38
PT Adhi Karya (Persero) Tbk. January 2020 persada properti persada gedung persada beton commuter properti MANAGEMENT PRESENTATION dumai tirta persada

MANAGEMENT PRESENTATION - ADHI

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

Page 1: MANAGEMENT PRESENTATION - ADHI

PT Adhi Karya (Persero) Tbk.January 2020

persada properti

persada gedung

persada beton

commuter properti

MANAGEMENT PRESENTATION

dumai tirta persada

Page 2: MANAGEMENT PRESENTATION - ADHI

COMPANY PROFILE

2

Page 3: MANAGEMENT PRESENTATION - ADHI

ADHI MILESTONE

PN Adhi Karyawas established by

nationalizing a former

Dutch company called

Associatie N.V.

CHANGEDInto PT. Adhi Karya

(Persero)

First SOE

Construction went public on

March 18th, 2004

TRANSFORMATION 2.0Changes vision, mission,

and values; organizational

restructuring; establishment

of ADHI Learning Center

ESTABLISHING ESTABLISHING

EXPANDINGMoU Mass SOE

Transportation;

Grandhika Hotel Blok M;

Precast Factory

Development.

RIGHT ISSUELRT & TOD construction

STARTING LRT construction along

station and supporting

property

ESTABLISHING

commuter properti

CONTRACT SIGNINGLRT Jabodebek Phase I

Project with the Ministry of

Transportation

3

ESTABLISHING

dumai tirta persada

Page 4: MANAGEMENT PRESENTATION - ADHI

BUSINESS LINES

4

persada gedung

persada beton

commuter properti

persada properti

CONSTRUCTION ENERGY PROPERTY INDUSTRY INVESTMENT

DEPT. INFRA I & II

DEPT. LRT

DEPT. GEDUNG

DEPT. EPC DEPT. INVESTASI

INFRASTRUCTURE

BUILDING

LRT

POWER PLANT

INDUSTRY

OIL AND GAS

PROPERTY

TOD & HOTElPRECAST CONCRETE INFRASTRUCTURE

WATER

ELECTRICITY

dumai tirta persada

Page 5: MANAGEMENT PRESENTATION - ADHI

SHARES OWNERSHIPAs of December 2019

5

Local : 34,3%

Foreign : 14,7%

51% 49%

99,9%99,7%99,9%99,6% 51,0%

Page 6: MANAGEMENT PRESENTATION - ADHI

BOARD OF COMMISIONERS

6

President

Commissioner Commissioner Commissioner CommissionerIndependent

Commissioner

Independent

Commissioner

Page 7: MANAGEMENT PRESENTATION - ADHI

BOARD OF DIRECTORS

President

Director

Director of

Operation 1Director of

Operation 2Director of

Finance

Director of

Human Capital

Director of

QHSE and Development

7

Page 8: MANAGEMENT PRESENTATION - ADHI

ORDER BOOK

8

Page 9: MANAGEMENT PRESENTATION - ADHI

31

.87

6

15

.65

5

36

.31

2

18

.44

1

24

.81

9 4.727

30

.47

2

4.260

36

.31

2 44

.08

3

-

10.000

20.000

30.000

40.000

50.000

60.000

70.000

80.000ORDER BOOK

9

IDR - Billion

Order Book

Carry

Over

to 2019

Revenue Order Book

56.695

66.784

(2018A)(2019F)

Carry

Over

to 2020

(Target)

Revenue

Carry Over

(Target)

New Order

Carry Over

New Order

NJO

JOJO

NJO

20.38222.701

Burnrate

35,95%

Burnrate

33,99%

Page 10: MANAGEMENT PRESENTATION - ADHI

9,1 T IDR (Excl. Tax)

Nov 2019New Contract:• Coast Guard Building in Palu : 248,2 B IDR• Apartment in Jakarta : 221,3 B IDR• Others : 262,7 B IDR

