation measures must be 

implemented during design, construction and operation.

BushfireWorks causing or impacted by bushfires. The site is not located within a bushfire hazard area as shown in BSC OV 3.1A. 

No action required ‐ site is not located within a bushfire hazard area.

Steep SlopesWorks within a steep slopes area. The site is not  shown as a  Landslide hazard investigation area in Beaudesert shire council planning scheme mapping OV 3.2A.

No action required ‐ site not shown in an area of  potential landslip hazard .

Unexploded ordnance (UXO's)

Working within an area known or suspected of having been used for military activity and assessed as having potential UXO contamination. A search of the UXO database on 12 December 2013 indicated that the site does not contain a known UXO contaminated area.

No action required ‐ site not shown to contain any known UXO. Stop works if a suspicious UXO item is found. Do not touch or disturb the item. Contact LWA and 

the Police.

Site mapped as non remnant vegetation

Environmental summary (Ecological perspective)

The project works are located adjacent the existing pump station within cleared land with a weedy groundcover and are considered unlikely to require clearance of native plants. Nonetheless, any design changes should be undertaken in a manner that avoids impacting on native vegetation and mitigation measures shall be employed during construction to ensure that adjacent vegetation is adequately protected (i.e. all access and laydown areas shall avoid impacts on surrounding vegetation and an arborist shall be consulted for any works within the Tree Protection zone of adjacent vegetation).No site assessment has been undertaken and prior to construction, a field investigation is required to identify any declared pest plants within the proposed works area and define mitigation requirements.

Site mapped as non‐remnant vegetation

Environmental Summary (non ecological perspective)The site is considered to be in environmentally low risk area. The items that will need further assessment and management are Public Amenity, Fire Ant and potential groundwater

TRIGGER/IMPACT ACTION

Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)

Significant impact on any Matter of National Environmental Significance (MNES) as defined by the EPBC Act.

Proposed works not likely to result in a significant impact on any MNES.

Vegetation Management Act 1999 (VM Act)

Clearance of remnant vegetation on any land tenure or clearance of non‐remnant vegetation on state land, unless an exemption applies.. 

There is remnant Endangered vegetation mapped to the south and west of the site, however there is no remnant RE likely to be cleared for the proposed works 

as they are generally located within disturbed land. 

Due to recent exemptions in relation to clearing of native vegetation under the VM Act, no formal permits would be required under the VM Act for 

clearance native vegetation for the works. Nonetheless, clearance of native vegetation should be limited to the minimum practical clearance.

Nature Conservation Act 1992 (NC Act)

Clearing of native plants where assessable under the VM Act. Clearing or pruning of threatened plants listed under the provisions of the NC Act on any land 

tenure. Tampering with animal breeding places protected under the provisions of the NC Act.

The works are located adjacent the existing pump station within cleared land with small patches of native regrowth adjacent to the works which may require 

clearing and/or trimming, although impacts are likely to be minor.

 Once the design has been confirmed and the extent of impacts known, further assessment would be required to verify the presence/absence of threatened species and identify any breeding places to be impacted by the 

works and advise on requirements. 

Land Protection (Pest and Stock Route Management) Act 2002

Presence of declared pest plants within the proposed alignment.Prior to construction, a field investigation is required to identify any declared 

pest plants within the proposed works area and define mitigation requirements.

South East Queensland Koala Conservation State Planning Regulatory Provisions (SPRP)

Clearing of non‐juvenile koala habitat trees within koala assessable development areas.

No action required ‐ site is not located within a koala assessable development area

Water Act 2000Works interfering with a waterway pursuant to the Water Act 2000 . Works will not interfere with surface water.

No action required ‐ works will not be in the bed or banks of the waterway

Fisheries Act 1994Works which will affect marine plants, waterways or declared Fish Habitat Areas relevant to the act. Works does not interfere  with waterways identified in the spatial data layer for Queensland waterways for waterway barrier works  (2013)

No action required ‐ work does not interfere with waterways. No marine plants are expected to be impacted by the works.

Coastal Protection and Management Act 1995 (Coastal Act)

Works requiring assessment and permit/s under the Queensland Coastal Plan. A search was undertaken on 19 December 2013 and the site is not  identified in the coastal management district or coastal hazard area. 

No action required ‐ site is not in coastal management district or coastal zone

Flood Regulated Area (planning scheme)Works within Flood and Inundation Area. A search of the LCC Flood Regulated Area Mapping was undertaken on 19 December 2013. The site is not in flood regulated area

No action required ‐ Site is not in the flood regulated area

Aboriginal Cultural Heritage Act 2003

The site is allocated a Category 4 ‐ (previously been subject to significant ground disturbance) under the Duty of Care Guidelines, given the installation of underground and aboveground services and disturbance due to the infrastructure on site, and the removal of vegetation, including the root ball. A search request was submitted on 19 December 2013 and no items were found on the register. The registered party is Jagera People #2

No items identified on the register. No consultation will be required prior to commencement of works within Category 4 areas . If any potential items are found during construction a 'stop work' will be required and consultation will need to be undertaken with the nominated Aboriginal parties of the area.

Non-indigenous cultural heritage (Queensland Heritage Act 1992 planning

Works within an area with non‐Indigenous cultural heritage items. No non‐indigenous cultural heritage was recorded on the council's planning scheme map,  No action required ‐ stop works and consultation with the relevant party/ies 

Legislation/Issue

WQI 06 - 14 Blueberry Ash Court, Jimboomba

(Queensland Heritage Act 1992 , planning scheme)

g g p g p,Queensland Heritage Register or Australia Heritage database cited 19 December 2013. 

q p p yif a potential cultural heritage item is discovered.

Acid sulphate soilsDisturbance/potential disturbance of acid sulphate soils (ASS). It is unlikely for ASS to be present onsite given that the area is at contours are 35m AHD.  No action required ‐ site not mapped as ASS area

Groundwater (dewatering)Contamination to groundwater. Geotechnical investigation are not undertaken for the site. Limited information available. 

Limited information available. If found, groundwater to be captured and tested prior to  release into the environment (i.e. irrigation to grasslands). 

Further assessment required during design and construction.

Environmental Protection Act 1994 - contaminated land

Contamination offsite or health impacts. A search of the environmental management register (EMR) and contaminated land register (CLR) was undertaken on 20 November 2013. None of the lots are on EMR/CLR

No action required ‐ None of the lots are on EMR/CLR

Fire ants (Plant Protection Act 1989 )Movement of restricted items within and out of a high or low risk area. A search of the restricted area map was undertaken on 19 December 2013. The site is within high risk area

Movement of restricted items outside the restricted area must be in compliance with the subcontractors ARMP. Stop works and inform LWA and 

Biosecurity QLD of any potential Fire Ant citings.

Public amenity (odour, noise, visual impacts)

Works within public areas. Works are adjacent to residential  premises. Adequate odour, noise and visual impact mitigation measures must be 

implemented during design, construction and operation.

BushfireWorks causing or impacted by bushfires. The site is not located within a bushfire hazard area as shown in BSC OV 3.1A. 

No action required ‐ site is not located within a bushfire hazard area.

Steep SlopesWorks within a steep slopes area. The site is not  shown as a  Landslide hazard investigation area in Beaudesert shire council planning scheme mapping OV 3.2A.

No action required ‐ site not shown in an area of  potential landslip hazard .

Unexploded ordnance (UXO's)

Working within an area known or suspected of having been used for military activity and assessed as having potential UXO contamination. A search of the UXO database on 12 December 2013 indicated that the site does not contain a known UXO contaminated area.

No action required ‐ site not shown to contain any known UXO. Stop works if a suspicious UXO item is found. Do not touch or disturb the item. Contact 

LWA and the Police.

Environmental summary (Ecological perspective)

The project works are located adjacent the existing pump station within cleared land with small patches of native regrowth adjacent to the works which may require clearing and/or trimming, although impacts are likely to be minor. Nonetheless, the site is surrounded by remnant RE12.9‐10.19 which is considered to comprise significant ecological values to the broader area, including habitat for threatened species. Any design changes should be undertaken in a manner that avoids impacting on this vegetation and mitigation measures shall be employed during construction to ensure that this vegetation is adequately protected (i.e. all access and laydown areas shall avoid impacts on surrounding vegetation and an arborist shall be consulted for any works within the Tree Protection zone of adjacent vegetation).No site assessment has been undertaken and prior to construction, a field investigation is required to identify the extent of impact to native vegetation, ensure no Threatened plants will be impacted and identify any declared pest plants within the proposed works area to define mitigation requirements.

Remnant vegetation in close proximity to the site

Environmental Summary (non ecological perspective)The site is considered to be in environmentally low risk area. The items that will need further assessment and management are Public Amenity, Fire Ant and potential groundwater

TRIGGER/IMPACT ACTION

Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)

Significant impact on any Matter of National Environmental Significance (MNES) as defined by the EPBC Act.

Proposed works not likely to result in a significant impact on any MNES.

Vegetation Management Act 1999 (VM Act)

Clearance of remnant vegetation on any land tenure or clearance of non‐remnant vegetation on state land, unless an exemption applies.

There is remnant Endangered, Of Concern and Least Concern REs mapped in close proximity to the proposed works along the waterway, however there is no 

remnant RE likely to be cleared for the proposed works as they are solely located within cleared land within the existing pump station complex. 

Due to recent exemptions in relation to clearing of native vegetation under the VM Act, no formal permits would be required under the VM Act for clearance of native vegetation for the works. The project is not expected to require 

clearance of native vegetation. 

Nature Conservation Act 1992 (NC Act)

Clearing of native plants where assessable under the VM Act. Clearing or pruning of threatened plants listed under the provisions of the NC Act on any land tenure. Tampering with animal breeding places protected under the provisions of the NC 

Act.The works are located within the existing pump station complex within cleared 

land. 

This project is not expected to require any clearing of native plants. Should any clearing be required, further assessment would be required to verify the 

presence/absence of threatened species and identify any breeding places to be impacted by the works and advise on requirements. 

