480

Transnet SOC Ltd © LTPF 2016

LTPF Long-Term Planning Framework

PLP Project Lifecycle Process

FEL Front End Loading

FER Front End Research

TFR Transnet Freight Rail

TNPA Transnet National Ports Authority

TPT Transnet Port Terminals

TPL Transnet Pipelines

TGC Transnet Group Capital

PICC Presidential Infrastructure Coordinating Commission

SIP Strategic Integrated Projects

IP Intellectual Property

MPP Multi-Product Pipeline

Page 3: LTPF - Transnet

481

Transnet SOC Ltd © LTPF 2016

1. INTRODUCTION ............................................................................................................................................................ 482

1.1. 30-YEAR EXPANSION CAPITAL REQUIREMENTS SUMMARY __________________________________________________ 482 1.2. CHANGES IN THE LTPF FROM 2015 TO 2016 _________________________________________________________ 483 1.3. CHANGES IN THE 30-YEAR ROLLING FORECASTS OF THE LTPF OVER THE PAST 5 MDS-YEARS ___________________________ 484 1.4. TOTAL RAIL, PORT AND PIPELINE EXPANSION CAPITAL REQUIREMENTS _________________________________________ 484 1.5. PROVINCIAL CAPITAL REQUIREMENTS ________________________________________________________________ 485 1.6. TRANSNET INVESTMENT IN THE PICC STRATEGIC INTEGRATED PROJECTS ________________________________________ 487

1.6.1. SIP 1: Unlocking the northern mineral belt .............................................................................................. 487 1.6.2. SIP 2: Durban-Free State-Gauteng logistics and industrial corridor ......................................................... 487 1.6.3. SIP 3: South-Eastern node and corridor development .............................................................................. 487 1.6.4. SIP 5: Saldanha-Northern Cape development corridor ............................................................................ 487

2. 30-YEAR EXPANSION CAPITAL REQUIREMENTS ............................................................................................................ 489

2.1. RAIL CAPITAL REQUIREMENTS _____________________________________________________________________ 489 2.1.1. Rail infrastructure requirements .............................................................................................................. 490 2.1.2. Rolling stock requirements ....................................................................................................................... 491

2.2. PORT CAPITAL REQUIREMENTS (TNPA & TPT) _________________________________________________________ 495 2.3. PORT CAPITAL REQUIREMENTS PER CARGO CATEGORY _____________________________________________________ 497 2.4. PIPELINE CAPITAL REQUIREMENTS __________________________________________________________________ 498 2.5. GAS CAPITAL REQUIREMENTS _____________________________________________________________________ 499 2.6. PROJECT STUDY FUNDING REQUIREMENTS _____________________________________________________________ 500

3. FUNDING ...................................................................................................................................................................... 502

3.1. FUNDING SOURCES AVAILABLE TO TRANSNET ___________________________________________________________ 502 3.2. SEVEN-YEAR FUNDING REQUIREMENTS IN THE CORPORATE PLAN _____________________________________________ 503 3.3. CAPITAL STRUCTURE ___________________________________________________________________________ 504

4. APPENDIX 1: ESTIMATING PRINCIPLES APPLIED ........................................................................................................... 505

4.1. PROJECT LIFE CYCLE PROCESS (PLP) _________________________________________________________________ 505 4.2. FRONT END LOADING (FEL)_______________________________________________________________________ 505 4.3. PROJECT DURATION ____________________________________________________________________________ 505 4.4. PROJECT TIMELINES ____________________________________________________________________________ 506 4.5. PROJECT ESTIMATES ____________________________________________________________________________ 506 4.6. ESCALATION _________________________________________________________________________________ 507 4.7. EXPANSION CAPITAL ONLY ________________________________________________________________________ 507 4.8. UNCONSTRAINED VIEW _________________________________________________________________________ 507 4.9. LAND ACQUISITION COST ________________________________________________________________________ 507

Page 4: LTPF - Transnet

482

Transnet SOC Ltd © LTPF 2016

1. INTRODUCTION

The Long-term Planning Framework (LTPF) provides a practical framework for a series of interventions to increase capacity in a

closed system of rail, port and pipeline infrastructure to match the projected demand. It provides an unconstrained view to guide

strategic infrastructure investment and offers a neutral way on capacity requirements not impacted by affordability, profitability or

other business constraints.

