LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

Embed Size (px)

Citation preview

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    1/24

    RPSCLROSA POWER SUPPLY COMPANY LIMITED

    LUCKNOW, UTTAR PRADESH

    2 x 300 MW - Stage - I

    Rosa Thermal Power Project

    Rosa, Shahjahanpur (U.P.)

    DOCUMENT TITLE

    Turbine Bypass System Commissioning Procedure

    DOCUMENT NO:

    LS-TSZD-- QJ 005

    UEEPL

    Utility Energytech and Engineers Pvt. Ltd.

    Ground Floor, H-146/147

    Sector-63

    Noida 201 307

    Uttar Pradesh

    DEVELOPMENT CONSULTANTS PRIVATE

    LIMITED CONSULTING ENGINEERS

    24B, PARK STREET, KOLKATA - 700 016, INDIA

    TPSC (INDIA) PRIVATE LIMITED

    A-1 Module, D-Quadrant, 2nd Floor

    Cyber Towers, Hi-Tec City, Hyderabad-81

    Shanghai Electric Group Co. Ltd.

    No. 8 , Xingyi Road.

    Shanghai

    China - 200336

    Tianjin Electric Power Construction Company

    The 26th floor, Harbor Centre ,No. 240

    Zhangzizhong Road, Heping district, Tianjin

    P.R.China p.c:300041

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    2/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 1 of 23

    DOCUMENT CONTROL SHEET

    PROJECT : 2300 MW ROSA THERMAL POWER PROJECT

    CLIENT : ROSA POWER SUPPLY COMPANY LIMITED

    DOCUMENT TITLE : TURBINE BYPASS SYSTEM COMMISSIONING PROCEDURE

    DOCUMENT NO. : LS-TSZD-- QJ005

    REV. NO. : 3

    ENDORSEMENTS :

    3

    Initials Sgn. Initials Sgn. Initials Sgn. Initials Sgn.RevNo

    Date DescriptionPrepared by Reviewed by Approved by

    IssueAuthorization

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    3/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 2 of 23

    Technical training list for commissioning measure

    Number:Project name

    Technical training list

    Unit name

    Specialty System Date

    Training contents:

    Complementarily and modification

    Trained person

    Training person Project in charge person

    Remarks

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    4/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 3 of 23

    Contents

    1. Project overview and work quantity ...........................................................................................4

    1.1 Project overview ............................................................................................................................4

    1.2 Commissioning schedule ...............................................................................................................7

    2 .System function introduction...........................................................................................................7

    3. Compiling basis ...............................................................................................................................7

    4. Required conditions before turbine bypass system commissioning ................................................8

    4.1 Organization and division of work ................................................................................................8

    4.2 Required conditions before system commissioning ......................................................................8

    4.3 Commissioning person deployment and qualification.................................................................10

    4.4 Equipment and instruments for commissioning.......................................................................10

    5. Commissioning procedure and method......................................................................................10

    5. Flow chart...................................................................................................................................10

    5.2 Commissioning procedure and methods ..................................................................................12

    6. Commissioning quality checking standard ................................................................................17

    6.1 key control point setting...........................................................................................................17

    6.2 Quality standard .......................................................................................................................18

    6.3 Recording content ....................................................................................................................18

    7. Safety requirement and environment condition during commissioning ....................................18

    7.1 Danger factors identification and control.................................................................................18

    7.2 Commissioning environment condition ...................................................................................19

    8. Appendix ....................................................................................................................................19

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    5/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 4 of 23

    This document is only for technical direction, is not the site construction and

    commissioning execution document.1. Project overview and work quantity

    1.1 Project overview

    The boiler for India ROSA project 2300MW is of SG1025/17.5-M type designed and

    made by Shanghai Boiler Works. It is of subcritical pressure parameter, natural circulation

    drum, single furnace, once through reheating. Boiler continuous steam output is 1025t/h,

    rated superheating steam temperature is 541, and pressure is 17.57Mpa. Turbine is of

    N300-16.67/538/538 type made by Shanghai Turbine Company, Ltd. It is reversed

    operation, single shaft, once reheat, two casings and two steam exhausts, pure

    condensate type. Its rated power is 300MW. Generator is of QFSN-300-2 type made by

    Shanghai Turbine Generator Co., Ltd, its rated power is 300MW, and cooling method is

    water-hydrogen-hydrogen. Boiler makeup water is DM water.