Total : 732,2 B IDR

Source of Fund

81%

18%1%

Contruction & Energy Property Others

Business Lines

72%

7%

21%

Building Road Others

Type of Work

10

23%

66%

11%

Govt. SOE Private

NEW CONTRACT ACHIEVEMENT UP TO NOV 2019

Page 11: MANAGEMENT PRESENTATION - ADHI

11

Q3 - PERFORMANCE

Page 12: MANAGEMENT PRESENTATION - ADHI

INCOME STATEMENT

12

TARGET

SEP 2018 SEP 2019 FY 2019

Revenue 9.432 8.942 18.441 ∇ -5,2% J 48,5%

Gross Profit 1.489 1.391 2.311 ∇ -6,5% K 60,2%

Gross Profit Margin 15,8% 15,6% 12,5%

Net Profit 336 351 755 ∆ 4,7% J 46,5%

Net Profit Margin 3,6% 3,9% 4,1%

INCOME STATEMENT

[SUMMARY]

REALIZATION ANALYSIS

YoY%VS FY

TARGET 2019

IDR - Billion

Page 13: MANAGEMENT PRESENTATION - ADHI

BALANCE SHEET

13

TARGET

DES 2018 SEP 2019 FY 2019

Asset 30.119 32.669 34.286 ∆ 8,5% M 95,3%

Liability 23.833 26.149 25.360 ∆ 9,7% M 103,1%

Equity 6.285 6.521 8.925 ∆ 3,7% K 73,1%

BALANCE SHEET

[SUMMARY]

REALIZATION ANALYSIS

YoY%VS FY

TARGET 2019

IDR - Billion

Page 14: MANAGEMENT PRESENTATION - ADHI

CASH FLOW

14

IDR - Billion

TARGET

SEP 2018 SEP 2019 FY 2019

Operating (2.097.071) (3.081.167) (854.658)

Investing (163.921) (1.147.201) (2.297.902)

Financing (366.705) 2.423.956 4.242.174

CASH FLOW

[SUMMARY]

