Upload
others
View
35
Download
0
Embed Size (px)
Citation preview
e-Tender Specification
B1 Tender (PERCENTAGE RATE)
Construction of Building and infrastructure facilities for
Punyashlok Ahilyadevi Holkar Government Agriculture
College, At – Halgaon, Tal – Jamkhed, Dist- Ahmednagar..
FOR
MAHATMA PHULE KRISHI VIDYAPEETH,
RAHURI-413 722, DIST-AHMEDNAGAR
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
I N D E X
SR. NO. C O N T E N T S PAGE NO.
1. Brief Tender Notice 2. Detailed Tender Notice
Post Qualification Criteria for the Contractor 3. General Description and Scope of Work 4. Printed B-1 Agreement Form 5. Tender for Works 6. Schedule ‘A’ 7. Conditions of Schedule ‘A’ 8. Price Variation Clause
A) Conditions and Additional General Specifications
10. B) Special Condition During Work till completion of Work C) Additional Special Conditions Bituminous works. Detail item wise Specifications.
11. Manner of Submission of Tender an accompaniments for Electrical work.
12. Summary 13. Schedule ‘B’ for Civil & Electrical Works 14. Drawing
1 to 2
3 to 5
5-40
40-44
45-68
68-72
73
74-78
79-85
86
Mahatma Phule Krishi Vidyapeeth, Rahuri
MAHATMA PHULE KRISHI VIDYAPEETH, RAHURI-413 722,
DIST-AHMEDNAGAR Office of the University Engineer
Phone (02426) 243 272, 243235 (Office), 243601 (fax),
No. MPKV/WRK/TC/397/of 2017, Dated : 04/05/2017
e-TENDER NOTICE No-1
The University Engineer invites online e- tenders in B-1 form from the reputed contractors in
appropriate class registered in state PWD/Central PWD/Military Engineering services and Railway
Department for the works of construction of Building and infrastructure Facilities for Punyashlok
Ahilyadevi Holkar Government Agriculture College at Halgaon, Tal –Jamkhed , Dist- Ahmednagar.
Sr.
No
Name of work Approximate
Estimated cost.
(Rs.Lakh)
Earnest
money
Deposit
(Rs.)
Total
SECURITY
DEPOSIT (5%)
(50 % cash + 50
% through bills)
Completion
period
Cost of
blank
tender
form
(Rs.)
Class of
Registration
1 Construction of Building
and infrastructure facilities
for Punyashlok Ahilyadevi
Holkar Government
Agriculture College, At –
Halgaon, Tal – Jamkhed,
Dist- Ahmednagar.
2641.36
2641370.00 1,32,06,850.00 24 Calendar
Months.
25,000/- Class 1-A
Time Table for e-Tendering
Sr. No Mahatma PhuleKrishi
Vidyapeeth Stage
Contractor stage From Date & Time Date & Time up to Envelope /
Remark
1 To publish e-tender --- 05/05/2017 from
10.00 Hrs.
05/05/2017 up to
15.00 Hrs.
---
2. --- Downloading e-
tenders
08/05/2017 from
10.00 Hrs.
01/06/2017 up to
17.15 Hrs.
Technical and
commercial
envelope
3. --- Preparation of e-
tenders
08/05/2017 from
15.01 Hrs.
03/06/2017 up to
17.15 Hrs.
As above
4. To close sale of online
e-tenders
--- 03/06/2017 from
17.16 Hrs.
05/06/2017 up to 17.15
Hrs.
As above
5. --- Submission of e-
tenders
05/06/2017 from
17.16 Hrs.
08/06/2017 up to 22.00
Hrs.
As above
6. Opening of Technical
envelope
--- 09/06/2017 from
10.00 Hrs.
09/06/2017 up to 17.15
Hrs.
Technical
envelope
7. Opening of
commercial envelope
--- 12/06/2017 from
10.00 Hrs.
12/06/2017 up to 17.15
Hrs.
commercial
envelope
8. Pre Bid meeting 19/05/2017 from 15:30
Hrs.
1.The interested and qualified contractors shall download e-tenders and to participate e-tendering procedure, by using
website Portal https//maharashtra.etenders.in. / Sub portal :ADF / Location: Mahatma Phule Krishi Vidyapeeth, Rahuri.
2. The interested contractors shall have enrollment with above website and have digital signature certificate. In this regard
if there is any quarries, they may contact telephone number of M/s. Sify Technologies Ltd. Nextender (India) Pvt. Ltd.,
Mumbai. On 020-25315555 / 25315556 (Pune),
3. The contractors will have to pay Rs. 1063.00 as a downloading charges of e-tenders for each work directly to the Sify
Technologies Ltd. Nextender (India) Pvt. Ltd., Mumbai. 4. The interested contractors will have to submit all required documents i.e copy of valid registration, PAN No & TIN No.
etc. with Earnest money Deposit, cost of blank tender form online. 5. The offer will be valid for 120 days from the date of opening of the tender 6. The other terms and condition are available in e-tender form available on above website. 7. The authority reserved the right to reject any all tenders So, received without assigning any reason and no explanation
can be demanded for the rejection of the offer by the person / firm making tender.
8. The office is not responsible for postal delay if any.
9. Price escalation will be given.
10. Presence of the contractor or his representative is essential for tender opening otherwise there tender will not be
considered.
11. As per G.R. C.A.T..2017 /¹ãÆ.‰ãŠ.8/ ƒ.½ãã.2 Dated :12/04/2017 the additional security deposit in form of D.D. in favor of Comptroller. MPKV, Rahuri. for below rate should be given.
12. The date of opening of commercial envelop is tentative and subject to change as per date and time finalized by
Hon’ble Vice Chancellor, MPKV, Rahuri.
13. Post Qualifying Criteria is applicable, Those contractors Qualified in the post qualification criteria there commercial
envelop will be opened. Commercial envelop of those contractors which are not qualified for post qualifying criteria will
be not open.
Sd/- University Engineer
MPKV, Rahuri.
NOT TO BE PUBLISHED –
Copy fwcs to : The Editor, Times of India, The India Express, Loksatta, Lokmat, Navbharat, Aaj ka Anand with a
request to publish the above tender notice in your newspaper in one insertion in minimum space. The bill of the same
may please be forwarded in TRIPLICATE in the name of the University Engineer, MPKV, Rahuri for payment.
Copy fwcs for information to : 1) The Dean, F/A MPKV, Rahuri 2) The Director of Extension Education, MPKV, Rahuri 3)
The Director of Research, MPKV, Rahuri 4) P.A. to Hon. Vice – Chancellor, MPKV, Rahuri 5) The Registrar, MPKV Rahuri. 6)
The Comptroller, MPKV Rahuri. 7) Nodal officer, Agril. College, Halgaon, MPKV, Rahuri 8) P.A.O./APAO MPKV Rahuri.
Copy for necessary action to: 1) Dy. University Engineer, MPKV, Rahuri. 2) Er. A. L. Gaikawad , Sectional Engg (Civil). MPKV, Rahuri
3) Er. M.D. Sonawane, Sectional Engineer (Ele.) MPKV, Rahuri 4) Cashier/ Superintendent 5) Tender Clerk 6) Drawing Branch
7) Notice Board of Works Branch, MPKV, Rahuri.
Copy for necessary action to: 1) The I/C Officer ARIS, MPKV, Rahuri. He is requested to publish to above tender notice on
MPKV website. 2) The Director of Communication, MPKV, Rahuri
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
DETAILED TENDER NOTICE TO CONTRACTORS
2. Cost of each Tender Form : Rs. 25,000.00
3. Estimated Cost of Work : Rs 26,41,36,858.00
4. Earnest Money Deposit 1% : Rs. 26,41,370.00
5. Initial Security Deposit 2.50% : Rs. 66,03,425.00
6. and further security : Rs. 66,03,425.00
Deposit to be deducted from bills 2.5 %
7. Last date and time upto : 03/06/2017 up to 17.15 hrs. Which blank tender forms
will be issued:
8. Pre-Bid Conference will be held on 19/05/2017 at 15:30 hours at Rahuri in the
office of the university Engineer.
9. Date and time of receipt : 03/06/2017 up to 15.00 hrs. Of Tender
10. Probable date and time : 12/06/2017 after 10.00 hrs, if possible,
of opening of commercial envelope tender.
11. Validity period : The Offer of the contractor shall remain valid For 120 days from the date of opening Envelope No.2
12. The tender notice shall form a part of the contract agreement. 13. The tenders are invited on the Departmental design only.
14. The tenderer is firm or company shall in their forwarding letter mention the
names of all the partners of the firm or the company (as the case may be ) and
the name of the partner who holds the power of attorney if any, authorizing him
to conduct transactions on behalf of the firm or company.
15. Right is reserved to revise or amend the contract documents full or part thereof
prior to the date notified or amended for the receipt of tender. Such deviations/
amendments if any shall be communicated in the form of corrigendum or by a
letter as may be considered suitable. 16. Right is reserved to reject any or all tenders without assigning any reason thereof.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 3 -
1. Name of work : Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon, Dist. Ahmednagar.
1.1 The University Engineer invites online e- tenders in B-1 form from the registred civil
contractors for the following works of Agriculture College Building & Infrastructure
Facilities, at Halgaon.
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
(2) EARNEST MONEY:
2.1 Earnest money of Rs. 26,41,370.00 along with the tender should be in the
shape of Online Payment mode, 2.2 Tender of those who do not deposit earnest money in one of the acceptable
forms shall be summarily rejected. 2.3 The amount of earnest money will be refunded to the unsuccessful tenderer on deciding
about the acceptance or otherwise of the tender or on expiry of the validity period
whichever is earlier. In case of the successful tenderer it will be refunded on his paying the
initial security deposit and completing the tender documents or will be transferred towards
a part of security deposit to be paid after awarding of the work. If successful tenderer does
not pay the security deposit in the prescribed time limit and complete the agreement bond,
his earnest money deposit will be forfeited to MPKV, Rahuri.
(3) TENDERING PROCEDURE:-
3.1 Issue of Bank tender forms :-
Blank tender forms available on website https://adf.maharashtra.etender.in 3.2 Pre Tender Conference : -
3.2.1 A pre -Bid Conference open to all prospective Tenderers will be held at Rahuri
on 19/05/2017 at 15:30 hours in the office of the University Engineer, MPKV,
Rahuri where in the prospective tenders will have an opportunity to obtain
clarifications regarding the work and the tender conditions. 3.2.2 The prospective tenderers are free to ask for any Additional information or
clarification either in writing or orally and the reply to the same will be given by
the University Engineer, M.P.K.V. in writing and this clarification referred to as
Common set of conditions shall form part of tender documents and which will
also be common and applicable to all tenders. 3.2.3 The tender submitted by tenderer shall be based on the clarification, Additional
facility issued {if University Engineer M.P.K.V, Rahuri any ) by the Department and
this tender shall be un conditional. Conditional tenders will be summarily rejected. 3.2.4 All tenders are cautioned that the tenders containing any deviation from the
contractual terms and conditions, specifications or other requirements and
conditional tenders will be rejected.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 4 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
3.3 Manner of submission of Tender and its accompaniments :-
Tender to be submitted in Online only.
Envelope No. 1 (Documents):- Technical Data. (Post Qualification Criteria Documents.)
The first envelope clearly marked as Envelope No.1 shall contain the following documents
1. The University Engineer invites online Post Qualification Documents for
prescribe work. Registered civil contractors in appropriate class registered
in state PWD/Central PWD/Military Engineering services and Railway
Department can apply for the above said work at Halgaon. Time table for
e-Tendering Post qualification procedure, by using website Portal
https//Maharashtra. e-tenders.in.
2. The interested contractors shall have enrollment with above website and
have digital signature certificate. In this regard if there is any quarries,
they may contact telephone number of M/s. Sify Technologies Ltd.
Nextender (India) Pvt. Ltd., Mumbai. On 02025315555 / 25315556 (Pune),
Mobile No. 8879656082.
3. The interested contractors will have to submit all required documents i.e
copy of valid registration, PAN No & TIN No. with Earnest money Deposit,
Three year balance sheet, Educational Building work experience certificate
etc. In the office of the University Engineer, MPKV, Rahuri. Before one day
of date for Technical opening the tender. Otherwise he shall not consider
for online Post qualification procedure. Blank Post-qualification forms are
directly downloaded from e-tender portal.
4. The other terms and condition are available in Post-qualification
documents.
5. The authority reserved the right to reject any or all PQ Documents
received without assigning any reason and no explanation will be given
for rejection of the offer by the person / firm making post qualification
documents. 5
6. The office is not responsible for postal delay if any.
7. Presence of the contractor or his representative is essential for Post-
qualification opening otherwise there documents will not be considered.
8. The date of opening of Post-qualification documents is tentative and
subject to change as per date and time finalized by Hon Vice Chancellor,
MPKV, Rahuri.
9. The Joint Venture is not allowed.
Post Qualification Criteria for the Contractor
1) The Contractor should have registered with PWD as a class 1 -A
Contractor. In addition to above, the Contractors should have a long &
good standing in the business. The desirous Contractor must produce
the firm’s resume and also the list of large scale works carried out in
last five years.
2) The desirous contractor must have executed a single similar type of
work of any institutional building for any Government/Semi
Government organization costing not less than Rs. 60 % of tender cost
Rs. 15.84 Crores cost (Similar type of work done means its area 11,000
sq.m. with execution of civil and electrical work)
3) The contractor should achieve an maximum annual turnover of more
than Rs.9.90 Crores for last Three Years. The contractors who can fulfill
this condition can only apply. They must produce the documentary
evidence to prove their ability in this regard with IT Clearance
certificate.
6
The desirous contractors must be well equipped with the required machinery
like JCB, Dumpers, adequate Centering & shuttering material with marine
plywood & steel plates , Concrete weigh batch mixers, Vibrators, Vacuum pads
for Tremix treatment and also with all the modern tools & plants required. The
Contractor must provide the list of Tools, Machinery, Plants which is going to be
engaged for construction at site till the Completion of the said activities.
T
The desirous contractor must have skilled Labours, experienced and well qualified supervisory staff and other administrative staff. The contractor must give the list of their key-personal and the name of the staff and their qualification with bio-data who will be engage permanently at the site till the completion of the work with PTR/PTR Certificate and its recent challen.
4) Bid Capacity of contractor should be more than project cost.
5) Should not have incurred any loss in more than three years during the last five
years ending 31st March 2017.
6) Solvency certificate of amount equivalent to 50% of the estimated cost should be
issued by nationalized bank/ scheduled bank and shall be valid for period of One
year. Solvency Certificate issued should not be earlier than 03 (Three) months
prior to date of bid submission.
7) Net cash accruals from operations for each of the last Three financial year shall be
at least Seven Crores INR positive as certified by Chartered Accountant.
8) No corporate debt restructuring in process and /or no unresolved debt
restructuring issues with the Banks/ Institutions as of 1 month before the
application due date. A Chartered Accountant Certificate in this regard shall be
furnished with the Application.
9) In possession of “No default certificate” from bankers in respect of Loans availed.
Bidder shall have at least 10 years’ experience in Institutional work.
Age of organization shall not be less than 10 Years.
10) Scan copy of a valid VAT registration certificate and latest VAT clearance
certificate for FY 2016-17 from Maharashtra State Sale Tax Department
11) Scan copy of Valid Professional Tax Registration certificate in form PT/R/ & PT/E
under section (I) & (II) of section 5 of Maharashtra State Tax on Profession, Trade,
Callings and employment Act,1975, rule 3(2) & 4 (4) from the Professional Tax
Officer of the concerned District in Maharashtra. The Professional tax clearance
certificate for FY 2016-17 and List of Employees duly attested by the Professional
tax officer shall be enclosed.
12) Certificate of Registration for Sales tax/VAT and acknowledgement of up to date
filed return if required.
13) Certificate of Registration for Service Tax and acknowledgement of up to date
filled Return
14) Limit of minimum reserve/Assets (Immovable And Movable)
(Affidavit to this effect shall be furnished along with valuation report from Govt.
approved valuer) Rs. 80.00 lakhs – 80% of minimum reserve shall be in the form
of immovable property.
Satisfactorily executed in any one year, out of last 3 years preceding 31st March 2017
the following minimum quantities of work:
Sr.
No
Item Quantity Unit
1 Reinforcement steel 600.00 Metric Tone
2 Brick Works 3000.00 Cubic Meter
3 Flooring/Dado 19000.00 Square Meter
4 Reinforced cement concrete works 3800.00 Cubic Meter
5 Plaster 42000.00 Square Meter
6 Painting 42000.00 Square Meter
7 Excavation 13000.00 Cubic Meter
8 Waterproofing 3800.00 Square Meter
9 Doors and Windows 2100.00 Square Meter
10 Tar road works Rs.120 lakhs
15) Plant & Machinery:
i) Fully Automatic Microprocessor based programmable logical control (PLC) with
SCADA Enabled Concrete Batch Mix Plant of minimum 30 cum/hr capacity
ii) Concrete Pumps with piping
iii) Mobile Tower Crane 50 M cap
iv) Transit Mixer- 03 Nos
v) Sand Screening cum Washing Unit electrically or diesel operated 4/6 Cubic Metre
per hour capacity.
vi) Fully Automatic Compression Testing Machine (CTM) for the testing cement mortar,
concrete at the site, linked with "SCADA" etc. 2000 Kn cap
vii) Excavator with Hyd. Breaker
viii) Vibratory Compactor/Walk Behind roller- 2 Nos
ix) Core Cutting Machine
x) Electrical generator 250 KVA – 1No
xi) Water tanker 10,000 liter capacity – 2 Nos.
xii) Tipper / Trucks – 4 Nos
xiii) Concrete conveying trolley – 3 Nos
xiv) Bar bending / cutting machine – 3 Nos
xv) Site inspection vehicle (Jeep/ car) – 2 Nos.
As per PWD Norm - Additional security Deposit for Plant & Machinery established or
installed at site within 15 Days of issue of work order
8
TECHNICAL PERSONS REQUIRED AS BELOW
1) Project Manager : 1 No. B.E. Civil or graduate in Civil
Engineering with 15 Yr experience
2) Sr. Engineer : 2 Nos. B.E. Civil or graduate in Civil
Engineering
with 10 Yr experience
3) Quality Engineer : 1 No B.E. Civil or graduate in Civil
Engineering
with 7 Yr. experience
4) Site Engineer : 2 No Diploma Civil Engineering
with 7 Yr. experience
5) Electrical Engineer : 1 No. B.E. Electrical with 7 Yrs Experience
6) Supervisor : 2 No. ITI Civil Draftsman or same
7) Clerk : 1 No. Graduate
F) The contractors who fulfill the above conditions, must produce their valid
PAN CARD, Statement of latest Income Tax returns, Balance sheet for last
three years, Maharashtra Value added Tax number, ESIC registration
certificate, PPF certificates, etc.
G) In addition to above the contractor must give the list of the works in hand
& their probable dates for completion.
H) The contractor may produce any other IMPORTANT documents,
certificates, excellence awards for outstanding works executed in near
past. 9
J) Affidavit on 100/- Bond paper regarding to correctness and true of
document
K) Financial Provision For this project details
L) Electrical Agreement with Class 1 Register subcontractor Agency
M) Electrical Contractor Turnover work done details
N) Division wise Payment Received in last 3 financial year statement
O) Statement Showing Bid Capacity of the Contractor
P) Pan Card, CA Certified Last three Year IT Return, VAT, SALE TAX
Certificates
9
16) As this Project includes all Civil & Electric works for Building, the Contractor
should produce documentary evidence of completion of electrical work costing not
less than Rs.2.0 Crores
17) Give details regarding Work Methodology, Quality Maintains, Testing & safety
measures & give detail work program with milestone in MS PROJECT Bar Chart & CPM
Chart
The contractor should submit the required information as per attached formats.
10
FORM No 1
List of Works tendered for and in hand as on the date of submission of this
tender
No. Name
of
Work
Place or
Country
Works in Hand Works tendered for
Tendered
Cost &
date of
work
order
Cost of
remaining
work
Anticipated
date of
Completion
Tendered
cost
Date
when
decision
is
expected
Stipulated
date of
period of
completion
Remarks
1 2 3 4 5 6 7 8 9 10
FORM No. II
List of plant and machinery immediately available with the Tender for the work.
Sr. Name of
Machinery
No of
Unit
Kind &
Make
Capacity Age &
Condition
Present
Location
Remark
1 2 3 4 5 6 7 8
FORM NO. III
Details of work of similar type and magnitude of the work carried by the
contractor.
Sr. No
Name of
Work
Cost of
work
Date of
starting
Stipulated
date of
completion
Actual date
of
completion
Remark
1 2 3 4 5 6 7
FORM NO. IV
Details of Technical Personnel available with Contractor
Name of the tenderer- ------------------------------
15
Sr. No.
Name of
Work
Qualification Whether
working in
field or in
office
Experience of
execution of
similar works
Period for
which the
person is
working with
the tenderer
Remarks
1 2 3 4 5 6 7
FINANCIAL STATEMENT
1. Capital
A) Authorized :
B) Issued and paid up :
2. A) Date of Incorporation of the firm :
B) Duration of existence of the firm :
3. Furnish Balance sheet and profit and Loss
statement with Auditor's report
For the last years, it should interlaid with
The following information.
1) Your working Capital :
2) Your turnover on Civil Engineering Works :
Amount of
Amount of turnover brought to
Year as
current Financial level (by
Turnover Multiplying
stated in multiplying amounts in Col. 2 by
Annexure-A during the year Factor factors given in Col. 3
(Rs. in Lakhs) (Rs. In Lakhs)
2014-15 1.2
2015-16 1.1
2016-17 1.0
16
III) YEARS GROSS INCOME (Rs. in Lakhs)
Sr.No. Year Gross Income
(Rs. In Lakhs)
1 Vth year
2 IVth year
3 IIIrd.year
4 IInd year
5 Ist year
4. Total liabilities
A) Current Ratio
1) Current Asset
2) Current liabilities
B) Total liabilities to net worth
5. Debt equity ratio (Defined as Debt / Equity)
6. What is the maximum value of the Project that you can handle?
7. Have your ever denied tendering Facilities by the Govt. Department,
Public sector undertaking (Give details)
8. What are your sources of finance? (Please give complete details, Bank
reference also)
9. Certificate of financial soundness from bankers of applicants.
10. Furnish the following information for last Five years (duly certified
by the Respective Banks)
A) Bank guarantee limit enjoyed by the Firm during each of the last five
year with
Bank wise breakup. 17
B) Portion of Bank guarantee already utilized as on date of application.
11. Overdraft limit enjoyed during each of The last five years with Bank
wise Breakup.
12. Name & Address of bankers from whom Reference can be obtained
13. Have you ever been declare bankrupt? If yes give details Certified
that above information true & correct to the best of my knowledge &
belief.
Date:
18
RESOURCES : PERSSONAL
1. Details of Board of Director:
A) Name of Directors:
B) Organization:
C) Address:
2. Details of Technical Key Persons Available with Company with documentary
evidence (PTE & PF recent Challan) as well as their designation and roll with
resume.
Certified that above information true & correct to the best of my knowledge & belief.
EQUIPMENT DETAILS
Details of plants and equipment by the applicant which shall be used for construction of work
Separate information for each type of equipment, supply colored photograph of the each machine which is costing more than Rs. 10 lakhs)
Certified that the above information is true & correct to the best of my knowledge & belief.
Signature of contractor
19
MACHINARY ESSENTAIL FOR THE WORK
Details of Additional Plants and Equipment’s which shall be Procured by the Applicant for this work in the Following Proforma.
Names of Output in
Type of Number of works on tonees of
Works in
which Location mix per
Machinery Unit hand.
deployed at
day or per
present hour
1 2 3 4 5 6
Certified that the above information is true & correct to the best of my knowledge & belief.
Signature of Contractor
20
STRUCTURE AND ORGANISATION
1) Name of Applicant:-
2) Nationality of Applicant:-
3) A) Registered office Address:-
Telegraphic Address
Telephone Address
Telex Number
Fax Number
B) Office address for Correspondence
4) A) Year established when where & legal name as formed individual/firm
B) Class of registration with Govt. Maharashtra
5) Whether the applicant
a) An Individual
b) A proprietary firm
c) A limited company or corporation
d) A member of group of companies (if yes give name, address,
connection and description of other companies)
e) A subsidiary of large organization (if yes give name address of the
organization) if the company is subsidiary what involvement if any will
be parent company have in the project
6) Attached the organization chart showing The structure of
the organization including the position Of the directors
7) What best describe you
a) Engineers and Contractors 21
b) Consulting Engineers and contractors
c) If other please specify
8) Number of years of experience
a) As a prime contractor
1) In own country
2) Internationally
9) How many years has your organization Been in business under your
present name? And What were your fields when your established
your Organization?
10) Where you required to suspend construction for A period of more
than six month continuously after You started? If so the reason there of
11) Have you ever failed to complete any work Awarded to you (if
so which where & why)?
12) In how many projects you asked for arbitration After rectification
(if so when where & why)
13) In how many projects you were imposed Penalties for delay?
14) Have any key personnel of partner of your Organization every failed
to complete the Constructions contract & laid in his own name
15) Have any key personnel of partner of your Organization every failed
to complete the Constructions contract & laid in his own name
16) In what fields do you claim specialization & are interested to work?
17) Give details of your experience in modern Concrete technology &
work for manufacture
18) & quality control.
19) Give details of your material testing laboratory & mobile
Laboratories 22
Certified that the above information is true & correct to the best of my knowledge & belief.
Signature of contractor
23
ADDITIONAL: INFORAMATION
1. Any further information
Which the Applicant considers relevant In regard to his capabilities
2 Please give brief note indicate
How the applicant considers himself
Eligible for prequalification for the work
Certified that the above information is true & correct to the best of my knowledge & belief.
Signature of contractor
24
Statement Showing Important Items Completed by the Contractor in any One Year of last three years.
Please Note down the Year :______________________
Total
Descriptio Minimu
Quantit
Sr. n of Wor Wor Wor Wor Wor & y of
m Remark
No important K k k k k Soo Each
quantity s
. items required No.1 No.2 No.3 No.4 No.5 n item at
completed Sr.No.1
to 7
1 2 3 4 5 6 7 8 9 10 11
Certified that the above information is true & correct to the best of my knowledge & belief.
Signature of contractor
25
Statement showing work done in all classes of Civil Engineering Construction works during last three year
Name of Tenderer
:_________________________________________________
Amount of work done
Amount
Of
during each of last
work still
Date of
three
remainin
Nam Name Cost
Award years (Rs. in lakhs)
Sr.
G
e of of Put to Agreeme of
Remar
No
to be
Work Divisio Tende nt no. Contrac k
. s n r
t if
executed
2012 2013 2014 2015-
award
-13 -14 -15 2016
(Rs. In
lakhs)
1 2 3 4 5 6 7 8 9 10 11
Certified that the above information is true & correct to the best of my knowledge & belief.
Signature of contractor
26
(On letter head of bank)
SAMPLE FORMAT FOR EVIDENCE OF ACCESS TO OR AVAILABILITY OF CREDIT
FACILITIES
This is to certify that M/s……………………………………………. is a reputed
company with a good financial standing.
If the contract for the work, namely …………………………… is awarded to the
above firm, we shall be able to provide overdraft/credit facilities to the extent
of Rs……………….. to meet their working capital requirements for the above
contract.
Sd/-
Name of Bank
Senior Bank Manager
Address of the bank
27
Time Limit
Time is essence of the project. The work must be completed in 24
calendar months in all respect from the date of issue of work order.
The Rights of the Employer.
The Employer and the Architect Reserve the right to issue the Tenders to
selected contractors or reject any or all the post-qualifications without
assigning any reason there off.
Submission of Post-qualification Form :-
All documents as mention is pack in Envelop sealed Data are submitted by
online only. The tenderer should ensure that their post qualification is received
by only on website of M.P.K.V., Rahuri before the expiry of the date and time.
No delays on account of any cause will be entertained for the late receipt after
the date and time is over will either not be accepted or if advertently accepted,
will not be opened. This office will not responsible for online delay.
Physically Submission :- All documents with Attestation must reach to the
office of The University Engineer, MPKV Rahuri, Dist Ahamadnagar on or
before 05/ 06/2017 up to 17:00 hrs. The documents reaching after this time
will not be accepted.