The capital chapter of the LTPF quantifies and summarises the interventions identified in the individual Port, Rail and Pipeline

Chapters and thereby completes the capital planning process which forms the basis for the capital budgeting process where the

viability and affordability of the capital investments are tested and the long-term sustainability of Transnet is ensured. The module

summarises the 30-year capital requirements from 2016 to 2045.

1.1. 30-YEAR EXPANSION CAPITAL REQUIREMENTS SUMMARY

The Transnet Operating Divisions have submitted an expansion and replacement capital requirement of R277 billion over the next

seven years. An amount of R273 billion capital expenditure has been approved by the board in the Corporate Plan, R109 billion of

the R273 billion is for expansion projects. Due to the prolonged subdued economic climate the 7-year constrained portfolio

cashflow forecast has been reduced by R62 billion to R239 billion (not reflected in the graph).

The LTPF highlights the expansion capital requirements up to 2045. It indicates that R759 billion (un-escalated) will be required up

to 2045. Of the R759 billion, R239 billion (escalated) will be required over the next seven years.

Figure 1: 30-year expansion capital requirements

Page 5: LTPF - Transnet

483

Transnet SOC Ltd © LTPF 2016

1.2. CHANGES IN THE LTPF FROM 2015 TO 2016

In this comparison the cash flows (cradle-to-grave) of the thirty years, in both the LTPF 2015 (2015-44) and LTPF 2016 (2016-45),

have been compared. The expansion requirements are in 2015 and 2016 base values and include study cost of R27,6 billion and

R26,4 billion respectively. The total rolling 30-year expansion requirements cost estimate has decreased from R821 billion in the

2015 LTPF to R786 billion in the 2016 LTPF.

The main difference between 2015 and 2016 is that growth forecasts have been lowered further to reflect the lowered economic

growth expectations for the next 10-years. Some higher “catch-up” expansion requirements were assumed in the latter years

(2037-2045), whilst in the earlier part of the 30-year period of the 2016 LTPF greater emphasis was placed on operational changes

to increase capacity before infrastructure expansion is considered.

Figure 2: LTPF 2015 and 2016

Page 6: LTPF - Transnet

484

Transnet SOC Ltd © LTPF 2016

1.3. CHANGES IN THE 30-YEAR ROLLING FORECASTS OF THE LTPF OVER THE PAST 5

MDS-YEARS

In the 2012 LTPF economic recovery was expected within the first 7-years in line with economist’s consensus forecasts. Over the

past five years these forecasts have consistently been deferred as it became evident that the world economy is taking longer to

recover than anticipated.

Over the past five years Transnet’s investment continued in line with the MDS and the Government’s Growth Path Strategy to

create capacity ahead of demand and lowering capacity constraint pressures on future years. The MDS investment commitments

are maintained, but delivery thereof are delayed to align capacity requirements with projected demand forecasts.

Figure 3: Changes in the 30-year forecasts

1.4. TOTAL RAIL, PORT AND PIPELINE EXPANSION CAPITAL REQUIREMENTS

Figure 4 below depicts the total rail, port, and pipeline expansion capital required over the next 30-years and totals R759 billion.

The rail capital component is the biggest, totalling R467 billion and representing 61% of the total capital requirement.

The average annual rail capital requirement remains fairly constant at about R17 billion per annum. This includes:

• Rail infrastructure;

• Rail hubs and terminals; and

• Rolling stock comprising of locomotives and wagons.

Port expansion capital of R226 billion is required up to 2045. Of this capital, Transnet Port Authority requires R138 billion and

Transnet Port Terminals R88 billion. Substantial port developments/investments are required until about 2032, declining thereafter.

The pipeline requirement of R67 billion is predominantly for the different Multi-Product Pipeline (MPP) expansion phases. The

individual operating division investment categories are analysed in more detail below.

Page 7: LTPF - Transnet

485

Transnet SOC Ltd © LTPF 2016

Figure 4: Total rail, port and pipeline expansion capital requirements

1.5. PROVINCIAL CAPITAL REQUIREMENTS

The capital expenditure distribution amongst the provinces is based on an estimation/ratio of how much of the physical

infrastructure is located in each province. The capital for each intervention is then distributed to each province based on this ratio.