    The bypass system is supplied by Shanghai XIXIAI energy control equipment

    company which is the hydraulic control system, and the type is the HLP secondary class

    series hydraulic bypass. The design capability of HP bypass is 60% BMCR, and the LP is

    60% BMCR plus desuperheating water quantity of HP bypass. HP bypass system includes

    bypass valve and desuperheating water spray governing valve and isolation valve. And the

    LP bypass system includes LP bypass valve and dusuperheating water spray governing

    valve. The bypass control system adopts the hydraulic actuator, and the main equipments

    are as following:

    1) HP bypass valve (1 set)

    2) HP bypass desuperheating spray valve (1 set)

    3) HP bypass desuperheating isolation valve (1 set)

    4) LP bypass valve (2 sets )

    5) LP bypass desuperheating spray valve (2 sets)

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    6/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 5 of 23

    Bypass system hydraulic oil station is made up by 2 nos oil pump and the

    corresponding system that supply the high pressure oil to the system as the power

    resource for hydraulic parts. Meanwhile, there has a accumulator installed on the oil supply

    pipe to stabilize the system work pressure.

    This bypass hydraulic control system includes the oil supply device, HP bypass

    actuator, LP bypass actuator, HP accumulator parts, LP accumulator parts and pipe

    fittings.

    The working medium for the bypass hydraulic system is adopted the phosphate

    burning resistance oil which has the good burning resistance and stability. And the oil is

    supplied by the single oil supply device. The system work pressure range is 15-13.5 MPa.

    And the oil temperature range is 40-55 deg C. While operation, the cleanness of the work

    medium shall reach NAS 6 Class or higher Class.

    Oil supply device has been set the regeneration device, circulation cooling device;

    main pump, standby pump is designed as redundancy. This is supplying the power

    resource for the actuator of the valve.

    The valve actuator has two types, one is regulation type, and the other is switch type,

    the HP & LP desuperheating valve actuator, HP & LP bypass spray governing valve

    actuator is regulation type, and the HP bypass spray valve actuator is switch type. There

    are two control methods for the regulation type valve, viz. normal regulating control and

    fast control, this two methods are parallel, while the operation, this two control methods

    are interlocked, and controlled by DCS.

    In order to open or close the valve quickly, there is set the 40L HP accumulator and

    40L LP accumulator for the HP bypass valve and LP bypass valve actuator respectively to

    guarantee the valve can active quickly and guarantee the oil device supply oil or discharge

    oil in time.

    H P

    b y p a s s

    C o l d

    s e c t i o n o f r e h e a t e r

    M a i n

    s t e a m R e h e a t e r

    H e a t

    s e c t i o n o f

    r e h e a t e r

    L P

    b y p a s s

    C o n d e n s e

    r

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    7/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 6 of 23

    Technical parameter of bypass system rating work condition

    Valve name Model Inlet Rating flux(t/h)

    Inlet workingparameter

    Discharge

    working

    parameter

    HP bypass

    valveC7z61Y-P5519.2V 615

    16.67

    MPa/538

    3.663

    MPa/318.5

    HP bypass

    desuperheating

    spray valve

    Tp7z63Y-32.01

    HP bypass

    desuperheating

    isolation valve

    Tp764Y-32.01

    LP bypass

    valveC7z61Y-P554.6V 716.3

    3.296

    MPa/5380.598MPa/160

    LP bypass

    desuperheating

    spray valve

    Tp7z64Y-4.01

    bypass valve regulating factor

    Valve name Qty.Driving

    methodActuator

    Switch on/off

    time

    Design

    capability

    HP Bypass

    valve1

    Hydraulic

    drivenBP-300

    Switch off 3s

    quickly, 3s

    quick

    60%BMCR

    HP bypass

    desuperheating

    spray valve

    2Hydraulic

    drivenLBP-300

    Switch off 3s

    quickly, 3s

    quick

    70%BMCR

    HP bypass

    desuperheating

    isolating valve

    1Hydraulic

    drivenBPE-300

    Switch off 3s

    quickly, 3s

    quick

    LP bypass 1 Hydraulic BD-300 Switch off 3s

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    8/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 7 of 23

    valve driven quickly, 3s

    quick

    LP bypass

    desuperheating

    spray valve

    2Hydraulic

    drivenLBPE-300

    Switch off 3s

    quickly, 3s

    quick

    1.2 Commissioning schedule

    The absolute commissioning schedule is 8 days.

    2 .System function introduction

    Bypass control system (BPS) is the important part to realize the unit auto control, it

    plays a very important role while unit start up, normal stop and emergency stop. The

    function of this system is to make the operation parameter in a controlled range, to

    guarantee the unit safety and economic operation. Desuperheating water of HP bypass is

    from the feeder water system, and the desuperheating water of LP bypass is from the

    condensate water system.

