Upload
others
View
11
Download
0
Embed Size (px)
Citation preview
Maintenance Task Schedule
Comparison of Changes - pre and post November 2012
Added changes
November 2012
Whilst reasonable steps have been taken to ensure that the information contained within this report is correct, you should be aware that the information contained within it may be incomplete, inaccurate or may have become out of date. Accordingly,
B&ES Publications make no warranties or representations of any kind as to the content of this report or its accuracy and, to the maximum extent permitted by law, accept no liability whatsoever for the same including, without limit, for direct, indirect or
consequential loss, business interruption, loss of profits, production, contracts, goodwill or anticipated savings. Any person making use of this report does so at his or her own risk [and it is recommended that they seek professional advice from their
own adviser whenever appropriate].
Table Of Contents
Groups Maintenance Task Schedules
Page 1: ACTUATORS
Page 3: AIR HANDLING UNITS
Page 5: BOILERS/HEAT GENERATORS
Page 13: BUILDING MANAGEMENT SYSTEMS
Page 18: CHILLERS - WATER
Page 22: COLD ROOMS AND FOOD STORAGE
Page 24: COMMUNICATION AND P.A. SYSTEMS
Page 26: COMPRESSORS - REFRIGERATION
Page 30: CONDENSERS
Page 32: CONTROL PANELS & CONTROLLERS
Page 44: DUCTING
Page 46: EVAPORATORS
Page 48: FANS
Page 56: FILTERS
Page 58: FIRE ALARM SYSTEMS
Page 64: FIRE PROTECTION SYSTEMS
Page 83: GRILLES AND DIFFUSERS
Page 85: HAZARDOUS AREA (ELECTRICS)
Page 89: HEAT EMITTERS
Page 95: HEAT EXCHANGERS
Page 98: HEAT REJECTION SYSTEMS
Page 102: HOT WATER SUPPLY
Page 107: HUMIDIFIERS INCLUDING DISINFECTION PROCEDURES
Page 111: ICE MAKING MACHINES
Page 113: INSULATION
Page 115: LIGHTING
Page 118: LIGHTNING PROTECTION
Page 120: PIPEWORK SYSTEMS
Page 127: PORTABLE EQUIPMENT
Page 130: POWER GENERATORS
Page 135: POWER SUPPLIES
Page 141: PUMPS
Page 150: REFRIGERANT DISTRIBUTION SYSTEM
Page 153: ROOM AIR CONDITIONERS
Page 155: SANITARY AND WASTE WATER PLUMBING
Page 159: SECURITY SYSTEMS
Page 161: SENSORS AND SWITCHING DEVICES
Page 163: SHOWERS
Page 165: SMOKE EXTRACT
Page 168: SOLAR PANELS
Page 170: SPLIT SYSTEMS INCLUDING HEAT PUMPS
Page 174: STARTERS
Page 182: STORAGE TANKS
Page 188: SWIMMING POOLS
Page 197: SWITCHES
Page 199: TERMINAL UNITS
Page 204: VACUUM SYSTEMS
Page 207: VALVES
Page 209: VENTILATION ANCILLARIES
Page 215: WATER TREATMENT
Page 218: WHIRLPOOLS-HYDROTHERAPY
Page 2: 01-04 PNEUMATIC ACTUATORS
Page 4: 03-01 AIR HANDLING UNITS - general
Page 6: 05-07 COAL FEED MECHANISMS - Under feed stokers
Page 7: 05-09 ASH HANDLING SYSTEM
Page 8: 05-13 FORCED DRAUGHT [PRESSURE JET] OIL CONDENSING BOILER
Page 9: 05-20 STEAM BOILERS Maintenance schedule.
Page 11: 05-26 WASTE AND WOOD BURNING APPLIANCES (including boilers) - Combustion Chamber
Page 12: 05-27 WASTE AND WOOD BURNING APPLIANCES (including boilers) - BOILER (if fitted)
Page 14: 06-03 BUILDING MANAGEMENT SYSTEMS - Central Operator Station
Page 15: 06-04 BUILDING MANAGEMENT SYSTEMS - COMMUNICATIONS
Page 16: 06-05 BUILDING MAINTENANCE SYSTEMS - OUTSTATIONS
Page 17: 06-06 BUILDING MANAGEMENT SYSTEMS - SOFTWARE FUNCTIONS
Page 19: 09-02 PACKAGED CHILLER UNITS
Page 20: 09-03 LITHIUM BROMIDE/WATER ABSORPTION CHILLERS
Page 21: 09-04 GAS FIRED ABSORPTION CHILLER UP TO 18 KW COOLING CAPACITY
Page 23: 10-01 COLD ROOMS
Page 25: 11-01 COMMUNICATIONS - PUBLIC ADDRESS SYSTEMS
Page 27: 12-01 COMPRESSORS REFRIGERATION - Reciprocal - (includes hermetic, semi-hermetic and open)
Page 28: 12-02 COMPRESSOR - SCREW
Page 29: 12-03 COMPRESSORS REFRIGERATION - CENTRIFUGAL
Page 31: 13-01 CONDENSERS - water cooled
Page 33: 14-03 CONTROL PANELS - lamps, meters, alarms etc.
Page 34: 14-06 SINGLE INPUT CONTROLLER
Page 35: 14-07 UNIT CONTROLLERS AND SENSOR CONTROLLERS
Page 36: 14-08 CONTROLLER TIMERS
Page 37: 14-09 STEP CONTROLLERS
Page 38: 14-10 TIMESWITCHES
Page 39: 14-11 MULTI-INPUT CONTROLLERS
Page 40: 14-12 INDICATORS AND DISPLAYS
Page 41: 14-13 ALARM MODULES
Page 42: 14-14 LEVEL CONTROLLERS
Page 43: 14-16 TRANSDUCERS - pneumatic to electronic and electronic to pneumatic
Page 45: 16-02 DUCTWORK SYSTEM - GENERAL
Page 47: 19-01 REFRIGERATION EVAPORATORS
Page 49: 20-02 FANS - VENTILATING - general
Page 50: 20-03 FANS -CENTRIFUGAL
Page 51: 20-04 FANS- AXIAL
Page 52: 20-05 FANS - PROPELLER
Page 53: 20-06 FANS-MIXED FLOW
Page 54: 20-07 FANS-BIFURCATED
Page 55: 20-08 FANS-EXTRACT - including fire/smoke extracts units
Page 57: 21-02 AIR FILTERS
Page 59: 22-01 FIRE ALARM SYSTEM
Page 65: 23-03 HOSE REELS - Static or Swinging
Page 66: 23-04 RISING FIRE MAINS and HYDRANTS
Page 67: 23-05 Gas Extinguishing systems
Page 68: 23-06 CARBON DIOXIDE TOTAL FLOODING FIRE EXTINGUISHING SYSTEM
Page 69: 23-07 EXPANSION FOAM SYSTEMS
Page 71: 23-08 FIRE EXTINGUISHERS - GAS SUPPRESSION (Halon)
Page 72: 23-09 FIRE EXTINGUISHERS - CARBON DIOXIDE
Page 73: 23-10 FIRE EXTINGUISHERS - FOAM (Stored Pressure)
Page 75: 23-11 FIRE EXTINGUISHERS - POWDER (GAS CARTRIDGE)
Contents Page 1 of 3
Page 78: 23-12 FIRE EXTINGUISHERS - WATER - GAS CARTRIDGE
Page 80: 23-13 FIRE EXTINGUISHERS - WATER STORED PRESSURE
Page 82: 23-14 SPRINKLER SYSTEMS
Page 84: 26-01 GRILLES AND DIFFUSERS
Page 86: 27-03 Hazardous areas - LIGHTING
Page 87: 27-04 Hazardous areas - EARTHING
Page 90: 28-01 HEAT EMITTERS
Page 92: 28-02 GAS FIRED CERAMIC PLAQUE INFRA RED HEATERS
Page 93: 28-03 GAS RADIANT TUBE HEATERS
Page 94: 28-04 GAS FIRED NATURAL AND FAN ASSISTED HEATERS - Conventional and Balanced Flue.
Page 96: 29-01 HEAT EXCHANGERS - COILS
Page 97: 29-02 ELECTRIC/AIR HEATER
Page 99: 30-02 COOLING TOWERS - Precautions against Legionnaires disease (legionella pneumophila)
Page 101: 30-03 DRY COOLERS
Page 103: 32-06 HOT WATER CALORIFIERS HEATED BY MTHW, HTHW or STEAM
Page 104: 32-07 HOT WATER SUPPLY CALORIFIERS
Page 105: 32-09 HOT WATER CYLINDERS
Page 106: 32-11 THERMAL STORAGE CYLINDER (individual dwellings for DHWS)
Page 108: 33-02 HUMIDIFIER - Direct steam injection type.
Page 109: 33-04 HUMIDIFIERS- Compressed air type
Page 110: 33-05 HUMIDIFIERS- Ultra sonic
Page 112: 34-01 ICE MAKING MACHINES
Page 114: 35-01 THERMAL INSULATION
Page 116: 36-03 LIGHTING FITTINGS including LUMINAIRES general
Page 117: 36-04 EXTERNAL LIGHTING including ILLUMINATED SIGNS
Page 119: 38-01 LIGHTNING CONDUCTOR AND EARTH
Page 121: 40-01 PIPEWORK SYSTEMS - General
Page 122: 40-08 AIR COMPRESSORS AND RECEIVERS
Page 124: 40-09 AIR COMPRESSORS Compressed air dryers
Page 125: 40-10 PIPEWORK FOR LOW PRESSURE NATURAL GAS, LIQUEFIED PETROLEUM GAS (LPG) OR OIL
Page 126: 40-11 STEAM SERVICES
Page 128: 42-01 PORTABLE APPLIANCE TESTING (PAT)
Page 131: 43-02 POWER GENERATION--STAND-BY GENERATOR
Page 134: 43-03 BATTERIES - LEAD ACID - unsealed
Page 136: 44-02 MAIN SWITCH PANEL AT SUPPLY INTAKE
Page 137: 44-05 POWER DISTRIBUTION UNIT (PDU)
Page 138: 44-06 EARTHING
Page 139: 44-07 DISTRIBUTION BOARDS
Page 140: 44-08 ELECTRICAL INSTALLATION - GENERALLY
Page 142: 45-01 PUMPS - General
Page 143: 45-02 CIRCULATING PUMPS-general
Page 144: 45-03 CENTRIFUGAL PUMPS
Page 145: 45-04 PRESSURISATION PUMPS
Page 146: 45-07 SEWAGE OR DRAINAGE PUMPS SUBMERSIBLE
Page 147: 45-08 SEWAGE and DRAINAGE PUMPS: DRYWELL
Page 148: 45-10 SUMP PUMPS: EXTENDED SHAFT
Page 149: 45-12 WATER PUMPING PRESSURE BOOSTING SETS
Page 151: 46-01 REFRIGERANT DISTRIBUTION SYSTEM
Page 154: 47-01 ROOM AIR CONDITIONERS
Page 156: 48-03 INTERCEPTORS - Petrol and Oil
Page 157: 48-05 SANITARY, WASTE WATER PLUMBING and DRAINS
Page 158: 48-08 SANITARY AND WASTE WATER PLUMBING - WATER SAVING DEVICES and METERS
Page 160: 49-01 SECURITY SYSTEMS-INTRUDER ALARMS
Page 162: 50-11 GAS DETECTOR SENSORS
Page 164: 51-01 SHOWERS
Page 166: 52-03 SMOKE RELIEF - Powered smoke and heat exhaust ventilators
Page 167: 52-04 SMOKE CURTAINS
Page 2 of 3
Page 169: 53-01 SOLAR HOT WATER PANELS and similar COLLECTING DEVICES
Page 171: 54-02 DX SPLIT SYSTEMS - with gas, electric or hot water heaters
Page 172: 54-03 SPLIT SYSTEMS/ HEATPUMPS – air-cooled with direct expansion evaporator (DX)
Page 175: 55-02 STARTERS - Star Delta
Page 176: 55-03 STARTERS -Two speed - Dual wound
Page 177: 55-04 STARTERS - Two speed - Pole change
Page 178: 55-05 STARTERS - Reversing
Page 179: 55-06 STARTERS - Auto-transformer
Page 180: 55-07 STARTERS - Quick transition, electric heater
Page 181: 55-08 STARTERS electrolyte type
Page 183: 56-02 COLD WATER STORAGE TANKS and CISTERNS
Page 184: 56-03 ICE STORAGE SYSTEMS
Page 185: 56-05 STORAGE TANKS - OIL
Page 189: 57-02 SWIMMING POOLS
Page 193: 57-03 SWIMMING POOLS - FILTERS
Page 194: 57-04 SWIMMING POOLS - PIPEWORK, PUMPS, HEATING etc.
Page 198: 58-01 ON/OFF SWITCHING DEVICES
Page 200: 59-01 TERMINAL UNITS VAV - self powered
Page 201: 59-02 TERMINAL UNITS VAV - fan powered
Page 202: 59-06 TERMINAL UNITS - FAN COIL
Page 203: 59-07 TERMINAL UNITS VRV SYSTEMS
Page 205: 60-01 VACUUM SYSTEMS - general
Page 206: 60-02 VACUUM TUBES - cash handling
Page 208: 61-01 VALVES
Page 210: 64-02 MOTOR DRIVEN EXHAUST HOSE REEL
Page 211: 64-03 SPRING RECOIL HOSE REEL
Page 212: 64-04 MOBILE DUST SEPARATOR FOR SPOT EXTRACTION
Page 213: 64-05 MOBILE ELECTRONICALLY CONTROLLED CYCLONE SEPARATOR
Page 214: 64-06 VEHICLE EXHAUST RAIL SYSTEM
Page 216: 65-03 ION EXCHANGE PLANT - BASE EXCHANGE SOFTENING - domestic (capacity usually below 50 litres)
Page 217: 65-09 OZONATION PLANT
Page 219: 66-01 WHIRLPOOL/SPA BATHS
Page 220: 66-02 HYDROTHERAPY POOLS
Page 222: 66-03 STEAM ROOMS and HUMIDIFIERS
Page 3 of 3
ACTUATORS
Page 1 of 222
Previous
Version
Updated
Version
Reason For
Change
PNEUMATIC ACTUATORS01-04 01-04 PNEUMATIC ACTUATORS
Title NotesActionFQTitle FQ Action Notes
9. Reaction to
safety signal i.e.
fire/smoke.
Check that the actuator assumes
correct position (if applicable).
See relevant control/sensor section
for this operation.
3MAdded
Page 2 of 222
AIR HANDLING UNITS
Page 3 of 222
Previous
Version
Updated
Version
Reason For
Change
AIR HANDLING UNITS - general03-01 03-01 AIR HANDLING UNITS - general
Title NotesActionFQTitle FQ Action Notes
7. Fans Check operation of fan in
accordance with the relevant
section of Fans SFG20-01 to 20-08
6MAdded
Page 4 of 222
BOILERS/HEAT GENERATORS
Page 5 of 222
Previous
Version
Updated
Version
Reason For
Change
COAL FEED MECHANISMS - Under feed stokers05-07 05-07 COAL FEED MECHANISMS - Under feed stokers
The burning of coal is a complex operation involving the storage, handling, combustion of solid
material, together with the handling, disposal of gaseous and solid waste. The materials are abrasive
and the wear and tear on mechanical plant considerable, hence regular maintenance is vital to ensure
continuous working and a clean environment. The maintenance of each section of the coal burning
operation is examined in sequence.(See also Motors SFG 39)
WARNING. A risk assessment and method statement must be undertaken before entering any
confined space such as a hopper, flue chamber or boiler to ensure that there is adequate ventilation
and an absence of any fumes or flue gases.
Added
Title NotesActionFQTitle FQ Action Notes
Page 6 of 222
Previous
Version
Updated
Version
Reason For
Change
ASH HANDLING SYSTEM05-09 05-09 ASH HANDLING SYSTEM
The burning of coal is a complex operation involving the storage, handling, combustion of solid
material, together with the handling, disposal of gaseous and solid waste. The materials are abrasive
and the wear and tear on mechanical plant considerable, hence regular maintenance is vital to ensure
continuous working and a clean environment. The maintenance of each section of the coal burning
operation is examined in sequence.(See also Motors SFG 39)
WARNING. A risk assessment and method statement must be undertaken before entering any
confined space such as a hopper, flue chamber or boiler to ensure that there is adequate ventilation
and an absence of any fumes or flue gases.
Added
Title NotesActionFQTitle FQ Action Notes
Page 7 of 222
Previous
Version
Updated
Version
Reason For
Change
FORCED DRAUGHT [PRESSURE JET] OIL CONDENSING BOILER05-13 05-13 FORCED DRAUGHT [PRESSURE JET] OIL CONDENSING BOILER
The essential feature of a condensing boiler is that to increase the efficiency the flue gases are cooled
below their dew point with the result that condensate is produced which has to be removed from the
flue via drainage pipework.
Boiler room ventilation should comply with BS 5440 -2: 2009 for boilers not exceeding 70kW and BS
6644:2005 for boilers with a capacity between 70kW and 1.8MW.
Undetected CO is poisonous, life threatening and also causes energy waste. The burner should be
quiet in operation, no excessive noise should occur when the burner ignites or shuts down. In
domestic premises, consider the installation of a CO detector that complies with BS EN 50291-1:2010
and BS EN 50292:2002.
Added
Title NotesActionFQTitle FQ Action Notes
Page 8 of 222
Previous
Version
Updated
Version
Reason For
Change
STEAM BOILERS Maintenance schedule.05-20 05-20 STEAM BOILERS Maintenance schedule.
Title NotesActionFQTitle FQ Action Notes
Self-monitoring
controls
Added
1. Water gauge
test
Record time test carried out, log
results with the operator`s name,
date of test plus any corrective
action taken.
1DAdded
2. Water level left
hand gauge
Manually blow down Record time test carried out.1DAdded
3. Water level right
hand gauge
Manually blow down Record time test carried out.1DAdded
4. Water level
control
Test low water level cut-out and
lock-out
At no time during a test should the
water be lowered to the extent that it
disappears from the gauge glass.
Record time test carried out
1DAdded
5. Feed pump
start/stop or
modulation
Check operation. Record time test carried out.1DAdded
6. Pressure
reading
Record pressure gauge reading Record time test carried out.1DAdded
7. Feed water and
condensate check
Check the feed tank level is
adequate and there are no
contaminants. Check that the
chemical dose metering device is
functioning and there are adequate
chemical stocks in the tanks. Check
that the in-house routine sample
results are within their given
parameters provided by the water
treatment specialist and take
remedial action when necessary.
Check the temperature is above the
required level for the treatment
doses specified for oxygen
scavenging.
Record time test carried out, log
results with the operator`s name,
date of test plus any corrective
action taken.
1DAdded
8. TDS water test Carry out TDS water quality test,
record the result and make
adjustments where necessary.
Record time test carried out.1DAdded
9. pH water test Carry out pH water quality test,
record the result and make
adjustments where necessary.
Record time test carried out.1DAdded
10. Blow down record quantity of water blown
down.
Record time test carried out.1DAdded
11. Flame failure Test flame failure lock-out.
This may not be present on non self
monitoring boilers
Record time test carried out.1WAdded
Page 9 of 222
Previous
Version
Updated
Version
Reason For
Change
12. Failure to
ignite
Test failure to ignite lock out. Record time test carried out.1WAdded
13. Water level 1st Test by lowering water level to 1st
low water level, by evaporation and
controlled blowdown, and check
burner locks out and the alarm is
sounded.
Discharge temperature to drain
should not exceed permissible
limits.
Record time test carried out.
At no time during a test should the
water be lowered to the extent that it
disappears from the gauge glass.
1WAdded
14. Water level
2nd
Test by lowering water level to 2nd
low water level, by evaporation and
controlled blowdown, and check
burner locks out and the alarm is
sounded.
Discharge temperature to drain
should not exceed permissible
limits.
Record time test carried out.
At no time during a test should the
water be lowered to the extent that it
disappears from the gauge glass.
1WAdded
Page 10 of 222
Previous
Version
Updated
Version
Reason For
Change
WASTE AND WOOD BURNING APPLIANCES (including boilers) -
Combustion Chamber
05-26 05-26 WASTE AND WOOD BURNING APPLIANCES (including boilers) -
Combustion Chamber
Check for asbestos containing material prior to dismantling any equipment, if suspected STOP
WORK, close off the area. Take actions in accordance with the Asbestos Regulations.
Refer to www.hse.gov.uk.
Added
Title NotesActionFQTitle FQ Action Notes
4. Refractory
linings.
Check condition and report.3MAdded
Page 11 of 222
Previous
Version
Updated
Version
Reason For
Change
WASTE AND WOOD BURNING APPLIANCES (including boilers) - BOILER (if
fitted)
05-27 05-27 WASTE AND WOOD BURNING APPLIANCES (including boilers) - BOILER (if
fitted)
Check for asbestos containing material prior to dismantling any equipment, if suspected STOP
WORK, close off the area. Take actions in accordance with the Asbestos Regulations.
Refer to www.hse.gov.uk.
Added
Page 12 of 222
BUILDING MANAGEMENT SYSTEMS
Page 13 of 222
Previous
Version
Updated
Version
Reason For
Change
BUILDING MANAGEMENT SYSTEMS - Central Operator Station06-03 06-03 BUILDING MANAGEMENT SYSTEMS - Central Operator Station
Title NotesActionFQTitle FQ Action Notes
5. Clock and
Calendar
Check real-time clock and date
settings
6MAdded
Page 14 of 222
Previous
Version
Updated
Version
Reason For
Change
BUILDING MANAGEMENT SYSTEMS - COMMUNICATIONS06-04 06-04 BUILDING MANAGEMENT SYSTEMS - COMMUNICATIONS
Title NotesActionFQTitle FQ Action Notes
5.Alarms -
receiving
Confirm that all critical alarms are
received by the central supervisor.
Check spurious alarms and
reported faults (as incurred).
