Upload
phamque
View
218
Download
2
Embed Size (px)
Citation preview
Market Performance and
Planning Forum
March 14, 2017
Last updated: March 15, 2017
Objective: Enable dialogue on implementation
planning and market performance issues
• Review key market performance topics
• Share updates to 2017 release plans, resulting from
stakeholders inputs
• Provide information on specific initiatives
–to support Market Participants in budget and
resource planning
• Focus on implementation planning; not on policy
• Clarify implementation timelines
• Discuss external impacts of implementation plans
• Launch joint implementation planning process
Page 2
Market Performance and Planning ForumAgenda – March 14, 2017
Time: Topic: Presenter:
10:00 – 10:05 Introduction, Agenda Kristina Osborne
10:05 – 10:20 - SDG&E Crosstrip Nomogram
- Peak RC Process Update
Dede Subakti
10:20 – 11:30 Market Performance and Quality Update Guillermo Bautista Alderete
Nancy Traweek
Amber Motley
11:30 – 12:00 Policy Update Brad Cooper
12:00 – 1:00 Lunch
1:00 – 1:30 Renewable generation market impacts Gabe Murtaugh
1:30 – 2:30 Release Update Adrienne Chiosea
Janet Morris
Slide 4
Dede Subakti
Director, Operations Engineering Services
SDG&E Crosstrip Nomogram
Background
• High East-West flow on 500 kV lines into Southern California system
• Contingency of TL50001 could cause overload in the underlying
parallel 230kV lines that would cause RAS to cross trip and open up
another 230kV line
• Objective of the mitigation is to avoid overload in the underlying
parallel 230kV lines and avoid cross tripping.
• Mitigation: nomogram 7820_TL23040_IV_SPS_NG
Page 5
Nomogram definition
• Nomogram definition is posted in CMRI
• The nomogram definition takes into account expected
RAS actions
– Note: Specific RAS information cannot be made public due to
the nature of the data classification
• Objective of the nomogram is to avoid overload in the
underlying parallel 230kV lines and avoid cross tripping
• Limit may be conformed up and down based on the real
time limit based on the real time condition and availability
of RAS
Page 6
Slide 7
Peak RC Process Update
Two New Processes Effective April 1, 2017
• New RC wide outage coordination process to meet the
new NERC IRO-017 Reliability Standard
• New RC System Operating Limit (SOL) methodology to
meet the spirit of the new NERC TOP/IRO Reliability
Standard
Page 8
Impact of IRO-017
• CAISO has filed modification to Section 9 of its Tariff and
the BPM for Outage Management is updated
• Every BES equipment outage requires RC’s
approval/confirmation
– webOMS is updated accordingly to show the RC’s
approval/confirmation
Page 9
Impact of New SOL Methodology
• It impacts how CAISO calculate System Operating Limit
• Excerpt from the new methodologyWECC Paths do not have single uniquely monitored SOLs unless the WECC
Path is associated with an established transient or voltage stability limit;
however, WECC Paths that are associated with scheduling will continue to have
TTCs
...
This SOL Methodology does not recognize WECC Path Ratings as SOLs.
WECC Path Ratings are determined in the planning horizon per the voluntary
WECC three-phase rating process. As stated earlier, this SOL Methodology
recognizes SOLs to be the Facility Ratings, System Voltage Limits and stability
limitations used in operations. If a WECC Path Rating is determined to be
“stability limited” per the WECC three-phase rating process, this information can
be used by TOPs and the RC to perform further analysis to determine if a
stability limit should be established for use in the Operations Horizon; however,
the “stability limited” WECC Path Rating itself is not automatically
considered as a stability limit (SOL) for use in the Operations Horizon
Page 10
Impact of New SOL Methodology
• Excerpt from the new methodologyWhile Peak will continue to monitor WECC Path flow relative to WECC Path
TTC values for situational awareness purposes, Peak does not acknowledge the
TTC as a SOL and does not require operation within TTC values or WECC Path
Ratings. Peak monitors the entire BES for SOL exceedance (as described in the
SOL Methodology) and implements Operating Plans as required to address
instances of SOL exceedances as determined by RTAs
Nomograms may be used to provide System Operators with helpful guidance as
part of an Operating Plan; however, they are not considered to be SOLs unless
the nomogram represents a region of stability (i.e., the nomogram defines a
stability limit).
