7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
1/24
RPSCLROSA POWER SUPPLY COMPANY LIMITED
LUCKNOW, UTTAR PRADESH
2 x 300 MW - Stage - I
Rosa Thermal Power Project
Rosa, Shahjahanpur (U.P.)
DOCUMENT TITLE
Turbine Bypass System Commissioning Procedure
DOCUMENT NO:
LS-TSZD-- QJ 005
UEEPL
Utility Energytech and Engineers Pvt. Ltd.
Ground Floor, H-146/147
Sector-63
Noida 201 307
Uttar Pradesh
DEVELOPMENT CONSULTANTS PRIVATE
LIMITED CONSULTING ENGINEERS
24B, PARK STREET, KOLKATA - 700 016, INDIA
TPSC (INDIA) PRIVATE LIMITED
A-1 Module, D-Quadrant, 2nd Floor
Cyber Towers, Hi-Tec City, Hyderabad-81
Shanghai Electric Group Co. Ltd.
No. 8 , Xingyi Road.
Shanghai
China - 200336
Tianjin Electric Power Construction Company
The 26th floor, Harbor Centre ,No. 240
Zhangzizhong Road, Heping district, Tianjin
P.R.China p.c:300041
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
2/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 1 of 23
DOCUMENT CONTROL SHEET
PROJECT : 2300 MW ROSA THERMAL POWER PROJECT
CLIENT : ROSA POWER SUPPLY COMPANY LIMITED
DOCUMENT TITLE : TURBINE BYPASS SYSTEM COMMISSIONING PROCEDURE
DOCUMENT NO. : LS-TSZD-- QJ005
REV. NO. : 3
ENDORSEMENTS :
3
Initials Sgn. Initials Sgn. Initials Sgn. Initials Sgn.RevNo
Date DescriptionPrepared by Reviewed by Approved by
IssueAuthorization
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
3/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 2 of 23
Technical training list for commissioning measure
Number:Project name
Technical training list
Unit name
Specialty System Date
Training contents:
Complementarily and modification
Trained person
Training person Project in charge person
Remarks
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
4/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 3 of 23
Contents
1. Project overview and work quantity ...........................................................................................4
1.1 Project overview ............................................................................................................................4
1.2 Commissioning schedule ...............................................................................................................7
2 .System function introduction...........................................................................................................7
3. Compiling basis ...............................................................................................................................7
4. Required conditions before turbine bypass system commissioning ................................................8
4.1 Organization and division of work ................................................................................................8
4.2 Required conditions before system commissioning ......................................................................8
4.3 Commissioning person deployment and qualification.................................................................10
4.4 Equipment and instruments for commissioning.......................................................................10
5. Commissioning procedure and method......................................................................................10
5. Flow chart...................................................................................................................................10
5.2 Commissioning procedure and methods ..................................................................................12
6. Commissioning quality checking standard ................................................................................17
6.1 key control point setting...........................................................................................................17
6.2 Quality standard .......................................................................................................................18
6.3 Recording content ....................................................................................................................18
7. Safety requirement and environment condition during commissioning ....................................18
7.1 Danger factors identification and control.................................................................................18
7.2 Commissioning environment condition ...................................................................................19
8. Appendix ....................................................................................................................................19
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
5/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 4 of 23
This document is only for technical direction, is not the site construction and
commissioning execution document.1. Project overview and work quantity
1.1 Project overview
The boiler for India ROSA project 2300MW is of SG1025/17.5-M type designed and
made by Shanghai Boiler Works. It is of subcritical pressure parameter, natural circulation
drum, single furnace, once through reheating. Boiler continuous steam output is 1025t/h,
rated superheating steam temperature is 541, and pressure is 17.57Mpa. Turbine is of
N300-16.67/538/538 type made by Shanghai Turbine Company, Ltd. It is reversed
operation, single shaft, once reheat, two casings and two steam exhausts, pure
condensate type. Its rated power is 300MW. Generator is of QFSN-300-2 type made by
Shanghai Turbine Generator Co., Ltd, its rated power is 300MW, and cooling method is
water-hydrogen-hydrogen. Boiler makeup water is DM water.
