Manpower Plan. Of X-Y File Group. Group Members. P.J. Mamacos Christy Mae Aquino. Problem: . A newly-wed couple plans to construct a house. The couple has already a house plan from their friend engineer. The plan of the house is illustrated below. . 1m. L aboratory. 2m. B edroom. 2m. - PowerPoint PPT Presentation

Citation preview

Page 1: Manpower Plan

Manpower Plan

OfX-Y File Group

Page 2: Manpower Plan

Group Members

P.J. MamacosChristy Mae Aquino

Page 3: Manpower Plan

Problem: A newly-wed couple plans to construct a house. The couple has already a house plan from their friend engineer. The plan of the house is illustrated below.

BedroomComfort roomMaster Bedroom

Laboratory

Dining RoomLiving Room

2m

1.5m2.5m

3m 3m

1m2m

3m

Page 4: Manpower Plan

Workers needed for this project

We need 1 foreman, 2 skilled workers and 4 unskilled workers to build the house that the couple want.

Page 5: Manpower Plan

Daily wage of the workers

Skilled worker--------------------P350.00/day

Foreman------------------------------P400.00/day

Unskilled worker-----------------P250.00/day

Page 6: Manpower Plan

Days needed for the project to be done

30 Days

Page 7: Manpower Plan

Computation of the cost of the entire job

Workers Daily wage

Total # of work

days

Total wage of every worker

Foreman 400 30 days 12000 pesos/ month

2 Skilled Worker

350 30days 21000 pesos/ month

4 Unskilled Worker

250 30days 30000 pesos/ month

Total Cost 52 200 pesos/ month

Page 8: Manpower Plan

Computation of daily costLet m be the cost of the job daily

52 200 pesos = m month 1 day52 200 pesos = m 30 days 1 day(30 days) m = (52 200 pesos) 1 day 30 days 30 days

m = 1740 pesos/day

Page 9: Manpower Plan

References:http://

www.bbisd.org/pages/uploaded_images/carpenter_lathe_carving_lg_nwm.gif

http://kmvb.weboldala.net/elsosegely/2.gif http://www.autopozicovna-nz.sk/images/worker.gif http://

www.pattanakit.net/images/1193720269/architect_reading_blu_a_ha.gif

http://www.francisxaviers.com/web2012/images/under_construction.gif

http://www.svdpri.org/under_construction_worker.gifhttp://msmcclure.com/wp-content/uploads/2010/09/anim

ated-construction-workers1.gif

Page 10: Manpower Plan

ComputationLet x be the total wage of the foreman in a month

x = daily wage X entire days= 400 pesos X 30 days1day

= 400 pesos X 30 days1day 1 month= 12000 pesos/ month

Page 11: Manpower Plan

ComputationLet y be the total wage of the skilled worker in a month

y = daily wage X entire work days= 350 pesos X 30 days1day

= 350 pesos X 30 days1day 1 month= 10500 pesos/ month

2y = 2 ( 10500 pesos/ month) = 21000 pesos/ month

Page 12: Manpower Plan

ComputationLet z be the total wage of the unskilled worker in a month

z = daily wage X entire work days= 250 pesos X 30 days1day

= 250 pesos X 30 days1day 1 month= 7500 pesos/ month

4z = 4 ( 7500 pesos/ month) = 30000 pesos/ month

Page 13: Manpower Plan

Computation of the cost of the entire job

Let n be the total cost of the entire job

n = x + 2y + 4z= 1200 pesos + 21 000 pesos + 30 000 pesos

month month month= 52 200 pesos/ month