12MAdded
6. Alarms -
generating
Check generation of alarms from all
input and output devices
12MAdded
7. Network Check communications between
central supervisory computer and
outstations and other networked
devices
12MAdded
Page 15 of 222
Previous
Version
Updated
Version
Reason For
Change
BUILDING MAINTENANCE SYSTEMS - OUTSTATIONS06-05 06-05 BUILDING MAINTENANCE SYSTEMS - OUTSTATIONS
Title NotesActionFQTitle FQ Action Notes
5. Stand-by
batteries/
uninterrupted
power supplies
(UPS).
Interrupt electrical supply to each
outstation, reinstate and ensure
system restarts satisfactorily
12MAdded
Page 16 of 222
Previous
Version
Updated
Version
Reason For
Change
BUILDING MANAGEMENT SYSTEMS - SOFTWARE FUNCTIONS06-06 06-06 BUILDING MANAGEMENT SYSTEMS - SOFTWARE FUNCTIONS
Title NotesActionFQTitle FQ Action Notes
14. Outstations Back up all outstation files. Make
two copies. Store one on site and
one off site.
6MAdded
15. O&M`s Advise where control strategy
descriptions in operating and
maintenance manuals are incorrect.
Ensure, where appropriate,
additional documentation meets all
quality assurance procedures
12MAdded
16. Schematics Check schematics indicate correctly12MAdded
17. Log Books Maintain a log book of all changes
made to the system
As Necessary0MAdded
Page 17 of 222
CHILLERS - WATER
Page 18 of 222
Previous
Version
Updated
Version
Reason For
Change
PACKAGED CHILLER UNITS09-02 09-02 PACKAGED CHILLER UNITS
Title NotesActionFQTitle FQ Action Notes
16. Condensers Carry out Routine Maintenance For further guidance see
Condensers SFG 13-01
3MAdded
Page 19 of 222
Previous
Version
Updated
Version
Reason For
Change
LITHIUM BROMIDE/WATER ABSORPTION CHILLERS09-03 09-03 LITHIUM BROMIDE/WATER ABSORPTION CHILLERS
Title NotesActionFQTitle FQ Action Notes
14. Insulation Check condition and make good
any defects however small.
Poor or faulty insulation can lead to
loss of efficiency, energy wastage
and the formation of condensation.
1MAdded
15. General
Inspection
Visually inspect for corrosion,
erosion and deformities.
1MAdded
16. Pressure relief
device
Any pressure relief device should
be checked if fitted.
1MAdded
Page 20 of 222
Previous
Version
Updated
Version
Reason For
Change
GAS FIRED ABSORPTION CHILLER UP TO 18 KW COOLING CAPACITY09-04 09-04 GAS FIRED ABSORPTION CHILLER UP TO 18 KW COOLING CAPACITY
Title NotesActionFQTitle FQ Action Notes
11. Ammonia
Charge
Measure and record ammonia
charge
Refer to manufacturers instructions4MAdded
12. Oil Analysis take a sample of oil for analysis If excessive moisture is found,
appropriate action shall be taken to
correct the balance. If the oil is PAG
(or similar) great care should be
taken to ensure
that the sample itself is not
contaminated during handling
4MAdded
13. Compressors,
Condensers and
Evaporators
Undertake maintenance on
Compressors
For further guidance see
Compressors SFG 12, Condensers
SFG 13 and Evaporators SFG 19
6MAdded
Page 21 of 222
COLD ROOMS AND FOOD STORAGE
Page 22 of 222
Previous
Version
Updated
Version
Reason For
Change
COLD ROOMS10-01 10-01 COLD ROOMS
Title NotesActionFQTitle FQ Action Notes
14. Door Lock Check for correct operation and
ensure handle is illuminated.
Ensure any personnel can exit the
cold room safely in an emergency
6MAdded
Page 23 of 222
COMMUNICATION AND P.A. SYSTEMS
Page 24 of 222
Previous
Version
Updated
Version
Reason For
Change
COMMUNICATIONS - PUBLIC ADDRESS SYSTEMS11-01 11-01 COMMUNICATIONS - PUBLIC ADDRESS SYSTEMS
Ensure that, following all inspection visits, conditional reports shall be submitted to the client, including
all specialist reports and test equipment printouts.
In addition, ensure that a Site Logbook is maintained on site containing duplicate copies of all the
reports information submitted to the client.
Added
Title NotesActionFQTitle FQ Action Notes
7 Hearing
assistance
induction loop
Check loop is active and is not
suffering any `Blind Spots`.
If any found report to the client.12MAdded
8 Power supplies Check mains power supplies.
Examine all plugs and fuses for
condition.
Measure resistance of installation
cables.
12MAdded
9 System Test system is fully operational Provide a signed engineer’s report,
one copy to be left in Site Log Book
and a further copy to be submitted
to the client.
12MAdded
10. Fire Alarm
interface
Check functioning of interface.12MAdded
Page 25 of 222
COMPRESSORS - REFRIGERATION
Page 26 of 222
Previous
Version
Updated
Version
Reason For
Change
COMPRESSORS REFRIGERATION - Reciprocal - (includes hermetic,
semi-hermetic and open)
12-01 12-01 COMPRESSORS REFRIGERATION - Reciprocal - (includes hermetic,
semi-hermetic and open)Title NotesActionFQTitle FQ Action Notes
A) Normal
systems:
<3 kg
Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
0MAdded
B) 3 kg to 30 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
12MAdded
C) 30 kg to 300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
6MAdded
D) >300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
3MAdded
E) Hermetically
sealed systems:
<6 kg
Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
0MAdded
F) 6 kg to 30 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
12MAdded
G) 30 kg to 300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
6MAdded
H) >300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
3MAdded
Page 27 of 222
Previous
Version
Updated
Version
Reason For
Change
COMPRESSOR - SCREW12-02 12-02 COMPRESSOR - SCREW
These machines come in a wide range of sizes, the larger machines can be complex both in terms of
operation and maintenance requirements. In the case of compressors serving small air conditioning
systems which may only run during the summer months, these may require less frequent
maintenance.
For the maintenance of rotary compressors refer to the manufacturer`s maintenance instructions.
Where the installed power on the refrigeration system exceeds 25kW, a Written Scheme of
Examination may be required to comply with the Pressure Systems Safety Regulations 2000
Service providers must be registered to an Approved Certified Scheme provider , in accordance with
the F Gas and Building Regulations.
Added
Title NotesActionFQTitle FQ Action Notes
A) Normal
systems:
<3 kg
Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
0MAdded
B) 3 kg to 30 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
12MAdded
C) 30 kg to 300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
6MAdded
D) >300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
3MAdded
E) Hermetically
sealed systems:
<6 kg
Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
0MAdded
F) 6 kg to 30 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
12MAdded
G) 30 kg to 300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
6MAdded
H) >300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
3MAdded
4. Leaks. Check for leaks should be part of
the routine servicing by plant
attendants.
Where a system has a refrigerant
charge greater than 300kg, an
automatic leak detection system
must be installed on the system to
comply with the F Gas Regulations
Added
Page 28 of 222
Previous
Version
Updated
Version
Reason For
Change
COMPRESSORS REFRIGERATION - CENTRIFUGAL - R 11/R 12
REFRIGERANT OR THEIR SUBSTITUTES R123/134a
12-03 12-03 COMPRESSORS REFRIGERATION - CENTRIFUGAL
Title NotesActionFQTitle FQ Action Notes
19. Leaks. Check for leaks should be part of
the routine servicing by plant
attendants.
Where a system has a refrigerant
charge greater than 300kg, an
automatic leak detection system
must be installed on the system to
comply with the F Gas Regulations
Added
A) Normal
systems:
<3 kg
Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
0MAdded
B) 3 kg to 30 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
12MAdded
C) 30 kg to 300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
6MAdded
D) >300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
3MAdded
E) Hermetically
sealed systems:
<6 kg
Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
0MAdded
F) 6 kg to 30 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
12MAdded
G) 30 kg to 300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
6MAdded
H) >300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
3MAdded
Page 29 of 222
CONDENSERS
Page 30 of 222
Previous
Version
Updated
Version
Reason For
Change
CONDENSERS - water cooled13-01 13-01 CONDENSERS - water cooled
Title NotesActionFQTitle FQ Action Notes
4. Isolating
Valves.
Check external condition, leak
tightness of glands and seats,
operational spindles and hand
wheels.
Repack as necessary.12MAdded
Page 31 of 222
CONTROL PANELS & CONTROLLERS
Page 32 of 222
Previous
Version
Updated
Version
Reason For
Change
CONTROL PANELS - lamps, meters, alarms etc.14-03 14-03 CONTROL PANELS - lamps, meters, alarms etc.
Before commencing any maintenance work on control panels, read Control panels and controllers
SFG 14 introductory notes, very carefully and follow all the safety procedures.
Added
Title NotesActionFQTitle FQ Action Notes
Page 33 of 222
Previous
Version
Updated
Version
Reason For
Change
SINGLE INPUT CONTROLLER14-06 14-06 SINGLE INPUT CONTROLLER
Before commencing any maintenance work on control panels, read Control panels and controllers
SFG 14 introductory notes, very carefully and follow all the safety procedures.
Added
Page 34 of 222
Previous
Version
Updated
Version
Reason For
Change
UNIT CONTROLLERS AND SENSOR CONTROLLERS14-07 14-07 UNIT CONTROLLERS AND SENSOR CONTROLLERS
Before commencing any maintenance work on control panels, read Control panels and controllers
SFG 14 introductory notes, very carefully and follow all the safety procedures.
Added
Page 35 of 222
Previous
Version
Updated
Version
Reason For
Change
CONTROLLER TIMERS14-08 14-08 CONTROLLER TIMERS
Before commencing any maintenance work on control panels, read Control panels and controllers
SFG 14 introductory notes, very carefully and follow all the safety procedures.
Added
Title NotesActionFQTitle FQ Action Notes
Page 36 of 222
Previous
Version
Updated
Version
Reason For
Change
STEP CONTROLLERS14-09 14-09 STEP CONTROLLERS
Before commencing any maintenance work on control panels, read Control panels and controllers
SFG 14 introductory notes, very carefully and follow all the safety procedures.
Added
Title NotesActionFQTitle FQ Action Notes
Page 37 of 222
Previous
Version
Updated
Version
Reason For
Change
TIMESWITCHES14-10 14-10 TIMESWITCHES
Before commencing any maintenance work on control panels, read Control panels and controllers
SFG 14 introductory notes, very carefully and follow all the safety procedures.
Added
Title NotesActionFQTitle FQ Action Notes
Page 38 of 222
Previous
Version
Updated
Version
Reason For
Change
MULTI-INPUT CONTROLLERS14-11 14-11 MULTI-INPUT CONTROLLERS
Before commencing any maintenance work on control panels, read Control panels and controllers
SFG 14 introductory notes, very carefully and follow all the safety procedures.
Added
Page 39 of 222
Previous
Version
Updated
Version
Reason For
Change
INDICATORS AND DISPLAYS14-12 14-12 INDICATORS AND DISPLAYS
Before commencing any maintenance work on control panels, read Control panels and controllers
SFG 14 introductory notes, very carefully and follow all the safety procedures.
Added
Page 40 of 222
Previous
Version
Updated
Version
Reason For
Change
ALARM MODULES14-13 14-13 ALARM MODULES
Before commencing any maintenance work on control panels, read Control panels and controllers
SFG 14 introductory notes, very carefully and follow all the safety procedures.
Added
Page 41 of 222
Previous
Version
Updated
Version
Reason For
Change
LEVEL CONTROLLERS14-14 14-14 LEVEL CONTROLLERS
Before commencing any maintenance work on control panels, read Control panels and controllers
SFG 14 introductory notes, very carefully and follow all the safety procedures.
Added
Page 42 of 222
Previous
Version
Updated
Version
Reason For
Change
TRANSDUCERS - pneumatic to electronic and electronic to pneumatic14-16 14-16 TRANSDUCERS - pneumatic to electronic and electronic to pneumatic
Before commencing any maintenance work on control panels, read Control panels and controllers
SFG 14 introductory notes, very carefully and follow all the safety procedures.
Added
Page 43 of 222
DUCTING
Page 44 of 222
Previous
Version
Updated
Version
Reason For
Change
DUCTWORK SYSTEM - GENERAL16-02 16-02 DUCTWORK SYSTEM - GENERAL
Title NotesActionFQTitle FQ Action Notes
6. Ductwork
Support
Check all ductwork supports and
handers to ensure they are secure
and not loose
Report to client if remedial work
required.
12MAdded
7. Hit Hazards Inspect duct run where it runs
across or parallel to a personnel
access route. Highlight any low
points with the appropriate hazard
tape or paint
12MAdded
Page 45 of 222
EVAPORATORS
Page 46 of 222
Previous
Version
Updated
Version
Reason For
Change
EVAPORATORS19-01 19-01 REFRIGERATION EVAPORATORS
Title NotesActionFQTitle FQ Action Notes
1. Compressor
full load operation.
Record inlet and outlet temperature
on water side. Pressure drop
across evaporator, refrigerant
pressures or superheat
temperatures and evaporator
temperature.
Any marked difference to the design
figures could indicate internal fouling
of the condenser and may require
additional work.
12MAdded
2. Flow
protection devices
Check for chilled water flow in the
system and correct operation.
12MAdded
3. Pump. Check and record pressure drop
across pump. Check for leakage,
bearing noise and unusual bearing
temperature. Lubricate according to
manufacturers instructions. Check
motor current.
For further guidance see Pumps
SFG 45-01
12MAdded
4. Automatic
Isolating Valves.
Check external condition, leak
tightness of glands and seats,
operational spindles and solenoid.
Some chillers have the ability to
automatically pump down refrigerant
to the evaporators in the event of a
refrigerant leak or other fault. For
further guidance see the
manufacturers instructions
12MAdded
2. Filter-Dryers Where fitted replace the filter
dryer(s) as required
check in line sight glass for
indication of moisture in system
6MAdded
7. Fans (if
applicable)
Check for correct operation and
clean fan blades as required
For further guidance see Fans SFG
20
6MAdded
Page 47 of 222
FANS
Page 48 of 222
Previous
Version
Updated
Version
Reason For
Change
FANS - VENTILATING - general20-02 20-02 FANS - VENTILATING - general
Title NotesActionFQTitle FQ Action Notes
10. Motor and fan
blade - cleaning
Clean and inspect all grilles. Clean
all dirt from the outside of any
motor.
Clean fan blades. Check for
excessive imbalance.
If dirt builds up on a motor it can act
as insulation which causes the
motor to operate at elevated
temperatures, resulting in shortened
motor life can be shortened and
motors commonly burn-out of
motors.
An excessive build up of dust or
damage to the fan blade can add
imbalance causing excessive
vibration. This can lead to fatigue
and dangerous failure.
Dirt should be removed by cleaning
with suitable equipment.
Fan blades and louvers can be
cleaned with a brush and detergent.
The fan motor casing must be totally
enclosed to prevent water from
damaging motor windings. If the
motor is not totally enclosed, then it
must be removed and cleaned
separately before the housing is
cleaned. If using a brush or
high-pressure washer care must be
taken not to damage the impeller
blades.
6MAdded
11. Motors -
electrical
Check the electrical and thermal
overload protection for the
motor, and if the motor has a
resettable overload protection.
Check that it is fully operational.
6MAdded
12. Electrics A) Check circuit breakers manually
each month.
Examine wiring and other electrical
system components for signs of
deterioration, loose connections
and damage. Check all connections
are tight.
1MAdded
12. B) Clean any sensors re-calibrate if
found to be inaccurate.
6MAdded
Page 49 of 222
Previous
Version
Updated
Version
Reason For
Change
FANS -CENTRIFUGAL20-03 20-03 FANS -CENTRIFUGAL
Ensure to read health and safety notes shown on SFG 20-01 before undertaking the following tasks.
The instructions in the table below refer to all air handling fans including exhaust, make up,
recirculation and small air handlers. Before working on any moving machinery switch off and ensure
that the equipment is isolated electrically in accordance with Health and Safety at Work
(www.hse.gov.uk) Regulations.
The isolator should be locked in the off position when maintenance takes place .
Added
Title NotesActionFQTitle FQ Action Notes
7. Motor and fan
blade - cleaning
Clean and inspect all grilles. Clean
all dirt from the outside of any
motor.
Clean fan blades. Check for
excessive imbalance.
6MAdded
8. Motors -
electrical
Check the electrical and thermal
overload protection for the
motor, and if the motor has a
resettable overload protection.
Check that it is fully operational.
6MAdded
9. Electrics Check circuit breakers manually
each month.
Examine wiring and other electrical
system components for signs of
deterioration, loose connections
and damage. Check all connections
are tight.
1MAdded
9. Electrics Clean any sensors re-calibrate if
found to be inaccurate.
6MAdded
Page 50 of 222
Previous
Version
Updated
Version
Reason For
Change
FANS- AXIAL20-04 20-04 FANS- AXIAL
Ensure to read health and safety notes shown on SFG 20-01 before undertaking the following tasks.
The instructions in the table below refer to all air handling fans including exhaust, make up,
recirculation and small air handlers. Before working on any moving machinery switch off and ensure
that the equipment is isolated electrically in accordance with Health and Safety at Work
(www.hse.gov.uk) Regulations.
The isolator should be locked in the off position when maintenance takes place .
Added
Title NotesActionFQTitle FQ Action Notes
9. Motor and fan
blade - cleaning
Clean and inspect all grilles. Clean
all dirt from the outside of any
motor.
Clean fan blades. Check for
excessive imbalance.
6MAdded
10. Motors -
electrical
Check the electrical and thermal
overload protection for the
motor, and if the motor has a
resettable overload protection.
Check that it is fully operational.
6MAdded
11. Electrics Check circuit breakers manually
each month.
Examine wiring and other electrical
system components for signs of
deterioration, loose connections
and damage. Check all connections
are tight.
1MAdded
11. Electrics Clean any sensors re-calibrate if
found to be inaccurate.
6MAdded
Page 51 of 222
Previous
Version
Updated
Version
Reason For
Change
FANS - PROPELLER20-05 20-05 FANS - PROPELLER
Ensure to read health and safety notes shown on SFG 20-01 before undertaking the following tasks.
The instructions in the table below refer to all air handling fans including exhaust, make up,
recirculation and small air handlers. Before working on any moving machinery switch off and ensure
that the equipment is isolated electrically in accordance with Health and Safety at Work
(www.hse.gov.uk) Regulations.
The isolator should be locked in the off position when maintenance takes place .
Added
Title NotesActionFQTitle FQ Action Notes
6. Motor and fan
blade - cleaning
Clean and inspect all grilles. Clean
all dirt from the outside of any
motor.
Clean fan blades. Check for
excessive imbalance.
6MAdded
7. Motors -
electrical
Check the electrical and thermal
overload protection for the
motor, and if the motor has a
resettable overload protection.
Check that it is fully operational.
6MAdded
8. Electrics Check circuit breakers manually
each month.
Examine wiring and other electrical
system components for signs of
deterioration, loose connections
and damage. Check all connections
are tight.
1MAdded
8. Electrics Clean any sensors re-calibrate if
found to be inaccurate.
6MAdded
Page 52 of 222
Previous
Version
Updated
Version
Reason For
Change
FANS-MIXED FLOW20-06 20-06 FANS-MIXED FLOW
Ensure to read health and safety notes shown on SFG 20-01 before undertaking the following tasks.
The instructions in the table below refer to all air handling fans including exhaust, make up,
recirculation and small air handlers. Before working on any moving machinery switch off and ensure
that the equipment is isolated electrically in accordance withHealth and Safety at Work
(www.hse.gov.uk) Regulations.
The isolator should be locked in the off position when maintenance takes place .
Added
Title NotesActionFQTitle FQ Action Notes
8. Motor and fan
blade - cleaning
Clean and inspect all grilles. Clean
all dirt from the outside of any
motor.
Clean fan blades. Check for
excessive imbalance.
6MAdded
9. Motors -
electrical
Check the electrical and thermal
overload protection for the
motor, and if the motor has a
resettable overload protection.
Check that it is fully operational.
6MAdded
10. Electrics Check circuit breakers manually
each month.
Examine wiring and other electrical
system components for signs of
deterioration, loose connections
and damage. Check all connections
are tight.
1MAdded
10. Electrics Clean any sensors re-calibrate if
found to be inaccurate.
6MAdded
Page 53 of 222
Previous
Version
Updated
Version
Reason For
Change
FANS-BIFURCATED20-07 20-07 FANS-BIFURCATED
Title NotesActionFQTitle FQ Action Notes
13. Motor and fan
blade - cleaning
Clean and inspect all grilles. Clean
all dirt from the outside of any
motor.
Clean fan blades. Check for
excessive imbalance.
6MAdded
14. Electrics Check circuit breakers manually
each month.
Examine wiring and other electrical
system components for signs of
deterioration, loose connections
and damage. Check all connections
are tight.
1MAdded
14. Electrics Clean any sensors re-calibrate if
found to be inaccurate.
6MAdded
Page 54 of 222
Previous
Version
Updated
Version
Reason For
Change
FANS-EXTRACT - including fire/smoke extracts units20-08 20-08 FANS-EXTRACT - including fire/smoke extracts units
Ensure to read health and safety notes shown on SFG 20-01 before undertaking the following tasks.
The instructions in the table below refer to all air handling fans including exhaust, make up,
recirculation and small air handlers. Before working on any moving machinery switch off and ensure
that the equipment is isolated electrically in accordance with Health and Safety at Work
(www.hse.gov.uk) Regulations.
The isolator should be locked in the off position when maintenance takes place .
Added
Title NotesActionFQTitle FQ Action Notes
9. Motor and fan
blade - cleaning
Clean and inspect all grilles. Clean
all dirt from the outside of any
motor.
Clean fan blades. Check for
excessive imbalance.
6MAdded
10. Motors -
electrical
Check the electrical and thermal
overload protection for the
motor, and if the motor has a
resettable overload protection.
Check that it is fully operational.
6MAdded
11. Electrics Check circuit breakers manually
each month.
Examine wiring and other electrical
system components for signs of
deterioration, loose connections
and damage. Check all connections
are tight.
1MAdded
11. Electrics Clean any sensors re-calibrate if
found to be inaccurate.
