Assessment for EOT Entitlement Window Slicing Approach with CPM Methodology ICP804: Project Planning, Monitoring & Control

MAJULINQWindow Slicing Method for Assessment of Number of Days Entitlement for EOT.pptx

Embed Size (px)

Citation preview

Page 1: MAJULINQWindow Slicing Method for Assessment of  Number of Days Entitlement for EOT.pptx

Assessment for EOT Entitlement

Window Slicing Approach with CPM Methodology

ICP804: Project Planning, Monitoring & Control

Page 2: MAJULINQWindow Slicing Method for Assessment of  Number of Days Entitlement for EOT.pptx

ORIGINAL Site Commencement

15/06/13

22/11/10

22/03/11

ACTUAL B2 Beams & Slab @ Zone 5

Original Float = 91 days(TF = 0 day on 13/02/11)

Revised site possession 15/08/2013

28/02/111 day

13/02/11

13/03/11

14 days original completion period for B2 beams & slab at Zone 5

(based on Original WP)

EOT Entitlement = 28 Days

WINDOW SLICING NO. 1: EoT Entitlement for B2 at Zone 5 (Podium)

Summary of EoT Claim for B2 at Zone 5:

• Duration = 13th Feb 2011 to 13th Mar 2011

• No. of Days = 28 days

Page 3: MAJULINQWindow Slicing Method for Assessment of  Number of Days Entitlement for EOT.pptx

ORIGINAL B2 Beams & Slab @ Zone 6

06/10/10 14/10/10

04/10/10 30/03/11

ACTUAL B2 Beams & Slab @ Zone 6

Original Float = 100 days(TF = 0 day on 02/03/11)

Kitchen Detail Level B2 – Section A-A, B-B & C-C received Status A: B2

slab works at Zone 5 clear to resume works

28/02/119 Days

02/03/11

09/03/119 days original completion period

for B2 beams & slab at Zone 6 (based on Original WP)

EOT Entitlement = 8 Days

WINDOW SLICING NO. 2: EoT Entitlement for B2 at Zone 6 (Podium)

Summary of EoT Claim for B2 at Zone 6:

• Duration = 2nd Mar 2011 to 9th Mar 2011

• No. of Days = 8 days

(Complete B2 Beams & Slab at Kitchen Area)