REALIZATION

Page 15: MANAGEMENT PRESENTATION - ADHI

FINANCIAL RATIO

15

TARGET

SEP 2018 SEP 2019 FY 2019

DER (X) [Covt. < 3,5x] 1,40 1,70 1,22

Collection Period (hari) - 72 122 60

TIE (X) [Covt. > 3,0x] 3,06 2,46 3,17

ROA - 2,38 1,85 4,13

ROE - 5,82 5,73 9,24

RATIO CovenantREALIZATION

Page 16: MANAGEMENT PRESENTATION - ADHI

CAPITAL EXPENDITURE

16

Fix Asset 165,2 654,0 J 25,3%

Inv. Projects and Land Aqs. 990,7 1.643,0 K 60,3%

Subsidiary 312,8 865,0 J 36,2%

TOTAL 1.468,6 3.162,0 J 46,4%

CAPEXREALIZATION

SEP 2019

TARGET

FY 2019

%VS FY

TARGET 2019

IDR - Billion

Page 17: MANAGEMENT PRESENTATION - ADHI

PROJECT UPDATE

LIGHT RAIL TRANSIT17

Page 18: MANAGEMENT PRESENTATION - ADHI

LRT JABODEBEK

18

LRT ROUTE LENGTH: 82.9 KM

4. D.Atas-Palmerah-Senayan : 7,8 km

5. Cibubur-Bogor : 25,0 km

6. Palmerah-Grogol : 5,7 km

1. Cawang-Cibubur : 14,9 km

2. Cawang-Kuningan-D.Atas : 11,1 km

3. Cawang–Bekasi Timur : 18,5 km

P h a s e I

P h a s e I I

TOTAL STATION: 18

Page 19: MANAGEMENT PRESENTATION - ADHI

Up to 10 January 2020

LRT Progress

19

69.6%

Cawang – Cibubur Cawang – Kuningan –

Dukuh AtasCawang – Bekasi Timur

87.1% 63.6% 61.8%

LRT Progress

Page 20: MANAGEMENT PRESENTATION - ADHI

LRT DISBURSEMENT FLOW

20

PREPARE

CERTIFICATE

PAYMENT

OCG

CHECKED BY

BPKPIndonesia’s National

Government Internal Auditor

PT KAI

LRT OPERATOR

RECEIVED

PAYMENT

Page 21: MANAGEMENT PRESENTATION - ADHI

LRT PHASE I DISBURSEMENT

21

3.4 T IDRExc. tax

*Based on progress from September 2015 until September 2017

1

Total Interim Payment Received

8.9 T IDRExc. tax

PAID on March 2018

2.5 T IDRExc. tax

*Based on progress from October 2017 until June 2018

2PAID on December 2018

1.2 T IDRExc. tax

*Based on progress from July 2018 until September 2018

3PAID on May 2019

1.2 T IDRExc. tax

*Based on progress from October 2018 until March 2019

4PAID on October 2019

0.6 T IDRExc. tax

*Based on progress from April 2019 until September 2019

5PAID on December 2019

Page 22: MANAGEMENT PRESENTATION - ADHI

PROJECT UPDATE

TRANSIT ORIENTED DEVELOPMENT22

Page 23: MANAGEMENT PRESENTATION - ADHI

ACP SHARE OWNERSHIP

23

99,9%99,7%99,9%99,6% 51,0%

Spin-off on July’18

Page 24: MANAGEMENT PRESENTATION - ADHI

TOD PROJECTS

DEVELOPMENT

SUMMARY

24

EASTERN GREEN – Sta. Bekasi

URBAN SIGNATURE – Sta. Ciracas

ROYAL SENTUL PARK – Sta. Sentul

GATEWAY PARK – Sta. Jaticempaka

GREEN AVENUE – Sta. Jatimulya

MTH 27 – Sta. Ciliwung

THE PREMIERE MTH– Sta. Cikoko

OASE PARK – Sta. Ciputat

CISAUK POINT – Sta. Serpong

RIVIA– Sta. Sentul

GRAND CENTRAL BOGOR– Sta. Bogor

ADHI CITY– Sta. Sentul

Page 25: MANAGEMENT PRESENTATION - ADHI

TOD SUMMARY PROJECTS

Commercial Area Office Space Apartment ShophouseLRT Stations

+ 9 5H a

Total Development Area

M o r e T h a n

2 6 , 0 0 0

Recreation Area

Apartment units

25

Page 26: MANAGEMENT PRESENTATION - ADHI

EXISTING PROJECT - URBAN SIGNATURE

DEVELOPMENT SUMMARY

Location : Ciracas, JakartaTotal Area : ±6,2 hectarePartnership Scheme : 60% ACPDevelopment Type : Apartment, Commercial, Park & Ride

Potential Saleable Unit/Area : 5 TowersApartment Development : ±3.668 units

26

Page 27: MANAGEMENT PRESENTATION - ADHI

EXISTING PROJECT - GATEWAY PARK

DEVELOPMENT SUMMARY

Location : Jaticempaka, Bekasi, West JavaTotal Area : ±5,9 hectarePartnership Scheme : 60% ACPDevelopment Type : Apartment, Commercial, Park & Ride

Potential Saleable Unit/Area : 5 TowersApartment Development : ±4.230 units

27

Page 28: MANAGEMENT PRESENTATION - ADHI

EXISTING PROJECT – GREEN AVENUE

DEVELOPMENT SUMMARY

Location : Jatimulya, Bekasi, West JavaTotal Area : ±2,0 hectarePartnership Scheme : 60% ACP; 40% APPDevelopment Type : Apartment and Commercial Area

Potential Saleable Unit/Area : 5 TowersApartment Development : ±2.944 units

28

Page 29: MANAGEMENT PRESENTATION - ADHI

EXISTING PROJECT - ROYAL SENTUL PARK

DEVELOPMENT SUMMARY

Location : Sentul, Bogor, West JavaTotal Area : ±14,8 hectarePartnership Scheme : 65% ACPDevelopment Type : Apartment, Commercial, Park & Ride

Potential Saleable Unit/Area : 12 TowersApartment Development : ±1.636 units

29

Page 30: MANAGEMENT PRESENTATION - ADHI

EXISTING PROJECT - EASTERN GREEN

DEVELOPMENT SUMMARY

Location : East Bekasi, West JavaTotal Area : ±1,4 hectarePartnership Scheme : 60% ACP : 40% APPDevelopment Type : Apartment, Commercial, Park & Ride

Potential Saleable Unit/Area : 5 TowersApartment Development : ±936 units

30

Page 31: MANAGEMENT PRESENTATION - ADHI

EXISTING PROJECT - MTH 27

DEVELOPMENT SUMMARY

Location : Cikoko, JakartaTotal Area : ±4,0 hectarePartnership Scheme : 100% ACPDevelopment Type : Apartment, Commercial, Office, Park & Ride

Potential Saleable Unit/Area : 1 Tower Apartment; 1 Tower OfficeApartment Development : ±760 units

31

Page 32: MANAGEMENT PRESENTATION - ADHI

EXISTING PROJECT – OASE PARK

DEVELOPMENT SUMMARY

Location : Ciputat, TanggerangTotal Area : ±5,2 hectarePartnership Scheme : 65% ACPDevelopment Type : Apartment, Commercial, Park & Ride

Potential Saleable Unit/Area : 4 TowersApartment Development : ±3.353 units

32

Page 33: MANAGEMENT PRESENTATION - ADHI

EXISTING PROJECT – CISAUK POINT

DEVELOPMENT SUMMARY

Location : Serpong, TanggerangTotal Area : ±1,6 hectarePartnership Scheme : 65% ACPDevelopment Type : Apartment, Commercial, Park & Ride

Potential Saleable Unit/Area : 6 TowersApartment Development : ±2.848 units

33

Page 34: MANAGEMENT PRESENTATION - ADHI

EXISTING PROJECT – THE PREMIER MTH

DEVELOPMENT SUMMARY

Location : Tebet, JakartaTotal Area : ±0,7 hectarePartnership Scheme : 70% ACPDevelopment Type : Apartment, Commercial, Park & Ride

Potential Saleable Unit/Area : 2 TowersApartment Development : ±390 units

34

Page 35: MANAGEMENT PRESENTATION - ADHI

EXISTING PROJECT – RIVIA

DEVELOPMENT SUMMARY

Location : Sentul, Bogor, West JavaTotal Area : ±4,5 hectarePartnership Scheme : 70% ACPDevelopment Type : Apartment, Commercial, Park & Ride

Potential Saleable Unit/Area : 5 TowersApartment Development : ±2.392 units

35

Page 36: MANAGEMENT PRESENTATION - ADHI

EXISTING PROJECT – GRAND CENTRAL BOGOR

DEVELOPMENT SUMMARY

Location : Bogor, West JavaTotal Area : ±0,5 hectarePartnership Scheme : 100% ACPDevelopment Type : Apartment, Commercial, Park & Ride

Potential Saleable Unit/Area : 1 TowersApartment Development : ±833 units

36

Page 37: MANAGEMENT PRESENTATION - ADHI

EXISTING PROJECT – ADHI CITY

DEVELOPMENT SUMMARY

Location : Sentul, Bogor, West JavaTotal Area : ±47,8 hectareApartment Development : ±2.079 unitsPartnership Scheme : 60% ACPDevelopment Type : Apartment, Commercial, Park & Ride

37

Page 38: MANAGEMENT PRESENTATION - ADHI

Visit us at www.adhi.co.idFor further information please contact:

Parwanto Noegroho, Corporate SecretaryP. +62 21 797 5312 F. +62 21 797 5311 E. [email protected]

Disclaimer:Important Notice• This document was prepared only for the party with the purpose of discussion. This document and

its contents may only be reproduced, disclosed or used with the express written consent of PT AdhiKarya (Persero) Tbk.

• This document may contain statements that projected hopes and expectations in the future, whichrepresents the Company's current circumstances with possible events in the future and financialplanning. The projections are based on assumptions and available data at the time this data iscreated, containing risks and are subject to change at any time.

• PT Adhi Karya (Persero) Tbk. or connected parties will not be liable in any way for any consequences(including but not limited to any direct, indirect, or consequential losses) arising from or relating toany reliance on or use of the content of this document.

THANK YOU