Land Protection (Pest and Stock Route Management) Act 2002

Presence of declared pest plants within the proposed alignment.

The works are located within the existing pump station complex within cleared land that is unlikely to support declared pest plants. Should pest plants be 

identified within or adjacent to the works area at a later stage, then measures to prevent spread shall be implemented in accordance with the EMP. 

South East Queensland Koala Conservation State Planning Regulatory Provisions (SPRP)

Clearing of non‐juvenile koala habitat trees within koala assessable development areas.

No action required ‐ site is not located within a koala assessable development area

Water Act 2000Works interfering with a waterway pursuant to the Water Act 2000 . Works will not interfere with surface water.

No action required ‐ works will not be in the bed or banks of the waterway

Fisheries Act 1994Works which will affect marine plants, waterways or declared Fish Habitat Areas relevant to the act. Works does not interfere  with waterways identified in the spatial data layer for Queensland waterways for waterway barrier works  (2013)

No action required ‐ work does not interfere with waterways. No marine plants are expected to be impacted by the works.

Coastal Protection and Management Act 1995 (Coastal Act)

Works requiring assessment and permit/s under the Queensland Coastal Plan. A search was undertaken on 19 December 2013 and the site is not  identified in the coastal management district or coastal hazard area. 

No action required ‐ site is not in coastal management district or coastal zone

Flood Regulated Area (planning scheme)Works within Flood and Inundation Area. A search of the LCC Flood Regulated Area Mapping was undertaken on 19 December 2013. The site is not in flood regulated area

No action required ‐ Site is not in the flood regulated area

Aboriginal Cultural Heritage Act 2003

The site is allocated a Category 4 ‐ (previously been subject to significant ground disturbance) under the Duty of Care Guidelines, given the installation of underground and aboveground services and disturbance due to the infrastructure on site, and the removal of vegetation, including the root ball. A search request was submitted on 19 December 2013. The results did not identify any items on the register. This is no registered party or body for this site. 

No consultation will be required prior to commencement of works (if no items are found on the register) within Category 4 areas . If any potential items are found during construction a 'stop work' will be required and consultation will 

need to be undertaken with the DATSIMA

Non-indigenous cultural heritage (Queensland Heritage Act 1992 , planning

h )

Works within an area with non‐Indigenous cultural heritage items. No non‐indigenous cultural heritage was recorded on the council's planning scheme map, Queensland Heritage Register or Australia Heritage database cited 19 December 

No action required ‐ stop works and consultation with the relevant party/ies if a potential cultural heritage item is discovered.

Legislation/Issue

WQI 07- Mundoolun Rd PS

scheme)Queensland Heritage Register or Australia Heritage database cited 19 December 2013. 

a potential cultural heritage item is discovered.

Acid sulphate soilsDisturbance/potential disturbance of acid sulphate soils (ASS). It is unlikely for ASS to be present onsite given that the area is at contours are 60m AHD.  No action required ‐ site not mapped as ASS area

Groundwater (dewatering)Contamination to groundwater. Geotechnical investigation are not undertaken for the site. Limited information available. 

Limited information available. If found, groundwater to be captured and tested prior to  release into the environment (i.e. irrigation to grasslands). 

Further assessment required during design and construction.

Environmental Protection Act 1994 - contaminated land

Contamination offsite or health impacts. A search of the environmental management register (EMR) and contaminated land register (CLR) was undertaken on 20 November 2013. None of the lots are on EMR/CLR

No action required ‐ None of the lots are on EMR/CLR

Fire ants (Plant Protection Act 1989 )Movement of restricted items within and out of a high or low risk area. A search of the restricted area map was undertaken on 19 December 2013. The site is within high risk area

Movement of restricted items outside the restricted area must be in compliance with the subcontractors ARMP. Stop works and inform LWA and 

Biosecurity QLD of any potential Fire Ant citings.

Public amenity (odour, noise, visual impacts)

Works within public areas. Works not adjacent to residential area.No action required ‐ due to high vegetation surrounding the reservoir and the 

nature of the works. 

BushfireWorks causing or impacted by bushfires. The site is not located within a bushfire hazard area as shown in BSC OV 3.1A. 

No action required ‐ site is not located within a bushfire hazard area.

Steep SlopesWorks within a steep slopes area. The site is not  shown as a  Landslide hazard investigation area in Beaudesert shire council planning scheme mapping OV 3.2A.

No action required ‐ site not shown in an area of  potential landslip hazard .

Unexploded ordnance (UXO's)

Working within an area known or suspected of having been used for military activity and assessed as having potential UXO contamination. A search of the UXO database on 12 December 2013 indicated that the site does not contain a known UXO contaminated area.

No action required ‐ site not shown to contain any known UXO. Stop works if a suspicious UXO item is found. Do not touch or disturb the item. Contact LWA 

and the Police.

Environmental summary (Ecological perspective)

The project works are located within the existing pump station complex within cleared land and are considered unlikely to require clearance of native plants. Nonetheless, the site is in close proximity to remnant REs which is considered to comprise significant ecological values to the broader area, including habitat for threatened species. Any design changes should be undertaken in a manner that avoids impacting on this vegetation and mitigation measures shall be employed during construction to ensure that this vegetation is adequately protected (i.e. all access and laydown areas shall avoid impacts on surrounding vegetation and an arborist shall be consulted for any works within the Tree Protection zone of adjacent vegetation).

Remnant vegetation in close proximity to the site

Environmental Summary (non ecological perspective)The site is considered to be in environmentally low risk area. The items that will need further assessment and management are  Fire Ant and potential groundwater

TRIGGER/IMPACT ACTION

Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)

Significant impact on any Matter of National Environmental Significance (MNES) as defined by the EPBC Act.

Proposed works not likely to result in a significant impact on any MNES.

Vegetation Management Act 1999 (VM Act)Clearance of remnant vegetation on any land tenure or clearance of non‐remnant 

vegetation on state land, unless an exemption applies.There is no remnant RE located within or adjacent to the proposed works. 

Due to recent exemptions in relation to clearing of native vegetation under the VM Act, no formal permits would be required under the VM Act for clearance of native vegetation for the works. The project is not expected to require 

clearance of native vegetation.

Nature Conservation Act 1992 (NC Act)

Clearing of native plants where assessable under the VM Act. Clearing or pruning of threatened plants listed under the provisions of the NC Act on any land tenure. Tampering with animal breeding places protected under the provisions of the NC 

Act.The works are located in grassed road reserve adjacent parkland with scattered 

trees. 

This project is not expected to require any clearing of native plants, however some pruning or works within the TPZ of nearby vegetation may be required. Should any clearing be required, further assessment would be required to 

verify the presence/absence of threatened species and identify any breeding places to be impacted by the works and advise on requirements. 

Land Protection (Pest and Stock Route Management) Act 2002

Presence of declared pest plants within the proposed alignment.

The works are located within cleared land that is unlikely to support declared pest plants. Should pest plants be identified within or adjacent to the works 

area at a later stage, then measures to prevent spread shall be implemented in accordance with the EMP. 

South East Queensland Koala Conservation State Planning Regulatory Provisions (SPRP)

Clearing of non‐juvenile koala habitat trees within koala assessable development areas.

The site is located within a Priority koala assessable development area mapped as High Value Other Habitat.

The project is not expected to require any clearing on non‐juvenile Koala habitat trees, however should any clearing be required an assessment would need to be undertaken in accordance with the Koala SPRP to define approvals 

requirements.

Water Act 2000Works interfering with a waterway pursuant to the Water Act 2000 . Works will not interfere with surface water.

No action required ‐ works will not be in the bed or banks of the waterway

Fisheries Act 1994Works which will affect marine plants, waterways or declared Fish Habitat Areas relevant to the act. Works does not interfere  with waterways identified in the spatial data layer for Queensland waterways for waterway barrier works  (2013)

No action required ‐ work does not interfere with waterways. No marine plants are expected to be impacted by the works.

Coastal Protection and Management Act 1995 (Coastal Act)

Works requiring assessment and permit/s under the Queensland Coastal Plan. A search was undertaken on 19 December 2013 and the site is not  identified in the coastal management district or coastal hazard area. 

No action required ‐ site is not in coastal management district or coastal zone

Flood Regulated Area (planning scheme)Works within Flood and Inundation Area. A search of the LCC Flood Regulated Area Mapping was undertaken on 19 December 2013. The site is not in flood regulated area

No action required ‐ Site is not in the flood regulated area

Aboriginal Cultural Heritage Act 2003

The site is allocated a Category 4 ‐ (previously been subject to significant ground disturbance) under the Duty of Care Guidelines, given the installation of underground and aboveground services and disturbance due to the infrastructure on site, and the removal of vegetation, including the root ball. A search request was submitted on 19 December 2013. No items were found on the register. The registered party for the site is Turrbal People

No items found on the register. No consultation will be required prior to commencement of works within Category 4 areas . If any potential items are found during construction a 'stop work' will be required and consultation will need to be undertaken with the nominated Aboriginal party for the area.

Non-indigenous cultural heritage (Queensland Heritage Act 1992 , planning scheme)

Works within an area with non‐Indigenous cultural heritage items. No non‐indigenous cultural heritage was recorded on the council's planning scheme map, Queensland Heritage Register or Australia Heritage database cited 19 December 2013. 

No action required ‐ stop works and consultation with the relevant party/ies if a potential cultural heritage item is discovered.

Legislation/Issue

WQI 09 - Gills Cl, Rochedale (DMA 14/15 PRV Site)

Acid sulphate soilsDisturbance/potential disturbance of acid sulphate soils (ASS). It is unlikely for ASS to be present onsite given that the area is at contours are 65m AHD.  No action required ‐ site not mapped as ASS area

Groundwater (dewatering)Contamination to groundwater. Geotechnical investigation are not undertaken for the site. Limited information available. 

Limited information available. If found, groundwater to be captured and tested prior to  release into the environment (i.e. irrigation to grasslands). Further 

assessment required during design and construction.