Capital which cannot be allocated to a specific province has been classified under National, and investments linked to neighbouring

countries e.g. Botswana, Zimbabwe, Swaziland etc. have been classified separately.

An analysis of the 30 year expansion capital requirements indicates that Transnet will be a major economic growth enabler in the

provinces. KwaZulu-Natal will require R216 billion (un-escalated) which represents 28% of the total R759 billion investments over

the next 30 years. National receives the largest investment at R297 billion (39%) due to the rolling stock capital requirements.

Locomotives and wagons function across provincial boundaries.

The Western Cape Province will require R72 billion (10%) of the capital expansion over the 30 years, in mainly Cape Town

Seaward expansions and investments in the Port of Saldanha.

The provinces of Gauteng and the Eastern Cape will each require 6% of the total expansion capital requirements, this is between

R43-R48 billion per province over the next 30 years. This is mainly to facilitate the investments in the Gauteng freight ring and

Gauteng terminals as well as the investment to facilitate the manganese ore exports through the port of Ngqura.

Incl FEL1&2 Excl FEL1&2

Rail 470 366 467 068

Port - Authority 139 697 137 648

Port - Operations 89 385 88 173

Pipeline 86 355 66 525

Total 785 803 759 414

Page 8: LTPF - Transnet

486

Transnet SOC Ltd © LTPF 2016

The Mpumalanga (R29 billion – 4%), Limpopo (R21 billion – 3%), Northern Cape (R13 billion – 2%), North West (R10 billion –1%),

and Free State (R3 billion – 0.4%) provinces complete the bottom end of the expansion capital requirements. Investments into

neighbouring countries account for R8 billion (1%) of the capital requirements.

Figure 5: LTPF capital requirements per Province

Page 9: LTPF - Transnet

487

Transnet SOC Ltd © LTPF 2016

1.6. TRANSNET INVESTMENT IN THE PICC STRATEGIC INTEGRATED PROJECTS

Transnet is responsible for SIP 2 and involved in several of the PICC’s SIPs. Transnet is involved and reports on progress in the

following SIPs:

1.6.1. SIP 1: UNLOCKING THE NORTHERN MINERAL BELT

Investment in rail, water pipelines, energy generation and transmission infrastructure to tap Limpopo’s rich mineral reserves.

1.6.2. SIP 2: DURBAN-FREE STATE-GAUTENG LOGISTICS AND INDUSTRIAL CORRIDOR

Linking the industrial hubs in Durban, the Free State and Gauteng, and improving access to Durban’s import/export facilities.

1.6.3. SIP 3: SOUTH-EASTERN NODE AND CORRIDOR DEVELOPMENT

Upgrade of port and rail capacity, construction of a new dam in Umzimvubu in the Eastern Cape, construction of rail infrastructure

to transport manganese from the Northern Cape to Port Elizabeth, construction of a manganese sinter facility in the Northern Cape

and a smelter in the Eastern Cape.

1.6.4. SIP 5: SALDANHA-NORTHERN CAPE DEVELOPMENT CORRIDOR

Expansion of rail and port infrastructure in the Saldanha area; construction of industrial capacity at the back of these ports

(including a possible industrial development zone); strengthening maritime support for the gas and oil activities along the West

Coast; expansion of iron ore mining production.

Although the SIPs are aimed at development over the short to medium term, programmes and projects in the LTPF 2016 that

could possibly be managed as part of the SIPs over the longer term are:

SIP 1: UNLOCKING THE NORTHERN MINERAL BELT

• Coal Expansion

• Port of Richards Bay Expansionary projects

• Swaziland Link

• Mozambique Link

• Zimbabwe Link

• Other North-Eastern System programmes

SIP 2: DURBAN-FREE STATE-GAUTENG LOGISTICS AND INDUSTRIAL CORRIDOR

• NATCOR

• Gauteng Freight Ring

• Gauteng Terminals

• Durban Terminals

• DDOP

• Other Port of Durban Expansionary projects

SIP 3: SOUTH-EASTERN NODE AND CORRIDOR DEVELOPMENT

• Export Manganese Expansion Programme (Rail and Port)

