V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
M. BAJKO AT MAS
on the behalf of the ANSALDO follow up team: F. Savary, A. Musso,and J. Herr (ISQ)
STATUS AND SPECIFIC ISSUES IN ASG
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
Status of the PRODUCTION Overview of the contract Production rate Problems
CONTENTStatus and specific issues at ASG
QUALITY Non Conformity Reports @ ASG Non Conformity Reports @ CERN
Conclusions
PERFORMANCE Specific Issues
Short Circuits Quench Heater Performance
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
STATUS OF THE CONTRACTStatus and specific issues at ASG
26.0
20.4
1.2
9.1
5.5
0.0
5.0
10.0
15.0
20.0
25.0
30.0
DELIVERED TESTED REJECTED ACCEPTED aftercold test
PROVISIONALLYACCEPTED
without cold test
% of the whole production of 416 cold masses
416 cold masses ORDERED108 cold masses DELIVERED
85 cold masses TESTED 5 cold masses REJECTED
38 cold masses ACCEPTED after cold test23 cold masses PROVISIONALLY ACCEPTED without cold test
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
STATUS OF THE CONTRACTStatus and specific issues at ASG
Courtesy of P. Lienard
Ansaldo Production Status01/10/2004
0
20
40
60
80
100
120
140
1.sep.021.oct.021.nov.021.déc.021.jan.031.fév.031.mars.031.avr.031.mai.031.juin.031.juil.031.aoû.031.sep.031.oct.031.nov.031.déc.031.jan.041.fév.041.mars.041.avr.041.mai.041.juin.041.juil.041.aoû.041.sep.041.oct.04
Time
Units
Total Equiv. Dipoles
Total Collared Coil Accepted
Total C.M. Welded
Total C.M. Delivered
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
STATUS OF THE CONTRACTStatus and specific issues at ASG
PRODUCTION
Time from June 2002 to SEPTEMBER 2006Time from June 2002 toJUNE 2006
To be done
Time left Time
left
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
NEEDED PRODUCTION RATEStatus and specific issues at ASG
3.3
3.7
3.3
00.5
11.5
22.5
33.5
4
In MARCH 2004 FORDELIVERY IN JUNE
2006
IN OCTOBER 2004 FORDELIVERY IN JUNE
2006
IN OCTOBER 2004 FORDELIVERY IN
SEPTEMBER 2006
COLD MASSES / WEEK
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
REAL PRODUCTION RATEStatus and specific issues at ASG
0
1
2
3
4
janvier.04février.04mars.04avril.04mai.04juin.04juillet.04août.04
septembre.04octobre.04
novembre.04décembre.04janvier.05février.05mars.05avril.05
delivered cold mass/ weekneded limit for JUNE 2006
0
1
2
3
4
janvier.04février.04mars.04avril.04mai.04juin.04juillet.04août.04
septembre.04octobre.04
novembre.04décembre.04janvier.05février.05mars.05avril.05
delivered cold mass/ weekneeded limit for SEPTEMBER 2006
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
Production: COLARED COILS, COLD MASSESStatus and specific issues at ASG
Production of collared coils and cold masses
0
2
4
6
8
10
12
14
jan.03fév.03mars.03
avr.03mai.03juin.03juil.03aoû.03sep.03oct.03nov.03déc.03jan.04fév.04mars.04
avr.04mai.04juin.04juil.04aoû.04sep.04oct.04
time staring from Jan 2003
production/month
Collaring
Cold mass delivery
2 per. Mov. Avg. (Collaring)Problem of performance;
waiting for feed back from cold test
Problem of coil geometry detected by
magnetic measurements **
** See presentation of E. Todesco and C. Voellinger
Intervention on the collaring press
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
Production: history and prevision
Status and specific issues at ASG
Courtesy of P. Lienard
Costruzione Collarati ASG
0
50
100
150
200
250
300
350
400
450
gen-01apr-01lug-01ott-01gen-02apr-02lug-02ott-02gen-03apr-03lug-03ott-03gen-04apr-04lug-04ott-04gen-05apr-05lug-05ott-05gen-06apr-06lug-06
Prev.tot.
Tot. ASG
Courtesy of ASG
Higher rate of production starting from
Sept 2004
ASG delivered the number of cold masses
foreseen by ASG
In spite of all problems,
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
QUALITY :Non Conformity Reports in ASGStatus and specific issues at ASG
NC distribution after March 31st, 2004 in ASG
9%
18%
24%0%
20%
29%
alignment
component
electrical
irriversible damage
mechanical
welding
Before March 31st, 2004
12%9%
17%
7%32%
23%alignment
component
electrical
irriversible damage
mechanical
welding
3.3 NC/ magnet
0.9 NC/ magnet
the QUALITY is better
Personal for Quality Control
0
4
8
12
16
déc.03 jan.04 fév.04mars.04
avr.04 mai.04 juin.04
time
number of controlers
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
QUALITY :Non Conformity Reports in ASGStatus and specific issues at ASG
NC on electrical and magnetical measurements (Normalised for delivered magnet numbers)
0.00
0.05
0.10
0.15
0.20
0.25
Quenchheater
Coil Wiresconnections
Temperaturesensor
Magnetic
NC/ magnet number
Until March 31st
After March 31st
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
QUALITY :Non Conformity Reports in ASGStatus and specific issues at ASG
NC on welding and alignment (Normalised for delivered magnet numbers)
0.0
0.3
0.6
0.9
Welding twist shape cold feetpads
assembly
NC/ magnet number
Until March 31st
After March 31st
The present NC on welding are mainly on short repairs and weld projections. The reduction of the extent of the radiographic examinations of the longitudinal welding has been started.
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
QUALITY : Non Conformity Reports in ASGStatus and specific issues at ASG
NC on Components (Normalised for the delivered magnet numbers)
0.00
0.05
0.10
0.15
collars bus bars copperwedges
endspacers
half shells interlayerspacer
cable polymide Correctors
NC/ magnet number
Until March 31st
After March 31st
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
QUALITY : Non Conformity Reports @ CERNStatus and specific issues at ASG
NC/cold mass
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
alstom ansaldo noell
NC/cold mass
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
QUENCH PERFORMANCE 1Status and specific issues at ASG
0
15
30
45
60
75
90
105
120
135
150
165
0 1 2 3 4 5 6 7 not reachedNumber of quenches to reach 8.33T
Number of Cryo-dipoles
01 Ansaldo 03
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
Quench performance is GOING BETTER!!!
6.00
7.00
8.00
9.00
1 11 21 31 42 57 74 86103
Magnet number
Field level [ T ]
1st quench
2nd quench
3rd quench
4th quench
5th quench
6th quench
7th quench
8th quench
9th quench
1st qu. ATC
2nd qu. ATC
3 per. Mov.Avg. (1stquench)
Quench history for Ansaldo Magnets
9 T
8.4 T
8.6 T
Courtesy of Quench Performance WU
QUENCH PERFORMANCE 2Status and specific issues at ASG
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
Quench performance is GOING BETTER!!!
0
10
20
30
40
50
60
1 QUENCH 2 QUENCHES 3 QUENCHES
FOR 8.33 T
% of magnets tested
MARCH 2004
OCTOBER 2004
QUENCH PERFORMANCE 3Status and specific issues at ASG
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
Specific issues Status and specific issues at ASG
Inter turn short circuits in the headsIdentify the most critical points: heads, end spacers; introduce extra insulation, take care during winding, insulate the end spacers; CERN helps ASG to identify by magnetic measurements before de collaring the sh .c . position
Quench heater damages during collaringReview the winding and collaring operations, reinforce quality control on QH
Quench performance: to open 2069To open the cold masses where well identified local weakness was detected during cold test; and learn from that
Keep quality control, reinforce the system following recommendations of the QA Audit
Magnetic field quality: a4, b.6 movements, a3Together with CERN continue the investigations to fix the cause and then to avoid a4 trend ; study the reasons of the bloc 6 movements in the series 208x and 209x.
V Session October 2004 M. Bajko
For the LHC Superconducting Cable and Magnet Production Review
CONCLUSIONSStatus and specific issues at ASG
PRODUCTION RATE is still not sufficient even with the new dead line, but the level of confidence for their planning presently is good. Starting from September the production rate have increased as foreseen… to be checked if they followed in 6 mounts.
QUALITY is better : less NC at the firms and lowest rate at CERN
QUENCH PERFORMANCE is going better: more magnet having 1 quench below 8.3T less magnets having 3 quenches
MAGNETIC FIELD QUALITY in generally is good but a4 has a trend for which no explanation up to today, b3 stabilized and some explanation for the b.6 movement were given but still not clarified
Refused magnets with well localized weak points should be opened AS SOON AS POSSIBLE to learn for them
ELECTRICAL incidents: as inter turn shorts and quench heater defects should be avoided by more quality control and review of the critical points of the assembly