Market Area Manager Panel, Vienna, 20/11/2012. Welcome!. Agenda. Update: Administration of Balance Groups Roadshows Balancing and Data Exchange Status Update Balancing Network Code Update Capacity platform Update Coordinated Network Development Plan 2012/2013 Agora - PowerPoint PPT Presentation

Citation preview

Page 1: Market Area Manager Panel, Vienna, 20/11/2012

Market Area Manager Panel, Vienna, 20/11/2012

Welcome!

Page 2: Market Area Manager Panel, Vienna, 20/11/2012

2

Agenda

- Update: Administration of Balance Groups

- Roadshows Balancing and Data Exchange

- Status Update Balancing Network Code

- Update Capacity platform

- Update Coordinated Network Development Plan 2012/2013

- Agora

- Implementation of the Market area manager’s duties – status quo and outlook

- Any other business • Next meeting

November 20th, 2012

Page 3: Market Area Manager Panel, Vienna, 20/11/2012

3

Update: Administration of Balance Groups

November 20th, 2012

Page 4: Market Area Manager Panel, Vienna, 20/11/2012

4

Administration of BG (1)

November 20th, 2012

0

10

20

30

40

50

60

70

80

90

82

3

Registration procedures 15/11/2012

Anträge insgesamtdavon abgeschlossene Registrierungen

Page 5: Market Area Manager Panel, Vienna, 20/11/2012

5

Administration of BG (2)

November 20th, 2012

Italie

n

Deutsc

hland

Österre

ich

Schweiz

Norweg

en

Tsche

chisc

he R

epub

lik

Großbri

tannie

n

Frankre

ich

Slowak

ische

Rep

ublik

Slowen

ien0

5

10

15

20

25

20

10

23

11

1 1

10

12

1

Page 6: Market Area Manager Panel, Vienna, 20/11/2012

6

Administration of BG (3)

November 20th, 2012

0

5

10

15

20

25

30

35

40

45

42

7

31

Contract types 15/11

FLFL+VGFL+VG+EKV

Page 7: Market Area Manager Panel, Vienna, 20/11/2012

7

Administration of BG (4)

November 20th, 2012

Bilanzkonten Subbilanzkonten0

10

20

30

40

50

60

70

80

72

8

Balance group / Sub balance accounts

Page 8: Market Area Manager Panel, Vienna, 20/11/2012

8

EIC-Administration (1)

 

15/11 

X-Codes international

18 Published: Entso-E

X-Codes national 9 Published: Gas Connect Austria

Y-Codes 106 Published: Gas Connect Austria

W-Codes 16 Published: Gas Connect Austria

Z-Codes 30 Published: Gas Connect Austria

Work in progress 3  

November 20th, 2012

Page 9: Market Area Manager Panel, Vienna, 20/11/2012

9

EIC-Adminstration (2) – rejections

  15/11

X-Codes international 6

Y-Codes national 4

X-Codes national 4

November 20th, 2012

Page 10: Market Area Manager Panel, Vienna, 20/11/2012

10

Road Show Ex-ante Balancing

November 20th, 2012

Page 11: Market Area Manager Panel, Vienna, 20/11/2012

11

Road Show Ex-ante Balancing

- Title of the road show: “Ex-ante Balancing and corresponding information provision in the Market Area East”.

- Held on October 3rd and 10th in Floridotower in German with simultaneous English translation

- ~ 80 participants per road show

-  Presentations held by GCA (in it’s role as MAM and TSO) and CEGH, moreover presence on panel (and Q&A) of BOG and TAG

- Overall feedback exclusively positive for road show on Oct 3rd, mostly positive for roadshow on Oct 10th

November 20th, 2012

Page 12: Market Area Manager Panel, Vienna, 20/11/2012

12

Status Balancing Network Code

November 20th, 2012

Page 13: Market Area Manager Panel, Vienna, 20/11/2012

13

Status Balancing Network Code

November 20th, 2012

 Date Content

28 September End of Stakeholder support process (SSP) on refined draft Network Code: mostly positive feedback from stakeholders

9 October ENTSOG Board approves final draft Network Code

25 October ENTSOG General Assembly approves of final draft Network Code

26 October ENTSOG submits Network Code to ACER and the EC

26 January Deadline for ACER to submit reasoned opinion to ENTSOG on Balancing Network Code

Page 14: Market Area Manager Panel, Vienna, 20/11/2012

Capacity platform – European Platform Initiative

Page 15: Market Area Manager Panel, Vienna, 20/11/2012

Capacity platform – European Platform Initiative (EPI) – Current Status and Next Steps Planned

16 October 2012 Introduction of Trac-X (EPI) regarding the functional and technical perspective including planned interfaces of the capacity platform

25 October 2012 Meeting of Management Board members of BOG, TAG and GCA with representatives of Trac-X (EPI)

Decision: All 3 Austrian TSOs intend to become shareholders from the first day

6 November 2012 Meeting of Trac-X with corresponding NRAs and TSOs presenting progress of EPI project

19 November 2012 Submission of the respective Governance-Documents by Trac-X (EPI)

4 December 2012 Conclusion of contracts regarding acquisition of shares in the new company

Page 16: Market Area Manager Panel, Vienna, 20/11/2012

16

Coordinated Network Development Plan 2012/2013

November 20th, 2012

Page 17: Market Area Manager Panel, Vienna, 20/11/2012

17

Coordinated NEP 2013 – 2022 Current Status and Next Steps Planned31 October 2012 Sending of the CNEP 2013 – 2022 by MAM to the

TSOs for submission to E-Control

09 November 2012 Publication of the Consultation Version of the CNEP 2013 – 2022 by E-Control

23 November 2012 - End of consultation phase- Publication of consultation responses online by E-Control

tbd Distribution of consultation responses to the respective TSO by MAM, with the request to submit the updated version of the NEP to MAM

tbd Incusion of updated NEPs in the CNEP 2013 – 2022 by MAM

tbd Sending of the updated CNEP 2013 – 2022 by MAM to the TSOs for submission to E-Control

November 20th, 2012

Page 18: Market Area Manager Panel, Vienna, 20/11/2012

18

Coordinated NEP 2014 – 2023 Ongoing Preparation

November 20th, 2012

Public Consultation“Szenariorahmen” for the German NEP-Gas 2013 @ BNetzA /Köln

• Request for including the congestion in Oberkappel in the NEP-Gas 2013

• Request for adapting the pressure for modelling the gas flows to Austria (Oberkappel) at least to the pressure agreed in the Pressure Support Agreement

Conference Renewable Energy @ Casineum Velden (KELAG)

• Current developments (increasing efficiency in electricity consumption vs. investments) in the Electricity Market should be reflected in the CNEP 2014 – 2023 in order to broaden the CNEP‘s perspective

Page 19: Market Area Manager Panel, Vienna, 20/11/2012

19

Agora

November 20th, 2012

Page 20: Market Area Manager Panel, Vienna, 20/11/2012

20

Capacity assignment § 170 GWG11

- Update AB RZF BGV V04 MG Ost: www.aggm.at Regelwerk Allg. Bedingungen des VGM

- Update key date

• Anmeldungstichtag: 30.11.2012• Zuteilungsstichtag: 7.12.2012

- Information• 19.11.2012 per e-mail

• 20.11.2012 per letter to BGV

November 20th, 2012

Page 21: Market Area Manager Panel, Vienna, 20/11/2012

21

Implementation of the Market area manager’s duties – status quo

November 20th, 2012

Page 22: Market Area Manager Panel, Vienna, 20/11/2012

22

Implementation – Status quo (1)Duties § 14 (1) Fulfilled?1. ensure the establishment of and non-discriminatory access to the virtual trading point and the designation of the operator of the virtual trading point in accordance with section 68, andcooperate with it;

• VTP: • Contract for cooperation:

WIP

2. manage the balance groups which are active in the market area; this includes, without limitation, informing market participants regarding the balance group system and balancing rules, assigning balance group IDs in cooperation with the clearing and settlement agent, organising the conclusion of the contracts required according to section 91 para. 2 item 1 on behalf and for account of the relevant contract parties in accordance with the market rules;

• Online platform – registration:

• EIC / local issuing office:

• Balancing management from 1/1/2013: WIP

3. coordinate system operation and the use of linepack as well as the use of physical balancing energy together with the market area’s distribution area manager, mainly via the virtual tradingpoint, with the aim to minimise the need for physical balancing energy by efficiently deploying control energy;

• Balancing management from 1/1/2013: WIP

November 20th, 2012

Page 23: Market Area Manager Panel, Vienna, 20/11/2012

23

Implementation – Status quo (2)

Duties § 14 (1) Fulfilled?4. establish a uniform methodology for the calculation and announcement of capacity at theentry/exit points of the market area’s transmission network pursuant to sections 34 and 35; themethodology shall be subject to approval by the regulatory authority. Changes shall be madeupon the request of the regulatory authority;

• Calculation model:

5. organise the establishment and operation of the online platform for offering capacity pursuant to section 39 and for publishing information about the market area pursuant to Regulation (EC)No 715/2009;

• European initiative: • Effective from 1/4/2013:

WIP

6. on the basis of a variety of load-flow scenarios and together with the transmission system operators and the distribution area manager, draw up a common forecast of the capacity need andutilisation in the market area’s transmission network over the next ten years;7. draw up a coordinated network development plan;

• Load flow scenarios: WIP

• KNDP:

November 20th, 2012

Page 24: Market Area Manager Panel, Vienna, 20/11/2012

24

Implementation – Status quo (3)

Duties § 14 (1) Fulfilled?8. coordinate measures to overcome physical congestions with the distribution area manager, the system operators and storage system operators in the market area;

• Measures: if required

• Contracts: WIP

9. enter into contracts on the exchange of data with the distribution area manager, the system operators, the balance responsible parties, the operator of the virtual trading point, the clearing and settlement agent and other market participants in line with the market rules;

• Contracts: WIP

10. submit its general terms and conditions to the regulatory authority for approval pursuant to section 16;

• GTC:

11. coordinate maintenance of the transmission and distribution network together with the distribution area manager pursuant to section 18 para. 1 item 28 such that the impact on system users is kept as small as possible;

• Measures: WIP• Contracts: WIP

November 20th, 2012

Page 25: Market Area Manager Panel, Vienna, 20/11/2012

25

Implementation – Status quo (4)

Duties § 14 (1) Fulfilled?12. determine and publish the calorific values for the market area, based on the data submitted by the system operators;

• Effective from 1/1/2013

• IT-solution: 13. coordinate the nomination procedure for the transmission system, including the exchange of nominations with the operator of the virtual trading point;

• Effective from 1/1/2013

• IT-solution: 14. organise the financial settlement of imbalance charges in the transmission network together with the operator of the virtual trading point and the transmission system operators.

• VTP organises the settlement:

November 20th, 2012

Page 26: Market Area Manager Panel, Vienna, 20/11/2012

26

Any other business

November 20th, 2012

Page 27: Market Area Manager Panel, Vienna, 20/11/2012

27

Any other business

- Next meeting: 19.3.2013, 1-3 p.m. , FLO 16.12

November 20th, 2012

Page 28: Market Area Manager Panel, Vienna, 20/11/2012

© 2012GAS CONNECT AUSTRIA GmbH