Marina Casablanca Quotation 7 (13 05 09)

Embed Size (px)

Citation preview

  • 8/8/2019 Marina Casablanca Quotation 7 (13 05 09)

    1/15

    SGTM Marruecos

    Marina Casablanca11th May 2009

    1

  • 8/8/2019 Marina Casablanca Quotation 7 (13 05 09)

    2/15

    Index

    1. Description of materials page 3

    2. Presentation page 4

    3. Quotation A : Formwork for Rectangular flats page 4

    A.Details of Works page 5

    B.Technical Study page 5

    B.1 Execution Diagrams page 6

    C. Price Study page 7

    D. Total Ex-Works Price page 7

    4. Quotation B : Formwork for Rect.+Triangular flats page 8

    A.Details of Works page 8

    B.Technical Study page 8

    B.1 Execution Diagrams page 9

    C. Price Study page 10

    D. Total Ex-Works Price page 10

    5. Total Quotation A+B page 11

    6. Repurchase option page 12

    7. General Conditions page 13

    Annex I : Details of System page 15

    OFE0167492 2

  • 8/8/2019 Marina Casablanca Quotation 7 (13 05 09)

    3/15

    1. Description of Materials

    OFE0167492 3

  • 8/8/2019 Marina Casablanca Quotation 7 (13 05 09)

    4/15

    RegistroMercan

    tildeMadrid,To

    mo2.454General1.804,Secci

    n3dellibrode

    Sociedades,Fo

    lio60,Hojan15.794

    .NI.F.A.-2

    8/228690

    2. Presentation

    SGTMCasablanca (Morocco)

    Att. Mr. Karim Darrab

    RW Madrid, 12 de December de 2010

    OFE0167491: Casablanca Marina in Casablanca

    Dear Sirs:

    Based on the information received, we have prepared the following quote of our

    materials for the construction of the Casablanca Marina.

    It consist on the sale of material for two independent sets of formwork for the executionof the rectangular floors of Buildings 1 and 2 (Quotation A) and the execution of triangular and

    rectangular floors of Building 3 (Quotation B).

    OFE0167492 4

  • 8/8/2019 Marina Casablanca Quotation 7 (13 05 09)

    5/15

    3. Quotation A : Formwork for Rectangular flatswith E-4 System.

    3. A) DETAILS OF WORKS

    - Total surface : 16.000 m

    - Open height : 3,30 m

    - Slab type : Grid Formwork with 20 + 10 coffers

    - Requested surface : 815 m

    3. B) TECHNICAL STUDY OF SLABS

    According to your request, we recommend the following execution plan:

    Formwork material (1+2,5) : 815 m of Grid formwork + Coffers2.038 m of support system.

    OFE0167492 5

  • 8/8/2019 Marina Casablanca Quotation 7 (13 05 09)

    6/15

    3.B.1.) EXECUTION DIAGRAM

    m2 N Mod m2 N Mod. 1

    6

  • 8/8/2019 Marina Casablanca Quotation 7 (13 05 09)

    7/15

    3. C) PRICE STUDY.

    Details of materials required for 810 m2 of Formwork + 2.038 m of E-4 SupportSystem : 800 m (1+2,5)

    Ref. Description Uts.Price Total

    /ud

    E-4 Grid Formwork+Coffers+Wood 815 m

    1001546 Cross beam 2200 (E-4) 315 29,78 9.380,702016479 Cross beam 3450 (E-4) 37 44,53 1.647,612016218 Cross beam 2500 (E-4) 5 21,42 107,102016215 Cross beam 3750 (E-4) 24 31,40 753,60

    2016289 Cross beam support 4100 N-14 107 42,73 4.572,11

    2016478 Head (E-4) 332 4,23 1387,76

    1001048 Wood board 820/758/27 550 16,15 8.882,50

    1001142 Coffer 20 N-14 684 50,56 34.583,04

    61.739,42

    E-4 Support System 2,5 x 800 m =2.000 m

    2016478 Head (E-4) 830 4,23 3.469,40

    3.469,40

    Props

    1001251 4 meter Prop 2336 14,25 33.288,00

    33.288,00

    Extra materials for specific works

    2016436 Cross beam edges 1,00 m 50 8,50 425,00

    1001129 Assembly Tool 2 0,00425,00

    TOTAL EX-W. 98.505,70

    3.D ) TOTAL EX-WORKS PRICE

    Price of 800 m2 of E4 formwork system with 20 cm N14 coffers + 2.000 m2 of supportsystem:

    EX-Works Torija (warehouse): 98.505, 70

    7

  • 8/8/2019 Marina Casablanca Quotation 7 (13 05 09)

    8/15

    4. Quotation B : Formwork for Rect + Triangular flatswith E-4 System.

    4 .A) DETAILS OF WORKS

    - Total surface : 10.000 m

    - Open height : 3,30 m

    - Slab type : Grid Formwork with 20 + 10 coffers

    - Requested surface : 1.200 m

    3. B) TECHNICAL STUDY OF SLABS

    According to your request, we recommend the following execution plan:

    Formwork material (1+2,5) : 1.200 m of Grid formwork + Coffers3.000 m of support system.

    OFE0167492 8

  • 8/8/2019 Marina Casablanca Quotation 7 (13 05 09)

    9/15

    4.B.1.) EXECUTION DIAGRAM

    Formwork Propped 9

  • 8/8/2019 Marina Casablanca Quotation 7 (13 05 09)

    10/15

    4. C) PRICE STUDY.

    Details of materials required for 1.600 m2 of Formwork + 4.000m of E-4 SupportSystem.

    Ref. Description Uts.Price Total

    /ud

    E-4 Grid Formwork+Coffers+Wood 1.200 m

    1001546 Cross beam 2200 (E-4) 541 29,78 16.110,982016479 Cross beam 3450 (E-4) 44 44,53 1.959,322016218 Cross beam 2500 (E-4) 5 21,42 107,102016215 Cross beam 3750 (E-4) 28 31,40 879,20

    2016289 Cross beam support 4100 N-14 162 42,73 6.922,26

    2016478 Head (E-4) 565 4,18 2.361,70

    1001048 Wood board 820/758/27 942 16,15 15.213,30

    1001142 Coffer 20 N-14 1066 50,56 53.896,96

    97.986,32

    E-4 Support System 2,5 x 1.200 m =3.000 m

    2016478 Head (E-4) 1413 4,18 5.904,255.904,25

    Props

    1001251 4 meter Prop 3587 14,25 51.114,75

    51.114,75

    Extra materials for specific works

    2016436 Cross beam edges 1,00 m 63 8,50 535,50

    1001129 Assembly Tool 2 0,00

    535,50

    TOTAL EX-W. 155,018,95

    3.D ) TOTAL EX-WORKS PRICE

    Price of 1.200 m2 of E4 formwork system with 20 cm N14 coffers + 3.000 m 2 of

    support system:

    EX-Works Torija (warehouse): 155.018,95

    10

  • 8/8/2019 Marina Casablanca Quotation 7 (13 05 09)

    11/15

    5. Total Quotation A+B: Formwork for 800+1.200 mand Support System (1+2,5) with E-4 System.

    Ref. Description Uts.Price Total

    /ud

    E-4 Grid Formwork+Coffers+Wood 1.200 m

    1001546 Cross beam 2200 (E-4) 856 29,78 25.491,68

    2016479 Cross beam 3450 (E-4) 81 44,53 3.606,932016218 Cross beam 2500 (E-4) 10 21,42 214,202016215 Cross beam 3750 (E-4) 52 31,40 1.632,80

    2016289 Cross beam support 4100 N-14 269 42,73 11.494,37

    2016478 Head (E-4) 897 4.18 3.704,61

    1001048 Wood board 820/758/27 1492 16,15 24.095,80

    1001142 Coffer 20 N-14 1750 50,56 88.480,00

    158.720,39

    E-4 Support System 2,5 x 1.200 m =3.000 m

    2016478 Head (E-4) 2243 4,18 9.263,59

    9.263,59

    Props

    1001251 4 meter Prop 5923 14,25 84.402,75

    84.402,75

    Extra materials for specific works

    2016436 Cross beam edges 1,00 m 113 8,50 960,50

    1001129 Assembly Tool 4 0,00960,50

    TOTAL EX-W. 253.347,23

    Price of 2.000 m2 of E4 formwork system with 20 cm N14 coffers + 5.000 m 2 of

    support system:

    EX-Works Torija (warehouse): 253.347, 23

    C/F Shipment Torija Casablanca: 20.000, 00

    ______

    TOTAL CIF 273.347, 23

    OFE0167492 11

  • 8/8/2019 Marina Casablanca Quotation 7 (13 05 09)

    12/15

    6. Repurchase Option

    6, 1 List of Materials that can be repurchased and repurchase price:

    Ref. Description Uts.Price Total

    /ud

    2016289 Cross beam support 4100 N-14 269 21,37 5.748,53

    1001142 Coffer 20 N-14 1750 25,28 44.240,00

    Materials must be returned within a maximum of 12 months.