The bypass system is supplied by Shanghai XIXIAI energy control equipment
company which is the hydraulic control system, and the type is the HLP secondary class
series hydraulic bypass. The design capability of HP bypass is 60% BMCR, and the LP is
60% BMCR plus desuperheating water quantity of HP bypass. HP bypass system includes
bypass valve and desuperheating water spray governing valve and isolation valve. And the
LP bypass system includes LP bypass valve and dusuperheating water spray governing
valve. The bypass control system adopts the hydraulic actuator, and the main equipments
are as following:
1) HP bypass valve (1 set)
2) HP bypass desuperheating spray valve (1 set)
3) HP bypass desuperheating isolation valve (1 set)
4) LP bypass valve (2 sets )
5) LP bypass desuperheating spray valve (2 sets)
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
6/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 5 of 23
Bypass system hydraulic oil station is made up by 2 nos oil pump and the
corresponding system that supply the high pressure oil to the system as the power
resource for hydraulic parts. Meanwhile, there has a accumulator installed on the oil supply
pipe to stabilize the system work pressure.
This bypass hydraulic control system includes the oil supply device, HP bypass
actuator, LP bypass actuator, HP accumulator parts, LP accumulator parts and pipe
fittings.
The working medium for the bypass hydraulic system is adopted the phosphate
burning resistance oil which has the good burning resistance and stability. And the oil is
supplied by the single oil supply device. The system work pressure range is 15-13.5 MPa.
And the oil temperature range is 40-55 deg C. While operation, the cleanness of the work
medium shall reach NAS 6 Class or higher Class.
Oil supply device has been set the regeneration device, circulation cooling device;
main pump, standby pump is designed as redundancy. This is supplying the power
resource for the actuator of the valve.
The valve actuator has two types, one is regulation type, and the other is switch type,
the HP & LP desuperheating valve actuator, HP & LP bypass spray governing valve
actuator is regulation type, and the HP bypass spray valve actuator is switch type. There
are two control methods for the regulation type valve, viz. normal regulating control and
fast control, this two methods are parallel, while the operation, this two control methods
are interlocked, and controlled by DCS.
In order to open or close the valve quickly, there is set the 40L HP accumulator and
40L LP accumulator for the HP bypass valve and LP bypass valve actuator respectively to
guarantee the valve can active quickly and guarantee the oil device supply oil or discharge
oil in time.
H P
b y p a s s
C o l d
s e c t i o n o f r e h e a t e r
M a i n
s t e a m R e h e a t e r
H e a t
s e c t i o n o f
r e h e a t e r
L P
b y p a s s
C o n d e n s e
r
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
7/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 6 of 23
Technical parameter of bypass system rating work condition
Valve name Model Inlet Rating flux(t/h)
Inlet workingparameter
Discharge
working
parameter
HP bypass
valveC7z61Y-P5519.2V 615
16.67
MPa/538
3.663
MPa/318.5
HP bypass
desuperheating
spray valve
Tp7z63Y-32.01
HP bypass
desuperheating
isolation valve
Tp764Y-32.01
LP bypass
valveC7z61Y-P554.6V 716.3
3.296
MPa/5380.598MPa/160
LP bypass
desuperheating
spray valve
Tp7z64Y-4.01
bypass valve regulating factor
Valve name Qty.Driving
methodActuator
Switch on/off
time
Design
capability
HP Bypass
valve1
Hydraulic
drivenBP-300
Switch off 3s
quickly, 3s
quick
60%BMCR
HP bypass
desuperheating
spray valve
2Hydraulic
drivenLBP-300
Switch off 3s
quickly, 3s
quick
70%BMCR
HP bypass
desuperheating
isolating valve
1Hydraulic
drivenBPE-300
Switch off 3s
quickly, 3s
quick
LP bypass 1 Hydraulic BD-300 Switch off 3s
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
8/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 7 of 23
valve driven quickly, 3s
quick
LP bypass
desuperheating
spray valve
2Hydraulic
drivenLBPE-300
Switch off 3s
quickly, 3s
quick
1.2 Commissioning schedule
The absolute commissioning schedule is 8 days.
