  • Current activity Funding Electronics, infrastructure, etc GEANT3 Monte-Carlo simulations Space limitations? Construction plans
  • Slide 3
  • Space limitations 180x180mm 2 @z=200cm possible? Wire chamber frame/cabling? Coil installation tolerance? 12.00 degree view19.45 degree view0.00 degree view
  • Slide 4
  • Tentative schedule Design, materials, etcMay-Jul 2010 First 3 chambers readyDec 2010 Test run installationDec 2010 Feb 2011 Test runFeb-Jul 2011 Remaining chambers readyJul 2011 Final installationJul-Aug 2011 CommissioningAug-Dec 2011