34
MARINA CONDITION ASSESSMENT &RESERVE FUND ANALYSIS Ashley Marina Charleston, SC Prepared for: The Ashley Marina Homeowner’s Association Prepared By: November 2013

M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

MARINACONDITIONASSESSMENT&RESERVEFUNDANALYSISAshleyMarinaCharleston,SC

Prepared for: 

TheAshleyMarinaHomeowner’sAssociation      

Prepared By:

November2013   

Page 2: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

   

   

 

TableofContentsProject Background & Methodology .............................................................................................. 1 

Project Background ..................................................................................................................... 1 

Methodology ............................................................................................................................... 1 

Background Information Gathering ........................................................................................ 1 

Field Investigation ................................................................................................................... 1 

Reporting and Reserve Fund Analysis ..................................................................................... 2 

Marina Condition Assessment ........................................................................................................ 3 

Input from Kick‐off Meeting ....................................................................................................... 3 

Results of Field Inspection .......................................................................................................... 4 

Observations ........................................................................................................................... 4 

Discussion.............................................................................................................................. 18 

Recommendations & Conclusion .............................................................................................. 22 

Immediate/Life‐Safety (Year 0) ............................................................................................. 22 

Short Term (Years 1‐5) .......................................................................................................... 22 

Intermediate/Long Term (Years 5‐10+) ................................................................................ 22 

Remaining Useful Life ........................................................................................................... 22 

Application ............................................................................................................................ 23 

Reserve Fund Analysis ................................................................................................................... 25 

Conceptual Capital Cost Estimate ............................................................................................. 25 

Capital Project Summary .......................................................................................................... 25 

Funding Requirement Summary ............................................................................................... 25 

Annual Sinking Fund Requirement Summary ........................................................................... 26 

Amortization Tables .................................................................................................................. 26 

Reserve Fund Spreadsheets ...................................................................................................... 27 

 

Page 3: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 1 

   

PROJECTBACKGROUND&METHODOLOGY

ProjectBackgroundApplied  Technology  and  Management  (ATM)  has  been  contracted  by  the  Ashley  Marina Homeowner’s Association (HOA) to conduct a marina condition assessment and reserve funding analysis  for  the Harborage on  the Ashley marina, which  is also known as  the Ashley Marina.  The  facility  is  located on  the Ashley River on peninsular Charleston,  SC directly north of  the James Island Connector (SC Highway 30).  This  effort  is  being  undertaken  in  order  to  allow  the HOA  to  understand  the  annual  capital contributions necessary to meet anticipated short and long‐term capital needs.  

Methodology

BackgroundInformationGatheringATM held a project kick‐off meeting with Mr. Brian Swan (President of the HOA) and Mr. Bruce Wallace (Senior Dockmaster) at the Marina on September 22nd, 2013 to review the goals of the project  and  discuss  facility  condition,  maintenance,  and  development  history.    Also,  we reviewed specific areas of concern regarding physical facility condition with marina personnel. 

FieldInvestigationAfter meeting with Mr. Swan and Mr. Wallace, two (2) ATM marina professionals conducted a general condition assessment of the marina.   This  included a visual  inspection of above‐water portions of the marina.  Key elements reviewed included:  

Floating Docks 

Anchor Piles 

Gangways and Gangway Connections 

Shoreline Protection 

Dock Appurtenances (cleats, safety cabinets, etc.) 

Marine Utility Systems  Note:  Detailed  materials  testing  and/or  subaqueous  inspection  were  not  included  in  the 

current scope of work.  Similarly, the assessment of the marine utilities was limited to a cursory, visual overview and did not  included specific  testing of electrical components, water pressure/flow, etc. 

 ATM  was  unable  to  observe  sub‐deck  conditions  of  the  floating  docks  during  our  initial inspection  as  the  vast majority  of  the  decking was  screwed  down without  easily  removable access hatches.  After review of the initial findings of our field assessment, we determined that a  follow‐up  site  visit  was  necessary  in  order  to  evaluate  the  condition  of  sub‐deck  dock components (timber framing, connections, etc.).    

Page 4: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 2 

   

ATM  conducted  this  follow‐up  inspection  on November  6th,  2013.   With  the  help  of marina staff,  several  deck  boards were  removed  in  selected  locations  to  allow ATM  to  observe  the condition of the sub‐deck framing and utilities.  The observations made during  these  inspections were documented via  field notes and digital photography.   

ReportingandReserveFundAnalysis Upon  completion  of  the  field  investigations  ATM  compiled  our  findings  into  this  summary report.    Included  herein  are  recommendations  for  repair  requirements,  estimates  of  the remaining  useful  life  of  key marina  elements,  and  estimates  for  replacement  costs  of  key marina elements.  All of this information is necessary to inform the development of the Reserve Fund Analysis.  The Reserve Fund Analysis  is also  included  in  this report and presents  the annual  investment required to properly account for anticipated maintenance and capital replacement expenses for existing marina infrastructure.    

Page 5: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 3 

   

MARINACONDITIONASSESSMENT

InputfromKick‐offMeetingMr. Wallace  and Mr.  Swan  provided  useful  information  with  regard  to  the  historic  capital projects at the marina and current conditions.  Their comments are summarized below:  

The marina was re‐constructed after Hurricane Hugo in 1990‐1991. 

A major renovation to the docks was undertaken in 2006‐2007 which included: o Installation of new utilities o Removal old decking and replacement with Ipe decking and fascia 

Mr. Wallace noted  that  some  siltation has occurred at  the  approximate  location of  a stormwater outfall near the southern end of the marina, but otherwise no dredging has been required or has occurred recently. 

Mr. Wallace  indicated that the only known area of damage or concern  is at the end of the dock under  the gangway  to  the main docks.    It was apparent  to marina staff  that there may be an issue with dock framing integrity in this area. 

The upland building  is not  the HOA’s  responsibility and  therefore was not  included  in this review effort. 

The  marina  fueling  system  is  not  the  HOA’s  responsibility  and  therefore  was  not included in this review effort. 

Page 6: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 4 

   

ResultsofFieldInspectionATM’s initial inspection was undertaken on the afternoon of September 23, 2013.  The weather was sunny and cool with a strong northwest wind.   The  inspection was conducted on a falling tide so that a maximum amount of shoreline and anchor piling would be visible/exposed during the course of the inspection.  

ObservationsIn general, the marina  is  in good condition.     General observations with regard to each of the primary components of the marina are outlined below.  A basic schematic of the marina facility is also presented below for reference.  

 Figure 1 – Ashley Marina Layout 

 

FloatingDocksThe floating docks are in overall fair condition, noting the following specific observations: 

Flotation We understand  the  flotation units are  the original  “polytubs” which were  installed  in 

1990‐1991.   These are  rotationally molded polyethylene “tubs”  that encase expanded polystyrene  flotation.    The  polytubs  ATM  observed  on  site  were  manufactured  by Carolina Waterworks of Mount Pleasant. 

No significant cracking or other damage was noted on the polytubs.   

Freeboard heights (distance from the deck to the surface of the water) are low relative to industry standards.  Recorded freeboard elevations ranged from 11 to 20‐in.   

Where freeboard height is especially low, the timber framing and outer fascia boards of the docks are exposed to splash from wind‐generated waves and boat wakes. 

 

Page 7: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 5 

   

 Photo 1 ‐ Low Freeboard at the End of "T" Dock 

Significant  listing  (uneven  flotation  of  the  docks  such  that  one  side  of  the  dock  is higher/lower  than  the  other) was  noted  in  several  locations  throughout  the marina.  This listing resulted in as much as five (5) inches difference in elevation over the nine (9) foot wide main walkway  in  isolated  locations.   This was noted on  the main walkways and numerous fingers throughout the marina.  

 Photo 2 ‐ Listing Finger Pier 

It was also noted that the dock is “sunken” in areas around the electrical substations as well as at the floating dock office.  This may be caused by the additional weight of these structures that were not specifically included in the initial design.  

Page 8: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 6 

   

 Photo 3 ‐ Uneven Deck where Floatation Under Office is "Sunken" 

The section of  floating dock underneath the main gangway  is noticeably damaged.   At lower  tide  levels,  the  end  of  the  dock  is  higher  than  the main walkway,  resulting  in apparent stress and failure in the framing and fascia boards. 

 

 Photo 4 – Dock Section at Gangway During Low Tide 

Field measurements taken along this section of the dock indicate that the freeboard at the end of the dock (beneath the gangway) is approximately 6 ½‐in. higher than that of the main walkway at the end of the gangway at lower tide levels.  However,  during  ATM’s  follow  up  inspection,  it  was  noted  that  at  high  tide  the freeboard of the end of the dock is not noticeably higher than the adjacent main walk.  

Page 9: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 7 

   

 Photo 5 ‐ Dock Section at Gangway During High Tide 

Apparently, at higher  tide  levels,  the PVC utility  sleeves underneath  the gangway  rest upon the end of the dock, effectively pushing it down.  

 Photo 6 ‐ PVC Utility Lines Resting on End of Dock 

Framing ATM  observed  three  (3)  selected  areas  of  sub‐deck  framing  during  our  follow‐up 

inspection.  The framing observed appears to be in good condition. 

The marine hardware observed on the western (waterward) side of Dock “T” framing is heavily  corroded,  however.    In  fact,  this  hardware  has  deteriorated  to  the  point  to where it was brittle to the touch. 

 

Page 10: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 8 

   

 Photo 7 ‐ Broken Through‐bolt on Outside of Dock “T” 

 

 Photo 8 ‐ Corroded and Broken Through‐bolts and Nuts on Outside of Dock "T" 

Hardware  on  the  inside  side  of  Dock  “T”  and  at  other  sub‐deck  locations  observed appear to have developed a slight patina, but overall are in fair condition.  

Page 11: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 9 

   

 Photo 9 ‐ Through‐bolts on Inside of Dock "T" 

Decking ATM understands that the decking was replaced in 2007 Ipe hardwood. 

The relatively new Ipe decking is in excellent condition throughout the facility. 

The  Ipe was  also  added  as  fascia  to  the  outside  of  the  dock  framing.    This was  also observed to be in very good/excellent condition. 

Deck  screws were coming  loose  in  isolated  locations  throughout  the marina.   Though not widespread, these do present a potential tripping hazard in those locations. 

ATM  has  observed  this  phenomenon  at  similar marina  installations where  Southern Yellow Pine framing  is used with  Ipe decking.   The differential movement between the two materials can result in loosening deck screws and necessitate regular maintenance in certain areas.  

Page 12: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 10 

   

 Photo 10 ‐ Protruding Deck Screws 

AnchoringSystemThe anchor piles  for  the marina are  square concrete pre‐cast piles approximately 14 X 14‐in.  These piles are  typically  set  in  internal pile guides  (i.e. –  inside  the  frame of  the dock).    It  is noted that some smaller piles are located on Dock “C”.  We understand these piles are original (installed in 1990‐1991).    Overall,  the  anchoring  system  is  in  fair  to  good  condition,  noting  the  following  specific observations: 

ConcretePiles Exposed metal was noted on many of the piles, apparently from  lifting rings that were 

cut off after installation.    

Page 13: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 11 

   

 Photo 11 ‐ Exposed Metal on Piles 

 

Isolated  piles were  twisted  relative  to  the  orientation  of  the  dock.    This  is  generally considered an aesthetic concern only and likely occurred during pile driving as the dock framing was built around the twisted piles. 

 

 Photo 12 ‐ Twisted Pile and Internal Pile Guide 

Longitudinal cracking was noted on several piles.  The majority of these cracked piles are located on Dock C.   It  is noted that the most severe cracking was observed on the two (2) smaller (10‐in.) piles on the portion of Dock C closest to the shore, one of which  is cracked on all four (4) sides. 

Page 14: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 12 

   

 Photo 13 ‐ Cracked Pile (14‐in. Pile, Dock F) 

  

 Photo 14 ‐ Cracked Pile (10‐in. Pile, Dock C) 

Shellfish (oyster) growth was observed on a number of pilings.   In some areas this was substantial  and may  be  adversely  affecting  dock movement.    This  also  presents  an apparent laceration hazard during periods of low tide. 

Page 15: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 13 

   

PileGuides The majority of the pile guides throughout the marina are  in good working order with 

free‐spinning rollers.  

 Photo 15 ‐ Typical Pile Guide 

An  external  pile  guide  is  located  near  the  bottom  of  the  gangway  onto  the  main walkway near dock “D”.   This pile guide  is  loose and  it appears  that bolts are missing where  the pipe  framing of  the pile guide  connects  to  the metal bracket on  the dock. Additional external pile guides of the same design were noted on the outer portion of Dock “C” with similar observed conditions.   

 Photo 16 ‐ External Pile Guide 

Page 16: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 14 

   

On  Dock  C,  particularly  around  the  smaller  (10‐in.)  piles,  several  of  the  rollers were “frozen” and would not spin.  It was unclear whether this is a result of damaged rollers, shellfish growth, or a combination of both.  

 Photo 17 ‐ "Frozen" Roller and Shellfish Growth 

GangwaysandGangwayConnectionsThere are two (2) aluminum gangways on the property.  The main gangway is 34 X 6‐ft. leading from the fixed access pier down to the main part of the marina.  The second gangway is 24 X 4 ft. and leads from the access pier down to Dock “C.”  Both  gangways  are  in  good  condition with no  apparent damage. However, neither  gangway appears to be compliant with the most current guidelines of the Americans with Disabilities Act.  Specifically, no graspable handrail and no kick plate were observed on the gangways.  Also, the slope of  the gangway  that services Dock “C” appears  to exceed with ADA maximum slope of 1:12.    Though  notable  for management  purposes,  compliance with  ADA  guidelines  is  not  a requirement for private marina facilities.  

Page 17: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 15 

   

 Photo 18 – Steep Gangway Slope at Low Tide 

 

FixedTimberAccessPierandDeckThe  floating  docks  at  the  marina  are  accessed  via  a  single  fixed  timber  access  pier approximately 140 ft. long X 10 ft. wide.  The access pier leads to the two gangways discussed above as well as a 30 X 35 ft. deck/pier head.    The access pier and deck are in good condition noting the following specific observations:  

The handrail around the deck was  loose and could be moved relatively easily by hand.  This is indicative of inadequate or loose connections to the framing elements. 

There is a single aluminum security gate located on the fixed access pier.  The gate itself is in good condition, although the coded security lock was not inspected/tested. 

Portions of  the security screening on  the aluminum access gate are damaged and are pulling away from the door framing. 

Page 18: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 16 

   

 Photo 19 ‐ Security Screen Pulling Away from Door Framing 

ShorelineProtectionThe shoreline of the property  is generally stabilized by a combination of rip‐rap and concrete rubble.    Additionally,  stands  of  salt marsh  (spartina)  and  other  native  vegetation  serve  to stabilize the shoreline along the subject site.    

 Photo 20 – Typical Shoreline Stabilization 

 It  is  noted  that  flat  pieces  of  concrete  rubble  do  not  typically  provide  reliable  shoreline stabilization,  particularly  where  wave  action  may  occur.    Also,  the  shoreline  stabilization observed on the site appears to be organically developed rather than purpose‐engineered for 

Page 19: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 17 

   

the subject site.   Such an approach to shoreline stabilization  is not uncommon, however, and the area of the subject shoreline  is rather protected  from wind/wave activity by virtue of the adjacent marinas, bridge, etc.  Overall,  the  shoreline appears  to be  stable along  the  length of  the property with no obvious defects or noteworthy observations.  

DockAppurtenances(cleats,safetycabinets,etc.)Dock appurtenances throughout the marina are in good condition noting the following specific observations: 

Isolated cleats were not  fully  tightened down.   This was not widespread and ATM did not observe any that were loose enough to cause concern. 

Fire  cabinets  were  noted  to  be  in  good  condition  with  properly  charged  fire extinguishers. 

Dock Boxes  are  located  adjacent  to  selected  slips,  though widespread  in  the marina.  Those observed are  in good condition.   (We realize these may be privately owned and may not be the responsibility of the HOA.) 

MarineUtilitySystemsATM understands that the entire marina utility system (power, water, pedestals) was replaced during the 2007 renovation.  However, Mr. Wallace indicated that the old marina utility cables and  lines were  left  in place and the new utility  lines were placed  in the dock raceways beside the old ones.    

 Photo 20 ‐ In‐deck Utility Lines 

Page 20: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 18 

   

The  marine  utility  system  appears  to  be  in  good  condition  noting  the  following  specific observations:  

Water pressure appears adequate at the outermost docks. 

Power amperage/voltage was not tested, but marina staff did not  indicate any specific problems or concerns. 

Water was dripping  from  the utility pedestals and  saturating  the deck  surface around the base of the pedestal at numerous locations throughout the marina. 

 

 Photo 21 ‐ Water Dripping from Utility Pedestal 

Discussion Though  the marina appears  to be  in good  condition overall, ATM does have a  few  concerns from a physical/functional perspective that could affect the remaining useful life of the facility.  These include:  

1. Low Freeboard  2. Dock Listing 3. Dock damage at Main Gangway 4. Framing and hardware on outer side of Dock “T” 5. Cracked piles 6. Exposed lifting hooks 

 Each of these concerns is discussed in more detail below. 

Page 21: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 19 

   

LowFreeboardAccording  to  ASCE’s  Planning  and  Design  Guidelines  for  Small  Craft  Harbors,  floating  dock freeboards  typically  range  from  16  to  24‐in.,  depending  upon  the  specific  size  and  type  of vessels  utilizing  the  docks.    According  to  measurements  taken  during  our  inspection, approximately a third of the docks at the marina have freeboard elevations below this industry standard.  It  is  likely that this relatively  low freeboard  is the result of several factors.   Specifically, during the 2007 renovation of the docks  it  is understood that the original decking was replaced with Ipe hardwood decking.    Ipe  is significantly denser  than  traditional Southern Yellow Pine  (SYP) and as such likely increased the dead load acting on the flotation units.     Additionally, we understand that he old utility lines, including the electrical cabling, were left in place on the docks and the new utility  lines were  laid beside them.   This would also serve to increase  the  dead  load  on  the  flotation  units  significantly.    Finally,  the  age  of  the  pontoons could play into the lower than normal freeboards as well.  While the pontoons appear to be in good condition with no widespread deterioration, over  time  the growth of marine organisms such as oysters and barnacles serve to further weigh down the docks.  While many of the docks throughout the marina have freeboard measurements below industry averages, the  integrity of the dock system does not appear to be compromised based on this.  In areas with very low freeboard (i.e. – less than 12‐in.), the Ipe fascia boards and internal SYP framing are  subject  to  repeated  saturation by minor wind‐generated waves.   Over  time,  this could lead to deterioration of the fascia board and adjacent, internal framing.  However, there were only a couple of isolated locations where measurements below 12‐in. were recorded.  As such,  the relatively  low  freeboard of  the docks  is not considered  to be a critical concern, but should be monitored.   

ListingTypically, performance  specifications  for  floating docks  indicate  that a  total deflection under dead  load of no more  than 1.5  inches  in 10  feet  (0.15‐in. per  ft)  is acceptable.   On  the main walkways, measurements of selected areas indicate ~ 0.4 to 0.55‐in. per foot deflection, which is well above what we would be considered acceptable on a new  floating dock  system.   The listing on  several  fingers was  even more  severe, with  equivalent deflections of  greater  than 0.75‐in. per foot in isolated locations.  Such  listing  is not  atypical  for  timber  frame  floating docks, but  should be  addressed  though dock maintenance  (i.e.  examination  and  tightening  of  dock  connection  hardware,  counter‐weighting where necessary, etc.). 

DamagedDockatMainWalkwayIt  is  apparent  that  there  is  either  framing  damage  or  substantial  framing  stress where  the access gangway  lands on the main access dock.   Marina staff have  indicated that they believe the uplift at the end of the main walkway (beneath the gangway) may be caused by the utility 

Page 22: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 20 

   

lines running underneath the gangway and into the docks which puts undue stress on the docks during extreme high tides.  While this certainly may contribute to the situation, it appears that the damage is more likely attributable to insufficient flotation directly beneath the gangway.    The gangway  imposes a direct point  load where  it comes  in contact with  the dock.   Without sufficient  flotation directly underneath the gangway, the point  load of the gangway creates a bending moment in the dock during low tide as generally illustrated below.  

 Figure 2 ‐ Gangway Loading at Low Tide 

However, at high tide, the gangway effectively rests on the end of the dock, which changes the 

loading pattern significantly: 

 

 

 Figure 3 ‐ Gangway Loading at High Tide 

Page 23: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 21 

   

Based upon our observations, this cyclical loading pattern is the most likely cause for the 

fatigue and failure in the fascia and framing members along this section of the dock, though it is 

noted  that with the presence of the gangway ATM was not able to access/observe the internal 

framing of the dock in this area. 

This area should be repaired as it provides critical access to the vast majority of the slips at the 

subject marina. 

FramingandHardwareonOuterSideofDock“T”Based upon  the  limited  sub‐deck  inspection conducted by ATM,  the primary area of concern with regard to the framing is the outermost side of Dock “T”.  Wind‐generated waves and vessel wakes  in  the  Ashley  River  splash  directly  onto  the  outer  side  of  this  dock.    This  increased exposure  is  leading  to  significant  degradation  of  the  framing  hardware,  and  particularly  the galvanized through‐bolts on the outer side of Dock “T”.  Due  to  the  advanced  deterioration  of  the  through  bolts  observed,  all  of  the  dock  framing hardware  in  this area of  the marina should be  replaced  immediately with new stainless steel materials.  This is a critical concern in light of the presence of marina fueling infrastructure on this dock, direct exposure to wind/wave/wake activity, and the presence of larger yachts in this area of the marina.    

ExposedLiftingHooksThis exposed  lifting  ring  remnants on  the piles  throughout  the marina are  corroding  slightly.  While  this  is  not  considered  to  be  an  immediate  structural  concern,  these  can  provide  an avenue for corrosion to penetrate the interior of the pilings and may also lead to staining of the piles.    Given that the rings have apparently been exposed since installation in the early 1990s, the rate of corrosion  is apparently slow enough  that  this  is not  likely  to become a concern during  the remaining useful life of the piles. 

CrackedPilesThe  longitudinal cracking along several of  the piles warrants discussion as well.   This damage was  isolated primarily  to Dock “C”  (and a  limited number of piles  in  the main portion of  the marina).   The cracking appeared  to occur primarily  in  the  intertidal  zone where  the piles are exposed to both air and water throughout the tidal cycles.   The cracks are moderately severe and  appear  to  penetrate  deeply  into  the  pile.    This  generally  indicates  that  the  interior reinforcing  steel  is  likely  exposed  to  water/air  as  well.    The  cracks,  along  with  potential corrosion  of  interior  bars, would  serve  to  significantly weaken  the  pile.    This  is  not  likely  a concern  during  normal  operating  conditions.    However,  periods  of  high wind  and/or wave loading, particularly during high tide or storm conditions, will place a greater moment on the piles and could lead to further damage to the piles.    

Page 24: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 22 

   

 

Recommendations&ConclusionBased  upon  our  inspections  and  discussions  outlined  above,  the  following  are  ATM’s recommendations with regard to the repair, maintenance, and replacement of various marina elements.   These  recommendations have been  categorized  into  Immediate/Life‐Safety,  Short Term, and Long Term needs based upon severity and potential  impact to the  longevity of the dock system as a whole. 

Immediate/Life‐Safety(Year0)ATM  recommends  the  following  immediate maintenance  and  repair  actions  at  the  subject marina: 

Replace heavily  corroded hardware along  the outside of Dock  “T” with  stainless  steel materials.   This  is critical as  the  framing  through bolts are substantially eroded.   Since this  dock  also  houses  fueling  infrastructure  and  serves  as  a  berthing  area  for  larger yachts, the structural integrity of the dock is vital. 

 

The  screws protruding above  the deck  surface  in  isolated  locations  represent a minor tripping hazard.   While  this  is not considered  to be a major  threat  to  life or  safety of marina patrons and/or staff, ATM recommends that marina staff tighten and/or replace the  screws  in  these  isolated  locations  to ensure  that  the condition doesn’t worsen or spread to create a more substantial hazard. 

ShortTerm(Years1‐5)ATM  recommends  the  following short‐term maintenance and  repair work  to help extend  the useful life of the floating dock system: 

Repair damaged dock section at main gangway.  This serves as the main point of access for the marina and could develop into a critical concern if left unchecked. 

Brace handrail on fixed deck to ensure appropriate rigidity/safety in this area. 

Repair dock listing. 

Replace cracked piles ‐ Based upon our observations, ATM suggests a total of seven (7) piles are cracking significantly and require replacement.   

Repair damaged pile guides. 

Scrape shellfish from piling to ensure free floating docks. 

Repair/monitor plumbing leaks. 

Monitor dock freeboard regularly. 

Intermediate/LongTerm(Years5‐10+)After the immediate and short‐term repairs recommended above are completed, ATM suggests that the marina systems be maintained diligently to maximize their useful life.   

RemainingUsefulLifeIt is noted that the typical design life for a timber frame floating dock in a marine environment is  on  the  order  of  25‐years.    Concrete  anchor  piling  typically  perform  for  a  period  of  30‐35 

Page 25: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 23 

   

years.   While  selected  elements  of  the  docks  have  been  replaced  recently  (2006‐2007),  the anchor  piling,  timber  framing,  and  flotation  are  ~22  years  old.    Implementing  the  repairs suggested above will help extend the useful life of the marina, but not indefinitely.  From  a  capital  replacement  standpoint  the  age  of  the  various marine  components  at  the subject  facility  creates  a  challenge with  regard  to  offering  recommendations  for  large‐scale facility replacement.  Further, the marina is generally in good condition and is well‐maintained.    Despite  the  condition  of  the  marina,  infrastructure  investment  in  2006‐2006,  ongoing maintenance  by  marina  staff,  implementation  of  suggested  repairs/maintenance  described herein,  key elements of  the marina  are becoming  aged.    In particular  the dock  framing  and anchor piling are reaching the end of their useful  lives.    In ATM’s experience  it  is unusual  for such elements to be serviceable beyond ~35 years and since these form the foundation of the marina facility, we suggest that full dock replacement be considered when the docks and pilings reach this age (~13 years).  Though other marina elements may be newer and  serviceable  (utilities, decking, etc.),  these may be salvaged and re‐used or sold to the extent practical.   ATM has estimated the remaining useful life for each of the key marina components.  These are outlined below: 

Pontoons:    5 to 15 years  

Framing:    5 to 15 Years 

Decking:    15 to 20 years 

Piles:      5 to 15 years 

Utilities:    15 to 20 years 

Fixed Access Pier  15 to 25 years *    The useful  life of the framing system assumes that the hardware on the outer side of Dock 

“T” is replaced within the next several years. 

ApplicationBased  upon  the  anticipated  remaining  useful  lives  of  the  independent  components  outlined above, we anticipate that the anchor piling and timber framing are likely be the components to reach  the end of  their useful  life  first.   As such,  these components are expected  to drive  the timeline for eventual wholesale replacement of the dock system.    We anticipate  that with proper diligence and attention, and without exposure  to any outside anomalies  such as  significant  storm events,  the existing dock  system may  remain  sufficiently functional for up to fifteen (15) years.   As such, we will use this as the basis for the following reserve  fund  analysis  and  assume  all  infrastructure  is  replaced  at  this  time.    As mentioned previously, should any elements of the marina remain in a condition suitable for salvage or re‐use at that time, the estimated cost of facility replacement may be mitigated.* 

Page 26: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 24 

   

 *Note:  ATM understands that utility cabling, pedestals, Ipe decking, etc. will be approximately 22 years old at the end of the above‐mentioned 15 year period.  Considering this, it is likely that these components may well have additional useful  life  remaining when  the docks and pilings are  replaced.   A  thorough  inspection  of  these  elements  and  careful  consideration  regarding salvage value or placement of older infrastructure on a new dock system should be included in dock replacement planning exercises.    Though ATM has worked on a few dock replacement projects where selected  infrastructure  is re‐used,  it  is  exceptionally  difficult  to  accurately  estimate  the  value  of  key  materials.    A conservative  placeholder  for  salvage  value  of  key marina  elements  will  be  included  in  the reserve fund analysis for HOA consideration.       

Page 27: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 25 

   

 

RESERVEFUNDANALYSIS

Utilizing the  information presented above, ATM has developed a reserve  fund analysis that  is intended to assist the HOA in their capital budgeting efforts for major marina maintenance and infrastructure  replacement.    The  attached  spreadsheets  depict  the  analysis  in  detail.    The following  discussion  is  intended  to  provide  additional  insight  related  to  the  genesis  of  the spreadsheet data.  

ConceptualCapitalCostEstimateThe  Conceptual  Capital  Cost  Estimate  presents  an  estimated  cost  for  recommended maintenance/repair and capital replacement projects that have been  identified  in the Marina Condition Assessment.  These are separated into discrete line items and have been assigned a year of execution based on estimated remaining useful life/need.  Line  item  costs have been developed  through ATM’s  experience  in  the  industry  though  it  is noted  some of  the  repair  costs are more difficult  to estimate  (based on nature and  scale of projects).  We have established preliminary estimates for these repair costs that can be vetted further in the future as capital budgets are finalized.  It is noted that a salvage value has been included with the floating dock replacement estimate.  As discussed, the Ipe decking and marina utilities (electrical cabling, pedestals, etc.) will be 22 years of age at the time of suggested replacement.  These elements will have some remaining useful  life and, depending on condition at the time of marina replacement, may be  inspected and  re‐used  if appropriate.    If not  suitable  for  re‐use  in  the marina,  there  should be  salvage value to the Ipe and copper wire.    

CapitalProjectSummaryThe  Capital  Project  Summary  presents  the  estimated  cost  for  each  identified repair/maintenance/replacement  project  and  also  projects  the  future  value  of  these  costs based on an assumed CPI boost.  We used a 3%  factor  for CPI/inflation.   This may be slightly conservative, but  is based on our experience with similar projects.   The most recent CPI data  from the US Bureau of Labor and Statistics indicated a 1% increase in CPI from October 2012‐October 2013.  

FundingRequirementSummaryThis schedule provides a summary of annual sinking fund requirements necessary to fully fund all identified projects.  Individual sinking fund requirements are presented for each project as is a summary of the years sinking fund payments must be made. 

Page 28: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 26 

   

AnnualSinkingFundRequirementSummaryThis  schedule  simply  combines  the  required  sinking  fund  contributions  to  depict  an  annual contribution requirement necessary to fund all projects identified.  It is noted that this summary does not include a sinking fund contribution for the replacement of  the marina  beyond  the  suggested  replacement  of  the  current marina  in  Year  15.    It  is suggested that the HOA develop a funding plan for the replacement of the new marina once it is developed.   Assuming a 25‐year useful  life  for a  timber  frame  floating dock and projecting capital  costs  out  using  the  aforementioned  3% CPI  boost,  an  annual  contribution  of  ~$441k from years 16‐40 would be necessary to fund the next marina replacement (year 40). 

AmortizationTablesAmortization tables are presented for each sinking fund.  

Year  0  requirements  –  Assume  funding  necessary  at  beginning  of  year  to  fund improvements; no interest earned.  

Year 1  requirements – Assume payment  at  the beginning of each  year  (0  and 1), 5% interest on the first year’s payment, and commitment of funds at the beginning of year 1 for the necessary works. 

 

Year 15 requirements – Assume payment at the beginning of each year.  Interest earned on each year’s payment save for year 15 when funds are committed for construction. 

 

Year 20 requirements – Assume payment at the beginning of each year.  Interest earned on each year’s payment save for year 20 when funds are committed for construction. 

   This  analysis  is  intended  to  provide  a  general  guide  to  the  HOA  only.    Construction  costs presented herein may vary and some “projects” may be conducted by marina staff under basic maintenance and repair budgets.  This analysis also does not include any existing funds that the HOA  may  currently  have  on  hand  for  capital  projects.    The  recommendations  and  costs presented herein are consistent with ATM’s experience in the marina industry and should serve to provide the HOA with general guidance with regard to the establishment and/or funding of their capital replacement account.   

Page 29: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

  

  Page 27 

   

ReserveFundSpreadsheets 

Page 30: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

Ashley Marina Homeowner's AssociationConceptual Capital Cost Estimate

Nov‐13

Project Description Qty Unit Unit Cost Total CostYear of 

ExecutionComments

Immediate/Life Safety1 Replace Framing Hardware 1 ls $7,500   $                    7,500  0 Allowance, SS hardware

Tighten protruding deck screws 1  ‐  0 Assume performed by dock staff

Total Immediate/Life Safety  $                    7,500  Assume commit project funds at beginning of year

Short Term (Years 1 ‐ 5)2 Repair damaged section of dock at main gangway 1 ls $25,000   $                  25,000  1 Allowance, includes mobilization and repairs

3 Brace handrail on fixed pier & deck 1 ls $1,500   $                    1,500  1 Allowance

4 Replace cracked piles 1 ls $50,000   $                  50,000  1 Allowance, includes mobilization, pile extraction, and new pile driving

Scrape Piling ‐ ‐ ‐  ‐  1 Assume performed by dock staff

5 Repair Pile Guides 1 ls $1,000   $                    1,000  1

6 Repair Dock Listing 1 ls $7,500   $                    7,500  1 Assume done in tandem with project 2

Total Short Term  $                  76,500  Assume commit project funds at beginning of year

Intermediate/Long Term (Replacement)Floating Docks 

7 Mobilization 1 ls $50,000  $50,000 

Contractor Bonding/Insurance 1 ls $100,000  $100,000 

Demolition 1 ls $150,000  $150,000 

Floating Docks (including piling) 43,000 sf $65  $2,795,000 

Outer Atttenuator (Dock "T", including piling) 13,500 sf $100  $1,350,000 

Marina Utilities, including: 250 slips $7,500  $1,875,000  Assume 250 slips, Incl. Side Tie

Electrical Cabling ‐ ‐  ‐   ‐ 

Utility Pedestals ‐ ‐  ‐   ‐ 

Potable Water System ‐ ‐  ‐   ‐ 

Marine Pumpout 1 ls $15,000  $15,000  Assume 75% funded by USFWS grant

Fire Standpipe 1 ls $250,000  $250,000  Current fire regs in CHS will call for standpipe in a redev. marina

Fire Cabinets 20 ea $1,200  $24,000 

Aluminum Gangways 1 ea $5,000  $5,000  Assume re‐use, re‐furbishment of existing gangways

Floating Docks Construction Sub‐total  $            6,614,000 

Permitting 0.5%% of 

Construction ‐  $33,070 

Engineering 2.0%% of 

Construction$132,280 

Construction Administration 2.0%% of 

Construction$132,280 

Floating Dock Replacement Total  $            6,911,630 

Salvage Value of Existing Materials 1 LS $350,000  ($350,000) Assume salvage electrical cables, Ipe, and electrical pedestals

Total Cost to HOA  $            6,561,630  15 Assume commit project funds at beginning of year

Fixed Pier & Deck8 Mobilization 1 ls $15,000  $15,000 

Contractor Bonding/Insurance 1 ls  $15,000  $15,000 

Demolition 1 ls $20,000  $20,000 

Fixed Pier & Deck 2,775 sf $75  $208,125 

Reconnect Utilities 1 ls $10,000  $10,000 

Fixed Pier & Deck Construction Sub‐total  $                268,125 

Permitting 1.0%% of 

Construction ‐  $2,681  Assume permit extension from floating dock project

Engineering 4.0%% of 

Construction$10,725 

Construction Administration 4.0%% of 

Construction$10,725 

Fixed Pier and Deck Replacement Total  $                292,256  20 Assume commit project funds at beginning of year

Ashley Marina Homeowner's Association Reserve Fund Analysis ‐ Nov. 2013

Page 31: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

Ashley Marina Homeowner's AssociationCapital Project Summary

Nov‐13

Project Number Description Year 2013 Estimated Cost Future Value at Year of Replacement

1 Replace Framing Hardware 0 $7,500 $7,500

2 Repair Damaged Dock at Gangway 1 $25,000 $25,750

3 Repair Pile Guides 1 $1,000 $1,030

4 Repair Dock Listing 1 $7,500 $7,725

5 Brace Handrail on Fixed Dock 1 $1,500 $1,545

6 Replace Cracked Piling 1 $50,000 $51,500

7 Replace Floating Dock System and Utilities 15 $6,561,630 $10,222,806

8 Fixed Pier and Deck Replacement 20 $292,256 $527,847

Assumed CPI Boost 3%

Ashley Marina Homeowner's Association Reserve Fund Analysis ‐ Nov. 2013

Page 32: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

Ashley Marina Homeowner's AssociationFunding Requirement Summary

Nov‐13

Project Number Description Year Future Value Annual Sinking Fund Requirement Years Payment Required

1 Replace Framing Hardware 0 $7,500 $7,500 0

2 Repair Damaged Dock at Gangway 1 $25,750 $12,561 0‐1

3 Repair Pile Guides 1 $1,030 $502 0‐1

4 Repair Dock Listing 1 $7,725 $3,768 0‐1

5 Brace Handrail on Fixed Dock 1 $1,545 $754 0‐1

6 Replace Cracked Piling 1 $51,500 $25,122 0‐1

7 Replace Floating Dock System and Utilities 15 $10,222,806 $432,117 0‐15

8 Fixed Pier and Deck Replacement 20 $527,847 $14,778 0‐20

Assumed Interest Rate 5%

Ashley Marina Homeowner's Association Reserve Fund Analysis ‐ Nov. 2013

Page 33: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

Ashley Marina Homeowner's AssociationAnnual Sinking Fund Requirement Summary

Nov‐13

Year Required Sinking Fund Contribution 

0 $497,102

1 $489,602

2 $446,895

3 $446,895

4 $446,895

5 $446,895

6 $446,895

7 $446,895

8 $446,895

9 $446,895

10 $446,895

11 $446,895

12 $446,895

13 $446,895

14 $446,895

15 $446,895 Sinking Fund for Replacement of New Marina in Yr. 4016 $14,778 $441,097

17 $14,778 $441,097

18 $14,778 $441,097

19 $14,778 $441,097

20 $14,778 $441,097

Ashley Marina Homeowner's Association Reserve Fund Analysis ‐ Nov. 2013

Page 34: M CONDITION ASSESSMENT RESERVE F ANALYSISThe section of floating dock underneath the main gangway is noticeably damaged. At lower tide levels, the end of the dock is higher than the

Ashley Marina Homeowner's AssociationAmortization Tables

Nov‐13

Year Interest Rate Contributions/Payments Cash Flow Out for Projects EOY Balance, Incl. Interest

Year 0 Requirements 0 5% $7,500 $7,500 $0

Replace Framing Hardware

Year 1 Requirements 0 5% $42,707 $0 $44,843

Repair Damaged Dock at Gangway 1 $42,707 $87,550 $0

Brace Handrail on Fixed Dock

Replace Cracked Piling

Repair Pile Guides

Repair Listing

Year 15 Requirements 0 5% $432,117 $0 $453,723

Replace Floating Dock System and Utilities 1 $432,117 $0 $930,132

2 $432,117 $0 $1,430,361

3 $432,117 $0 $1,955,602

4 $432,117 $0 $2,507,105

5 $432,117 $0 $3,086,184

6 $432,117 $0 $3,694,216

7 $432,117 $0 $4,332,649

8 $432,117 $0 $5,003,005

9 $432,117 $0 $5,706,878

10 $432,117 $0 $6,445,945

11 $432,117 $0 $7,221,965

12 $432,117 $0 $8,036,786

13 $432,117 $0 $8,892,348

14 $432,117 $0 $9,790,689

15 $432,117 $10,222,806 $0

Year 20 Requirements 0 5% $14,778 $0 $15,517

Fixed Pier and Deck Replacement 1 $14,778 $0 $31,809

2 $14,778 $0 $48,916

3 $14,778 $0 $66,878

4 $14,778 $0 $85,739

5 $14,778 $0 $105,542

6 $14,778 $0 $126,336

7 $14,778 $0 $148,169

8 $14,778 $0 $171,094

9 $14,778 $0 $195,166

10 $14,778 $0 $220,440

11 $14,778 $0 $246,979

12 $14,778 $0 $274,844

13 $14,778 $0 $304,103

14 $14,778 $0 $334,825

15 $14,778 $0 $367,083

16 $14,778 $0 $400,953

17 $14,778 $0 $436,518

18 $14,778 $0 $473,860

19 $14,778 $0 $513,070

20 $14,778 $527,847 $0

Ashley Marina Homeowner's Association Reserve Fund Analysis ‐ Nov. 2013