    HP & LP bypass valve is the angle type bypass valve with the throttle spray valve.This bypass valve can lead the main steam going through the bypass to the cold section of

    reheater and also lead the reheater heat section steam going through LP bypass to the

    condenser while the unit start-up, stop or at other conditions. Through TG setting, this

    system can make the unit on load operation with the auxiliary power. While the turbine

    tipping or generator breaker switch on, it can make the HP & LP bypass open

    automatically. The valve leakage glass is the minimum V glass, and the spray valve

    outlet flow speed shall not exceed 30M/S.

    3. Compiling basis

    3.1 Indian ROSA 2 x 300MW unit commissioning outline

    3.2 Indian ROSA project equipment erection instruction

    3.3 Indian ROSA project China-Indian general contract

    3.4 The relevant drawings from GEDI

    3.5 Equipment instruction, drawings, and data documents for Indian ROSA project

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    9/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 8 of 23

    generator bypass system

    4. Required conditions before turbine bypass system commissioning

    4.1 Organization and division of work

    NO. Organization and division of work Confirmation

    4.1.1

    Under organized and directed by sub-system commissioning

    group, the person in charge of commissioning should carry out

    commissioning of system and make out commissioning

    measures of such system.

    4.1.2

    Commissioning person should be responsible for transmission

    of related valve, C&I signal and interlock in the system. Before

    the trial, shall give the technical and safety training, Meanwhile,

    measure and record necessary data.

    4.1.3

    Operation person is in charge of the operating and operation

    monitoring, making the safety isolation for the trial run

    equipments.

    4.1.4

    Construction unit should be responsible for finishing

    commissioning of related individual units in the system and

    maintaining, overhauling and eliminating the defects in

    commissioning of system. Organize and coordinate safety,

    fire fighting and safeguard works on commissioning site

    4.1.5

    The commissioning direction unit shall be in charge of

    compiling the commission measure and directing the site

    commissioning. And shall make the technical training before

    trial run.

    4.1.6

    Supervision unit shall be in charge of coordinating and

    attending the system acceptance, coordinating the equipment

    and system storage problem, and coordinating the problems

    disposal which happened in the commissioning. Quality

    supervising and checking before/ after trial run.

    4.2 Required conditions before system commissioning

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    10/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 9 of 23

    NO. Required conditions before commissioning Confirmation

    4.2.1

    Site is flat without debris, the scaffolding shall be removed, the

    handrail of stairways shall be installed completely, and

    adequate light is prepared. Fire fighting device is ready. There

    shall have the clear dividing line around the trial run site. The

    warning board or enclosure shall be set around the danger

    area

    4.2.2Covers of ditch and holes are complete; ladders, paths,

    handrails are available for platform.

    4.2.3 Enough firefighting facilities are available at site;

    4.2.4Adequate light is ready for using at the trail run site. And the

    emergency light can operate automatically.

    4.2.5 Good ventilation establishment

    4.2.6 Good communication system.

    4.2.7 Equipments, pipes, valves shall be hanged the nameplate

    4.2.8

    Equipment and system are installed as per the requirement

    and accepted. The installation recording is complete. And the

    relevant equipment individual trial run is finished.

    4.2.9The instrument calibration is accepted, and the warning and

    showing is correct.

    4.2.10The person deployment is clear, and the commissioning work

    training is finished.

    4.2.11

    Equipment and system are installed as per the requirement

    and accepted. The installation recording is complete. And therelevant equipment individual trial run is finished. And the unit

    is ready for starting.

    4.2.12

    The entire pipes and equipment in the bypass system shall be

    installed complete. The oil circu8lation is finished, oil quality is

    accepted, the oil pressure test for hydraulic pipe is accepted,

    the bypass oil station commissioning is accepted.

    4.2.13 The pressure filling to accumulator is finished.

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    11/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 10 of 23

    4.2.14

    Calibration, erection and wire connection for C & I and

    electrical equipment is finished, and the bypass system C & I

    commissioning is finished and accepted.

    4.2.15

    The steam blowing for HP bypass system is accepted, and the

    cleaning for LP bypass system is accepted, flushing for HP, LP

    bypass desuperheating piping is accepted.

    4.2.16

    Commissioning instrument is ready, the calibration for the

    instrument is accepted, and the precision of the test instrument

    meets the requirement.