Environmental Protection Act 1994 - contaminated land

Contamination offsite or health impacts. A search of the environmental management register (EMR) and contaminated land register (CLR) was undertaken on 20 November 2013. None of the lots are on EMR/CLR

No action required ‐ None of the lots are on EMR/CLR

Fire ants (Plant Protection Act 1989 )Movement of restricted items within and out of a high or low risk area. A search of the restricted area map was undertaken on 19 December 2013. The site is within high risk area

Movement of restricted items outside the restricted area must be in compliance with the subcontractors ARMP. Stop works and inform LWA and 

Biosecurity QLD of any potential Fire Ant citings.

Public amenity (odour, noise, visual impacts)

Works within public areas. Works are adjacent to residential  premises. Adequate odour, noise and visual impact mitigation measures must be 

implemented during design, construction and operation.

BushfireWorks causing or impacted by bushfires. The site is not located within a bushfire hazard area as shown in LCC OL Map 4 

No action required ‐ site is not located within a bushfire hazard area.

Steep SlopesWorks within a steep slopes area. The site is not shown as a steep slopes area as shown in the LCC OL Map 5.

No action required ‐ site not shown in an area of unstable soils or potential landslip hazard area.

Unexploded ordnance (UXO's)

Working within an area known or suspected of having been used for military activity and assessed as having potential UXO contamination. A search of the UXO database on 12 December 2013 indicated that the site does not contain a known UXO contaminated area.

No action required ‐ site not shown to contain any known UXO. Stop works if a suspicious UXO item is found. Do not touch or disturb the item. Contact LWA 

and the Police.

Site mapped as non‐remnant vegetation Site within a Priority Koala Assessable Development Area

Environmental summary (Ecological perspective)

The project works are located within cleared road reserve adjacent parkland with scattered trees and are considered unlikely to require clearance of native plants. Nonetheless, any design changes should be undertaken in a manner that avoids impacting on native vegetation and mitigation measures shall be employed during construction to ensure that adjacent vegetation is adequately protected (i.e. all access and laydown areas shall avoid impacts on surrounding vegetation and an arborist shall be consulted for any works within the Tree Protection zone of adjacent vegetation). The site is located within a Priority koala assessable development area mapped as High Value Other Habitat. The project is not expected to require any clearing on non‐juvenile Koala habitat trees, however should any clearing be required an assessment would need to be undertaken in accordance with the Koala SPRP to define approvals requirements.No site assessment has been undertaken and prior to construction, a field investigation is required to identify any declared pest plants within the proposed works area and define mitigation requirements.

l ( l l )The site is considered to be in environmentally low risk area. The items that will need further assessment and management are  Fire Ant, Public Amenity and potential groundwaterEnvironmental Summary (non ecological perspective)

TRIGGER/IMPACT ACTION

Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)

Significant impact on any Matter of National Environmental Significance (MNES) as defined by the EPBC Act.

Proposed works not likely to result in a significant impact on any MNES.

Vegetation Management Act 1999 (VM Act)

Clearance of remnant vegetation on any land tenure or clearance of non‐remnant vegetation on state land, unless an exemption applies.

There is no remnant RE located within or adjacent to the proposed works. 

Due to recent exemptions in relation to clearing of native vegetation under the VM Act, no formal permits would be required under the VM Act for 

clearance native vegetation for the works. Nonetheless, clearance of native vegetation should be limited to the minimum practical clearance.

Nature Conservation Act 1992 (NC Act)

Clearing of native plants where assessable under the VM Act. Clearing or pruning of threatened plants listed under the provisions of the NC Act on any land 

tenure. Tampering with animal breeding places protected under the provisions of the NC Act.

The works are located adjacent the existing pump station within cleared land adjacent the road reserve with landscaping trees adjacent the works that may require clearance/trimming. There is a large Eucalyptus tree on the adjoining 

property in close proximity to the proposed water quality sample line and works or construction access have the potential to be required within the Tree 

Protection Zone for this tree.

 Once the design has been confirmed and the extent of impacts known, further assessment would be required to verify the presence/absence of threatened species and identify any breeding places to be impacted by the 

works and advise on requirements. 

Land Protection (Pest and Stock Route Management) Act 2002

Presence of declared pest plants within the proposed alignment.Prior to construction, a field investigation is required to identify any declared 

pest plants within the proposed works area and define mitigation requirements.

South East Queensland Koala Conservation State Planning Regulatory Provisions (SPRP)

Clearing of non‐juvenile koala habitat trees within koala assessable development areas.

No action required ‐ site is not located within a koala assessable development area

Water Act 2000Works interfering with a waterway pursuant to the Water Act 2000 . Works will not interfere with surface water.

No action required ‐ works will not be in the bed or banks of the waterway

Fisheries Act 1994Works which will affect marine plants, waterways or declared Fish Habitat Areas relevant to the act. Works does not interfere  with waterways identified in the spatial data layer for Queensland waterways for waterway barrier works  (2013)

No action required ‐ work does not interfere with waterways. No marine plants are expected to be impacted by the works.

Coastal Protection and Management Act 1995 (Coastal Act)

Works requiring assessment and permit/s under the Queensland Coastal Plan. A search was undertaken on 19 December 2013 and the site is not  identified in the coastal management district or coastal hazard area. 

No action required ‐ site is not in coastal management district or coastal zone

Flood Regulated Area (planning scheme)Works within Flood and Inundation Area. A search of the LCC Flood Regulated Area Mapping was undertaken on 19 December 2013. The site is not in flood regulated area

No action required ‐ Site is not in the flood regulated area

Aboriginal Cultural Heritage Act 2003

The site is allocated a Category 4 ‐ (previously been subject to significant ground disturbance) under the Duty of Care Guidelines, given the installation of underground and aboveground services and disturbance due to the infrastructure on site, and the removal of vegetation, including the root ball. A search request was submitted on 19 December 2013. No items were found on the register. The registered CH body is Jabree Pty ltd

No items were found on the register. No consultation will be required prior to commencement of works within Category 4 areas . If any potential items are found during construction a 'stop work' will be required and consultation will need to be undertaken with the nominated Aboriginal parties of the area.

Non-indigenous cultural heritage (Queensland Heritage Act 1992 , planning scheme)

Works within an area with non‐Indigenous cultural heritage items. No non‐indigenous cultural heritage was recorded on the council's planning scheme map, Queensland Heritage Register or Australia Heritage database cited 19 December 2013. 

No action required ‐ stop works and consultation with the relevant party/ies if a potential cultural heritage item is discovered.

Legislation/Issue

WQI 10 - 38 Centenary Pl, Logan Village

Acid sulphate soilsDisturbance/potential disturbance of acid sulphate soils (ASS). It is unlikely for ASS to be present onsite given that the area is at contours are 20m AHD.  No action required ‐ site not mapped as ASS area

Groundwater (dewatering)Contamination to groundwater. Geotechnical investigation are not undertaken for the site. Limited information available. 

Limited information available. If found, groundwater to be captured and tested prior to  release into the environment (i.e. irrigation to grasslands). 

Further assessment required during design and construction.

Environmental Protection Act 1994 - contaminated land

Contamination offsite or health impacts. A search of the environmental management register (EMR) and contaminated land register (CLR) was undertaken on 20 November 2013. None of the lots are on EMR/CLR

No action required ‐ None of the lots are on EMR/CLR

Fire ants (Plant Protection Act 1989 )Movement of restricted items within and out of a high or low risk area. A search of the restricted area map was undertaken on 19  December 2013. The entire alignment is within low risk area

Movement of restricted items outside the restricted area must be in compliance with the subcontractors ARMP. Stop works and inform LWA and 

Biosecurity QLD of any potential Fire Ant citings.

Public amenity (odour, noise, visual impacts)

Works within public areas. Works are adjacent in commercial area. Adequate odour, noise and visual impact mitigation measures must be 

implemented during design, construction and operation.

BushfireWorks causing or impacted by bushfires. The site is not located within a bushfire hazard area as shown in BSC OV 3.1A. 

No action required ‐ site is not located within a bushfire hazard area.

Steep SlopesWorks within a steep slopes area. The site is not  shown as a  Landslide hazard investigation area in Beaudesert shire council planning scheme mapping OV 3.2A.

No action required ‐ site not shown in an area of  potential landslip hazard .

Unexploded ordnance (UXO's)

Working within an area known or suspected of having been used for military activity and assessed as having potential UXO contamination. A search of the UXO database on 12 December 2013 indicated that the site does not contain a known UXO contaminated area.

No action required ‐ site not shown to contain any known UXO. Stop works if a suspicious UXO item is found. Do not touch or disturb the item. Contact 

LWA and the Police.

Site mapped as non‐remnant vegetation

Environmental Summary (non ecological perspective)

Environmental summary (Ecological perspective)The project works are located adjacent the existing pump station within cleared land within cleared land adjacent the road reserve with landscaping trees adjacent the works that may require clearance/trimming. There is a large Eucalyptus tree on the adjoining property in close proximity to the proposed water quality sample line and works or construction access have the potential to be required within the Tree Protection Zone for this tree. Any design changes should be undertaken in a manner that avoids impacting on this tree and mitigation measures shall be employed during construction to ensure that this tree is adequately protected (i.e. all access and laydown areas shall avoid impacts on surrounding vegetation and an arborist shall be consulted for any works within the Tree Protection zone of adjacent vegetation).No site assessment has been undertaken and prior to construction, a field investigation is required to identify the extent of impact to native vegetation, ensure no Threatened plants will be impacted and identify any declared pest plants within the proposed works area to define mitigation requirements.

Environmental Summary (non ecological perspective)The site is considered to be in environmentally low risk area. The items that will need further assessment and management are  Fire Ant, Public Amenity and potential groundwater

TRIGGER/IMPACT ACTION

Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)

Significant impact on any Matter of National Environmental Significance (MNES) as defined by the EPBC Act.

Proposed works not likely to result in a significant impact on any MNES.