2 .System function introduction
Bypass control system (BPS) is the important part to realize the unit auto control, it
plays a very important role while unit start up, normal stop and emergency stop. The
function of this system is to make the operation parameter in a controlled range, to
guarantee the unit safety and economic operation. Desuperheating water of HP bypass is
from the feeder water system, and the desuperheating water of LP bypass is from the
condensate water system.
HP & LP bypass valve is the angle type bypass valve with the throttle spray valve.This bypass valve can lead the main steam going through the bypass to the cold section of
reheater and also lead the reheater heat section steam going through LP bypass to the
condenser while the unit start-up, stop or at other conditions. Through TG setting, this
system can make the unit on load operation with the auxiliary power. While the turbine
tipping or generator breaker switch on, it can make the HP & LP bypass open
automatically. The valve leakage glass is the minimum V glass, and the spray valve
outlet flow speed shall not exceed 30M/S.
3. Compiling basis
3.1 Indian ROSA 2 x 300MW unit commissioning outline
3.2 Indian ROSA project equipment erection instruction
3.3 Indian ROSA project China-Indian general contract
3.4 The relevant drawings from GEDI
3.5 Equipment instruction, drawings, and data documents for Indian ROSA project
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
9/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 8 of 23
generator bypass system
4. Required conditions before turbine bypass system commissioning
4.1 Organization and division of work
NO. Organization and division of work Confirmation
4.1.1
Under organized and directed by sub-system commissioning
group, the person in charge of commissioning should carry out
commissioning of system and make out commissioning
measures of such system.
4.1.2
Commissioning person should be responsible for transmission
of related valve, C&I signal and interlock in the system. Before
the trial, shall give the technical and safety training, Meanwhile,
measure and record necessary data.
4.1.3
Operation person is in charge of the operating and operation
monitoring, making the safety isolation for the trial run
equipments.
4.1.4
Construction unit should be responsible for finishing
commissioning of related individual units in the system and
maintaining, overhauling and eliminating the defects in
commissioning of system. Organize and coordinate safety,
fire fighting and safeguard works on commissioning site
4.1.5
The commissioning direction unit shall be in charge of
compiling the commission measure and directing the site
commissioning. And shall make the technical training before
trial run.
4.1.6
Supervision unit shall be in charge of coordinating and
attending the system acceptance, coordinating the equipment
and system storage problem, and coordinating the problems
disposal which happened in the commissioning. Quality
supervising and checking before/ after trial run.
4.2 Required conditions before system commissioning
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
10/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 9 of 23
NO. Required conditions before commissioning Confirmation
4.2.1
Site is flat without debris, the scaffolding shall be removed, the
handrail of stairways shall be installed completely, and
adequate light is prepared. Fire fighting device is ready. There
shall have the clear dividing line around the trial run site. The
warning board or enclosure shall be set around the danger
area
4.2.2Covers of ditch and holes are complete; ladders, paths,
handrails are available for platform.
4.2.3 Enough firefighting facilities are available at site;
4.2.4Adequate light is ready for using at the trail run site. And the
emergency light can operate automatically.
4.2.5 Good ventilation establishment
4.2.6 Good communication system.
4.2.7 Equipments, pipes, valves shall be hanged the nameplate
4.2.8
Equipment and system are installed as per the requirement
and accepted. The installation recording is complete. And the
relevant equipment individual trial run is finished.
4.2.9The instrument calibration is accepted, and the warning and
showing is correct.
4.2.10The person deployment is clear, and the commissioning work
training is finished.
4.2.11
Equipment and system are installed as per the requirement
and accepted. The installation recording is complete. And therelevant equipment individual trial run is finished. And the unit
is ready for starting.
4.2.12
The entire pipes and equipment in the bypass system shall be
installed complete. The oil circu8lation is finished, oil quality is
accepted, the oil pressure test for hydraulic pipe is accepted,
the bypass oil station commissioning is accepted.
4.2.13 The pressure filling to accumulator is finished.
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
11/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 10 of 23
4.2.14
Calibration, erection and wire connection for C & I and
electrical equipment is finished, and the bypass system C & I
commissioning is finished and accepted.
4.2.15
The steam blowing for HP bypass system is accepted, and the
cleaning for LP bypass system is accepted, flushing for HP, LP
bypass desuperheating piping is accepted.