Opening of Post-qualification Documents :
On the date specified in the Post qualification documents following procedure
will be adopted for opening. Envelope of the Postqualification will be opened to
verify its contents as per requirements. If the various documents contained in
this envelope do not meet the requirements of the Departments a note will be
recorded accordingly by the opening authority.
28
Acceptance of Contractor
The acceptance of Post-qualification may be communicated to the contractor
telegraphically or by mail or otherwise either by the tender opening Authority or
any Authority in the Department including M.P.K.V.
The dates of issue and Submission of the guide lines.
The guide line to submission of Post-qualification of contractors will be issued
from Applications Forms are available at the www.maharashtra.etender.co.in
web site on 08/05/2017and submission.
The selected contractors will be notified and will be called for submission of the
Tender for the said work.
29
SUMMARY QUESTIONERY
General Information
Notes for completion:
Please answer every question. Failure to do so may result in your application
being disqualified. If the question does not apply to you please write N/A; if
you don’t know the answer please write N/K.
30
A) Company Profile
1 Name of Company : Establishment year :
2 Address of Head Office : Regional Office :
Telephone No: Telephone No:
E-mail address: E-mail address:
3 Parent company details, if any :
4 Tie up with Indian / Foreign partner?
5 Give details of the legal status of the company e.g. Partnership, Limited
Company etc.
6 Please provide a brief description of your business and indicate what
services are provided
7 Under Any appropriate Indian / European Construction Industry Schemes,
please list those that relate to Tax Certificates & / or Registration or state:
Copy Enclosed? If none, please give reason why:
8 Please provide evidence of insurance for,
Employers Liability Insurance :
Public Liability (Third Party) Insurance
:
Professional Indemnity Insurance :
9 PF/ESI Details:
10
11 Financial Performance -
If annual reports are unavailable then please provide the following
information :
Turnover :
Profit before tax :
Current Liabilities :
12 State the approximate number of contracts completed within the past three
years in each range:
a) Under Rs.50,000,000
b) Rs.50,000,000 to Rs.200,000,000
c) Rs.200,000,000 to Rs.500,000,000
d) Above Rs.500,000,000
13 Provide a copy of your Organisation Chart –
Copy Enclosed?
14 State the approximate number of employees on a regular basis :
Managerial –
Technical –
Safety –
Quality –
QS –
Admin –
HR -
15 What type of work, if any, do you sub-contract?
16 Do you have in-house design capabilities?
If yes, for which functions (please describe):
17 Please list any professional bodies the company or the staff are members of
or registered with & provide details of numbers of personnel registered as
Professional
18 How do you manage training such that your employees are competent and
have the skills and knowledge for their work?
Is your organisation accredited to any People development institutions? Yes
or No?
19 Details of Three major Projects in Hand:
1.
20 Details of Three major Projects completed:
21 In-house Infrastructure/Equipment/Machinery details:
22 A brief enlistment of Architects with whom your organization has worked:
23 A brief enlistment of Project Management Consultants with whom your
organization has worked:
24 List any arbitration cases/ legal disputes on Current/ previous projects -
Mention name of project, reason for dispute, party filing the suit and
current status):
B) SAFETY HEALTH & ENVIRONMENT (SHE/HSE/EOHS)
25 Provide a copy of your company Health and Safety policy under which you
manage safety at work.
Date of last revision:
26 Please provide details of your company’s health and safety management
Procedures
Details enclosed?
27 State the name of the person in your company who has responsibility for the
management of health and safety:
Name: Tel :
Title:
Give details of the (Health & Safety) experience and qualifications of this
person:
28 Please include details of health and safety training given to all staff
(including managers, supervisors and, if appropriate, designers) in the last
Year
Details enclosed?
29 Provide an example of a recent Risk Assessment and Method Statement
Information enclosed?
30 Please provide the total number of accidents (including non-reportable)
sustained by your employees and the total man-hours worked:-
Last year This year to date
Accidents
Man-hours
31 Please provide details of your accident/incident investigation procedures
Information enclosed?
32 Give details of any accidents/incidents reported by, or on behalf of, your
company to the Indian Health & Safety Executives during the last three
years.
Details enclosed?
33 Give details of any formal notices issued or legal proceedings taken against
your company by the HSE in the past three years?
Details enclosed?
34 Please provide details of how you assess the Health and Safety record and
competence of companies with whom you place contracts.
Details enclosed?
34
C) QUALITY
35 Do you have a Quality Policy:
Copy enclosed?
36 Do you have a Quality Management System (QMS):
If no, do you have plans to do so?
Who reviews the QMS and what is the frequency:
37 Are you certified to ISO 9001 or other quality assured accredited schemes:
Copy of certificate enclosed?
38 If not ISO certified
Do you plan, carry out & document internal quality audits/ inspections:
39 Do you have customer-related processes including communication that
include:
• Contract Review:
• Notification/agreement of changes that impact on the customer (e.g.
changes in organization, contract / order requirements, use of or change in
subcontractor):
• Customer feedback including complaints:
40 If not ISO certified
Do you have a procedure for correcting / preventing identified non-
compliances (audits, customer complaints etc) :
41 Do you have a procedure to select, assess and review suppliers capability to
meet your requirements :
Do you have an Approved Supplier List:
D) REFERENCES
42 Experience of Post Tension Concrete Construction- Yes/ No
Name the projects and its value in last 3 years.
Experience of working in and around Hilly/Tribal Area?
Name the projects and its value in last 5 years
43 Provide persons/organisations willing to provide a reference:
44 We hereby apply for inclusion on the register of Approved Contractors
Signed_________________________ Name :
Title Date:
a) Demand draft of earnest money deposit in the name of the comptroller, M.P.K.V.
Rahuri Certificate as a registered contractor with the Government of Maharashtra
as may be applicable. Earnest money exemption certificate is not accepted. b) The copy of Qualification letter issued by MPKV, Rahuri.
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon opening of the tender.
Envelope No.1 :
First of all, Envelope No.1 of the tender will be opened to verify its contents as
per requirements. If the various documents contained in this envelope do not
meet the requirements of the Departments a note will be recorded accordingly
by the tender opening authority and the said tenderer's Envelope No.2 will not
be considered for further action but the same will be recorded.
Envelope No.2 :-
This envelope shall be opened after opening of Envelope No.1, only if contents of
Envelope No.1 are found to be acceptable to the Departments, the tendered rates in
Schedule-B, of percentage above / below the Estimated rates shall then be read out.
Additional Security Deposit (D.D.) for below rate criteria should be attached in envelop
no 2.
3.6 Acceptance of tender
3.6.1 The acceptance of tender may be communicated to the contractor
telegraphically or otherwise either by the tender opening Authority or any
Authority in the Department including M.P.K.V. 3.6.2 The successful tenderer will be required to produce to the satisfaction of the
specified concerned authority, a valid and concurrent license issued in his
favour under provisions of the contract labour. (Regulations and Abolition ) Act
1970 before starting the work. On failure to do so, the acceptance of the tender
is liable to be withdrawn and earnest money forfeited. 3.6.3 The tenderer whose tender is accepted will have to give an undertaking in writing to the
effect the he /they will pay the labours engaged on the work, the wages as per Minimum
wages Act 1948 applied to the zone in which the work lies and act accordingly. 3.6.4 The contractor shall comply with the provision of the Payment of Wages Act 1936,
Minimum Wages Act 1948, Employees Liability Act 1938. Workmen's Compensation Act
1961, The Contract Labour (Regulation and Abolition) Act 1979 and any modification
thereof or any law relating thereto, and rules made there under from time to time.
3.6.5 The contractor whose tender is accepted is required to note that no foreign
exchange will be released by the Department. 3.6.6 The Contractor will have to sign the original copy of the tender papers and the
drawings according to which the work is to be carried out. The contractor shall
also have to give a declaration to the effect that he has fully studied the ,
plants, specification ; local conditions and availability of labour and materials
and that he has quoted his rates with the consideration to these factors.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri 37 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
3.7 Security Deposit :
3.7.1 The successful tender shall have to pay 50% security deposit in cash or in DD
in favour of Comptroller, M.P.K.V. Rahuri and complete the contract documents
failing which his earnest money will be forfeited to MPKV, Rahuri. The balance
50% security deposit will be recovered from the R.A. Bills . 3.7.2 All compensation or other sums payable by the contractor under the terms of this
contract or any other contract or on any account may be deducted from his Security
Deposit or from any sums which may be due to him or may become due to him by
government on any account and in the event of the Security being reduced by reason
of any such above noted deduction the contractor shall within ten days of receipt of
notice of demand from the Engineer in charge make good the deficit. 3.7.3 There shall be no liability on the Department to pay any interest on the
Security Deposit by or recover from the contractor. 3.7.4 The Security Deposit shall be refunded after completion of defect liability period
prescribed for this contract in accordance with the provisions in Clause - 1 & 20
of the contract
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri 38 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
DECLARATION OF THE CONTRACTORS
____________________ | /We hereby declare that I /We have made myself/ ourselves
thoroughly conversant with the Sub- soil conditions, the local conditions regarding all materials
( such as stone, murum sand etc.) and labour on which I/We have based my / our rates for this
work. The Specifications, conditions bore results and lead of materials on this work have been
carefully studied and understood by me / us before submitting this tender. I / We undertake to
use only the best materials approved by the University Engineer M.P.K.V. Rahuri or his duly
authorized assistant, before starting the work and to abide by his decision.
Sign. Of Contractor.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 39-
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
GENERAL DESCRIPTION AND SCOPE OF WORK.
1. Name of work : Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon, Dist. Ahmednagar.
2. Place of Work : Halgaon
3. Nearest Railway Station : Ahmednagar
4. Nearest Bus Station : Jamkhed
5. Nearest Airport Station : Pune
6. Details of Work : The all building work to be constructed is RCC framed structure
The Total built up area is mentioned in drawings & the quantity of various items to be constructed is as per schedule B & E. See Drawings
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 40 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
FORM B -1 PERCENTAGE RATE TENDER AND CONTRACT FOR WORKS
MAHATMA PHULE KRUSHI VIDYAPEETH, RAHURI - 413722, DIST. - A'NAGAR .
General Rules and Directions for the Guidance of contractors.
1. All works proposed to be executed by contract shall be notified in a form of invitation to
tender pasted on a board hung up in the office of the University Engineer.
This form will state the work to be carried out as well as the date for submitting and opening
tenders, & the time allowed for carrying out the work, also the amount of earnest money to
be deposited with the tender and the amount of security deposit to be deposited by the
successful tenderer, and percentage, if any, to be deducted from bills. It will also state
whether a refund of a quarry fees, royalties, dues and ground rents will be granted. Copies
of the specifications, designs and drawings, estimated rates, scheduled rates and any other
documents required in connection with the work shall be signed by the University Engineer
for the purpose of identification and shall also be open for inspection by contractors at the
office of the University Engineer during office hours.
Where the works are proposed to be executed according to the specifications
recommended by a contractor and approved by a competent authority on behalf of
the Governor of Maharashtra such specifications with designs and drawings shall
form part of the accepted tender. 2. In the event of the tender being submitted by a firm, it must be signed by each
partner thereof, and in the event of the absence of any partner, it shall be signed on
his behalf by a person holding a power of attorney authorizing him to do so.
2 (A)
i) The contractor shall pay along with the tender the sum of Rs 26,41,368.00 (Rupees
Twenty Six Lakh forty one thousand three hundred and sixty eight Only ) as and by
way of earnest money through online payment. The said amount of earnest money
shall not carry any interest what so ever. * Strike out which is not required. ii) In the event of his tender being accepted, subject to the provisions of sub clause (iii)
below, the said amount of earnest money shall be appropriated towards the amount of
security deposit payable by him under conditions of General Conditions of Contract. iii) If, after submitting the tender, the contractor withdraws his offer, modified the same or if after
the acceptance of his tender the contractor fails or neglects the furnish the balance of security
deposit without prejudice to any other rights and powers of the M.P.K.V. hereunder, or in law,
M.P.K.V. shall be entitled the forfeit the full amount of earnest money deposited
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 41 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
by him.
iv) In the event of his tender not being accepted, the amount of earnest money
deposited by the contractor, shall unless It is prior thereto forfeited under provisions
of sub-clause (iii) above, be refunded to him on his passing receipt therefore.
3. Receipts for payments made on account of any work, when executed by a firm should
also be signed by all the partners except where the contractors are describe in their tender
as a firm, in which case the receipt shall be signed in the name of the firm by one of the
partners, or any some other person having authority to give effectual receipt for the firm. 4. Any person who submit a tender shall fill the usual printed form stating at what percentage
above or below the rates specified in the Schedule 'B' ( memorandum showing items of work to be
carried out) he is willing to undertake the work. Only the rate or such percentage of al! Estimated
rated / Schedule rates shall be named. Tenders which' propose any alteration in the works specified
in the sad form of invitation to tender, or in the time allowed for carrying out the work, or which
contain any other conditions of any sort will be liable to rejection. No printed forms of tender shall
include a tender for more than one work but if contractors who wish to tender two or more works,
they shall submit a separate tender for each. Tender shall have the name and number of the work to
which they refer, written outside the envelope.
5. University Engineer or his duly authorized Assistant shall open tenders in the presence
of contractors who have submitted tenders or their representatives who may be present at the
time, and he will enter the amounts of several tenders in a comparative statement in a suitable
form. In the event of a tender being accepted, the contractor shall for the purpose of
identification, sign copies of the specification and other documents mentioned in Rule 1. In the
event of the tender being rejected, the competent officer shall authorize the Account Officer
concerned to refund the amount of the earnest money deposited to the contractor making the
tender, on his giving a receipt for the return of the money. 6. The officer competent to dispose of the tenders shall have the right of rejecting
all or any of the tenders. 7. No receipt for any payment alleged to have been made by a contractor in
regard to any matter relating to this tender or the contract shall be valid and binding on
M.P.K.V. unless it is signed by the University Engineer. 8. The memorandum of the work to be tendered for and the Schedule of
materials to be supplied by the M.P.K.V. and their rates shall be filled in and completed
by the office of the University Engineer before the tender form is issued. If a form
issued to an intending tenderer has not been so filled in and completed he shall
request the said officer to have this done before he completes and delivers his tender.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 42 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
9. All work shall be measured net by standard measure and according to the rules
and customs of the M.P.K.V. and their rates shall be without reference to any local custom. 10. Under no circumstances shall any contractor be entitled to claim enhanced
rates for items in this contract. 11. Every unregistered contractor shall, { unless exempted in writing by the
Superintending Engineer concerned ) produce along with his tender a solvency
certificate to the extent of the tendered cost of work from the Collector of the District or
Tahasildar of Taluka within which he resides or a banker's certificate of his financial
stability. If he fails to produce such a certificate his tender will not be considered.
OR
Every registered contractor should produce along with his tender certificate of registration as
approved contractor in the appropriate class and renewal of such registration with date of expiry.
12. All corrections and additions or pasted slips should be initialed. 13. The measurement of work will be taken .according to the usual methods in use in
the M.P.K.V. and no proposals to adopt alternative method will be accepted. The University
Engineer's decision as to what is the usual method in use in the M.P.K.V. will be final. 14. The tendering contractor shall furnish a declaration along with the tender showing all works for
which he has already entered into contract and the value of the work that remains
to be executed in each case on the date of submitting the tender. 15. Every tenderer shall furnish along with the tender, information regarding the Income Tax. Circle
or Ward of the District in which he is assessed to Income- Tax, the reference to the number of
the assessed and the assessment year, and a valid Income Tax clearance certificate.
16. In view of the difficult position regarding the availability of foreign exchange no foreign
exchange would be released by the Department for purchase of plant and machinery
required for the execution of the work contracted for ( GCB / PWD / CFM / 1058
- 62517 dated 26.9.1959)
17. The contractor will have to construct shade for storing controlled and valuable materials
issued to him under Schedule 'A' of the agreement at the work site, having double
locking arrangement materials will be taken for use in the presence of the
departmental persons. No materials will be allowed to be removed from the site of works.
18. The contractors shall also give list of machinery in their possession and which
they propose to use on the work.
19. Every unregistered contractor should furnish along with tender statement
showing previous experience and staff employed by him.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 43 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
20. Successful tenderer will have to produce to the satisfaction of the accepting authority a
valid and current license issued in his favor under the provision of Contract labour
(Regulation and Abolition Act 1973 before starting work, failing which acceptance of the
tender will be liable for withdrawal and earnest money will be forfeited to MPKV.
21. The contractor shall comply with the provision of the Apprentices Act 1962 and the
rules and orders issued there under from time to time. If he fails to do so, his failure
will be a breach of the contract and the University Engineer, may in his discretion
cancel the contract. The contractor shall also be liable for any pecuniary liability
arising on account of any violation by him of the provision of the Act.
22. The work of electrification of the work tendered for is to be got executed from the
Government registered electrical contractor of appropriate class having electrical
license from appropriate authority. The agreement on bond paper of Rs. 100.00
duly signed by both civil and electrical contractor is to be submitted in the
envelop no 1 of the tender at the time of submitting the tender.
23. The successful contractor shall produce a construction program/ bar chart within
month from the date of work order.
24. The successful contractors should establish a field lab within one month from
date of work order, failing which a compensation of Rs 10,000.00 per day till
establishment of the laboratory will be levied.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 44 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
TENDERS FOR WORKS 1. I / We hereby tender for the execution for the Government of Maharashtra and hereinafter
referred to as " M.P.K.V.") of the work specified in the underwritten memorandum within the
time specified in such memorandum at * ———————————————— (
) percent below / above the estimate rates entered in schedule ' B'
(memorandum showing items of work to be carried out) and in accordance in all
respects with the specifications, designs, drawings and instructions, in writing referred
to in Rule - 1 hereof and in Clause-12 of the annexed conditions of the contract and
agree that when material for the work are provided by the M.P.K.V. such materials and
the rate to be paid for them shall be as provided in Schedule 'A' hereto.
MEMORANDUM (a) Genera! Description Proposed Construction of (a) In several sub works are Agriculture College Building & included they should be detailed Infrastructure Facilities, At. Halgaon, in a separate list.
Dist. Ahmednagr.
(b) Estimated Cost RS. 26,41,36,858.00 (b) The amount of earnest money to be deposited shall be in accordance with the provision of para 204 & 205 of the MPW Manual.
(c) Earnest Money Deposit 1.0 Rs. 26,41,368.00 The deposit shall be in % accordance with para 211 & 212 of the MPW Manual (d) Security Deposit (d) The percentage where the i) Cash ( not less than the amount Rs. 66,03,422.00 security deposit is taken will vary of earnest money) 2.5% from 5% to 10% according to the requirement of the case where security deposit is taken see Note 1 to Clause 1 of condition of contact.
ii) To be deducted from current Rs. 66,03,422.00
bill 2.5%
Total Security Deposit 5% Rs. 1,32,06,843.00
(e) Percentage if any to be 2.5 % (e) Give Schedule Wher
ededucted from bills so as to necessary showing dates bymake up the Total amount which the various item are to be required as security deposit by complete.
the time, half the work at
measured by the cost, is done.
(f) Time allowed for the work 24 Calendars months (Including
from the date to written order to monsoon)
commence.
1. l / We agree that the offer shall remain open for acceptance for a minimum period of 120
days from the date fixed for opening the same thereafter until it is withdrawn by me / us by
notice in writing duly addressed to the authority opening the tenders and sent by the
registered post A.D. or otherwise delivered at the office of such authority. Demand draft for a
period of one year receipt No. and date —————— in respect to the sum of Rs. ——
No. of Corrections University Engineer 44
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
—————————————— in words Rs. ———-—-—————————-———
—— representing the earnest money is herewith forwarded. The amount of earnest
money shall not bear interest and shall be liable to be forfeited to the M.P.K.V. should I
/We fail to (i) abide by the stipulation to keep the offer open for the period mentioned
above or (ii) sign and complete the contract document as required by the Engineer and
furnish the authority deposit as specified in item (d) of the memorandum contained in
paragraph 1 above with in the time limit laid down in the clause (1) of the annexed
General conditions of contract. The amount of earnest money may be adjusted towards
the security deposit or refunded to me / us is so desired by me/us in writing, unless the
same or any part thereof has been forfeited as aforesaid. 2. I/We have secured exemption of earnest money after executing the necessary bond in favour
of Government a true copy of which is enclosed herewith, should any occasion for forfeiture
of earnest money for this work arise due to failure on my / our part to (i) abide the stipulations
to keep the offer open for the period mentioned above or (ii) sign and complete the contract
documents and furnish the security deposit as specified in item (d) of the Memorandum
contained in paragraph 1 above within the time limit laid down in clause
(1) of the annexed General condition of contract the amount deposited in the lump sum for
securing exemption in so far as the same may extend in terms of the option said bond and in
the event of the deficiency out of any other contract or payable to me/us by the Government
under any other contract or transaction of any nature whatsoever or otherwise.
3. Should this tender be accepted I/We hereby agree to abide by and fulfill all the
terms and provisions of the conditions of contract annexed here to so far as
applicable and in default thereof to forfeit and pay to Government the sum of
money mentioned in the said conditions.
Amount to be Receipt No. ———— dated ———.. from Account Officer at -———
specified in words in respect of the sum of Rs. —-—-—------- is herewith forwarded
and figures. Strike out representing the earnest money (a) the full value of which is to be
(a) if on security absolutely forfeited to MPKV. Should I/We not deposit the full amount
deposit is to be taken. of security deposit specified in the above memorandum, in accordance
with clause 1(A) of the said conditions of contract, otherwise the said
sum of Rs. _______________________ shall be refunded.
Signature of Contractor
Contractor before
submission offender Address
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 45 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Dated the ________________day of ________2017
Signature of (Witness) contractor before
submission of tender. Address
(Occupation)
The above tender is hereby accepted by me for and on behalf of the
Governor of Maharashtra / Mahatma Phule Krishi Vidyapeeth Dated — ——————— day of ————————— 200 ——— University
Engineer M.P.K.V. Rahuri.
CONDITION OF CONTRACT
Clause 1 - The person / persons whose tender may be accepted (hereinafter
called the contractor, which expression shall unless excluded by or repugnant
to the context include his heirs, Executors, administrators, and assigns ) shall
(A) ( within on day for a contract of Rs. 1000/- or less or two days for contract
of more that Rs.1000/- but less than Rs. 2000/- and so on upto a limit of ten
days, which may be extended by the vice- Chancellor, Mahatma Phule Krishi
Vidyapeeth concerned upto 15 days, if the vice Chancellor thinks it fit to do
so far a contract over Rs. 10,000/- of the receipt by him of the notification of
the acceptance of his tender) deposit with the Engineer in Charge {if
deposited ) for more than 12 months ) a sum sufficient which will make up the
full security deposit specified in the tender or (B) (permit M.P.K.V. at the time
of making any payment to him for work done under the contract to deduct
such sum as will amount "percent of all moneys so payable such deductions
to hle by Mahatma Phule Krishi Vidyapeeth by way of security Deposit.)
Provided always that in the event of the contractor depositing a lump sum by
way of security deposit as contemplated at (A) above then and in such case,
if the sum so deposited shall not amount o percent of the total estimated cost
of the work, it shall be lawful for Mahatma Phule Krishi Vidyapeeth at the time
of making of any payment to the contractor for the work under the contract to
makeup the full amount of percent by deducting a sufficient sum for every
such payment at last aforesaid until the full amount of the security deposit is
made-up
All compensation or other sums of money payable by the contractor
Mahatma Phule Krishi Vidyapeeth under the terms of his contract may be
Signature of
Officer by whom
Accepted.
Security Deposit
* this will be Same
percentage : that
in the tender
(e).
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 46 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
deducted from, there from, or from any sums which may be due or may
become due by Mahatma Phule Krishi vidyapeeth to the contractor under any
other contract or traction of any nature whatsoever in the even of his security
deposit being reduced by reason of any such deductions or sale as aforesaid,
the contractor shall, within 10 days hereafter, make good in case or M.P.K.V.
Securities endorsed as aforesaid any sum or sums which may have been
deducted from or raised by sale of his security deposit or any part thereof.
The security deposit referred to when paid in cash may, at the cost of the
depositor has expressly desired this in writing. The security deposit will not
be accepted in form of Insurance company bonds.
If the amount of the security deposit to be paid in lump sum within
the period specified at (A) above is not paid the tender/ contract
already accepted shall be considered cancelled and legal steps
taken against the contractor for recovery of the amount. The
amount of security deposit lodged the contractor shall be refunded
50% after payment of final bill and remaining 50% of security
deposit shall be refunded after expiry of 12 months after payment
of final bill or the expiry of defect liability period. Whichever is later.
The defect liability period for the work is Eighteen months. The
defect liability period starts from the date of completion of the work.
Clause 2 - The time allowed for carrying out the work as entered tender Compensation for
for delay. shall be strictly observed by the contractor and shall be reckoned Delay
from the date on which the order to commence work is given to the
contractor, The work shall through the stipulated period of the contract be
proceeded with, with all due diligence (time being deemed to as
compensation an amount equal to one percent or such smaller amount as the
University Engineer (whose decision in writing shall be final) may decide, of the amount of the estimated cost of the whole work as shown by the
tender for every day that the work remains uncommented or unfinished,
after the proper dates. And further to ensure good progress during
execution of the work, the contractor shall be bound, in all case in which
the time allowed for any work exceeds one month to complete.
1/6* of the work in 1/4lh
of the time. ½ of the work in ½ of the time.
¾ of the work in ¾
of the time.
Note - The quantity of the work to be within a particular time to be
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 47 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
specified above shall be fixed and inserted in the blank space kept for the
purpose by the Office competent to accept the contracts after taking into
consideration the circumstances of each case and abide by the program
of the detailed progress laid down by the University Engineer.
The following proportion will usually be found suitable :
In ¼, ½, ¾ of the time.
Reasonable progress of the earth work, 1/6, 1/2, 3/4 of the total
value of the work to be done.
Do Do of masonry work 1/10,4/10,8/10 Do Do
In the event of the contractor failing to comply with this conditions he shall
be liable to pay as compensation an amount equal to one percent or such
smaller amount as the University Engineer (whose decision in writing
shall be final) may decide of the said estimated cost of the whole work for
every day that the due quantity of the work remains incomplete provided
always that the total amount of compensation to be paid under the
provisions of the clause shall not exceed 10 percent of the estimated cost
of the work as shown in the tender Vice Chancellor, M.P.K.V., Rahuri,
should be the final authority in this respect, irrespective of the fact that the
tender is accepted by the University Engineer or M.P.K.V., Rahuri.
Clause 3 - In any case in which under any clause of this contract the Action when
contractor shall have rendered himself liable to pay compensation whole of security
amounting to the whole of his security deposit whether owing to serious deposit Is
illness or death of the contractor or any other cause the Engineer, on forfeited.
behalf of the M.P.K.V. shall have power to adopt any of the following courses, as he may deem best suited to the interest of M.P.K.V.
(a) To rescind the contract (for which rescission notice in writing to the contractor under the hand of University Engineer shall be conclusive
evidence ) and in the case the security deposit of the contractor shall stand forfeited and be absolutely at the disposal of MPKV.
(b) To carry out the work or any part of the work departmental debiting
the contractor with the cost of the work, expenditure incurred on tools and
plant, and charges on additional supervisory staff including the cost of
work charged establishment employed for getting the un-executed part of
the work completed and creding him with the value of the work done.... Departmentally in all respects in the same manner and at the same rates as if
it had been carried out by the contractor under the terms of his contract.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 48 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
The certificate of the University Engineer as to the costs and other
allied expenses so incurred and as to the value of the work so done
departmentally shall be final and conclusive against the contractor.
c) To order that the work of the contractor be measured up and to take
such part thereof as shall be unexecuted out of his hands, and to give
it to another contractor to complete, in which case all expenses
incurred on advertisement for fixing a new contracting agency,
additional supervisory staff including the cost of the work charged
establishment and the cost of the work executed by the new contract
agency will be debited to the contractor and the value of the work
done or executed through the new contractor shall be credited to the
contractor in all respects and in the same manner and at the same
rates as if it had been carried out by the contractor under the terms of
his contract. The certificate of the Executive Engineer as to all the cost
of the work and other expenses incurred as aforesaid for or in getting
the unexecuted work done by the new contractor and the value of the
work so done shall be final and conclusive against the contractor. In case the contract shall be rescinded under clause (a) above the contractor
shall not be entitled to recover or be paid, any sum for any work therefore
actually performed by him under this contract unless and until the University
Engineer shall have certified in writing the performance of such work and the
amount payable to him in respect thereof and he shall only be entitled to be
paid the amount so certified. In the event of either or courses referred to in
clause (b) or (c) being adopted and the cost of the work executed
departmentally or through a new contractor and other allied expenses
exceeding the value of such work and allied expenses, provided always that
whichever of the three courses mentioned in clause (a), (b) or (c) is adopted
by the M.P.K.V. Engineer, the Contractor shall have no claim to
compensation for any loss sustained by him by reason of his having
purchased or procured any materials, or entered into any engagements, or
made any advance on account of or with a view to the execution of the work
or the performance of the contract.