6MAdded
Page 55 of 222
FILTERS
Page 56 of 222
Previous
Version
Updated
Version
Reason For
Change
FILTERS21-02 21-02 AIR FILTERS
Note: - In normal use air filters do not present a health and safety hazard. However used air filters do
contain quantities of dust which, unless precautions are taken, may expose maintenance personnel to
a `nuisance dust' hazard, as defined by the `Control of Substances Hazardous to Health (COSHH)
Regulations'. A risk assessment must be carried out before the work starts and a method statement
produced. PPE may be needed.
Used filters should be sealed into plastic bags for disposal. ENVIRONMENTAL REGULATIONS apply.
In normal use air filters do not present a health and safety hazard. However used air filters do contain
quantities of dust which, unless precautions are taken, may expose maintenance personnel to a
`nuisance dust` hazard, as defined by the `Control of Substances Hazardous to Health (COSHH
(www.hse.gov.uk/hthdir/noframes/coshh/index.htm)) Regulations`. A risk assessment must be carried
out before the work starts and a method statement produced. Used filters should be sealed into
plastic bags for disposal. Controlled Waste Regulations apply.
Visual inspection of air filters is a the basic first action. If they are clearly dirty then they can be
changed and form part of a preventative planned maintenance program. (PPM). A better method for
filter change is based on filter change by noting increased operating pressure across the filter. When
the filter pressure is twice the initial value it is time to change. Where possible Low Energy Air Filters
should be selected so that running costs and energy use are minimised. Regular monitoring and
recording of pressure drop readings and recording of filter changes is to be encouraged.
The frequency of duct cleaning will depend upon the degree of contamination.
BS EN 15780:2011 gives three levels of cleanliness for typical applications;
Low - rooms with only intermittent occupancy e.g.
storage rooms, technical rooms.
Medium - offices, hotels, restaurants, schools,
theatres, residential homes, shopping
areas, exhibition buildings, sport buildings,
general areas in hospitals and general
working areas in industries.
High - Laboratories, treatment areas in hospitals
high quality offices.
Filter recommended inspection intervals according to the above cleanliness quality classes are; Low
and Medium 12 months and high is 6 months.
Added
Title NotesActionFQTitle FQ Action Notes
Page 57 of 222
FIRE ALARM SYSTEMS
Page 58 of 222
Previous
Version
Updated
Version
Reason For
Change
FIRE ALARM SYSTEM22-01 22-01 FIRE ALARM SYSTEM
Title NotesActionFQTitle FQ Action Notes
9) Alarm signals The operation of any facility for
automatic transmission of alarm
signals to an alarm receiving centre
should be checked.
Where more than one form of alarm
signal can be transmitted (e.g. fire
and fault signals), the correct
transmission of each signal should
be confirmed.
6MAdded
10) Ancillary
functions
All ancillary functions of the control
and indicating equipment should be
tested.
6MAdded
11) Fault
indicators
All fault indicators and their circuits
should be checked, where
practicable, by simulation of fault
conditions.
6MAdded
12) Printers All printers should be tested to
ensure that they operate correctly
and that characters are legible.
It should be ensured that all printer
consumables are sufficient in
quantity or condition to ensure that
the printer can be expected to
operate until the time of the next
service visit.
6MAdded
13) Radio
Systems
Radio systems of all types should
be serviced in accordance with the
recommendations of the
manufacturer.
6MAdded
14) Manufacturers
checks and tests
All further checks and tests
recommended by the manufacturer
of the control and indicating
equipment and other components
of the system should be carried out.
6MAdded
15) Completion On completion of the work, any
outstanding defects should be
reported to the responsible person,
the system log book should be
completed and a servicing
certificate should be issued.
6MAdded
a) The work described may be carried
out over the course of two or more
service visits during each twelve
month period
6MAdded
16) Manual Call
Points
The switch mechanism of every
manual call point should be tested,
either by removal of a frangible
element, insertion of a test key or
operation of the device as it would
be operated in the event of fire.
12MAdded
Page 59 of 222
Previous
Version
Updated
Version
Reason For
Change
17) Automatic
detectors
All automatic fire detectors should
be examined, as far as practicable,
to ensure that they have not been
damaged, painted, or otherwise
adversely affected. Thereafter,
every detector should be
functionally tested. The tests used
need prove only that the detectors
are connected to the system, are
operational and are capable of
responding to the phenomena they
are designed to detect.
General :
Connections – check condition and
make good if necessary.
Mounting – Check security
12MAdded
18) Heat detectors Every heat detector should be
functionally tested by means of a
suitable heat source, unless
operation of the detector in this
manner would then necessitate
replacement of part or all of the
sensing element (e.g. as in fusible
link point detectors or
non-integrating line detectors).
Special test arrangements will
be required for fusible link heat
detectors. The heat source should
not have the potential to ignite a
fire; live flame should not be used,
and special equipment might be
necessary in explosive
atmospheres
12MAdded
19) Point smoke
detectors
Point smoke detectors should be
functionally tested by a method that
confirms that smoke can enter the
detector chamber and produce a
fire alarm signal (e.g. by use of
apparatus that generates simulated
smoke or suitable aerosols around
the detector). It should be ensured
that the material used does not
cause damage to, or affect the
subsequent performance of, the
detector; the manufacturer’s
guidance on
suitable materials should be
followed.
12MAdded
20) Optical beam
smoke detectors
Optical beam smoke detectors
should be functionally tested by
introducing signal attenuation
between the transmitter and
receiver, either by use of an optical
filter, smoke or simulated smoke
12MAdded
Page 60 of 222
Previous
Version
Updated
Version
Reason For
Change
21) Aspirating fire
detection systems,
VESDA system
Aspirating fire detection systems
should be functionally tested as
described in 45.4d of BS5839 part
1, with each sampling point, or
group of sampling points, in the
pipework of the system treated as a
point detector.
45.4d "Point smoke detectors
should be functionally tested by a
method that confirms that smoke
can enter the detector chamber and
produce a fire alarm signal (e.g. by
use of apparatus that generates
simulated smoke or suitable
aerosols around the detector). It
should be ensured that the material
used does not
cause damage to, or affect the
subsequent performance of, the
detector; the manufacturer’s
guidance on suitable materials
should be followed.
Not all test products may be
appropriate for the purpose
12MAdded
22) Carbon
Monoxide fire
detectors
Carbon monoxide fire detectors
should be functionally tested by a
method that confirms that carbon
monoxide can enter the detector
chamber and produce a fire alarm
signal (e.g. by use of apparatus that
generates carbon monoxide or a
gas that has a similar effect on the
electro-chemical cell as carbon
monoxide
It should be ensured that any test
gas used does not cause damage
to, or affect the subsequent
performance of, the
detector; the manufacturer’s
guidance on suitable test gases
should be followed.
12MAdded
23) Flame
detectors
Flame detectors should be
functionally tested by a method that
confirms that the detector will
respond to a suitable frequency of
radiation and produce a fire alarm
signal. The guidance of the
manufacturer on testing of
detectors should be followed.
12MAdded
24) Analogue
values
In fire detection systems that
enable analogue values to be
determined at the control and
indicating equipment, it should be
confirmed that each analogue value
is within the range specified by the
manufacturer.
12MAdded
25) Multi-sensor
detectors
Multi-sensor detectors should be
operated by a method that confirms
that products of combustion in the
vicinity of the detector can reach
the sensors and that a fire signal
can be produced as appropriate
The guidance of the manufacturer
on the manner in which the detector
can be functionally tested effectively
should be followed
12MAdded
Page 61 of 222
Previous
Version
Updated
Version
Reason For
Change
26) Visual devices All fire alarm devices should be
checked for correct operation. It
should be confirmed that visual fire
alarm devices are not obstructed
from view and that their lenses are
clean.
12MAdded
27) Filament
Lamps
All unmonitored, permanently
illuminated filament lamp indicators
at control and indicating equipment
should be replaced.
12MAdded
28) Radio signal Radio signal strengths in
radio-linked systems should be
checked for adequacy.
12MAdded
29) Cables A visual inspection should be made
to confirm that all readily accessible
cable fixings are secure and
undamaged.
12MAdded
30) Cause & Effect The cause and effect programme
should be confirmed as being
correct.
12MAdded
31) Standby
Power
The standby power supply capacity
should be checked to establish it
remains suitable for continued
service.
12MAdded
32) Shutters Operation - Check and ensure
action responds to appropriate
signals. Indicator lights - Check
operation and replace any faulty
lamps.
12MAdded
33) Drop fire
curtains
Condition – Check for mechanical
damage.
Operation - Check operation and
control mechanisms
See relevant section Smoke extract
SFG 52
12MAdded
34) Magnetic door
latches
Condition – Check for mechanical
damage.
Operation - Check operation and
control mechanisms
See relevant section Smoke extract
SFG 52
12MAdded
35) Smoke relief
vents - Fireman`s
control for vent
plant
Check operation and log operation
of fans and dampers.
3MAdded
36) Smoke relief
vents
Condition – Check for mechanical
damage.
Operation - Check operation and
control mechanisms
See relevant section Smoke extract
SFG 52
12MAdded
37) Emergency
manual operated
systems.
Test Operation These devices should be tested
frequently by the clients’ operators
3MAdded
38) Interlocks Condition – Check for mechanical
damage.
Operation - Check operation and
control mechanisms.
Interlocks will be with heating,
ventilating and cooling equipment
and with fire extinguishing and other
systems , i.e. Smoke curtains SFG
52-04
12MAdded
Page 62 of 222
Previous
Version
Updated
Version
Reason For
Change
Page 63 of 222
FIRE PROTECTION SYSTEMS
Page 64 of 222
Previous
Version
Updated
Version
Reason For
Change
HOSE REELS - Static or Swinging23-03 23-03 HOSE REELS - Static or Swinging
Title NotesActionFQTitle FQ Action Notes
9) Swinging reels Check that the movement is free
and that the reel swings minimum
required angles shown in BS EN
671 parts 1 & 2. Check condition of
‘O’ rings
If leakage is evident replace `O`
rings.
12MAdded
10a) Stop Valves
– Manual reels
check the manual stop valve is of
correct type and that it operates
easily and correctly
12MAdded
10b) Stop Valves
– Automatic reels
check the correct operation of the
automatic valve and check for the
correct operation of the isolating
service valve
12MAdded
11)Back flow
prevention devices
(check valves).
Check operation. Ensure that valve is seating
properly.
12MAdded
12) Notices Check that the location is clearly
marked and that the operating
instructions are clear.
12MAdded
13) Water flow Check that the flow of water is
steady and sufficient
12MAdded
14)Hose All hoses shall be pressurised to
maximum working pressure in
accordance with BS EN 671 parts 1
& 2
60MAdded
Page 65 of 222
Previous
Version
Updated
Version
Reason For
Change
RISING FIRE MAINS and HYDRANTS23-04 23-04 RISING FIRE MAINS and HYDRANTS
Where, due to unforeseen difficulties, it is necessary to leave an installation not available for use, the
fire and rescue service should be informed immediately in order that alternative arrangements can be
made to cover this deficiency should the need arise. In addition a suitable notice to indicate that the
installation is not available for use should be placed in a prominent position.
Added
Title NotesActionFQTitle FQ Action Notes
Page 66 of 222
Previous
Version
Updated
Version
Reason For
Change
HALON FIRE PROTECTION SYSTEMS23-05 23-05 Gas Extinguishing systems
Title NotesActionFQTitle FQ Action Notes
8) Master/slave
system.
Check slave actuation system
including pistons in pneumatic valve
actuators.
6MAdded
9) Auxiliary electric
device/ alarm,
door closures, etc.
Test operation. Operational test to be carried out in
accordance with manufacturers
recommended procedure.
6MAdded
10) Enclosure
Integrity test
Check the enclosure for any
boundary penetrations or other
changes to it that could affect
leakage of gas on operation. If this
can not be visually determined an
integrity test should be carried out.
Test should be carried out in
accordance with Annex E BS EN
15004-1:2008
Where the integrity test reveals
increased leakage that would result
in an inability to retain the
extinguishant for the required
period, remedial action shall be
carried out.
12MAdded
Page 67 of 222
Previous
Version
Updated
Version
Reason For
Change
CARBON DIOXIDE TOTAL FLOODING FIRE EXTINGUISHING SYSTEM23-06 23-06 CARBON DIOXIDE TOTAL FLOODING FIRE EXTINGUISHING SYSTEM
Title NotesActionFQTitle FQ Action Notes
8) Master/slave
system.
Check slave actuation system
including pistons in pneumatic valve
actuators.
6MAdded
9) Auxiliary electric
device/ alarm,
door closures, etc.
Test operation. Operational test to be carried out in
accordance with manufacturers
recommended procedure.
6MAdded
10) Enclosure
Integrity test
Check the enclosure for any
boundary penetrations or other
changes to it that could affect
leakage of gas on operation. If this
can not be visually determined an
integrity test should be carried out.
Test should be carried out in
accordance with Annex A BS
5306-4:2001
Where the integrity test reveals
increased leakage that would result
in an inability to retain the
extinguishant for the required
period, remedial action shall be
carried out.
12MAdded
Page 68 of 222
Previous
Version
Updated
Version
Reason For
Change
EXPANSION FOAM SYSTEMS23-07 23-07 EXPANSION FOAM SYSTEMS
Title NotesActionFQTitle FQ Action Notes
6) Pipework Visual check of pipework, foam
outlets, nozzles and pipe supports
for damage or deterioration
If visual indication of normally dry
pipework indicates questionable
strength due to corrosion or
mechanical damage, hydraulically
pressure test.
1MAdded
7) Frost protection Check frost protection for the
permanently charged pipework
system
1MAdded
8) Tanks Test automatic refill devices of
water tanks
1MAdded
9) Alarms Check of alarm signalling to a
permanent manned location in the
case of automatic released
extinguishing systems.
1MAdded
10) Air Inlet Check the air inlet opening of foam
generating devices/nozzles are free
from obstruction
1MAdded
11) Strainers Check and clean strainers6MAdded
12) Foam
concentrate
proportioner
Functionally test the foam
concentrate proportioner using
water without the use of foam
concentrate (where specified by the
manufacturer
6MAdded
13) Valves Test the free movement of all
valves and mechanically operated
components. Check for free
operation of stop valves.
6MAdded
14) Foam
Concentrate
A check of the foam concentrate
properties shall be carried out by
competent and trained foam
laboratory
personnel. The sampling shall be
carried out according to the
manufacturer’s instructions.
The checks shall include; foam type,
specific gravity, PH, undissolved
solids/sediment, drain time, foam
expansion rate, spreading
coefficient - film formation (on
Cyclohexane) – film forming foams
only, alcohol burnback test (AR
foams only).
The results, and ‘pass’ or ‘fail’
conclusions, shall be given in a
report.
If the foam concentrate report does
not give a ‘pass’ i.e. fit for use, as a
result of its quality check tests, it
shall be
replaced immediately using foam
concentrate of the same type which
is passed fit for use
12MAdded
Page 69 of 222
Previous
Version
Updated
Version
Reason For
Change
15) Foam
proportioning
accuracy test
A test of the proportioner and
associated fittings shall be carried
out. The test shall be carried out at
the maximum and minimum system
design flow rates. The accuracy of
foam proportioning shall be in
accordance with the tolerance given
in EN 13565-1. These tests should,
where possible, be carried out with
environmentally compatible foam
substitutes.
12MAdded
16) Discharge test A discharge test should be carried
out on each system to verify;
correct function of the system,
nozzles are free from blockage,
correct functioning of valves,
required discharge coverage is
achieved
12MAdded
17) Premix A check of the premixed foam
solutions properties shall be carried
out by competent and trained foam
laboratory personnel. If the
premixed foam solution report does
not give a ‘pass’ i.e. fit for use, as a
result of its quality check tests, it
shall be replaced immediately using
foam concentrate of the same type
which is passed fit for use
12MAdded
18) Concentrate Check the foam concentrate tanks
and components permanently in
contact with foam concentrate for
signs of external defects, e.g.
leakage, debris on seals.
12MAdded
19) Vapour seals Inspect integrity of vapour seals on
tank foam pourers and burst discs
in subsurface systems
12MAdded
Page 70 of 222
Previous
Version
Updated
Version
Reason For
Change
FIRE EXTINGUISHERS - GAS SUPPRESSION23-08 23-08 FIRE EXTINGUISHERS - GAS SUPPRESSION (Halon)
Title NotesActionFQTitle FQ Action Notes
7) Extinguisher -
Overhaul
Empty the extinguisher and strip the
components down completely.
Reassemble and recharge the
extinguisher with new headcaps
and valves.
Selected halon alternative agents
have superseded halon usage in
fixed fire suppression system and
portable fire extinguisher
applications.
120MAdded
Page 71 of 222
Previous
Version
Updated
Version
Reason For
Change
FIRE EXTINGUISHERS - CARBON DIOXIDE23-09 23-09 FIRE EXTINGUISHERS - CARBON DIOXIDE
Title NotesActionFQTitle FQ Action Notes
6) Safety pin Remove the safety pin and check
that the operating lever is
undamaged and its movement is
unobstructed. Safety precautions
should be taken to avoid
inadvertent operation. Return the
safety pin or, where necessary, a
replacement pin to the extinguisher
12MAdded
7) Seals Ensure that all seals for the
discharge horn, the hose, the
nozzle and the valve body are in
place, as prescribed in the
extinguisher manufacturer’s
instructions.
12MAdded
8) Label Complete the details on the
maintenance label
12MAdded
9) Mounting
bracket/stand
Check any mounting bracket or
stand if accessible and rectify any
problems.
12MAdded
10) Report Write an inspection report advising
the responsible person of the state
of maintenance of the extinguisher
12MAdded
11)Overhaul
procedure every
10 years
a) Discharge the extinguisher.
Remove the swivel horn/hose
assembly, the valve and the valve
assembly, and remove the diptube
from the valve assembly. Destroy
the valve.
b) Pressure-test the body shell in
accordance with the test pressure
indicated on the body. Do not
overhaul the body if it is unmarked.
Permanently mark the body shell
with the retest date and the
identification of the organization
performing the test. (Attention is
drawn to the Carriage of Dangerous
Goods and Use of Transportable
Pressure Equipment Regulations
2007
c) Reassemble and recharge the
extinguisher with new
headcaps/valves
120MAdded
Page 72 of 222
Previous
Version
Updated
Version
Reason For
Change
FIRE EXTINGUISHERS - FOAM (Stored Pressure)23-10 23-10 FIRE EXTINGUISHERS - FOAM (Stored Pressure)
When removing parts from extinguishers, competent persons should ensure that they are clear of any
parts which might be ejected. Under no circumstances should any attempt be made to remove the
valves of high pressure extinguishers or cartridges under field conditions. Extreme caution should be
used when opening any extinguisher.
Such devices must only be maintained and tested by qualified engineers and in accordance with BS
5306-3:2009
Added
Title NotesActionFQTitle FQ Action Notes
8) Seals The seals for the discharge horn,
the hose, the nozzle and the valve
body should be replaced with new
seals when these components are
removed from the extinguisher. If
the hose is fitted with a diaphragm,
this should always be replaced with
a new diaphragm.
Check the condition and fitness for
use of the discharge nozzle, horn
and hose, and ensure that the
nozzle, horn and hose, if fitted, are
not obstructed, cracked, worn, or
damaged. Replace with a new
nozzle, horn and/or hose if
necessary.
12MAdded
9) Reassembly Reassemble the extinguisher in
accordance with the instructions of
the extinguisher manufacturer.
Replace with new any safety clip
and indicating device designed to
show whether the extinguisher
might have been operated.
12MAdded
10) Label Complete the details on the
maintenance label
12MAdded
11) Mounting
bracket/stand
Check any mounting bracket or
stand if accessible and rectify any
problems.
12MAdded
12) Report Write an inspection report advising
the responsible person of the state
of maintenance of the extinguisher
12MAdded
Extended Service
procedures every
5 years
60MAdded
Page 73 of 222
Previous
Version
Updated
Version
Reason For
Change
13) Prior to performing the test
discharge, the extinguisher should
be examined externally for any
obvious signs of damage to the
body or operating mechanism. If a
plastics headcap is coated in such
a way as to disguise degradation
(e.g. by painting), replace with a
new headcap before proceeding to
action 2. In the case of stored
pressure extinguishers, additional
safety precautions should be
observed.
60MAdded
14) Perform the test discharge on the
extinguisher.
60MAdded
15) Examine the body internally and in
detail for corrosion, dents, cuts,
gouges or lining damage. Pay
special attention to the welds.
Follow the extinguisher
manufacturer’s instructions where
there are any doubts about the
welds.
60MAdded
16) Examine and check all closures for
thread wear, damage and corrosion
as applicable.
60MAdded
17) Return the extinguisher to
operational condition. If the
extinguisher was fitted with a
plastics headcap, it should be fitted
with a new headcap, if this has not
already been fitted in action 13
(above). Reassemble and recharge
the extinguisher in accordance with
the extinguisher
manufacturer’s instructions
60MAdded
Page 74 of 222
Previous
Version
Updated
Version
Reason For
Change
FIRE EXTINGUISHERS - POWDER23-11 23-11 FIRE EXTINGUISHERS - POWDER (GAS CARTRIDGE)
When removing parts from extinguishers, competent persons should ensure that they are clear of any
parts which might be ejected. Under no circumstances should any attempt be made to remove the
valves of high pressure extinguishers or cartridges under field conditions. Extreme caution should be
used when opening any extinguisher.
Such devices must only be maintained and tested by qualified engineers and in accordance with BS
5306-3:2009
Added
Title NotesActionFQTitle FQ Action Notes
10) Gas cartridge Examine the gas cartridge
externally for corrosion or damage.
If the gas cartridge has suffered
mechanical damage or is corroded,
replace as recommended by the
extinguisher supplier. Weigh the
gas cartridge and check the mass
against that marked on the gas
cartridge. If the gas cartridge has
sustained a loss of content greater
than 10% (15% for cartridges with a
content mass of less than 30 g) of
the original content, withdraw it
from service and replace it with a
gas cartridge as recommended by
the extinguisher manufacturer.
Check the date marked on the
cartridge
12MAdded
11) Seals The seals for the discharge horn,
the hose, the nozzle and the valve
body should be replaced with new
seals when these components are
removed from the extinguisher. If
the hose is fitted with a diaphragm,
this should always be replaced with
a new diaphragm.
Check the condition and fitness for
use of the discharge nozzle, horn
and hose, and ensure that the
nozzle, horn and hose, if fitted, are
not obstructed, cracked, worn, or
damaged. Replace with a new
nozzle, horn and/or hose if
necessary.
12MAdded
12) Body - powder Examine the interior with the aid of
an inspection light. Check for
corrosion and deterioration of lining,
if fitted.
0MAdded
Page 75 of 222
Previous
Version
Updated
Version
Reason For
Change
13) Reassembly Reassemble the extinguisher in
accordance with the instructions of
the extinguisher manufacturer.
Replace with new any safety clip
and indicating device designed to
show whether the extinguisher
might have been operated.
12MAdded
14) Label Complete the details on the
maintenance label
12MAdded
15) Mounting
bracket/stand
Check any mounting bracket or
stand if accessible and rectify any
problems.
12MAdded
16) Report Write an inspection report advising
the responsible person of the state
of maintenance of the extinguisher
12MAdded
Extended Service
procedures every
5 years
60MAdded
17) Prior to performing the test
discharge, the extinguisher should
be examined externally for any
obvious signs of damage to the
body or operating mechanism. If a
plastics headcap is coated in such
a way as to disguise degradation
(e.g. by painting), replace with a
new headcap before proceeding to
action 2. In the case of stored
pressure extinguishers, additional
safety precautions should be
observed.
60MAdded
18) Perform the test discharge on the
extinguisher.
60MAdded
19) Examine the body internally and in
detail for corrosion, dents, cuts,
gouges or lining damage. Pay
special attention to the welds.
Follow the extinguisher
manufacturer’s instructions where
there are any doubts about the
welds.
60MAdded
20) Examine and check all closures for
thread wear, damage and corrosion
as applicable.
60MAdded
Page 76 of 222
Previous
Version
Updated
Version
Reason For
Change
21) Return the extinguisher to
operational condition. If the
extinguisher was fitted with a
plastics headcap, it should be fitted
with a new headcap, if this has not
already been fitted in action 13
(above). Reassemble and recharge
the extinguisher in accordance with
the extinguisher
manufacturer’s instructions.
60MAdded
Page 77 of 222
Previous
Version
Updated
Version
Reason For
Change
FIRE EXTINGUISHERS - WATER - GAS CARTRIDGE23-12 23-12 FIRE EXTINGUISHERS - WATER - GAS CARTRIDGE
Title NotesActionFQTitle FQ Action Notes
10) Gas cartridge Examine the gas cartridge
externally for corrosion or damage.
If the gas cartridge has suffered
mechanical damage or is corroded,
replace as recommended by the
extinguisher supplier. Weigh the
gas cartridge and check the mass
against that marked on the gas
cartridge. If the gas cartridge has
sustained a loss of content greater
than 10% (15% for cartridges with a
content mass of less
than 30 g) of the original content,
withdraw it from service and replace
it with a gas cartridge as
recommended by the extinguisher
manufacturer. Check the date
marked on the cartridge
12MAdded
11) Seals The seals for the discharge horn,
the hose, the nozzle and the valve
body should be replaced with new
seals when these components are
removed from the extinguisher. If
the hose is fitted with a diaphragm,
this should always be replaced with
a new diaphragm.
Check the condition and fitness for
use of the discharge nozzle, horn
and hose, and ensure that the
nozzle, horn and hose, if fitted, are
not obstructed, cracked, worn, or
damaged. Replace with a new
nozzle, horn and/or hose if
necessary.
12MAdded
12) Body: water,
water-based
and foam
Examine the interior with the aid of
an inspection light. Check for
corrosion or lining deterioration.
Check separate containers for
additives and replace if they are
leaking or damaged
12MAdded
13) Water and
water-based
(including foam)
charges
Return the original charge to the
extinguisher, or replace with new
charge according the instructions of
the extinguisher manufacturer
12MAdded
14) Reassembly Reassemble the extinguisher in
accordance with the instructions of
the extinguisher manufacturer.
Replace with new any safety clip
and indicating device designed to
show whether the extinguisher
might have been operated.
12MAdded
Page 78 of 222
Previous
Version
Updated
Version
Reason For
Change
15) Label Complete the details on the
maintenance label
12MAdded
16) Mounting
bracket/stand
Check any mounting bracket or
stand if accessible and rectify any
problems.
12MAdded
17) Report Write an inspection report advising
the responsible person of the state
of maintenance of the extinguisher
12MAdded
Extended Service
procedures every
5 years
60MAdded
17) Prior to performing the test
discharge, the extinguisher should
be examined externally for any
obvious signs of damage to the
body or operating mechanism. If a
plastics headcap is coated in such
a way as to disguise degradation
(e.g. by painting), replace with a
new headcap before proceeding to
action 2. In the case of stored
pressure extinguishers, additional
safety precautions should be
observed.
60MAdded
18) Perform the test discharge on the
extinguisher.
60MAdded
19) Examine the body internally and in
detail for corrosion, dents, cuts,
gouges or lining damage. Pay
special attention to the welds.
Follow the extinguisher
manufacturer’s instructions where
there are any doubts about the
welds.
60MAdded
20) Examine and check all closures for
thread wear, damage and corrosion
as applicable.
60MAdded
21) Return the extinguisher to
operational condition. If the
extinguisher was fitted with a
plastics headcap, it should be fitted
with a new headcap, if this has not
already been fitted in action 13
(above). Reassemble and recharge
the extinguisher in accordance with
the extinguisher manufacturer’s
instructions
60MAdded
Page 79 of 222
Previous
Version
Updated
Version
Reason For
Change
FIRE EXTINGUISHERS - WATER STORED PRESSURE23-13 23-13 FIRE EXTINGUISHERS - WATER STORED PRESSURE
When removing parts from extinguishers, competent persons should ensure that they are clear of any
parts which might be ejected. Under no circumstances should any attempt be made to remove the
valves of high pressure extinguishers or cartridges under field conditions. Extreme caution should be
used when opening any extinguisher.
Such devices must only be maintained and tested by qualified engineers and in accordance with BS
5306-3:2009
Added
Title NotesActionFQTitle FQ Action Notes
9) Reassembly Reassemble the extinguisher in
accordance with the instructions of
the extinguisher manufacturer.
Replace with new any safety clip
and indicating device designed to
show whether the extinguisher
might have been operated.
12MAdded
10) Label Complete the details on the
maintenance label
12MAdded
11) Mounting
bracket/stand
Check any mounting bracket or
stand if accessible and rectify any
problems.
12MAdded
12) Report Write an inspection report advising
the responsible person of the state
of maintenance of the extinguisher
12MAdded
Extended Service
procedures every
5 years
60MAdded
13) Prior to performing the test
discharge, the extinguisher should
be examined externally for any
obvious signs of damage to the
body or operating mechanism. If a
plastics headcap is coated in such
a way as to disguise degradation
(e.g. by painting), replace with a
new headcap before proceeding to
action 2. In the case of stored
pressure extinguishers, additional
safety precautions should be
observed.
60MAdded
14) Perform the test discharge on the
extinguisher.
60MAdded
15) Examine the body internally and in
detail for corrosion, dents, cuts,
gouges or lining damage. Pay
special attention to the welds.
Follow the extinguisher
manufacturer’s instructions where
there are any doubts about the
welds.
60MAdded
Page 80 of 222
Previous
Version
Updated
Version
Reason For
Change
16) Examine and check all closures for
thread wear, damage and corrosion
as applicable.
60MAdded
17) Return the extinguisher to
operational condition. If the
extinguisher was fitted with a
plastics headcap, it should be fitted
with a new headcap, if this has not
already been fitted in action 13
(above). Reassemble and recharge
the extinguisher in accordance with
the extinguisher manufacturer’s
instructions
60MAdded
Page 81 of 222
Previous
Version
Updated
Version
Reason For
Change
SPRINKLER SYSTEMS23-14 23-14 SPRINKLER SYSTEMS
Title NotesActionFQTitle FQ Action Notes
SERVICE &
MAINTENANCE
The effect of any changes of
structure, occupancy, storage
configuration, heating, lighting or
equipment etc. of a building on
hazard classification or installation
design shall be identified in order
that the appropriate modifications
may be carried out.
Added
Page 82 of 222
GRILLES AND DIFFUSERS
Page 83 of 222
Previous
Version
Updated
Version
Reason For
Change
GRILLES AND DIFFUSERS26-01 26-01 GRILLES AND DIFFUSERS
Where possible these should be removed for cleaning. Washing to remove grease and staining may
be required.
Diffuser/grille locations and orientation should be marked or recorded if they are to be taken away for
washing, so that they can be returned to the correct location. Opposed blade dampers should have
the ‘as found’ setting marked to aid resetting.
Certain grille and diffuser arrangements may be installed such that they cannot be practicably
removed for cleaning, e.g. linear diffusers or those trapped by partition walls. Insitu cleaning by air line
and extraction to capture dislodged deposits may be used.
Diffusers may have plenum boxes, possibly containing dampers behind them, which also require
cleaning. Access will be required to permit cleaning or air jetting and extraction methods.
Added
Title NotesActionFQTitle FQ Action Notes
Page 84 of 222
HAZARDOUS AREA (ELECTRICS)
Page 85 of 222
Previous
Version
Updated
Version
Reason For
Change
Hazardous areas - LIGHTING27-03 27-03 Hazardous areas - LIGHTING
Before commencing any maintenance work on Flame proof equipment, read Hazardous area
(electrics) introductory procedures SFG 27-01 very carefully and follow all the safety procedures.
Replacement parts shall be in accordance with the safety documentation. Alterations to equipment
shall not be carried out without appropriate authorisation where they adversely affect the safety of the
equipment as stated in the safety documentation. Repairs and reclamation of equipment shall be
carried out in accordance with IEC 60079-19.
Added
Title NotesActionFQTitle FQ Action Notes
Page 86 of 222
Previous
Version
Updated
Version
Reason For
Change
Hazardous areas - EARTHING27-04 27-04 Hazardous areas - EARTHING
Before commencing any maintenance work on Flame proof equipment, read Hazardous area
(electrics) introductory procedures SFG 27-01 very carefully and follow all the safety procedures.
Replacement parts shall be in accordance with the safety documentation. Alterations to equipment
shall not be carried out without appropriate authorisation where they adversely affect the safety of the
equipment as stated in the safety documentation. Repairs and reclamation of equipment shall be
carried out in accordance with IEC 60079-19
Added
Title NotesActionFQTitle FQ Action Notes
a) Earth connections to maintain the
integrity of the intrinsic safety safe
system (such as transformer screen
earth, barrier relay frame earth)
shall be measured. There is no
requirement to measure the earth
loop impedance of mains powered
equipment associated with
intrinsically safe circuits other than
that required for normal control
room instrumentation to protect
against electric shock. Since, in
some equipment, the intrinsic
safety earthing is internally
connected to the equipment frame,
any impedance measurements
(such as between the earth pin of
the plug and the equipment frame,
or the equipment frame and the
control panel) shall be made using
a tester specifically designed for
use on intrinsically safe circuits
6MAdded
Page 87 of 222
Previous
Version
Updated
Version
Reason For
Change
b) Intrinsically safe circuit earthing
and/or insulation
The insulation testing of intrinsically
safe circuits is necessary to confirm
that they are earthed or insulated
from earth throughout, whichever of
these conditions is required by the
original design. This requirement
may be unnecessary if an earth
fault is self revealing, for example, if
a circuit "fails safe" as result of an
earth fault or the circuit uses an
earth leakage monitoring device.
Insulation testing of intrinsically
safe systems or circuits shall only
be carried out using a test device
specifically approved for connection
to such circuits.
Where, in order to carry out these
tests, the common earth connection
to a group of barriers is
disconnected, the tests can only be
made if either the plant is free from
hazard, or if power is removed
completely from all the circuits
which depend upon that common
earth connection. This test is only
required on a sample basis.
6MAdded
Page 88 of 222
HEAT EMITTERS
Page 89 of 222
Previous
Version
Updated
Version
Reason For
Change
HEAT EMITTERS28-01 28-01 HEAT EMITTERS
Title NotesActionFQTitle FQ Action Notes
7. TRV`s Check air temperature calibration
against surface temperature of heat
emitter. Advise client if air flow
around sensor is restricted or
affected by any reflected or other
thermal gains. Check operation of
thermostatic radiator valves.
Low temperature surfaces for heat
emitters are desirable in homes for
senior citizens/disabled.
12MAdded
8. General. Leave unit in good working order. Report on any further work
considered necessary.
12MAdded
Fan convectors
[electric]
12MAdded
1. Casing Examine condition of casing,
access panels and grilles. Check
unit is secure, free from dust and
dirt especially at air inlet and
discharge grilles.
12MAdded
2.Controls Check all thermostats and other
controls operate satisfactorily and
are set in accordance with
specification.
12MAdded
3.Fan Inspect air circulation fan set(s),
check fan/motor assembly for
damage and for correct alignment.
Check for wear at any resilient
mounts.
12MAdded
4. Heat exchanger Examine heater battery/element,
clean and comb as required.
12MAdded
7. Electrical Heater Unit Check function &
operation of local isolation device
(stoplock/isolator). Examine and
report condition of all associated
wiring, ensure security of all
terminal connections and check for
satisfactory condition of any flexible
cables/conduits. Ensure plant has
adequate earth conductor and
bonding is secure. Take and log
motor current and compare with
nameplate details. Check all
temperature control devices for
correct operation and function.
12MAdded
Page 90 of 222
Previous
Version
Updated
Version
Reason For
Change
5. TRV’s Check air temperature calibration
against surface temperature of heat
emitter. Advise client if air flow
around sensor is restricted or
effected by any reflected or other
thermal gains. Check operation of
thermostatic radiator valves.
Low temperature surfaces for heat
emitters are desirable in homes for
senior citizens/disabled.
12MAdded
Page 91 of 222
Previous
Version
Updated
Version
Reason For
Change
GAS FIRED CERAMIC PLAQUE INFRA RED HEATERS28-02 28-02 GAS FIRED CERAMIC PLAQUE INFRA RED HEATERS
Title NotesActionFQTitle FQ Action Notes
1. General check unit is secure and that all
bolts, nuts, setscrews etc. for
security. Check and clean surfaces
of unit, check for corrosion, repair
and treat as found necessary.
12MAdded
Page 92 of 222
Previous
Version
Updated
Version
Reason For
Change
GAS RADIANT TUBE HEATERS28-03 28-03 GAS RADIANT TUBE HEATERS
These heaters are usually placed high up in a building and consequently are not easily accessible. A
risk assessment and method statement should be carried out. Access by stepladders is not
recommended. Regular maintenance is essential and whilst annual maintenance may be adequate in
a clean environment, dusty conditions will require more frequent maintenance. In very dusty
environments, e.g. textile factories, it may be more desirable to duct a direct combustion air line to the
heater.
Correct combustion entails the adequate mixing of the fuel with air to ensure that the fuel is
completely burnt without producing excessive smoke or diluting the combustion gases with excess air
both of which cause energy wastage. With all fossil fuels, insufficient air produces carbon monoxide, a
safety and health hazard, as undetected CO is poisonous.
Added
Title NotesActionFQTitle FQ Action Notes
17. Wiring and
Controls
Check for satisfactory operation of
local electrical isolation switch.
Check function and operation of all
control switches and temperature
controls. Examine and report
condition of all associated wiring,
ensure security of all terminations
and check for satisfactory condition
of any flexible cables/conduits.
Ensure plant has adequate earth
conductor and bonding is secure
12MAdded
Page 93 of 222
Previous
Version
Updated
Version
Reason For
Change
GAS FIRED NATURAL AND FAN ASSISTED HEATERS - Conventional and
Balanced Flue.
28-04 28-04 GAS FIRED NATURAL AND FAN ASSISTED HEATERS - Conventional and
Balanced Flue.
These heaters are usually placed high up in a building and consequently are not easily accessible. A
risk assessment and method statement should be carried out. Access by stepladders is not
recommended. Regular maintenance is essential and whilst annual maintenance may be adequate in
a clean environment, dusty conditions will require more frequent maintenance. In very dusty
environments, e.g. textile factories, it may be more desirable to duct a direct combustion air line to the
heater.
Correct combustion entails the adequate mixing of the fuel with air to ensure that the fuel is
completely burnt without producing excessive smoke or diluting the combustion gases with excess air
both of which cause energy wastage. With all fossil fuels, insufficient air produces carbon monoxide, a
safety and health hazard, as undetected CO is poisonous.
Added
Title NotesActionFQTitle FQ Action Notes
11 Gas pressure,
gas pipework and
cocks
Check with rated value and adjust if
necessary. Check gas cocks are
free to turn, lubricate as necessary.
Inspect gas pipework system,
check for leaks, loose brackets and
supports, repair as necessary,
report all findings.
The rated value will be found on the
identification plate or in the
operating instructions.
12MAdded
12. Wiring and
Controls
Check for satisfactory operation of
local electrical isolation switch.
Check function and operation of all
control switches and temperature
controls. Examine and report
condition of all associated wiring,
ensure security of all terminations
and check for satisfactory condition
of any flexible cables/conduits.
Ensure plant has adequate earth
conductor and bonding is secure.
12MAdded
Page 94 of 222
HEAT EXCHANGERS
Page 95 of 222
Previous
Version
Updated
Version
Reason For
Change
HEAT EXCHANGERS - COILS29-01 29-01 HEAT EXCHANGERS - COILS
Title NotesActionFQTitle FQ Action Notes
5. Coil vent. Check operation, condition of filters
and sight glasses.
6MAdded
6. Pipework Inspect connections, pipes and
supports for damage, loose or
missing fittings. Repair as
necessary.
12MAdded
5. Pipework Inspect connections, pipes and
supports for damage, loose or
missing fittings. Repair as
necessary
12MAdded
5. Flues Service. For detailed information on
maintenance of Flues see Flues
SFG 24-01.
12MAdded
Page 96 of 222
Previous
Version
Updated
Version
Reason For
Change
ELECTRIC/AIR HEATER29-02 29-02 ELECTRIC/AIR HEATER
Title NotesActionFQTitle FQ Action Notes
1. air side, Clean coils air-side surfaces by
blowing through with dry, oxygen
free, nitrogen from the opposite
side to the air flow. Where Nitrogen
is used, a Risk Assessment must
be done prior and suitable training
given.
Comb fins if appropriate. Where
necessary clean with appropriate
sterilising solution. Particularly dirty
coils should be reported to the client
as the filter changing regime may
need to be amended.
12MAdded
Page 97 of 222
HEAT REJECTION SYSTEMS
Page 98 of 222
Previous
Version
Updated
Version
Reason For
Change
COOLING TOWERS - Precautions against Legionnaires disease (legionella
pneumophila)
30-02 30-02 COOLING TOWERS - Precautions against Legionnaires disease (legionella
pneumophila)Title NotesActionFQTitle FQ Action Notes
Tower HygieneAdded
Tower
Maintenance
Added
1. Fans and
Motors
Check the condition of the fan
motor through temperature or
vibration analysis and compare to
baseline values. Assure that all
bearings are lubricated per the
manufacture`s recommendation.
Check for excessive wear and
secure fastening. Aligning the
motor coupling allows for efficient
torque transfer.
1MAdded
2. Strainers Physically clean screen(s) of all
debris.
1WAdded
3. Drain and
Overflow
Check that drain and overflow are
clear from blockage.
1WAdded
4. Float Switches Operate switch manually to ensure
proper operation.
1WAdded
5. tower structure Check for excessive vibration in
motors, fans, and pumps. Check for
loose fill, connections, leaks, etc.
1WAdded
6. Water
Treatment
Check that water treatment
automatic dosing equipment is
functional.
For Further Guidance see Water
treatment SFG 65.
1WAdded
7. Test water
samples (Open
System)
Test for proper concentrations of
dissolved solids, and
microbiological quality of the pond
water by undertaking a dip slide
test. Adjust blowdown and
chemicals as necessary. Record
the result. Undertake additional
water quality tests such as pH,
conductivity and tests for hardness
salts as determined by risk
assessment.
See `Table 1 Typical on-site
monitoring checks recommended for
good operating practice` page 36 of
L8 3rd Edition 2000.
1WAdded
Page 99 of 222
Previous
Version
Updated
Version
Reason For
Change
8. Test water
samples (Closed
System)
Test for proper concentrations of
dissolved solids, and
microbiological quality of the pond
water by undertaking a dip slide
test. Adjust blowdown and
chemicals as necessary. Record
the result. Undertake additional
water quality tests such as pH,
conductivity and tests for hardness
salts as determined by risk
assessment.
See `Table 1 Typical on-site
monitoring checks recommended for
good operating practice` page 36 of
L8 3rd Edition 2000.
1MAdded
9. All internal
areas
Check internal surfaces for algae,
scale, rust and limescale
accumulation.
1MAdded
10. Drift
eliminators,
louvers, tubes and
fill
Look for proper positioning and
scale build up. Clean as needed
The frequency of the task can vary
depending on the water quality. The
Risk assessment may give greater
or lesser frequencies for this task.
1MAdded
11. Sparge Pipe Make sure water is flowing through
nozzles to ensure even distribution
over the fill.
1MAdded
12. Bearings Inspect bearings and drive belts for
wear. Adjust, repair, or replace as
necessary.
12MAdded
13. Motors Undertake annual maintenance.
For further Guidance see Motors
SFG 39-01.
12MAdded
Page 100 of 222
Previous
Version
Updated
Version
Reason For
Change
DRY COOLERS30-03 30-03 DRY COOLERS
Title NotesActionFQTitle FQ Action Notes
6. Electrical. Check for satisfactory operation of
local electrical isolation device
stoplock/isolator). Examine and
report condition of all associated
wiring, ensure security of all
terminal connections and check for
satisfactory condition of any flexible
cables/conduits. Ensure plant has
adequate earth conductor and
bonding is secure.
6MAdded
7. Insulation. Check condition. Repair and reseal
as necessary.
6MAdded
8. General
cleanliness.
Clean surfaces and components of
unit particularly fan impeller and
motor casing. Check and clean
surfaces of unit casing, check for
corrosion, repair and treat as found
necessary
Remove any dirt or rubbish from
vicinity of plant.
6MAdded
9. System
operation.
Check function and operation of all
automatic sensors /detectors
(flow/temperature). Check for
correct operation/shut-down of
plant. Ensure all devices are
returned to their correct settings.
Clean air inlet & discharge grilles.
Check all access doors for fit and
can be made secure. When shut,
ensure for air tight seal.
i.e. Start/stops and capacity
regulators should be in accordance
with externally applied control
systems if applicable.
6MAdded
Page 101 of 222
HOT WATER SUPPLY
Page 102 of 222
Previous
Version
Updated
Version
Reason For
Change
HOT WATER CALORIFIERS HEATED BY STEAM32-06 32-06 HOT WATER CALORIFIERS HEATED BY MTHW, HTHW or STEAM
Title NotesActionFQTitle FQ Action Notes
12 Internal
Inspection
Arrange for an internal inspection to
be carried out by a Competent
Person as required by the Written
Scheme of Examination.
Pressure Systems Safety
Regulations 2000 will apply.
12MAdded
Page 103 of 222
Previous
Version
Updated
Version
Reason For
Change
HOT WATER SUPPLY CALORIFIERS - including LOAD LEVELLERS32-07 32-07 HOT WATER SUPPLY CALORIFIERS
Prior to carrying out the planned maintenance of the calorifier, the pre-maintenance procedure
detailed in 32-04 should be followed:
(a) Check equipment operating status (i.e. whether in operation or not in use, whether isolated from
system) including safety.
(b) Inspect calorifier insulation and/or shell for signs of damage.
(c) Inspect all manholes, mounting and joints for signs of leaks.
Added
Title NotesActionFQTitle FQ Action Notes
7. Sacrificial
anode.
Check status. Replace as necessary.12MAdded
2 Storage
Temperature
Check and record the calorifier
water storage temperature
It is recommended that the hot
water should be stored at 60oC
(ACOP L8). Where temperatures
are recorded below 60oC, increase
set point to achieve the desired
temperature. If the temperature
cannot be maintained, report to
Client
1WAdded
11. Pasteurisation Hold temperature one hour above
60°C. prior to reinstatement.
Procedure as laid down in ACOP
L8: 2000 and HTM 04 Part B
12MAdded
Page 104 of 222
Previous
Version
Updated
Version
Reason For
Change
HOT WATER CYLINDERS32-09 32-09 HOT WATER CYLINDERS
Prior to carrying out the planned maintenance of the cylinder, the pre-maintenance procedure detailed
in 32-04 should be followed:
(a) Check equipment operating status (i.e. whether in operation or not in use, whether isolated from
system) including safety.
(b) Inspect calorifier insulation and/or shell for signs of damage.
(c) Inspect all manholes, mounting and joints for signs of leaks.
(d) Report any necessary remedial work where repairs, adjustment or replacement will be required
during routine maintenance.
PASTEURISATION
All secondary systems used to provide a hot water service must be pasteurised after a period of
shutdown or standby over a one week period in accordance with ACOP L8,2000 (www.hse.gov.uk)
and HTM 04 Part A & B. This includes shutdown to inspect calorifiers.
Added
Title NotesActionFQTitle FQ Action Notes
11. Temperature
sensor
Ensure that the temperature sensor
has a good surface to surface
contact with the cylinder.
12MAdded
1 Storage
Temperature
Check and record the calorifier
water storage temperature
It is recommended that the hot
water should be stored at 60oC
(ACOP L8). Where temperatures
are recorded below 60oC, increase
set point to achieve the desired
temperature. If the temperature
cannot be maintained, report to
Client
1WAdded
8. Pasteurisation Hold Temperature one hour above
60°C. prior to reinstatement.
Procedure as laid down in ACOP
L8: 2000 and HTM 04 Part B
12MAdded
Page 105 of 222
Previous
Version
Updated
Version
Reason For
Change
THERMAL STORAGE CYLINDER (individual dwellings for DHWS)32-11 32-11 THERMAL STORAGE CYLINDER (individual dwellings for DHWS)
PASTEURISATION
All secondary systems used to provide a hot water service must be pasteurised after a period of
shutdown or standby over a one week period in accordance with ACOP L8,2000 (www.hse.gov.uk)
and HTM 04 Part A & B. This includes shutdown to inspect calorifiers.
Added
Title NotesActionFQTitle FQ Action Notes
10. Temperature
sensor
Ensure that the temperature sensor
has a good surface to surface
contact with the cylinder.
12MAdded
1 Storage
Temperature
Check and record the calorifier
water storage temperature
It is recommended that the hot
water should be stored at 60oC
(ACOP L8). Where temperatures
are recorded below 60oC, increase
set point to achieve the desired
temperature. If the temperature
cannot be maintained, report to
Client
1WAdded
8. Pasteurisation Hold Temperature one hour above
60°C. prior to reinstatement.
Procedure as laid down in ACOP
L8: 2000, paragraph 154 and HTM
04 Part B.
12MAdded
Page 106 of 222
HUMIDIFIERS INCLUDING DISINFECTION PROCEDURES
Page 107 of 222
Previous
Version
Updated
Version
Reason For
Change
HUMIDIFIER - Direct steam injection type.33-02 33-02 HUMIDIFIER - Direct steam injection type.
Title NotesActionFQTitle FQ Action Notes
2. System Check any flange bolts for tightness
and adjust as required. Check all
gland seals adjust as required.
Visually inspect all pipe work and
joints for leaks.
1MAdded
15. Valves Inspect all valves for wear or scale
deposits. Worn or damaged parts
should be replaced as well as the
gland seal packaging. Check for
complete isolation and free
movement.
Graphite packaging is subject to
wear. It is therefore recommended
to replace such items.
12MAdded
18. Switch off
devices
Check the function of the switch-off
devices, e.g. the max hygrostat.
12MAdded
Page 108 of 222
Previous
Version
Updated
Version
Reason For
Change
HUMIDIFIERS- Compressed air type33-04 33-04 HUMIDIFIERS- Compressed air type
Title NotesActionFQTitle FQ Action Notes
1. Airline
components
Check (visually)inlet and outlet
compressed air and water supply
pressures, visual inspection of the
compressed air filter to check on air
quality, and visual inspection of the
sprays.
1MAdded
6. Water line
components
Water line components in the
control panel are subject to greater
wear and tear particularly in hard
water areas, and sediment filter
elements prior to the control panel
should be changed.
6MAdded
6. Airline
components
Airline components in the control
panel, such as pressure regulators,
pressure switches and solenoid
valves, will require annual
inspection and cleaning. According
to compressed air quality, air filters
immediately prior to the control
panel will need cleaning or
replacement between six months
and a year.
12MAdded
7. UV lamps (if
fitted)
Change UV lamps Weekly inspection of UV-lamp
operation is recommended,
although many compressed air
systems using this technology
incorporate failsafe systems to shut
down the humidifier in the event of
reduced effectiveness or failure.
12MAdded
Page 109 of 222
Previous
Version
Updated
Version
Reason For
Change
HUMIDIFIERS- Ultra sonic33-05 33-05 HUMIDIFIERS- Ultra sonic
Title NotesActionFQTitle FQ Action Notes
6. UVC lamps Change lamps UVC lamps in general have a life of
approximately 8,000 hours, however
due to the nature of their
construction; the
degradation in output accelerates
towards the end of its useful life.
12MAdded
7. Automatic
shutdown and
alarm system
Check that the alarm system (both
audible and visual)works when the
automatic shutdown system
operates. Check that the equipment
shuts down correctly and drains the
water reservoir.
12MAdded
Page 110 of 222
ICE MAKING MACHINES
Page 111 of 222
Previous
Version
Updated
Version
Reason For
Change
ICE MAKING MACHINES34-01 34-01 ICE MAKING MACHINES
Cleaning and maintenance of ice machines and storage units is essential in preventing contamination
of ice or equipment. Where possible always follow manufacturer’s instructions for maintenance and
cleaning. A regular cleaning schedule should be established and cleaning and maintenance records
maintained. The client should inspect the interior of the machine twice a week for build up of mould or
other contaminants, and clean accordingly.
The water supply to this equipment should be taken from a potable supply via a double check valve to
prevent backflow. Check that the water supply is taken upstream of a regularly used outlet with the
minimum of intervening pipe-run, that is, less than 3 m. The supply should not be softened.
Additionally, it should be established that the usage is sufficient to avoid deterioration in water quality ,
for example that the inlet water temperature does not exceed 20°C.
The Automatic Vending Association of Britain (AVAB) codes of practice should be followed regarding
hygiene and water quality and hygienic operation of vending machines.
Disconnect ice machines before planned water disruptions.
Added
Title NotesActionFQTitle FQ Action Notes
9. Ice Scoop Ensure the ice scoop and scoop
receptacle are also cleaned with
neutral detergent and water and
dried on a regular basis or as
specified by the manufacturer
Scoop should be kept on a chain
short enough not to reach the floor.
The scoop should be kept on a
clean hard surface or dedicated
receptacle and not in the storage
bin.
12MAdded
10. System check Check temperature of inlet water
temperature.
Ensure that the warm exhaust is
not impinging directly on taps, pipes
or hoses supplying the cold water.
Record temperature in logbook.
Ice should not be allowed to
stagnate in an ice-making machine’s
storage bin, but should be changed
frequently.
12MAdded
Page 112 of 222
INSULATION
Page 113 of 222
Previous
Version
Updated
Version
Reason For
Change
INSULATION35-01 35-01 THERMAL INSULATION
Title NotesActionFQTitle FQ Action Notes
4. Insulation
Jackets
Re-install any valve, flange or
similar fittings boxes / insulation
jackets that have been removed
and left off. Report any of these
missing.
12MAdded
5. Cladding Check all cladding to make sure it
has not been damaged / dented
[especially near step over points].
repair any damage or report if
unable to repair
12MAdded
Page 114 of 222
LIGHTING
Page 115 of 222
Previous
Version
Updated
Version
Reason For
Change
LIGHTING FITTINGS including LUMINAIRES general36-03 36-03 LIGHTING FITTINGS including LUMINAIRES general
Please see Lighting SFG 36-01 introductory procedures before commencing.
Wear cotton gloves on highly reflective luminaire diffusers and when changing tungsten capsule
lamps.
See Hazardous area (electrics) SFG 27 for any lighting works in explosive areas or where intrinsically
safe fittings are installed.
Added
Title NotesActionFQTitle FQ Action Notes
Page 116 of 222
Previous
Version
Updated
Version
Reason For
Change
EXTERNAL LIGHTING including ILLUMINATED SIGNS36-04 36-04 EXTERNAL LIGHTING including ILLUMINATED SIGNS
WARNING : Equipment may operate at voltages above 415 and extra precautions should be
taken.
Please see Lighting SFG 36-01 introductory procedures before commencing.
Wear cotton gloves on highly reflective luminaire diffusers and when changing tungsten capsule
lamps.
See Hazardous area (electrics) SFG 27 for any lighting works in explosive areas or where intrinsically
safe fittings are installed.
<B>WARNING</B> : Equipment may operate at voltages above 415v.
Added
Title NotesActionFQTitle FQ Action Notes
External FittingsAdded
1. General Clean and check: For physical
damage. Signs of water ingress or
condensation, if present check
seals and report toclient.
Check mounting
brackets/supports/columns etc., for
corrosion, damage and security,
report all findings
Frequency of cleaning will depend
on environment, in dirty areas more
frequent cleaning may be
necessary.
6MAdded
2. Lamps Check for failed or flickering lamps
or signs of deterioration. Replace
as required
Care should be taken in handling as
broken glass from broken
tubes/lamps can be dangerous.
Disposal of tubes/lamps should be
in accordance with H&S and
Environmental regulations.
12MAdded
3. Cable
connections
Check externally for security and
signs of arcing or overheating.
Renew or re-fix as necessary.12MAdded
4. Lamp control
gear.
Check operation and compatibility
with lamp.
12MAdded
5. Switches and
control contactors
Check operation of all switches.
Check function and operation of
any lighting control contactors;
ensure that lamp circuits operate at
correct times, both for normal
operation and for extended on/off
periods
Replace if faulty.12MAdded
6. Electrical wiring. Check integrity and report to client if
renewal necessary
12MAdded
7. Earth continuity Check and remedy if necessary.6MAdded
SignageAdded
Page 117 of 222
LIGHTNING PROTECTION
Page 118 of 222
Previous
Version
Updated
Version
Reason For
Change
LIGHTNING CONDUCTOR AND EARTH38-01 38-01 LIGHTNING CONDUCTOR AND EARTH
Title NotesActionFQTitle FQ Action Notes
2. Electrical
continuity tests
For those parts of an earthing
system and bonding network which
are not visible for inspection,
measurements of electrical
continuity should be performed
13MAdded
Page 119 of 222
PIPEWORK SYSTEMS
Page 120 of 222
Previous
Version
Updated
Version
Reason For
Change
PIPEWORK SYSTEMS - General40-01 40-01 PIPEWORK SYSTEMS - General
Title NotesActionFQTitle FQ Action Notes
1. General Check all pipework for signs of
leaks, if possible repair and stem
leak
12MAdded
7. Expansion
bellows
Check condition and alignment of
expansion bellows /compensators.
Report any defects.12MAdded
8. Sensors,
gauges, detectors
Ensure all pipeline mounted
detectors/sensors and gauges are
in good repair
12MAdded
9. Hit Hazards Inspect pipework run and where it
runs across or parallel to a
personnel access route. Highlight
any low points where heads could
be hit with the appropriate hazard
tape or paint
12MAdded
10. ID tags Check identification tags are
provided for all pipeline mounted
equipment, valves etc.
12MAdded
11. Insulation Report on condition of all insulation
and coverings, paying particular
attention to integrity of any vapour
seals
See Insulation SFG35-01.12MAdded
Page 121 of 222
Previous
Version
Updated
Version
Reason For
Change
AIR COMPRESSORS40-08 40-08 AIR COMPRESSORS AND RECEIVERS
Title NotesActionFQTitle FQ Action Notes
1. Cooling Water. The cooling water should be
visually checked to make sure that
it is circulating properly by
observing the flow outlet or flow
indicator
1DAdded
2. Oil level. The level of the oil in the crank
chamber should be checked using
a dipstick, level gauge or other
device. Any excessive usage of
lubricating oil should be
investigated
1DAdded
3. Oil pressure Oil pressure should be checked1DAdded
4. Oil feed Check oil feed to the cylinders to
make sure that it is adequate but
not excessive. Oil consumption
should be recorded, as excessive
consumption can often lead to
explosions downstream of the
compressor
1DAdded
5. Air pressure &
temperature
Check and record the outlet air
pressure and temperature.
1DAdded
6. General Check the compressor performance
by listening for any unusual noises
during running.
1DAdded
7. Defects Defects found should be rectified
and a record kept
1DAdded
8. Air receiver Any accumulation of oil and water
should be drained from the air
receiver, the intercooler, the
aftercooler and main supply pipes.
1DAdded
9. Safety valves Safety valves (where design allows)
should be checked by easing them
by hand.
1WAdded
Page 122 of 222
Previous
Version
Updated
Version
Reason For
Change
10. Air filter. Inspect air filter, clean/replace as
found necessary.
The condition of the inlet air filters
should be checked and thoroughly
cleaned or replaced. The interval
between successive replacements
will be determined by local
circumstances but is, to a certain
extent, controlled by the capacity of
the filter and the cleanliness of the
atmosphere in the vicinity.
Where oil wetted viscous filters are
used, spare units should be
provided and excess oil should be
drained from the filter units for at
least four to eight hours before the
units are replaced, except where the
manufacturer advises otherwise
1MAdded
14b Oil Drain and change the lubricating oil
using recommended lubricating oil
12MAdded
20a
Delivery Ports and
pipework
Where oil coke deposits are liable
to occur, check the delivery ports
and pipework. Clean as required
The period between inspections can
be modified in the light of
experience gained from operating a
particular installation
6MAdded
24. VALVES
[various]
Check condition of the valves.
Inspect and clean the
non-return/unloader valve
assembly.
Remove and inspect the crankcase
breather valve
After each 2000 hours of running or
annually (whichever is the sooner)
12MAdded
25. cooler section Clean the intercooler and
aftercooler sections.
After each 2000 hours of running or
annually (whichever is the sooner)
12MAdded
26. Radiator the radiator should be drained and
washed out
After each 2000 hours of running or
annually (whichever is the sooner)
12MAdded
27. Air Receiver Prepare for and assist with
insurance inspection.
The air receiver should be
thoroughly cleaned and examined
internally.
Frequency will be set by Insurance
inspector
24MAdded
Page 123 of 222
Previous
Version
Updated
Version
Reason For
Change
AIR COMPRESSORS Compressed air dryers40-09 40-09 AIR COMPRESSORS Compressed air dryers
The chambers of air dryers are pressure vessels and should conform with PD 5500:2009
“Specifications for unfired fusion- welded pressure vessels” or to a standard providing equal integrity.
If means are provided for isolating the dryer (and it is good practice to provide means of isolation for
all equipment), either the chambers should be constructed to withstand the maximum pressure that
can be generated by the compressor or a suitable pressure reducing valve and a safety valve should
be fitted to prevent the safe working pressure of the chambers from being exceeded.
Where there is no means of isolating the dryer from a suitable safety valve, e.g. on the receiver, and
where non-return valves are fitted to the dryer outlet (to protect it from stored energy in the system),
no safety valves are needed.
Maintenance operations should only be conducted when the system has been shut down, isolated
and fully depressurised. All connections must be undone with care, paying particular attention to the
areas that become pressurised. Do not modify or adjust control settings. Check all connections for
leakage and secure seating. Ensure all loose parts are removed or secured to the dryer before
operation.
Added
Title NotesActionFQTitle FQ Action Notes
Page 124 of 222
Previous
Version
Updated
Version
Reason For
Change
FUEL SUPPLY FOR LOW PRESSURE GAS (LPG) OR OIL40-10 40-10 PIPEWORK FOR LOW PRESSURE NATURAL GAS, LIQUEFIED
PETROLEUM GAS (LPG) OR OIL
The following tasks are to be carried out to all pipework within the designated areaAdded
Title NotesActionFQTitle FQ Action Notes
1b) Pipework
Oil
Visible oil feed pipes should be
inspected annually. Check for
leaks. Check sleeves and physical
soundness. Check all ends are
suitably plugged/capped.
Ensure the fill point drip-tray is
clean, free of water, debris and oil
before and after any oil delivery.
Some Regional requirements mean
some systems should be pressure
tested every 5 years where there
are joints in the system or every 10
years where there are no joints. In
environmentally sensitive areas an
alternative is to have a ‘pipe within a
pipe’ system incorporating a leak
detection and alarm system
12MAdded
2 b) Valves
Oil
Check for soundness and leakage.
Check all fire valves for cut off in
the event of a fire alarm, fire or
overheating
12MAdded
Page 125 of 222
Previous
Version
Updated
Version
Reason For
Change
STEAM SERVICES40-11 40-11 STEAM SERVICES
Title NotesActionFQTitle FQ Action Notes
1 General Check all pipework for signs of
leaks, if possible repair and stem
leak
Do not forget hidden pipework
where access is provided.
3MAdded
10. Pressure
reducing devices
Check PRD valve(s) for correct
function and operation, log
upstream and downstream
pressures.
12MAdded
11. Expansion
bellows
Check condition and alignment of
expansion bellows /compensators.
Report any defects.12MAdded
12. Sensors,
gauges, detectors
Ensure all pipeline mounted
detectors/sensors and gauges are
in good repair
12MAdded
13. Hit Hazards Inspect pipework run and where it
runs across or parallel to a
personnel access route. Highlight
any low points where heads could
be hit with the appropriate hazard
tape or paint
12MAdded
14. ID tags Check identification tags are
provided for all pipeline mounted
equipment, valves etc.
12MAdded
Page 126 of 222
PORTABLE EQUIPMENT
Page 127 of 222
Previous
Version
Updated
Version
Reason For
Change
PORTABLE EQUIPMENT PAT TESTING42-01 42-01 PORTABLE APPLIANCE TESTING (PAT)
Title NotesActionFQTitle FQ Action Notes
Equipment HireAdded
a). external visual
inspection
Frequency: before and after return0MAdded
b). full inspection
& electrical testing
Unless earlier inspection indicates
immediate testing is necessary.
Frequency: before issue0MAdded
ConstructionAdded
a). external visual
inspection
Frequency: before initial use and
then 1 month
0MAdded
b). full inspection
& electrical testing
Unless earlier inspection indicates
immediate testing is necessary.
3MAdded
IndustrialAdded
a). external visual
inspection
Frequency: before initial use and
then 1 to 3 months
0MAdded
b). full inspection
& electrical testing
Unless earlier inspection indicates
immediate testing is necessary.
Frequency: 6M-12M0MAdded
CommercialAdded
a). external visual
inspection
Frequency: 6 months - 2 years0MAdded
b). full inspection
& electrical testing
Unless earlier inspection indicates
immediate testing is necessary.
Frequency: 6 months – 4 years0MAdded
Premises used by
public e.g. hotels
Added
a). external visual
inspection
Frequency: 6 months - 2 years0MAdded
b). full inspection
& electrical testing
Unless earlier inspection indicates
immediate testing is necessary.
Frequency: 12 months – 4 years0MAdded
SchoolsAdded
Page 128 of 222
Previous
Version
Updated
Version
Reason For
Change
a). external visual
inspection
Frequency: 4 months – 1 year0MAdded
b). full inspection
& electrical testing
Unless earlier inspection indicates
immediate testing is necessary.
Frequency: before issue 12 months
– 4 years
0MAdded
Testing For full details of tests to be carried
out reference should be made to
the IEE`S Code of Practice
For frequencies see examples
above
Added
3) Mains on/off
switch either 4 or
5, and 6
(a) visual inspection Pass condition
correct operation; no damage
0MAdded
8) Labels After each item of equipment is
tested mark it individually indicating
if it has passed or failed, the date of
the test and the date of the next
re-test
0MAdded
9) Log sheet The details of the tests and results
shall be recorded onto a log sheet,
suitable for recording the
information obtained from the test
and inspection carried out on that
item of equipment.
Check to ensure that the details
entered on the test label, fixed to
the equipment, tally with those
entered on the log sheet.
