MacLeod Public School Revitalization February 2012

MacLeod Public School Revitalization

Embed Size (px)

DESCRIPTION

MacLeod Public School Revitalization. February 2012. MacLeod Public School. Agenda. Process Existing Site Plans Site Layout Plans Temporary Accommodation Timelines Questions. Existing Site Plan. Aerial View of Existing Site. Current Statistics for MacLeod Public School. - PowerPoint PPT Presentation

Citation preview

Page 1: MacLeod Public School Revitalization

MacLeod Public School Revitalization

February 2012

Page 2: MacLeod Public School Revitalization

MacLeod Public School

Page 3: MacLeod Public School Revitalization

• Process

• Existing Site Plans

• Site Layout Plans

• Temporary Accommodation

• Timelines

• Questions

Agenda

Page 4: MacLeod Public School Revitalization

Existing Site Plan

Page 5: MacLeod Public School Revitalization

Aerial View of Existing Site

Page 6: MacLeod Public School Revitalization

Current Statistics for MacLeod Public School

• Enrolment at October 31, 2011 –

563 students, JK to 8

• Number of staff - 43, plus 4 daycare staff

Page 7: MacLeod Public School Revitalization

• Annex, Main Building and modulars are a total of 47,878 square feet

• Approximately 50 parking spaces

• Play area is 115,100 square feet

• No separate bus layby or loading zone

Current Statistics for MacLeod Public School (con’t)

Page 8: MacLeod Public School Revitalization

• Dedicated daycare space consists of one classroom (16 toddlers)

• The Before and After daycare program operates out of shared space with the school

• The Hub is operating after hours in shared space with the school and the Hub office is located at Lockerby Composite School

Current Statistics for MacLeod Public School (con’t)

Page 9: MacLeod Public School Revitalization

New Green School

Page 10: MacLeod Public School Revitalization

New Green School (con’t)

• Anticipated completion date of fall 2013

• Build a school for 600 pupil places

• Approximately 69,000 square feet

Page 11: MacLeod Public School Revitalization

• Full daycare with a mix of infants, toddlers and preschoolers for a total of 49 children

• The Hub office will be relocated from Lockerby Composite School to the New Green School

• Designed to allow for future expansion

New Green School (con’t)

Page 12: MacLeod Public School Revitalization

• 93 parking spaces

• Play area approximately 173,900 square feet

• The main entrance to the school will be off Walford Road with a separate bus layby off Laval Street and exiting off Walford Road

New Green School (con’t)

Page 13: MacLeod Public School Revitalization

Green Features

• Geo-Thermal Heating and Cooling System

• Displacement Ventilation and Heat Recovery System

• Radiant floor heating

Page 14: MacLeod Public School Revitalization

• High insulation values in windows, walls

and floors

• Energy efficient plumbing and lighting

fixtures

• The roof will be constructed to allow for the installation of solar panels at a later date

Green Features (con’t)

Page 15: MacLeod Public School Revitalization

Temporary Accommodation

JK to Grade 2 students as well as the daycare will remain at the Annex.

Grades 3 to 8 students will be relocated to the Wembley site as of Monday, March 19th until the completion of the project.

Page 16: MacLeod Public School Revitalization

Transportation

Regular bus routes will be maintained. In the morning, students will be dropped off at the Annex and the bus will then continue to the Wembley site.

In the afternoon, students will be picked up at the Wembley site, then proceed to the Annex.

Page 17: MacLeod Public School Revitalization

Bell Times for MacLeod, Grade 3 to 5

Grades 3, 4, 5

Entry Bell 8:35

Block1 8:40-10:40 am

Break 10:40-10:55 am (15 minutes)

Block2 10:55-11:55 am

Break 11:55-12:35 pm (40 minutes)

Block 3 12:35-2:35 pmExit Bell 2:35 pm

Page 18: MacLeod Public School Revitalization

Bell Times for MacLeod, Grade 6 to 8

Grades 6, 7, 8

Entry Bell 8:35

Block1 8:40-10:40 am

Break 10:40-10:55 am (15 minutes)

Block2 10:55-12:35 pm

Break 12:35-1:15 pm (40 minutes)

Block 3 1:15-2:35 pm

Exit Bell 2:35 pm

Page 19: MacLeod Public School Revitalization

TimelinesFriday, February 17, 2012

• Letters will be sent to parents/guardians for students who are impacted

Monday, February 27, 2012

• Community Information Night, 6 pm to 7 pm

Friday, March 2, 2012

• Contents of the Main Building to be packed

Week of March 3 to 9, 2012

• Moving the contents of the Main Building to the MacLeod, Wembley site

Friday, March 9, 2012

• Main Building staff unpack and set up classrooms at the MacLeod, Wembley Site for Grades 3 to 8