Clause 4 - If the progress of any particular portion of the work is Action when the
unsatisfactory the M.P.K.V. Engineer shall not with standing that the general progress of any Progress of the work is in accordance with the conditions mentioned in particular portion
clause 2, be entitled to take action under clause 3 (b) after giving the of the work is
contractor 10 days’ notice in writing. The contractor will have no claim for unsatisfactory.
compensation, for any loss sustained by him owing to such action.
Signature of Contractor No. of Corrections University Engineer
49 49
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Clause 5 : - In case in which any of the powers conferred upon the Contractor
University Engineer by Clause 3 and 4 hereof shah have become remains liable to
exercisable and the same shall not have been exercised, the non exercise pay compensation
thereof shall not constitute a waiving of any of the conditions hereof and if action not taken
such powers shall notwithstanding be exercisable in the event of any future under Clause 3 &
case of default by the contractor for which under any clause hereof he is 4
declared liable to pay compensation amounting to the whole of his
security deposit and the liability of the contractor for past and
future • compensation shall remain unaffected.
In the event of the University Engineer taking action under sub - clause (a) or Power To take
(c) or clause 3m, he may , if he so desires, take possessions of all or any Possession of or
tools any plant, materials and stores in or. upon the work of the site thereof require removal of
or belonging to the contractor, or procured by him and intended to be used or sell contractor's
for the execution of the work or any part thereof paying or allowing for the plant.
same, in account at the contract rates, or in the case of contract rates not
being applicable at current market rates to be certified by the University
Engineer may, after giving notice in writing
to the contractor or his clerk of the work, foremen or other authorized agent
require him to be remove such tools and plant, material or stores from the
premises within a time to be specified in such notice, and in the event of the
contractor failing to comply with any such requisition, the University Engineer
may remove them at the contractor's expenses of any such removal and the
amount of the proceeds and expense of any such sale shall be final and
conclusive against the contractor.
Clause 6 - If the contractor shall desire an extension of the time for Extension of
completion of work on the ground of his having been unavoidably hindered time
in its execution or on any other ground he shall apply in writing to the University Engineer before the expiration of the period stipulated in the tender
or before the expiration of 30 days from the date on which he was hindered
as aforesaid or on which he was hindered as aforesaid or on which the cause
for asking for extension occurred, whichever is earlier and the University
Engineer, or in the opinion of University Engineer, as the case may be if in
his opinion , there were reasonable grounds for granting an extension, grant
such extension as he things necessary or proper. The decision of the
University Engineer in this matter shall be final.
Signature of Contractor No. of Corrections University Engineer
50
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Clause 7 - On the completion of the work the contractor shall be furnished Final Certificate
with a certificate by the University Engineer ( hereinafter called the
Engineer -in-charge ) of such completed until the contractor shall have
removed from the premises on which the work shall have been executed, all
scaffolding, surplus materials and rubbish, and shall have cleaned off, the
dirt from all wood work, doors, windows, wall, floor or other parts of any
building in or upon which the work has been executed or of which he may
have had possession for the purpose of executing the work, nor until the
work shall have been measured by the Engineer - in - charge or where the
measurements have been taken by his subordinate until they have received
approval of the Engineer -in-charge, the said measurements begin binding
and conclusive against contractor. If the contractor shall fail to comply with
the requirements of this clause as to the removal of scaffolding surplus
materials and rubbish and the cleaning of dirt on or before the date fixed
for the completion of the work the Engineer - in charge may at the expense
of the contractor, remove such scaffolding, surplus materials and rubbish
and dispose of the same as he thinks fit and clean off such dirt as aforesaid
and the contractor shall forthwith pay the amount of all expense so
incurred, but shall have no claim in respect of any such scaffolding or surplus
materials as aforesaid except for any sum actually realized by the sale
thereof.
Clause 8 - No payment shall made for any work, estimated to cost less than Payment on
rupees one thousand till after the whole of work shall have been completed intermediate
and a certificate of completion given. But in the case of works estimated to certificate to be
cost more than rupees one thousand the contractor shall on submitting a regarded as
monthly bill therefore be entitled to receive payment proportionate to the advance.
part of the work then approved and passed by the Engineer-in-charge,
whose certificate of such approval and passing of the sum so payable shall
be final and conclusive against the contractor All such intermediate
payments shall be regarded as payments by way of advance against the
final payments only and not as payments for work actually done and
completed and shall not preclude the unskillful work to be removed or taken
away and reconstructed or re-erected nor shall any such payment be
considered as an admission of the due performance of the contract or any
part thereof in any respect or the accruing of any claim nor shall it conclude
determine, or effect in any other way the powers of the Engineer in charge
as to the final settlement and adjustment of the account or otherwise, in any
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 51 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
other way very or affect the contract. The final bill shall be
submitted by the contractor within one months of the date fixed for
the completion of the work, otherwise the Engineer-in-charge's
certificate of the measurements and of the total amount payable for
the work shall be final and binding on the parties.
Clause 9 - The rates for several items of work estimated to cost more
than Rs. 1000/- agreed to within, shall be valid only when the item
converted is accepted as having been completed fully in accordance
with the sanctioned specifications. In case where the of work are not
accepted as so completed fully in accordance with the sanctioned
specifications. In case where the items of work are not accepted as so
completed by the Engineer-in-charge he may make payment on
account of such items at such reduced rates as he may consider
reasonable in the preparation of final or on account bills.
Payment at
reduced rates on
account of items of work not
accepted to be
at the discretion
of the Engineer- in-charge.
Clause 10 - A bill shall be submitted by the contractor in each month on or Bill to be
before the ate fixed by the Engineer-in-charge for all work executed in the submitted
previous month and the Engineer-in-charge shall take or cause to be taken monthly.
the requisite measurement for the purpose of having, the same verified and
the claim, so far as it is admissible shall be adjusted, if possible, within ten
days from the presentation of the bill. If the contractor does not submit the
bill within the time fixed as aforesaid, the Engineer - in - charge may
depute a subordinate to measure up the said work in the presence of the
contractor or his duly authorized agent whose countersignature to
measurement list shall be sufficient warrant, and the Engineer-in-charge
may prepare a bill from such list which shall be binding on the contractor in
all respects.
Clause 11 - The contractor shall submit ail bills on the printed forms to Bills to be
be had on application at the office of the Engineer- in- charge. The on printed forms.
charges to be made in the bills shall always be entered at the rates
specified in the tender or in the case of any extra work ordered in
pursuance of these conditions, and not mentioned or provided for in the
tender at the rates hereinafter provided for such work.
Clause 12- If the specification or estimate of the work provides for the use Stores supplied by
of any special description of material to be supplied from the store to the Government.
M.P.K.V. store or if it is required that the contractor shall use certain stores
to be provided by the Engineer - in- charge ( such material and stores and
their prices to be charged therefore as hereinafter mentioned being so far
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 52 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
as practicable for the convenience of the contractor but not so as in any
way to control the meaning or effect of this contract specified in the
schedule or memorandum here to annexed ) the contractor shall be
supplied with such material and stores as may be required from time to
time to be used by him for the purposes of the contract only, and value of
the full quantity of the materials and stores so supplied shall be set off or
deducted from any sums then due due, or thereafter to become due to
the contractor under the contract or otherwise , or from the security
deposit or the proceeds of sale thereof if the security deposit is held in
University securities, the same or a sufficient portion thereof shall in that
case be sold for the purpose. All materials supplied to the contractor shall
remain the absolute property of University and shall on no account be
removed from the site of the work, and shall at all times be open for
inspection by the Engineer-in-charge. Any such materials unused and in
perfectly good condition at the time of completion or determination of the
contract shall be returned to the M.P.K.V. store if the.
Engineer-in-charge so requires by a notice in writing given under
his hand but the contractor shall not entitile to return any such
material except with consent of the Engineer-in-charge and he
shall have no claim for compensation on account of any such
material supplied to him as aforesaid but remaining unused by him
or for any wastage in or damage to such materials.
Clause 12 (A)- All stores of controlled materials such as cement,
steel etc. supplied to the contractor by government should be kept
by the contractor under lock and key and will be accessible for
inspection by the University Engineer or his agent at all the times.
Clause 13- The contractor shall execute the whole and every part of the Works to be
work in the most substantial and workmanlike manner, and both as regards executed In
materials and every other respect in strict accordance with specifications. accordance with
The contractor shall also confirm exactly fully and faithfully to the designs, specification,
drawings and instructions in writing relating to which, the contractor shall be drawings order
entitled to have access for the purpose of inspection at such office, or on the etc.
site of the work during office hours. The contractor will be entitled to receive three sets of contract drawing and working drawings as well as one
certified copy of the accepted tender along with the work order free of
cost. Further copies of the contract drawings and working drawings if
required by him shall be supplied at the rate of Rs. 100 per set of contract
drawings and Rs.50 per working drawing except where otherwise
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 53 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
specified.
Clause 14- The Engineer in charge shall have power to make any alteration Alterations in
in or additions to the original specifications, drawings, designs and specifications and
instructions that may appear to him to be necessary or advisable during the designs not to
progress of the work and the contractor shall be bound to carry out the invalidate contact.
work in accordance with any instructions in this connections which may be
given to him in writing signed by the Engineer-in-charge and such alteration
shall not invalidate the contract, and any additional work which the
contractor may be directed to do in the manner above specified as part of
the work shall be carried out by the contractor on the same conditions in all
respects on which he agreed to do the main work. And if the additional and
altered work includes any class of work for which he agreed to do the main
work. And if the additional and altered work includes any class of work for
which no rate is specified in this contract, then such class of work shall be
carried out at the rates entered in the Schedule of Rates of the Division or
at the rates mutually agreed upon between the Engineer-in-charge and the
contractor, whichever are lower.
If the additional or altered work for which no rate is entered in the schedule Rates items
of Rates of the Division is ordered to be carried out before the rates are estimate or
agreed upon then the contractor shall within seven days of the date of Schedule of Rates
receipt by him of the order to carry out the work, inform the Engineer-in- of the District.
charge of the rate which it is his intension to charge for such class of work,
and if the Engineer-in-charge does not agree to this rate he shall be notice
in writing be at liberty to cancel his order to carry out such class of work and arrange to carry out in such manner as he may consider
advisable provide always that if the contractor shall commence work
or incur any expenditure in regard there before the rates shall have
been determined as lastly hereinbefore mentioned, then in such case
he shall only be entitled to be paid in respect of the work carried out or
expenditure incurred by him prior to the date of the determination of
the rate as aforesaid according to such rate or rates as shall be fixed
by the Engineer-in-charge. In the event of a dispute the decision of the
University Engineer of the Circle will be final. Where however, the work is to be executed according to the designs,
drawings and specifications recommended by the contractor and accepted by
the competent authority the alterations above referred to shall be within the
scope of such designs, drawings and specifications appended to the tender.
The time limit for the completion of the work shall be extended in
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 54 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
the proportion that increase in its cost occasioned by alterations or
additions bear to the cost of the original contract work, and the certificate
of the Engineer -in-charge as to such proportion shall be conclusive.
Clause 15- (1) If at any time after the execution of the contract documents Extension of time
the Engineer shall for any reason what-so-ever (other than default on the in consequence of
part of the contractor for which the M.P.K.V. is entitled to rescind and additions or
contract) desire the whole or any part of the work specified in the tender alterations No
should be suspended for any period or that the whole or part of the work claim to any
should not be carried out at all, he shall give to the contractor a notice in payment: or
writing of such desire and upon the receipt of such notice the contractor shall compensation for
forthwith suspend or stop the work wholly or in part as required, after alteration in/or
having due regard to the appropriate stage at which the work should be restriction of work. stopped or suspended so as not to case any damage or injury to the work
already done or endanger the safety thereof provided that the decision of
the Engineer as to the stage at which the work or any part of it could be
or could have been safety stopped or suspended shall be final and
conclusive against the contractor. The contractor shall have no claim to
any payment or compensation whatsoever by reason of or in pursuance
of any notice as aforesaid, on account of any suspension stoppage or
curtailment except to the extent specified hereinafter. (2)Where the total suspension of work ordered as aforesaid continued for
a continuous period exceeding 90 days the contractor shall be at liberty to
withdraw from the contractual obligations under the contract so far as it
pertains to the unexecuted part of the work by giving a 10 days prior
notice in writing to the engineer, within 30 days of the expiry of the said
period of 90 days, of such intention and requiring the Engineer to record
the final measurement of the work already done and to pay final bill. Upon
giving such notice the contractor shall be deemed to have been
discharged from his obligation to complete the remaining unexecuted
work under his contract. On receipt of such notice the Engineer shall
proceed to complete the measurements and make such payment as may
be finally due to the contractor within a period of 90 days from the receipt
of such notice in respect of the work already done by the contractor. Such
payment shall not in any manner prejudice the right of the contractor to
any further compensation under the remaining provisions of this clause. (3) Where the Engineer required the contractor to suspend the work for a
period in excess of 30 days at any time or 60 days in the aggregate, the
contractor shall be entitled to apply to the Engineer within 30 days of the
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 55 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
resumption of work after such suspension of payment of compensation to the
extent of pecuniary loss suffered by him in respect of working machinery
remained idle on the site or on the account of his having and to pay the
salary or wages of labour engaged by him during the said period of
suspension provided always that the contractor shall not be entitled to any
claim in respect pf any such working Machinery, salary or wages for the first
30 days suspension whatsoever occasioned by unsatisfactory work or any
other default on his part. The decision of the Enginee' in this regard shall be
final and conclusive against the contractor.
(4)ln the event of-
(i)Any total stoppage of work on notice from Engineer under sub
clause (1) in that behalf.
(ii)Withdrawal of the contractor from the contractural obligations to
complete the remaining unexecuted work under sub-clause (2) on
account of continued suspension of work for a period exceeding 90 days.
OR
(iii) Curtailment in the quantity of item or items originally tendered on No claim to
account of any alteration, omission or substitution in the specifications, compensation on
drawings, designs or instructions under clause (14)-1 where such curtailment account of loss
exceeds 25% in quantity and the value of the quantity curtailed beyond due to delay in
25% at the rates for the item specified in the tender is more than Rs. supply of
5000/-. materials
University.
It shall be open to the contractor, within 90 days from the service of (i) the
notice of stoppage of work or (ii) the notice of withdrawal from the
contractual obligations under the contract on account of the continued
suspension of work or (iii) notice under clause 14(1) resulting in such
curtailment to produce to the Engineer satisfactory documentary evidence
that he has purchased or agreed to purchase materials for use in the
contracted work, being receipt by him of the notice of stoppage,
suspension or curtailment and require the Government to take over on
payment such material at the rates determined by the Engineer, provided,
however, such rates shall in no case exceed the rate at which the same
was acquired by the contractor. The MPKV shall thereafter take over the
material so offered, provided the quantities offered, are not in excess of
the requirements of the unexecuted work as specified in the accepted
tender and are of quality and specifications approved by the Engineer.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 56 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
CLAUSE 15 A- The Contractor shall not be entitled to claim any
compensation from Government for the loss suffered by him on
account of delay by M.P.K.V. IN THE SUPPLY OF MATERIAL
ENTERED IN Schedule A where such delay is caused by –
(i) Difficulties relating to the supply of railway wagons,
(ii) Force majeure
(iii) Act of God (iv) Act of enemies of the State or any other
reasonable cause beyond the control of M.P.K.V.
(iv) In the case of such delay in the supply of materials, M.P.K.V.A
shall grant such extension of time for the completion of the
work as shall appear to the University Engineer to be
reasonable in accordance with the circumstances of the case.
The decision of the University Engineer as to the extension of
time shall be accepted as final by the contractor.
Clause 16 - Under no circumstances whatever shall the contractor be
entitled to any compensation from MPKV on any account unless the
contractor shall have submitted a claim in writing to the Engineer in-
charge within one month of the case of such claim occurring. Clause 17- If any time before the security deposit or any part thereof is
refunded to the contractor is shall appear to the Engineer- in-charge or his
subordinate in charge of the work, that any work has been executed with
unsound, imperfect or unskillful workmanship work has been executed with
unsound, imperfect or that any materials or articles provided by him for the
execution of the work are unsound, or of a quality inferior to that contracted
for, or are otherwise not in accordance with the contract it shall be lawful for
the Engineer in-charge to intimate this fact in writing to the contractor and
then notwithstanding the fact that the work, materials or articles complained
of may have been inadvertently passed, certified and paid for the contractor
shall be bound forthwith to rectify, or remove and reconstruct the work so
specified in whole or in part as the case may require or if so required, shall
remove the materials or articles so specified and provide other proper and
suitable materials or articles at his own charge and cost and in the event of
his failing to do so within a period to be specified by the Engineer-in-charge in
written intimation aforesaid, the contractor shall be liable to pay
compensation at the rate of one percent on the amount of the estimate for
every day not exceeding 10 days during
No claim to
compensation on
account of loss
due to delay In
supply of
materials by
Time limit for
unforeseen
claims.
Action and
compensation
payable in case
of bad work.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 57 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
which the failure so continues and in the case of any such failure the
Engineer-in-charge may rectify or remove and re-execute the work or remove
and replace the materials or articles complained of as the case may be at the
risk and expense in all respects of the contractor. Should the Engineer-in-
charge consider that any such inferior work or materials as described above
may be accepted or made use of it shall be within his discretion to accept the
same at such reduced rates as he may fix therefore
PWD Resolution
No CAT
1087/CR/94
Building 2 dt.
14.6.1989
Clause 18- All work under or in course of execution or executed in Work to be open pursuance of the contract shall at all times be open to the inspection and to inspection. supervision of the Engineer-in-charge and his subordinates and the contractor shall at all times during the usual working hours, and at all other times at which reasonable notice of the intention of the Engineer-in-charge and his subordinate to visit the work shall have been given to the contractor either himself be present to receive orders and instructions or have a responsible agent duly credited in writing present for that purpose. Orders given to the contractor's duly authorized agent shall be considered to have the same force and effect as if they had been given to the contractor himself.
Clause 19- The contractor shall give not less than five days notice in
writing to the Engineer-in-charge or his subordinate in charge of the
work before covering up or otherwise placing beyond the reach of
measurement any work in order that the same may be measured and
correct dimensions thereof taken before the same is so covered up or
placed beyond the reach of measurements and shall not cover up or
place beyond the reach of measurement any work without the consent
in writing of the Engineer-in-charge or his subordinate in charge of the
work and if any work shall be covered up or placed beyond the reach
of measurements shall be uncovered at the contractor's expenses and
in default thereof no payment or allowance shall be made for such
work or for the materials with which the same was executed. Clause 20- If during the period- of Eighteen months from the date of
completion as certified by the Engineer-in-charge pursuant to Clause -7 of
the contractor or Eighteen months after commissioning the work whichever is
earlier in the opinion of the University Engineer; the said work is defective in
any manner whatsoever, the contractor shall forthwith on receipt of notice in
that behalf from the University Engineer, duly commence execution and
completely carry out at his cost in every respect all the work that may be
necessary for rectifying and setting right the defects specified therein
Contractor Or
responsible Agent
to be present.
Notice to be
given before work
is Covered up.
Contractor liable
for damage
done and for
imperfections.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 58 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
including dismantling and reconstruction of unsafe portions strictly in
accordance w with and in the manner prescribed and under the supervision
of the University Engineer. In the event of the contractor failing or neglecting
to commence execution of the said rectification work within the period
prescribed therefore in the said notice and/or to complete the same as
aforesaid as required by the said notice, the University Engineer get the
same executed and carried out departmentally or by any other agency at the
risk on account and at the cost of the contractor. The shall forthwith on
demand pay to the Government the amount of such cost, charges and
contractor expenses sustained or incurred by the M.P.K.V., Rahuri of which
the certificate of the University Engineer shall be final and binding on the
contractor. Such cost, charges and expenses shall be deemed to be arrears
of land revenue and in the event of the contractor failing or neglecting to pay
the same on demand as aforesaid without prejudice to any other rights and
remedies of the M.P.K.V. Rahuri the same may be recovered from the
contractor as arrears of land revenue. The M.P.K.V. shall also be entitled to
deduct the same from any amount which may then be payable or which may
thereafter become payable by the M.P.K.V. to the contractor either in respect
of the said work or any other work whatsoever or from the amount of security
deposits retained by M.P.K.V. the defect liabilities period in particular for
water proofing treatment (Building works) shall be 7 years.
P.W.D. Resolution
No. CAT-1087/
CR/94/Bldg.2 dt.
14.6.89
Clause -21 The contractor shall supply at his own cost all material (except Contractor to
such special materials if any as may in accordance with the contract, be supply plant
supplied from M.P.K.V. Stores) plant tools, appliances, implements, ladders, ladder scaffolding
cordage, tackles, scaffolding and temporary works requisite or proper for etc.
the proper execution of the work, whether in the original, altered or
substituted from and whether included in the specification or other
documents forming part of the contract or referred to in these conditions or
not and which may be necessary for the purpose of satisfying requirements
of the Engineer-in-charge as to any matter as to which under these conditions he is entitled to be satisfied, or which ie is entitled to require
together with the carriage therefore to and from the work. The contractor shall
also supply without charge the requisite number of persons with the means
and materials necessary for the purpose of setting out works and counting,
weighing and assisting in the measurement or examination at any time and
from time to time of the work or the materials failing which the same may be
provided by the Engineer-in-charge at the expense of the contractor and the
expenses may be deducted from any money due to the
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 59 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
contractor under the contract or from his security deposit or the proceeds of
sale thereof, or of a sufficient portion thereof. The contractor shall provide all
necessary fencing and lights required to protect the public from accident and
shall also be bound to bear the expenses of defense of ever suit, action or
other legal proceeding, that may be brought by any person for injury
sustained owing to neglect of the above precautions, and to pay any
damages and cost which may be awarded in any such suit action or And is liable for
proceeding to any such person or which may with consent of the contractor damages arising
be paid for compromising any claim by any such person. List of machinery from non
in contractor's possession and which they propose to use on the works should provisions of
be submitted along with the tender. light, fencing etc.
Clause-21-A The contractor shall provide suitable scaffolds and
working platforms gangways and stairways and shall comply with
the following regulations in connections herewith.
(a) Suitable scaffolds shall be provided for workmen for all works
that cannot be safely done from a ladder or by other means. (b) A Scaffold shall not be constructed, taken down or substantially
altered except, (i) Under the supervision of a competent and
responsible person and (ii) As far as possible by competent
workers possessing adequate experience in this kind of work. (c) All scaffolds and appliances connected there with and ladders
shall-(i) Be of sound material.
(ii) Be of adequate strength having regard to the loads and strains
to which they will be subjected and
(iii)Be maintained in proper condition.
(d) Scaffolds shall not be over loaded and so far as practicable the
load shall be evenly distributed. (e) Scaffolds shall be so constructed that no part thereof can be
displaced in consequent of normal use. (f) Before installing lifting gear on scaffolds special precautions
shall be taken to ensure the strength and stability of the scaffolds. (g) Scaffold shall be periodically inspected by the competent person. (h) Before allowing a scaffold to be used by his workmen the contractor shall,
whether the scaffold has been erected by his workmen or not, take steps to
ensure that it complies fully with the regulations here-in-specified.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 60 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Working platform, gangways stairways shall-
i) Be so constructed that no part there of can sag unduly or unequally. ii) Be so constructed and maintained having regard to the
prevailing conditions as to reduce as far as practicable risks of
persons tripping or slipping, and iii) Be kept free from any unnecessary obstruction.
(i) In the case of working platform, gangways, working
places and stairways at the height exceeding 2 meters.
i) Every working platform and every gangway shall be closely
boarded unless other adequate measures are taken to ensure safety. ii) Every working platform and gangway shall have adequate width and iii) Every working platform gangway, working place and
stair way shall be suitably fenced.
(j) Every opening in the floor of a building or in a working platform shall
except for the time and to the extent required to allow the excess of
persons or the transport or shifting of materials be provided with
suitable means to prevent the fall of persons or material.
(k)When persons are employed on roof where there is a danger
of falling from a height exceeding 2 meters suitable precautions
shall be taken to prevent the fall of persons or materials. (I) Suitable precautions shall be taken to prevent persons being struck
by articles which might fall from scaffold or other working places.
(m) Safe means of access shall be provided to all working
platforms and other working places. (n)The Contractor(s) will have
to make payments to the labours as per Minimum Wages Act.
Clause 21-B- The contractor shall comply with the following
regulations as regards the hoisting appliances to be used by him
(a) Hoisting machine and tackle including their attachments,
anchorages and support shall-
i) be of good mechanical construction, sound material and
adequate strength and free from patent defect.
And ii) be kept in good repair and good working order.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 61 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
(b) Every rope used in hoisting or lowering materials as a means of
suspension shall be of suitable quality and adequate strength and
free from patent defect. (c) Hoisting machine and tackle shall be examined and adequately
tested after erection on the site and before use and be re-examined in
position at intervals to be prescribed by the Government. (d) Every chain, ring, hook, shade swivel and pulley block used in
hoisting or lowering materials or as a means of suspension shall be
periodically examined. (e) Every crane driver pr hoisting appliance operator shall be
properly qualified (f) No person who is below the age of 21 years shall be in control
of any hoisting machine including any scaffold which or give
signals to the operator. (g) In the case of every hoisting and of every chain, ring, hook, shackle,
swivel, pulley block used in hosting or lowering or as means of suspension
the safe working load shall be ascertained by adequate means.
(h) Every hoisting machine and all gear referred to in preceding
regulation shall be plainly marked with the safe working load. (i) In the case of hoisting machine having a variable safe working
load, each safe working load and the conditions under which it is
applicable shall be clearly indicated. (j) No part of any hoisting machine or of any gear referred or in regulation (g) above shall be loaded beyond the safe working load except for
the purpose of testing. (k) Motors, gearing, transmissions, electric working and other dangerous
part of hoisting appliances shall be provided with efficient safeguards.
(I) Noising appliances shall be provided with such means as will
reduce to minimum the risk of the accidental descenmt of the load.
(m) Adequate precaution shall be taken to reduce to a minimum the
risk of any part of a suspended load becoming accidentally displaced.
Clause 22- The contractor shall not set fire to a standing jungle, trees, brush Measure
for woods or a grass without a written permit from the University Engineer. prevention
of fire When such permit is given and also in all case when destroying cut or dug
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 62 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
up trees, brush woods, grass etc. by fire the contractor shall take the
necessary measure to prevent such fire spreading to or otherwise
damaging surrounding property. The contractor shall make his own
arrangements for drinking water for the labour employed by him.
Clause 23- Compensation for all dangers done intentionally or un-
intentionally by contractor's labour whether in or beyond the limits of
M.P.K.V. property including any damage caused by the spreading of
fire mentioned in Clause 22 shall be estimated by the Engineer-in-
charge or such other officer as he may appoint and the estimate of the
Engineer-in-charge subject to the decision of the Vice Chancellor on
appeal shall be final and the contractor shall be bound to pay the
amount of the assessed compensation on demand, failing which, the
same will be recovered from the contractor as damages in the manner
prescribed in clause 1 or deducted by the Engineer-in-charge from
any sums that may be due or become due from M.P.K.V to contractor
under this contractor or otherwise
The contractor shall bear the expenses of defending any action or
other legal proceeding that may be brought by and person for injury
sustained by him owing to neglect of precautions to prevent the
spread of fire and he shall pay damages and cost that may be
awarded by the court in consequence. Clause 24- The employment of female labour on work in neighborhood of
soldiers barracks should be avoided as far as possible.