Vegetation Management Act 1999 (VM Act)Clearance of remnant vegetation on any land tenure or clearance of non‐remnant 

vegetation on state land, unless an exemption applies.There is no remnant RE located within or adjacent to the proposed works. 

Due to recent exemptions in relation to clearing of native vegetation under the VM Act, no formal permits would be required under the VM Act for clearance native vegetation for the works. Nonetheless, clearance of native vegetation 

should be limited to the minimum practical clearance.

Nature Conservation Act 1992 (NC Act)

Clearing of native plants where assessable under the VM Act. Clearing or pruning of threatened plants listed under the provisions of the NC Act on any land tenure. Tampering with animal breeding places protected under the provisions of the NC 

Act.The majority of the works are expected to be within cleared land in the road reserve, 

and any clearance of native plants is expected to be minimal. 

 Once the design has been confirmed and the extent of impacts known, further assessment would be required to verify the presence/absence of threatened 

species and identify any breeding places to be impacted by the works and advise on requirements. 

Land Protection (Pest and Stock Route Management) Act 2002

Presence of declared pest plants within the proposed alignment.Prior to construction, a field investigation is required to identify any declared 

pest plants within the proposed works area and define mitigation requirements.

South East Queensland Koala Conservation State Planning Regulatory Provisions (SPRP)

Clearing of non‐juvenile koala habitat trees within koala assessable development areas.

No action required ‐ site is not located within a koala assessable development area

Water Act 2000Works interfering with a waterway pursuant to the Water Act 2000 . Works will not interfere with surface water.

No action required ‐ works will not be in the bed or banks of the waterway

Fisheries Act 1994Works which will affect marine plants, waterways or declared Fish Habitat Areas relevant to the act. Works does not interfere  with waterways identified in the spatial data layer for Queensland waterways for waterway barrier works  (2013)

No action required ‐ work does not interfere with waterways. No marine plants are expected to be impacted by the works.

Coastal Protection and Management Act 1995 (Coastal Act)

Works requiring assessment and permit/s under the Queensland Coastal Plan. A search was undertaken on 19 December 2013 and the site is not  identified in the coastal management district or coastal hazard area. 

No action required ‐ site is not in coastal management district or coastal zone

Flood Regulated Area (planning scheme)Works within Flood and Inundation Area. A search of the GCC Flood Regulated Area Mapping was undertaken on 19 December 2013. The site is not in flood regulated area

No action required ‐ Site is not in the flood regulated area

Aboriginal Cultural Heritage Act 2003

The site is allocated a Category 4 ‐ (previously been subject to significant ground disturbance) under the Duty of Care Guidelines, given the installation of underground and aboveground services and disturbance due to the infrastructure on site, and the removal of vegetation, including the root ball. A search request was submitted on 19 December 2013 . No items were identified on the register. The registered party is Gold Coast Native Title Group

No items found on the register. No consultation will be required prior to commencement of works within Category 4 areas . If any potential items are found during construction a 'stop work' will be required and consultation will need to be undertaken with the nominated Aboriginal parties of the area.

Non-indigenous cultural heritage (Queensland Heritage Act 1992 , planning scheme)

A search of the GCCC planning scheme (no individual maps identified), Queensland Heritage Register and Australian Heritage Register was undertaken on 19 December 2013. No items of non‐Indigenous heritage were identified.

No action required ‐ stop works and consultation with the relevant party/ies if a potential cultural heritage item is discovered.

Disturbance/potential disturbance of acid sulphate soils (ASS). It is unlikely for ASS 

Legislation/Issue

WQI 11 - DMA 62 PRV Site

Acid sulphate soils

/p p ( ) yto be present onsite given that the site is outside the ASS area as per GCC planning scheme mapping

No action required ‐ site not mapped as ASS area

Groundwater (dewatering)Contamination to groundwater. Geotechnical investigation are not undertaken for the site. Limited information available. 

Limited information available. If found, groundwater to be captured and tested prior to  release into the environment (i.e. irrigation to grasslands). Further 

assessment required during design and construction.

Environmental Protection Act 1994 - contaminated land

Contamination offsite or health impacts. A search of the environmental management register (EMR) and contaminated land register (CLR) was undertaken on 20 November 2013. None of the lots are on EMR/CLR

No action required ‐ None of the lots are on EMR/CLR

Fire ants (Plant Protection Act 1989 )Movement of restricted items within and out of a high or low risk area. A search of the restricted area map was undertaken on 19 December 2013. The site is outside the restricted area

No Action required. Site is not within fire ant restricted area

Public amenity (odour, noise, visual impacts)

Works within public areas. Works are adjacent to residential  premises. Adequate odour, noise and visual impact mitigation measures must be 

implemented during design, construction and operation.

BushfireWorks causing or impacted by bushfires. The site is not located within a bushfire hazard area as shown in GCCC OM10‐1. 

No action required ‐ site is not located within a bushfire hazard area.

Steep SlopesWorks within a steep slopes area. The site is not shown as a steep slopes area as shown in the GCCC OM 16‐4.

No action required ‐ site not shown in an area of unstable soils or potential landslip hazard area.

Unexploded ordnance (UXO's)

Working within an area known or suspected of having been used for military activity and assessed as having potential UXO contamination. A search of the UXO database on 12 December 2013 indicated that the site does not contain a known UXO contaminated area.

No action required ‐ site not shown to contain any known UXO. Stop works if a suspicious UXO item is found. Do not touch or disturb the item. Contact LWA and 

the Police.

Site mapped as non‐remnant vegetation

Environmental Summary (non ecological perspective)

Environmental summary (Ecological perspective)

The project works are re expected to be within cleared land in the road reserve, and any clearance of native plants is expected to be minimal. The final design should be avoids impacting on native vegetation as far as practicable and mitigation measures shall be employed during construction to ensure that any adjacent vegetation is adequately protected (i.e. all access and laydown areas shall avoid impacts on surrounding vegetation and an arborist shall be consulted for any works within the Tree Protection zone of adjacent vegetation).No site assessment has been undertaken and prior to construction, a field investigation is required to identify the extent of impact to native vegetation, ensure no Threatened plants will be impacted and identify any declared pest plants within the proposed works area to define mitigation requirements.

The site is considered to be in environmentally low risk area. The items that will need further assessment and management are  Public Amenity and potential groundwater

TRIGGER/IMPACT ACTION

Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act)

Significant impact on any Matter of National Environmental Significance (MNES) as defined by the EPBC Act.

Proposed works not likely to result in a significant impact on any MNES.

Vegetation Management Act 1999 (VM Act)

Clearance of remnant vegetation on any land tenure or clearance of non‐remnant vegetation on state land, unless an exemption applies. 

The site is surrounded by remnant Least Concern vegetation, however the proposed works are located within the paved fenced area of the existing reservoir and no 

remnant RE 12.9‐10.17 will be impacted by the works. The remnant RE consists of a Eucalypt woodland that is limited to the other side of the fenceline.

Due to recent exemptions in relation to clearing of native vegetation under the VM Act, no formal permits would be required under the VM Act for 

clearance native vegetation for the works. Nonetheless, clearance of native vegetation should be limited to the minimum practical clearance.

Nature Conservation Act 1992 (NC Act)

Clearing of native plants where assessable under the VM Act. Clearing or pruning of threatened plants listed under the provisions of the NC Act on any land tenure. 

Tampering with animal breeding places protected under the provisions of the NC Act.The works are located within the existing reservoir site in cleared paved land, and no 

clearance of native plants is expected. 

This project is not expected to require any clearing of native plants. Should any clearing or trimming of the adjoining vegetation be required, further 

assessment would be required to verify the presence/absence of threatened species and identify any breeding places to be impacted by the works and 

advise on requirements. 

Land Protection (Pest and Stock Route Management) Act 2002

Presence of declared pest plants within the proposed alignment.

The works are located adjacent the existing reservoir and associated buildings within cleared land that is unlikely to support declared pest plants. Should 

pest plants be identified within or adjacent to the works area at a later stage, then measures to prevent spread shall be implemented in accordance with 

the EMP. 

South East Queensland Koala Conservation State Planning Regulatory Provisions (SPRP)

Clearing of non‐juvenile koala habitat trees within koala assessable development areas.

The site is located within a Priority koala assessable development area mapped as Medium Value Rehabilitation Habitat.

The project is not expected to require any clearing on non‐juvenile Koala habitat trees, however should any clearing be required an assessment would need to be undertaken in accordance with the Koala SPRP to define approvals 

requirements.

Water Act 2000Works interfering with a waterway pursuant to the Water Act 2000 . Works will not interfere with surface water.

No action required ‐ works will not be in the bed or banks of the waterway

Fisheries Act 1994Works which will affect marine plants, waterways or declared Fish Habitat Areas relevant to the act. Works does not interfere  with waterways identified in the spatial data layer for Queensland waterways for waterway barrier works  (2013)

No action required ‐ work does not interfere with waterways. No marine plants are expected to be impacted by the works.

Coastal Protection and Management Act 1995 (Coastal Act)

Works requiring assessment and permit/s under the Queensland Coastal Plan. A search was undertaken on 19 December 2013 and the site is not  identified in the coastal management district or coastal hazard area. 

No action required ‐ site is not in coastal management district or coastal zone

Flood Regulated Area (planning scheme)Works within Flood and Inundation Area. A search of the LCC Flood Regulated Area Mapping was undertaken on 19 December 2013. The site is not in flood regulated area

No action required ‐ Site is not in the flood regulated area

Aboriginal Cultural Heritage Act 2003

The site is allocated a Category 4 ‐ (previously been subject to significant ground disturbance) under the Duty of Care Guidelines, given the installation of underground and aboveground services and disturbance due to the infrastructure on site, and the removal of vegetation, including the root ball. A search request was submitted on 19 December 2013. No items were registered on the register. The registered parties are Jagera People #2 and Turrbal People

No items found on the register. No consultation will be required prior to commencement of works  within Category 4 areas . If any potential items are found during construction a 'stop work' will be required and consultation will need to be undertaken with the nominated Aboriginal parties of the area.

