Page 2: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

Approval Process

• Identify Program Requirements and Budget• Develop Design Documents • NJDOE Approval (educational capacity)• Planning Board Courtesy Review• NJDCA Approval (specification codes)• Bid• Construct

Page 3: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

Identify Program RequirementsSchool Year Middle School Enrollments Increase Over Previous Year

2002-2003 1,547

2003-2004 1,504 (40)

2004-2005 1,468 (36)

2005-2006 1,414 (54)

2006-2007 1,371 (43)

2007-2008 1,332 (39)

2008-2009 1,356 14

2009-2010 1,394 38

2010-2011 1,404 10

2011-2012 1,416 57

2012-2013 projected 1,440 24

2013-2014 projected 1,544 104

2014-2015 projected 1,584 40

Page 4: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

Develop Design Documents

• 2010-2011 Confirmed Need to Address Increasing Enrollment

• 2010-2011 Identified Need to Renovate Science Labs

• Reviewed 2001-2003 Original Addition Plans • Updated Plans for current needs, efficiencies,

and cost analysis• 2011-2012 Funding for Project Identified

Page 5: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

Plan Development and Approvals

• NJDOE Approved Project and Educational Capacity

• Maplewood Planning Board Raised question regarding brick façade facing Maple Avenue and Impact on Existing Foliage

• Interior Details Being Finalized for Submittal to NJDCA

Page 6: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

Future Timeline

• June 2012 Submittal to DCA• Summer 2012 Bid for Project

• (dependent on DCA review)

• September 2012 Begin Construction• (dependent on DCA review)

• September 2013 Opening of New Addition

Page 7: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

Site Plan for

Maplewood Middle School

Addition

Page 8: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

Existing BuildingFront FaçadeFacing Burnet Street

Page 9: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

Addition Facing the Front of the School

Page 10: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

View from Rear of Addition

Page 11: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

Existing Building Side View Facing Maple Avenue

Page 12: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

Side of Addition Facing Maple Ave

Page 13: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

Revised Side View for Discussion

Page 14: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

Existing Tree in Front of Maplewood Middle School Near the Site of the Addition

Page 15: Maplewood Middle School Addition Board of Education Meeting May 7, 2012
Page 16: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

First and Second Floor Science Labs

Page 17: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

Basement Level Classrooms

Page 18: Maplewood Middle School Addition Board of Education Meeting May 7, 2012

What’s Next?• Finalization of Plans and Internal Space• June 2012 Submittal to DCA• Summer 2012 Bid for Project • September 2012 Begin Construction• September 2013 Opening of New Addition

Communication to Neighbors:– Sign up for Notification this evening– Send contact information to: