Upload
bryan-roberts
View
214
Download
0
Embed Size (px)
Citation preview
LST SAFETY
INSTALLATION READINESS REVIEW 5/5/2004
FRANK O’NEILL (SLAC)
SAFETY ISSUES
• Safety Plan
• Design Safety Issues
• FHA Addendum
• Environmental/Emissions
SAFETY PLAN
• October 2003, Review Committee - Recommendation #3“Third is the need for more formal safety planning. The circumstances of the installation in 2004 and 2005 present a significant risk of accident. Early, detailed, safety planning is needed to ensure adequate personnel training and full-time coverage by safety officers on all shifts for the duration of the installation. With appropriate advance planning, training, and staffing, the work can be conducted safely.”
SAFETY PLAN
• Safety Team and Coverage• Safety Training• Job Hazard Analysis• Tailgate Safety Meetings • Safety on agenda for Daily Operations
Meetings• Safety Coordination - Fire Safety, Security,
OHP, PRCS, ETC.• Management Safety Walkthroughs
SAFETY TEAM
• Team Leader is Sandy Pearson• Members include Frank O’Neill and Joe
Kenny - Four additional team members are needed for the day and swing shifts
• Candidates have been identified• Time commitment is two 8 hour shifts
per week• BaBar Operators will be considered for
Graveyard shift safety coverage
SAFETY TRAINING
• Accident Prevention Talk & Walk
• IR-2 Safety Briefings will be conducted every day the first week
• IR-2 Safety Briefings will be conducted weekly thereafter - Wednesday at 1:30 at IR-2 Cornelius - and as required
JOB HAZARD ANALYSIS
• Rigging Procedures and Job Hazard Analysis (JHA) have been completed for special purpose handling fixtures
• Safety Review of these procedures and JHA has been accomplished
TAILGATE SAFETY MEETINGS
• Will be conducted at the start of each shift and as necessary at the beginning of new activity and operations
• Review of the JHA with the crews is an essential part of the tailgate safety meeting
DAILY OPERATIONS MEETINGS
• Safety on Agenda at Daily Operations Meetings
• A Safety Team Member will attend and communicate safety issues and concerns
SAFETY COORDINATION
• Fire Safety
• Security
• OHP
• PRCS
MANAGEMENT SAFETY WALKTHROUGHS
• This is under consideration
DESIGN SAFETY ISSUES
• Flammable Component of Gas Mixture
• Electrical/Electronics Final Design
GAS MIXTURE
• 3 components: Argon, Isobutane, and CO2 • Similar Gas Mixtures utilized on other
Detectors– SLD: 2.5% Ar, 9.5% isobutane, 88% CO2
– ZEUS: 3% Ar, 8% isobutane, 89% CO2
• Final decision on mixture pending• Nonflammable mixture will be utilized• Hughes Associates providing consulting
services for evaluation of mixtures
0 5 10 15 20
7.5
8
8.5
9
9.5
10
Compare_errors_vs_flammable_region_II
Per Cent Argon (proposed limit, 9.7% isobutane at 0% argon)Runnable Region (9.41 % isobutane at 0% argon)Runnable Region + 1.0% driftExample Point (8.65% isobutane, 3% argon)
Per Cent Argon
%CO2=100-%Ar-%Isobutane
All Operational Settings Are To Be Below the Blue Line
GAS MIXTURE STATUS
• Hughes Associates Inc. reviewed and approved the gas system proposal
• Fire Protection Safety Committee review completed April 6, 2004
• Hazardous Experimental Equipment Committee (HEEC) review completed April 12, 2004 – final walkthrough before start-up is required
FIRE HAZARD ANALYSIS (FHA) ADDENDUM
• Hughes Associates Inc. is currently working on the second Addendum to the FHA
• Recently received a description of the LST Electrical/Electronics – an issue to be addressed is do we need to provide VESDA coverage
• Ed Budnick has committed to delivering the Addendum by the end of June
• Submit to the DOE for Information Only
ENVIRONMENTAL SAFETY
• Bay Area Air Quality Management District (BAAQMD) issues SLAC a permit for discharge of VOCs – BaBar emissions may approach the limits
of the permit– Monitoring the emission levels and
coordination with the SLAC Environmental Protection Department is ongoing