Upload
faisal-karim
View
214
Download
0
Embed Size (px)
Citation preview
8/6/2019 LV&HV
1/35
Engineering & Project ManagementEngineering & Project Management 1 of 54
LV & HV SwitchgearsLV & HV Switchgears
PRESENTATIONPRESENTATION
8/6/2019 LV&HV
2/35
Engineering & Project ManagementEngineering & Project Management2
of 54
1) Definitions
a) Switchgear
b) Disconnector
c) Switch
d) Circuit Breaker
2) Types of LV Circuit Breakers
3) Types of HV Circuit Breakers
4) Ring Main Unit (RMU)
Table of Contents
8/6/2019 LV&HV
3/35
Engineering & Project ManagementEngineering & Project Management3
of 54
A general term covering switching devices with associated control, measuring and
protection equipment, and assemblies of equipment with support structures, connections,enclosures.
Switchgear functions
Allow network control and disconnecting of circuits.
Protect the network from faults (Circuit Breaker)
Provide system monitoring (i.e. voltage and current)
Allow safe access to circuits
Switchgear
8/6/2019 LV&HV
4/35
Engineering & Project ManagementEngineering & Project Management 4 of 54
Disconnector (Isolator)
A device used to create a safe, insulated gap in an electrical system and generally intended
to be operated off load.Able to withstand system over-voltages. Can carry rated fault
current when closed. Cannot be used to break fault or load current.
Switch
A device capable of breaking load current, up to a defined level of overload. Also able to CLOSE
fault current up to a defined current and time limit (rating) but not BREAKfault current. Often
used for the same safety function as a Disconnector when it is then referred to as a Switch
Disconnector.
Three position combined
disconnector and earthing
switch
8/6/2019 LV&HV
5/35
Engineering & Project ManagementEngineering & Project Management 5 of 54
Circuit Breaker
A device capable of MAKING and BREAKINGfault current up to a defined limits of current and
time. Capable of automatic operation when the
protection system detects a system fault.
The maximum operating time for CB is 65
milliseconds
8/6/2019 LV&HV
6/35
Engineering & Project ManagementEngineering & Project Management6
of 54
Types of LV Circuit Breaker
1) Current Limiting
2) Withdrawable
3) Moulded Case CB (MCCB)
4) Miniature CB (MCB)
8/6/2019 LV&HV
7/35
Engineering & Project ManagementEngineering & Project Management7
of 54
Types of HV Circuit Breaker
1) Oil Circuit Breaker
2) Air Circuit Breaker
3) Air Blast Circuit Breaker
4) SF6 Circuit Breaker
5) Vacuum Circuit Breaker
8/6/2019 LV&HV
8/35
Engineering & Project ManagementEngineering & Project Management8 of 54
Oil Circuit Breaker
This is the basic
action of oil circuit
breakers
The arc is
stretched and
cooled until it
is extinguished
8/6/2019 LV&HV
9/35
Engineering & Project ManagementEngineering & Project Management9 of 54
Small oil volume
circuit breaker
action
The oil in the lower
compartment is
normally separate from
that in the uppercompartment, but it is
pumped through to the
upper compartment, to
clear the arc, when the
CB operates
Oil Circuit Breaker
8/6/2019 LV&HV
10/35
Engineering & Project ManagementEngineering & Project Management10 of 54
The Air Circuit
Breaker was once
popular, now
superseded by SF6or Vacuum for
applications above
1kV. This is the
magnetic blow out
principle
Air Circuit Breaker
8/6/2019 LV&HV
11/35
Engineering & Project ManagementEngineering & Project Management11 of 54
The Air Blast Circuit breaker is still widely used at transmission voltages
Arc
splitter
plates
Air tank
Blast
valve
Blast
nozzle
Air Blast Circuit Breaker
8/6/2019 LV&HV
12/35
Engineering & Project ManagementEngineering & Project Management12 of 54
This isolator
must be
capable of
closing fault
current
Method of operation
Air Blast CB
Air Blast Circuit Breaker
8/6/2019 LV&HV
13/35
Engineering & Project ManagementEngineering & Project Management13 of 54
SF6Circuit Breaker
8/6/2019 LV&HV
14/35
Engineering & Project ManagementEngineering & Project Management14 of 54
Vacuum Interrupter
Vacuum Circuit
Breaker
8/6/2019 LV&HV
15/35
Engineering & Project ManagementEngineering & Project Management15 of 54
Ring Main Unit (RMU)
A three element device combining two
Switch disconnectors and a Circuit
Breaker (sometimes a Switch Fuse) in the
same enclosure. Used widely in
distribution systems.
8/6/2019 LV&HV
16/35
Engineering & Project ManagementEngineering & Project Management16 of 54
CB
OPEN
8/6/2019 LV&HV
17/35
Engineering & Project ManagementEngineering & Project Management17 of 54
CLOSED
And a three
position switch-
disconnector/
earthing switch
8/6/2019 LV&HV
18/35
Engineering & Project ManagementEngineering & Project Management18 of 54
OPEN
And a three
position switch-
disconnector/
earthing switch
8/6/2019 LV&HV
19/35
Engineering & Project ManagementEngineering & Project Management19 of 54
EARTH
And a three
position switch-
disconnector/
earthing switch
8/6/2019 LV&HV
20/35
Engineering & Project ManagementEngineering & Project Management20 of 54
Important -
The circuit is
not earthed
until the CB is
also closed
8/6/2019 LV&HV
21/35
Engineering & Project ManagementEngineering & Project Management21 of 54
The vacuum
Circuit Breaker is
not a POINT of
ISOLATION; the
disconnector is the
POINT of
ISOLATION
8/6/2019 LV&HV
22/35
Engineering & Project ManagementEngineering & Project Management22 of 54
The Ring
Switches
comprise athree position
switch
disconnector/
earthing switch
CLOSED
8/6/2019 LV&HV
23/35
Engineering & Project ManagementEngineering & Project Management23 of 54
OPEN
The Ring
Switches
comprise athree position
switch
disconnector/e
arthing switch
8/6/2019 LV&HV
24/35
Engineering & Project ManagementEngineering & Project Management24 of 54
EARTH
The Ring
Switches
comprise athree position
switch
disconnector/e
arthing switch
8/6/2019 LV&HV
25/35
Engineering & Project ManagementEngineering & Project Management25 of 54
Test access to the
circuit may be
obtained by
removing the lower
panel, opening
these sockets andusing the operating
handle to remove
the star bar
(otherwise known
as the EARTH
LINK
) from theearth contacts
8/6/2019 LV&HV
26/35
Engineering & Project ManagementEngineering & Project Management26 of 54
Although network diagrams appearcomplex, they are made up of simple
elements
Consider the circuit shown in red
8/6/2019 LV&HV
27/35
Engineering & Project ManagementEngineering & Project Management27 of 54
Although network diagrams appearcomplex, they are made up of simple
elements
Consider the circuit shown in red
It comprises circuit breakers at A and B
And an open point at C
8/6/2019 LV&HV
28/35
Engineering & Project ManagementEngineering & Project Management28 of 54
The circuit breaker at A protects thenetwork shown in green
The circuit breaker at B protects the
network shown in brown
8/6/2019 LV&HV
29/35
Engineering & Project ManagementEngineering & Project Management29 of 54
The non automatic switches(disconnectors) out on network allow
different parts of the network to be
isolated, if faulty, and then repaired
This arrangement is known as
a RADIAL NETWORK
8/6/2019 LV&HV
30/35
Engineering & Project ManagementEngineering & Project Management30 of 54
Only the circuit breakers at A and Boperate automatically to disconnect
faults. The remainder of the network
switchgear is non automatic but it has
the capability to OPEN load current
and CLOSE fault current
8/6/2019 LV&HV
31/35
Engineering & Project ManagementEngineering & Project Management31 of 54
At each substation, the localtransformer is protected by a circuit
breaker or switch fuse
8/6/2019 LV&HV
32/35
Engineering
& Project
Management
Engineering
& Project
Management 32 of 54
In radial networks, the restorationtime after a fault or damage incident
is normally:
Formost of the substations, the time
needed to carry outmanual switching
In the worst case, the repair time on
the cable or overhead line
8/6/2019 LV&HV
33/35
Engineering
& Project
Management
Engineering
& Project
Management 33 of 54
WHY DO THE NETWORKSWITCHES NEED A FAULT
MAKING CAPABILITY?
Consider a fault occurring
on the network controlled
by circuit breaker A
At this stage, it is not
possible to knowwhere the
fault is located, only that
circuit breaker A hastripped and supplies are lost
8/6/2019 LV&HV
34/35
Engineering
& Project
Management
Engineering
& Project
Management 34 of 54
WHY DO THE NETWORK
SWITCHES NEED A FAULT
MAKING CAPABILITY?
Begin restoration by
opening at the firstsubstation and closing the
circuit breaker
Next close the switch to the
branch circuit
Close the switch towards theopen point C
At this point we have re-
energised the fault; the
network switch has closed
fault current, circuit
breaker A should open 1-2seconds later
8/6/2019 LV&HV
35/35
Engineering
& Project
Management
Engineering
& Project
Management 35 of 54
THANK
YOU