Page 10: LTPF - Transnet

488

Transnet SOC Ltd © LTPF 2016

SIP 5: SALDANHA-NORTHERN CAPE DEVELOPMENT CORRIDOR

• Export Iron Ore Expansion Programme (Rail and Port)

• Saldanha Bay to Atlantis Natural Gas Pipeline project

• Other Port of Saldanha expansionary projects

Figure 6: LTPF SIP capital requirements

More than half of the SIP attributable LTPF capital requirement is accounted for on the SIP 2 projects. Transnet is the official co-

ordinator for SIP 2. The SIP 2 capital requirements make up 59% of the total 30 year LTPF SIP capital requirements.

Incl FEL1&2 Excl FEL1&2 SIP 1 88 362 86 966

SIP 2 205 096 201 558

SIP 3 26 578 26 290

SIP 5 26 417 25 425

346 453 340 240

Page 11: LTPF - Transnet

489

Transnet SOC Ltd © LTPF 2016

2. 30-YEAR EXPANSION CAPITAL REQUIREMENTS

2.1. RAIL CAPITAL REQUIREMENTS

Rail capital requirements, comprising of rolling stock, infrastructure, hubs and terminals are considered for capacity expansion only.

Rolling stock requirements totals R283 billion (61%) of the total rail capital requirements).

Substantial infrastructure investments (R167 billion) are required for the next 20 years to serve higher traffic levels and to

compensate for the under investment of the previous few decades. No provision is, however, made for rail gauge changes or high

speed passenger solutions.

Investments in hubs and terminals remain comparatively low (R16 billion), but forms an integral part of the total service solution.

Capacity creation in terminals assumes significant contributions from the private sector and terminal operators.

Figure 7: Rail capital requirements

Incl FEL1&2 Excl FEL1&2

Rolling Stock 283 413 283 413

Infrastructure 170 154 167 445

Hubs & Terminals 16 799 16 210

Total 470 366 467 068

Page 12: LTPF - Transnet

490

Transnet SOC Ltd © LTPF 2016

2.1.1. RAIL INFRASTRUCTURE REQUIREMENTS

An analysis of the R167 billion rail infrastructure investment requirements per rail system reveals that 48% of the infrastructure

expansion requirements are needed on the Durban - Gauteng (R80 billion) and 27% on the Integrated Coal (R45 billion) systems.

The Export Ore and the North Eastern systems account for a further 11% (R19 billion) and 9% (R15 billion) of the rail

infrastructure investment requirements respectively.

The R80 billion for rail infrastructure development on the Durban - Gauteng system will be required to cater for the substantial

volume growth expected over this system over the next 30 years. The capacity increase is required over the next 30 years, with

investment peaks of R13 billion in 2034 and R17 billion in 2041.

The R45 billion for the Coal system is required over the next 10 years (2017 to 2026) with capacity creation requirements peaking

at the end of the 7-year plan at R10 billion in 2024, R11 billion in 2025 and R8 billion in 2026.

The investment requirements on the Export Ore system (Iron Ore) are scaled down in line with the industry throughput

requirements. Some of the R19 billion for the first phase of the Export Ore System is required over the next 5 years (2017 to

2021), peaking at R6 billion in 2019. The second phase of investment is from 2023 to 2026.

Expansion on the North Eastern system (R15 billion) is required within the next 7 years (2017 to 2021). Capacity creation peaks in

2019 at R7 billion.

Figure 8: Rail infrastructure capital requirements

Page 13: LTPF - Transnet

491

Transnet SOC Ltd © LTPF 2016

2.1.2. ROLLING STOCK REQUIREMENTS

Rolling stock requirements (R283 billion) over the 30 years are split between locomotives (53% - R150 billion) and wagons (47% -

R134 billion). Major locomotive expansions are required in the short term (seven years – as per the 2 064 locomotive acquisition

programme). Future rolling stock requirements are smoothed to ease acquisition and planning.

The long lead times applicable to ordering rolling stock, especially locomotives, and the smoothing of acquisition may result in over

capacity provision in some periods, whilst under-provision/shortages might be experienced in other periods.

