Assessment for EOT Entitlement
Window Slicing Approach with CPM Methodology
ICP804: Project Planning, Monitoring & Control
ORIGINAL Site Commencement
15/06/13
22/11/10
22/03/11
ACTUAL B2 Beams & Slab @ Zone 5
Original Float = 91 days(TF = 0 day on 13/02/11)
Revised site possession 15/08/2013
28/02/111 day
13/02/11
13/03/11
14 days original completion period for B2 beams & slab at Zone 5
(based on Original WP)
EOT Entitlement = 28 Days
WINDOW SLICING NO. 1: EoT Entitlement for B2 at Zone 5 (Podium)
Summary of EoT Claim for B2 at Zone 5:
• Duration = 13th Feb 2011 to 13th Mar 2011
• No. of Days = 28 days
ORIGINAL B2 Beams & Slab @ Zone 6
06/10/10 14/10/10
04/10/10 30/03/11
ACTUAL B2 Beams & Slab @ Zone 6
Original Float = 100 days(TF = 0 day on 02/03/11)
Kitchen Detail Level B2 – Section A-A, B-B & C-C received Status A: B2
slab works at Zone 5 clear to resume works
28/02/119 Days
02/03/11
09/03/119 days original completion period
for B2 beams & slab at Zone 6 (based on Original WP)
EOT Entitlement = 8 Days
WINDOW SLICING NO. 2: EoT Entitlement for B2 at Zone 6 (Podium)
Summary of EoT Claim for B2 at Zone 6:
• Duration = 2nd Mar 2011 to 9th Mar 2011
• No. of Days = 8 days
(Complete B2 Beams & Slab at Kitchen Area)