LTU/Undulator Installation Status. Enzo Carrone June 17 th , 2008. Scope. Install, Commission and Test Controls by JAN 09. Subsystems: BPM Cable Plant (monitoring) LTU Motion Control - UCM (Undulator Control Modules) Magnet Power MPS Network PPS/BCS Timing Vacuum. AMO - PowerPoint PPT Presentation
Citation preview
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 20081
LTU/Undulator Installation Status
Enzo Carrone
June 17th , 2008
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 20082
Scope
Install, Commission and Test Controls by JAN 09.
Subsystems: BPM
Cable Plant (monitoring)
LTU Motion Control - UCM (Undulator Control Modules)
Magnet Power
MPS
Network
PPS/BCS
Timing
Vacuum
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 20083
LCLS Installation and Commissioning Time-LineLCLS Installation and Commissioning Time-Line
LTU
/Und
/Dum
p
LTU
/Und
/Dum
p
Inst
all
Inst
all
LTU/LTU/UndUnd
Comm. Comm.
Re-Re-commission commission
Inj/BC2 to SL2Inj/BC2 to SL2
First LightFirst Lightin FEEin FEE
PEP-I
I ru
n
PEP-I
I ru
n
ends
ends
FEE/N
EH
In
stall
FEE/N
EH
In
stall
PPS C
ert
. LT
U/D
um
pPPS C
ert
. LT
U/D
um
p
FEH
In
stall
FEH
In
stall
CD
-4C
D-4
(7
/31
/201
0)
(7/3
1/2
01
0)
X-R
ays
in N
EH
X-R
ays
in N
EH
First LightFirst Lightin FEHin FEH
JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJ AAAA SSSS DDDD JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJ AAAA SSSS OOOO NNNN DDDD JJJJ FFFF MMMM AAAA MMMM JJJJ JJJJOONNAA
2008 2009 20102008 2009 2010 2008 2009 20102008 2009 2010DownDown
PPS
PPS
AAMM
now
now
Linac/BC2 Linac/BC2 CommissioninCommissionin
g g FEEFEE
Comm. Comm. April 18, 2008April 18, 2008
FEH
Hutc
h B
OFE
H H
utc
h B
OXPP XPP
ExperimeExperiment nt
program program beginsbegins
AMOAMOExperimeExperime
nt nt programprogrambeginsbegins
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
Phase 4 Installation
4
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 200855
Ion Pump
WPM
HLS
Interface Cable Box
Undulator Magnet
QUAD
RFBPM
Girder
RF Receiver Box
BFW
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 20086
Undulator Segment (Wall side)
Vacuum chamber EIA(Raceway)
(Courtesy of Scott Doran, ANL)
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 20087
Undulator Segment (Aisle side)
BPM
Quad/Corrector
Translation Stage
CAM Mover
Electronics Rack (UCM)
BFW
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 20089
UIR- (Undulator Instrumentation Rack)
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
Electronic Interface Assembly (EIA)
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
Electronic Interface Assembly (EIA)
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 200812
Time Management
ScheduleThree levels of scheduling: System (working), Controls (management), Master (communication).
Owners: System Leads, LCLS Installation Manager, LCLS Project Office.
Structure: waterfall approach.
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 200813
Schedule Control:Weekly Master Installation Schedule Management Meetings: review of schedule, action items, technical, personnel and safety issues.
Same for Weekly Controls Schedule Management.
Master Schedule organized both by geographical and system representation.
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
Management Schedule
14
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
ANL Delivery
16
A delegation from SLAC visited ANL in May, 08 (A. Alarcon, E. Carrone, E. Williams).
The outcome has been very satisfying:An assembly line has been setup at ANL to populate the Undulator Instrumentation Racks (“Mini Racks”);
EIA are manufactured outside;
The whole manufacturing/subcontractor management process is very well organized;
LTT is remarkably accurate;
ANL has been doing heroic efforts to deliver in time.
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 200817
UIR Assembly Line
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
ANL Racks shipping
18
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
Undulator Motion Controls Installation
16 pre-assembled UIR received from ANL on June, 16th;
EIA will be shipped on next June, 24th.
Installation is Davis-Bacon;
Begin: 6/16/08 – End: 6/26/08.
ANL has released a “Handover Plan”.
SLAC to follow a documented procedure for test and installation.
19
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
Undulator Motion Control Installation Schedule
20
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
Racks – Weekly Readiness Status
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
Rack Population Tracking System
Building 24 assembly area
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
Racks in the field
0 of 3925 of 70
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
Vacuum
24
All LTU PLCs assembled and programmed;
Complete:BTH: 7/25/08
UH: 10/2/08
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
MPS
25
Link Processor and Link Node complete;
Beam Loss Monitor complete;
A nice test bench is in use.
Complete:BTH: 10/28/08
UH: 10/29/08
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
BPM
26
50 BPM Chassis complete, tested and installed;
Cavity BPM Receiver Power Supply and Signal Distribution Panels complete;
Complete:BTH: 10/14/08
UH: 10/27/08
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
PPS/BCS
27
New organization: Documentation Office (Leader: M. Saleski);
PLC firmware updated;
Critical safety software complete (PILZ).
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 2008
PPS/BCS
29
A LION mockup has been installed in the Undulator Hall during last week;
Complete:BTH: 20/6/08
UH: 9/30/08 (a little ahead)
Certification: 10/20/08 to 10/31/08
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 200830
Network
Cable Fibers are being pulled;
Complete:BTH: 6/30/08
UH: 9/18/08
Cable Plant
Davis-Bacon contract.
Complete:BTH: 9/9/08
UH: 9/23/08
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 200831
Magnets Power Supply
All Racks in B912 Installed;
DataBase and displays ready;
Complete:BTH: 12/09/08
UH: 10/7/08
Timing
Complete:BTH: 9/23/08
UH: 10/28/08
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 200832
J. Murphy
Installation
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 200833
SLAC On-Field Installation Management
Daily tailgate meetings (by K. Ratkliffe/M. Zurawel)
Review parts availability, deliveries, acceptance, inventories;Discuss daily work plan, technical and transportation issues, personnel issues and safety issues.
Turner and LCLS meet weekly for co-occupancy schedule integration
A set of procedures and documentation is available on line (sharepoint).
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 200834
Installation Management - Safety
System Leads are being “Green Dot” trained and certified by SLAC/TCCo.
LCLS Project Office has put in place a systematic procedure for construction area access.
A Pilot Project (BCS LION Installation) paved the road.
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 200835
Areas to watch carefully
Tight Installation ScheduleANL is delivering in time.
MPS (new system);
BLMs (schedule, budget);
Downtime → PPS (Certification, upgrades, preventive maintenance);
Motion Controls;
Co-occupancy with TCCo.
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 200836
Summary
Controls installation expected on schedule;
Controls will not be in the way of the beam delivery to LTU in next Jan 09;
SLAC can count on the assistance of ANL system experts on site, if needed.
Enzo Carrone
LTU/Undulator Installation Status [email protected]
June 17th, 200837
Special thanks to the ANL team for working so hard to deliver in time!