4.2.16
Commissioning instrument is ready, the calibration for the
instrument is accepted, and the precision of the test instrument
meets the requirement.
4.3 Commissioning person deployment and qualification
Sn. Person Qty Quality Responsibility
1Commissioning
person2 Commissioning
In charge of executing the
measure and operation
direction
2Erection
person4
Technical person in
charge and person on
duty
Maintenance and overhaul
3Operation
person
So
manyOperator Each operation during test
4.4 Equipment and instruments for commissioning
S.N. Items Model Precision Qty Remarks
1 Infrared thermal meter 1
5. Commissioning procedure and method
5. Flow chart
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
12/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 11 of 23
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
13/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 12 of 23
5.2 Commissioning procedure and methods
5.2.1 System commission plan
S.N. Items Content Result Time Remarks
1Systeminspection
Inspect the mainsteam ,reheating steam/
bypass system piping as perthe scheme
Main steam and reheatingsteam bypass pipe system
blowing
HP & LP bypass
desuperheating water pipeflushing
Control oil system circulation
2Systemblowing
Cleanness checking
Main steam pipe hydraulictest
Main steam reheating steampipe steam tightness test
Governing valve, spray valveleakage test
3Systemtightness
Electrical motoroperation
commissioning
Measurement and C & Isignal
Interlock protection loop
Function groupcommissioning
4C & I
commissioning
Auto regulation loop
Control oil system
HP & LP bypass governingvalve
HP & LP desuperheatingspray valve
Close LP bypass governingvalve
5Componentcommissioning
Discharge valve
6 C & I systemtest
Signal, interlock andprotection test
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
14/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 13 of 23
Function group test
Control system factor test
7Static state
regulation test Regulation functionsimulation test
Operation at any condition
8System
operationBypass system
operation
Operation characteristicchecking
Parameter optimizing setting 9 Test regulation
after operationDynamic characteristic
inspection on the loadrejection condition andother working condition
5.2.2 System commissioning items
5.2.2.1 Inspect the complete bypass system.
5.2.2.2Transmission test, switch on/off test shall be done for the valve to check
whether it is flexible and reliable.
5.2.2.3 DAS measurement point and local instrument checking
5.2.2.4 Interlock protection and C & I signal test
5.2.2.5 Bypass system, static state function test
5.2.3 Main commissioning procedure
5.2.3.1 bypass system static state commissioning
A Bypass valve static state characteristic test
1HP & LP bypass governing valve switch feedback calibration, fast switch on/ off
time measurement
2HP bypass spray governing valve switch feedback calibration, fast switch on/off
time measurement
3LP bypass spray governing valve switch feedback calibration, fast switch on/off
time measurement
B Bypass system control function and interlock protection test
1 HP bypass protection test
HP bypass protection function, the HP bypass is forced to close in the following status
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
15/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 14 of 23
a) manual HP valve close quickly
b) HP spray valve pressure is lower
c) reheater pressure is higher
The HP bypass desuperheating water control: HP bypass desuperheating water control
subsystem to control HP bypass outlet temperature in the suitable temperature around the
setting value.
HP decompression control: the HP bypass decompression control subsystem to
control the main steam pressure as per the pressure setting value. Before the HP cylinder
starting to stably the main steam pressure till the unit parameter reaches to the turbine
rolling parameter, and then the HP bypass valve is switch to the heating standby status.
While the HP cylinder starting, in order to avoid affecting the reheater pressure and HP
cylinder steam discharge stop valve action caused by HP bypass switch on/off quickly, the
auto control of the bypass shall be changed into manual control. In addition, while the unit
operated as load rejection model, the HP bypass can be operation in time.
2 LP bypass control function
LP bypass protection function, the LP bypass is forced to close as the following status:
a) condenser vacuum pressure is low
b) condenser temperature is high
c) LP desuperheating spray water pressure is low
d) three-class desuperheating water pressure is low
e) condenser water level is high
The LP bypass is open as the following status:
a) reheating steam pressure is high
b) open the LP bypass by manual methodLP bypass desuperheating water control: LP bypass desuperheating water control
subsystem to control the LP bypass outlet temperature in the suitable value around the
setting value. .
