  • Long Lake

    Hydro Project Update

    Presented by

    David Carter – Regional Power

    Minerals North 2011

    Long Lake Joint Venture

  • Long Lake Joint Venture

    Project Location

    25 km north of Stewart, in northwest B.C.

    Situated near historic Premier & Big Missouri mining camps

    Moderated coastal climate and terrain ideal for hydro

    Long Lake valley

    looking south

  • Long Lake Joint Venture

    Developer Background

    Regional Power

    developer and operator of hydroelectric power plants since 1985, over 120 plant years of operating experience

    Developed hydro plants in BC and Ontario

    Regional has 6 hydroelectric development sites “under contract” representing 97 MW in capacity

    Two 11 MW sites on Bear Creek, near Sechelt currently under construction and Long Lake access construction started summer 2010

    a subsidiary of Manulife Financial

  • Long Lake Joint Venture

    Developer Background

    Joint Ventured with Premier Power

    Corp. in Long Lake Project

    Premier’s affiliate company,

    Summit Power, owns and operates

    two hydro developments in

    southwestern B.C.

    14 MW Soo River Hydro, near Whistler

    5.3 MW Doran-Taylor Hydro, near

    Port Alberni

    Doran-Taylor 5.3 MW Project

  • Long Lake Joint Venture

    Joint Venture Background

    Innovative approach to Project development

    Identify environmentally and economically sound opportunities

    Established a favourable, cooperative relationship with government agencies, stakeholders

    Doran-Taylor Hydro tailrace (Oct 98)(Fisheries Renewal BC project co-sponsored by Summit Power, DFO, Hupacasath First Nation, MC Wright & Associates)

    Sechelt Creek Hydro spawn channel (Sep 03)(A cooperative arrangement between

    Regional Power, DFO, Sechelt First Nation)

  • Long Lake Joint Venture

    Project History

    Several hydro schemes

    powered the old Premier

    and Big Missouri mines

    during 1923 through

    1956

    Developments on lower

    Cascade & Fletcher

    Creeks provided power

    to nearby Premier mine

    and townsite

  • Long Lake Joint Venture

    Project History

    Cominco built dam

    at Long Lake to

    provide storage for

    Big Missouri mine

    power development

    Storage provided

    firm power year

    round to mine and

    townsite

    Former Long Lake Dam

  • Long Lake Joint Venture

    Project Background

    Westmin studied Long Lake hydro concept to service a new 2,000 tpd mine in late 1980’s

    Plans for the hydro plant were shelved when BC Hydro extended the 138kV transmission line from Aiyansh to Stewart

    Premier Gold mine operated until mid 1990’s

  • Long Lake Joint Venture

    Project Background

    Summer 1999: Premier Powerinitiated technical, environmental and socioeconomic investigations

    Late 2002: Premier Power and Regional Power formed Long Lake Joint Venture to advance the development

    Early 2005: Completed regulatory review process for 2.83cms (CEAA / CWL)

    Fall 2008: Project was successfully bid into BC Hydro’s 2008 Clean Power Call process

    Summer 2010: Awarded Energy Purchase Agreement

  • Long Lake Joint Venture

    Project Design

    Redevelop concept using Westmin 1980’s strategy

    Develop hydro power to optimize utilization of hydrologic resource

    – 31 MW installed capacity

    – 5.0 m3/s design flows

    – utilize storage on Long Lake

    – develop 776 m gross head

  • Long Lake Joint Venture

    Project Design

    Rockfill dam & intake structure designed for stability under MCE and PMF (highest Canadian Dam Safety Criteria)

    7.25km penstock generally following Big Missouri Haul Road to vicinity of Premier Gold mill site

    Powerhouse with two 16 MW two-jet Pelton-type turbine generator units

    Power transmission via new 10km, 138kV line connecting to BC Hydro

    Short tailrace to return water to Cascade Creek

    Project fully designedSheet Pile / Rock Fill Dam construction at Pingston Creek(Photo: P. Kemp, Canadian Projects)

  • Long Lake Joint Venture

    Project Design

    Penstock:• Steel pipeline

    • Integrated Resource Management

    Planning

  • Long Lake Joint Venture

    Construct new 10 km, 138kV transmission line, all within BC

    Connecting to BC Hydro grid

    Extending the 138kV transmission

    Project Design

  • Long Lake Joint Venture

    Project Design

    Two jet pelton configuration similar to Dease Lake

    Remote access of powerhouse controls

    3-4 Operators

    5.3 MW Pelton turbine

    (similar to unit proposed for Long Lake)

  • Long Lake Joint Venture

    Project Schedule

    Design of Major Infrastructure Completion -

    Summer 2005

    Commenced construction –

    August 2010

    Rehabilitate BMHR –

    August 2010

    Major Equipment & General Contracts –

    May / June 2011

    Commercial Operation -

    Summer 2013

  • Long Lake Joint Venture

    Project Benefits

    Project will become the largest tax base in the District of Stewart

    Sustainable, long term resource investment in district

    Help maintain valuable infrastructure

    Affords numerous environmental benefits

    Construction of “Soucie Pass” Road to Long Lake dam site

    September 2010

    Photo: S. Giesbrecht, Triton Environmental

  • Long Lake Joint Venture

    Special Thanks…

    District of Stewart, Mayor and council, and stakeholders, for their tireless and ongoing support for the Project

    Nisga”a and SKLH for their support

    Provincial and federal regulatory agency support and policies for promotion of development of clean energy

    BC Hydro for awarding the Project the most northerly hydro contract under the 2008 Clean Power Call

    Soucie Construction for their excellent work on pioneering the “Soucie Pass” access road summer 2010

    Minerals North organizers and volunteers