Non-indigenous cultural heritage (Q l d H it A t 1992 l i

Works within an area with non‐Indigenous cultural heritage items. No non‐indigenous cultural heritage was recorded on the council's planning scheme map No action required ‐ stop works and consultation with the relevant party/ies 

Legislation/Issue

WQI 12 - Springwood Low Level Reservoir

(Queensland Heritage Act 1992 , planning scheme)

indigenous cultural heritage was recorded on the council s planning scheme map, Queensland Heritage Register or Australia Heritage database cited 19 December 2013. 

No action required stop works and consultation with the relevant party/iesif a potential cultural heritage item is discovered.

Acid sulphate soils

Disturbance/potential disturbance of acid sulphate soils (ASS). It is unlikely for ASS to be present onsite given that the area is not mapped as an ASS area as shown in LCC OL Map 3.  Contours are mapped as 100m AHD. 

No action required ‐ site not mapped as ASS area

Groundwater (dewatering)Contamination to groundwater. Geotechnical investigation are not undertaken for the site. Limited information available. 

Limited information available. If found, groundwater to be captured and tested prior to  release into the environment (i.e. irrigation to grasslands). 

Further assessment required during design and construction.

Environmental Protection Act 1994 - contaminated land

Contamination offsite or health impacts. A search of the environmental management register (EMR) and contaminated land register (CLR) was undertaken on 20 November 2013. None of the lots are on EMR/CLR

No action required ‐ None of the lots are on EMR/CLR

Fire ants (Plant Protection Act 1989 )Movement of restricted items within and out of a high or low risk area. A search of the restricted area map was undertaken on 19  December 2013. The entire alignment is within low risk area

Movement of restricted items outside the restricted area must be in compliance with the subcontractors ARMP. Stop works and inform LWA and 

Biosecurity QLD of any potential Fire Ant citings.

Public amenity (odour, noise, visual impacts)

Works within public areas. Works are adjacent to residential  premises. Adequate odour, noise and visual impact mitigation measures must be implemented during design, construction and operation. However, due to nature of the work noise is the only likely impact and will be minimal

BushfireWorks causing or impacted by bushfires. The site is not located within a bushfire hazard area as shown in LCC OL Map 4, but is adjacent to a medium bushfire hazard district. 

Site is directly adjacent to Medium bushfire hazard area. Management during construction may be required.

Steep SlopesWorks within a steep slopes area. The site is not shown as a steep slopes area as shown in the LCC OL Map 5. However, the site is directly adjacent to steep slope

Site is on the edge of steep slope area. To be considered and managed during design and construction 

Unexploded ordnance (UXO's)

Working within an area known or suspected of having been used for military activity and assessed as having potential UXO contamination. A search of the UXO database on 12 December 2013 indicated that the site does not contain a known UXO contaminated area.

No action required ‐ site not shown to contain any known UXO. Stop works if a suspicious UXO item is found. Do not touch or disturb the item. Contact 

LWA and the Police.

Site mapped as non‐remnant vegetation Site within a Priority Koala Assessable Development Area

Environmental Summary (non ecological perspective)

Environmental summary (Ecological perspective)The project works are located adjacent the existing reservoir within a paved fenced area and no clearance of native vegetation is expected to be required for the works. Nonetheless, the site is surrounded by remnant RE 12.9‐10.17 which is considered to comprise significant ecological values to the broader area, including habitat for threatened species. Any design changes should be undertaken in a manner that avoids impacting on this vegetation and mitigation measures shall be employed during construction to ensure that this vegetation is adequately protected (i.e. all access and laydown areas shall avoid impacts on surrounding vegetation and an arborist shall be consulted for any works within the Tree Protection zone of adjacent vegetation). The site is located within a Priority koala assessable development area mapped as Medium Value Rehabilitation Habitat. The project is not expected to require any clearing on non‐juvenile Koala habitat trees, however should any clearing be required an assessment would need to be undertaken in accordance with the Koala SPRP to define approvals requirements.No site assessment has been undertaken and prior to construction, a field investigation is required to identify any potential impacts to adjoining vegetation and define mitigation requirements.

Environmental Summary (non ecological perspective)

The site is considered to be in environmentally low risk area. The items that will need further assessment and management are  Fire Ant, Public Amenity, bushfire hazard, steep slope area and potential groundwater

Prepared by: Hayley Gardner

Reviewed by: Pieter van der Linde & Alex Moro

Date: 28.11.13

Assessment based on these drawings: G:\7600\000\300\303 Environment\11 Projects\PDP‐90‐12‐38 Online WQ monitoring Priority 1&2 sites\Design Plans

Title Searches confirming owners & easement location:

\\Lwafapsvr01\admin\7600\000\300\303 Environment\11 Projects\PDP‐90‐12‐38 Online WQ monitoring Priority 1&2 sites\Approvals\Title Searches.pdf \\Lwafapsvr01\admin\7600\000\300\303 Environment\11 Projects\PDP‐90‐12‐38 Online WQ monitoring Priority 1&2 sites\Approvals\Indicative easement locations.docx

Site Details Council Freehold State Land with Trustee Local Road State controlled road reserve

Address & Lot description 

19 Apollo Court, Cedar Vale (RP229316/997)14 Blueberry Ash Court, Jimboomba (SP107993/921)Lot 970 Thornbill Cl, Greenbank (RP819215/970)

353‐379 Mundoolun Road, Jimboomba (WD3218/89)387‐403 Springwood Road, Springwood (SL10166/171)23 Black Diamond Crescent, Bethania (RP849310/941)

0 Centenary Place, Logan Village (MISC14617/222)0 Gills Close, Rochedale South (MISC20061/31)0 Belivah Road, Belivah (MISC54685/407)

0 Mount Lindesay Highway, Jimboomba (MISC32619/131) ‐ note; don't have exact location available however assume State controlled road given address provided

Tenure Council Freehold

Lot 89 ‐ DNRM (Purpose: Park and Recreation) with LCC as TrusteesLot 171 ‐ DNRM (Purpose: Water Supply) with SEQ Distributor Retailer Authority as TrusteesLot 941 ‐ DNRM (Purpose: Park and Recreation) with LCC as Trustees

Local road reserve State controlled road reserve

Registered Owner Logan City Council (all lots)

Lot 89‐ DNRM, with LCC as TrusteesLot 171 ‐ DNRM, with  SEQ Distributor Retailer Authority as TrusteesLot 941‐ DNRM, with LCC as Trustees

Logan City Council Department of Transport and Main Roads

Easements, Interests & Encumbrancesnote: relevant items listed only

Lot 997 ‐ Easement A (refer to easement figure attached ‐ easement is in favour of Beaudesert Shire for water supply, being the purpose of the proposal therefore the proposal is considered to be consistent with the purpose of the easement and no changes to the easement would be required.)Lot 970 ‐ Easement A (ENERGEX) (refer to easement figure attached ‐ proposal not considered to impact existing easement)

Lot 941 ‐ Easement A (ENERGEX) (refer to easement figure attached.  Note: the easement does not appear to be located on property – will need to survey to confirm)

Not applicable Not applicable

Domain designation within applicable local planning scheme

Lot 997 ‐ Community Facilities Precinct, Beaudesert Shire Planning SchemeLot 921 ‐ Passive Recreation Precinct, Beaudesert Shire Planning SchemeLot 970 ‐ Community Facilities Precinct, Beaudesert Shire Planning Scheme 

Lot 89 ‐ Passive Recreation Precinct, Beaudesert Shire Planning SchemeLot 171 ‐ Residential Zone, Logan Planning SchemeLot 941 ‐ Open Space Domain, Gold Coast Planning Scheme

Not applicable Not applicable

Logan City Council Flooding and Inundation Map 2 No lots are within Flooding and Inundation Area  Lot 89 and Lot 941 ‐ Located within Flooding and Inundation Area  Not located within the Predicted 1% AEP Flood Extent area. Not located in  Predicted 1% AEP Flood Extent area.

Applicable legislation Private Freehold State Land  with Trustee Road State controlled road reserve

Material Change of Use development application under the Gold Coast Planning Scheme 2003

The works are considered to comply with the definition of 'Utility Minor'  in the Beaudesert Shire Planning Scheme and are therefore exempt development within all domains under the planning scheme. No application required. 

The works are considered to comply with the definitions of 'Public Utility', 'Utility Minor' and 'Local Utilities'  in the respective planning schemes and are therefore exempt development within all domains under the planning scheme. No application required. 

Not applicable. No application required. 

Not applicable. No application required. 

Operational Works (OPW) development application under the Gold Coast Planning Scheme 2003, and Sustainable Planning Regulation 2009

Pursuant to Schedule 4, Table 4, Item 1 of the Sustainable Planning Regulation 2009, the proposed operational works are exempt development, thais, “Operational work or plumbing or drainage work (including maintenance and repair work) if the work is carried out by or on behalf of a public sector entity authorised under a State law to carry out the work”. In this regard, the proposed operational work is being undertaken by Logan City Council being a public sector, authorised to carry out the work without an assessment under the Local Government Act 2009.No application required. 

Pursuant to Schedule 4, Table 4, Item 1 of the Sustainable Planning Regulation 2009, the proposed operational works are exempt development, that is, “Operational work or plumbing or drainage work (including maintenance and repair work) if the work is carried out by or on behalf of a public sector entity authorised under a State law to carry out the work”. In this regard, the proposed operational work is being undertaken by Logan City Council being a public sector, authorised to carry out the work without an assessment under the Local Government Act 2009.No application required. 

Pursuant to Schedule 4, Table 4, Item 1 of the Sustainable Planning Regulation 2009, the proposed operational works are exempt development, that is, “Operational work or plumbing or drainage work (including maintenance and repair work) if the work is carried out by or on behalf of a public sector entity authorised under a State law to carry out the work”. In this regard, the proposed operational work is being undertaken by Logan City Council being a public sector, authorised to carry out the work without an assessment under the Local Government Act 2009.