LP bypass keeps closed while the HP cylinder starting. Before the turbine rolling, the
LP bypass valve switch to heat standby status, in addition, while the unit is operated as the
load rejection model, the LP bypass can operate immediately.
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
16/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 15 of 23
3 Reheating steam over-pressure protection
While the unit operation, if the deviation between reheating steam pressure and the
setting value is more than___ MPa (refer to the setting value from GEDI) or the reheating
steam pressure exceeds ___ MPa (refer to the setting value from GEDI), the LP bypass
open immediately, and the LP desuperheating valve is also open.
4 condenser protection test
While the condenser vacuum is lower, and the condenser water level or the high
temperature protection at the downstream of the LP are active, LP decompression valve
shall be close, meanwhile, the LP desuperheating valve is also close,
5.2.3.2 bypass control system dynamic commissioning
ARegulate the dynamic control parameter of each control subsystem at the
different load, and setting the corresponding PID parameter.
B
After the bypass control system operation and the control parameter regulated,
the setting valve dynamic perturbation test for this control system shall be done
to precisely regulate the control parameter and improve the regulation quality of
control system while the controlled heating power system is operated stably.
5.2.3.3 bypass system operation
A operation condition
1 Bypass system static state commissioning work is finished.
2water discharge system commissioning for main steam, reheating steam is
finished, and this system is ready for operation
3 The staring preparation work of the main unit is finished.
B system operation
1Open the water discharge valve of the bypass system, HP & LP bypass are
operated automatically.
2
After the boiler lighting and the pressure generation, HP bypass is switch to the
minimum opening, and the LP bypass is opening gradually, go along with the
main steam parameter rising, warm the HP & LP bypass piping. Control the
temperature rising speed to 2 deg C per min. While the main steam pressure
rising to the setting value, control the HP bypass valve to maintenance the main
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
17/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 16 of 23
steam valve at the setting value.
3Control the LP bypass opening as per the main steam pressure changing to
maintenance the main steam setting valve.
4During operation, monitor the desuperheating water governing valve following
status, checking the pipe expansion, and discharge is normal.
5.2.3.4 test after bypass system operation
The test after bypass system operation shall be finished before the turbine rolling.
Because the HP cylinder is operating, before the turbine rolling, first, secondary class
bypass system shall be removed.
1 bypass system characteristic test
A test goal
1Measure the relationship between HP & LP bypass governing valve pressure
and flux characteristic
2 Check the spray desuperheating system working characteristic
B Test condition
1 Unit bypass is operation, and the main body is in the barring gear status
2 Bypass operation is normal
3 Boiler operation is normal
4 Condenser vacuum is normal
5 Circulation water system is operation
C test procedure
1 HP bypass characteristic test
a) Under the different opening of the governing valve, change the boiler working rate,
doing the test till the bypass system valve is full open and the main steam parameter
reaches to the rating valve
b) During test, the LP bypass is in the following model, the HP bypass desuperheating
water is operated automatically.
c) Record the relative data
d) Calculate the characteristic relationship
2 LP bypass characteristic test
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
18/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 17 of 23
a) Under the different opening of the governing valve, change the boiler working rate
and the HP bypass opening, doing the test till the LP bypass governing valve is full open
and the main steam parameter reaches to the rating valve
b) During test, the LP desuperheating water can operate automatically, and the HP
bypass can be operated by manual method.
c) Record the relative data
d) Calculate the characteristic relationship
2 dynamic characteristic test
Before the load rejection operation model, the warming and water discharge shall be done
for the bypass system, while the unit load rejection operation starting, the HP & LP bypass
valve open immediately, in order to estimate the HP & LP spray desuperheating water
refection characteristic, record the valve open time, steam pressure, temperature stability
valve, peak value and its time.
