Make your contracts work for youThe eff iciency of properly managing contracts with purchasers and suppliers
Negota
10 June 2014 ADVOKATFIRMAET NEGOTA AS • NEGOTA PROJECT AS • www.negota.no
2
Negota Advokatfirmaet Negota ASNegota Project AS
10 June 2014 ADVOKATFIRMAET NEGOTA AS • NEGOTA PROJECT AS • www.negota.no
• Established in 2002• Approximately 20 people from 7 different countries• Qualified lawyers under Norwegian, Swedish, American,
Malaysian, Hungarian, Swiss and English law• Offices in Halden and Oslo
• Provides legal and consultancy services to purchasers and suppliers in construction, oil & gas, energy and shipbuilding/rig construction industries
• Worldwide scope, with lawyers, engineers and other professionals with backgrounds and experience from around the world
3
NegotaContract Management Timeline
Tendering Project Execution Dispute Resolution
10 June 2014 ADVOKATFIRMAET NEGOTA AS • NEGOTA PROJECT AS • www.negota.no
Purchaser
Supplier
• Bid preparation• Negotiation
• Bid evaluation• Negotiation• Award of contract
• Reviewing Instructions from Purchaser
• Variation Order Requests• Assisting Project Manager
• Preparing Variation Orders• Evaluating VORs• Assisting Project Manager
• Disputed Variation Orders• Assembling claims• Settlement negotiation• Arbitration or litigation
• Disputed Variation Orders• Settlement negotiation• Arbitration or litigation
4
NegotaSome examples
- Protect and increase your margin - Protect you from LD’s Three main issues Extension of time (supplier)
◦ Late input from customer is the normal issue◦ Do claim them as soon as possible - timer bars etc
◦ Saudi job – lost USD 3 mill Changes to scope of work
◦ Normally a lot more changes then we think◦ Any change to character, quantity and time is a change under normal contracts ◦ Do claim them as soon as possible - timer bars
◦ Supplier to a rig --) waited 8 weeks --) lost in court Spend time on your Schedule
◦ Make sure that CP is linked what really matters◦ Update your schedule when the you get late input from buyer
◦ Lead to claim for ext of time and a claim for additional payment
10 June 2014 ADVOKATFIRMAET NEGOTA AS • NEGOTA PROJECT AS • www.negota.no
5
NegotaContract management support
10 June 2014 ADVOKATFIRMAET NEGOTA AS • NEGOTA PROJECT AS • www.negota.no
• Negota offers free advice on contractual or legal questions in relation to projects in our field
• We set aside two days per month when you can make an appointment for Q & A here at Strandgata 10 here in Moss
• We can use that time to evaluate your issue and provide general advice for moving forward
• But WHY free• To demonstrate that:
• it does not need to take a lot of time -) be expensive • Its better to involve support at an early stage
• Contact Pål Are Sund on mob: 40 43 64 28 or [email protected]