No application required. 

Pursuant to Schedule 4, Table 4, Item 1 of the Sustainable Planning Regulation 2009, the proposed operational works are exempt development, that is, “Operational work or plumbing or drainage work (including maintenance and repair work) if the work is carried out by or on behalf of a public sector entity authorised under a State law to carry out the work”. In this regard, the proposed operational work is being undertaken by Logan City Council being a public sector, authorised to carry out the work without an assessment under the Local Government Act 2009.

No application required. 

Logan City Council Temporary Local Planning 

Instrument (“TLPI”) No. 1 (Logan Interim Flood 

Response) 2012

No private freehold properties are subject to flooding.No application required. 

Notwithstanding the OPW exemption outlined above, as two lot are subject to flooding, it is the Alliance’s responsibility to ensure our obligation is met to mitigate adverse flooding impacts to external sites by ensuring correct flood mitigation measures are designed and implemented. If the Alliance requires confirmation to ensure the correct flood mitigation methods are implemented, plans can be provided to LCC’s Flood Team and they can informally advise what measures should be undertaken.Should substantial cut and/or fill be required, the TLPI key items  should be considered.No application required. 

Not applicable. No application required. 

Not applicable. No application required. 

Environmental Protection Act 1994

The proposed water monitor will not require an ERA application pursuant to Schedule 2 Section 64 of the Environmental Protection Regulation 2008.No application required. 

The proposed water monitor will not require an ERA application pursuant to Schedule 2 Section 64 of the Environmental Protection Regulation 2008.No application required. 

The proposed water monitor will not require an ERA application pursuant to Schedule 2 Section 64 of the Environmental Protection Regulation 2008.No application required. 

The proposed water monitor will not require an ERA application pursuant to Schedule 2 Section 64 of the Environmental Protection Regulation 2008.No application required. 

South East Queensland Koala Conservation State 

Planning Regulatory Provisions (SPRP) 2010 & 

Environment Protection  and Biodiversity Conservation Act 1999

The sites are all outside the SPRP Koala Assessable Development Area and consequently a Development Application is not required for the proposed works. Furthermore, as the SPRP is the overarching state planning instrument that regulates new development in koala habitat value areas, assessment against SPP 2/10  Koala Conservation in Queensland 2010 is also not required. As the sites are not located in the Koala Assessable Development Area, the works are not referrable under the Environment Protection and Biodiversity Conservation Act 1999.No application required. 

The lots are outside the SPRP Koala Assessable Development Area and consequently a Development Application is not required for the proposed works. Furthermore, as the SPRP is the overarching state planning instrument that regulates new development in koala habitat value areas, assessment against SPP 2/10  Koala Conservation in Queensland 2010 is also not required. As the site is not located in the Koala Assessable Development Area, the works are not referrable under the Environment Protection and Biodiversity Conservation Act 1999.No application required. 

The road is outside the SPRP Koala Assessable Development Area and consequently a Development Application is not required for the proposed works. Furthermore, as the SPRP is the overarching state planning instrument that regulates new development in koala habitat value areas, assessment against SPP 2/10  Koala Conservation in Queensland 2010 is also not required. As the sites are not located in the Koala Assessable Development Area, the works are not referrable under the Environment Protection and Biodiversity Conservation Act 1999.No application required. 

The road is outside the SPRP Koala Assessable Development Area and consequently a Development Application is not required for the proposed works. Furthermore, as the SPRP is the overarching state planning instrument that regulates new development in koala habitat value areas, assessment against SPP 2/10  Koala Conservation in Queensland 2010 is also not required. As the sites are not located in the Koala Assessable Development Area, the works are not referrable under the Environment Protection and Biodiversity Conservation Act 1999.No application required. 

Environment Protection and Biodiversity 

Conservation Act 1999 (EPBC Act)

The Federal Environment Minister has listed the Queensland, New South Wales and Australian Capital Territory koala populations as 'vulnerable' under the Environmental Protection and Biodiversity Act 1999 (“EPBC Act”) in order to protect the species.  Any future clearing of confirmed koala habitat on the site may require consideration or assessment under the EPBC Act if there is a potentially significant impact on the species. The associated risk is considered low.No application required. 

The Federal Environment Minister has listed the Queensland, New South Wales and Australian Capital Territory koala populations as 'vulnerable' under the Environmental Protection and Biodiversity Act 1999 (“EPBC Act”) in order to protect the species.  Any future clearing of confirmed koala habitat on the site may require consideration or assessment under the EPBC Act if there is a potentially significant impact on the species. The associated risk is considered low.No application required. 

It is important to note that the Federal Environment Minister has listed the Queensland, New South Wales and Australian Capital Territory koala populations as 'vulnerable' under the Environmental Protection and Biodiversity Act 1999 (“EPBC Act”) in order to protect the species.  Any future clearing of confirmed koala habitat on the site may require consideration or assessment under the EPBC Act if there is a potentially significant impact on the species. The associated risk is considered low.No application required. 

It is important to note that the Federal Environment Minister has listed the Queensland, New South Wales and Australian Capital Territory koala populations as 'vulnerable' under the Environmental Protection and Biodiversity Act 1999 (“EPBC Act”) in order to protect the species.  Any future clearing of confirmed koala habitat on the site may require consideration or assessment under the EPBC Act if there is a potentially significant impact on the species. The associated risk is considered low.No application required. 

Easements are not required over road reserve.No application required. 

Local Government Act 2009

Should construction access, or a lay down area be required for the proposed works, approval for temporary use of the site from LCC would be required as owner of the properties. Where this is required, a simple consent application would be lodged with the LCC Property Team. Conditions of approval would likely relate to safety, maintenance and revegetation requirements.LCC Consent required.

As Logan City Council are trustee of the lots, they have the rights to issue approval for temporary use of the site for construction access and/or lay down areas. Where this is required, a simple consent application would be lodged with the LCC Property Team. Conditions of approval are likely to relate to safety, maintenance and revegetation requirements LCC Consent required.

Any construction works or geotechnical investigations within the reserve will require prior approval from the LCC Roads and Infrastructure Branch. 

Council can provide ‘in principle’ approval for the pipe alignment based on preliminary design drawings. However Council will not provide final construction approval until the final set of design drawings are available and the construction sub‐contractor has been appointed.  

The sub‐contractor will then lodge an excavation and/or road closure application to Council for the works. This process is normally undertaken by the sub‐contractor and would typically form part of their scope of works. If not, the LWA Approvals team can lodge these applications. 

It is important to note that any excavation works within the road reserve, regardless of whether the surfaceis sealed or not sealed, will require a Road Excavation Permit. One week should be allowed for this approval. In Principal approval and Final Construction approval required from LCC Roads and Infrastructure Branch.Road excavation permit and Road Closure Permit required from Logan City Council.

In principal approval will need to be obtained from DTMR for the proposal within State‐controlled Road.  Closer to construction commencing, a pre‐start meeting will need to be held on site with DTMR where the IFC drawings, SQE report and EMP for the project must be provided. Provided DTMR have no objection to these documents, a Works Permit will be issued, allowing construction to begin. If there will be no impacts to traffic flow on the state controlled road, a pre start meeting and Works Permit may not be required from DTMR.  DTMR In principle application required (also obtain consent from existing infrastructure providers in 

road reserve area ‐ i.e. Energex, Telstra)

DTMR Works permit required. 

Building Act 1975

Pursuant to Schedule 3, Part 2, Table 1, any building work in relation to the Council project is self assessable development as "building work carried out by or on behalf of the State, a public sector entity or a local government” is self assessable and will not require a building approval.No application required. 

Pursuant to Schedule 3, Part 2, Table 1, any building work in relation to the Council project is self assessable development as "building work carried out by or on behalf of the State, a public sector entity or a local government” is self assessable and will not require a building approval.No application required. 

Pursuant to Schedule 3, Part 2, Table 1, any building work in relation to the Council project is self assessable development as "building work carried out by or on behalf of the State, a public sector entity or a local government” is self assessable and will not require a building approval.No application required. 

Pursuant to Schedule 3, Part 2, Table 1, any building work in relation to the Council project is self assessable development as "building work carried out by or on behalf of the State, a public sector entity or a local government” is self assessable and will not require a building approval.No application required. 

Coastal Management and Protection Act 1995 and 

Sustainable Planning Regulation 2009

The lots are not located in the Coastal Management District (CMD) or within close proximity to a tidal waterway.  No application required. 

The lots are not located in the Coastal Management District (CMD) or within close proximity to a tidal waterway.  No application required. 

The lots are not located in the Coastal Management District (CMD) or within close proximity to a tidal waterway.  No application required. 

The lots are not located in the Coastal Management District (CMD) or within close proximity to a tidal waterway.  No application required. 

Native Title Act 1993

Native title can only be claimed on certain areas of land or water, for example on vacant or unallocated Crown land but not on residential freehold land or public works like roads, schools or hospitals. No further assessment required. 

Native title can only be claimed on certain areas of land or water, for example on vacant or unallocated Crown land but not on residential freehold land or public works like roads, schools or hospitals. No further assessment required. 

Native title can only be claimed on certain areas of land or water, for example on vacant or unallocated Crown land but not on residential freehold land or public works like roads, schools or hospitals. No referral required. 

Native title can only be claimed on certain areas of land or water, for example on vacant or unallocated Crown land but not on residential freehold land or public works like roads, schools or hospitals. No referral required. 

Summary

Relevant Authority Associated timeframe

ENERGEX 1 month each

Department of Natural Resources and Mines (DNRM) 2 months 

Department of Transport and Main Roads 2 months 

Department of Transport and Main Roads 2 months 

LCC Roads and Infrastructure Branch 1 month 

LCC Roads and Infrastructure Branch 1 week each

Logan City Council  3 weeks 

LCC Road excavation/Road closure permit application

LCC Consent for infrastructure over LCC Freehold land and associated lay down areas

No waterway located near road. No application required. 