Clause-25 - No work shall be done on a Sunday without the
sanction in writing of the Engineer-in-charge. Clause -26- The Contract shall not be assigned or sublet without the written
approval of the Engineer-in-charge. And if the contractor shall assign or
sublet his contract or attempt so to do or become insolvent or commence any
proceeding to get himself adjudicated and insolvent or make any composition
with his creditors or attempts so to do or if brief, gratuity, fifth, loan,
perquisite, reward or advantage pecuniary or otherwise shall either directly or
indirectly be given, promised or offered by the contractor of any of his
servants or agents to any public officer or person in the employ of M.P.K.V. in
any way relating to his office or employment or if any such officer or person
shall become in any way directly or indirectly interested in the contract, and
the Engineer-in-charge may thereon by notice in writing rescind the contract,
the contract, and the Engineer-in-charge may thereon
Liability of
contractor for
any damage
done in or out
side work area.
Employment
female labour.
Work on Sunday.
Work not to
sublet contract
may be rescinded
and security
deposit forfeited
for subletting it
without approval
or for bribing a
public officer or if
contractor
becomes
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 63 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
by notice in writing srescind the contract, he contract and the security insolvent.
deposit of the contractor shall there upon stand forfeited and be absolutely
at the disposal of M.P.K.V. and the same consequences shall ensure as of
the contract had been rescinded under clause 3 hereof and in addition the
contractor shall not be entitled to recover or be paid for any work
therefore actually performed under the contract.
Clause - 27 All sums payable by a contractor by way of compensation Sum payable by
under any of these conditions shall considered as a reasonable way of
compensation to be applied to the use of M.P.K.V. without reference to the compensation to
actual loss or damage sustained and whether any damage has or has not be considered
been sustained. reasonable
compensation
without reference
to actual loss
Clause 28- In the case of tender any charge in the constitution of a
firm shall be forthwith notified by the contractor to the Engineer in
charge for his information.
Clause 29- All works to be executed under the contract shall be
executed direction and subject to the approval in all respect of the
University Engineer of the Circle , for the time being who shall be
entitled to direct at what point or points in what manner they are to
be commenced and from time to time carried on.
Clause 30- (1) Except where there otherwise specified in the contract and
subject to the powers delegated to him by M.P.K.V. under the Code,
rules then in force, the decision of the University Engineer of the circle for the time being shall be final, conclusive and binding on all parties to
the contract upon all questions relating to the meaning of the
specifications, designs and instructions herein before mentioned and
as to the quality or work ship, or material used on the work or a to any
other question, claim right matter or thing what - so ever if any way
arising out of or relating or otherwise concerning the works or the
executions or failure to execute the same whether arising during the
process of the work or after the completion or abandonment thereof.
(2) The contractor may within thirty days of receipt by him of any
order passed by the University Engineer as aforesaid appeal
against it with the contract work project provided that- (a) The accepted Value of the contract exceed Rs. 10 lakhs (Rs. Ten Lakh)
Change in
the constitution of firm to be notified.
Direction & Control of the University Engineer.
Direction & control
of the University
Engineer.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 64 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
(b) Amount of claim is not less than Rs. 1.00 Lakh (Rs. One Lakh)
(3) If the Contractor so not satisfied with the order passed by the Chief
Engineer as aforesaid the contractor may within thirty days of the
receipt by him of any such order appeal against it to the University
M.P.K.V. who if convinced that prima ficia the contractor's claim
rejected by University/ Chief Engineer is not frivolous and that there is
some substances in the claim of contractor as would merit a detailed
examination and decision by the Standing committee shall put up to
the standing Committee at Government level for suitable decision, (as
per PW Circular No. CAT 1086 OR 110/Bldg. dt. 7-5-86)
Clause 31 - The contractors shall obtain from the Departmental stores, all Store of
European stores and articles of European or in American manufacturer which may be or
American required for the work or any part thereof or in making up any articles
manufacture to be required thereof or in connection there with unless he has obtained
obtained from the permission in writing from Engineer- in-charge to obtain such stores and
government. articles elsewhere. The value of such store and articles as may be supplied to the contractor by the Engineer-in-charge will be debited to the contractor in
his account at the rates shown in the schedule, in Forma A attached to the
contract and if they are not entered in the said schedule they shall be debited
to him at cost price which for the purpose of these contract shall include the
cost of carriage & other expenses whatsoever, which shall have been
incurred in obtaining delivery of the same at the stores aforesaid.
Clause 32-When the estimate on which a tender is made includes lump sum Lump sum in
in respect of parts of the work, the contractor shall be entitled to payment estimates
in respect of the items of work involved or the part of the work in question
at the same rates at are payable under this contract for each items, or if
the part of the work in question is not in the opinion of the Engineer-in-
charge capable of measurement, the Engineer-in-charge may at his
discretion pay the lump sum amount entered in the estimate and the
certificate in writing of the Engineer-in-charge shall be final and conclusive
against the contractor with regard to any sum or sums payable to him under
the provision of this clause.
Clause 33- In the case of any class of work for which there is no such Action where no
specification as is mentioned in rule 1 such work shall be carried out in specifications.
accordance with the Divisional specifications, and in the event of there
being on Divisional specification, then in such case the work shall be carried
out in all respects in accordance with all instructions and requirements of the
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 65 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Engineer-in-charge.
Clause 34- The expression "Works" or "Work" used in these conditions, shall Definition of
unless there be something in the subject or context repugnant to such work.
construction, be construed to mean the work or works contracted to be
executed under or in virtue of the contract, whether temporary or
permanent and whether original, altered, substituted or additional.
Clause 35- The percentage referred to in the tender shall be deducted Contractors
from/added to Contractors percentage whether the gross amount of the bill percentage
before deducting the value of any stock issued. whether applied
net or gross
amount of the bill
Clause 36 – All quarry fees, royalties, octroi, dues and ground rent, water
charges for stock materials, if any should be paid by the contractor.
Clause 37- The contractor shall be responsible for and shall pay any Compensation
compensation to his workmen payable under the workmen's Compensations under workmen
Act, 192G (VIII of 1923), (herein after called the said Act) for injuries compensation act. caused to the workmen. If such compensation is payable be paid by
Government as principle under Sub section (1) of section 12 of the said At on behalf of the contractor it shall be recoverable by Government from the
contractor under sub section (2) of the said section. Such Compensation
shall be recovered in the manner laid down in the Clause-1 above Clause 37A- The contractor shall be responsible for and shall pay the
expenses of providing medical aid to any workmen who may suffer a
bodily injury as a result of an accident. If such expenses are incurred by
Government the same shall be recoverable from the contractor forthwith
and be deducted without prejudice to any other remedy of Government
from any amount due to or that may become due to the contractor.
Clause 37 B- The contractor shall provide all necessary personal
safety equipment and first aid apparatus available for the use of
the persons employed on the site and shall maintain the same in
condition suitable for immediate use at any time & shall comply
with the following regulations in connection therewith.
(a) The workers shall be required to use the equipment so
provided by the contractor and the contractor shall take adequate
steps to ensure proper use of the equipment by those concerned.
{b) When work is carried on in proximity to any place where there is a
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 66 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
risk of drowning all necessary equipment shall be provided and
kept ready for use and all necessary steps shall be taken for the
prompt rescue of any person in danger.
(c) Adequate provision shall be made for prompt first aid treatment of
all injuries likely to be sustained during the course of the work.
Clause 37 C - The contractor shall duly comply with the provisions of the
Apprentices Act, 1961 (III of 1961) the rules made there under the orders
that may be issued from time to time order the Act the said rules and on his
failure or neglect to do so he shall be subject to all the liabilities and
penalties provided by the said Act and said Rules.
Clause 38- (1) Quantities in respect of the several items shown in the tender Claim for
are approximate and no revision in the tendered rate shall be permitted in quantities entered
respect of any of the times so long as subject to any special provision In the tender or
contained in the specifications prescribing different percentage of estimate.
permissible variation the quantity of the item does not exceed the
tender quantity by more than 25% and so long as the value of the
excess quantity beyond this limit at the rate of the item specified in
the tender is not more than Rs. 5000/-
(2) The contractor shall if ordered in writing by the Engineer so to do, also
carry out any quantities in excess of the limit mentioned in sub clause (1)
hereof on the same conditions as and in accordance with the
specifications in the tender at the rate (i) derived from the rates entered in
the current schedule of rates and in the absence of such rates, (ii) at the
rate prevailing in the market, the said rates being increased or decreased
as the case may be by the percentage which the total tendered amount
bears to the estimated cost of work as put tender based upon the
schedule of rates applicable to the year in which the tenders were invited.
For the purpose of the operation of this clause this cost shall be taken to
be cost worked out on the basis of D.S.R. 2013-2014 Claims arising out of reduction in the tendered quantity of any item beyond
25% will be governed by the provision of clause 15 only when the amount of
such reduction beyond 25% at the rate of the item specified in the tender is
more than Rs. 50007- (The clause is not applicable to extra items)
(3) The clause is not applicable to extra items. (4) There is no change in the rate if the excess is more than 25% of the
tendered quantity, but the value of the excess work at the Tendered rates
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 67 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
does not exceed. Rs. 500O/-
(5) The quantities to be paid at tendered rate shall include:-
(a) Tendered quantity Plus (b) 25% excess of the Tendered quantity or the excess quantity
of the value of Rs.5000/- at the Tendered rates whichever is more.
Clause 39- The contractor shall employ any famine convict or other Employment of
labour of a particular kind or class if ordered in writing to do so by the famine labour etc.
Engineer-in-charge. Claim for
Clause 40- No compensation shall be allowed for any delay caused in the compensation for
starting of the work on account of acquisition of land, or in the case of delay in starting
clearance works on account of any delay in according to sanction of the Work.
estimates.
Clause 41- No compensation shall be allowed for any delay in the
execution of the work in account of water standing in borrow pits or
compartments. The rates are inclusive for hard or cracked soil, excavation in
mud, soil water standing in borrows pits and no claim for extra rate shall be
entertained unless otherwise expressly specified.
Clause 42- The contractor shall not enter upon or commence any portion of Entering upon or
work except with the written authority and instructions of the Engineer-in- commencing any
charge or of his subordinate in charge of the work. Failing such authority the portion of work.
contractor shall have no claim to ask for measurements of or payment for
work.
Clause 43- (i) No contractor shall employ any person who is under
the age of 18 years.
(ii) No contractor shall employ donkeys or other animals with
breeching of string or thin rope The breeching must be at least
inches wide and should be of tape (Newer) (iii) No animal suffering from sores, lameness or emaciation or
which is immature shall be completed on the work.
(iv) The Engineer-in-charge or his Agent is authorised to remove from
the work any person or animal found working which does not satisfy
these conditions and no responsibility shall be accepted by M.P.K.V.
for any delay caused in the completion of the work by such removal. (v) The contractor shall pay fair and reasonable wages to the workmen
employed by him, in the contract under-taken by him. In the event of any
Minimum age of
person employed
the employment
of donkey and or
other animal and
the payment of
fair wages.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 68 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
dispute arising between the contractor and his workmen on the
grounds that the wages paid are not fair and reasonable the dispute
shall be referred without delay to the University Engineer who shall
decide the same. The decision of the University Engineer shall be
conclusive and binding on the contractor but such decision shall not in
any way affect the conditions in the contract regarding the payment to
be made by Government at the sanctioned tender rates.
(vi) Contractor shall provide drinking water facilities to the workers.
Similar amenities shall be provided to the workers engaged on
large work in urban, areas. (vii) Contractor to take precaution against accidents which takes place on
account of bout using loose garments while working near machinery.
Clause 44- Payment to contractor shall be made cheque drawn on any Method of
treasury within the division convenient to them provided the amount exceeds Payment
Rs. 10 Amounts not exceeding Rs. 10 will be paid in cash.
Clause 45- Any contractor who does not accept these conditions shall be not Acceptance of
allowed to tender for work. conditions
compulsory before
tendering for work
Clause 46- If M.P.K.V. declares a state of scarcity or famine to exist in the Employment Of
village situated within 10 miles of the work, the contractor shall employ Scarcity labour. upon such parts of the works, as are suitable for unskilled labour, any
person certified to him by the University Engineer, or by any person to
whom the University Engineer may have delegated this duty in writing
to be need or relief and shall be bound to pay to such person wages,
not below the minimum which, M.P.K.V. may have fixed in this behalf.
Any disputes which may arise in connection with the implementation
of this clause shall be decided by the University Engineer whose
decision shall be final and binding on the contractor. Clause 47- The price quoted by the contractors shall not in any case exceed
the control price if any, fixed by M.P.K.V. or reasonable price which it is
permissible for him to charge a private purchaser for the same class and
description the controlled price or price permissible under Hoarding and
Profiteering Ordinances 1948 as amended from time to time. If the price
quoted exceeds the controlled price or the price permissible under Hoarding
and Profiteering Prevention ordinance the contractor will specifically mention
this fact in his tender along with the reasons for quoting
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 69 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
such higher prices. The purchaser at his discretion will in such case
exercise the right of revising the price at any stage so as to confirm with
the controlled price exercise the right of revising the price at any stage so
as to conform with the controlled This discretion will be exercised without
prejudice to any other action that may be taken against the contractor. Clause -47 A- The tendered rates shall be inclusive of all taxes rates and Maharashtra Act cases and shall also be inclusive of the tax livable in respect of works of 1985 clause contract under the provision of the Maharashtra Sales tax on transfer of regarding property in goods involved in the execution of works contract Act 1985 Turnover Tax vide (Maharashtra Act, No. XIX of 1985). P.W.D Circular No.
330/Bldg-2
dt.10/6/1986
Clause 48 - The rates to be quoted by the contractor must be inclusive of sales Tax No extra payment on this account will be made to the contractor.
Clause 49- In case of materials that may remain surplus with the contractor from those issued for the work contracted for the date of ascertainment of the materials being surplus will be taken as the date of sale for the purpose of sale tax and the sales tax will be recovered on such sale.
Clause 50- The Contractor shall employ the unskilled labour to be employed by him on the said work only from locally available labours & shall give preference to those persons enrolled under Maharashtra Government employment & self employment Department's Scheme.
Provided however, that if the required unskilled labours are not available locally, the contractor shall in the first instance employee such number of persons as is available & thereafter may with previous permission, in writing of the University Engineer in charge of the said work, obtain the rest of requirement of unskilled labour from outside the above scheme.
Clause 51- Wages to be paid to the skilled and unskilled laborers engaged by the contractor.
The contractor shall pay the laborers skilled and unskilled according to the wages prescribed by the minimum Wages Act 1948 applicable to the area in which the work is located.
The contractor shall comply with the provisions of the apprentices Act 1961 and Rules and orders issued the under from time to time. If he fails to do so his failure will be a breach of the Contract and the University Engineer may in his discretion, cancel the Contract. The contractor shall also be liable for
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 70 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
any pecuniary liability arisen on account of any violation by him of
the provision of Act. The contractor shall pay the laborers skilled
and Un-skilled according to wages prescribed by Minimum Wages
Act applicable to the area in which the work lies.
Clause 52- All amounts whatsoever which the contractor is liable
to pay to the M.P.K.V. in connection with the execution of the
work including the amount payable in respect of
(i) Materials and or stores supplied/issued hereunder by the
M.P.K.V. to the Contractor (ii) Hire charges in respect of heavy plant, machinery and equipment
given on hire by the M.P.K.V. to the contractor for execution by him of the
work and/or on which advances have been given by the M.P.K.V. to the
contractor shall be deemed to be arrears of the Land Revenue and the
M.P.K.V. may without prejudice to any other rights and remedies of the
M.P.K.V. recover the same from the contractor as arrears of Revenue.
Clause 53- The contractor shall duly comply with all the provisions of the P.W. Deptt. Contract Labour (Regulation and Abolition) Act, 1970 (37 of 1970) and the NO.CAT1284 Maharashtra Contract labour (Regulation and abolition) Rules, 1871 as (Building-2) dated amended from time to time and all other relevant statutes and statutory provisions concerning payment of wages particularly to workmen employed by the contractor and working on the site of the work. In particular the contractor shall pay wages to each worker employed by him on the site of the work at the raes 'prescribed under the Maharashtra Contract Labour (Regulation and Abolition Rules 1971). If the contractor fails or neglects to pay wages at the said rates or marks short payment and the M.P.K.V. makes such payment of wages in full or part thereof less paid the contractor, as the case may be , the amount so paid by the M.P.K.V. to such workers shall be deemed to be arrears of land Revenue and the M.P.K.V. shall be entitled to recover the same as such from the contractor or deduct same from the amount payable by the M.P.K.V. to the contractor hereunder or from any other amount payable by the M.P.K.V. to the contractor hereunder or from any other amount/s payable to him by the M.P.K.V.
Clause 54- The contractor shall engage apprentices such as bricks layer, carpenters, wiremen’s, plumbers as well as black smith as recommended by the State Apprenticeship Advisor Director of technical Education, Dhobi Talav, Bombay 1 on the construction work. (Government of Maharashtra Educational Department No. TSA-5170YT-56689 dated 7.7.1972).
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 71 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Clause 55- (Government of Maharashtra P.W.D. Resolution No.
CAT-1086/CR-243/K/Bidg.32dt.11.8.1987).
(A) The anti-malaria and other health measures shall be as directed
by the Joint Director (Malaria and Fitaria) of Health services, Pune. (B) Contractor shall see that mosquito zenic conditions are not
created so as to keep vactor population to minimum level. (C) Contractor shall carry out anti malaria measures in the area as per
guidelines prescribed under National Malaria Eradication Programme and
as directed by the Joint Director (M &F) of Health Services, Pune. (D) In case of default in carrying out prescribed anti malaria
measures resulting in increase in malaria incidence, contractor shall
be liable to pay Government the amount spent by Government on anti
malaria measures to control the situation in addition to fine. (E) Relations with Public Authorities - The contractor shall make
sufficient arrangements for draining away the sullage water as well as
water coming from the bathing and washing places and shall dispose of
these water in such a way as not to because any nuisance. He shall also
keep the premises clean by employing sufficient number of sweepers.
The contractor shall comply with all rules, regulations, bye-laws
and directions, given from time to time by any local or public
authority in connection with this work and shall pay fees or charges
which are leviable on him without any extra cost of Government.
Clause 56- The tender rates are inclusive of all taxes, rates, taxes
and also inclusive of the livable tax in respect of sale by transfer of
property in goods involved in the execution of a works contract
under the provision of Rule 58 of Maharashtra Value Added Tax
ACT-2005 for the purpose of levy of Tax.
Clause 57- Tax Deducted at Source
Value added Tax @ 2% of tender cost from the contractors registered
under Maharashtra Value Added Tax ACT 2005 and @5% of tender
cost from those contractors who have not registered under
Maharashtra Value Added Tax ACT 2005 will be deducted from bills
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri 72 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
SCHEDULE 'A'
Schedule showing (Approximately) the materials to the supplied from the departmental stores for work, contracted to be executed and preliminary and ancillary works and the rates at which they are to be charged for:
Particulars Rates at which the materials will be charged to the Place of delivery contractor.
Unit In figures In Words
1 2 3 4 5
Note :- The person or firm submitting the tender should see that the rates in the above schedule are filled up by the University Engineer-in-charge on the issue of the form prior to the submission of the tender.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 73 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
ANNEXURE
Additional Conditions for procurement of Materials.
1. The contractor shall make his own arrangement for supply of materials including
bitumen 60/70 grade/cement & steel RCC Pipes collars. The contractor shall be
responsible for all transportation &* storages of the materials at site & shall be
bear all the related costs. The Engineer shall be entitled at any time, to inspect or
examine all such materials. The contractor shall provide reasonable assistance for
such inspection or examination as may be required.
2. The contractor shall keep as accurate record of use of material as like bitumen
cement & steel used in the works in a manner prescribed by the Engineer.
3. After receiving the bitumen the authorised challan/gate pass should be obtained
from the refinery mentioning the quantity of bitumen/grade of bitumen, date time
of delivery etc. & it should be handed over to Department for each consignment.
4. While transportation of bouzer a through transport pass should be obtained
from the corporation/ Municipality through which the bouzer is passed &
same should be handed over to the authorized person of Department.
5. If there is any doubt regarding the material received the same should be get tested
from the Govt. Laboratory of the cost of the Contractor & is the results are sub-
standard , the material or the work executed with such material will be rejected.
6. The day-today record of the receipt/Utility/Balance of material should be kept
by the contractor at plant site/ site of work/store & the same will be checked by
the Engineer-in charge of authorized Engineer at any time.
7. The procurement of cement/ steel RCC pipe etc. should be from authorized
manufacturing company & the vouchers regarding purchase thereof shall be
submitted to Engineer in-charge .
8. The testing charges shall be borne by the contractor.
B. Materials for Department works.
1) The contractor shall be entitled to such sum as the Engineer may consider
proper to respect of materials intended for but not yet incorporated in the
permanent works provided that :-
a) The materials are in accordance with the specification for the permanent works.
b) Such materials have been delivered to site and are properly stored and protected
against loss or damage or deterioration to the satisfaction of the Engineer.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 74 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
c) The contractor's records of the requirement, order, receipts and use of
materials are kept in a form approved by the Engineer and such records shall
be available for inspection by the Engineer.
d) The contractor shall submit with his monthly statement the estimated value of the materials
on site together with such documents as may be required by the Engineer for the purpose
of valuation of the materials and providing evidence of ownership and payment thereof.
e) Ownership of such materials shall be deemed to vest in the Employer, and
f) The sum payable for such materials, secured advance loans on site shall not
exceed 75 per cent of the
i) extactory, exwarahouse price of locally manufactured materials or
ii) Stockpile value of locally produced materials such as Bricks, sand
Aggregates and crushed metal. (7) CONDITIONS FOR MATERIALS ISSUED UNDER SCHEDULE 'A'
The issue of material by the Department under Schedule 'A' of this contract will
be subject to interalia the following conditions:-
1. All the materials shall be made available for delivery on working day only during working
hours to be arranged mutually by the contractor between himself and the Storekeeper or
the University Engineers, who so ever shall issue the same. The material shall be made
available at the place of delivery mentioned in Schedule 'A' of the tender.
2. The contractor shall be submit periodically as well as on completion of work, an
account of all materials issued to him in a manner as directed by Engineer-in-
charge. The contractor shall also furnish an account of previous materials issued
before placing demand for further materials. In additions, a separate register
shall be maintained on site for recording daily item-wise cement consumption of
cement issued under Schedule 'A' as directed. This shall be signed daily by
contractor or his representative and representative of Engineer-in-charge.
3. The quantities in Schedule 'A' are approximate and may vary according to actual
and bonafide use as certified by the Engineer-in-charge.
4. All the materials mentioned in schedule 'A' required for the works shall be taken
from the Department only. The materials from other source in lieu of the materials in
Schedule 'A' shall not be allowed except under written permission from the
University Engineer. In such case, certificate for its quality shall be produced by the
contractor and samples of such materials shall be tested from any Government
Laboratory by the contractor at his own cost and the test results be supplied to the
Department. The materials not conforming to the required standard shall be
removed at once from the site of the work by the contractor at his own cost.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 75 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
5. The rates mentioned in Schedule 'A' are inclusive of Sales Tax and storage charges.
6. After issue of any material for use on bonafide Government work to contractor if
the Engineer-in-charge ascertains on any particular date that the portion of such
supplies becomes surplus to the requirement of the work, the date of
ascertainment will be taken as the date for sale for the purpose of payment of
sales tax on such portion and recovered from the contractor as per rules.
7. The contractor shall construct shed/sheds as per direction of the Engineer-in-charge of
the work for storing the materials issued to him by the Department and provide double
locking arrangements, one lock shall be with incharge of Departmental person and
materials shall be taken for use in presence of the Departmental persons only.
8. The contractor shall make his own arrangement for the safe custody of the
materials which are supplied to him by the Department.
9. The contractor shall not use cement and other material under Schedule 'A' in items
other than as per this tender except for such ancillary small items as are connected with
the absolutely necessary for execution of this work as may be decided by the Engineer.
10. All steel issued under Schedule 'A' which remains surplus with the contractor after use
in the work, shall be returned to the Department. Generally, only full length bars in
lengths supplied by the Department shall be taken back by the Department. However,
the Engineer-in-charge may at his discretion, take back bars of particular diameter in
any other lengths approved by him, if same are required for use in Government work,
The rates for repayment of the surplus acceptable materials returned by the contract at
trie godown of issue, shall be at the prevailing market rates or the rates charged to the
contactor, excluding the element of storage charges or issue rates excluding the
element of storage charges at the time of return, whichever is lower. The quantity of
such surplus steel as is not acceptable to the Department may be disposed of by the
Contractor in any manner he likes and the cost thereof shall entirely be borne by the
contractor. However in case in which the materials issued to a contractor become
surplus owing to change in the design of the work after materials were issued to the
contractor the materials should be taken back from the contractor at the same rate, at
which they were supplies to him by Government provided the materials at the time of
taking over, were not actually needed and are serviceable.
11. Mild steel, Tor steel bars shall be issued to the contractor either in coils or
straight, on actual weighment, However, for the purpose of payment, the weight
of steel bars used on the work shall be calculated on the basis of standard
weight per unit length vide table in B-10, 13 of Standard Specification Book
1972, edition by B. and fc. Department. Hence claims on account of difference in
actual weight and calculated on the basis of standard weight per unit length shall
not be entertained. No extra payment for straightening the bars will be made.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 76 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
12. The contractor shall make his own arrangement for securing structural steel
such as square bars, flats, rolled steels, joints, angles, iron, plates, etc. The
department is neither responsible for securing permit nor to supply required
structural steel. However, necessary certificate to the effect that the materials is
required for the said bonafide Government work, will be issued of required.
13. The charges for conveyance of materials from the place of delivery to the site of
work and the actual spot on work site shall be entirely borne by the contractor.
No claims on this account shall be entertained.
14. If surplus materials after completion of the work are not returned by the contractor,
recovery of such materials at the penal rates of twice the issue rate of these materials
shall be made from the conotractor. Sales Tax and General Tax on the cost of surplus
materials which are not returned, shall be recovered from the contractors as decided by
the University Engineer. However, it is clear that any surplus materials returned is in
unserviceable or damaged dconditions, the same will not be accepted. In such case the
cost will be recovered from the contractor as stated above in the clause.
15. Empty asphalt drums will have to be returned to the Department jn case of non-
return of empty asphalt drums, recovery at Rs.200/- (two hundred) per drum will
be charges to the contractor.
16. The person/firm submitting the tenders should see that the rates in the above
schedule 'A' are filled-up by the University Engineer-lncharge of the work on the
issue of the form prior to the submission of the tender.
17. The University shall not be responsible for the loss in cement during transit from
M.P.K.V. stores to worfc site. Cement so delivered to the contractor at the M.P.K.V.
stores shall mean 50% / per bag by weight. The rate quoted should correspond to
this method of reckoning. The correction will have to be done by weight basis. While
mixing, if cement is found short in a bag, it will have to be made good by the
contractor for which additional cement would be supplied by the Department at
issue rate in Schedule 'A'. Item or percentage rate quoted for schedule reckon this.
18. For the purpose of issue rate, the area of a A.C. sheets and ridges shall be the
actual gross size before laying in the roof and each dimension shall be measured at
straight line in plain (neglecting extra length, due to corrugations etc.)
19. The contractor shall furnish unstamped receipts for all materials issued under Schedule 'A'.
20. The contractor shall furnish the account of steel cement etc. issued to him at each time
before placing an ident for further supply. Also he should submit on completion of the
work final account of all the materials supplied to him by the Department. His account
will be scrutinized by the Engineer-in-charge, and if any extra use of found, shortages
are seen, and any quantity of material remained unaccounted for, recovery at penal
rates will be affected for such quantities as mentioned in Clause 14 above.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 77 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
21. A separate register shall be maintained on site for recording detailed item wise
cement and steel consumption on the work. This register shall be signed by the
contractor or his authorized representative and got signed from the
representative of the Engineer-in-charge.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 78 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
ACCOMPANIMENT TO THE GOVERNMENT RESOLUTION, PUBLIC WORKS DEPARTMENT NO. BDG 1091/CR-172/Bldg.2/, DATED 10-1-92
PRICE VARIATION CLAUSE
1. If during the Operative Period of the contract as defined in condition (i) below, there shall be any variation in the Customer Price Index (New Series) for Industrial workers for ___________________ centre as per the Labour Gazette published by the Commissioner of Labour, Government of Maharashtra and/ Industry, Government of India, as compared to the respective figure therefore, on the date of 30 days before the last date prescribed for receipt of tender and/or in the price of Petrol/Oil and lubricants, then subject to the other conditions mentioned below, price adjustment on account of (i) Labour component (ii) Material component and {iii} POL components, which respectively are ________%________% and ___________% of the total cost of work put to tender, calculated as per the formula hereinafter appearing, shall be made, {total of all these three components will be 100).
A) Formula for Labour Component
V1=0.85 (P-cost of Schedule 'a' materials used) X {K1/100 x CI-CO/CO}
Where
V1 =Amount of price variation in Rupees to be allowed.
P= Cost of work done during the period under consideration.
K1=Percentage of Labour Component as indicated above.
C0= Basic Consumer Price Index for......... Centre Ascertained as above on the date 30 days Preceding the last date prescribed for Receipt of tender.
C1= Average Consumer Price Index for ....... Centre ascertained as above during the period under
consideration,
(B) Formula for Materials component:
V2 =0.85 (P-Cost of Schedule 'a' materials used) X {K2/100 X II-IO/PO}
where=
V2=Amount of Price variation in Rupees to be allowed.
P= Cost or work done during the period under consideration.
K2= Percentage of Materials Component as indicated above. IO= Basic Wholesale Price Index ascertained as above on the date 30 days preceding the last date prescribed for receipt of tender.
I1- Average Wholesale Price Index ascertained as above during the period under consideration.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 79 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
C) Formula for Petrol Oil and Lubricant component: V3=0.85 (P-cost of Schedule 'a'
material used) X {K3/100 x P1-PO/PO}
Where
V3=AmoLint of price variation in Rupees to be allowed.
P= Cost of work done during the period under consideration.
K3= Percentage of petrol, oil and lubricant component, as indicated above.
P1= Average Price of H.S.D. for Bombay during the period under consideration.
PO= Average price of H.S.D. for Bombay on the date 30 days preceding the last date prescribed for receipt of tender.
II. Conditions referred to In Paragraph-1
I. The Operative Period of the contract shall mean the period commencing from the date of the
work order issued to the Contractor and ending on the date when the time allowed for the
work specified in the Memorandum under Tender for work expires taking into consideration
the extension of time, if any , for completion of the work granted by Engineer-in-charge
under the relevant clause of the conditions of contract in cases other than those where such
extension in necessitated on account of default of the contractor. The decision of the
Engineer-in-charge as regards the Operative Period of the contract shall be final and binding
on the contractor. Where compensation for liquidated damages is levied on the contractor on
account of delay in completion or inadequate progress under the relevant contract
provisions, the escalation amount for the balance work from the date of levy of such
compensation shall be worked out by pegging the indices, C-1, 1-1 and P-1 to levels
corresponding to the date of from which such compensation is levied.
II. This price variation clause shall be applicable to all contracts in B-1 , B-2 and C
forms but shall not apply for piece works.
III. Price variation shall be calculated in accordance with the formula mentioned
above, separately for labour, material and POL components.
IV. The price variation under this clause shall not be payable for the extra items required to be
executed during the completion of the work and also on the excdss quantities payable under
the provisions of Clause 38/37 of the contract of B1/B2 respectively, since the rates payable
for the extra items or the extra quantities under Clause 38/37 are to be fixed as per the
current DSR or as mutually agreed to subject to yearly revision till completion of such work.
In other words, when the completion/ execution of extra items as well as extra quantities
under clause 38/37 of the contract from B-1 / 62 extends beyond the operative date of the
then DSR, the rates payable for the same beyond that date shall be revised with reference
to he next current DSR prevalent at that time on year to year basis or
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 80 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
revised in accordance with mutual agreement thereon, as provided for in the
contract, whichever is less.
V. This clause is operative both ways, i.e. , if the price variation in the said Wholesale
Price Index for all commodities, Consumer Price Index {New Series) or price of HSD
for is on the plus side, payment on account of the price variation shall be allowed to
the Contractor and if it is on the negative side, the Government shall be entitled to
recover the amount from the contractor and the amount shall be deductible from the
contractors bill for the respective period in which there are fluctuations.
PRICE VARIATION CLAUSE If during the operative period of the contract as defined in condition (i) below there shall
be any variation in the Consumer Price Indeed (New series) for Industrial workers for
Nashik Central as per, the labour Gazette published by the Commissioner of Labour,
Government of Maharashtra and/ or in the whole sale price Index for all commodities
prepared by the office of Economic Advisor. Ministry of Industry Govt. of India, as
compared to the respective figures therefore on the date 30 days before the last date
prescribed for receipt of tenders and / or in the price of Petrol/ Oil and Lubricants, then
subject to the other conditions mentioned below, price adjustment of account of (i) Labour Components : PL 13.66 % (ii) Cement Components: PC 12.54% (iii) Steel Components : Ps 29.52%(iv) Bitumen Components : Pb - NIL % (v) Fuel & Lubricant Components : P1 3.00 % (vi) Other materials components : pm 41.28 %
Calculated as per the formula hereinafter appearing shall be made. (Total of tall these components will within 100)
Price Adjustment - Contract price shall be adjusted for increase or decrease in rates
and price of Labour, Material fuel and Lubricants in accordance with the following
principles and procedures and as per formula given in the contract data.
The cost of materials supplied by the Employer, if any at fixed prices shall be excluded
from the scope of price adjustment.
Price adjustment shall apply for the work done from the date given in the contract data
upto the end of the initial intended completion date or extensions granted by the
employer and shall not apply to the work carried out beyond the stipulated time for
reasons attributable to the contractor.
The price adjustment shall be determined during each quarter from the formula given in
the contract data.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 81 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Following expressions and meanings are assigned to the work done during each
quarter. R= Total value of work done during the quarter excluding cost of the Employer
at fixed prices, it would include the value of materials on which secured advances has
been granted. If any, during the quarter less the value of material in respect of which
secured advance has been recovered, if any during the quarter. To the extent that full compensation for any rise of fall costs to the contractor is not covered by the
provisions of this or other clauses in the contract, that unit rates and prices included is the contract
shall be deemed to include amounts to cover the contingency of such other rise of fall in costs. Adjustment for Labour Components
Price adjustment for increase of decrease in the cost due to labour shall be paid in
accordance with the following formula:- VL = 0.85xP1/100xRx(LI-LO)/Lo
VL = Increase or decrease in the cost of work during the quarter under consideration
due to changes in rates for local labour.
Lo = The average consumer price index for industrial workers for Nashik centre for
quarter proceeding the date of opening of bids as published by Labour. PI = The average consumer price index for industrial workers for NASHIK centre for the quarter
under consideration as published by Labour Bureau, Ministry of Labour Government of India.
PL = Percentage of Labour components of work.
Adjustment for cement components Price adjustment for increase or decrease in the cost of cement procured by the contractor shall be paid in accordance with the following formula :-
Vc = 0,85xpc/1 OOxRx(ci-co)/co
Vc = Increase or decrease in the cost of work during the quarter under
consideration due to changes in the rates for cement
Co = The all India average wholesable price index for cement for the quarter
preceding the date of opening of bids as published by the Ministry of
Industrial Government of India New Delhi
Ci = The all India average wholesale price Index for cement for the quarter
under consideration as published my Ministry of Industrial Development,
Government of India, New Delhi.
PC = Percentage of cement components of the work
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 82 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Adjustment for Steel component
Price adjustment for increase or decrease in the cost of steel procured by the contractor shall be paid in accordance with the following formula:-
Vs = 85xps/100xRx(si-so)/so
Vs = Increase or decrease in the cost of work during the quarter under consideration due to changes in the rates for steet.
So = The all India average wholesale price index for steel (Bars and Rods) for the quarter preceding the date of opening of bids as published by the Ministry of Industrial Development New Delhi
Si = The all India average wholesale price Index for Steel {Bars and Rods) for the quarter under consideration as published by Ministry of Industrial Development New Delhi
Ps = Percentage of steel components of the work.
Note:- For the application of this clause, Index of Bars and Rods has been chosen to represent group.
Adjustment for bitumen component
Price adjustment for increase or decrease in the cost of bitumen shall be paid in accordance with thy following formula:
Vb = 0.85xpb/100xRx (Bi-Bo)/Bo
Vb = Increase or decrease in the cost of work during the quarter under consideration due to changes in the rates for bitumen.
Bo = The average official retail price of bitumen at the IOC depot at Mumbai on the day 30 days prior to date of opening bids.
Bi = The average official retail price of bitumen of IOC depot at Mumbai for
the 15tM
day of the middle calenderer of the quarter under consideration.
Pb = Percentage of bitumen components of the work.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 83 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Adjustment for Fuel and lubricant Component
Vs = 85xps/100xRx(si-so)/so
Vs = Increase or decrease in the cost of work during the quarter under
consideration due to changes in the rates for steel.
So = The all India average wholesale price index for steel (Bars and Rods) for the quarter preceding the date of opening of bids as published by the Ministry of Industrial Development New Delhi
Si = The all India average wholesale price Index for Steel {Bars and Rods) for the quarter under consideration as published by Ministry of Industrial Development New Delhi.
Ps = Percentage of steel components of the work.
Note:- For the application of this clause, Index of Bars and Rods has been chosen to represent group.
Adjustment for bitumen component
Price adjustment for increase or decrease in the cost of bitumen shall be paid in accordance with thy following formula:-
Vb = 0.85xpb/100xRx (Bi-Bo)/Bo
Vb = Increase or decrease in the cost of work during the quarter under consideration due to changes in the rates for bitumen
Bo = The average official retail price of bitumen at the IOC depot at Mumbai on the day 30 days prior to date of opening bids.
Bi = The average official retail price of bitumen of IOC depot at Mumbai for
the 15tM
day of the middle calenderer of the quarter under consideration.
Pb = Percentage of bitumen components of the work.
Adjustment for Fuel and lubricant Component
Price adjustment for increase or decrease in the cost of POL (fuel and lubricant) shall be paid in accordance with the following formula:-
Vf = 0.85xof/1QOxRx (Fi-Fo) / Fo
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 84 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Vf = Increase or decrease in the cost of work during the quarter under consideration due to changes in the rates for fuel and lubricants
Vf = Increase or decrease in the cost of work during the quarter under consideration due to changes in the rates for fuel and lubricants.
Fo = The average official retail price of High Speed Diesel (HSD) at the existing consumer pumps of IOC at MUMBAI on the day thirty days prior to the date of opening of bids
Fi = The average official retail price of High Speed Diesel (HSD) at the existing consumer pumps of IOC at MUMBAI for the 15"
1 day of the
middle calendar month of the quarter consideration.
Pf = Percentage of fuel and lubricant components of the work.
Note :- For the application of this clause the price of High Speed diesel Oil has been chosen to represent fuel and lubricant group.
Adjustment for Other materials component
Vi = Price of adjustment for increase or decrease in the cost of local materials other than cement steel bitumen and POL procured by the contract shall be
paid1 in accordance with the following formula:-
Vm = 0.85xpm / 100x R x (Mi - Mo ) / Mo
Vm = Increase or decrease in the cost of work during the quarter under consideration due to changes in rates For local materials other than cement steel, bitumen and POL
Mo = The all India average wholesale price index (all commodities) for the quarter preceding the date of opening of bids, as published by the Ministry of Industrial Development, Govt. of India, New Delhi.
Mi = The all India average wholesale price Index (all commodities) for the quarter under consideration as published by Ministry of Industrial Development, New Delhi
Pm = Percentage of local material components (Other than cement, Steel,
Bitumen and POL) of the work.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 85 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
A) Additional General Conditions and specifications
SR. NO. C O N T E N T S PAGE NO.
1. General 88
2. Contractor to Study site conditions 88
3. Declaration of Contractor 88
4. Indemnity 88
5. Definition 89 to 91
6. Errors, Omissions and discrepancies 92
7. Working method and progress schedule 93 to 95
8. Agent and work order book 96
9. Setting Out 96
10. Levelling instruments 96
11. Authority of representative of Engineer-in-charge 96
12. Co-Ordination 97
13. Assistance in procuring Priorities / permits etc. 97
14. Quarries 99 to 101
15. Collection of Materials 101
16. Site Office 102
17. Treasure-Trove 102
18. Patented Device 103
19. Explosive 103
20. Damage By Floor for accident 103
21. Police Protection 103
22. Traffic Regulations 103
23. Inspections & Supervision 104
24. Initial Measurements 104
25. Samples & Testing of Materials 104
26. Change in cement contains etc. 106
27. Cement Concrete / form work for concrete 107 to 109
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 86 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
SR. NO. C O N T E N T S PAGE NO.
28. Miscellaneous 110 to 112
29. Medical and sanitary arrangement for labour 113
30. Safety Code 114 to 116
31. Scope of Rates for different items of work 117
32. Payments 118
33. Handing over of work 118
34. Claims 118
35. Quality Assurance & Maintenance 118
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 87 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
ADDITIONAL GENERAL CONDITIONS AND SPECIFICATIONS:-
1) These are to apply as additional condition and specifications unless
otherwise already provided for contradictorily elsewhere in this contract.
2) CONTRACTOR TO STUDY SITE CONDITIONS:
The contractor shall be deemed to have carefully examined the work and side conditions
including labour, the general and the special conditions, specifications, schedules and
drawings and shall be deemed to have visited the site of the work and to have fully
informed himself regarding the local conditions and carried out his own investigations to
arrive at rates quoted in the tender. In this regard, he will be given necessary information
to the best of knowledge of department but without any guarantee about it. If he shall have
any doubt as to the meaning of any portions of these general conditions or the special
conditions, the scope of work of the specifications and drawings, or any other matter
concerning the contradict he shall in good time, before submitting his tender, set forth the
particulars thereof and submit them to the University Engineer M.P.K.V. Rahuri in writing in
order that such doubts may be clarified authoritatively before tendering once a tender is
submitted, the matter will be decided according to tender conditions in the absence of such
authentic pre clarification.
3) DECLARATION OF THE CONTRACTOR: The contractor should sign the declaration from on page 14
4) INDEMNITY:
The contractor shall indemnify the Government against all actions, suits, claims and
demands brought or made against him in respect of anything done or committed to be
done by the contractor in execution of or in connection with the work of this contract
and against any loss or damage to the Government in consequence of any action or
suit being brought against the contractor for anything done or committee to be done in
the execution of the works of this contract.
5) DEFINITIONS:
Unless excluded by or repugnant to the context.
a) The expression "M.P.K.V." as used in the lender papers shall mean the
Mahatma Phule Krishi Vidyapeeth, Rahuri, Dist. A'nagar. b) The expression "Engineer" or "Engineer-in-charge" as used in the tender papers
shall mean the University Engineer-in-charge of the work for the time being.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 88 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
c) The expression "Contractor" used in the tender papers shall mean the
successful renderer whose tender has been accepted and who has been
authorized to proceed with the work. d) The expression "Contract" as used in tender papers shall mean the deed of
contract together with its original accompaniments and those later
incorporated in it by mutual consent. e) The expression "Plant" as used in the tender papers shall mean every temporary and
necessary means necessary or considered necessary by the Engineer to execute,
construct, complete and maintain the works and used in, altered, modified, substituted
and additional work ordered in the time and the manner herein provided and all
temporary materials and special and other articles of appliances of every sort, kind
and description what - so- ever intended or used thereof. f) "Drawing" shall mean the drawings referred to in the specification and any modification
or such drawings approved in writing by Engineer and such other drawings as may
from time to time the furnished or approved in writing by the Engineer. g) "Engineer's representative" shall man an assistant of the Engineer notified in
writing to the contractor by the Engineer. h) Provisional sum or "Provisional lump sum" shall mean a lump sum included by
M.P.K.V. in tender documents and shall represent the estimated value of work
for which details are not available at the time of issue of tender. i) "Provisional items" shall mean items for which approximate quantities have
been included in the lender documents. j) The "Site" shall means the lands and/or other places, on under in or through which
the work is to be executed under the contract including any other lands or places
which may be allotted by M.P.K.V. or used for the purpose of contract. k) The "Work" shall mean the works to be executed in accordance with the contract or part
(s) thereof as the case may be and shall include all extra or additional, altered
or substituted works as required for performance of the contract. l) The "Contract sum" shall mean the sum for which the tender is accepted. m) The "Accepting Authority" shall mean the officer competent to accept the tender. n) The "Day" shall mean a day of 24 hours from midnight to midnight irrespective
of the number of hours worked in any day in that week. o) "Temporary works" shall mean all temporary works of every kind required in or
about the execution, completion, or maintenance of the works. p) "Urgent works" shall mean any measure which, in the opinion of the Engineer-in-charge,
become necessary during the progress of the work or the persons working, thereon.
Where the context so requires, words importing the singular only also include the plural
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 89 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
and vice-versa.
Heading and marginal notes, if any, to the general conditions shall not be
deemed to from pan thereof or be taken into consideration in the interpretation
or construction thereof the contract. Wherever there is mention of "Schedule of
rates" of the Division or simply D.S.R. in this tender, it will be taken to means
as "the Schedule of the rate of the Division in whose jurisdiction the work lies".
a) University Engineer" means the University Engineer of the Mahatma
Phule Krishi Vidyapeeth Rahuri or his representative. b) "Architect" means every partner of the firm appointed for the works or in the
event of their ceasing to be Architect for the work such other firm or person as
may be appointed by the University, as Architect of this work.
The Architect so appointed is required to obtain all necessary permissions viz.
N.A. permission, commencement certificate, completion certificate, certificate
from all departments of Municipal Corporation required for it's lawful execution/
Occupation of the work / building in question.
The contractor shall allow the Architect to inspect the works who will give directives to
the Contractor through the University Engineer or his representative at the site during
the progress of work to observe rules and regulations of the local authorities. c) "Comptroller" Means the Comptroller of the Mahatma Phule Krishi Vidyapeeth, Rahuri.
d) "Contractor" means the person or persons, firm or company whose tender has
been accepted by Mahatma Phule Krishi Vidyapeeth and includes the
contractor's personal representative, successors and permitted assigns. e) "Contract price" means the sum name in the tender subject to such additions thereto
or deductions therefrom as may be made in the provisions hereinafter contained. f) "Contract Plant" means all appliances or things of whatsoever required in or
about the execution plant or maintenance of works or temporary works (as
hereinafter defined) but does not include materials or other things intended to
for or forming part of the permanent work. g) Services of notice in writing or "Written Notice" means notice of a communication in
writing, typed or printed character sent to the last known private or business address or
registered office to which in the ordinary course of post it would have been delivered. h) "Virtual Completion" means that the completion as in the opinion of the University
is fit for occupation in every respect including removal and scaffolding plant,
surplus materials and rubbish and cleaning of dirt from works and site. i) "Works" means all the works defined by Bill of quantities, drawings, specifications, and
such other works as the contractor may be entrusted with for executing with the contract. j) "Act insolvency" means any of insolvency as defined by the Maharashtra
insolvency Act or any amending Statute.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 90 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
k) "Site Order Book" means the order book which shall be maintained by the contractor
at the site of the work in which instruction shall be given to the contractor by the
university as and when necessary. These orders shall have to be assigned and
complied by the contractor and nothing else will be written on it, if the contractor wants
to represent anything relating thereto, he can do so by separate letter.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 91 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
6) ERRORS, OMISSIONS AND DISCREPANCIES:
a) In case of errors, omissions and / or dis-agreement between written an scaled
dimensions on the drawing or between drawings and specifications etc. the
following order of preference shall apply,
i) Between actual called and written dimensions or descriptions on a drawing the
letter shall be adopted ii) Between the written or shown description of dimensions in the drawing and
corresponding one in the specifications, the later shall apply. iii) Between the quantities shown in schedule of quantities and those arrived at
from the drawings, the later shall be preferred.
b) In case of discrepancy between percentage rate quoted in figures and words,
the lowest of the two will be considered for acceptance of tender. c) In all cases of omission and/or doubts of discrepancies in the dimension or
description of the item or specifications, a reference shall be made to the
University Engineer M.P.K.V. Rahuri whose elucidation, elaboration or decision
shall be considered as authentic. The contractor shall be held responsible for any
errors that may occur in the work through lack of such reference and precaution. d) The special provision in detailed specifications and wording of any item shall gain
precedence over corresponding contradictory provision (if any) in the Standard
Specifications of Public Works Department Hand Book where reference to such
specifications is given without reproducing the details in contract.
7.1 PROGRAMME OF WORK
The work is requiring to be completed within a period of Eighteen months (including the
monsoon period.)
7.2 (A) METHODOLOGY OF CONSTRUCTION AND CONSTRUCTION EQUIPMENTS: Contractor shall furnish at least 15 days in advance his programme of commencement of item or
work, the details of actual methods that would be adopted by contractor for the execution of various
items of work such a well sinking, cas-in-situ, super structure for Bridge work and Earth work,
W.B.M. Black topping items etc. for Road works supported by necessary detailed drawing and
sketches Including those of the plant an Machinery that would be used their locations, arrangement
for conveying and handling materials etc. and obtain prior approval of the Engineer-in-charge
reserves the right to suggest modifications or make complete changes in the method proposed by
the contractor, whether accepted previously or not at any stage of the work,
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 92 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
to obtain the desired accuracy, quantity and progress of the work which shall be bining on
the contractor, and no claim on account of such change in method of execution will be
entertained by M.P.K.V. so long as specifications of the item remain unaltered. The side
responsibility for the safety and adequacy of the methods adopted by the contractor, will
however, rest on the contractor irrespective of any approval given by the Engineer.
In case of slippage from the approved work programme at any stage, the contractor
shall furnish revised programme to make up the slippage within the stipulate Time
schedule an obtain the approval of the engineer to the revised programme.
(b) CONSTRUCTION EQUIPMENT: The contractor shall be required to give a trial run of the equipments for establishing their capability
to achieve the laid down specifications and tolerance to the satisfaction of the Engineer before
commencement of the work. All equipment provided shall be of proven efficiency and shall be
operated and maintained at all times, in a manner acceptable to the Engineer and no equipment or
personnel will be removed from site without permission of the Engineer.
(c) PROGRESS SCHEDULE: The contractor shall furnish within the period of one month of the order to start the work, the
programme of work in CPM/PERT charts in quadruplicate indicating the date of actual start, the
monthly/progress expected to be achieved an the anticipated completion date of each major item of
work to be done by him, also indications dates of procurement and setting up of materials, plant and
machinery. The schedule is to be such as is practicable of achievement towards the completion of
whole work in the time limit, the particulars items, if any, on the due dates specified in the contract
and shall have the approval of the Engineer-in-charge. No revised schedules hall be operative
without such acceptance in writing. The Engineer is further empowered to ask for more detailed
schedule or schedules say; week by week for any item to items, in case of urgency of work as will
be directed by him and the contractor shall supply the same as and when asked for.
The contractor shall furnish sufficient plant, equipment an labour as may be necessary
to maintain the progress of schedule. The working and shift hours restricted to one shift a day
for operations to be done under the Government supervision shall be such may be approved by
the Engineer-in-charge. They shall not be varied without the prior approval of the Engineer.
Night work which requires supervision shall not be permitted except when specifically allowed
by Engineer each time if required by the contractor. The contractor shall provide necessary
lighting arrangements etc. for night work as directed by Engineer without extra cost.
Further, the contractor shall submit the progress report of work in prescribed from and
charts etc. at periodical intervals, as may be specified by the Engineer-in-charge.
Schedule shall be in the form of progress charts, forms, progress statement and / or
reports a's may be approved by the Engineer.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 93 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
The contractor shall maintain proforma charts; details regarding machinery, equipment,
labour, materials, personnel etc. as may be specified by the Engineer and submit
periodical returns thereof as may be specified by the Engineer-in-charge.
AGENT AND WORK ORDER BOOKS: The contractor shall himself manage the work or engage an authorized all time agent on the
work capable of managing and guiding the work and understanding the specifications and
contract conditions. A qualified and experienced, engineer shall be provided by the contractor
as his agent for technical matters in case the Engineer-in-charge considers this is essential for
the work and directs contractors. He will take orders as well be given by the University
Engineer or his representative and shall be responsible for carrying them out. This agent shall
not be changed without prior intimation to the University Engineer and his representative on the
work site. The contractor shall supply to the Engineer the details of all supervisory and other
staff employed by the contractor and notify changes when made and satisfy the Engineer
regarding the quantity and sufficiency of the staff, thus employed. The Engineer will have the
unquestionable right to ask for changes in the quality and number of contractor's supervisory
staff and to order removal from work of any of such staff. The contractor shall comply with such
others and effect replacements to the satisfaction of the Engineer. A work order book shall be maintained on site it shall be the property of M.P.K.V. and the contractor
shall promptly sign orders given therein by the Executive Engineer or his representing and his
superior officers and comply with them. The compliance shall be reported by the contractor to the
Engineer in good time so that it can be checked. The blank work order book with machine numbered
pages will be provided by the department free of charges for this purpose. The contractor will be
allowed to copy out instructions therein from time to time. __________
(9) SETTING OUT (I) ROAD WORKS:
9.1 The contractor shall establish working bench marks in the area soon after taking
possession of the site. The reference Bench mark for the area shall be as indicated
in the Contract Documents. The working bench marks/ shall be at the rate of four
per KM and also at or near all drainage structures, over bridge and underpasses.
The working bench marks/ levels should be got approved from the engineer.
Checks must be made on these bench marks one every month and adjustment if
any got agreed with the Engineer and recorded. An upto date record of all bench
marks including approved adjustment, if any shall be maintained by the contractor
and also a copy supplied to the Engineer for his record. 9.2 The lines and levels of formation, side slopes, drainage, carriageways and
shoulders shall be carefully set out and frequently checked, care being taken to
ensure that correct gradients and cross sections are everywhere obtained.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 94 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
9.3 In order to facilitate the setting out of the works, the centre line of the carriageway or
highway must be accuracy established by the contractor and approved by the Engineer. It
must then be accurately referenced in a manner satisfactory to the Engineer every 50 m.
intervals in plain and rolling terrain and 20 m. intervals in hilly terrain and in all curve points
as directed by the Engineer, with marker pegs chainages boards set in or near the fence
line, and a schedule of reference dimensions shall be prepared and supplied by the
contractor to the engineer. These markers shall be maintained until the works reach
finished formation level and are accepted by the Engineer.
9.4 On construction reaching the formation level stage the center lines shall again
be set out by the Contractor an when approved by the Engineer shall be a
accurately referenced in a manner satisfactory to the Engineer by marker pages
set at the outer limits of the formation. 9.5 No reference page of market shall be moved or withdrawn without the approval
of the Engineer and no earthwork or structural work shall be commenced until
the centre line has been referenced. 9.6 The contractor will be the sold responsible party for safeguarding all survey monuments,
bench marks, beacons etc. the Engineer will prove the Contractor with the data necessary
for the setting out of the center lineall dimensions and levels shown on the drawings or
mentioned in document forming part of or issued under the contract shall be verified by the
contractor on the site and he shall immediately inform the Engineer of any appearant errors
of (discrepancies) in such dimensions or levels. The contractor shall after or in connection
with the setting gut of the centre line, survey the terrain along the road and the centre line
and cross sections at intervals as required by the Engineer.
9.7 After obtaining approval of the Engineer, work on earthwork can commence and the profile
and the cross sections shall from the basis for measurements and payment. The contractor
is responsible for checking that all the basic traverse points are in place at the
commencement of the contract and if any are mission or appear to have been disturbed,
the Contractor shall make rearrangements in reestablish these points A "Survey File"
containing the necessary data will be made available purpose design notification of the
centerline or grade are advisable the Engineer will issue detailed instructions to
the contractor and the contractor shall perform the modifications in the field, as
required and modify the ground levels on the cross sections accordingly as
many times as required. There will be no separate payment for any survey work
performed by the Contractor. The cost of these services shall be considered as
being included in the cost of the iterrfe of the work in the bill of Quantities. 9.8 The work of setting out shall be deemed to be a part of general works preparatory to
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 95 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
the execution of the work and no separate payment shall be made for the same.
II) SETTING OUT FOR (BRIDGE WORKS):
Immediately on receipt of the work order, the Contractor shall at his own expense
clean the site and take up a provisional and final setting out an lining out of the
work under the supervision of his responsible representatives and shall provided
necessary material labour, toots instruments etc. required for the same.
One tentative abutment location will be indicated by Engineer-in-charge and the centre line
of the bridge shall be defined by him. The contractor will then have to fix up the location of
the other abutment. The abutment location will then be verified by the Department and may
be adjusted. Once the final location of the abutment is so finalized it will be the contractor’s
responsibility to line out and locate the remaining foundations.
The contractor shall be responsible for true and proper setting out of the works and for
the corrections of the positions, level dimensions and agreement of all the parts of
works, and for providing all necessary instruments appliance and labours in connection
therewith at his own cost. Officers may assist the Contractor in proper setting out
Government instruments may be allowed to be used for setting out of the work for
which no cost shall be recovered from the contractor. If at any time furnishing the
progress of work. Any error arise in regard to leaves or dimensions or alignment of any
part of the work rectification thereof on being required to do so will be carried out by the
contractor at his own cost, unless such errors are based on in correct data, supplied in
writing by the Engineer or his authorized representative in which case the expense of
the rectification shall be refunded by M.P.K.V.
The checking of any setting out or checking levels by the Engineer or his authorised
representative shall not in any way relieve the contractors of his responsibility for the
correctness thereof. The contractor shall carefully protect and preserve all bench marks
site rails, pegs another things used in setting out of works.
SETTING OUT FOR (BUILDING WORKS)
The Engineer-in-charge shall furnish the contractor with only the four corners of
the work site and a level bench mark and the contractor shall set out the works
and shall provide an efficient staff for the purpose and shall be solely
responsible for the accuracy of such setting out.
The Contractor shall provide fix and be responsible for the maintenance of all stacks,
templates, level marks profiles and other similar things and shall take all necessary
precautions to prevent their removal or disturbance and shall be responsible for the
consequence of such removal or disturbances should be the same take place and for
their efficient and timely re installment. The contractor shall also be responsible for the
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 96 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
maintenance of all existing survey marks boundary marks, distance marks and centre
line marks, either existing or supplied and fixed by the contractor. The work shall be set
out the satisfaction of Engineer-in-charge. The approval therefore or joining with the
Contractor by the Engineer-in-charge in setting out the work shall out relieve
the contractor or joining with the contractor by the Engineer-in-charge in setting
out the work, shall out relieve the contractor of any of his responsibilities.
Before beginning the work, the contractor shall at his own cost provide all necessary
reference and level posts, pegs, bamboos, flags, ranging rods, strings and other materials
for proper layout of the work in accordance with the scheme for bearing marks acceptable
to the Engineer-in-charge. The centre, longitudinal or face lines and cross line shall be
marked by means of small masonry pillars. Each pillar shall have distinct mark at the centre
to enable theodolite to be set over it. No work shall be started until all these points are
checked and approved by the Engineer-in-charge in writing but such
• Approval shall not relieve the contractor of any of his responsibilities. The
contractor shall also provides all labour, material and other facilities, as necessary
for the proper chocking of layout and inspection of the points during construction.
Pillar bearing geodetic marks located at the site of units of works under the
construction should be protected and fenced by the contractor.
On complication of works, the contractor must submit the geodetic documents according to which the works was carried out.
RESPONSIBILITIES FOR LEVEL AND ALIGNMENT:
The contractor shall be entirely and exclusively responsible for the horizontal
and vertical alignment, the levels and correctness of every part of the work and
shall rectify effectually any errors or imperfections therein; such rectifications
shall be carried out by the contractor at his own cost, when instructions are
issued to that effect by the Engineer-in-charge.
10) LEVELING INSTRUMENTS:
If measurements of items of the work are based on volumetric measurements
calculated from levels taken before and after constructions of the item, a large
number of leveling stays tapes etc. will have to be kept available by the Contractor
at the site of work for this purpose. Lack of such leveling staves; tapes etc. in
required numbers may cause delay in measurements and the work. The contractor
will have therefore to keep sufficient number of these readily available at site. 11) AUTHORITIES OF THE ENGINEER IN CHARGE'S REPRESENTATIVE:
The duties of the representative of the Engineer-in-charge to watch and supervise the
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 97 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
work and to test and examine any material to be used or workmanship
employed in connection with the works.
The Engineer-in-charge may from time to time, in writing delegate to his
representative any powers and authorities vested in the Engineer-in-charge and
shall furnish to the contractor a copy of all such delegations of power and
authorities, Any written instructions of approval given by the representative of
the Engineer-in-charge to the contractor within the terms of such delegations
(but not otherwise) shall bind the contractor and the department as through it
had been given by the Engineer-in-charge, provided always as follows.
Failure of the representative of the Engineer-in-charge to disapprove any work
or materials shall not prejudice the power of the Engineer-in-charge thereafter
to disapprove such work or materials and so order the putting down, removal of
break in up thereof.
12) CO-ORDINATION:
When several agencies for different sub-works of the project are to work
simultaneously on the project site, there must be full coordination and cooperation
between contractors to ensure timely completion of the whole project smoothly.
The scheduled dates for completion specified in each contract shall therefore, be
strictly adhered to Each contractor may make his independent arrangement for
water, power, housing etc. if they so desire On the other hand the contractors are
at liberty of mutual agreement in this behalf and make joint arrangements with the
approval of the Engineer. No single contractor shall take or cause to be taken any
steps or action that may cause, disruption discontent, or disturbance of work,
labour or arrangement etc. of the other contractor which the Engineer in his
unquestioned discretion may consider as infringement of the above code, would be
considered as a breach of the contract conditions and shall be dealt with as such.
In case of any dispute, disagreement between the contractors, the Engineer's decision
regarding the coordination, co-operation and facilities to be provided by any of the
contractors shall be final and binding on the contractors concerned and such a decision
or decisions shall not vitate any contract nor absolve the contractor(s) of his/ their
obligations under the contract nor consider for the grant for any claim or compensation. 13) ASSISTANCE IN PROCURING PRIORITIES, PERMITS, ETC.:-
The Engineer, on a written request by the contractor, will, if in his opinion, the request is
reasonably and in the intersect of work and its progress assist the contractor in securing,
the priorities for deliveries transport permits for controlled materials etc. where such are
needed. The M.P.K.V. will not however, be responsible for the non-availability of such
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 98 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
facilities or delay in this behalf and no claims on account of such failure or
delays shall be allowed by the M.P.K.V.
The Contractor shall have to make his own arrangement for machinery required
for the work. However, such machinery conveniently available with the
Department, may be spread as per rules in force on recovery of necessary
Security Deposit and rent with agreement in the prescribed from. Such an
Agreement shall be independent of this contract and the supply of machinery
shall not form a ground for any claim or extension of time limit for this work.
14) QUARRIES:-
14.1 No P.W.D. quarries are available with this Department. The contractor(s) shall
have to arrange the same himself/ themselves. 14.2 The quarrying operations shall be carried out by the Contractor with proper
equipment such as compressors, Jack-hammers, drill bits, explosives etc. and
sufficient number of workmen shall be employed so as to get the required out- turn. 14.3 The Contractor shall carry out the works in the quarries on conformity with all the rules and
regulations already laid down or that may be laid down from time to time by M.P.K.V. Any
cost incurred by M.P.K.V. due to non compliance of any rules or regulations or due to
damages by the Contractor shall be the responsibility of the Contractor. The Engineer-in-
charge or his representative shall be given full facilities by the contractor for inspection at all
times of the working of query, records maintained, the stocks of the explosives and
detonators etc. So as to enable him to check that the working records and storage are all in
accordance with the relevant rules. The Engineer-in-charge or his representatives shall at
any times be allowed to inspect the works, buildings and equipment at the quarters.
14.5 The Contractors shall maintain at his own cost the books, registers etc. required
to be maintained under the relevant rules and regulations and as directed by
the Engineer-in-charge. These books shall be open for inspection at all times by
the Engineer-in-charge or his representative and the contractors shall furnish
the copies of extracts of books or registers as and when required. 14.6 All quarrying operations shall be carried out by the Contractor in organised and
expenditious manner, systematically and with proper planning. The Contractor shall engage
licensed blasters and adopt electric blasting and / or any other approved method which
would ensure complete safety to all the mean engaged in the quarry and its surroundings.
The Contractor shall himself provide suitable magazines and arranges to procure and store
explosives etc. are required under the rules at his own cost. The design and the location of
the magazine shall be got approved in advance from the Chief Inspector of Explosive and
the Rules and Regulations in this connection as laid down by the
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 99 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Chief Inspector of Explosive form time to time shall be strictly adhered to by the
contractor. It is generally experienced that it takes time to obtain the necessary
licence for blasting and licence for storage of materials from the concerned
authorities. The Contractor must, therefore, take timely advance action for
procuring all such licences so that the work progress may not be humpered.
14.6 The approaches to the quarrying places from the existing public roads shall
have to be arranged by the Contractor at his own cost and the approaches shall
be maintained by the Contractor at his own cost till the work is over. 14.7 The Quarrying operations shall be carried out by the Contractor to the entire satisfaction of
the Engineer-in-charge and the development of the quarry shall be made efficiently so as to
avoid wastage of stones. Only such stones as are of the required quality shall be used on
the work. Any stone which is in the opinion of the Engineer-in-charge, not in accordance
with the specifications or of required quality will be rejected at any time, at the quarry or at
the site of work. The rejected stones shall not be used on the work and such rejected
materials shall be removed to the place shown at the Contractor's cost. 14.8 Since all stones quarried from Government quarry (if made available) by the Contractor
including the excavated over burden are the property of the Government. No stones or
earth shall be supplied by the Contractor to any other agencies or works or allowed to
be taken away for any other works. All such surplus quarried materials not required for
work under this contract shall be the property of the Government and shall be handed,
over to the Contractor to Government free of cost at quarry site duly heaped at the
spots indicated by the Engineer-in-charge. The contractor will be entitled to do the
refund of royalty if any paid by him for such quantity handed over to Government for
which necessary certificate will be issued by Executive Engineer as per usual
procedure. If however, the M.P.K.V. does not required such surplus material the
Contractor may be allowed to dispose off or use such material elsewhere with prior
written permission of the Engineer-in-charge. Leaving off a quarry face or opening of a
new quarry face shall be done only on the approval of the Engineer-in-charge. 14.9 Quarrying permission will have to be directly obtained by the contractor from the Collector
of the District concerned for which purpose the Department will render necessary
assistance. All quarry fees, royalty charges, octroi duties, ground rent for staking material
etc. if any to be paid, shall be paid directly by the contractor as per rules in force. The
Contractor will however, be entitled to a refund of part of such charges as are admissible
under rules as mentioned elsewhere in this contract after obtaining a certificated from the
Engineer-in-charge that the material were required for use on Government works. 14.10 The Contractor will be permitted to earect at his own risk and cost at the quarry site if
suitable vacant space in M.P.K.V. area is available for the purpose his own-structures for
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 100 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
stores, offices etc. at places approved by the Engineer-in-charge. On
completion of the work the contractor shall remove all the structures erected by
him and restore the site to its original condition.
14.11 The Contractor shall not use any land in the quarry either for cultivation or for
any other purpose except that required for breaking or transporting stones.
15) COLLECTION OF MATERIALS:
i) Where suitable and approved P.W. Department's quarries exist, the contractor or piece
worker will be allowed if otherwise there is no objection to obtain the materials to the
extent required for the work from the quarry. He will be , however, liable to pay
compensation of any damage if caused to the quarry either deliberately or through
negligence or for wastage of materials by himself or his staff or labour. The Contractor
shall pay necessary royalty in advance and claim refund according to rules, if
admissible, and shall submit detailed accounts or materials from quarries as directed. ii) Where no suitable P.W. Department's quarries exist or when the quantity of the
material required cannot be obtained from a P.W. Department quarry the Contractor or
piece-worker shall make his own arrangements to obtain the material from existing or a
new quarry in Government waste land, private land or land belonging to other" States
or talukas etc. After opening the quarry but before starting collection the quarry shall be
got approved by the Engineer-in-charge or his representatives. The Contractor or piece
worker shall pay all royalty charges compensation etc. No claims or responsibility on
account of any of obstructions caused to execution of the work by difficulties arising out
of private owners of the land will be entertained. iii) The rates in the tender include all incidental charges such as opening of new
quarry, opening out a new portion in an existing quarry, removing top soil and
the unsuitable material, quarry, cost of blasting power of fuse, lift, lead, repairs
to existing cart tracks, marking new cart tacks, control charges, Central/ State
Government or Municipal Taxes, Local Board Cess etc. iv) The rates in the tender are for the delivery of the approved material on road
side properly stacked at the places specified by the Engineer-in-charge and are
inclusive of conveyance charges in respect of the leads and lifts. No claims on
account of changes in lead will be entertained. v) No material shall be removed from the land within the road boundary or from the land
touching It without the written permission of the Engineer-in-charge or his authorised agent.
If any material is unauthorisely obtained from such places , the contractor or piece worker
shall have to make good the damages and Pay such compensation in addition as may be
decided by the Executive Engineer and will have to stop further collection.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 101 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
vi) Any material that falls on any P.W.D. road from the card etc. during conveyance shall be
immediately picked up and removed by the Contractor or piece worker, failing which it wit
be got removed Departmentally at his cost. No heap shall be left prior to stacking even
temporarily on the road surface or in any so as to cause any obstruction or danger to the
traffic. The any claims of compensation etc arising out of any accident etc. any such
materials causing obstruction or danger etc will be got removed Departmentally at his cost
thus removed will be entertained. The contractor Shall also be responsible for the damage
or accident etc arising out of any material that falls on the road or track, not in charge of the
Department and shall attend to any complaints which may be received.
vii) The materials shall not be stacked in place where it is liable tb~ be damaged or
lost due to traffic passing over it, to be washed away by rain or floods, to be
buried under the land slides etc. of the slip down and embankment or hill side
etc. No claims for any loss due to these and similar causes will be entertained. viii) Before stacking, the materials shall be free from all earth, rubbish vegetable matter
and other extraneous substance and in the case of metal, screened to gauge if so
directed when ready. It shall be stacked entirely clear of the road way on ground
which has been cleaned of vegetation and levelled. On high banks ghat roads etc.
where it may not be practicable to stack it entirely clear of the roadway it may be
stacked with the permission of the Engineer-in-charge on brms in such a way as to
cause minimum danger and obstruction to the traffic or as may be directed by him. ix) The size of the stack for materials other than rubble shall be 1.0 m x 1.0 x 0.5
m. or such other size as may be directed by the Engineer-in-charge and all but
one stack in furlong shall be of the same uniform size and shall be uniformly
distributed over whole lengths. One stack (at the end) in each furlong may be of
length different from the rest in order to adjust total quantity to be required but
its width arfd height will be the same as those of the rest. x) The University Engineer shall supply the contractor with statement showing furlong
wise quantities that will be required and the order in which the collection is to be
done. No materials in excess of requirements in that furlong shall be staced. Any
excess quantity shall be removed at the Expense of the contractor or piece worker
to where it is required before the material in that furlong is finally measured. xi) In stacking materials the deposition shall commence at the end of the mile furthst from the
quarry and be carried continuously to the other end (unless otherwise directed by the
University Engineer). Stacking in one furlong shall be completed before it is started in
another unless directed otherwise in writing by the University Engineer. Measurements of
the materials stacked in a furlong will not be recorded until the full quantity required has
been stacked unless otherwise authorised by Engineer in writing. Collecting and spreading
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 102 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
shall not be carried out at the same time in one and the same mile or in two
adjoining miles except with the written permission of the University Engineer.
xii) Unless otherwise directed the materials shall be collected in the following order
according to availability of space (1) Rubble (if included in tender) (2) metal (3) Soft
murum and (4) Hard murum. Hard murum shall be stacked on the side opposite to
that on which soft murum has been stacked. Similarly, metal collected for petty
repairs shall be sfacked on the side opposite to metal for new layer. Where metal
for two layers has to be stacked, as in the case of new roads, the metal for each
layer shall be stacked on the opposite sides of the road. xiii) All road material shall be examined and measured before it is spread. The labour for
measurements (and check measurements wherever carried out shall be supplied by the
contractor or piece worker. Immediately after the measurements are recorded the stacks
shall be marked by the contractor or piece worker by white wash or otherwise as may be
directed by the University Engineer to prevent from any possibility of the same material
being measured and recorded over again and to prevent any unauthorized tampering with
the stacks. If the contractor or the piece worker fails to attend the measurements of
materials after receiving the notice from the University Engineer or his subordinate stating
date and time of the intention to measure the work, , shall be measured nevertheless and
no complaint in this respect will be entertained later on. If the contractor or piece worker
fails to supply sufficient labour for the materials required at the time to measurements or
check measurements, after due notice has been given to him, the expenses incurred on
account of employing departmental labour or material etc . or any accident or occurrence
what-so-cver in connection, there wtili. all operations in or for which explosives are
employed being at the risk of contractor and upon his sole responsibility and the contractor
hereby gives to M.P.K.V. an absolute indemnity in respect thereof xiv) No deduction will be made for voids.
16) THEMPORARY QUARTERS AND SITE OFFICE :-
i) The contractor shall at his own expense maintain sufficient experienced supervisory
staff etc. required for the work and shall make his own arrangement, provide
housing for them with nil necessary arrangements, including fire preventive
measures etc. as directed by the Engineer -in- charge ii) The contractor shall provide, furnish, maintain and remove on completion of the work, a
suitable office on the wok site for the use of University Engineer's representative. The Sft.
Covered area Exclusive of Verandah should not be less than 400. Ii may have brick walls
and asbestos or corrugated iron roof, paved floor should be 18" above ground level. He
should provide a suitable latrine, urinals and keep (hem clean daily, this will be supposed
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 103 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
to be included in his rate.
17) TREASURE TROVE :- ln (he event of discovery by (he contractor or his
employees, during the progress of the work of any treasure, fossils, minerals
or any other articles of value or interest, the contractor shall give immediate
intimation thereof to the Engineer and forthwith hand over to the Engineer such
treasure to things which shall be the proper! y of Government. 18) PATENTED DEVICE:
Whenever the contractor desires to use any designed devices, materials or process
covered by the letter of patent or copy right, the right for such use shall be secured
by suitable legal arrangement and agreement with patent owner and the copy of
their agreement shall be with the Engineer-in-charge if so desired by the later. 19) EXPLOSIVES:
The contractor shall at his own expense construct and maintain proper magazines, if
such are required for the storage of explosives for use in connection with the work and
such magazine, being situated constructed and maintained in accordance with the
Government Rules applicable in the behalf. The contractor shall at his own expenses
obtain such license or Licenses as may be necessary for storing and using explosives
notwithstanding that the location etc. or storage of explosives are approved by the
Engineer, the M.P.K.V shall not be incurring any responsibility whatever in connection
with storage and use of explosives on (he site or any accident or accurance what so
ever in connection, there with, all opration in or for which explosive are employed being
at the risk of contractor and upon his sole responsibility and the contractor hereby give
to MPKV and absolute indemnity in respect therefore. 20) DAMAGE BY FLOODS OR ACCIDENTS :-
The contractor shall take all precautions against damage by floods or like or from accident
etc. No compensation will be allowed to the Contractor on this account or for correcting
and repairing any such damage to the work during construction. The contractor shall be
liable to make good at his cost any plant or materials belonging to the Government lost or
damaged by floods or from any other cause which is in his charge. 21) POLICE PROTECTION :-
For the Special Protection of camp and of the contractor's works, the
Department will halp the contractor as far as possible to arrange for such
protection with the concerned authorities if so required by the Contractor in
writing, the full cost of such protection shall be borne by the Contractor. 22) TRAFFIC REGULATION FOR ROAD WORKS :-
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 104 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
22.1 Unless separately provided for in the contract, the Contractor shall have to make all
necessary arrangements for regulating traffic, day to night during the period of construction
to the entire satisfaction of the Engineer. This includes the construction and maintenance of
diversions if necessary. The contractor shall have to provide necessary caution bonds,
barricades flags, lights and watchmen etc. so as to comply with the latest Motor Vehicles
Rules and regulation and lor traffic safely and lie shall be responsible for all claims from
accidents which may arise due to his negligence whether in regulating (he traffic or in
stacking material on the roads, or due to any other reasons.
22.2 The contractor shall at ail times carry out the work on the road in a
manner creating least interference to the flow of traffic, while consistent with the
satisfactory execution of the same. For all works involving improvements to the
existing road, the contractor shall, in accordance with the directives of the
Engineer-in-charge, provide and maintain, during the execution of work a
passage for traffic, either along a part of the existing carriage way under
improvement, or along a temporary diversion constructed close to the road.
22.3 TRAFFIC REGULATION FOR BRIDGES AND C.D.WORKS :-
It is to be clearly understood that whatever work carried out by the Contractor for
construction of diversion road including earthwork. W.B.M. bituminous surface
dressing. R.C.C. pipe drains etc. will be paid lord only once if the items Of temporary
diversion are included in the Contract and if due to flow of traffic, due lo floods or due to
any other cause, this diversion road and/or the R.C.C. drain gets damaged it shall be
repaired and maintained by the Contractor in good conditions till completion of the
whole work at his own expenses. Traffic safety and control shall be as per cause No.
112.4 of M.O.S.T. Specification for Roads and Bridges (ll nd Revision 1990).
23) SUPERVISION AND INSPECTION OF WORKS AND QUALITY
CONTROL :-23.1 SUPERVISION :-
The contractor shall either himself supervise the execution of the works or shall
appoint the competent agent approved by the Engineer-in-charge. to act on his
behalf. If in the opinion ol the Engineer-in-charge, the contractor has himself no
sufficient knowledge and experience of receiving instructions or cannot give his
full attention to the works, the contractor shall at his own expenses, employ as
his accredited agent a qualified Engineer approved by the Engineer-in-chargc.
Orders given to the contractor's agent shall be considered to have the force as if these had
been given to the contractor himself. If the contractor fails to appoint a suitable agent as
directed by the Engineer-in-charge. the Engineer-in-charge shall have full power to
suspend (he execution of the work until! such date a suitable agent is appointed and the
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 105 - 0
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
contractor shall be responsible for the delay so caused to the works and
contractor shall not be entitled for any compensation on this behalf.
23.2 INSPECTION :-
The contractor shall inform the Engineer-in-charge in writing when any portion of the work
is ready for inspection giving him sufficient notice to enable him to inspect the same without
affecting the further progress of the work. The work shall not be considered to have been
completed in accordence with the terms of the contract un till the Engineer-in-charge shall
have certified in writing to that effect. Approval of materials or workmenship or approval of
part ol the work during the progress of execution shall not bind the Engineer-in-charge or in
any way affect him even to reject the work which is alleged to be completed and to
suspend the issue of his certificate of completion until] such alteration and modifications or
reconstruction have been effected at ihe cost of the contractor as shall enable him to certify
that the work has been completed to his satisfaction.
The contractor shall provide at his cost necessary ladders and such
arrangements as to provide necessary facilities and assistance for proper
inspection of all parts of the work at his own cost.
24) INITIAL MEASUREMENTS FOR RECORDS :-
Where, for proper measurement of the work, it is necessary to have and inlitial set of
levels or other measurements taken, the same as recorded in the authorised field book
or measurement book ol M.P.K.V. by the Engineer or his authorised representative will
be signed by the contractor who will be entitled to have a true copy of same made at
his cost. Any failure on the part of the contractor to get such levels etc, recorded before
starting the work will render him liable to accept the decision of the Engineer as to the
basis of taking measurements. Like-wise the contractor will not cover any work which
will render its subsequent measurements difficult or impossible without first getting the
same jointly measured by himself and the authorised representative of the University
Engineer. The record of such measurements on the M.P.K.V. side will be signed by the
Contractor and he will be entitled to have a true copy of the same made at his cost. 25) SAMPLES AND TESTING OF MATERIALS :-
i) All materials to be used on work shall be got approved in advance from the Engineer-
in-charge and shall pass the test and/or analysis required by him which will be
(a) as specified in the specification for the items concerned and/or
(b) I.S.I, specifications (whichever and wherever applicable) or
(c) such recognized specifications acceptable to Engineer-in-charge as equivalent
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 106 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
there too absence of such authorised specification.
d) such requirement (est and/or analysis as may be sped fed by the Engineer-
in-charge in order of p/ecedence given above.
ii) The Contractor shall at his risk and cost make all arrangements and/or shall
provide all such facilities as the Engineer-in-charge may require for collecting,
preparing required number of samples for test or analysis at such time and to
such places as may be directed by Engineer and bear all such charges. Such
samples shall also be deposited with Engineer-in-charge.
iii) The contractor shall if and when required submit at his cost the samples of materials
to be tested or analyzed and if so directed, shall not make use of or incorporate in the
work any materials represented by the samples until the required tests or analysis have
been made and the materials, finally accepted by the Engineer-in-charge.
iv) The contractor shall not be eligible for any claim or compensation either arising
out of any delay in the work or due to any corrective measure required to be
taken on account of and as a result of testing of the materials.
v) The contractor or his authorised representative will be allowed to remain present in the
departmental alboratory while testing samples furnished by him. ; However, the results of all
the tests carried out in the departmental laboratory in the presence of absence of the
contractor or his authorised representative \\ ill be binding on the contractor.
vi) The contractor shall at his own cost set up laboratory to carry out the routine
tests of materials which are to be used on the work. The tests will have to be
carried out eighter in his field laboratory or in an approved laboratory. In case
tests are carried out in field laboratory, atleasl 50% test should be carried out in
nearest quality control laboratory for the Department.
vii) In case of material procured by the contractor, testing as required by the codes and
specifications shall be arranged by him at his own cost. Testing shall be done in the
presence of authorised representative of the Engineer-in-charge at the nearest
approved laboratory. If additional testing other than as required by specification is
ordered, the testing charges, shall be borne by the Department, if the lest results are
satisfactory and by the contractor if the same are not satisfactory.
viii) In case of materials supplied by the M.P.K. V. if the contractor demands
certain testing, the charges thereof shall be paid by the contractor if the testing
results are satisfactory and by the Department if the same are not satisfactory. '
ix) All Quality control test should be got done from the Institute as directed by
the Engineer Incharge.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 107 - 0
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
26) CHANGE OF CEMENT CONTENTS ETC. :-
The tendered rated for any item, involving the use of cement shall apply to the quantity
of cement pacified for the mix for that item in the specifications. If for any reasons,
except those required for compensating he deficiencies. in the components, the
cement content and properties are altered by the Engineer (Engineer-n-charge) at any
time or from lime to time the tendered rales for the particular item and quantity or
quantities, hall be duly enhanced or reduced only to account for the addition or
reduction in cost of the cement content rom that laid down in the specification at the
rales specified in the Schedule 'A' of the contract plus 10% to over all other incidental
charges whatever. Likewise if any additives compounds water proofing materials tc. arc
ordered by the Engineer to be added to the mortar or concrete, no extra rate shall be
payable for this hanged which shall be carried out as per direction of the Engineer-in-
charge, provided cost of such additives is borne by M.P.K.V. or these are supplied free
of costs to contractor at site by the M.P.K.V. 27) CEMENT CONCRETE:-
27.1 General:
a) All concrete shall be controlled concrete and machine mix unless
otherwise directed by Engineer-in charge. For controlled or High grade
concrete, the grading of aggregates shall be got approved from the Engineer.
b) The correct proportions and the total amount of water for the mix will
be determined by means of preliminary tests and shall be got approved by the
Engineer. However, such approval docs not relieve the Contractor from his
responsibility regarding the minimum works strength requirements. Work test
shall be taken in accordance with relevancodes specifications. All proportioning
of aggregates shall be done by weight if so ordered by the Engineer.
c) All mixing shall be done by mechinieal means in approved mixers, the
Engineer may at his discretion, allow in writing hand mixing of concrete for
minor items where small quantities are involved but in that case the Contractor
shall increase the cement content of the mixure by 10% without any extra cost.
d) The form work used shall be made preferably of steel or with lining of
steel. Wooden shuttering may be allowed at the discretion of the Engineer e.g.
lintels small slabs and beams coping etc.
e) The concrete shall be machincally vibrated for proper compaction by the
method approved by the Engineer.
f) The concrete shall be cured only by a sweet potable water for full 21 days after
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 108 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
the time or the period specified in the detailed specification or as may be
directed by Engineer-in-charge.
27.2 FORM WORK AND STAGING FOR BRIDGE STRUCTURES :
27.2.1 For bridge structure. Forms for concrete shall be constructed of mild steel
plates or marine plywood and be of substantial and rigid construction true to shape
and dimensions shown on the drawings. Where metal forms are used all bolts and
rivets shall be counter sunk and well ground to provide a smooth plane surface.
27.2.2 Forms shall be morter tight and shall be sufficiently rigid by the use of ties
and brancings to prevent any displacement or sagging between supports. They
shall be strong enough to withstand all pressure, ramming and vibration, without
deflection from the prescribed lines occurring during and after placing the concrete
and shall be tight enough to prevent any appreciable loss of concrete during
vibration. Screw jacks or hard wood wedges where required shall be provided to
make up any settlement in the form work before or during the placing of concrete.
27.2.3 Schedule ember shall be provided in horizontal members of structures,
specially in long spans to counter act the effects of any deflection. The form
work shall be so fixed as to provided for such camber.
27.2.4 Forms shall be so constructed as to be removal in
sections in the desired sequence. Without damaging the surface of concrete
ordisturbine other section
27.5 NUMBER OF SETS OF STAGING AND SHUTTERING AND EQUIPMENT.
(FOR BRIDGE WORKS ONLY)
IN ORDER TO ENSURE COMPLETION OF BRIDGE WITHIN THE STIPULATED PERIOD, THE
CONTRACTOR SHALL HAVE TO ARRANGE A MINIMUM NUMBER OF SETS OF STAGING
AND SHUTTERING AS WELL AS EQUIPMENT OF THE REQUIRED SIZE
FOR DIFFERENT COMPONENTS as STIPULATED HEREUNDER >
I) FORWELL a) Staging and.................... sets.
foundations shuttering.
b) Equipments sets.
ii) For Other (a) Staging and................ sets.
items of shuttering,
substructure (b) Equipments................. sets.
iii) For super (a) Staging and————— sets. structure. shuttering.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 109 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
(b) Equipment’s ——— sets.
Use of slip form shuttering wherever feasible will be preferred,
27.2.6 Forms shall be constructed so as to be removable in sections in the desired
sequence without damaging the surface of concrete ordistrubing other sections.
28) MISCELLANEOUS :-
1. Rate shall be inclusive of ST.. General Tax and other Taxes etc.
2. For providing electric wiring or water lines etc. recesses shall be
provided if necessary through walls, slabs, beams etc. and later refilling up with
bricks or stone chipping, cement mortar without any extra cost.
3. In case it becomes necessary for the due performance of the contract
for the Contractor to occupy land outside the Department limits the Contractor
will have to make his own arrangements with the land owners and to pay such
rents if any are payable as mutually agreed between them.
The Department will afford the Contractor all the reasonable assistance to
enable him to obtain Government land for such purpose on usual terms and
conditions as per rules of Government, if such land is available.
4. The special provision in detailed specifications or wording of any item
shall gain precedence over corresponding contradictory provision (if any) in the
standard specifications of P.W.D. Hand Book, where reference to such
specifications is given without reproducing the details in contract.
5. Suitable separating Barricades and enclosures shall be provided to separate
material brought by contractor and material issued by M.P.K. V. to contractor under
Schedule 'A' Same applies for the material obtained from different sources of supply.
6. The stacking and storage of construction material at site shall be in such
manner as to prevent deterioration or infusion of foreign matter and to ensure the
preservaion of their quality, properties and fitness lor the work. Suitable precautions
shall be taken by the Contractor to protect the material against atmospheric
actions, fire and other hazards. The materials likely to be carried away by wind
shall be stored in suitable stores or with suitable barricades and where there is
likelihood of subsidence of soil, such heavey materials shall be store on platforms.
7. For Road and Bridge works the contractor shall in additon to the
specifications cited here comply with requirements of relevant I.R.C. code practice.
8. The Contractor shall he responsible for making good the damages
done to the existing properity during construction by his men.
9. If it is found necessary from safety point of view to test any part of the structure
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 110 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At
Halgaon the test shall by carried out by the Contractor with the help of Department al his
own cost.
10. Defective work is liable to be rejected at any stage. The contractor, on
no account can refuse to rectify the defects merely on reasons thai further work
has been carried out. No extra payment shall be made for rectification.
11. In the Schedule 'B' the work has been divided in to sections but
notwithstanding this, every part of it shall be deemed supplementary to and
complementary of every other part.
12. General directions or detailed description of work, materials and items
coverage of rates given in the specification are not necessarily repeated in the BUI
of Quantities. Reference is. however, drawn to the appropriate section clause(s) of
the General Specifications in accordance with which the work is to be carried out.
13. In the absence of specific directions to the contrary the rates and prices
inserted in the items are to be considered as the full inclusive rates and prices for the
finished work described thereunder and are to cover all labour, materials, westage.
temporary work plant overhead charges and profits, as well as the general liabilities,
obligations and risks arising out of the General Conditions of Contract.
14. The quantities set down against the item in the Schedule 'B' are only
estimated quantities of each kind of work included in the Contract an are not to
be taken as a guarantee that the quantities scheduled will be carried out or
required or that they will not be exceeded.
15. All measurements will made in accordance with the methods indicated in
the specification and read in conjunction with the General Conditions of Contract.
16. The details shown on drawings and all other information pertaining to the work
shall be treated a indicative and provisional only and arc liable to variation as found
necessary while preparing working drawing which will he supplied by the Government
during execution. The contractor shall not, on account of such variation be entitled to
any increase over the ones quoted in the lender which are on quantity basis.
17. The recoveries if any due from contractor will be effected as arrears of
land revenue through the Collector of the District.
18. Clause 101 to 107 of Specifications of Road Bridges work adhered
herewith will be applicable to works as per Schedule 'B' unless specified
otherwise in the detailed specifications of the relevant items.
19. All materials used in the construction shall conform to the requirement
of Specification Clause under Section 1000 "Materials for Structures" of
Specification of Road and Bridge work M.O.S.T. New Delhi 1990 Edition.
20. Extraneous materials and steps to minimize dust nuisance during construction
shall be as per clause 111 of MOST Specification (Second Edition 1990).
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 111 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
PROTECTION OF UNDERGROUNDTELEPHONE CABLE & AERIAL TELEPHONE WIRES & POLES, TRANSMISSION TOWERS, ELEC. CABLES AND WATER SUPPLY LINES :-
During the execution of work it is likely that the contractor may meet with telephone cables,
electrical cable, water supply lines etc. it will, therefore, be the responsibility of the contractor to
protect them carefully. All such cases should be brought to the notice of the Engineer-in-charge
by the contractor and also to the concerned Department. Any damage what-so-ever done to
these-cables and pipe lines by the contractor shall be made good by him at his cost.
29. MEDICAL & SANTITARY ARRANGEMENTS TO BE PROVIDED FOR LABOUR EMPLOYED IN
THE CONSTRUCTION BY THE (ON TR A C K ) R :-
a) The contractor shall provide an adequate supply of water for the use of labour
on work and in camps
b) The contractor shall construct trench or semi-permanent latrines for the use of
the Labours. Separate latrines shall be provided for men and women.
c) The Conn actor shall build sufficient number of huts on a suitable plot of land for
use of the labourers according to the following specifications i-
1. Huts of Bamboos and Grass may be constructed.
2. A good site not liable to submergence shall be selected on high ground remote
from jungle but well provided with trees, shall be chosen wherever it is available.
The neighbor hood of tank, jungle, grass or wood shroud be particularly avoided.
Camps should not be established close to large cutting of earth work.
3. The lines of huts shall have open spaces of at least ten yards between rows. When a good
natural site cannot be procured. particular attention should be given to the drainage.
4. There should be no over crowding. Floor space at the rate of 3- sq. ft. per head shall be
provided. Care should be taken to see that the huts are kept clean and in good order,
5. The contractor must find has own land. If he wants Government land, he should
apply for it and pay assessment for it. if made available by M.P.K.V.
6. The contractor shall construct a sufficient number of bathing places. Washing places should also be provided for the purpose of ashing cloths.
7. The contractor shall make sufficient arrangements for draining away the surface and
sullage water as well as water from the bathing and washing places and shall
dispose off this waste water in such way as not to cause any nuisance.
a) The contractor shall engage a Medical Officer with a travelling dispensary for a Camp
containing 500 or more persons if there is no M.P.K.V. of other private dispensary
situated within 8 KMs from the camp. In case of emergency the contractor shall arrange
at his cost of transport for quick medical help to his sick worker.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 112 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
a) The contractor shall provide the necessary staff for effecting satisfactory
drainage system and cleanliness of the camp to the satisfaction of the Engineer.
Al least one sweeper per 200 persons should be engaged.
b) The Assistant Director of Public Health shall be consulted before opening a labour
camp and his instructions on matters such as water supply, sanitary conveniences,
the camp site accommodation and food supply shall be followed by the contractor.
c) The contractor shall make arrangements for all anti malaria measures to be
provided for the labours employed on the work. The anti malaria measures shall
be provided as directed by the Assistant Director of Public Health.
(30) SAFTY CODE:-
Suitable scaffolds shall be provided for workmen for all works shat can not safely be
done from the ground, or from soild construction except such sho/t period work as can
be done safely from ladders. When ladder is used an extra ma/door shall be engaged
for holding the ladder and if the ladder is used for carrying materials as well suitable
footholds and handholds shall be provided on the ladder and the ladder shall be given
an inclination not steeper than 1 to 4 (horizontal and 4 vertical.
Scaffolding or staging more than 3.25 meters above the ground or floors, swing or
suspended from an overhead support or erected with stationary supports, shall have a
guard rail properly attached, bolted braced and otherwise assured at least one meter
high above the floor or platform of such scaffolding or slagging and extending along the
entire length of the outside and ends thereof with only such openings as may be
necessary tor the delivery of malarias. Such scaffolding or staging shall be so fastened
as to prevent it from swaying from the building or structure.
Working platform gangways, and stairways shall be so constructed that they do not
sagun duly or is more than 3.25 meters above ground level or floor level, it shall be
closely boarded, have adequate width and be suitably fenced as described in 2 above.
Every opening in floor of the building or a working platform shall be provided with
suitable protection to prevent fall of persons or materials be providing suitable fencing
or railing with minimum height of 1 meter.
Scfe means of access shall be provided to all working platform and other working places, livery
ladder shall be securely fixed No protable single ladder shall be over0 metres in length, width
between side rails in arung ladder shall in no case be less than 30 cms. for ladders UPTO and
including 3 meters in length. For longer ladders this width shall be increased atlcast 6 mm for
each additional 30 cms. of length Uniform step spacing shall not exceed 30 cms. Adequate precautions shall be taken to prevent danger from electrical equipment. No materials on
any of the sites shall be stacked or placed as to cause danger or inconvenience to any person
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 113 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
or the public. The Contractor shall provide all necessary fencing and lights to protect public
from accident and shall be bound to bear expenses of defense of every suit, action or other
proceedings as law that may be brought by any person for injury sustained owing to
neglect of the above precaution and to pay any damages and costs which may be
•awarded in any such suit action or proceedings to any such person or which may with the
consent of tin contractor, to be paid to compromise any claim by any such person.
EXCAVATION AND TRENCHING :-
All trenches, 1.5 meters or more in depth, shall at all times be supplied with at least one
ladder for each 30 meters in length or fraction thereof. Ladder shall be extended from
bottom of trench to at least 1 meter above surface of the ground, sides of a trench which is
1.5 meters or more in depth shall be stepped back give suitable or security held by timber
bracing , so as to avoid the danger of side collapsing Excavated materials shall not be
placed 1.3 meters of trench or half of depth of whichever is more. Cutting shall be done
from to bottom under no circumstance shall undermining or under cutting be done .
DEMOLITION :-
Before any demolition work is commenced and also during the process of the work,
site shall either be closed or suitable protected . a. All roads and open areas adjacent to the work site shall either be closed or suitable protected
b. No electric cable or apparatus which is liable to be a source on danger or a cable or
apparatus used by operator shall remain electrically charged . c. All practical steps , shall taken to prevent danger to person employed , from risk or
fire or explosion or hooding . No floor, roof or other part of a building shall be so
overloaded with debris of materials as to render it unsafe.
All necessary personal safety equipment as considered adequate by the Engineer-in
charge shall be available for use of persons employed on the site and maintained in
condition suitable for immediate use and the contractor shall take adequate step to
ensure proper use of equipment by those concerned .
A. Workers employed on mixing aspartic materials , cement lime , concrete , shall be
provided with protective footwear and protective goggles .
B. Those engaged in handing any materials , which is injurious to eyes shall be provided with
protective goggles .
C. Those engaged in welding works shall be provided with welder's protective eye shads .
D. Stone breakers shall be provided in with protection goggles and protective
clothing and seated E. sufficiently safe intervals .
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 114 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
F. When works are employed in sewers and manholes which are in use, the
contractor shall ensure that manhole covers are opened and manhole are
ventilated at least for an hour before workers are allowed to get into them . Man
holes opened shall be cordoned off with suitable railing and provided with
warning signals or boards to prevent accident to public.
G. The Contractor shall not employ . men below the of 18 and women on the work
of painting with products containing the following precautions shall be taken . i)
No. paint containing lead of lead product shall used except in the form of paste
H. or ready made paint. ii) Suitable face masks shall be supplied for use by workers when
paint is applied in the form of spray or a having lead paint dry rubbed and scraped.
I. Over alls shall be supplied by the Contractor to workmen and adequate facilities shall be
provided to enable working painters to wash during and on cessation of wok.
J. When work is done near any place where there is risk of drowning all necessary
equipment shall be provided and kept ready for use and all necessary steps taken for
prompt rescue of any person in danger and adequate provision made for prompt first aid
treatment of all injuries likely to be sustained during the course of the work.
a) These shall be of good mechanical construction round materials and adequate strength
b) and free form potent defects and shall be kept in good repair in good working order, ii)
Every rope used in hoisting or lowering materials or as means of suspension shall
be of durable quality and of adequate strength and free from potent defects.
c) Every crane driver or hoisting appliance operator shall be property qualified and
not person under the age of 21 years shall be in charged of any hoisting
machine including any scaffolding.
d) In case of every hoisting machine and of every chain ring hook, shackle ownel
and pulley block used in hoisting or lowering or use means of suspension safe
working load shall be ascertained by adequate means. Every hoisting machine
and all gear referred to above shall be plainly marked with safe working load.
e) In case of a hoisting machine having a variable safe working load, each safe
working load and the conditions under which it is applicable shall be clearly
indicated. No part of any machine or any gear referred to above in this paragraph
shall be loaded beyond safe working load except for the purpose of testing.
f) In case of departmental machines safe working load shall be notified by the
Engineer-in-charge regards contractor's machines the contractor shall notify
safe working load of each machine to the Engineer -in-charge whenever, he
brings it to site of work and get it verified by the Engineer -in-charge.
g) Motors, gearing, transmission , electric wiring and other dangerous parts of hoisting
appliances shall be provided with such means as will reduce to the minimum risk of
accidental descent of load. Adequate precautions shall be taken to reduce to the minimum
the risk of any part of a suspended load becoming accidentally displaced, when workers
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 115 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
are employed. On electrical installations which are already energized insulating
materials wearing approved such as gloves, sleaves and coats as may be
necessary, shall be provided. Workers shall not wear any rings, watches and
carry keys or other materials which are good conductors of electricity.
h) All scaffolds, ladders, and other safety deices mentioned or described hearing
shall be maintained in a safe condition and no scaffold ladder or equipment shall
be altered or removed while it is in use. Adequate washing facilities shall be
provided at or near places of work.
i) These safety provisions shall be brought to the notice of all concerned by display on a
notice board at a prominent place the work spot. Persons responsible for ensuring
compliance with the safety code shall be named therein by the contractor.
j) i) To ensure enforcement of the rules and regulations relating to safety
precautions, arrangements made by the contractor shall be open to inspection by the
Engineer -in-charge or his representatives and the inspecting officers, ii) Failure to
comply with the provision hereunder shall make the contractor liable to pay to the
Department as penalty an amount not exceeding Rs.50/- for each default and decision of the
Engineer-in-charge shall be final and binding. Not with standing the above conditions 1 to 14
the contractor is not exempted from the operation of any other Act or Rules inforce.
31) SCORE OF RATES FOR DIFFERENT ITEMS OF WORK :-
For item rate contracts, the contract unit rates for different items of work shall be payment in full
for completing the work to the requirements of the specifications including full compensation for
all the operations detailed in the relevant sections of these Specifications under "Rates". In the
absence of any directions to the contrary, the rates are to be considered as the full inclusive
rate for finished work covering all labour, materials, wastage temporary work, plant, equipment, overhead charges and profit as well as the general liabilities, obligations
and risks arising out of the General Conditions of Contract
The item rates quoted by the Contractor shall, unless otherwise specified, also include
compliance with/supply for following :-
a. General works such as setting out, clearance of site before setting out and
clearance of works after completing. b. A detailed programme for the construction and completion of the works (using CPM/PERT
techniques) giving, in addition to construction activities, detailed network activities for the
submission and approval of materials, procurement of critical materials and equipment
fabrication of special production/ equipments and their installation and testing and for all
activities of the Employee that are likely to effect the progress of work, etc. including updating
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 116 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
of all such activities on the basis of the decisions taken at the periodic site review
meeting or as directed by the Engineers.
c. Sample of various materials proposed to be used on the work for conducting tests
thereon as required as per the Provisions of the Contract. d. Design of mixes as per the relevant clauses of the Specifications giving proportions
of ingredients, sources of aggregates and binder along with accompanying trial
mixes as per the relevant Clauses of these specifications to be submitted to the
Engineer for his approval before use of the works. e. Detailed design calculations and drawings for all Temporary Works (such as formwork, staging,
centering, specialized constructional handing and launching equipment and the like). f. Detailed drawings for templates, support and end anchorage, details for pre
stressing cable profiles, bar bending and cutting schedules for reinforcement,
material lists for fabrication of structural steel etc. ' g. Mill test reports for all milled and high tonsils steel and cast steel as per the relevant
provisions of the Specifications : Testing of various finished items and materials
including bitumen, cement, concrete, bearings as required under these
specifications and furnishing test reports/certificate. h. Inspection Reports in respect of formwork, staging reinforcement and other items of work as
per the relevant Specifications
i. Any other data which may be required as per these specifications or the Conditions of
j. Contract or any other annexures /schedules forming part of the contract. k. Any other item of work which is not specifically provided in the Bill of Quantities but
which is necessary fro complying with the provisions of the Contract and l. All temporary works, formwork and false work.
Portions of works beyond the limits and or any work may be got constructed by the Employee
directly through agencies . Accordingly , other agencies employed by the Employer may be
working in the vicinity of the being executed by the Contractor. The Contractor shall liaise with
such agencies and adjust his construction programme for the completion of work accordingly
and no be indemnity-fied the Contractor for any claims from other agencies on this account.
32) PAYMENTS :-
Running Bills :-
Two payments is a month will be granted by the Engineer - in charge if the progress is
satisfactory. Contractor should submit bill to the Engineer - in charge in appropriate forms.
a) Final Bill :-
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 117 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
b) The contractor should submit final bill within one month after completion on of the
work and the same will be paid within 3 months if is in order. Disputed item and-if any
shall be exclude from the final bill and settled separately later on .
33) HANDING OVER OF WORK :-
All the work and materials before finally taken by M.P.K.V. will be the entire liability of
the contractor for guarding , maintaining and making good any damage of any
magnitude. Interim payments made for such work will not alter this position -
34) CLAIMS :-
Bills for extra work for any claim shall be paid separately apart from the interim bills for
the main work. The payment of bills for the main work shall not be with held for want of
decision on the extras or claims not covered in the appendices.
Claims for extra work shall be registered within 30 days of occurance of the event. However,
bills for these claims including supporting date/details may be submitted subsequently.
35) QUALITY ASSURANCE AND MAINTENANCE :-
(for works costing more than 100 lakhs)
1) Ensure the specified quality of work which will also 'include necessary surveys temporary
works etc, the contractor shall prepare a quality assurance plan and get the same
approved from the engineer-in-charge with in one month from the date of work order. For
the, the contractor shall submit and organization chart of his technical personnel to be
delayed on the work along with their qualification. Job descriptions defining be functions of
reporting supervision inspecting and approving. The contractor shall also submit a list of
tools, equipment and the machinery and instrumentation which he proposes to use for the
construction and for testing in the field and/or in the laboratory and monitoring. The
contractor shall modify/supplement the organization chart and the list of machinery,
equipment etc. as per the directions of the University Engineer and shall deploy te
personnel and equipment on the field as per the approved chart and list respectively. The
contractor shall submit written method statements detailing his exact proposals of
execution of the work in accordance with the specification. He will have to get these
approved from the : Engineer-in-Charge. The quality of the work shall be properly
documented through certificate, records, check list and log books of results etc., Such
records shall be complied from the beginning of the work and be continuously updated and
supplemented and this will be the responsibility of the contractor. The forms should be got
approved from the Engineer-in-Charge. 2) Where the work is to be done on lump sum basis on contractor shall be prepare and
submit a maintenance manual giving procedure for maintenance, with the periodicity
of maintenance work including inspections, tools and equipment to be used, means of
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 118 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
accessibility for all parts of the structure. He shall also include in the manual, the
specifications for maintenance work that would be appropriate for his design and
technique of construction. This manual shall be submitted within the contract period.
B) SPECIAL CONDITIONS DURING WORK TILL COMPLETION OF WORK
i) Successful Contractor have to provide one inspection vehicle along with driver to the
University Engineer office ( Scorpio, Honda city or Accent with A.C.) for the period till
the Work is complete. The monthly running of the said vehicle will be maximum 2000
Km. The cost of fuel & repairs etc.will be born by the Contractor. After work is
completed the said vehicle will be returned to the Contractors.
ii) One Laptop ( Computer Note Book ) for office use at Agriculture College, Pune.( Dell
basic Laptop Vostro 1510 , Intel Core 2 Duo 2.4 4Hz 800
MHz FSB Configuration , RAM-1 GB, Hard Disk 120 GB
Serial SATA (5400 RPM) Screen39.1 CM (15.4") TFT Screen ,
Intel graphics Media Acceleration 8 X DVD RW Drive , Key Board with touch PAD,
2 USB Ports , VGA out Wi-fi , Modem , Bluetooth , Operating system - Window Vista
Business Preloaded other Specification as per mentioned in the DCS & DRC.)
iii) One Desktop PC with Lazer Printer ( Intel ® , Pentium Core 2 DUO, 3.00 GH ,
Configuration-RAM 1 GB, Hard disk 160 GB , 19" wide LCD display, Operating
System-Windows XP , DVD RW Drive.)
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 119 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
ADDITIONAL SPECIAL CONDITIONS FOR NATIONAL HIGHWAY WORKS :
1) (i) Clause No. 106 of Ministry's Specification (2nd
Revision) This clause stipulates certain conditions relating to choice and use of equipment which
have relevance to production of quality work. These are :-
a. The contractor shall be required to give a trial run of the equipment for establishing
capability to achieve the laid down specifications and tolerances to the satisfaction
of the Engineer before commencement of work. b. All equipment provided should be of proven efficiency and shall be operated and
maintained at all times in a manner acceptable to the Engineer. c. No equipment and personnel will be removed from the site with the permission of the Engineer,
(ii) Clause No. 901 of Ministry's Specification (2nd
Revision). a. The responsibility for the quality of the entire construction work is on the Contractor.
For this purpose he is required to have his own independent and adequate set-up. b. The Engineer for satisfying himself about ther quality of the materials and work will
also have tests conducted by quality control units or by any other agency, generally
to the frequency set out in the Specifications. For test to be done by the Engineer,
ther_ Contractor is to renbder all necessary co-opoeration and assistance including
the provision of labour assistance in packing and despatching samples etc. c. For the work of embankment, subgrade and pavement, construction of subsequent
layer of the same for other materials over the finished layer shall be done only after
obtaining approval from the Engineer. d. The contractor shall be responsible for rectifying/replacing any work filling short of
quality requirements as directed by the Engineer.
(iii) Clauses in the Conditions of Contract :-
a. All materials and workmanship shall be of the respective type described in the contract
and in accordance with the Engineer's instructions and shall be subjected from time to
time to such tests as the Engineer may direct at the place of manufacture of fabrication,
or on the site/ All samples shall be supplied by the contractor. b. No work is to be covered up or put out of view without the approval of the Engineer
for his examination and measurements. c. During the progress of the works, the Engineer shall have the power to order the
removal from the site of any unsuitable material, substitution of proper and suitable
material and the removal and proper reaction not withstanding any previous test or
interim payment, therefore and of any work which in respect of material or
workmanship is not, in the opinion of the Engineer in accordance with the contract.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 120 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Guidelines on Quality Control Operations :-
The onus of achieving quality of work will be on the contractor who will take actions as
stipulated in Section 900 of Minister's Specification for Road and Bridge Works (2nd
The Ministry's specification for Road and Bridge work ( 2nd
Revision) will form part of
contract documents and the contractor will be legally bound to the various stipulations
made therein unless and otherwise specifically relaxed or waived wholly or partly
through a special clause in the contract document.
Contractor's Facilities :
According to the contract (see para 1.3 above ) the Contractor is responsible for the
quality of the entire construction work, and for this purpose he is required to have own
independent and adequate set-up. To meet this requirement a. The contractor shall set up his own laboratory at locations(s) approved by the Engineer.
The laboratory shall be equipped with modern and efficient equipment with sufficient
standbys suitable to carry our the tests prescribed for different materials and work
according to the specifications. The list of equipment to be procured and the facilities to
be provided shall be got approved by the Engineer. The equipment shall be maintained
in a workable condition to the satisfaction of the Engineer. b. Sampling and testing procedures shall be in accordance with the relevant standards of BIS
(Previously called 1ST) or IRC. Frequency of testing shall be as laid down in the Ministry's
Specifications for Road and Bridge Work (2nd
Revision). In the absence of relevant Indian Standards, sampling and testing procedures shall be as approved by the Engineer
c. The laboratory should managed by a qualified materials Engineer assisted by materials
Inspector / Technician, and the set up should be got approved by the Engineer. d. The contractor should prepare printed Performa for recording readings and results of
each type of test, after getting formats of the performance approved from the Engineer.
He should keep a daily record of all the tests conducted by him. Two copies of the test
results should be submitted to the Engineer for his examination and approval of which
one copy will be returned to the Contractor for being kept at site of work. e. The material Engineer of the contractor should keep close liason with the Quality Control Unit of
the Engineer and keep the later informed of the sampling and testing programmes so that the
Engineer's representative could be present during this activity, if considered necessary.
Day-to-day Quality Control Operations :-
The day-to-day controls to be exercised by the Contractor and the Engineer are
enumerated in the below paragraphs :-
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 121 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Alignment and Level Control:-
a. The contractor should locate the centre-line of the road from the pegs, pillars or reference
points fixed during the location survey and from the information furnished in the Contract
drawings. Any discrepancy between the reference points on the ground and those on the
drawings should immediately be brought to te notice of the Engineer for reconciliation.
b. Based on the approved centre-line the Contractor should set up batter pegs (to
delineate the limits of embankment/cutting and cleaning stakes and grubbing) and
have these got checked and approved by the Engineer.
c. The Contractor should check the reduced levels of bench marks setup along the alignment.
Any discrepancy in the reduced levels of those at site and as indicated in the drawings should
immediately be brought to the notice of the Engineer for reconciliation. The contractor should
re-establish those bench marks which are found missing at site, and should establish
additional bench marks as needed, for ensuring effective level control.
d. The Contractor shall be responsible for the true and proper setting out of the works in
b. relation to original survey points lines and levels of reference given by the Engineer in writing.
If at any time during the progress of the works, any error shall appear or arise in the position,
levels 'dimensions or alignment of any part of the works, the Contractor on being required to
do so by the Engineer, shall at his own cost rectify the error the satisfaction of the Engineer,
unless such error is based on incorrect data supplied in writing by the Engineer.
c. The Contractor shall carefully protect and prepare all bench marks, reference
pillars and pegs used in setting out the works till final take over by the Engineer.
NATURAL GROUND FOR EMBANKMENT CONSTRUCTION/CUT FORMATION AND THEIR COMPACTION :-
a. Unterberg limits, in site dry density and CBR of the material at ground/out formation level,
should be determined and got approved by the Engineer. Any unsuitable material shall be
removed and replaced by better material as ordered by the Engineer.
b. The Engineer's Quality Control Unit(s) shali have independent test checks on the
quality and compaction of the nature ground/cut formation.
c) Embankment Construction :-
a. All borrow area shall be got approved by the Engineer based on results of tests
for Unterberg Limits Proctor/modified proctor density, CBR and soil classification.
b. Layer thickness and in-situ density shall be checked and got approved by the
Engineer before processing to the next layer.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 122 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Sub grade :-
a. Specific borrow areas having soil satisfying the requirements of specifications and
specified strength criteria shall be indentified for use in subgrade and got approved by the
Engineer based on tests on borrow material for Proctor/modified proctor density and CBR.
b. In-situ density and CBR of the constructed subgrade shall be checked and got
approved by the Engineer before proceeding on with the next pavement layer.
c. The soil used in actual construction of subgrade shall be remolded at density
referred in sub-para (b) above at placement moisture content and checked for 4
days soaked and un soaked CBR. A set of 3 specimens shall be collected from
each 3000 m3 area of the sub grade (i.e. top 0.5 m of embankment for CBR test.
d. In case of any appreciable variation of inbuilt sub grade characteristics from the
designed ones, the pavement design shall be reviewed to mach the inbuilt
characteristics of the sub grade.
Sub-base :-
a. The Source of supply of material shall be inspected, tested and got approved by
the Engineer before any Material is delivered to site of work(s).
b. Job-mix formula falling within the specified limits where applicable, shall be got
approved by the Engineer based ontest results there of.
c. Samples of materials from the laid sub-base shall be tested for gradation, proctor
density, PI and CBR,
d. Field compaction shall be checked and got approved by the Engineer before
proceeding with the work on the next payment layer.
e. In case of any appreciable variation of inbuilt sub-base characteristics from the
designed ones, the pavement design shall be reviewed to match the inbuilt
characteristic of the sub-base.
Granular Base Course :-
a. For graded type of granular material, the job mix formula falling within the specified
grading limits should be got approved by the Engineer. b. Testing of aggregate brought to site of works for gradation AIV should be done. c. Testing of filler material for WBM for gradation LL and PI shall be done. d. Field compaction- control should be exercised for density and by other sensory checks such
as observation of movement of layer under compaction plant, sinking/crushing of a piece of
aggregate placed before a moving roller completes removal of roller marks etc.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 123 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Shoulders :- a) Checking for the quality of shoulder materials including gradation shall be done. b) Field compaction shall be checked at site on the compacted layer. c) Checking for the cross fall built shall be done.
Bituminous Construction -General :-
a. Manufacturer's test certificate for quality of bitumen will be acceptable to the
Engineer. However, where the quality is in doubt, the Engineer may call for tests to
be conducted by the Contractor for verification. b. The base on which bituminous courses are to be laid must be'dry and free of dust
and other delirious matters. c. Mineral aggregates to be used should be checked for their specification
requirements and got approved by the Engineer.
Bituminous sprayed work :- a. Temperature of binder in the boiler and rate of spray at site shall be checked. Spraying shall
be uniform and shall be carried out with the help of either self propelled or towed bitumen
pressure sprayer with self heating arrangements and spraying nozzles
arrangements. b. Rate and uniformity of spread of chippings should be checked and controlled. c. Adequate embedment of the chippings by rolling shall ensured.
Hot Mixed and Hot-laid Bituminous Construction :-
a. Job mix formula (JMF) satisfying specification requirements should be worked out
based on laboratory tests and got approved by the Engineer. The Engineer will
have independent test made before approving the JMF. b. The plant should be checked for capability to produce mix conforming to the JMF. If
necessary, trial stretches should be laid and checked approximately. c. Control should be exercised on temperature of binder in the boiler, aggregate in the
dryer and mix at the time of laying and rolling. d. Tests for stability flow, unit weight etc, of mix collected from the discharge point of
the plant, extraction test for binder content and aggregate gradation should be
performed to check on the quality of mix discharged fom the plant. e. Thickness and density of the compacted mix should be checked by taking core samples.
Culverts and other Appurtenances :- a. Lines, levels and quality of the foundation should be checked. b. In case of Pipe culverts :-
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 124 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
i. The quality of the pipes should be checked. For BIS (formerly ISI) marked pipes,
manufacturer's certificated is acceptable. For others, the Contractor shall
demonstrate the strength capability of pipes through! tests either at the place of
manufacture or at site of works.
ii. The quality of Materials used for pipe bedding should be checked. Invert level, smoothness
of the pipeline and proper sealing of joints should be checked prior to backfilling.
c) In case of cement concrete works :-
i. Besides manufacturer's test certificate for quality of cement, at least one set of
physical and chemical tests should be conducted for each source of supply for
verification. Where the quality is in doubt, or where the cement had been stored
for long periods or in improper condition, the Engineer shall call for testing the
cement at more frequent in tervals.
ii. Job mix formula worked out based on trials carried out in the Contractor's laboratory should be got approved by the Engineer.
iii. The mineral aggregates should be tested for their properties. Water to be used
for mixing should be tested for chemical impurities. iv. Checking for stability and sturdiness of form work.
v. Ensuring that the crucial equipment like mixers and vibrators are in working
order before start of work. vi. Control on water-cement ratio. vii. Control on workability and time elapsed between mixing and placing of concrete. viii. Control on compaction and finishing, ix. Tests on cube samples at 7 and 28 days. x. Check on provisions for adequate curing.
xi. In case of masonry work, control should be exercised on the quality of the
material (e.g. stone, brick, sand cement etc.) as also on mortar proportions,
d) For RCC work, quality of steel in each batch may be approved on the basis of
test certificate. The reinforcement layout should be checked for conformity with
approved drawings and bar bending schedules. All laps should checked for
conformity with the specification. The reinforcement should be free of oil and
loose rust scale and should be properly tied with binding wire. The size and
spacing of the bars as also the cover should be checked for correctness.
Pavement Courses - General Controls :-
a. The base on which the pavement layers to be placed should be checked for levels and regularity, and should be in a condition to receive the pavement layer.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 125 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
b. Each layer should be checked for thickness, levels, crossfall (camber), regularity
and strength before next layer is permitted to be laid.
12) DRAWINGS :- Contract Drawings :-
The contract drawings provided for tendering purpose with the tender documents shall
be used as a reference only. Contractor should visualize the nature of type of work
contemplated and to ensure that the rates and prices quoted by him in the bill of
quantities take due consideration of the complexities of work involved during actual
execution/construction as experienced contractors in the field. The tendered rates / prices for the work shall be deemed to include the cost of
preparation, supply and delivery of all necessary drawings, prints, tracings and
negatives which the contractor is required to provide in accordance with the contract.
DOCUMENTATION :-
If so ordered by the Engineer in charge the contractor will prepare drawings of the work
at constructed and will supply original and three copies to the Engineer who will verify
and certify these drawings. Final as constructed drawings shall than be prepared by
the Contractor and supplied in triplicate along with a micro-film of the same to the
Engineer for record and reference purposes at the contractor's cost.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 126 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
MANNER OF SUBMISSION OF TENDER AND ITS
ACCOMPANIMENTS
SPECIAL ATTENTION TO CONTRACTOR
As the contract includes works of Electrical Installation with civil work. The Civil contractor not
having the registration of carrying out above mention electrical and allied works shall go in for
joint venture with valid A to B electrical contractor registered with Maharashtra state P. W.
Dept. or can be the respective electrical and allied works to the eligible class contractor the
agreement should made with concern agencies till ending over of work and copy of the same
should be enclosed in an .envelope No. 1. However the responsibility of whole work
(Civil, electrical & allied work) lies with the Civil Contractor only. Performance guarantee shall be submitted in the proforma attached envelope No. 1 and which
will be binding for 3 years. Security Deposit lithe form of Bank guarantee or fixed /call Deposit
should be submitted which will be refundable after successful completion of comprehensive
maintenance once of three years after commissioning of installation / system.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 127 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
SPECIAL CONDITIONS FOR ELECTRICAL WORKS.
As required by the rule 45 of the Indian Electricity rule 1956, Electrical Installation
works shall be carried out by an Electrical contractor licensed by the Licensing Board
of the state Government in this behalf and registered in as appropriate (A ) & (B) Class
with public works Department and under the direct supervision of a person holding
certificate of competency issued by the Licensing Board.
There shall be a written agreement order between the main civil contractor and the electrical
contractor, latter shall give the intimation of starting of work to the Electrical Inspector as required by
the rules and conditions issued by the I.E & L Department under the Rule 45 of the I.E . Rule. The wiring and the other electrical works shall conform to the I.E. Rules. The materials
used for electrical works shall comply with the standard laid down in that behalf by the
Bureau of Indian Standard
The contractor shall also arrange to receive service connections and meters from the
MSEDCL by paying necessary charges as per the supplier's conditions. The payment
towards service connection charges made by the contractor is reimbursable on
production of the necessary documentary evidence of payment.
As soon as the Electrical installation works is completed in all respect and tested by the
electrical contractor, the Contractor should submit to the MSEDCL the installation test
report in the form prescribed by the MSEDCL for releasing the Electrical supply.
All Electrical works shall be clamed out under the direction of the Executive Engineer (Electrical)
public works department and completion certificate be obtained for effecting payment. All Civil engineering works such as foundation of various motors, compressors,
switchgears, panels and making and finishing of holes and recess in the walls/ ceiling
for ducting, pipe line, plumbing etc. necessary for completion of Electrical works shall
be carried out by the electrical contractor in an approved manner.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 128 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
DOCUMENTS TO BE ENCLOSED IN ENVELOPE NO. 1 FOR
ELECTRICAL WORKS Sub work :- For Electrical Installation
i. In case of partnership firm, attested copy of partnership deed and in case of
company attested copy of Memorandum, & article of association and power of
attorney should be attached. ii. The documents showing annual turnover of minimum iii. Attested Photostat copy of valid Electrical contractor valid license. iv. Attested Photostat copy of valid "A & B" class P.W. D. Registration certificate in
Maharashtra State.
2. SCOPE OF WORK.
Scope of work covered under this tender shall be as mention but not limited to following . 1. Internal Electrification design, supply, installation, testing & commissioning.
2. Supply, installation testing and commission of Elevators.
3. The necessary permission along with the approved plans for electrical
instillations, be got approved from appropriate authority on completion of the
works submitted to Engine in charge.
4. The electrical supply for the other activities than those have to be obtained
separately from Electric supply company by the contractor
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 129 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
PREFACE
All the Electrical work shall be carried out as per.
i. The relevant Indian standards formulated by Bureau of Indian standards New Delhi
ii. Indian Electricity Rules 1956 (Revised )
iii. National electrical code
iv. Chapter 16 of PWD Hand Book Government of Maharashtra
v. Bombay Lift Act. 1939 / Bombay Lift Rules. 1958
vi. Development control Regulations.
vii. Development control Regulation of Mahatashtra state and rules of local bodies
pertaining of e.i. works including fire Alarm system, fire fighting system public
announcement system, lift etc.
Intent of Specification.
This specification covers complete design, supply, installation, Testing & commissioning of total
electrical work. Scope of work covered under this tender shall include design, supply of the
necessary equipment installation, erection testing and commissioning of the system. All
electrical work shall be carried out in accordance with these specifications. These specifications
shall be read in conjunction with the relevant Indian standards, NEC India electricity I. E. Rules,
Chapter 16 of PWD Handbook and Development control rules of Govt, and local Authorities,
the work shall be executed according to most stringent of these requirements.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 130 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
1.3 Standards
The following standards shall be applicable:
Specification for electrical installation
Sr. No. Particulars IS. No. 1. Electric wiring shall be with copper wiring 732
2. Protection such as M.C.B.M.C.C B. & Breakers. Etc. 8828 3. Switches 4949 4. Electric fans 2997 5. Exhaust fans for Kitchen or any smoke 4283 area/
bathroom/toilet.
6. Electronic type fan Regulator 11037 7. Electrical Lamp and their Anxieties 13021 Part 1 & Part II 8. Tubular Florescent Lamp 2418 Part I, II & III 9. Appliance Connected inlets 3010 Part I & II 10. Box for Enclosure of Electrical accessories 5133 11. Box for Enclosure ceiling rose 371
12. Conduit for E.I. 9537 Part iii PIV 13. Plug and socket outlets per rated Voltage up 250V. 1293 to and Including
current 16A.
14. Switch for domestic and similar purpose 3458 15. Electric call bells and buzzers 2268 16. Electric water boilers. 3412 17. Code of practice of Earthing 3043 18. Code of practice as per the projection of buildings 2309
and allied structures against lighting
19. Dangers notice plates 2555 20. Guide for electrical layout in residential building 4648 21. Chart on treatment for electric shock Sp35 22. National Electrical code Sp30 23. Warning symbol for dangerous Voltages. 8923 24. AC Electric Meters 722 Part 3, 5, 6, 7, 88, 9 25. Electric lighting fitting 4053 26. Current transformer 2705 Part 1 To 4 27. Code or practice for selection installation and 100 II8 Part I to 4
maintenance of switches and controller
28. Power cable --
29. Bus glands for PVC Cable 12943 2.conductors tor insulated electric cable and flexible
cords
3. Cross linked polyethylene insulated PVC
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 131-
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
WIRING ON SURFACE OF WALL/CEILING
1) Wiring in PVC casing capping
PVC casing n-capping type wiring to be adopted with its accessories such as T, bends elbows
etc. PVC casing -n-capping and its accessories shall be confirm to IS 14927 part I The route of
casing - n-capping on wall and ceiling should be approved prior to fixing, by Engineer in charge.
2) Wiring in PVC conduit
Conduit wiring system with rigid Non -metallic conduit to be fixed on wall and ceiling as per design
requirement The conduit shall confirm to Is 9537 (part -3) and corresponding accessories shall
confirm to Is 3419 conduits shall be joined by means or compiling . for long run, on junction
inspection type couplers junction boxes shall be provided at intervals not exceeding junction.
BUNCHING OP INSULATED WIRES
1) Conductors for concealed and wiring on surface of wall ceiling in conduits shall be bunched. The number of insulated cables that may be drawn into single conduit is given in the following table. In this table the space factor should not exceed 40%
Size of conduit (mm ) outside diameter Nominal cross section area 20 25 32 38 50
sq.mm. No. of cable Max.
2.5 5 10 14 —
4.0 3 6 10 14 —
6 2 5 8 1 1 —
10 4 7 9 —
16 — 2 4 5 12
25 2 2 6
35 — — — 2 5
50 2 3
Design of wiring , mains shall be such that voltage drop shall be limited to 1% of the system voltage for single phase & 1.5% of the system voltage for motor load like pumps lifts etc and 2%
of the system "voltage for other three phase loads. 1) Conductors for surface wiring in casing N -capping shall be restricted to occupy not more than 60% the space casing -capping on it fixing position' on wall ceiling .
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 132 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
LIST OF APPROVED MATERIALS TO BE USED ON WORK.
1. PVC cables (aluminums) Finolex. RR cable, Kay dour 2. PVC insulated copper wires Finolex, Polycab,RR Cable ,
Indonet / Indoplast 3. PVC Rigid conduits Finolex Diamond d. Modi 4. 6A. 16A.Modular type switches 7 sockets with Anchor Roma,
silver contacts, ceiling Rose, Holders Buzzers Bell
push Bells.
5. Distribution boards, MCB s 9KVA MDS Legrand, Hager, indo , Asian (L& T) Siemens GE, Standard
6. ELCB /RCCB /MCB GE standard MDS Legrand, (L& T) Siemc
7. Electrical fittings (Fluorcescent, CFL . MV Metal Philips. GE Bajaj. Crompton halide etc, Fixolite Crom
8. Ceiling fans. Exhaust Fans Crompton, Orient, Havells 9. 6A/16A Switches, socket, 5x1 Kalki. Vijay, Ketco 10. Single phasing perverted L& T, Jaguar, Minilee 11. CFL Accessories Bajaj, Philips, Orpat 12. Switchgear Kalki. Standard. Joshica, CPL 13. M CB Isolator Simence, LT, Havells 14. PVC Casing-N –capping Diamond, Modi, Prestoplast, 15. Fluorescent Tubes & Bulbs Philips, crompton, Bajaj, wipro
Surya 16. Electrical Fan Regulators! Step type Anchor Roma. MDS 17. Measuring instruments AE IMP, Meco 18. CTs AE , IMP Meco, Siemens,
Indcoil 19. Indication Lamps L&T Technique 20. HRC switch Fuse unit GEC. L&T. 21. Cable Gland and lugs Siemens, Dowels, 22. Industrial sockets Crompton, MDS, Siemens,
Hammer. 23. Water heaters. Racold, Bajaj
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 133 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
MINIATURE CIRCUIT BREAKERS DISTRIBUTION BOARD ;
Distribution boards along with the controlling Mobs /Fuse or Isolator as shown shall be
fixed in sheet steel enclosure suitable for recessed mounting in wall . Distribution
boards shall be made of 16SWG sheet steel duly rust inhibited through a process of
degreasing acid prickling and spray painted to approved color over a coat of red oxide
primer Three phase boards shall have phase barriers and a wire channel on three
sides Neutral bar shall be a solid tinned copper bar with tapped holes and chase
headed screws. For 3 phase DBs Independent neutral bars shall be provided.
All DB's shall be internally pre-wired using PVC insulated copper wires brought to a
terminal strip of appropriate rating for out going feeders.
Conduit knockouts shall be provided as required/ shown on drawings ana the entire
boards shall be rendered dusts and vermin proof with necessary rubber gaskets.
MCB's shall have quick make and break non welding self wiping silver alloy contacts
for 10KA short circuit both on the manual and automatic operation. Each pole of the
breaker shall be provided with inverse time thermal over load and instantaneous over
current tripping with trip free mechanism. In case of multi pole breakers, the tripping
must on all the poles and operating shall be common to Is 8828 -
Pressure clamp terminals for stranded / solid conductor insertions are acceptable up to
4sqmm. Aluminum or 2.5sq.mm copper and for higher ratings, the terminals shall be
suitable shrouded wherever MCB isolators are specified they are without the tripping
elements-Fuses shall be HRC links Bottle type fuse are not acceptable fuse carrier
terminals shall be suitable shrouded rewritable fuse Carrier shall be porcelain. Distribution boards shall have HRC/ Rewritable fuses as shown on the schedule and drawing. Board
shall meet with the requirements of Is 2675 and making arrangement of bus bars shall in
accordance with IS375 bus bars shall suitable for the incomer switch rating and sized for
temperature rise of 35% C over the ambient. Each board shall have two separate earthing terminals.
Circuit diagram indicating the loan distribution shall be posted on the inside of the DBs as instructed
one earthing terminal for single phase and two terminals for Sphase DBs shall be provided with an
Earth strip connecting the brass studs and the outgoing ECC earth bars.
In case of MCB distribution boards the backup fuses wherever shown shall be not less than
63A. With delayed characteristic and a minimum pre arcing time of O.Ssec at 9KV fault current.
All outgoing feeders shall terminate on a terminal strip which in turn is inter connected
to the MCB /Fuse base by means of insulated single conductor copper wire as follow.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 134 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Up to 15 Amps. - 2.5sqmm.
25 Amps - 4.0 sq mm
63 Amps. 10 sq mm.
EARTHING :-
Earthing shall be done In accordance with IS 3043 of 1987
Systems of earthing .
Equipment and portion of installation shall be deemed to be earthed only if earthed in
accordance with the directed earthing system. In all case, the relevant provisions of
'Rules 33 and 61 of the Indian Electricity Rules 1956 shall be complied with.
EARTH ELECTRODES
A. Type :- Earth plate electrodes shall be provided and they shall not be less than 60
cm x 60 cm x 60 mm copper as per clause 9.2of IS -3043 B. Installation :- Electrodes shall as far as possible, be embedded below permanent
moisture level. In addition, they shall be buried at a depth of not less than 3m. complete
installation shall be as per IS 3043 and as per plate no. 4 of chapter 16 of PWD handbook.
C . Copper earth plate of 60cmx60cmx6mm. shall be buried In
Specifically prepared earth pit so as to keep top of earth plate "3M below ground with
40Kgs each charcoal and salt (with alternate layers of charcoal and salt) with 19mm.
dia. Gl ;pipe provided with funnel with a wire mesh for watering and brick masonry
block. Cl cover etc. complete as per para. 9 of Is 3043 of 1987
With necessary length of double copper earth strip of adequate size bolted with lug to the plate
and covered in adequate size Gl pipe 2.5m long compete connected to the switch gear with
end socket as per direction and duly tested by earth tester and recording results. Distance
between two earth pits shall not be less than 6 mtrs. i. e. double the depth of each Electrode
General Rule Applying to All system .Ms. of Earthing Method of earthing .
A) Connection of earthing conductors.
1. Main earthing copper strip shall be laid from the earth station provide in the sub
station HT equipment. VBC stabilizer, and Transformer shall be earthed in the
substation as per the provision of IS 3043-1987. 2. Main LT panel connection shall be taken from earth electrode provided near main
L.T. panel room.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 135 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
3. There will be copper strip of vertical riser from the earth pits independently
provided for earthing of distribution floor panels located at different floors. 4. Interloping of sub panels to room DBS shall be done with PVC insulated copper
con doctor of appropriate size.
B) Cable sheathing and armoring - These shall be earthed at the ends adjacent to switch boards at which they originate or
other wise at the commencement of the run by an earthing conductor connected to an
earth clip, clamp or gland ineffective electrical contract with cable sheathing and armoring.
Earthing conductor-
Every earthing conductor shall be either stranded strips or circular Or rectangular bar.
Protection against mechanical injury shall be provided where necessary.
The earth conductor may be of high conductivity copper The sizes of earthing
conductors shall corresponds to the load current as given below. Size of earth
conductor form main switchboard to sub main switches or DBS.
Cross sectional area of Cross sectional area of current
Current carrying conductor Carrying
Copper Conductor copper
( Sq. mm ) (Sq. mm ) ( Sq. mm )
4 4 12
6 4 12
10 6 10
16 10 8
25 16 8
35 16 8
50 25 6
70 35 2
95 50 20x3mm
120 70 25x3mm
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 136 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Size of earth conductors of plug sockets for the use of portable appliances.
Cross sectional area of current Cross sectional area of earth Carrying conductor copper / continuity Conductor Copper (SWG )
Aluminum (sq mm )
2.5 14
4 12
6 12
Cables :- Design aspect-load, length. Voltage drop
Switchgears:- Protection - rating S.C. rating nominal rating, back up etc. MCB/ MCCB / ELCB/RCCB. The contract includes 3 years comprehensive maintenance period for Electrical Installation after completion of the work. •
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 137 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
Scope of Work:-
1. Stand by arrangement for maintenance shall have to be done by the contractor incase of any
BANDH OR STRIKE OR MAJOOR BREAKDOWN so as to get an uninterrupted service. 2. If any part of the complete system is modified or altered with change in design/
concept the contractor for the Executive Engineer will terminate that particular
item /full. In case of fatal or non- fatal accident occurred to the workers during
erection and maintenance of system, the Department will not be liable to pay for
an compensation and it is duty of contractor to observe all labour Acts and Rules.
WORKING PROCEDURE 1. All complaint/calls shall have to be attended by contractors workers wHhin reasonable time
and with .fastest possible speed but in any case , it shall not be extended beyond 24 hours. 2. Log Book has to be maintained by the contractor at site.in consultation with the site Engineer.
3. Inspection :- Inspection not with completion reports shall have to be maintained in
duplicate by the contractor mentioning all work details and to be signed by contractors
Representatives and site in charge by handing over one copy to site in charge. 4. Periodicity within monthly shall have to be made with respect to work order
schedule for regular servicing and inspection and repair if any reguired. 5. The Contractor shall preferably obtain the signature of Engineer in charge after
attending the breakdown calls and inspection / servicing and all work should be
carried out with knowledge to in charges 6. Daily comprehensive contract covers work of replacement of unserviceable/
defective operational .parts, moving parts switchgears related in the
system, control cables and switchgears etc. 7. The contractor has to maintain cleanliness towards respective system, sufficient
safety, sufficient safety, ethics and politeness in behaviour by him staff.
DAILY COMPREHENSIVE CONTRACT COVERS
1. Work of repair of replacement of unserviceable operational parts or moving parts such
as motor, car rope to be governed, gear box , pulley, contact relays, switchgears etc.
2. Replacement of consumable items such as bulbs, fuses, control cables, lugs,
locks with keys etc, and also lubricants, service materials. 3. Replacement of gear box oil in periodically with test result.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 138 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
4. Cleaning of all necessary parts periodically with help of required materials with
respect to method of construction / servicing to be decided with Engineer In
charge checking of system and alignment and overhauling.
5. Complete installation, machine room lift pit etc. shall be maintained neat and in
clean manner every day.
6. Painting shall be done once in a year for complete machinery including moving
and non moving parts 7. Rewinding of motor and all its preventive maintenance. 8. Monthly regular servicing and inspection shall be carried out.
SEQUENCE OF WORK
Preliminary activities like hutment for labours, site office, steel yard for C. P. C. C. » treatment. Cement godown etc.
Casing or R.C. C. raft slabs, columns for lift well.
Casing or R.C. C. Columns from pit cap level.
B.B. masonry for shopping complex plinth work.
Filling soling. P.C.C. for shopping complex plinth work
Pre-constructional Antitermite Treatment.
Construction of under Ground Tank.
Casing of R.C. slab at 2.75 meter (above stilt level of Main Building.)
Soiling. P.C. C. concrete pavers block below stilt portion of main Bldg.
Casting of R.C. C. slab for shopping complex at 4.20 M. level.
B.B. masonry fixing of doors and windows frame inside plaster, flooring.
Casting of R.C.C. slab of ground floor of Main Building at 6.40M. level.
Laying under ground pipe for Electrical Telephone, computer wiring
B.B. Masonry fixing of doors, and Windows frame inside plaster flooring.
Internal wiring of stilt, ground floor laying cable in meter room and laying fire alarm cable
.
Casting of R.C. slab of first floor of main Building at 9.70 Meter level.
Laying under ground pipe for Electrical, Telephone, computer wiring.
Internal wiring of first floor laying cable from meteSr room and laying firfe alarm cable.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 139 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
B.B. Masonry fixing of doors and windows frame inside plaster, flooring.
Casting of R.C. C. slab of 2n floor of main Building at 13.00 M. level.
Laying under ground pipe for Electrical. Telephone, computer wiring.
Internal wiring of second floor laying cable in meter room and * laying fire alarm cable.
B.B. Masonry fixing of doors and windows frame inside plaster, flooring.
Casting of R.C. C slab of 3rd
floor of main Building at 16.30M level
Laying underground pipe for Electrical, Telephone, computer wiring.
Infernal wiring of Third floor laying cable from meter room and laying fire alarm cable .
B. B. masonry fixing of doors and windows frame inside plaster flooring.
Casting of R.C.C. lift Machine Room slab.
Laying pipe for fire fighting system and erection of lift
External sand lace plaster.
Internal water supply and sanitary fittings. .
External water supply and sanitary fittings.
Internal painting from stilt to 3rd floor,
Providing (an fitting and smoke detector.
External, drainage line system. Compound wall with security cabin. Providing switchgear in meter room.
Construction of pump House.
Providing pumps and generating set.
Construction of Rainwater Harvesting Tank
Providing gardening.
C.C. Pavement for car parking and upper area.
External at painting.
Release of electrical supply from supply company and trial.
Handing over the building.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 140 -
Proposed Construction of Agriculture College Building & infrastructure Facilities, At Halgaon
SCHEDULE B
Memorandum showing items of work to be carried out.
Tendered rates Total Quantities amount
Items estimated
Item of In figures In words
according but may be Unit No. more or Work Rs. Ps. To
estimate less.
quantities
See separate sheets attached
NOTE 1 :- All work shall be carried out as per Public Works Department Hand Book & Standard Specification of the division or directed and as per
specification five in chapter no. 11.
NOTE 2 :- Rates quoted include clearance of site (prior to commencement of work and at its close) in all respect and hold good for work under all site condition, moister weather etc.
Signature of Contractor No. of Corrections University Engineer
Mahatma Phule Krishi Vidyapeeth, Rahuri - 141 -