16

Click here to load reader

Low Delta T 4B2_Moe

Embed Size (px)

Citation preview

Page 1: Low Delta T 4B2_Moe

Low Delta T (∆T)is Far Too Expensive

for District Cooling

Eric M. MoeIDEA Annual Conference

Scottsdale, ArizonaJune 2007

Page 2: Low Delta T 4B2_Moe

Common(and Expensive)

Myths

Energy – Capacity – Complexity - Comfort

Page 3: Low Delta T 4B2_Moe

Myth: Without decoupling buildings or indirect connections, existing (low ∆T) cooling coils are incompatible with the new (high ∆T) plant.

chilled water plant41/57F design

(5.0/13.9C)

1000 toncustomer

45/55F coils(7.2/12.8C)

1500 toncustomer

44/56F coils(6.7/13.3C)

41F(5.0C)

16F (8.9C) ∆T

10F (5.6C) ∆T12F (6.7C) ∆T

Page 4: Low Delta T 4B2_Moe

Reality: Colder water and better control will deliver greater than design ∆T at peak and part load

Energy Labs Coil 5WC-0 806-54x160-A36/6C

0

10

20

30

40

50

60

70

80

0 50 100 150 200 250

Flow Rate (gpm)

Coo

ling

Load

(ton

s)

41F (7.2C) EWT45F (5.0C) EWT

Colder CHWST to Coil Increases ∆T∆T Rises Above Design at Part Load

10.0F (5.6C) ∆T

16.2F (9.0C) ∆T

19.8F (11.0C) ∆T

Page 5: Low Delta T 4B2_Moe

Avoid the Expense: Design with cold water and better control to achieve high ∆T at cooling coils

• Design the chilled water plant and distribution for high ∆T despite low ∆T cooling coils in buildings

• Simplify customer interconnections– Direct connect if possible, HEX if required– Maintain the supply water temperature to coils– Avoid return water temperature control

• Rely on (high quality) pressure independent control– Achieve high ∆T performance across coils – Eliminate balancing, even as a system expands

Page 6: Low Delta T 4B2_Moe

Myth: System performance (including ∆T) can be optimized at the building interface alone

T

T

LAT

T

T

LATVFD (w/ 2-way & balancing valves)

Building level return watertemperature control

Decoupling (blending)

HEX (indirect connection)

Flow limiter (balancing)

Page 7: Low Delta T 4B2_Moe

Reality: Low ∆T at coils commonly leads to rising supply water temperature which adversely affects performance for the utility and its customer

32

42

52

62

72

82

Two Weeks in July 2007

Tem

pera

ture

(deg

F)

0

6

11

17

22

28

Tem

pera

ture

(deg

C)

Wet Bulb Outside Air Temperature

Supply Water Temperature To Building

Supply Water Temperature To Coils

Page 8: Low Delta T 4B2_Moe

Avoid the Expense: Achieve high ∆T at coils to reduce total energy use, retain customers, simplify systems, and get paid

• For the Chilled Water Utility– Re-capture lost latent cooling revenue

• Eliminate low ∆T at the loads• Maintain low chilled water supply temperature to coils

– Acquire, satisfy, and retain customers• More comfort, greater efficiency, less equipment, lower costs

• For the Connected Customer– Minimize complexity

• Direct connections, HEX if required, no balancing– Reduce pump and fan energy consumption

• Higher ∆T in building, maintain low supply air temps• Remove pumps if not required

Page 9: Low Delta T 4B2_Moe

Myth: District cooling utilities can’t control what customer’s choose to do within their buildings.

• Lowest first cost design• Insufficient maintenance, dirty coils• Bypasses, 3-way valves, C/S pumps• Bad pump, pipe, and valve sizing practice• Minimal engineering, oversized equipment• Poor chilled water flow control• Low leaving air temperature

Page 10: Low Delta T 4B2_Moe

Reality: District cooling utilities may develop rate structures that influence customer design and performance

$/ton-hr ∆T (°F) ∆T (°C) gpm/ton$0.22 ≤13 ≤7.2 1.85$0.21 14 7.8 1.71$0.20 15 8.3 1.60$0.19 16 8.9 1.50 chilled water plant design$0.18 17 9.4 1.41$0.17 18 10.0 1.33$0.16 19 10.6 1.26$0.15 ≥20 ≥11.1 1.20

It may take a carrot to add a stick to change existing long term contracts!

Page 11: Low Delta T 4B2_Moe

Example: ~ 25,000 ton commercial plant with ongoing (expensive) low ∆T issues

• New plant designed for 10°F (5.6°C) ∆T - coils have 15°F (8.3°C) ∆T capability with 40°F (4.4°C) supply

• Direct customer connections in original design, no decoupled buildings or heat exchangers

• Additional chiller added after startup due to low ∆T performance in buildings

• Utility now has a rate structure that penalizes customers with poor ∆T performance

• Some customers are adding heat exchangers to try to deal with low ∆T

• Rising supply water temperature is creating comfort issues in customer buildings

Page 12: Low Delta T 4B2_Moe

What to Do: Explore common low ∆T issues relative to coil, distribution, and plant capability

• Low return temperature (to the plant)• High supply temperature (to cooling coils)• Where does the excess water go?

– Overflow running chillers– Operate additional chillers– Blend return water with supply– Quickly deplete TES capacity

Page 13: Low Delta T 4B2_Moe

What to Do: Use ARI certified software to fully understand coil capability at peak and part Load

Energy Labs 5WC-0 806-36x160-A14/10C

0%

20%

40%

60%

80%

100%

120%

0% 20% 40% 60% 80% 100%

Coil Design Flow (%)

Coo

ling

Load

(%)

Design Conditions (16.0F, 8.9C ∆T)

Actual Peak Load (21.6F, 12.0C ∆T)

explore what happens withchanges to the entering waterand leaving air temperatureconditions

Page 14: Low Delta T 4B2_Moe

What to Do: Assess the economic benefit of correcting low peak and part load ∆T

Example: 12,000 Ton (Growing) Level 1 Trauma Center“10°F (5.6°) ∆T Coils with a 16°F (8.9°C) ∆T Plant”

– Retrofit project– Pressure independent control (DeltaPValves), no new coils– Reduced gpm/ton by over 60% raising part load ∆T from 7°F (3.9°C)– Removed building pumps and bridges– Increased peak load ∆T from 12 to 16°F (6.7 to 8.9°C) – 7,082,381 kWh annual savings (equivalent lbs CO2 reduced)– 53,631 kW reduction at peak (campus has CHP and reverse metering)– Increased available system capacity by ~ 3000 tons– Improved system reliability and comfort control– Eliminated waterside balancing requirements

$1,260,000 investment ($105/ton)$708,238 annual savings (plant energy alone)

1.78 years simple payback

Page 15: Low Delta T 4B2_Moe

What to Do: To drive good design, create chilled water contracts that vary with ∆T performance

Example: 4,500 Ton District Cooling (Airport) Customer“Penalties in contract for less than 18°F (10°C) ∆T”

– New construction project– Pressure independent control (DeltaPValves) at coils– 38/56°F (3.3/13.3°C) chilled water plant design– Thermal storage (ice) is fully utilized to minimize peak load– Cold water maintained all the way to cooling coils– Customer achieves 20-24°F (11.1-13.3°C) ∆T at all loads– Distribution managed with a single secondary pump in central plant– No excess pumping, piping, control, balancing, or heat transfer

equipment in the terminal buildings

Page 16: Low Delta T 4B2_Moe

Questions?

Eric MoeFlow Control [email protected]: 425-483-1297Cell: 206-890-3266