    4.3 Commissioning person deployment and qualification

    Sn. Person Qty Quality Responsibility

    1Commissioning

    person2 Commissioning

    In charge of executing the

    measure and operation

    direction

    2Erection

    person4

    Technical person in

    charge and person on

    duty

    Maintenance and overhaul

    3Operation

    person

    So

    manyOperator Each operation during test

    4.4 Equipment and instruments for commissioning

    S.N. Items Model Precision Qty Remarks

    1 Infrared thermal meter 1

    5. Commissioning procedure and method

    5. Flow chart

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    12/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 11 of 23

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    13/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 12 of 23

    5.2 Commissioning procedure and methods

    5.2.1 System commission plan

    S.N. Items Content Result Time Remarks

    1Systeminspection

    Inspect the mainsteam ,reheating steam/

    bypass system piping as perthe scheme

    Main steam and reheatingsteam bypass pipe system

    blowing

    HP & LP bypass

    desuperheating water pipeflushing

    Control oil system circulation

    2Systemblowing

    Cleanness checking

    Main steam pipe hydraulictest

    Main steam reheating steampipe steam tightness test

    Governing valve, spray valveleakage test

    3Systemtightness

    Electrical motoroperation

    commissioning

    Measurement and C & Isignal

    Interlock protection loop

    Function groupcommissioning

    4C & I

    commissioning

    Auto regulation loop

    Control oil system

    HP & LP bypass governingvalve

    HP & LP desuperheatingspray valve

    Close LP bypass governingvalve

    5Componentcommissioning

    Discharge valve

    6 C & I systemtest

    Signal, interlock andprotection test

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    14/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 13 of 23

    Function group test

    Control system factor test

    7Static state

    regulation test Regulation functionsimulation test

    Operation at any condition

    8System

    operationBypass system

    operation

    Operation characteristicchecking

    Parameter optimizing setting 9 Test regulation

    after operationDynamic characteristic

    inspection on the loadrejection condition andother working condition

    5.2.2 System commissioning items

    5.2.2.1 Inspect the complete bypass system.

    5.2.2.2Transmission test, switch on/off test shall be done for the valve to check

    whether it is flexible and reliable.

    5.2.2.3 DAS measurement point and local instrument checking

    5.2.2.4 Interlock protection and C & I signal test

    5.2.2.5 Bypass system, static state function test

    5.2.3 Main commissioning procedure

    5.2.3.1 bypass system static state commissioning

    A Bypass valve static state characteristic test

    1HP & LP bypass governing valve switch feedback calibration, fast switch on/ off

    time measurement

    2HP bypass spray governing valve switch feedback calibration, fast switch on/off

    time measurement

    3LP bypass spray governing valve switch feedback calibration, fast switch on/off

    time measurement

    B Bypass system control function and interlock protection test

    1 HP bypass protection test

    HP bypass protection function, the HP bypass is forced to close in the following status

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    15/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 14 of 23

    a) manual HP valve close quickly

    b) HP spray valve pressure is lower

    c) reheater pressure is higher

    The HP bypass desuperheating water control: HP bypass desuperheating water control

    subsystem to control HP bypass outlet temperature in the suitable temperature around the

    setting value.

    HP decompression control: the HP bypass decompression control subsystem to

    control the main steam pressure as per the pressure setting value. Before the HP cylinder

    starting to stably the main steam pressure till the unit parameter reaches to the turbine

    rolling parameter, and then the HP bypass valve is switch to the heating standby status.

    While the HP cylinder starting, in order to avoid affecting the reheater pressure and HP

    cylinder steam discharge stop valve action caused by HP bypass switch on/off quickly, the

    auto control of the bypass shall be changed into manual control. In addition, while the unit

    operated as load rejection model, the HP bypass can be operation in time.

    2 LP bypass control function

    LP bypass protection function, the LP bypass is forced to close as the following status:

    a) condenser vacuum pressure is low

    b) condenser temperature is high

    c) LP desuperheating spray water pressure is low

    d) three-class desuperheating water pressure is low

    e) condenser water level is high

    The LP bypass is open as the following status:

    a) reheating steam pressure is high

    b) open the LP bypass by manual methodLP bypass desuperheating water control: LP bypass desuperheating water control

    subsystem to control the LP bypass outlet temperature in the suitable value around the

    setting value. .

    LP bypass keeps closed while the HP cylinder starting. Before the turbine rolling, the

    LP bypass valve switch to heat standby status, in addition, while the unit is operated as the

    load rejection model, the LP bypass can operate immediately.