6. Commissioning quality checking standard
6.1 key control point setting
Inspection unit
Sn. Work controlpoint Constru
ction
Commissionin
g
Development
unit
Produce unit
Supervisionunit
Witness method
1
Bypass oilstation
control oilpressure andtemperature
* * * R
2
Bypass oilstation oil
flushing andoil cleanness
* * * * * R
3
Bypasssysteminterlock
protectiontest
* * * * * R
4
Fast opentime forbypasssystem
* * * * * R
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
19/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 18 of 23
R- record confirmed point W- witness point Hhold for inspection point Ssupervise
continually6.2 Quality standard
Sn. Items Inspection standard
1 Interlock and signalItem completely, and the action
is correct
2 Fast open time of Bypass system 3S
6.3 Recording content
1 HP & LP bypass system valve transmission recording list
2 HP & LP bypass system subsection trial run recording list
3 HP & LP bypass system logical transmission recording list
7. Safety requirement and environment condition during commissioning
7.1 Danger factors identification and control
Danger factors identification and control list
Sn. Description Control and strategy
Executive
person in
charge
Signature
person
1
lose control of
temperature and
pressure
Operation person and
erection person to check the
equipment operation status
periodically
Operation
person,
erection
person
Commissioning
person in
charge
2Injured by the
system leakage
Operation person and
erection person to check the
equipment operation status
periodically
Operation
person,
erection
person
Commissioning
person in
charge
3Leakage in the
steam valve
Operation person and
erection person monitor the
pressure and temperature on
the downstream of bypass
Operation
person,
erection
person
Commissioning
person in
charge
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
20/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 19 of 23
valve periodically, and
dispose the leakage once the
leakage appeared.
4
LP bypass
desuperheating
water pressure is
lower, the LP
bypass will be
open by
interlocked
Maintenance the CEP normal
operation to avoid the low
pressure at the CEP outlet
Operation
person,
erection
person
Commissioning
person in
charge
7.2 Commissioning environment condition
Sn. Description Control strategy
Executive
person in
charge
Signature
person
1 Steam leakage
Operation person and
erection person to check the
equipment operation status
periodically
Operation
person,
erection
person
Commissioning
person incharge
8. Appendix
NO. Content
1 HP & LP bypass system subsection trial run recording list
2 HP & LP bypass system logical transmission recording list
3 HP & LP bypass system valve transmission recording list
4 HP & LP bypass system subsection trial run acceptance and signature card
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
21/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 20 of 23
Number Unit subsystem commissioning recording list
Specialty Turbine HP & LP bypass system
Motor bearing vibration Oil pump bearing vibration
Time Leveldirection
Axialdirection
Verticaldirection
Leveldirection
Axialdirection
Verticaldirection
Motorbearingtemperature
Oil pumpbearingtemperature
Outletpressure ofpump
Commissioning in charge person : Commissioning recording person:
Date:
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
22/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 21 of 23
Number Unit subsystem commissioning recording list
Specialty TurbineHP & LP bypass system logical transmission
recording
Sn. Items Result Signature
Commissioning in charge person : Commissioning recording person:
Date:
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
23/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 22 of 23
Number Unit subsystem commissioning recording list
Specialty Turbine HP & LP bypass system valve transmission recording
Valve name Fast open times Fast close
timesOpen times Close times Remarks
Commissioning in charge person : Commissioning recording person:
Date:
7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure
24/24
Turbine Bypass SystemCommissioning Procedure
2300 MW Rosa ThermalPower Project
DOCUMENT NO. : LS-TSZD-- QJ005 Page 23 of 23
Subsection trial run acceptance and signature card
Specialty: turbine Item name: turbine bypass system
Turbine specialty HP & LP bypass system Date
EvaluationSn. Inspection Content
Acceptance Non-acceptanceRemarks
1System interlock protection and signal itemcomplete, and action is correct
2System C & I instrument is complete, andthe show is correct
3System pressure, temperature parameter
is conformed to the design regulation4
System trial run, each valve is flexible, andcan be operated normally
5 Piping is tightness without leakage
Evaluation:
The subsection trial run of this equipment/system has been completed between _____
(Day) _____ (Month), _____ (Year) and _____ (Day) _____ (Month), _____ (Year).
Through acceptance inspection according to the Criteria for Acceptance Inspection and
Assessment of Adjustment Commissioning Quality of Thermal Power Projects by former
Ministry of Electric Power, this equipment/system is rated as qualified ( ) / good ( )
and has achieved conditions required for operation. We hereby agree to enter the whole-set
startup stage.
Construction unit signature : Date:
Commissioning unit signature Date:
Commissioning direction unit signature Date:
Production unit signature Date:
Development unit signature Date:
Supervision unit signature Date: