Magnetic Mitigation - Contents
Magnetic Mitigation General West Wall Compressors Rack Room 2 (north wall alternative) Magnetic Shielding Yoke
Jason Tarrant – Integration Engineering
Magnetic Mitigation - General Parallel approach
Baseline [UK led] Remove / Shield Equipment in
Areas of High Risk (compressor move, external rack room & local shielding)
Parallel option [US led] Single ‘yoke’ solution Requires some UK resource
K Marinov
H Witte
P Smith
Magnetic Mitigation - General Validation of Analysis
AFC Filed Mapping in R9 Opera Modelling Compare Measurements & Modelling
Including penetration of field into cabinets
I Taylor, C Pidcott, M George
West Wall Compressor Move Why
Compressor location under south mezzanine in high magnetic field
Length limit of ~30m on He hoses (compressor to cold heads) so unable to place outside MICE Hall
West wall relatively uncluttered + opportunity to build mezzanine platform
V Bayliss
Requirements ~30m hose lengths Platform to support compressors, personnel etc. Safe personnel access Compressor handling & installation Equipment delivery & assembly space for MICE
experimental devices
Existing West Wall
Existing high power cable to
be moved
4
PPS system trunking
West wall mezzanine will be at this level
between the existing services
Services to be moved or bridged by the west mezzanine
Platform, Compressor & Services
West Wall Mezzanine
Perforated flooring for thermal management
< 30m Hoses
19 Compressors for Step IV + 12 for Steps V & VI in stands
Air-conMove
Cable trays for compressor hoses & power cables from ground floor compressors
Cable trays for compressor hoses & power cables from
first floor compressors
Hose and cable tidy along south
mezzanine corridor
ControlRack
West Wall Compressor Move What (Completion Date)
Distribution board move (March 2013) Design, structural engineering and approval (May 2013) South west air-con & supply services (June 2013) Auxiliary equipment crane move (June 2013) Mezzanine platform build on west wall of MICE Hall (Sep 2013) Water services, including water plant relocation (Sep 2013) Services installation & management (Jan 2014) Some related infrastructure changes(Jan 2014)
• Lighting• PPS• Power cables
Compressor stands with integrated power (Feb 2014) Compressor & services installation (April 2014)
West Wall Compressor Move When
Ready for Running April 2014
RR2 Why
Same magnetic field problem as compressors but longer services length, therefore move out of Hall to new Rack Room 2 (RR2)
Allows operational changes without breaking PPS or disrupting running
Requirements Capacity in RR2 to eventually house all racks for Step VI Minimal change to building (cost related + will be returned to
ISIS) Fire safe, including services runs Safe access to racks Manage climate: Thermally for RR2
RR2 & MLCR Reconfiguration
Existing Rack Room
New Rack Room RR2
MLCR
Cables Routed Under Stairwell & False Floor
Luke Fry / February 2013
RR2 What (Completion Date)
Asbestos removal work (May 2013) Design, structural engineering & approval (July 2013) Cable ways through walls and cable management (Aug 2013) Building (doors, apertures, walls) (Nov 2013) Air management & temperature control (Jan 2014) Install services, power distribution & electrical (Jan 2014) False Flooring (rack room and main walkway) & cable trays
(March 2014) Rack installation (May 2014)
RR2 When
Ready for Running 09th May 2014
Magnetic Shielding Yoke Why
Apart from compressors & racks above many other components and systems in proximity of Step IV MICE experimental devices that could malfunction in the level of magnetic field that will be produced.
Requirements Magnetic shielding yoke that sufficiently lowers the level
of the magnetic field to enable safe operation of the experimental devices and the infrastructure of the MICE Hall, as well as protecting the ISIS control room.
Compatible with the MICE Hall environment, MICE experimental devices, services, maintenance etc.
Magnetic Shielding Yoke
Integrated with Step IV
Devices
Brookhaven Yoke Design
Integrated into the
MICE Hall
Magnetic Shielding Yoke Design Iteration
Fit with Experimental Devices
Fit with Hall Flooring & Trench
Fit with South Mezz Platform & Tracker Cryo
Fit with Detectors
Fit with Services
Modifications required to
current yoke design and the
MICE Hall
Magnetic Shielding Yoke What (UK)
Change front of south mezzanine to fit around yoke Reconfigure & extend on-device services connections, thus
compatible with reduced access when yoke installed Reconfigure cold head hoses & power, vacuum lines and magnet
cables & their management to fit with yoke Move Tracker Cryo & extend waveguides if necessary (waveguide
= US purchase) Move hydrogen filling station (either yoke or tracker shield) Provide modifications for lower yoke columns into trench and floor
on north side, requires significant modifications to false flooring and trench roof
What (US) Supply Step IV yoke Min 1x installation representative
Magnetic Shielding Yoke When
Parallel path until baseline shielding shown to be inadequate.
Decision point identified 30Sep13: External review of baseline and yoke option Would allow fabrication of yoke parts to start in US
FY 14
--- Extra Slides
Delivery, Assembly & Handling
Small equipment
crane
SS in lifting position with tandem lifting frame
Floor plan showing legs of platform and room for delivery and assembly area of
the MICE experimental devices
Step V & VI stairway change (TBC)