Figure 9: Rolling stock requirements

Incl FEL1&2 Excl FEL1&2

Locomotives 149 902 149 902

Wagons 133 511 133 511

Total 283 413 283 413

Page 14: LTPF - Transnet

492

Transnet SOC Ltd © LTPF 2016

2.1.2.1. Locomotives capital requirements

Figure 10: Future locomotive fleet and capital requirement

Figure 11: Locomotive fleet by traction

Page 15: LTPF - Transnet

493

Transnet SOC Ltd © LTPF 2016

Figure 12: Locomotive fleet capital requirements by traction

Diesel 45

50kV AC 1

Dual Voltage 104

Total (Rbn) 150

Page 16: LTPF - Transnet

494

Transnet SOC Ltd © LTPF 2016

2.1.2.2. Wagon capital requirements

Figure 13: Future wagon fleet and capital requirements

Page 17: LTPF - Transnet

495

Transnet SOC Ltd © LTPF 2016

2.2. PORT CAPITAL REQUIREMENTS (TNPA & TPT)

Transnet National Port Authority is basically the landlord of port infrastructure and responsibilities include marine services, activities

such as tugs, pilot boats and pilot helicopters, port control, etc. Transnet Port Terminals’ responsibilities include the loading and

offloading of trains, road vehicles and vessels, as well as the conveyance and storage of products within the port. Major

investments in the ports include:

• Durban Dig-out Port developments;

• Durban Pier 1 Phase 2 Infill (Salisbury Island);

• Cape Town Seaward expansion; and

• Port Elizabeth container terminal expansions.

TNPA investment requirements (R138 billion – 61%) are significantly more than that of TPT (R88 billion – 39%) for the 30-year

period. Common to the nature of port infrastructure investments, substantial expansion investment is required upfront to create

basic port infrastructure. Port furnishings and terminal investments can be better phased to align to market demand.

Figure 14: Port capital requirements

Incl FEL1&2 Excl FEL1&2

Port - Authority 139 697 137 648

Port - Operations 89 385 88 173

Total 229 082 225 821

Page 18: LTPF - Transnet

496

Transnet SOC Ltd © LTPF 2016

2.2.1 CAPITAL REQUIREMENTS PER PORT

An analysis of the capital requirements per port highlights the ports of Durban (R105 billion), Ngqura (R36 billion) and Richards

Bay (R27 billion) as the main port capital investment destinations. The expansion requirements of all the major ports, over the 30-

year period, are indicated below.

Durban will attract 47% of the port investments to cater for consistently strong service demand. Large investments are required for

Phase 1 of the Durban airport site port development to start in 2029 and continuing into the 2040’s. An estimated R67 billion is

needed by TNPA and the Terminal operator for phase 1. Another major project in the port of Durban include Pier 1 Phase 2 Infill

(Salisbury Island) at an estimated R23 billion.

In the port of Richards Bay R27 billion is required for expansion projects over the 30-year period. Major projects include land

acquisitions for future port development; ship repair facilities and a dry dock; as well as a facility for Liquefied Natural Gas (LNG).

Expansion capital requirements in the port of Saldanha Bay totals R19 billion, of which a large portion (75%) is required within the

next seven-year period.

Significant expansions are also required in the port of Ngqura (R36 billion) to accommodate the move of the manganese facility

from the port of Port Elizabeth and to increase container terminal capacity to align with transhipment demand and TNPA capacity.

Predominantly container terminal capacity is required in the ports of Cape Town and Port Elizabeth, and the 30-year expansion

capital requirements in these ports are R20 billion, and R13 billion respectively. Capacity expansion investment requirements in the

ports of East London (R4 billion) and Mossel Bay (R1,4 billion) are comparatively small.

Figure 15: Capital requirements per port

Page 19: LTPF - Transnet

497

Transnet SOC Ltd © LTPF 2016

2.3. PORT CAPITAL REQUIREMENTS PER CARGO CATEGORY

When the capacity expansion requirements are summarized per cargo category, it is apparent that R123 billion (55%) of port

investments are for container traffic expansions due to the strong growth in this sector and current capacity constraints.

During the first few years some dry bulk investments (R23 billion – 10%) are required at the ports of Richards Bay, Ngqura and

Saldanha Bay to cater for the growth in the export commodities of coal, manganese and iron ore.

Significant liquid bulk investments (R34 billion – 15%) are required in mainly the ports of Saldanha, Richards Bay, Ngqura and

Durban. These include investments for Liquefied Natural Gas (LNG) and Liquid Petroleum Gas (LPG).

Expansion investments in the cargo categories of break bulk (2%) and automotive (2%) are comparatively small. Provisions have

also been made for expansions in ship repair (5%), and maritime commercial activities (1%) to facilitate project Phakisa.

Figure 16: Capital requirements per cargo category

Page 20: LTPF - Transnet

498

Transnet SOC Ltd © LTPF 2016

2.4. PIPELINE CAPITAL REQUIREMENTS

The Multi-Product Pipeline (MPP) expansion requirements (R27 billion) make up 41% of the Total Pipeline’s expansion capital

requirements of R67 billion. Four further phases are planned. The timing of the further phases is dependent on the timelines of the

planned Mthombo Oil Refinery in the Ngqura Development Zone.

Two scenarios have therefore been listed for expansions on the MPP, i.e. where 1) a new Ngqura – Gauteng pipeline (NGP) is

commissioned, and 2) where product from Mthombo gets shipped to Durban and pumped to Gauteng via the MPP. The two

scenarios have different capacity requirements for the MPP.

Scenario 1

(Ngqura – Gauteng pipeline)

Scenario 2

(Shipping case)

Phase 1 2019 2019

Phase 2 2022 2021

Phase 3 2034 2025

Phase 4 2036 2029

Phase 5 2038 2031

Table 1: Mthombo oil refinery scenarios

Figure 17: Pipeline capital requirements per Scenario

Page 21: LTPF - Transnet

499

Transnet SOC Ltd © LTPF 2016

2.5. GAS CAPITAL REQUIREMENTS

Provision has been made for investment in gas (LNG and LPG) infrastructure requirements in the ports and pipelines capital

requirements. Due to the emphasis that has been placed on the importance of creating gas infrastructure, the proposed

investments have been singled out and are reflected below. These investments form part of the ports and pipelines infrastructure

and are not additional to that listed above.

Figure 18: Gas capital requirements

Incl FEL1&2 Excl FEL1&2

TPL 16 065 9 800

TNPA 6 145 6 046

TPT 12 342 12 158

Total 34 552 28 004

Page 22: LTPF - Transnet

500

Transnet SOC Ltd © LTPF 2016

2.6. PROJECT STUDY FUNDING REQUIREMENTS

Project study requirements for the PLP process and the funding thereof follow the normal Transnet financial policy and procedure

guidelines. FER, FEL-1, and FEL-2 studies are funded predominantly from the operating budget, whilst FEL-3 and FEL-4 is funded

from the capital budget.

The cost for project studies, once again, varies based on the size and complexity of the project. A Generic study cost estimates for

future projects are based on the following percentages of the projected total project cost:

PLP Stage Allocation of ETC

FEL-1 0,4%

FEL-2 1,25%

FEL-3 2,85%

Table 2: Study cost allocation per PLP phase

Over the 30-year period Transnet would need to make provision for approximately R26,4 billion in the operating budget and R22

billion in the capital budget for project study funding. Project study funding FEL1-3 totals only 6 % of total project cost.

Figure 19: Transnet 30-year capital and study requirements

FEL - 1 6 143

FEL - 2 20 246

FEL - 3 22 006

FEL - 4 737 408

Total 785 803

Page 23: LTPF - Transnet

501

Transnet SOC Ltd © LTPF 2016

The project and study estimates over the 30 years are static and thus remain un-escalated. The study estimates and timelines in

the LTPF 2016 are based on generic percentage estimates and timelines for the different PLP phases. Project timelines are

dependent on the date the intervention is required and the construction period.

Study funding will require R26,4 billion from predominantly the operating budget for FER, FEL-1 and FEL-2 studies and R22 billion

in the capital budget for FEL-3 studies over the 30 years.

Figure 20: 30-year capital and study funding per PLP phase

Page 24: LTPF - Transnet

502

Transnet SOC Ltd © LTPF 2016

3. FUNDING

3.1. FUNDING SOURCES AVAILABLE TO TRANSNET

The objective of the funding plan is to ensure that the company has sufficient liquidity to meet all its requirements, without

breaching the key financial ratios as agreed with the Shareholder through the Shareholder’s Compact, whilst exploring innovative

funding solutions which seek to minimise any constraint that the increase in the investment plan might have on the balance sheet.