In Principle Approval application to DTMR for works in State‐controlled Road

Final Construction Approval application to DTMR for works in State‐controlled Road

Final Construction Approval application to LCC Roads and Infrastructure Branch for works local road reserve

Three DNRM easement application including LCC Trustee Consent

Applications/Negotiations

Sustainable Planning Regulation 2009  and Water Act 

2000 (Taking or interfering with water)

A waterway is not located in close proximity to the lots. No application required.

Land Title Act 1994 and Acquisition of Land Act 1967

As the sites are owned by Logan City Council, an easement will not be required over the proposed water monitors. However, the following actions will still be required:‐ Notify LCC of proposed access to sites‐ Obtain consent from LCC Property and Parks & Conservation teams for the infrastructure.

Existing easements are not considered to impact on the proposal.

Notification to LCC for access.

LCC consent for works. 

90‐12‐38, Online Water Quality Monitoring ‐ Property and Approvals Assessment

Liaison with ENERGEX if works within ENERGEX easement.  Based on current drawings, works will not be within ENERGEX easement.

A waterway is not located in close proximity to the lots. No application required.

As the lots are state owned, an easement will be required over each lot to protect the proposed water quality monitors. Actions required:‐ Provide notification to LCC for any investigation works (as trustee of the properties)‐ Prepare an easement application (including easement drawing, trustee consent letters from LCC and relevant DNRM forms) and lodge with DNRM (Undertaken by LCC Property Team).‐ Obtain offer of approval to 'Enter and Construct' from DNRM and accept conditions of approval and pay compensation amount (Undertaken by LCC Property Team).‐ Prepare survey plans once construction works have been completed and provide plans to DNRM for easement finalisation (allow $10,000 for each survey plan). Notification to LCC for investigation works

Three DNRM easements (lodged under one easement application)

Easements are not required over road reserve.No application required. 

No waterway located near road. No application required. 

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 54 of 55 Rev: 1

Appendix D Cost Estimate

LWA ‐ Planning Estimate 90‐12‐38

Online Water Quality Monitoring ‐ Priority Sites 1 & 2

(First Principle Estimate ‐ RC)

Description Unit Quantity Unit rate Amount Remarks

DESIGN DEVELOPMENT COSTS

Design Development Cost Total ‐ Design Development Cost item 1.000 0.05 23,046.40$                

Work Package ‐ Project Management

Project Management ,Supervision,Community and EstimatingQ‐Leave Levy Total ‐ Work Package ‐ Project Management item 1.000 0.12 55,311.36$                

DELIVERY COST ‐ (Indirect & Direct)

Indirect Delivery Cost

Design Group ManagementEnvironmental ManagementDefects Liability Cost AllowanceTotal ‐ Indirect Delivery Cost item 1.000 0.10 46,092.80$                 4,609.28$                                                                                                    

Direct Delivery Cost

Site 1 ‐ WQ1 03 Monitoring Point ‐ Spring Mountain Reservoir

Prelims,  Site Establishment , Management & Supervision item 1.000 $5,687.50 5,687.50$                    Assumed project duration = 5 weeksConstruct ‐ Concrete Plinth for Water Quality Cabinet item 1.000 898.00$                  898.00$                      Install  ‐  Water Quality Cabinet item 1.000 5,676.00$              5,676.00$                   Install ‐ Sample line and Discharge Line item 1.000 3,718.00$              3,718.00$                   Install ‐  Power and Telemetry Conduit item 1.000 9,471.00$              9,471.00$                   Provisional Sum  ‐ Install 3000L Poly Tank(inground) item 1.000 3,923.00$              3,923.00$                   Provisional Sum  ‐ Irrigation system item 1.000 2,000.00$              2,000.00$                   Instrumentation item 1.000 12,000.00$            12,000.00$                 Basic Cabinet Cost (Free + Total) based on E+H quoteSite commissioning into SCADA item 1.000 1,000.00$              1,000.00$                    Estimate based on discussion with RB. Total ‐ Site 1 ‐ WQ1 03 Monitoring Point ‐ Spring Mountain Reservoir 44,373.50$                

Site 2 ‐ WQ1 04 Monitoring Point ‐ Wood Hill Reservoir

Prelims,  Site Establishment , Management & Supervision item 1.000 $5,687.50 5,687.50$                    Assumed project duration = 5 weeksConstruct ‐ Concrete Plinth for Water Quality Cabinet item 1.000 898.00$                  898.00$                      Install  ‐  Water Quality Cabinet item 1.000 5,676.00$              5,676.00$                   Install ‐ Sample line and Discharge Line item 1.000 4,114.00$              4,114.00$                   Install ‐  Power and Telemetry Conduit item 1.000 3,949.00$              3,949.00$                   Provisional Sum  ‐ Install 3000L Poly Tank(inground) item 1.000 3,923.00$              3,923.00$                   Provisional Sum  ‐ Irrigation system item 1.000 2,000.00$              2,000.00$                   Instrumentation item 1.000 12,000.00$            12,000.00$                 Basic Cabinet Cost (Free + Total) based on E+H quoteSite commissioning into SCADA item 1.000 1,000.00$              1,000.00$                    Estimate based on discussion with RB. Total ‐ Site 2 ‐ WQ1 04 Monitoring Point ‐ Wood Hill Reservoir 39,247.50$                

Site 3 ‐ WQ1 05 Monitoring Point ‐ JMSP‐6(SPS 80) Pump Station

Prelims,  Site Establishment , Management & Supervision item 1.000 $5,687.50 5,687.50$                    Assumed project duration = 5 weeksConstruct ‐ Concrete Plinth for Water Quality Cabinet item 1.000 898.00$                  898.00$                      Install  ‐  Water Quality Cabinet item 1.000 5,676.00$              5,676.00$                   Tapping to Water Main (if no tapping exists) item 1.000 4,818.00$              4,818.00$                   Install ‐ Sample line and Discharge Line item 1.000 3,454.00$              3,454.00$                   Install ‐  Power and Telemetry Conduit item 1.000 3,949.00$              3,949.00$                   Instrumentation item 1.000 19,000.00$            19,000.00$                 Based on E+H quote including Nitrate measurementSite commissioning into SCADA item 1.000 1,000.00$              1,000.00$                    Estimate based on discussion with RB. Total ‐ Site 3 ‐ WQ1 05 Monitoring Point ‐ JMSP‐6(SPS 80) Pump Station 44,482.50$                

Site 4 ‐ WQ1 06 Monitoring Point ‐ Flagstone(SPS 78) Pump Station

Prelims,  Site Establishment ,  item 1.000 $5,687.50 5,687.50$                    Assumed project duration = 5 weeksConstruct ‐ Concrete Plinth for Water Quality Cabinet item 1.000 898.00$                  898.00$                      Install  ‐  Water Quality Cabinet item 1.000 5,676.00$              5,676.00$                   Tapping to Water Main (if no tapping exists) item 1.000 4,818.00$              4,818.00$                   Install ‐ Sample line and Discharge Line item 1.000 3,454.00$              3,454.00$                   Install ‐  Power and Telemetry Conduit item 1.000 3,949.00$              3,949.00$                   Instrumentation item 1.000 12,000.00$            12,000.00$                 Basic Cabinet Cost (Free + Total) based on E+H quoteSite commissioning into SCADA item 1.000 1,000.00$              1,000.00$                    Estimate based on discussion with RB. Total ‐ Site 4 ‐ WQ1 06 Monitoring Point ‐ Flagstone(SPS 78) Pump Station 37,482.50$                

Site 5 ‐ WQ1 07 Monitoring Point ‐ Mundoolun Pump Station

Prelims,  Site Establishment , Management & Supervision item 1.000 $5,687.50 5,687.50$                    Assumed project duration = 5 weeksConstruct ‐ Concrete Plinth for Water Quality Cabinet item 1.000 898.00$                  898.00$                      Install  ‐  Water Quality Cabinet item 1.000 5,676.00$              5,676.00$                   Tapping to Water Main (if no tapping exists) item 1.000 4,818.00$              4,818.00$                   Install ‐ Sample line and Discharge Line item 1.000 1,859.00$              1,859.00$                   Install ‐  Power and Telemetry Conduit item 1.000 770.00$                  770.00$                      Provisional Sum  ‐ Install 3000L Poly Tank (inground) item 1.000 3,923.00$              3,923.00$                   Provisional Sum  ‐ Irrigation system item 1.000 2,000.00$              2,000.00$                   Instrumentation item 1.000 12,000.00$            12,000.00$                 Basic Cabinet Cost (Free + Total) based on E+H quoteSite commissioning into SCADA item 1.000 1,000.00$              1,000.00$                    Estimate based on discussion with RB. Total ‐ Site 5 ‐ WQ1 07 Monitoring Point ‐ Mundoolun Pump Station 38,631.50$                

Site 6 ‐ WQ1 09 Monitoring Point ‐ DMA 14/15 PRV Site

Prelims,  Site Establishment , Management & Supervision item 1.000 $5,687.50 5,687.50$                    Assumed project duration = 5 weeksConstruct ‐ Concrete Plinth for Water Quality Cabinet item 1.000 898.00$                  898.00$                      Install  ‐  Water Quality Cabinet item 1.000 5,676.00$              5,676.00$                   Tapping to Water Main (if no tapping exists) item 1.000 4,818.00$              4,818.00$                   Install ‐ Sample line and Discharge Line item 1.000 5,471.00$              5,471.00$                   Install ‐  Power and Telemetry Conduit item 1.000 8,261.00$              8,261.00$                   Instrumentation item 1.000 19,000.00$            19,000.00$                 Based on E+H quote including Nitrate measurementSite commissioning into SCADA item 1.000 1,000.00$              1,000.00$                    Estimate based on discussion with RB. Total ‐ Site 6 ‐ WQ1 09 Monitoring Point ‐ DMA 14/15 PRV Site 50,811.50$                

Site 7 ‐ WQ1 10  Monitoring Point ‐ Logan Village 2 (SPS 71) Pump Station

Prelims,  Site Establishment , Management & Supervision item 1.000 $5,687.50 5,687.50$                    Assumed project duration = 5 weeksConstruct ‐ Concrete Plinth for Water Quality Cabinet item 1.000 898.00$                  898.00$                      Install  ‐  Water Quality Cabinet item 1.000 5,676.00$              5,676.00$                   Tapping to Water Main (if no tapping exists) item 1.000 4,818.00$              4,818.00$                   Install ‐ Sample line and Discharge Line item 1.000 8,624.00$              8,624.00$                   Install ‐  Power and Telemetry Conduit item 1.000 3,812.00$              3,812.00$                   Install ‐  RPZ  Valve item 1.000 700.00$                  700.00$                      Instrumentation item 1.000 12,000.00$            12,000.00$                 Basic Cabinet Cost (Free + Total) based on E+H quoteSite commissioning into SCADA item 1.000 1,000.00$              1,000.00$                    Estimate based on discussion with RB. Total ‐ Site 7 ‐ WQ1 10  Monitoring Point ‐ Logan Village 2 (SPS 71) Pump Station 43,215.50$                

Site 8‐ WQ1 12  Monitoring Point ‐ Springwood Low Level Reservoir

Prelims,  Site Establishment , Management & Supervision item 1.000 $5,687.50 $5,687.50 Assumed project duration = 5 weeksConstruct ‐ Concrete Plinth for Water Quality Cabinet item 1.000 898.00$                  898.00$                      Install  ‐  Water Quality Cabinet item 1.000 5,676.00$              5,676.00$                   Tapping to Water Main (if no tapping exists) item 1.000 4,818.00$              4,818.00$                   Install ‐ Sample line and Discharge Line item 1.000 5,676.00$              5,676.00$                   Install ‐  Power and Telemetry Conduit item 1.000 34,144.00$            34,144.00$                Instrumentation item 1.000 19,000.00$            19,000.00$                 Based on E+H quote including Nitrate measurementSite commissioning into SCADA item 1.000 1,000.00$              1,000.00$                    Estimate based on discussion with RB. Total ‐ Site 8‐ WQ1 12  Monitoring Point ‐ Springwood Low Level Reservoir $76,899.50

Site 9‐ WQ1 08  Monitoring Point ‐ Bethania Reticulation (DMA site)

Prelims,  Site Establishment , Management & Supervision item 1.000 $5,687.50 $5,687.50Construct ‐ Concrete Plinth for Water Quality Cabinet item 1.000 898.00$                  $898.00Install  ‐  Water Quality Cabinet item 1.000 5,676.00$              $5,676.00Tapping to Water Main (if no tapping exists) item 1.000 4,818.00$              $4,818.00Install ‐ Sample line and Discharge Line item 1.000 3,718.00$              $3,718.00Install ‐  Power and Telemetry Conduit item 1.000 9,471.00$              $9,471.00Instrumentation item 1.000 12,000.00$            $12,000.00 Basic Cabinet Cost (Free + Total) based on E+H quoteSite commissioning into SCADA item 1.000 1,000.00$              $1,000.00Site 9‐ WQ1 08  Monitoring Point ‐ Bethania Reticulation (DMA site) $43,268.50

Site 10‐ WQ1 11  Monitoring Point ‐ Bannockburn reticulation

Prelims,  Site Establishment , Management & Supervision item 1.000 $5,687.50 $5,687.50Construct ‐ Concrete Plinth for Water Quality Cabinet item 1.000 898.00$                  $898.00Install  ‐  Water Quality Cabinet item 1.000 5,676.00$              $5,676.00Tapping to Water Main (if no tapping exists) item 1.000 4,818.00$              $4,818.00Install ‐ Sample line and Discharge Line item 1.000 8,624.00$              $8,624.00Install ‐  Power and Telemetry Conduit item 1.000 3,812.00$              $3,812.00Instrumentation item 1.000 12,000.00$            $12,000.00 Basic Cabinet Cost (Free + Total) based on E+H quoteSite commissioning into SCADA item 1.000 1,000.00$              $1,000.00Site 10‐ WQ1 11  Monitoring Point ‐ Bannockburn reticulation $42,515.50

TOTAL ‐ Direct Cost 460,928.00$              

TOTAL ‐ DELIVERY COST (Indirect & Direct) 507,020.80$              

PROJECT FEE

Project Fee Total ‐ Project Fee item 1.000 0.135$                    79,026.11$                

Logan Water

Logan WaterTotal ‐ Logan Water item 1.000 0.01$                      4,609.28$                  

TOTAL TOC  ‐  (A+B+C+D+E+F) 669,013.95$              

Contingency

Contingency Allowance item 1.000 0.05$                      25,351.04$                

TOTAL  BUDGET ‐ (A+B+C+D+E+F+G) 694,364.99$              

Assumptions:Project Duration = 5 weeksProject Manager/Project Engineer = 2hours/day for project durationSite Supervision = 4 hours/day for project duration

Online Water Quality Monitoring Priority 1 and 2 Sites – Detailed Planning Document Number: 7600-000-P-REP-PL-8204

90-12-38 Date issued: 28/02/2014 Page 55 of 55 Rev: 1

Appendix E POAR Meeting Minutes

Meeting Minutes

7600-000-P-MOM-PL-8229

MOM-PL-8229 Date issued: 02.12.2013 Page 1 of 4 Rev: A

MEETING MINUTES

MEETING: Online Water Quality Monitoring Sites Priority 1 + 2 : POAR Workshop

MEETING NUMBER: 1

DATE: 02/12/2013

START TIME: 1:00pm END TIME: 2:15pm

LOCATION: L3 Meeting Room, LWA

CHAIRMAN: Simon Hawkes

ATTENDEES / APOLOGIES

NAME (Present = YES) ABBR

Reg Bailey RB

Chris Pipe-Martin CPM

Toni Widdop TW

Peter Bell PB

Craig Kelly CK

Lester Bridgham LB

Rebecca Pollard RP

Simon Hawkes SH

MINUTES

NUMBER: ITEM:

1 WQI 03 – Spring Mountain Reservoir No comments regarding proposed location or discharge options.

2.

WQI 04 – Woodhill Reservoir Sites proposed for booster chlorination station as part of the Logan South Disinfection Strategy. Design/location of the proposed WQ monitoring equipment should ensure this is in conjunction with the proposed chlorination booster stations (CPM).

3

WQI 05 – Jimboomba 6 SPS LB noted supply from Round Mountain along the PEET main into Flagstone is pending commissioning of this main.

Meeting Minutes

7600-000-P-MOM-PL-8229

MOM-PL-8229 Date issued: 02.12.2013 Page 2 of 4 Rev: A

Action: CPM to confirm whether both WQI 05 and WQI 06 are required for WQ monitoring, given the proximity of these two sites.

4

WQI 06 – Flagstone 2 SPS No comments regarding proposed location or discharge options. Action: As noted in item 3.

5

WQI 07 – Mundoolun Road WPS Site is proposed for booster chlorination station as part of the Logan South Disinfection Strategy. Design/location of the proposed WQ monitoring equipment should ensure this is in conjunction with the proposed chlorination booster stations (CPM).

6 WQI 08 – DMA 58, Bethania No comments regarding proposed location or discharge options.

7 WQI 09 – DMA 14/15, Rochedale No comments regarding proposed location or discharge options.

8.

WQI 10 – Logan Village 2 SPS RP queried whether there was an alternative location for the monitoring point which may be in a location with poorer water turnover. The current location (adjacent to the LV2 SPS) has good turnover due to the industrial demand in the area. Action: SH to investigate alternative location

9.

WQI 11 – DMA 62, Belivah

LB queried whether this site is a duplicate of the existing monitoring location in the area. The map below shows the general location of the existing monitoring point, LB to confirm exact location.

It appears that the existing monitoring location will provide representative sample of water quality in the network. The existing site should be visited to confirm whether Total Chlorine monitoring can be included in future in the existing cabinet.

Action: CPM to confirm that the existing monitoring location is maintained, and the proposed WQI 11 site be dropped from the list. Provision for future upgrade of this site to monitor Total Chlorine can be considered.

Meeting Minutes

7600-000-P-MOM-PL-8229

MOM-PL-8229 Date issued: 02.12.2013 Page 3 of 4 Rev: A

10.

Discharge to stormwater

During discussion of sites where alternative disposal (disposal to stormwater) is considered it was agreed that LWA environmental team can help undertake a risk assessment in the fulfilment of any EHP/General Environmental Duty requirements.

Action: SH to liaise with environmental team to arrange contribution to risk assessment

11.

Equipment

CPM queried ongoing maintenance requirements in the selection of equipment for nitrate monitoring. CPM noted ion selective electrodes for nitrate monitoring were previously subject to high maintenance costs on a regular ongoing basis.

Action: SH to confirm with suppliers

12.

Communications

RB queried acceptability of MODBUS communication protocol of proposed instrumentation.

Action: PB to confirm suitability/acceptance

13.

Telemetry

It was noted site audits of spare RTU I/O be undertaken for the proposed WQ monitoring sites.

Action: RB to engage LWA electrical design engineer/liaise with PB

14. Cost Estimates

It was noted that site costs for the sites adjacent to proposed DMA sites (WQI 08, WQI 11) be included in the site costing.

Meeting Minutes

7600-000-P-MOM-PL-8229

MOM-PL-8229 Date issued: 02.12.2013 Page 4 of 4 Rev: A

Action: SH to include these site costs (noting inclusion/exclusion of WQI 11 site to be confirmed)

15.

Equipment suppliers

It was agreed by stakeholders that E+H be engaged to supply instrumentation given: - E+H instrumentation preferred by Operations - E+H instrumentation offered at lowest cost - E+H can provide instrumentation to monitor all of the desired parameters Action: LWA design engineer to liaise with E+H to develop instrumentation layout within cabinet

16.