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    16/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 15 of 23

    3 Reheating steam over-pressure protection

    While the unit operation, if the deviation between reheating steam pressure and the

    setting value is more than___ MPa (refer to the setting value from GEDI) or the reheating

    steam pressure exceeds ___ MPa (refer to the setting value from GEDI), the LP bypass

    open immediately, and the LP desuperheating valve is also open.

    4 condenser protection test

    While the condenser vacuum is lower, and the condenser water level or the high

    temperature protection at the downstream of the LP are active, LP decompression valve

    shall be close, meanwhile, the LP desuperheating valve is also close,

    5.2.3.2 bypass control system dynamic commissioning

    ARegulate the dynamic control parameter of each control subsystem at the

    different load, and setting the corresponding PID parameter.

    B

    After the bypass control system operation and the control parameter regulated,

    the setting valve dynamic perturbation test for this control system shall be done

    to precisely regulate the control parameter and improve the regulation quality of

    control system while the controlled heating power system is operated stably.

    5.2.3.3 bypass system operation

    A operation condition

    1 Bypass system static state commissioning work is finished.

    2water discharge system commissioning for main steam, reheating steam is

    finished, and this system is ready for operation

    3 The staring preparation work of the main unit is finished.

    B system operation

    1Open the water discharge valve of the bypass system, HP & LP bypass are

    operated automatically.

    2

    After the boiler lighting and the pressure generation, HP bypass is switch to the

    minimum opening, and the LP bypass is opening gradually, go along with the

    main steam parameter rising, warm the HP & LP bypass piping. Control the

    temperature rising speed to 2 deg C per min. While the main steam pressure

    rising to the setting value, control the HP bypass valve to maintenance the main

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    17/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 16 of 23

    steam valve at the setting value.

    3Control the LP bypass opening as per the main steam pressure changing to

    maintenance the main steam setting valve.

    4During operation, monitor the desuperheating water governing valve following

    status, checking the pipe expansion, and discharge is normal.

    5.2.3.4 test after bypass system operation

    The test after bypass system operation shall be finished before the turbine rolling.

    Because the HP cylinder is operating, before the turbine rolling, first, secondary class

    bypass system shall be removed.

    1 bypass system characteristic test

    A test goal

    1Measure the relationship between HP & LP bypass governing valve pressure

    and flux characteristic

    2 Check the spray desuperheating system working characteristic

    B Test condition

    1 Unit bypass is operation, and the main body is in the barring gear status

    2 Bypass operation is normal

    3 Boiler operation is normal

    4 Condenser vacuum is normal

    5 Circulation water system is operation

    C test procedure

    1 HP bypass characteristic test

    a) Under the different opening of the governing valve, change the boiler working rate,

    doing the test till the bypass system valve is full open and the main steam parameter

    reaches to the rating valve

    b) During test, the LP bypass is in the following model, the HP bypass desuperheating

    water is operated automatically.

    c) Record the relative data

    d) Calculate the characteristic relationship

    2 LP bypass characteristic test

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    18/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 17 of 23

    a) Under the different opening of the governing valve, change the boiler working rate

    and the HP bypass opening, doing the test till the LP bypass governing valve is full open

    and the main steam parameter reaches to the rating valve

    b) During test, the LP desuperheating water can operate automatically, and the HP

    bypass can be operated by manual method.

    c) Record the relative data

    d) Calculate the characteristic relationship

    2 dynamic characteristic test

    Before the load rejection operation model, the warming and water discharge shall be done

    for the bypass system, while the unit load rejection operation starting, the HP & LP bypass

    valve open immediately, in order to estimate the HP & LP spray desuperheating water

    refection characteristic, record the valve open time, steam pressure, temperature stability

    valve, peak value and its time.

    6. Commissioning quality checking standard

    6.1 key control point setting

    Inspection unit

    Sn. Work controlpoint Constru

    ction

    Commissionin

    g

    Development

    unit

    Produce unit

    Supervisionunit

    Witness method

    1

    Bypass oilstation

    control oilpressure andtemperature

    * * * R

    2

    Bypass oilstation oil

    flushing andoil cleanness

    * * * * * R

    3

    Bypasssysteminterlock

    protectiontest

    * * * * * R

    4

    Fast opentime forbypasssystem

    * * * * * R

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    19/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 18 of 23