It is of paramount importance that a
record of maintenance, including
test results, is maintained
throughout the life of each item of
equipment. The provision of these
records will demonstrate that testing
has been carried out to an adequate
standard, and any difference
between subsequent tests can be
noted. Should these tests show a
deterioration in any part of the
equipment, remedial action is
necessary to ensure that danger
does not arise.
0MAdded
Page 129 of 222
POWER GENERATORS
Page 130 of 222
Previous
Version
Updated
Version
Reason For
Change
POWER GENERATION--STAND-BY GENERATOR43-02 43-02 POWER GENERATION--STAND-BY GENERATOR
Title NotesActionFQTitle FQ Action Notes
10. Drive Belts Check belts for slackness,
alignment or wear, adjust as
necessary.
6MAdded
11. Battery
Charger
Check condition of battery charger,
inspect for damage. Open and
check on condition of wiring and
transformer insulation. Check on all
electrical connections, clean or
blow out. Test operation of any
ON/OFF or selector switches, test
accuracy of meters. Inspect or
renew if damaged any flying leads,
terminals or clips. Take insulation
and earth impedance test.
6MAdded
12. Anti freeze Add anti-freeze to cooling system or
check specific gravity as applicable
6MAdded
13. Fuel Filter Change the fuel filter element and
clean the filter bowl.
6MAdded
14. Air intake
grilles - alternator
Check that air intake grilles on
alternator are clean and
unobstructed. Remove cover from
non-drive and remove any fluff or
dirt that may have accumulated
around diode plates and exciter
assembly.
6MAdded
15 a) Electrical Check all electrical connections for
security. Examine brush gear in the
dynamo and starter and clean
commutator, renew brushes as
necessary.
Check operation of low oil and high
coolant shutdown switches
6MAdded
Page 131 of 222
Previous
Version
Updated
Version
Reason For
Change
15 b) Electrical Open all composite control panels
and associated switchgear. Clean
out interior of all panels. Inspect all
wiring for condition. Inspect all
terminations for security and
overheating. Visually check that an
efficient earth is being maintained.
Open, inspect and clean any
changeover switches on emergency
supply system. Check overloads
are functional and are set to correct
value. Ensure fuses of correct size
and type are fitted. Examine all
contacts for arcing and pitting,
dress or replace contacts as
applicable. Lightly lubricate all
contact faces with pure petroleum
jelly. Check relays for correct
function, replace any defective
components. Examine
switch-blades in isolators, ensure
they are free to move. Lubricate
pivots lightly with grease, ensuring
no grease comes into contact with
a conducting surface. Check for
smooth operation and that switches
are clearly marked. Before carrying
out the following test disconnect L.
V. circuits, i. e. rotating rectifier
diodes and A. V. R. circuits etc.
Carry out the following test:- a.
Insulation Resistance Test on
alternator and wiring. A figure of 1
megohm or above is acceptable. b.
Earth Loop Impedance Test on
alternator frame. Supply voltage =
Maximum allowed 3 X rating of
Fuse in amps, impedance in ohms
12MAdded
16. Operation and
auto-change
facility (where
applicable).
Check engine starter and solenoid
for good strong operation.
Check operation and starting
sequence.
6MAdded
17. Instruments Check that instruments are
functioning correctly and that glass
is clean.
6MAdded
18. Fuel transfer
pump
Check operation12MAdded
Page 132 of 222
Previous
Version
Updated
Version
Reason For
Change
19 Load Bank
Testing
Carry out a load test of the
generator including a 110%
overload and 50% drop test
Load Bank Testing – It should be
reviewed and decided why do this
type of testing and what are its
benefits, versus the risks of not
doing this type of testing.
1) Can the facility`s critical load be
taken off line or placed onto a
generator backup in order to have
this type of testing performed?
2) Where will the load banks be
staged? What type of heat will be
generated and how will the added
heat affect the building? When
doing large system tests there will
be a large amount of heat
generated and that can affect
sprinkler systems if the load banks
are staged inside of the building.
3) Are doors going to have load
bank cables ran through them so
that the doors can not be locked or
used for normal use, this may
require extra security personnel
during testing?
In addition, on some older systems
it can make perfect sense to do a
system test with load banks in order
to re-calibrate the system and the
modules. On some of these older
systems that use calibration
potentiometers, these
potentiometers can drift out of
calibration over the years and by
performing a recalibration it will
insure that the system is operating
at peak performance
24MAdded
Page 133 of 222
Previous
Version
Updated
Version
Reason For
Change
BATTERIES - LEAD ACID - unsealed43-03 43-03 BATTERIES - LEAD ACID - unsealed
Title NotesActionFQTitle FQ Action Notes
7. Battery charger Check voltage setting on the
charger
1MAdded
8. Vent plugs or
valves
Check6MAdded
9. Battery Check temperature of battery6MAdded
10. General Check for cleanliness and leakage1MAdded
Page 134 of 222
POWER SUPPLIES
Page 135 of 222
Previous
Version
Updated
Version
Reason For
Change
MAIN SWITCH PANEL AT SUPPLY INTAKE44-02 44-02 MAIN SWITCH PANEL AT SUPPLY INTAKE
The frequencies for the tasks given below are guideline only and shall be individually assessed per
site. Suitable isolation to be undertaken prior to commencement of work.
Added
Title NotesActionFQTitle FQ Action Notes
1. General Carry out a visual inspection and
operational check. check for;
a) All contacts, fuse bridges, phase
barriers etc. for signs of
arcing/burning where accessible
without interrupting the supply.
b) Time clocks, timing relays etc.,
are at correct time/setting.
c) Where provided, all indicator
lamps are working, replace lamps
as required.
d) Check that all trunking, conduit
cable gland terminations are
secure, adjust accordingly.
e) Check all indicator gauges and
meters, check for cracked
glass/covers, replace as found.
f) Check correctness of labelling.
g) Check enclosures for holes and
damage.
Check arc shields for the presence
of asbestos containing material
prior to dismantling any equipment,
if suspected STOP WORK. Take
actions in accordance with the
Asbestos Regulations.
Refer to www.hse.gov.uk.
3MAdded
4. Panel Doors Check all door and cover gaskets.
Inspect door hinges and locks.
Lightly lubricate as found
necessary. Ensure all doors and
access panels can be securely
closed and locked.
12MAdded
11. Earth Bars Check all connections and bonding
to earth bars. Check earth bars and
insulators for security
12MAdded
13. Main
Connections
Check all connections using
infra-red equipment [thermal
imaging].
Must be on normal load24MAdded
2. General -
Thermal imaging
Check using thermal imaging and
inspect for signs of hot spots and
overheating.
12MAdded
Page 136 of 222
Previous
Version
Updated
Version
Reason For
Change
POWER DISTRIBUTION UNIT (PDU)44-05 44-05 POWER DISTRIBUTION UNIT (PDU)
Title NotesActionFQTitle FQ Action Notes
2. General -
Thermal imaging
Check using thermal imaging and
inspect for signs of hot spots and
overheating.
12MAdded
Page 137 of 222
Previous
Version
Updated
Version
Reason For
Change
EARTHING44-06 44-06 EARTHING
Danger can arise when removing a conductor connected to earth unless suitable precautions are
taken
Added
Title NotesActionFQTitle FQ Action Notes
Page 138 of 222
Previous
Version
Updated
Version
Reason For
Change
DISTRIBUTION BOARDS44-07 44-07 DISTRIBUTION BOARDS
Title NotesActionFQTitle FQ Action Notes
2. General Locally isolate incoming electrical
supply. Open cover panels / access
doors. Check for signs of
overheating, unusual odours and
noises during operation. Remove
any build up of dirt and dust on
insulating components. Clean
equipment generally.
After all works [listed below]
completed securely refix cover
panels / access doors
12MAdded
Page 139 of 222
Previous
Version
Updated
Version
Reason For
Change
RING MAIN and SUB CIRCUITS44-08 44-08 ELECTRICAL INSTALLATION - GENERALLY
Carry out all work and provide all services required to all areas specified. Routine inspection work
includes inspection of installations generally in accordance with 17th Edition of IEE Regulations. Refer
to requirements of BS7671:2008. Testing should be carried out in the following sequence to the
relevant items: Continuity of protective conductors, main and supplementary bonding. Continuity of
ring final circuits. Insulation resistance. Site applied insulation. Protection by separation of circuit.
Protection by barriers or enclosures provided during erection. Insulation of non conducting floor and
walls. Polarity. Earth electrode resistance. Earth fault loop impedance. Operation or residual current
devices (RCD). Electrical testing should be carried out by a competent qualified electrician fully versed
in the system installed. The incoming supply to distribution switch boards must be isolated by locking
off LV circuit breakers, fuse switches and supplies from other distribution switchboards as detailed on
record drawings, as determined on site by the provider and as instructed by the client before any work
commences.
Installation should be checked with suitable, reliable test equipment. Precautions must be taken to
ensure tripped circuit devices cannot be accidentally closed, by either padlocking in the `OFF` position
or withdrawing the device as applicable. Where incoming supplies have been isolated, certain
auxiliary / control supplies may be `LIVE` due to external sources, e. g. Battery units.
It is essential that results from installation testing are recorded and the records are maintained and
updated annually.
Any electrical systems found to deviate from regulatory recommendation should be identified and
appropriate repair action taken.
Frequency shown is a guideline, actual frequencies will vary according to the type of installation, type
and use of building and the findings of any previous inspection.
Added
Title NotesActionFQTitle FQ Action Notes
1.Polarity and
continuity.
Check. Carry out checks in accordance with
IEE regulations.
12M 1. Small Power
Circuits/Outlets
Small Power Circuits/Outlets
Examine all small power outlets
within designated are, check for
damage and ensure any
disconnection switches operate
correctly, isolating electrical supply.
Check operation of RCD-protected
socket outlets by utilising Test
Button, reset RCD following Test.
12MAdded
Page 140 of 222
PUMPS
Page 141 of 222
Previous
Version
Updated
Version
Reason For
Change
PUMPS - General45-01 45-01 PUMPS - General
Title NotesActionFQTitle FQ Action Notes
10. Valves
Isolation,
regulation and
non-return valves
Check operation. Tighten glands or
repack if necessary
See Valves SFG61.12MAdded
11. Drain and
tundish (where
fitted)
Check for blockage, clean12MAdded
12. Pump
Pressures
Check and Record12MAdded
Page 142 of 222
Previous
Version
Updated
Version
Reason For
Change
CIRCULATING PUMPS-general45-02 45-02 CIRCULATING PUMPS-general
Title NotesActionFQTitle FQ Action Notes
13. Drive guards.
(where fitted
Check they are in place and secure3MAdded
Page 143 of 222
Previous
Version
Updated
Version
Reason For
Change
CENTRIFUGAL PUMPS45-03 45-03 CENTRIFUGAL PUMPS
Title NotesActionFQTitle FQ Action Notes
3. Electrical Examine and report condition of all
associated wiring, ensure security
of all terminal connections and
check for
satisfactory condition of any flexible
cables/conduits.
Ensure plant has adequate earth
conductor and bonding is secure.
Take and log motor current and
compare with nameplate details
3MAdded
11. Drain and
tundish (where
fitted)
Check for blockage, clean3MAdded
12. Pump
Pressures
Check and Record3MAdded
Page 144 of 222
Previous
Version
Updated
Version
Reason For
Change
PRESSURISATION PUMPS45-04 45-04 PRESSURISATION PUMPS
Title NotesActionFQTitle FQ Action Notes
7. Valves
Isolation,
regulation and
non-return valves
Check externally for leaks Rotate spindles and handwheels to
check freedom of operation,
examine drains for signs of gland
leakage.
See Valves SFG61.
3MAdded
8. Electrical Examine and report condition of all
associated wiring, ensure security
of all terminal connections and
check for
satisfactory condition of any flexible
cables/conduits.
Ensure plant has adequate earth
conductor and bonding is secure.
Take and log motor current and
compare with nameplate details
3MAdded
13. Pump
Pressures
Check and record3MAdded
Page 145 of 222
Previous
Version
Updated
Version
Reason For
Change
SEWAGE OR DRAINAGE PUMPS SUBMERSIBLE45-07 45-07 SEWAGE OR DRAINAGE PUMPS SUBMERSIBLE
Title NotesActionFQTitle FQ Action Notes
1. Casing general
- Noise, vibration
and overheating
Isolate pump(s) and withdraw form
sump. Visually inspect pump for
physical or mechanical damage.
Check pump intake is clear and
unobstructed. Clean pump casing
as required. Touch up paintwork
after removing signs of corrosion.
Check, rectify if possible and report
6MAdded
4. Electrical Remove motor terminal covers,
check connections for tightness and
terminal block for damage or
dampness. Open starter and check
condition of wiring and contacts,
clean and blow out. Ensure that
overload devices are operational
and set for correct loading. Carry
out the following tests to all pumps
and record results:-a. Insulation
resistance test on wiring and
motors. b. Earth loop impedance
test on case or frame of units. c.
Load test on motors (start and run
current). Compare results with
manufacturers specification.
Check that power leads at motors
are undamaged and are securely
held.
6MAdded
8. Return pump to
service
Check sump is free of debris, clean
as required.
Replace pump(s) and check
operation before closing sump
6MAdded
Page 146 of 222
Previous
Version
Updated
Version
Reason For
Change
SEWAGE and DRAINAGE PUMPS: DRYWELL45-08 45-08 SEWAGE and DRAINAGE PUMPS: DRYWELL
Title NotesActionFQTitle FQ Action Notes
3. Casing general
- Noise, vibration
and overheating
Isolate pump(s) and withdraw form
sump. Visually inspect pump for
physical or mechanical damage.
Check pump intake is clear and
unobstructed. Clean pump casing
as required. Touch up paintwork
after removing signs of corrosion.
Check, rectify if possible and report
6MAdded
Page 147 of 222
Previous
Version
Updated
Version
Reason For
Change
SUMP PUMPS: EXTENDED SHAFT45-10 45-10 SUMP PUMPS: EXTENDED SHAFT
Title NotesActionFQTitle FQ Action Notes
1. Casing general
- Noise, vibration
and overheating
Isolate pump(s) and withdraw form
sump. Visually inspect pump for
physical or mechanical damage.
Check pump intake is clear and
unobstructed. Clean pump casing
as required. Touch up paintwork
after removing signs of corrosion.
Check, rectify if possible and report.
12MAdded
7. Return pump to
service
Check sump is free of debris, clean
as required.
Replace pump(s) and check
operation before closing sump
6MAdded
Page 148 of 222
Previous
Version
Updated
Version
Reason For
Change
WATER PUMPING PRESSURE BOOSTING SETS45-12 45-12 WATER PUMPING PRESSURE BOOSTING SETS
Title NotesActionFQTitle FQ Action Notes
5. Electrical Check condition of local isolator,
open and clean if required. Remove
motor terminal covers, check
connections for tightness and
terminal block for damage or
dampness. Open starter and check
condition of wiring and contacts,
clean and blow out. Ensure that
overload devices are operational
and set for correct loading. Carry
out the following tests to all pumps
and record results:-a. Insulation
resistance test on wiring and
motors. b. Earth loop impedance
test on case or frame of units. c.
Load test on motors (start and run
current). Compare results with
manufacturers specification.
Check that power leads at motors
are undamaged and are securely
held
12MAdded
12. Valves Check operation. Tighten glands or
repack if necessary.
See relevant section for more
detailed information on Valves
SFG61.
3MAdded
Page 149 of 222
REFRIGERANT DISTRIBUTION SYSTEM
Page 150 of 222
Previous
Version
Updated
Version
Reason For
Change
REFRIGERANT DISTRIBUTION SYSTEM46-01 46-01 REFRIGERANT DISTRIBUTION SYSTEM
Personnel carrying out leak checking, gas recovery or other refrigerant handling activities such as
plant installation and maintenance must have a suitable refrigerant handling qualification. These
works are covered under EC Regulation 842/2006, Fluorinated Greenhouse Gases Regulations 2009
(FGG Regulations 2009)
Check for leaks should be part of the routine servicing. “Checked for leakage” means that the Joints,
valves including stems, seals, including seals on replaceable driers and filters, parts of the system
subject to vibration, connections to safety or operational devices of the equipment or system is
examined for leakage using direct or indirect measuring methods, focusing on those parts of the
equipment or system most likely to leak. The frequency of testing depends on refrigerant charge and
system type.
Systems containing: <3 kg no leak test required, 3 kg to 30 kg annual leak test required, 30 kg to 300
kg half yearly leak test required and >300 kg quarterly leak test required.
Hermetically sealed systems: <6 kg no leak test required, 6 kg to 30 kg annual leak test required, 30
kg to 300 kg half yearly leak test required and >300 kg quarterly leak test required.
These applications must also be checked for leakage within one month after a leak has been repaired
to ensure that the repair has been effective.
Plants with more than 300 kg must be fitted with a leakage detection system, which is defined as: “a
calibrated mechanical, electrical or electronic device for detecting leakage of refrigerants which, on
detection, alerts the operator”. The detection system must be checked at least once a year to ensure
proper functioning in line with manufacturers’ recommendations.
For any plant fitted with a leakage detection system (including those below the mandatory 300 kg
threshold), the frequency of leak checking can be halved, although an annual check remains the
minimum frequency.
ALWAYS UPDATE RECORDS
Added
Title NotesActionFQTitle FQ Action Notes
1. Leaks. Check for leaks should be part of
the routine servicing by plant
attendants.
Where a system has a refrigerant
charge greater than 300kg, an
automatic leak detection system
must be installed on the system to
comply with the F Gas Regulations
Added
A) Normal
systems:
<3 kg
Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
0MAdded
B) 3 kg to 30 kg Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
12MAdded
C) 30 kg to 300 kg Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
6MAdded
Page 151 of 222
Previous
Version
Updated
Version
Reason For
Change
D) >300 kg Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
3MAdded
E) Hermetically
sealed systems:
<6 kg
Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
0MAdded
F) 6 kg to 30 kg Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
12MAdded
G) 30 kg to 300 kg Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
6MAdded
H) >300 kg Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
3MAdded
Page 152 of 222
ROOM AIR CONDITIONERS
Page 153 of 222
Previous
Version
Updated
Version
Reason For
Change
ROOM AIR CONDITIONERS unitary rev. cycle heat pump terminal units with
elec. htg. and rev. valve
47-01 47-01 ROOM AIR CONDITIONERS
Title NotesActionFQTitle FQ Action Notes
12. Leaks. Check for leaks should be part of
the routine servicing.
Where a system has a refrigerant
charge greater than 300kg, an
automatic leak detection system
must be installed on the system to
comply with the F Gas Regulations
Added
A) Normal
systems:
<3 kg
Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
0MAdded
B) 3 kg to 30 kg Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
12MAdded
C) 30 kg to 300 kg Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
6MAdded
D) >300 kg Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
3MAdded
E) Hermetically
sealed systems:
<6 kg
Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
0MAdded
F) 6 kg to 30 kg Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
12MAdded
G) 30 kg to 300 kg Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
6MAdded
H) >300 kg Check for refrigerant leaks. Any
leak of refrigerant should be dealt
with immediately.
3MAdded
Page 154 of 222
SANITARY AND WASTE WATER PLUMBING
Page 155 of 222
Previous
Version
Updated
Version
Reason For
Change
INTERCEPTORS - Petrol and Oil48-03 48-03 INTERCEPTORS - Petrol and Oil
Title NotesActionFQTitle FQ Action Notes
Petrol interceptors.Added
Page 156 of 222
Previous
Version
Updated
Version
Reason For
Change
SANITARY, WASTE WATER PLUMBING and DRAINS48-05 48-05 SANITARY, WASTE WATER PLUMBING and DRAINS
Title NotesActionFQTitle FQ Action Notes
3. Sinks / Basins Check basins/sinks for leaks and
damage. 2. Check traps and
overflows are free from
obstructions/soap build up etc. 3.
Check operation of taps, ensure
plug and chain are secure
6MAdded
Page 157 of 222
Previous
Version
Updated
Version
Reason For
Change
SANITARY AND WASTE WATER PLUMBING - WATER SAVING DEVICES
and METERS
48-08 48-08 SANITARY AND WASTE WATER PLUMBING - WATER SAVING DEVICES
and METERSTitle NotesActionFQTitle FQ Action Notes
7. Dosing system
(where fitted)
Where dosing system provided,
check solenoid, battery unit and
operation of dosing system
generally.
6MAdded
Page 158 of 222
SECURITY SYSTEMS
Page 159 of 222
Previous
Version
Updated
Version
Reason For
Change
SECURITY SYSTEMS-INTRUDER ALARMS49-01 49-01 SECURITY SYSTEMS-INTRUDER ALARMS
Title NotesActionFQTitle FQ Action Notes
8. Control Panel Check control panel internally,
check all control devices, fuse
bridges, phase barriers etc. for
signs of arcing/burning. Check all
indication lamps are working,
replace any defective lamps. Check
panel door(s) can be securely
locked and that door isolation
device is operative.
Added
Page 160 of 222
SENSORS AND SWITCHING DEVICES
Page 161 of 222
Previous
Version
Updated
Version
Reason For
Change
GAS DETECTOR SENSORS50-11 50-11 GAS DETECTOR SENSORS
Title NotesActionFQTitle FQ Action Notes
Carbon Monoxide
Sensors
Added
Flammable Gases
and Oxygen
Sensors
It is assumed that the operational
staff will undertaken the routine
visual inspections of the installation.
Before proceeding with any
maintenance task, the operative is
to check the faults log for any
outstanding faults conditions.
Fixed gas detectors should be
included in the plant maintenance
schedule. The performance of most
detectors deteriorates with time, the
rate depending on the type of
sensor and the operating
conditions, for example a dusty,
corrosive or damp environment.
These factors will affect the
frequency of inspection,
maintenance and calibration
Repair or maintenance of fixed
apparatus (whether incorporating
single-point sensors, open path
sensors, a combination of these,
or sampling systems) should be
carried out under a control led
procedure. Defective apparatus
should be removed for repair in
a workshop outside the area being
protected. If a replacement
apparatus cannot be provided
immediately, then transport table
apparatus should be used as a
temporary substitute
Before any work is undertaken on
and sensor in a hazardous area,
ensure the notes in Hazardous
areas (electrics) SFG 27 are read
and fully understood. Ensure all
necessary local Permit to Work
procedures are fully complied with.
Added
Page 162 of 222
SHOWERS
Page 163 of 222
Previous
Version
Updated
Version
Reason For
Change
SHOWERS51-01 51-01 SHOWERS
Title NotesActionFQTitle FQ Action Notes
3. Internal
Surfaces; tiles and
silicone joints
Check internal surfaces for cracks
in the tiles or grouting. Check all
silicone joints and seals. Rake out
damaged grout or silicone and
repair as necessary.
Generally, the day to day cleaning
of the internal surfaces should be
undertaken by the clients staff.
Cracks or chips in the surfaces can
be a breeding ground for bacteria.
3MAdded
Page 164 of 222
SMOKE EXTRACT
Page 165 of 222
Previous
Version
Updated
Version
Reason For
Change
SMOKE RELIEF - Powered fire ventilators52-03 52-03 SMOKE RELIEF - Powered smoke and heat exhaust ventilators
Frequency of maintenance and testing for smoke relief ventilators should conform to BS EN
12101-3:2002 Smoke and heat control systems and should be in accordance with local authority
requirements.
Added
Title NotesActionFQTitle FQ Action Notes
10. Operating
mechanism.
Check action for smooth operation
and to ensure they open and close
correctly. Lubricate all linkages in
accordance with manufacturers
recommendations
Only use lubricant as recommended
by manufacturer. Report to client if
repairs or replacement required.
12MAdded
11. Louvers/flaps
or dampers.
Clean bearings and lubricate as
necessary.
Only use lubricant as recommended
by manufacturer
12MAdded
12. Compressor
(where applicable)
Carry out tasks as directed in
relevant section.
Check rails are clear of any
obstruction so that the curtain will
drop into place when required.
The client should carry out this task
as part of their fire alarm testing
once every week to ensure that the
system integrity is maintained.
See Pipework systems SFG40-08
Added
Page 166 of 222
Previous
Version
Updated
Version
Reason For
Change
SMOKE CURTAINS52-04 52-04 SMOKE CURTAINS
Frequency of maintenance and testing for smoke relief ventilators should conform to BS EN
12101-1:2005 Smoke and heat control systems and should be in accordance with local authority
requirements.
Added
Title NotesActionFQTitle FQ Action Notes
Page 167 of 222
SOLAR PANELS
Page 168 of 222
Previous
Version
Updated
Version
Reason For
Change
SOLAR HOT WATER PANELS and similar COLLECTING DEVICES53-01 53-01 SOLAR HOT WATER PANELS and similar COLLECTING DEVICES
Working at heights should be in strict accordance with the Work at Height Regulations 2005Added
Title NotesActionFQTitle FQ Action Notes
6. Anti-freeze
solution.
Replace anti-freeze solution.36MAdded
6. Anti-freeze
solution.
Replace anti-freeze solution.36MAdded
Page 169 of 222
SPLIT SYSTEMS INCLUDING HEAT PUMPS
Page 170 of 222
Previous
Version
Updated
Version
Reason For
Change
SPLIT SYSTEMS – air-cooled with direct expansion evaporator (DX), with
gas, hot water or elec. htrs
54-02 54-02 DX SPLIT SYSTEMS - with gas, electric or hot water heaters
Title NotesActionFQTitle FQ Action Notes
5. Condenser –
general
Check all nuts, (including holding
down bolts) bolts, setscrews, etc.
for security. Check any drip tray for
blockage/leaks etc. Remove any
debris and clean.
6MAdded
b) leaks Check refrigerant Charge,
recharge/report as found
necessary. Check Joints, valves
including stems, seals, including
seals on replaceable driers and
filters, parts of the system subject
to vibration, connections to safety
or operational devices of the
equipment or system. Examine for
leakage using direct or indirect
measuring methods.
Check for leaks should be part of
the routine servicing by plant
attendants.
Any removed refrigerant (CFC) must
be recovered and not released to
atmosphere.
Where a system has a refrigerant
charge greater than 300kg, an
automatic leak detection system
must be installed on the system to
comply with the F Gas Regulations
6MAdded
A) Normal
systems:
<3 kg
Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
0MAdded
B) 3 kg to 30 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
12MAdded
C) 30 kg to 300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
6MAdded
D) >300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
3MAdded
E) Hermetically
sealed systems:
<6 kg
Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
0MAdded
F) 6 kg to 30 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
12MAdded
G) 30 kg to 300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
6MAdded
H) >300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
3MAdded
Page 171 of 222
Previous
Version
Updated
Version
Reason For
Change
SPLIT SYSTEMS/ HEATPUMPS – air-cooled with direct expansion
evaporator (DX)
54-03 54-03 SPLIT SYSTEMS/ HEATPUMPS – air-cooled with direct expansion
evaporator (DX)
Engineers working on these systems must belong to an approved Certified Scheme provider, in
accordance with the "F" Gas and Building Regulations
Check for leaks should be part of the routine servicing. “Checked for leakage” means that the Joints,
valves including stems, seals, including seals on replaceable driers and filters, parts of the system
subject to vibration, connections to safety or operational devices of the equipment or system is
examined for leakage using direct or indirect measuring methods, focusing on those parts of the
equipment or system most likely to leak. The frequency of testing depends on refrigerant charge and
system type.
Systems containing: <3 kg no leak test required, 3 kg to 30 kg annual leak test required, 30 kg to 300
kg half yearly leak test required and >300 kg quarterly leak test required.
Hermetically sealed systems: <6 kg no leak test required, 6 kg to 30 kg annual leak test required, 30
kg to 300 kg half yearly leak test required and >300 kg quarterly leak test required.
These applications must also be checked for leakage within one month after a leak has been repaired
to ensure that the repair has been effective.
Plants with more than 300 kg must be fitted with a leakage detection system, which is defined as: “a
calibrated mechanical, electrical or electronic device for detecting leakage of refrigerants which, on
detection, alerts the operator”. The detection system must be checked at least once a year to ensure
proper functioning in line with manufacturers’ recommendations.
For any plant fitted with a leakage detection system (including those below the mandatory 300 kg
threshold), the frequency of leak checking can be halved, although an annual check remains the
minimum frequency.
Added
Title NotesActionFQTitle FQ Action Notes
A) Normal
systems:
<3 kg
Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
0MAdded
B) 3 kg to 30 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
12MAdded
C) 30 kg to 300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
6MAdded
D) >300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
3MAdded
E) Hermetically
sealed systems:
<6 kg
Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
0MAdded
F) 6 kg to 30 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
12MAdded
G) 30 kg to 300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
6MAdded
Page 172 of 222
Previous
Version
Updated
Version
Reason For
Change
H) >300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
3MAdded
5. Condenser –
general
Check all nuts, (including holding
down bolts) bolts, setscrews, etc.
for security. Check any drip tray for
blockage/leaks etc. Remove any
debris and clean.
6MAdded
Page 173 of 222
STARTERS
Page 174 of 222
Previous
Version
Updated
Version
Reason For
Change
STARTERS - Star Delta55-02 55-02 STARTERS - Star Delta
Before carrying out any work on electrical equipment, check status and isolate in accordance with
HASAWA and the Electricity at Work Regulations 1989 requirements.
Added
Title NotesActionFQTitle FQ Action Notes
Page 175 of 222
Previous
Version
Updated
Version
Reason For
Change
STARTERS -Two speed - Dual wound55-03 55-03 STARTERS -Two speed - Dual wound
Before carrying out any work on electrical equipment, check status and isolate in accordance with
HASAWA and the Electricity at Work Regulations 1989
Added
Title NotesActionFQTitle FQ Action Notes
Page 176 of 222
Previous
Version
Updated
Version
Reason For
Change
STARTERS - Two speed - Pole change55-04 55-04 STARTERS - Two speed - Pole change
Before carrying out any work on electrical equipment, check status and isolate in accordance with
HASAWA and the Electricity at Work Regulations 1989 requirements.
Added
Title NotesActionFQTitle FQ Action Notes
Page 177 of 222
Previous
Version
Updated
Version
Reason For
Change
STARTERS - Reversing55-05 55-05 STARTERS - Reversing
Before carrying out any work on electrical equipment, check status and isolate in accordance with
HASAWA and the Electricity at Work Regulations 1989
Added
Title NotesActionFQTitle FQ Action Notes
Page 178 of 222
Previous
Version
Updated
Version
Reason For
Change
STARTERS - Auto-transformer55-06 55-06 STARTERS - Auto-transformer
Before carrying out any work on electrical equipment, check status and isolate in accordance with
HASAWA and the Electricity at Work Regulations 1989
Added
Title NotesActionFQTitle FQ Action Notes
Page 179 of 222
Previous
Version
Updated
Version
Reason For
Change
STARTERS - Quick transition, electric heater55-07 55-07 STARTERS - Quick transition, electric heater
Before carrying out any work on electrical equipment, check status and isolate in accordance with
HASAWA and the Electricity at Work Regulations 1989
Added
Title NotesActionFQTitle FQ Action Notes
Page 180 of 222
Previous
Version
Updated
Version
Reason For
Change
STARTERS electrolyte type55-08 55-08 STARTERS electrolyte type
Before carrying out any work on electrical equipment, check status and isolate in accordance with
HASAWA and the Electricity at Work Regulations 1989
Added
Page 181 of 222
STORAGE TANKS
Page 182 of 222
Previous
Version
Updated
Version
Reason For
Change
COLD WATER STORAGE TANKS and CISTERNS56-02 56-02 COLD WATER STORAGE TANKS and CISTERNS
Title NotesActionFQTitle FQ Action Notes
1. General Check for adequate water level and
where provided, check tank warning
pipe for signs of discharge. Inspect
tank for evidence of leaks and
corrosion.
3MAdded
14. Earthing and
bonding
Where pipework, fittings or
appliances are to be replaced,
continuity of earthing and
equipotential bonding shall be
maintained. Where pipework has
been used for earthing, alternative
earthing arrangements shall be
made in accordance with BS 7430
by a competent person. Where
there is no evidence of main
equipotential bonding, which may
be required, the installer should
inform the responsible person that
any bonding should be checked
and remedied where necessary by
a competent person.
12MAdded
Page 183 of 222
Previous
Version
Updated
Version
Reason For
Change
ICE STORAGE SYSTEMS56-03 56-03 ICE STORAGE SYSTEMS
Title NotesActionFQTitle FQ Action Notes
3. Coolant flow
rates
Check and log flow rates and
pressure drops at appropriate loads
and conditions and check against
commissioning data
6MAdded
4. Circulating
pumps
Check operation of pumps. Take account of density of the
secondary coolant.
See Pumps SFG 45
6MAdded
5. Flow and return
temperatures
Check that the flow and return
temperatures across the ice store
are being achieved in both ice
charge and discharge modes.
6MAdded
6. Set points Check control set points for correct
values and operation.
3MAdded
Ice StoreAdded
1. Water level Check correct level of water in
storage container
6MAdded
2. Inventory device Check ice inventory device is
correctly calibrated and operating to
ensure correct glycol concentration
levels.
6MAdded
1. BMS Check that all temperatures,
pressures, flow rates etc., are being
received.
Check sensors for any not working.6MAdded
2. Insulation and
vapour barrier
Check all insulation is in place. Check to ensure the full record of
operating conditions over a period of
time is being saved.
6MAdded
3. System
pressurisation unit
(if used).
Check operation. Should any pipework be removed
during and maintenance or repairs
ensure that it is reinstated paying
special attention to the quality of the
vapour sealing. The system will
need to be dried out prior to being
reinsulated to avoid sealing in
moisture which could corrode
pipework.
6MAdded
4. Tank shut off
unit (if fitted).
Check operation.6MAdded
Page 184 of 222
Previous
Version
Updated
Version
Reason For
Change
STORAGE TANKS - OIL56-05 56-05 STORAGE TANKS - OIL
The Control of Pollution (Oil Storage) (England) Regulations 2001 set minimum standards. They do
not change other legislation under which it is an offence to cause water pollution . Variations in local
conditions may mean more stringent standards are needed to prevent pollution.
If there is a spill, immediate action must be taken to stop the oil getting into any drains or
watercourses. Soak up the spilt oil with the contents of the spill kit in accordance with the risk
assessment. Don’t hose the spillage down or use any detergents to try to get rid of it. Notify the
Environment Agency by calling their Emergency Hotline on 0800 80 70 60.
If oil soaks into the ground, the soil soaked in oil should be removed, by a specialist company. Store
any materials that are soaked in oil in containers that won’t let the oil run away until it can be correctly
and legally disposed of.
In addition to the tasks there are daily and weekly operational tasks to be carried out including visual
checks of the oil tanks, pipework and bund. Please also see the section below [bund 3 monthly] which
refers to the removal of rain water. This must be done every time there has been heavy rainfall.
Refer to the Control of Substances Hazardous to Health (COSHH) Regulations. Staff to be Competent
and fully trained in COSHH. Risk Assessment / Method Statement requirements must be carried out
before the work starts and a method statement produced. Refer to www.hse.gov.uk for details.
Added
Title NotesActionFQTitle FQ Action Notes
Bulk Oil Storage
[Heavy and
Medium Oils]
If there is a spill, immediate action
must be taken to stop the oil getting
into any drains or watercourses.
Soak up the spilt oil with the
contents of the spill kit in
accordance with the risk
assessment. Don’t hose the
spillage down or use any
detergents to try to get rid of it.
Notify the Environment Agency by
calling their Emergency Hotline on
0800 80 70 60.
Added
Outflow heater(s) Refer to the Control of Substances
Hazardous to Health (COSHH)
Regulations. Staff to be Competent
and fully trained in COSHH. Risk
Assessment / Method Statement
requirements must be carried out
before the work starts and a
method statement produced. Refer
to www.hse.gov.uk for details.
3MAdded
Oil log Check and log oil level. Log also
any inspections, any repair work on
the tanks and who’s done the
works.
3MAdded
Contents Gauge Dip tank to ensure gauge is
working.
3MAdded
Page 185 of 222
Previous
Version
Updated
Version
Reason For
Change
Valves and
pipework
Check valves are locked or have
there hand wheels removed [
vandalism / theft]. Pipework should
be checked for leaks, corrosion,
missing brackets etc. Check any
trace heating and insulation is in
place and working where
appropriate.
3MAdded
Valves and
pipework
Note settings of valves and take
through total travel, returning to
correct settings. Lock or remove
hand wheel as appropriate.
Pipework should be checked for
leaks, corrosion, missing brackets
etc.
12MAdded
Notices Check that the notice showing the
product type, tank capacity and,
where appropriate, tank number is
clearly visible – clean or replace as
necessary. Check all notices are
clearly visible warning that all
valves must be locked when not in
use.
3MAdded
Bund Bunds should be inspected
regularly for signs of damage, e.g.
missing bricks in walls and water in
the bund. Inspect closely where any
draw off / feed lines pass through
the bund wall to ensure it remains
fully sealed to retain oil.
Check that any trigger guns and
hoses are being kept within the
bund or the secure cabinet, which
should be locked shut when not in
use
Checked visually by the operator at
least weekly or after any heavy
rainfall.
Open bund - check the bund after
heavy rainfall. If there’s no rainwater
in the bund, it might not be sealed
properly and you should have it
inspected and repaired. Where rain
water has collected in the bund, it
will reduce the amount of oil it can
contain. To remove accumulated
rainwater, use a manually operated
pump or by bailing from the sump.
Any accumulated water, oil or debris
should be removed
and disposed of in line with waste
management legislation. In all cases
where wastes are removed, as the
waste producer you are obliged
under Waste management, the Duty
of Care, a code of practice (revised
1996) to describe the waste
accurately and dispose of it
properly.
Guidance on the disposal of
condensate and bund water. Joint
OFTEC/WaterUK/Environment
Agency/ SEPA publication.
3MAdded
Page 186 of 222
Previous
Version
Updated
Version
Reason For
Change
Bund A more detailed annual check by a
trained operator, e.g. in the OFTEC
registered scheme.
12MAdded
Overfill prevention
devices
Check that the device sounds the
alarm / shows the visual warning or
automatically stops the delivery –
whatever applies.
3MAdded
Fill points Check that the lockable fill cap and
chain are in place and work. Clean
the fill point drip tray.
3MAdded
Tank 60M Bulk Oil Storage [Heavy Oil]
Clean tank externally, derust and
paint, as found necessary. Place
No Smoking Signs, drain tank,
open manholes and vent tank.
Refer to Permit to Work and safe
Systems of Work before entering
tank, internally inspect, clean and
repair as found necessary. Report
condition before placing tank back
on-line. After maintenance
inspection, close all manholes and
covers, recharged tank and check
for leaks. Clean down exterior of
outdoor tanks and repaint with
bituminous paint. Inspect condition
of any fixed ladders, handrails and
catwalks. Check all fixings for
security
60MAdded
Daily (small) oil
storage
All tasks and frequencies are the
same as for Bulk Oil Storage
[Heavy and Medium Oils] above
without the task for out flow
heaters.
Added
Page 187 of 222
SWIMMING POOLS
Page 188 of 222
Previous
Version
Updated
Version
Reason For
Change
SWIMMING POOLS57-02 57-02 SWIMMING POOLS
Title NotesActionFQTitle FQ Action Notes
Page 189 of 222
Previous
Version
Updated
Version
Reason For
Change
Water Quality
Testing
Carry out routine testing of the
water quality. Tests should include:
water clarity
disinfectant level
pH
water temperature
air temperature
The manual monitoring and
measurement of the chemical state
of the pool water should be
performed using colorimetric
comparison kits (comparator or
spectrophotometer) or commercially
available test kits using test tablets.
The accuracy of test kits should be
maintained by:
a) keeping them scrupulously clean
(including rinsing glassware
components with deionized water to
ensure that all traces of test
reagents from previous uses are
removed);
b) using separate cells for pH and
disinfectant testing;
c) not exceeding the shelf life of the
test reagents;
d) following storage instructions;
e) using only the test kit
manufacturer’s specified test
tablets;
f) diluting and testing a second
sample for disinfectant residuals if
the first gives a result at the top or
the bottom of the kit’s range;
g) using a test kit with the applicable
range for the water under test; and
h) being aware of the potential false
readings that can arise from things
like high calcium hardness and
contamination with pool cleaning
chemicals.
Where free chlorine levels are not
monitored and controlled
automatically by the water treatment
plant, manual testing should be
carried out, using commercially
available test kits and the
appropriate tablets.
These tests should be undertaken:
a) before the pool opens;
b) every 2 h during opening hours;
and
c) after it closes.
Even when free chlorine levels are
monitored and controlled by
automatic systems, chlorine levels
should be tested manually at least
three times daily at the start,
midway and at the end of each day.
The tests should monitor both free
1DAdded
Page 190 of 222
Previous
Version
Updated
Version
Reason For
Change
chlorine and combined chlorine
residuals.
Pool water samples for analysis
should be taken at a depth of 200
mm to 400 mm, from a part of the
pool that has been found to be
representative of the general
concentration.
Water Quality
Testing
Carry out routine testing of the
water quality. Tests should include:
alkalinity,
cyanuric acid
See Notes above1WAdded
2. Suction Filters. Clean Filters1DAdded
1. Transfer
Channels
If applicable, the deck-level
transfer channels are be drained a
minimum of once a month. They
should be flushed out with a
disinfecting solution suitable for the
task, for example 10 mg/l
chlorinated water, which can be
returned to the balance tank. The
undersides of transfer channel
grilles should be cleaned.
1MAdded
2. Balance Tanks Balance tanks should be drained at
least twice per year. Debris should
be removed and inner surfaces
brushed and flushed down with a
disinfecting solution, for example 10
mg/l chlorinated water, which can
be returned to the circulation
system via the filters. For safety,
individuals should not enter balance
tanks on their own
6MAdded
4b. Controls Re-calibrate automatic monitoring
equipment. Check all control
indicator lamps and alarms.
1MAdded
6. Suspended
ceilings
In the case of an indoor pool having
a suspended ceiling the wire
hangers holding the ceiling frame to
the slab should be checked by a
structural engineer due to the highly
corrosion nature of the atmosphere
and the possibility of the ceiling
collapsing.
6MAdded
7. Log Book Check log book for any reported
defects and attend as required. Any
works carried out should be clearly
recorded in accordance with the
operating code of practice.
This task is in addition to the daily
check carried out as part of any
operational procedure.
1MAdded
Page 191 of 222
Previous
Version
Updated
Version
Reason For
Change
8. Chlorine gas
detectors
Check chlorine gas detectors in the
plantroom / chemical store.
6MAdded
9. Chemical
dosing
Check and clean the chemical
control system including all dosing
and monitoring equipment. In
addition any specialist items like
ozonators and ultraviolet lamps.
Although the frequency has been
set at 6 Months, the DFE guidance
note Guide 2, Managing Schol
Facilities requires a minimum of 4
visits per year
6MAdded
10. ElectricalAdded
Zones 0 & 1 Ensure notices on all outlets and
control devices are in place.
12MAdded
Supplementary
bonding
Check that all extraneous
conductive parts in zones 0, 1 and
2 are connected by supplementary
bonding conductors to the
protective conductors of exposed
conductive parts in these zones.
12MAdded
Added
Page 192 of 222
Previous
Version
Updated
Version
Reason For
Change
SWIMMING POOLS - FILTERS57-03 57-03 SWIMMING POOLS - FILTERS
Title NotesActionFQTitle FQ Action Notes
1. Backwashing Carry out backwashing of main
filters and discharge the back wash
water to waste. Backwash flow
should be fast enough to fluidise
the sand bed and should have a
speed of at least 30 m/h.
Fluidisation of the bed should be
checked visually if possible, through
a viewing window where provided.
Backwashing should continue at
least as long as recommended by
the manufacturer, but certainly until
the backwash water is clear.
Filters should be backwashed at
least once a week and whenever
the pressure loss across the sand
bed reaches the level specified by
the filter manufacturer.
Filters should be backwashed if the
water circulation has been stopped
(because of a failure or for
maintenance). Backwashing is best
done at the end of the working day.
Air scouring prior to the
backwashing at a speed of
approximately 32 m/h can aid the
backwashing process.
If a filter is being backwashed while
other filters are still in service, flow
to the filter should start and stop
slowly over a 15 second to 20
second period to avoid rapid flow
rate change in the in-service filters.
1WAdded
5. Filter bed Inspect the filter and the top of the
sand bed. Check for signs of
corrosion, problems with the
under-drains and problems with the
filter medium e.g. mud balling,
fissures, uneven bed.
12MAdded
Page 193 of 222
Previous
Version
Updated
Version
Reason For
Change
SWIMMING POOLS - PIPEWORK, PUMPS, HEATING etc.57-04 57-04 SWIMMING POOLS - PIPEWORK, PUMPS, HEATING etc.
Title NotesActionFQTitle FQ Action Notes
Hot water
temperature (at
outlet of post swim
showers).
Monitor to ensure compliance with
ACOP L8, 2000 requirements. Hot
water supplied to the showers
should be piped at no less than 50
°C and mixed to (41 ± 2) °C.
Responsibility for this test should be
agreed with client. Advise client if
temperature outside ACOP L8, 2000
requirements for any remedial work
to be put in hand.
1MAdded
Indoor air
temperatures and
RH
Manually check the pool hall air
temperatures and Relative Humidity
levels
The pool hall air temperatures
should be no more than 1 °C above
that of the water temperature.
Air temperatures over 30 °C should
be avoided.
Relative humidity should be
maintained at a level of (60 ± 10) %
throughout the pool hall area.
1WAdded
3. Pump Check for leaks and corrosion,
tighten gland if required. Check
electrical connections for tightness
and signs of corrosion.
See also Pumps SFG 45.
Although the frequency has been
set at 6 Months, the DFE guidance
note Guide 2, Managing Schol
Facilities requires a minimum of 4
visits per year
12MAdded
4. Ventilation Carry out maintenance procedures
on the ventilation plant serving the
pool and changing areas. For
further Guidance on Maintenance
see Air handling units SFG 03,
Ducting SFG 16 and Fans SFG 20.
The Relative humidity should be
maintained at a level of (60 ± 10) %
throughout the pool hall area. It is
understood that manufacturers of
AHU`s and ductwork specified for
swimming pools will coat internal
surfaces to protect from Chlorine
attack. Therefore standard
maintenance frequencies
recommended in SFG 03, 16 and
20 can be used.
3MAdded
Page 194 of 222
Previous
Version
Updated
Version
Reason For
Change
57-04 SWIMMING POOLS - PIPEWORK, PUMPS, HEATING etc.
Once a pool is winterised then the level of regular maintenance required is very much less than during
the season. There are no hard and fast rules governing the actual date of winterising; however the
lower ambient temperature becomes the more expensive the heating becomes.
The Pool must not be emptied, without professional advice, as hydrostatic pressures can force a
concrete structure out of the ground and ground water can lift and displace liners.
All floating covers should be removed from the pool, cleaned and carefully dried and stored safely
away from vermin. Slatted covers should be cleaned and rolled away for the winter. The fitting of a
proper winter cover will help keep the majority of debris and sunlight out of the pool.
Winterising does not mean that the algae will stop growing, therefore there will be a requirement to
treat the water until the water temperature
drops to about 7°C.
Remove, clean and store all pool-side equipment and summer covers etc. Check all filtration, heating
and cleaning equipment and report on its condition. Remove and store pool cleaner if fitted. De-leaf
and clean the pool.
Check the chemical values and adjust including a shock dose. A number of chemicals which are long
lasting are available for winterisation. However the variance of winter weather and temperature affects
the longevity of these products and occasional testing is recommended
Added
Title NotesActionFQTitle FQ Action Notes
Option 1
Winterisation
Lower the level of the pool water* to
approximately 30 cms below the
skimmers as a frost precaution and
plug
and empty out the skimmer. Store
the pumps in a warm environment.
Isolate all electrics and drain all
equipment such as pumps,
filters, heaters etc. Leave the pool
area and plant room in a tidy state.
1YAdded
Water Testing Check the water condition regularly
and dose if required.
This can be easily done by lifting a
corner of the cover.
Chemicals that dissolve quickly in
the summer will be slower
reacting in the winter, so pre
dissolving them is essential.
1MAdded
Option 2
Winterisation
Set the filter pump time clock
control to allow the pump to run for
one hour per day and set a frost
thermostat to 2oC. Install a bypass
around the heater and drain the
heater, electrically disconnect, or
switch off other
equipment..
1YAdded
Page 195 of 222
Previous
Version
Updated
Version
Reason For
Change
Water Testing Check the water condition regularly
and dose if required.
This can be easily done by lifting a
corner of the cover.
Chemicals that dissolve quickly in
the summer will be slower
reacting in the winter, so pre
dissolving them is essential.
1MAdded
Filters backwash the filter, once every 2
months, or if pool water level
increases
from rainfall.
2MAdded
Re-commissioning Remove the winter cover from the
pool, clean it off, dry and fold it,
then store away. . Store the cover
away from vermin.
• Clean the coping stones and
surround paving to remove any
mould or algae growth.
• Re-fit all the pool side equipment
such as ladders, diving boards etc.
• If necessary re-assemble all the
filtration and heating equipment in
the plant room
• Start the equipment and
thoroughly test it. Heaters should
not be left running unless specific
instructions have been provided.
• Set all time clocks forcorrect
running hours.
• Check all valves for freedom of
operation and ease if necessary.
• De-leaf pool and vacuum or set
the pool cleaner in operation.
• Check and adjust the chemical
values.
• Generally tidy and clean the pool
area and plant room.
Once the pool has been
recommissioned,
run the filter continually for the first
5 days, backwashing daily, to
thoroughly clean the water.
1YAdded
Page 196 of 222
SWITCHES
Page 197 of 222
Previous
Version
Updated
Version
Reason For
Change
ON/OFF SWITCHING DEVICES58-01 58-01 ON/OFF SWITCHING DEVICES
Title NotesActionFQTitle FQ Action Notes
1. Condition Clean and check operation.12MAdded
Vane operated
flow switches
Added
Page 198 of 222
TERMINAL UNITS
Page 199 of 222
Previous
Version
Updated
Version
Reason For
Change
TERMINAL UNITS VAV - self powered59-01 59-01 TERMINAL UNITS VAV - self powered
Title NotesActionFQTitle FQ Action Notes
2. Bellows Where fitted, check condition of
bellows and replace as necessary
6MAdded
Page 200 of 222
Previous
Version
Updated
Version
Reason For
Change
TERMINAL UNITS VAV - fan powered59-02 59-02 TERMINAL UNITS VAV - fan powered
Title NotesActionFQTitle FQ Action Notes
5. Reheaters Check operation and carry out
routine maintenance
For further guidance on maintaining
the reheaters see Heat exchangers
SFG 29-01 and 29-02.
6MAdded
Page 201 of 222
Previous
Version
Updated
Version
Reason For
Change
TERMINAL UNITS - FAN COIL59-06 59-06 TERMINAL UNITS - FAN COIL
Title NotesActionFQTitle FQ Action Notes
9. Strainers Inspect and clean strainers as
necessary.
Report any build up of sludge/filing
to the client.
12MAdded
10. Chilled
water/LPHW
control valves.
Check functioning. For detailed maintenance see
Valves SFG 62-01 to 62-07.
6MAdded
11. Thermostats. Check operation by moving set
point. Restore to original setting.
For detailed maintenance see
Switches SFG 58-01.
12MAdded
Page 202 of 222
Previous
Version
Updated
Version
Reason For
Change
TERMINAL UNITS VRV SYSTEMS59-07 59-07 TERMINAL UNITS VRV SYSTEMS
Where the installed power on the refrigeration system exceeds 25kW, a Written Scheme of
Examination may be required to comply with the Pressure Systems Safety Regulations 2000
Service providers must be registered to an Approved Certified Scheme provider , in accordance with
the F Gas and Building Regulations.
Added
Title NotesActionFQTitle FQ Action Notes
3a. Leaks - Oil Check for oil leaks. Any leak of
refrigerant should be dealt with
immediately.
6MAdded
4. Compressors Carry out Service of the
compressor
For further guidance see
Compressors - refrigeration SFG
12-01.
6MAdded
3 . Leaks -
Refrigerant
Check refrigerant Charge,
recharge/report as found
necessary. Check Joints, valves
including stems, seals, including
seals on replaceable driers and
filters, parts of the system subject
to vibration, connections to safety
or operational devices of the
equipment or system. Examine for
leakage using direct or indirect
measuring methods.
Check for leaks should be part of
the routine servicing by plant
attendants.
Any removed refrigerant must be
recovered and not released to
atmosphere.
Where a system has a refrigerant
charge greater than 300kg, an
automatic leak detection system
must be installed on the system to
comply with the F Gas Regulations
Added
A) Normal
systems:
<3 kg
Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
0MAdded
B) 3 kg to 30 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
12MAdded
C) 30 kg to 300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
6MAdded
D) >300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
3MAdded
E) Hermetically
sealed systems:
<6 kg
Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
0MAdded
F) 6 kg to 30 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
12MAdded
G) 30 kg to 300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
6MAdded
H) >300 kg Check for oil and refrigerant leaks.
Any leak of refrigerant should be
dealt with immediately.
3MAdded
Page 203 of 222
VACUUM SYSTEMS
Page 204 of 222
Previous
Version
Updated
Version
Reason For
Change
VACUUM SYSTEMS - general60-01 60-01 VACUUM SYSTEMS - general
In addition to routine maintenance, examinations of some pressure vessels are required under the
Pressure Systems Safety Regulations 2000 - see relevant section 40-08.
Maintenance should be carried out by only competent persons.
Added
Title NotesActionFQTitle FQ Action Notes
Page 205 of 222
Previous
Version
Updated
Version
Reason For
Change
VACUUM TUBES - cash handling60-02 60-02 VACUUM TUBES - cash handling
In addition to routine maintenance, examinations of some pressure vessels are required under the
Pressure Systems Safety Regulations 2000 - see relevant section 40-08.
Maintenance should be carried out by only competent persons.
Added
Title NotesActionFQTitle FQ Action Notes
Page 206 of 222
VALVES
Page 207 of 222
Previous
Version
Updated
Version
Reason For
Change
VALVES61-01 61-01 VALVES
When opening valves (especially steam valves etc.) they must be done in such a way as to avoid the
chances of `water hammer` occurring.
Added
Title NotesActionFQTitle FQ Action Notes
2. Inspection Strip down, overhaul and then
rebuild to comply with the
Competent Persons requirements
under the Pressure Regulation and
the written scheme of examination.
The Competent Person may require
additional testing on completion of
the rebuild
12MAdded
Page 208 of 222
VENTILATION ANCILLARIES
Page 209 of 222
Previous
Version
Updated
Version
Reason For
Change
MOTOR DRIVEN EXHAUST HOSE REEL64-02 64-02 MOTOR DRIVEN EXHAUST HOSE REEL
Title NotesActionFQTitle FQ Action Notes
1. Extract Fans Carry out routine maintenance of
the extract fans. For Guidance see
Fans - extract SFG 20-08
Depending on what the fans are
extracting, the maintenance
frequencies may need to be
increased.
6MAdded
9 System Undertaken a Thorough test and
Inspection of the system in
accordance with Section 10 of
ACOP 258:2008. Thorough’ means
careful, methodical, painstaking
and complete. The task should
only be carried out by a competent
person. The term Competence is
defined Chapter 2 and the
Appendix 1 of the ACOP 258:2008
The maximum time between tests of
LEV systems is set down in COSHH
and for most systems this is 14
months (see the exceptions in Table
18 of the ACOP 258:2008). In
practice this is normally taken to
mean annually. If wear and tear on
the LEV system is liable to mean
that the system effectiveness will
degrade between tests then
thorough examinations and tests
should be more frequent.
12MAdded
Page 210 of 222
Previous
Version
Updated
Version
Reason For
Change
SPRING RECOIL HOSE REEL64-03 64-03 SPRING RECOIL HOSE REEL
Title NotesActionFQTitle FQ Action Notes
1. Extract Fans Carry out routine maintenance of
the extract fans. For Guidance see
Fans - extract SFG 20-08
Depending on what the fans are
extracting, the maintenance
frequencies may need to be
increased.
6MAdded
9 System Undertaken a thorough test and
Inspection of the system in
accordance with Section 10 of
ACOP 258:2008. The task should
only be carried out by a competent
person. The term Competence is
defined Chapter 2 and the
Appendix 1 of the ACOP 258:2008
The maximum time between tests of
LEV systems is set down in COSHH
and for most systems this is 14
months (see the exceptions in Table
18 of the ACOP 258:2008). In
practice this is normally taken to
mean annually. If wear and tear on
the LEV system is liable to mean
that the system effectiveness will
degrade between tests then
thorough examinations and tests
should be more frequent.
12MAdded
Page 211 of 222
Previous
Version
Updated
Version
Reason For
Change
MOBILE DUST SEPARATOR FOR SPOT EXTRACTION64-04 64-04 MOBILE DUST SEPARATOR FOR SPOT EXTRACTION
Title NotesActionFQTitle FQ Action Notes
1. Extract Fans Carry out routine maintenance of
the extract fans. For Guidance see
Fans - extract SFG 20-08
Depending on what the fans are
extracting, the maintenance
frequencies may need to be
increased.
6MAdded
8. System Undertaken a thorough test and
Inspection of the system in
accordance with Section 10 of
ACOP 258:2008. The task should
only be carried out by a competent
person. The term Competence is
defined Chapter 2 and the
Appendix 1 of the ACOP 258:2008
The maximum time between tests of
LEV systems is set down in COSHH
and for most systems this is 14
months (see the exceptions in Table
18 of the ACOP 258:2008). In
practice this is normally taken to
mean annually. If wear and tear on
the LEV system is liable to mean
that the system effectiveness will
degrade between tests then
thorough examinations and tests
should be more frequent.
12MAdded
9. Mobile Unit Undertake a test of the unit
(Portable Appliance Test) in line
with the requirements of the
Electricity at Work Act 1989
(Regulation 4(2)). For Guidance
see Portable equipment PAT testing
SFG 42-01.
12MAdded
Page 212 of 222
Previous
Version
Updated
Version
Reason For
Change
MOBILE ELECTRONICALLY CONTROLLED CYCLONE SEPARATOR64-05 64-05 MOBILE ELECTRONICALLY CONTROLLED CYCLONE SEPARATOR
Title NotesActionFQTitle FQ Action Notes
1. Extract Fans Carry out routine maintenance of
the extract fans. For Guidance see
Fans - extract SFG 20-08
Depending on what the fans are
extracting, the maintenance
frequencies may need to be
increased.
6MAdded
8. System Undertaken a thorough test and
Inspection of the system in
accordance with Section 10 of
ACOP 258:2008. The task should
only be carried out by a competent
person. The term Competence is
defined Chapter 2 and the
Appendix 1 of the ACOP 258:2008
The maximum time between tests of
LEV systems is set down in COSHH
and for most systems this is 14
months (see the exceptions in Table
18 of the ACOP 258:2008). In
practice this is normally taken to
mean annually. If wear and tear on
the LEV system is liable to mean
that the system effectiveness will
degrade between tests then
thorough examinations and tests
should be more frequent.
12MAdded
9. Mobile Unit Undertake a test of the unit
(Portable Appliance Test) in line
with the requirements of the
Electricity at Work Act 1989
(Regulation 4(2)). For Guidance
see Portable equipment PAT testing
SFG 42-01.
12MAdded
Page 213 of 222
Previous
Version
Updated
Version
Reason For
Change
VEHICLE EXHAUST RAIL SYSTEM64-06 64-06 VEHICLE EXHAUST RAIL SYSTEM
Title NotesActionFQTitle FQ Action Notes
1. Extract Fans Carry out routine maintenance of
the extract fans. For Guidance see
Fans - extract SFG 20-08
Depending on what the fans are
extracting, the maintenance
frequencies may need to be
increased.
6MAdded
11. System Undertaken a thorough test and
Inspection of the system in
accordance with Section 10 of
ACOP 258:2008. The task should
only be carried out by a competent
person. The term Competence is
defined Chapter 2 and the
Appendix 1 of the ACOP 258:2008
The maximum time between tests of
LEV systems is set down in COSHH
and for most systems this is 14
months (see the exceptions in Table
18 of the ACOP 258:2008). In
practice this is normally taken to
mean annually. If wear and tear on
the LEV system is liable to mean
that the system effectiveness will
degrade between tests then
thorough examinations and tests
should be more frequent.
12MAdded
Page 214 of 222
WATER TREATMENT
Page 215 of 222
Previous
Version
Updated
Version
Reason For
Change
ION EXCHANGE PLANT - BASE EXCHANGE SOFTENING - domestic
(capacity usually below 50 litres)
65-03 65-03 ION EXCHANGE PLANT - BASE EXCHANGE SOFTENING - domestic
(capacity usually below 50 litres)
Maintenance of water treatment plant is very important to avoid scaling of heat exchange surfaces in
plant which can lead to deposits and subsequent blockage of outlet fittings, in addition it can lead to
energy wastage and increased costs. The operator should refer to and be familiar with the
manufacturer`s operator`s handbook and follow the manufacturer`s recommendations regarding the
frequency at which the various maintenance functions should be carried out. These can vary
depending on the type of plant and manufacturer.
In addition to the routine checks below the client`s operator will undertake operational tasks including
checking salt levels in the salt saturator/brine tank, check and record, in the log book, inlet water
hardness and outlet (soft) water hardness. The operator will check for leaks and if present, locate
source and report (leaks on control valves and vessel, manufacturer`s advice should be sought).
Added
Title NotesActionFQTitle FQ Action Notes
Page 216 of 222
Previous
Version
Updated
Version
Reason For
Change
OZONATION PLANT65-09 65-09 OZONATION PLANT
Title NotesActionFQTitle FQ Action Notes
1. Joints and
Unions
All mechanical joints and unions
exposed to ozone should be
opened up and the rubber seals
inspected to check if perishing or
any wear and deformation is
occurring If found, the seals should
be replaced before restarting the
equipment again.
1WAdded
Page 217 of 222
WHIRLPOOLS-HYDROTHERAPY
Page 218 of 222
Previous
Version
Updated
Version
Reason For
Change
WHIRLPOOL/SPA BATHS66-01 66-01 WHIRLPOOL/SPA BATHS
Title NotesActionFQTitle FQ Action Notes
7. Air Filter Clean Input air filter when fitted.1MAdded
8. Safety Systems Check all automatic systems are
operating correctly e.g. safety
cut-outs, automatic timers etc.
1MAdded
9. Water
Treatment
Disinfectant/pH controller - clean
electrode and check calibration
(see manufacturers instructions).
1MAdded
10. Sand Filter Thoroughly check sand filter or
diatomaceous earth filter
membranes
3MAdded
11. Air Lines Where possible clean and
disinfect airlines
3MAdded
12. Sand Filter Check sand filter efficiency12MAdded
Page 219 of 222
Previous
Version
Updated
Version
Reason For
Change
HYDROTHERAPY POOLS66-02 66-02 HYDROTHERAPY POOLS
Title NotesActionFQTitle FQ Action Notes
4. Circulatory
pipework,
including solar
panels (where
fitted).
Isolate from pool and drain down.
Clean out and dry.
12MAdded
5. Automatic air
vents.
Remove, drain and clean.12MAdded
6. Heating
equipment - Oil -
Solar
-Gas
Carry out maintenance procedures
appropriate to the type of heating
plant as detailed in relevant
sections.
Maintenance of heating plant, other
than routine, is best carried out
before the heating season starts.
6MAdded
a) Filtration plant. The filtration plant of
a pool is designed to remove water
from the pool, filter it, disinfect it
and return it to the pool in a sterile
condition. The main types of pool
filters are:
a) Conventional rate pressure sand
filtration
b) Medium rate pressure sand
filtration
c) High rate pressure sand filtration
d) Pre-coat cartridge (pressure and
vacuum)
e) Disposable cartridge or glass
fibre mat filtration
Added
7. Conventional,
medium and high
rate pressure
filtration
The terms conventional, medium
and fast rate refer to the rate of flow
of water through the filter. The
maintenance requirements for the
three types is similar.
Added
8. Inlet strainer. Check condition and clean. More frequent cleaning by the
operator may be necessary if the
inlet flow rate falls below the design
level. (May be shown by increased
suction pressure).
1MAdded
9. Chemical
cleaning of filter
bed material.
Check clean `running` pressure, if
high, may indicate fouling of filter
medium.
Refer to manufacturer`s handbook
for instructions and type of
chemicals to be used.
6MAdded
10. Rate of flow
indicator.
Clean and check operation. The accuracy of the flow meter
should be within 5%.
3MAdded
Page 220 of 222
Previous
Version
Updated
Version
Reason For
Change
11. Pre-coat
filtration 1. Inlet
strainer.
Check condition and clean. More frequent cleaning by the
operator may be necessary if the
inlet flow rate falls below the design
level. (May be shown by increased
suction pressure).
1MAdded
12. Filter
elements.
Clean off any coating material and
check condition of support
elements.
If replacement necessary, report to
the client.
1MAdded
15. Cartridge type
filters 1. Inlet
strainer.
Check condition and clean. More frequent cleaning by the
operator may be necessary if the
inlet flow rate falls below the design
level. (May be shown by increased
suction pressure).
1MAdded
16. Seals. Check condition of seals on
cartridge holders. Replace if
necessary.
1MAdded
17. Rate of flow
indicator.
Clean and check operation. The accuracy of the flow meter
should be within 5%.
3MAdded
Page 221 of 222
Previous
Version
Updated
Version
Reason For
Change
STEAM ROOMS and HUMIDIFIERS66-03 66-03 STEAM ROOMS and HUMIDIFIERS
Title NotesActionFQTitle FQ Action Notes
4. Ventilation Check operation of all ventilation
fans (supply and extract)
For more detailed information on the
maintenance requirements for
steam generation see Fans -
ventilation SFG 20-03.
6MAdded
5. Internal
Surfaces
Check internal surfaces for cracks
in the tiles or grouting. Repair as
necessary with silicone sealant
Generally, the day to day cleaning
of the internal surfaces should be
undertaken by the operational staff.
Cracks or chips in the surfaces can
be a breeding ground for bacteria.
3MAdded
Page 222 of 222