Name of Project: INTERIOR TENANT OFFICE RENOVATIONS Address: 961 MARCON BLVD., SUITE 310, ALLENTOWN, PA Proposed Use: OFFICES Contact Person: STEVEN GLICKMAN ARCHITECT Suite #: 3RD FLOOR, SUITE 310 Code Enforcement Jurisdiction: HANOVER TOWNSHIP, LEHIGH COUNTY LEAD DESIGN PROFESSIONAL: Architectural: STEVEN GLICKMAN ARCHITECT 400 NORTHAMPTION STREET, SUITE 500 , EASTON PA 18042 610.243.6536, steven@stevenglickmanarchitect.com YEAR EDITION OF CODE: PA UCC - IBC / IEBC / IFC / IEC / IPC / IMC / IECC, 2009 EDITIONS (EXISTING BUILDING) Drawing List CS-1 Title Sheet Project Info 1 D-1 Office Floor Plan Demolition 2 A-1.1 Office Floor Plan 3 A-1.2 Office Floor Finish Floor Plan 4 A-2 Office Reflective Ceiling Floor Plan 5 A-3 Interior Elevations 6 A-4 Schedules 7 A-5 Details 8 PROJECT NARRATIVE: Alternate Prices 1. Glass wall in Reception Area 2. New carpet in Storage Records/ Storage Library 3. Allowance for electrical work per the Bid Form Electrical Allowance: Contractor to propose an Work Area

LVPC CD-R1 11/06/14 CD-R1 11_06_14.pdf · 610.243.6536, [email protected] YEAR EDITION OF CODE: PA UCC - IBC / IEBC / IFC / IEC / IPC / IMC / IECC, 2009 EDITIONS

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: LVPC CD-R1 11/06/14 CD-R1 11_06_14.pdf · 610.243.6536, steven@stevenglickmanarchitect.com YEAR EDITION OF CODE: PA UCC - IBC / IEBC / IFC / IEC / IPC / IMC / IECC, 2009 EDITIONS

Name of Project: INTERIOR TENANT OFFICE RENOVATIONS

Address: 961 MARCON BLVD., SUITE 310, ALLENTOWN, PAProposed Use: OFFICES

Contact Person: STEVEN GLICKMAN ARCHITECT

Suite #: 3RD FLOOR, SUITE 310

Code Enforcement Jurisdiction: HANOVER TOWNSHIP, LEHIGH COUNTY

LEAD DESIGN PROFESSIONAL:Architectural: STEVEN GLICKMAN ARCHITECT

400 NORTHAMPTION STREET, SUITE 500 , EASTON PA 18042610.243.6536, [email protected]

YEAR EDITION OF CODE: PA UCC - IBC / IEBC / IFC / IEC / IPC / IMC / IECC, 2009 EDITIONS(EXISTING BUILDING)

Drawing List CS-1 Title Sheet Project Info 1

D-1 Office Floor Plan Demolition 2A-1.1 Office Floor Plan 3A-1.2 Office Floor Finish Floor Plan 4A-2 Office Reflective Ceiling Floor Plan 5A-3 Interior Elevations 6A-4 Schedules 7A-5 Details 8

PROJECT NARRATIVE:

Alternate Prices 1. Glass wall in Reception Area 2. New carpet in Storage Records/ Storage Library

3. Allowance for electrical work per the Bid FormElectrical Allowance: Contractor to propose an

Work Area

Page 2: LVPC CD-R1 11/06/14 CD-R1 11_06_14.pdf · 610.243.6536, steven@stevenglickmanarchitect.com YEAR EDITION OF CODE: PA UCC - IBC / IEBC / IFC / IEC / IPC / IMC / IECC, 2009 EDITIONS

Kitchen

Phase 3 Phase 1

Phase 2

Page 3: LVPC CD-R1 11/06/14 CD-R1 11_06_14.pdf · 610.243.6536, steven@stevenglickmanarchitect.com YEAR EDITION OF CODE: PA UCC - IBC / IEBC / IFC / IEC / IPC / IMC / IECC, 2009 EDITIONS

Phase 3 Phase 1

Phase 2

Page 4: LVPC CD-R1 11/06/14 CD-R1 11_06_14.pdf · 610.243.6536, steven@stevenglickmanarchitect.com YEAR EDITION OF CODE: PA UCC - IBC / IEBC / IFC / IEC / IPC / IMC / IECC, 2009 EDITIONS

Phase 3 Phase 1

Phase 2

Page 5: LVPC CD-R1 11/06/14 CD-R1 11_06_14.pdf · 610.243.6536, steven@stevenglickmanarchitect.com YEAR EDITION OF CODE: PA UCC - IBC / IEBC / IFC / IEC / IPC / IMC / IECC, 2009 EDITIONS

Kitchen

Phase 3 Phase 1

Phase 2

Page 6: LVPC CD-R1 11/06/14 CD-R1 11_06_14.pdf · 610.243.6536, steven@stevenglickmanarchitect.com YEAR EDITION OF CODE: PA UCC - IBC / IEBC / IFC / IEC / IPC / IMC / IECC, 2009 EDITIONS

12'-0"

Ref.

Kitchen

Page 7: LVPC CD-R1 11/06/14 CD-R1 11_06_14.pdf · 610.243.6536, steven@stevenglickmanarchitect.com YEAR EDITION OF CODE: PA UCC - IBC / IEBC / IFC / IEC / IPC / IMC / IECC, 2009 EDITIONS

Equipment Schedule

IDDW-1 1 Bosch/PGN spec. sheet 24" Panel ready dishwasher 33 7/8" x 23 9/16" x 23 1/16" SHV7PT53UC 12 1300 120 Provide Plam-1 panel to match cabinetryMW-1 1 Bosch Drawer Microwave 800 series - stainless steel 16 5/16" x 23 7/8" x 23 3/8" HMD8451UCWH-1 1 Under-sink electric tankless water heater 7736500683 50 2685 240, 220, 208 3/4" 3/4" 6GA wire minimum

F-1 1 Grohe - Single Leaver Faucet 32138Concetto

* * *Refer to manufacturer

S-1 Elkay- kitchen Countertop Sink (ADA) 21L x 15W x5 3/8"D GE12521 1 1/2" angle stop craft model G2CR198200A or approved equal.00 flex kit with 20" length braided riser and 1/4 turn valve Provide one-piece faucet supply kits 1/2 sweaat with 3/8" polished chrome p-trap proflo model PF8617H or equal. drain with tailpiece proflo model PFHGO. 1 1/2" 17 gauge bowl, 1faucet hole, and 5-3/8" bowl depth. provide grid bearing stainless steel, self-running, 3 1/2" drain opening in Single bowl countertop sink, #22 gauge, typ 304 nickel

CL Hafele Luminoso LED Cabinet Light 3/8" x 2 5/16" x 78 3/4" 830.64.231CT Roppe Tile Carpet Joiner 177

Refrigerator (by owner)

GENERAL NOTES - PLUMBING

1. Provide all labor and materials needed for a complete and properly operational plumbing system

2.. The plumbing contractor is responsible for checking and verifying all conditions and dimensions and for coordination of his work with that of other trades. perform work in an orderly manner and with the least possible interference.

3. The plumbing contractor shall conform to NSF 61 for the water distribution piping.

4. Valves and fittings shall be lead free which means not containing more than 0.2 percent lead when used with respect to solder and flux;and not more than a weighted average of 0.25 percent lead when used with respect to the wetted surfaces of pipes, pipe fittings, plumbing fittings, and fixtures per the "safe drinking water act (section 1417) amended 1-4 2011" and other equivalent stat regulations

5. The plumbing contractor shall protect the piping from stress and strain to conform to all applicable codes.

6. All equipment and materials incorporated in this work shall be new unless noted otherwise and shall be current products by manufacturers regularly engaged in the production of the products.

7. All factory applied coatings and finishes shall be provided without rust, scratches, or dents.

8. Provide owner with certificates of final inspections and acceptance from the authority having jurisdiction.

15050 BASIC PLUMBING REQUIREMENTS

1. GeneralA. The owner accepts no responsibility for loss or damage to materials or structures on site, or for the salvage value of

which the plumbing contractor my have reflected on their bid. The contractor shall effectually protect at their own expense, their work, materials, and equipment that is subject to damage during construction period.