    If they are missing, damaged or lost, they will be purchased at initial sale price.The customer will bear the returning cost of the materials to our warehouse together

    with taxes.

    6, 2 In the event SGTM wants to use the rest of the system for flat slabs, IN

    Sistemas proposes to replace the coffers and cross beam support 4100 N13 with thefollowing materials:

    Importe

    Cross beam 3450 E-4 81 81 0,00

    Cross beam 3750. 81 52 29 910,60

    Cross beam 2200 E-4 258 856 0,00

    Cross beam 2,50 M. 258 10 248 5.312,16

    Cross beam support 4060 M 160 160 7.384,00

    Cross beam support 3045 55 55 1.931,60

    Support 1970. E-4 1089 1089 15.942,96

    Support 970. E.4 180 180 1.222,20

    Header. E-4 339 3140 0,00

    Wood 1970 X 500 X 27 MM. 2015 2015 21.137,35

    Flat slab ( S = 2.015 m) 53.840,87

    Extra units

    requiredDescripcin

    Units

    required

    Units

    available on

    Marina

    This material will allow you to have 2 015 square meters of flat slab E-4 system.The cost is 53 840, 87 of which 49 988, 53 can be paid with the coffers and cross

    beam supports. SGTM will only have to purchase extra material valued at:

    3 852, 34

    in order to convert the current material to flat slab (1 to 2containers)

    OFE0167492 12

  • 8/8/2019 Marina Casablanca Quotation 7 (13 05 09)

    13/15

    7. General Conditions

    If the offer is of your interest, please sign a copy and have it sent back. We will then

    prepare a definite proposal in which the general conditions will be shown.

    Cost of IN Sistemas Material for Marina Project: 273.347,23 Current IN Sistemas Material: 97 640, 28

    Current IN Sistemas Material usable for Marina Project: 25 170, 63

    Materials Description Quantity

    Cross beam 2200 (E-4) 130

    Cross beam 3450 (E-4) 19

    Header Center 220

    Prop 4,00 mts. 1480

    Current IN Sistemas Material not needed for Marina Project: 69 947, 90

    Materials Description Quantity

    Cross beam 2500 (E-4) 154

    Cross beam 3750 (E-4) 36

    Cross beam support 4060 60

    Cross beam support 3045 68

    Support 1970 double distribution 696

    Support 970 36

    Support one way 378

    Wood 1,97 mts.1060

    Wood 0,97 mts. 362

    Prop 3,00 mts. 2594

    Prop 6,00 mts. 1390

    Payment terms:

    Transferable Letter of Credit due on delivery of material at Casablanca Portfor

    273.347,23 - 97 640, 28 = 175 706, 95

    The rest of IN sistemas Material (not required for Marina) will be handed back to INSistemas once the supplied system has been demonstrated and is working.

    OFE0167492 13

  • 8/8/2019 Marina Casablanca Quotation 7 (13 05 09)

    14/15

    The material to be handed back to IN Sistemas that is valued at 97 640, 28 and consists

    of:

    Materials Description Quantity

    Cross beam 2200 (E-4) 130

    Cross beam 3450 (E-4) 62

    Cross beam 2500 (E-4) 164

    Cross beam 3750 (E-4) 88

    Cross beam support 4060 60

    Cross beam support 3045 68

    Support 1970 double distribution 696

    Support 970 36

    Support one way 378

    Header Center 220

    Wood 1,97 mts. 1.060

    Wood 0,97 mts. 362

    Prop 3,00 mts. 2.594

    Prop 4,00 mts. 1.480

    Prop 6,00 mts. 1.390

    If any of these units are not handed back, they will be purchased (paid for) attheir original value.

    16 units of the cross beam support 4060 will be handed over to SGTM free of charge.

    These will be used on the triangular building according to plans (they will need a smallmodification.

    This offer is valid for 30 days.

    The mentioned Total C/F Price do not includes VAT.

    Lead Time: 3 weeks maximum to delivery at Casablanca Port (from receipt of PurchaseOrder)

    Best regards, Por Andamios In, S.A.

    Richard Walsh Tel: 609.471.511

    Int. Business Director

    OFE0167492 14

  • 8/8/2019 Marina Casablanca Quotation 7 (13 05 09)

    15/15

    Annex I : Details of System