Manpower Plan. Of X-Y File Group. Group Members. P.J. Mamacos Christy Mae Aquino. Problem: . A newly-wed couple plans to construct a house. The couple has already a house plan from their friend engineer. The plan of the house is illustrated below. . 1m. L aboratory. 2m. B edroom. 2m. - PowerPoint PPT Presentation
Citation preview
Manpower Plan
OfX-Y File Group
Group Members
P.J. MamacosChristy Mae Aquino
Problem: A newly-wed couple plans to construct a house. The couple has already a house plan from their friend engineer. The plan of the house is illustrated below.
BedroomComfort roomMaster Bedroom
Laboratory
Dining RoomLiving Room
2m
1.5m2.5m
3m 3m
1m2m
3m
Workers needed for this project
We need 1 foreman, 2 skilled workers and 4 unskilled workers to build the house that the couple want.
Daily wage of the workers
Skilled worker--------------------P350.00/day
Foreman------------------------------P400.00/day
Unskilled worker-----------------P250.00/day
Days needed for the project to be done
30 Days
Computation of the cost of the entire job
Workers Daily wage
Total # of work
days
Total wage of every worker
Foreman 400 30 days 12000 pesos/ month
2 Skilled Worker
350 30days 21000 pesos/ month
4 Unskilled Worker
250 30days 30000 pesos/ month
Total Cost 52 200 pesos/ month
Computation of daily costLet m be the cost of the job daily
52 200 pesos = m month 1 day52 200 pesos = m 30 days 1 day(30 days) m = (52 200 pesos) 1 day 30 days 30 days
m = 1740 pesos/day
References:http://
www.bbisd.org/pages/uploaded_images/carpenter_lathe_carving_lg_nwm.gif
http://kmvb.weboldala.net/elsosegely/2.gif http://www.autopozicovna-nz.sk/images/worker.gif http://
www.pattanakit.net/images/1193720269/architect_reading_blu_a_ha.gif
http://www.francisxaviers.com/web2012/images/under_construction.gif
http://www.svdpri.org/under_construction_worker.gifhttp://msmcclure.com/wp-content/uploads/2010/09/anim
ated-construction-workers1.gif
ComputationLet x be the total wage of the foreman in a month
x = daily wage X entire days= 400 pesos X 30 days1day
= 400 pesos X 30 days1day 1 month= 12000 pesos/ month
ComputationLet y be the total wage of the skilled worker in a month
y = daily wage X entire work days= 350 pesos X 30 days1day
= 350 pesos X 30 days1day 1 month= 10500 pesos/ month
2y = 2 ( 10500 pesos/ month) = 21000 pesos/ month
ComputationLet z be the total wage of the unskilled worker in a month
z = daily wage X entire work days= 250 pesos X 30 days1day
= 250 pesos X 30 days1day 1 month= 7500 pesos/ month
4z = 4 ( 7500 pesos/ month) = 30000 pesos/ month
Computation of the cost of the entire job
Let n be the total cost of the entire job
n = x + 2y + 4z= 1200 pesos + 21 000 pesos + 30 000 pesos
month month month= 52 200 pesos/ month