    R- record confirmed point W- witness point Hhold for inspection point Ssupervise

    continually6.2 Quality standard

    Sn. Items Inspection standard

    1 Interlock and signalItem completely, and the action

    is correct

    2 Fast open time of Bypass system 3S

    6.3 Recording content

    1 HP & LP bypass system valve transmission recording list

    2 HP & LP bypass system subsection trial run recording list

    3 HP & LP bypass system logical transmission recording list

    7. Safety requirement and environment condition during commissioning

    7.1 Danger factors identification and control

    Danger factors identification and control list

    Sn. Description Control and strategy

    Executive

    person in

    charge

    Signature

    person

    1

    lose control of

    temperature and

    pressure

    Operation person and

    erection person to check the

    equipment operation status

    periodically

    Operation

    person,

    erection

    person

    Commissioning

    person in

    charge

    2Injured by the

    system leakage

    Operation person and

    erection person to check the

    equipment operation status

    periodically

    Operation

    person,

    erection

    person

    Commissioning

    person in

    charge

    3Leakage in the

    steam valve

    Operation person and

    erection person monitor the

    pressure and temperature on

    the downstream of bypass

    Operation

    person,

    erection

    person

    Commissioning

    person in

    charge

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    20/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 19 of 23

    valve periodically, and

    dispose the leakage once the

    leakage appeared.

    4

    LP bypass

    desuperheating

    water pressure is

    lower, the LP

    bypass will be

    open by

    interlocked

    Maintenance the CEP normal

    operation to avoid the low

    pressure at the CEP outlet

    Operation

    person,

    erection

    person

    Commissioning

    person in

    charge

    7.2 Commissioning environment condition

    Sn. Description Control strategy

    Executive

    person in

    charge

    Signature

    person

    1 Steam leakage

    Operation person and

    erection person to check the

    equipment operation status

    periodically

    Operation

    person,

    erection

    person

    Commissioning

    person incharge

    8. Appendix

    NO. Content

    1 HP & LP bypass system subsection trial run recording list

    2 HP & LP bypass system logical transmission recording list

    3 HP & LP bypass system valve transmission recording list

    4 HP & LP bypass system subsection trial run acceptance and signature card

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    21/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 20 of 23

    Number Unit subsystem commissioning recording list

    Specialty Turbine HP & LP bypass system

    Motor bearing vibration Oil pump bearing vibration

    Time Leveldirection

    Axialdirection

    Verticaldirection

    Leveldirection

    Axialdirection

    Verticaldirection

    Motorbearingtemperature

    Oil pumpbearingtemperature

    Outletpressure ofpump

    Commissioning in charge person : Commissioning recording person:

    Date:

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    22/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 21 of 23

    Number Unit subsystem commissioning recording list

    Specialty TurbineHP & LP bypass system logical transmission

    recording

    Sn. Items Result Signature

    Commissioning in charge person : Commissioning recording person:

    Date:

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    23/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 22 of 23

    Number Unit subsystem commissioning recording list

    Specialty Turbine HP & LP bypass system valve transmission recording

    Valve name Fast open times Fast close

    timesOpen times Close times Remarks

    Commissioning in charge person : Commissioning recording person:

    Date:

  • 7/29/2019 LS-TSZD-_- QJ005 Turbine Bypass System Commissioning Procedure

    24/24

    Turbine Bypass SystemCommissioning Procedure

    2300 MW Rosa ThermalPower Project

    DOCUMENT NO. : LS-TSZD-- QJ005 Page 23 of 23

    Subsection trial run acceptance and signature card

    Specialty: turbine Item name: turbine bypass system

    Turbine specialty HP & LP bypass system Date

    EvaluationSn. Inspection Content

    Acceptance Non-acceptanceRemarks

    1System interlock protection and signal itemcomplete, and action is correct

    2System C & I instrument is complete, andthe show is correct

    3System pressure, temperature parameter

    is conformed to the design regulation4

    System trial run, each valve is flexible, andcan be operated normally

    5 Piping is tightness without leakage

    Evaluation:

    The subsection trial run of this equipment/system has been completed between _____

    (Day) _____ (Month), _____ (Year) and _____ (Day) _____ (Month), _____ (Year).

    Through acceptance inspection according to the Criteria for Acceptance Inspection and

    Assessment of Adjustment Commissioning Quality of Thermal Power Projects by former

    Ministry of Electric Power, this equipment/system is rated as qualified ( ) / good ( )

    and has achieved conditions required for operation. We hereby agree to enter the whole-set

    startup stage.

    Construction unit signature : Date:

    Commissioning unit signature Date:

    Commissioning direction unit signature Date:

    Production unit signature Date:

    Development unit signature Date: