Powerpoint Templates L OW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A CTIVITIES MS4 Statewide Stormwater Summit June 18, 2013 Evan Canfield, Ph.D, P.E. Pima County Regional Flood Control

LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Powerpoint Templates

LOW IMPACT DEVELOPMENT GUIDANCE MANUALAND LID WORKING GROUP

ACTIVITIES

MS4 Statewide Stormwater SummitJune 18, 2013

Evan Canfield, Ph.D, P.E.Pima County Regional

Flood Control

Page 2: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Outline• Origin of the LID Working Group• Products that Provide Guidance on GI/LID Practices

• Case Studies Catalog• Where do we go from here?

Page 3: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

March 21, 2011 LID Workshop ‐ Initiate Dialogue Among Experienced Professionals 

Form LID WorkingGroup of Interested 

Professionals

PAG Resolution Supporting Green Infrastructure and 

Low Impact Development

Development of Products 

Supporting GI/LID

Origin of the LID Working Group

Page 4: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

PAG Regional Council GI/LID Resolution

Page 5: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

LID Working Group Priorities (08/22/11)Product TotalLID Site Design BMP Guidance 7Manual providing examples of successful (and unsuccessful) projects (or BMPs?) 6Identification of Barriers to Adoption of LID 3A Set of Performance Metrics/Indicators 3Develop LID Education Materials 2Annual Conference 1.5LID Roadway Design Manual 1A BMP Maintenance Manual 1Contact List 1ProcessesRecognize Accomplishments 1Develop an LID Policy 1On-going Coordination 2Areas of Interest (not mentioned above)Influence Policy 2Write Grants/ seek funding 1

Do applied Research/Demonstration Projects to support LID 1

Page 6: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

LID Working Group Priorities (08/22/11)Product TotalLID Site Design BMP Guidance 7Manual providing examples of successful (and unsuccessful) projects (or BMPs?) 6Identification of Barriers to Adoption of LID 3A Set of Performance Metrics/Indicators 3Develop LID Education Materials 2Annual Conference 1.5LID Roadway Design Manual 1A BMP Maintenance Manual 1Contact List 1ProcessesRecognize Accomplishments 1Develop an LID Policy 1On-going Coordination 2Areas of Interest (not mentioned above)Influence Policy 2Write Grants/ seek funding 1

Do applied Research/Demonstration Projects to support LID 1

Page 7: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Outline• Origin of the LID Working Group• Products that Provide Guidance on GI/LID Practiceso Analysis and Design for Stormwater Management(i.e. Revised Regulatory Flood Detention‐Retention Guidance Manual)

o Guidance Manual for Low Impact Development and Green Infrastructure

• Case Studies Catalog• Where do we go from here?

Page 8: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Pima County:Draft Detention‐Retention Manual

Page 9: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Pima County:Draft Detention‐Retention Manual

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

0% 20% 40% 60% 80% 100%

Dai

ly P

reci

pita

tion

(inch

)

Percent

85th Percentile Rainfall 0.48 inch

Replace Retention Requirement with a‘First Flush’ Retention Requirement (data U of A Daily rainfall 1895‐2000)

Page 10: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Outline• Origin of the LID Working Group• Products that Provide Guidance on GI/LID Practiceso Analysis and Design for Stormwater Management(i.e. Revised Regulatory Flood Detention‐Retention Guidance Manual)

o Guidance Manual for Low Impact Development and Green Infrastructure

• Case Studies Catalog• Where do we go from here?

Page 11: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Goal

Demand Management Goal #5: Increase the use of rainwater and stormwater to reduce demands on potable supplies

Action Plan

Demand Management Action Plan #7:Develop Design guidelines for neighborhood stormwaterharvesting to encourage the creation of habitat and water efficient landscapes.

Page 12: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

‘Harvestable’ Water (Rainwater/Stormwater)i.e. water yield

Page 13: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing
Page 14: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Histogram of Annual RainfallUniversity of Arizona 1896‐2000 (water years)

Mean 11.29Median 10.61Standard Deviation 3.37Minimum 4.73Maximum 21.97

Count 105

Page 15: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Histogram of Daily Rainfall (1895 to 2000, University of Arizona)

Mean 0.25Median 0.14Standard Deviation 0.32Kurtosis 14.61Skewness 3.03Minimum 0.02Maximum 4.16Count 4712Number of events/yr 44.88

Page 16: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Impervious Doesn’t Mean a 

Roof Sheds 100% of the Rain Rough

Absorbent

Absorbent and Rough

Depression Storage

Page 17: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Total Volume of Rainfall and Runoff with 0.05” Threshold (1895 to 2000, University of Arizona)

Page 18: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Annual Peak Rainfall(U of A 1896‐2000 Water Years)

Mean 1.44Median 1.40Standard Deviation 0.57Minimum 0.45Maximum 4.16Count 105

Page 19: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Modeled Effect on Flood Mitigation(0.8 ac watershed, 80% impervious, harvesting 1.5”)

Page 20: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Example : Palo Verde 

Tree

Plant TypePlant ET Factors (Waterfall,High Low

LowWater Use 0.26 0.13MediumWater Use 0.45 0.26High Water Use 0.64 0.45

March Plant Water Use

ET March = ETO March X (Plant Water Use Factor)

ETO March = 4.90 inch (AZMET)

4.90 inch (0.26) = 1.27 inch

Effective P March= 50%x Pavg March

Pavg March = 0.77 inch

Need: 3.3 x catchment to canopy

0.01.02.03.04.05.06.07.08.09.0

10.0

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Ref

ernc

e E

T (E

To) -

Inch

/mon

th

Month

Page 21: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

LID Planning Practices Should Be Considered Before Structural Practices

LowImpactDevelopmentBenefits

SitePlanning(AvoidanceandPrevention)

GreenInfrastructure(Structural)

• Flood Control• Stormwater Management•Pollution Prevention•Energy Efficiency•Pedestrian Friendly

• Preserve Natural Flow Paths•Minimize Impervious area•Reduce Disturbed and Compacted Soils

• Rainwater and StormwaterHarvesting Features

•Naturalized Conveyance Features

Page 22: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing
Page 23: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

LID Planning Practices

Page 24: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Alternative Site Design

Page 25: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Structural Practices

Page 26: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Pervious Pavements

Page 27: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Curb Cut Standards

Page 28: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Water Harvesting Basins

Page 29: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Outline• Origin of the LID Working Group• Products that Provide Guidance on GI/LID Practiceso Analysis and Design for Stormwater Management (i.e. Revised Regulatory Flood Detention‐Retention Guidance Manual)

o Guidance Manual for Low Impact Development and Green Infrastructure

• Case Studies Catalog• Where do we go from here?

Page 30: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Success Criteria (simplified)Key performance indicators

Stakeholder Requested

Planning Post‐Construction

N/A Included Successful Not SuccessfulRegulatory Requirements Met

Stormwater RunoffStormwater QualityResource Protection 

Sustainability Elements Optimized includedWater ConservationNatural Area EnhancementUrban Heat Island MitigationEducation

Cost Acceptable includedCost Estimate Within BudgetProjected Maintenance Costs Favorable

Implementation Successful includedConstructability AcceptableStakeholder Expectations MetMaintenance Entity Identified

Project Recognition includedAwards Received

Project Function Successful includedEase of Maintenance Value and Function Retained

Page 31: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Case Study: 20‐30 Park (Highland Vista Park): Collector street – residential land useNative vegetation irrigated with harvested stormwater, reduced ponding and associated mosquito problems

Page 32: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Infiltration Trenches

Page 33: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

20‐30 Park

Page 34: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Outline• Origin of the LID Working Group• Products that Provide Guidance on GI/LID Practiceso Analysis and Design for Stormwater Management (i.e. Revised Regulatory Flood Detention‐Retention Guidance Manual)

o Guidance Manual for Low Impact Development and Green Infrastructure

• Case Studies Catalog

• Where do we go from here?

Page 35: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Where do we go from here?• Finish Guidance Manual ‐ review of the work in progress by the LID Working Group.

• Working draft by end of 2013. Circulated as a web page.

• ‘Final’ version by July 2015.• Continue to Gather Case Studies.

Page 36: LOW IMPACT DEVELOPMENT GUIDANCE MANUAL AND LID WORKING GROUP A · 2013-07-01 · LID Working Group Priorities(08/22/11) Product Total LID Site Design BMP Guidance 7 Manual providing

Questions

Evan Canfield: [email protected]