Some of the possible funding sources to be used include:

• International and domestic capital markets;

• Loan market (public and private);

• Development Finance Institutions (domestic and international);

• Export credit market;

• Structured leasing;

• Partial funding by customers and/or interesting parties of part of Transnet’s investment plan; and

• Project specific funding.

Page 25: LTPF - Transnet

503

Transnet SOC Ltd © LTPF 2016

3.2. SEVEN-YEAR FUNDING REQUIREMENTS IN THE CORPORATE PLAN

External funding of about R97.4 billion, as identified in the corporate plan, will be required over the next seven years. The capital

investment and funding requirements as per the corporate plan and long-term planning framework are depicted in Figure 22

below. Individual projects where external funding will be pursued are going to be identified.

Figure 22: Seven-year funding requirements including LTPF

3.6 4.2 4.5 5.1 5.4 5.8 6.4

16/17 17/18 18/19 19/20 20/21 21/22 22/23

Cash generated from operations after working capital changes (Rbn)

(2.3)

(3.9) (3.9) (4.5) (4.4) (4.8) (3.7)

(0.0)

(0.2) (0.6) (0.3) (0.2)

(0.2)

(0.4) (2.1)

(2.0) (2.2)

(0.9) (0.2)

1.0

(0.1)

16/17 17/18 18/19 19/20 20/21 21/22 22/23

Capital Investment (Rbn)

Corporate Plan investment (Rbn) LTPF External Funding LTPF Unfunded

(0.8) (1.7)

(1.1) (1.3) (1.9) (1.8)

(1.2)

(2.1)

(2.0) (2.2)

(0.9) (0.2)

1.0

(0.1)

16/17 17/18 18/19 19/20 20/21 21/22 22/23

Funding Required

Corporate Plan Funding Required (Rbn) LTPF Unfunded

Page 26: LTPF - Transnet

504

Transnet SOC Ltd © LTPF 2016

3.3. CAPITAL STRUCTURE

Transnet has access to the debt capital markets for funding at appropriate cost levels. As an entity with commercial objectives, it is

imperative for Transnet to retain and improve its financial strength. Transnet therefore has to remain within acceptable capital and

debt structure parameters to ensure:

• Adequate reinvestment to maintain operations as well as to create capacity to meet market demand needs;

• Optimal cost of capital; and

• Optimal working capital.

To achieve the above objectives, the Transnet Board of Directors has set the following financial metrics to monitor performance:

• Maximum capital to debt (gearing ratio) structure of less than 50%;

• Generally maintain a cash interest cover of at least 3,0 times;

• Return on total assets (ROTA) of >6%; and

• Earnings before interest, tax, dividends, and amortisation (EBITDA) of >40%.

Figure 23: Affordability

Page 27: LTPF - Transnet

505

Transnet SOC Ltd © LTPF 2016

4. APPENDIX 1: ESTIMATING PRINCIPLES APPLIED

4.1. PROJECT LIFE CYCLE PROCESS (PLP)

Transnet developed and implemented the Project Life cycle Process (PLP) in order to continuously and systematically improve the

levels of consistency in the approach to the preparation and management of capital investment projects and thereby the reliability

of the results received. The Project Life cycle Process therefore provides a standardised, generic methodology in capital project

execution.

4.2. FRONT END LOADING (FEL)

The concept of Front End Loading (FEL) phases is key to the successful implementation and execution of projects. The term “Front

End Loading” is commonly used to illustrate the value and opportunity that may be realised by doing upfront work in the early

study phases of the project life cycle when there is still the potential to influence the successful outcome of the project.

The following project phases are commonly used in the project terminology:

• FER Front End Research

• FEL-1 Concept

• FEL-2 Prefeasibility

• FEL-3 Feasibility

• FEL-4 Execution

• Close-out

FER A basic need determination, based on future requirements.

FEL-1 A conceptual study in which the broad business concept is tested and a number of options are generated to implement

the requirement.

FEL-2 A pre-feasibility study in which the options are evaluated. A preferred option is prioritised, selected and the viability of

the project is more rigorously tested.

FEL-3 A feasibility study in which the selected option is more fully defined and its viability confirmed. The project to deliver

the solution is defined in terms of cost, schedule, scope and other required disciplines.

FEL-4 Execution in which the final design is completed and the capital investment is made and the project is executed to

deliver the defined outcomes in line with the scope, schedule, cost, quality and other defined parameters.

Close-out The closing and evaluation process to terminate the PLP project phase and to ensure all deliverables are handed over

in line with owner requirements.

Estimating capital requirements 30 years into the future requires clarification and standardisation to enable consistent application

of principles.

4.3. PROJECT DURATION

Project timing is crucial in the planning framework. Required capacity is market driven, all projects are therefore planned to provide

capacity when required (ahead of demand) regardless of short-term cyclical swings. The project’s future required date is therefore

used as the base and all planning phases are planned accordingly.

The project duration will differ from project to project depending on the size and complexity of the project. The typical project

duration (FEL-4 Execution) for Transnet projects can vary between one to seven years.

Page 28: LTPF - Transnet

506

Transnet SOC Ltd © LTPF 2016

4.4. PROJECT TIMELINES

Working back from the project required date, allowing for the project execution, (FEL4), time must also be allowed for the planning

phases of the PLP process, i.e. FEL 1-3. The duration of project studies varies, based on the size and complexity of the project. The

duration of study phases are typically (in months):

FEL-1 between 6 to 12 months

FEL-2 between 6 to 12 months

FEL-3 between 12 to 18 months

For long-term planning purposes, where the studies have not been committed, study durations have been standardised for FEL-1

and FEL-2 at six to twelve months each and for FEL-3 at twelve months per project.

4.5. PROJECT ESTIMATES

Each FEL phase is associated with a specific “class” of estimate corresponding to the level of work done during that phase. A cost

estimate is a forecast of the cost of an engineered construction project, prepared in a systematic manner appropriate to the size

and complexity of the project and to a level of accuracy commensurate with the available information and the intended use of the

information developed.

The indicative accuracy of project estimates and the level of contingency included in the different PLP phases are as per the PLP

manual and are:

Indicative accuracy range Level of contingency

FER <-50% to >+50% >30%

FEL-1 -50% to +50% 30% to 50%

FEL-2 -20% to +20% 20% to 30%

FEL-3 -10% to +15% 10% to 15%

FEL-4 -5% to +10% up to 10%

Table 3: Study accuracy and contingency per PLP phase

Projects in the 30-year plan (LTPF) estimates are determined based on the following:

• Rail projects: estimates for rail projects included in the LTPF in the FER stage are based on a Unit Costing Model

developed for Group Capital. This model provides estimates on a -30% to +50% accuracy (FEL-1).

• Port projects: estimates for port projects in the FER stage are based on best past experience and the knowledge and

expertise of industry experts. Accuracy levels are as indicated above.

• Pipeline projects: accuracy levels are as per the above guidelines.

Page 29: LTPF - Transnet

507

Transnet SOC Ltd © LTPF 2016

4.6. ESCALATION

Values included in the LTPF 2016 are non-escalated 2016 values. Although we recognise the critical role inflation can play in

project cost estimation, the 30-year estimates are based on real cost projections and exclude escalation cost. Escalation is,

however, considered in the FEL1-3 study estimates and included in the Corporate Plan estimates.

4.7. EXPANSION CAPITAL ONLY

Only expansion capital requirements are included in the 30-year plan. The fundamental starting point of developing the long-term

planning framework is that the existing capacity and the capacity created by the various expansion interventions are maintained at

the designed levels. Capital required to replace existing capacity and sustaining the current levels are therefore provided for by the

individual operating divisions for inclusion in the Corporate Plan (CP) and the budget.

4.8. UNCONSTRAINED VIEW

All capacity requirements represent an unconstrained view and have not been verified and tested against profitability and

affordability and cannot solely be funded off Transnet’s balance sheet.

4.9. LAND ACQUISITION COST

Land acquisition costs are not reflected in the rail capacity expansion estimates. Some strategic land acquisitions are however

indicated in the port plans, but are not project specific and are excluded from the project cost.