B. The plumbing contractor shall file, secure, and pay for any necessary approvals, permits, and inspections.C. All systems shall be tested in accordance with the requirements of all federal, state, and local authorities having

jurisdiction.. the plumbing contractor to coordinate tests with local officials.D. Prior to testing, the plumbing contractor shall make all system adjustments required for proper operations.

2. Scope of workA. It is the intent of the drawings and specifications that he plumbing contractor shall provide a working installation

complete in every detail, and all items necessary for a complete installation shall be furnished whether of not specified or shown on the drawings.

B. Upon completion of the work, all equipment shall be thoroughly cleaned and left in first class condition.C. The contractor shall be responsible for the start up of all systems.D. The contractor shall build into his work all sleves, anchors, inserts, chases, recesses, openings, etc. necessary for

installation of the plumbing work unless otherwise noted. The plumbing contractor shall provide information as to the location of such items to the general contractor or construction manager prior to construction.

1. Scope of WorkA. The work of this contract includes the furnishings of all labor, materials, equipment and services necessary for, and

reasonably incidental to the installation in place, finished complete, unless otherwise noted, of all electrical work in accordance with the specifications and drawings.

B. Provide all testing of all equipment installed under this section and adjust the operation of such equipment. Systems shall be left in perfect operating condition.

C. Upon completion of the work, all equipment shall be thoroughly cleaned and left in first-class condition.D. This contractor shall be responsible for the protection of all equipment under this section until the final acceptance of the job.

2. RegulationsA. The electrical installation shall meet the latest requirements of the national electric code. In addition, state, municipal or

other authority laws, rules and regulations applicable to the work shall be followed.B. Secure and pay for any and all permits and inspections required by any of the foregoing authorities, and pay all other

costs in connection with the work. Upon the completion of the work, secure certificates of inspection from the middle department inspection association. All certificates shall be in triplicate and shall be delivered to the architect and shall become the property of the owners.

Finish ScheduleID Finish

Carpet-1 Carpet roll Tandus String Theory 04415 Shadow Lines 76004 Hybrid Resilient with Med floor backing rooms as notedRefer to drawings, submit sample to client for approval,

Carpet-2 Carpet tile Tandus Thoroughfare 04042 TBD Modular 24" x 24" w/ R3 backing All rooms except notedBase-1 Vinyl wall base Roppe 100 BlackPaint-1 Paint Sherwin Williams SW-7007 Ceiling Bright White EggshellPaint-2 Paint Sherwin Williams SW-6794 Flyway EggshellPaint-3 Paint Sherwin Williams SW-6922 Outrageous Green EggshellPaint-4 Paint Sherwin Williams SW-7007 Ceiling Bright White Gloss door frames throughoutWallcover-1 Bulletin Board Forbo 2182 at new desk - see drawingWallcover-2 Panel Fabric Knoll Textiles TBD Circle Line in Fennel Existing bulletin board re-cover existing - re-install as directed by owner

Reception desk counterlaminate work surfaces with wood & glass insert transaction Existing and new half-height walls with new power and data.

Kitchen cabinets throughout with laminate countertops and backsplashcabinets, microwave mounted under counter, adj. shelves sink, dishwasher with laminate faced panel to match Laminate upper and lower cabinets, handicap accessible

Lam-1 Cabinet faces Formica WhiteLam-2 countertops Formica GreyLam-3 Backsplash Formica 6901 vibrant green (gloss)CP Cabinet Pull Mockett DP3A/AS Satin Nickel

WD-1 TBD Plain black walnut (light finish) completedSample to be approved by owner before shop drawings

VCT Kitchen Floor Armstrong Imperial 51915Standard Excelon

Texture Charcoal

Page 8: LVPC CD-R1 11/06/14 CD-R1 11_06_14.pdf · 610.243.6536, steven@stevenglickmanarchitect.com YEAR EDITION OF CODE: PA UCC - IBC / IEBC / IFC / IEC / IPC / IMC / IECC, 2009 EDITIONS