Page 11
Impact of New SOL Methodology
• Nomogram naming convention are going to changed
• Since they are not considered SOL, the name SOL will
be taken out of nomogram that are non-stability related
• The new naming convention will utilize the term “Control
Point” (CP)
• Procedure:
– Control Point (CP): ####_CP#_NG
– Stability Limitation: ####_SOL#_NG
• Outage:
– OMS_#######_CP#_NG
– OMS_#######_SOL#_NG
Page 12
Market Performance and Quality Update
Guillermo Bautista Alderete, Ph.D.
Director, Market Analysis and Forecasting
Nancy Traweek
Executive Director, System Operations
Amber Motley
Manager, Short Term Forecasting
Slide 13
Over-Supply Update
Page 14
Page 15
ISO total monthly VERS schedules and forecasts
Page 16
IFM under-scheduling of solar generation
Page 17
IFM under-scheduling of wind generation
Monthly wind (VERS) downward flexibility in FMM
Page 18
Monthly solar (VERS) downward flexibility in FMM from
11 AM to 5 PM
Page 19
Page 20
Hydro production already higher than recent historical
production
Page 21
RTD renewable (VERS) curtailment trended upward since
last August
How are curtailments determined?
• Priority on real-time schedule types are managed based
on synchronized relaxation parameters that are listed in
BPM
• If economic bids are exhausted self-schedules may be
curtailed pursuant to priority
• Any self-schedule curtailment based relaxation
parameter is communicated through ADS
Page 22TOR/ETC
IFM self schedule
RMT
Price taker
PBC violation
Economical bids
Frequency of negative system prices has steadily
increased year over year
Page 23
0%
2%
4%
6%
8%
10%
12%
14%
16%
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Freq
uen
cy
2014 2015 2016 2017
Distribution of negative prices have shifted from early
morning hours to midday hours*
Page 24
0%
5%
10%
15%
20%
25%
30%
35%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Freq
uen
cy
2014 2015 2016 2017
* Metric of 2017 may be over-estimated since it includes only January and February.
Page 25
Hydro production is trending higher for Spring
Page 26
Self schedules in the real-time market remain high
Transfer from the ISO to other EIM areas has
increased
Page 27
Last updated: March 15, 2017
0
50
100
150
200
250
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Ave
rage
Tra
nsf
er (
MW
)
2016 2017
The gross volume of transfers out of the ISO BAA
occurs during midday hours
Page 28
Last updated: March 15, 2017
0
50
100
150
200
250
300
350
400
450
500
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Tran
sfer
(M
W)
2016 2017
The maximum transfer from the ISO to other BAAs in
in 2017 have been the highest
Page 29
Last updated: March 15, 2017
0
500
1000
1500
2000
2500
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Max
imu
m T
ran
sfer
(M
W)
2016 2017
Load profile in Spring sets conditions for oversupply
Page 30
Last updated: March 15, 2017
15,000
20,000
25,000
30,000
35,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
(MW
)
March 2016
Net Gross
15,000
20,000
25,000
30,000
35,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
(MW
)
April 2016
Net Gross
15,000
20,000
25,000
30,000
35,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
(MW
)
May 2016
Net Gross
15,000
20,000
25,000
30,000
35,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
(MW
)
June 2016
Net Gross
Gross versus Net Load in Spring 2016
Generation oversupply leading to potential
curtailments expected this Spring
• Real Time Operations is expecting significant oversupply
of generation this spring due to load system demand,
exceptional hydro condition, increases solar and wind
production.
• Generation that is not scheduled in the Day Ahead
Market will impact Real Time operations leading to
potential self scheduled generation curtailments
• Identifying oversupply indicators in the D+2 and D+1
timeframe to provide MPs advanced notice of low
demand and oversupply conditions
• Operators will manage real time conditions in
accordance with Overgeneration procedure 2390
Slide 31
Very short term forecast of potential oversupply
Page 32
Last updated: March 15, 2017
Oversupply Risk
Net Load
< 20,000 MW
VER Forecast
> 5,000 MW
Cloud Cover Forecast
Wind Speed Forecast
Load Forecast < 25,000 MW
Temperature Forecast
Hydro Self Schedule
> 3,500MW
Current solar capacity is capable of increasing the risk of oversupply without factoring in wind or
hydro schedule
Using daily average numbers
Very short term forecast of potential oversupply
Page 33
Last updated: March 15, 2017
Oversupply Risk
Net Load
< 16,000 MW
VER Forecast
> 5,500 MW
Cloud Cover Forecast
Wind Speed Forecast
Load Forecast < 21,500 MW
Temperature Forecast
Hydro Self Schedule
> 4,000 MW
Current solar capacity is capable of increasing the risk of
oversupply without factoring in wind or hydro schedule
Using daily average numbers
Aliso Canyon Nomogram
SoCalGas issued natural gas curtailment watches this
winter.
• SoCalGas issued curtailment watches from January 23
through January 26 arising from cold temperatures and
forecasted high gas demand
• The CAISO implemented gas burn constraints in the
day-ahead and real-time markets to limit the gas burn by
electric generation in SCE and SDG&E areas
• SoCalGas withdrew gas from Aliso Canyon on January
24-25 to maintain gas pressures in its system
• No gas curtailments to date necessary
Slide 35
Additional safety measures for natural gas storage will
further constrain SoCalGas operations.
• Constraints at Aliso Canyon for withdraws or injections
this summer will likely continue
• On February 23, 2017 SoCalGas posted a notice
outlining a Storage Safety Enhancement Plan
• Beginning March 1, SoCalGas will implement storage
enhanced safety measures at La Goleta, Playa del Rey
and Honor Rancho
• SoCalGas forecasts reductions in the maximum
withdrawal capabilities at these gas storage facilities
Slide 36
Gas conditions in the market were managed using gas
nomograms
• The ISO enforced two gas nomograms during the
curtailment watches.
MAXBURN_ALISO_SDGE and
MAXBURN_ALISO_TOTAL
• Shadow prices posted on OASIS
• Pricing locations do not reflect the shadow prices of the
gas nomograms
Shadow Prices of MAXBURN_ALISO_SDGE Nomogram
show instances where the nomogram had to be relaxed
Shadow Prices of MAXBURN_ALISO_TOTAL show
constraint relaxation in some instances
Compare RTD, IFM and RUC Gas Burn for all gas
resources (fuel provided by SoCalGas)
Date RTD (Mmcfd) IFM (Mmcfd) RUC (Mmcfd)
1/23/2017 410 427 501
1/24/2017 441 448 507
1/25/2017 446 455 484
1/26/2017 458 428 486
Comparison among IFM, RUC and RTD gas burns
Flexible Ramp Update
Flexible Ramp Product Up Requirement
Flexible Ramp Product Down Requirement
Flexible Ramp Product Up Awards
Flexible Ramp Product Down Awards
Most of the time the EIM area is binding.
Average Flexible Ramp Up Price ($/MWh)
Average Flexible Ramp Down Price ($/MWh)
Settlement of Flexible Ramp Product
• FMM Forecasted Movement Settlement = -1*FMM
forecasted movement quantity * (FMM FRU Price – FMM
FRD Price)
• RTD Forecasted Movement Settlement = -1*(RTD
forecasted movement quantity – FMM forecasted
movement quantity) * (RTD FRU Price – RTD FRD
Price)
• Allocation – Scheduling Coordinators with metered
demand (pro-rata share).
Forecasted Movement
Binding Advisory …
Forecasted Ramp
A A
Binding Advisory A
RTD Upward example 9:15 9:20 9:25 9:30
Run time
9:07.5 for 9:15
90 MW 100 MW 110 MW
…
Forecasted Movement = 100 – 90 = 10 MW (upward)
Settlement = -1*10 MW * ($20 (FRU) - $10 (FRD)) = -$100 (Payment)
Binding Advisory A
RTD downward example 9:15 9:20 9:25 9:30
Run time
9:07.5 for 9:15
90 MW 85 MW 75 MW
…
Forecasted Movement = 90 – 85 = 5 MW (downward)
Settlement = -1*5 MW * ($10(FRU) - $15 (FRD)) = $25 (Charge)
Forecasted Movement Settlement ISO – From
November 1 to February 28, 2017
Scheduled Settlement
Correction
Uncertainty Movement – Example
Binding Advisory
B A …
ARTD Run 1
RTD Run 2
9:15 9:20 9:25 9:30
Run time
9:07.5 for 9:15
Run time
9:12.5 for 9:20
90 MW 100 MW 110 MW
107 MW 113 MW
…
Uncertainty movement = 107 – 100 MW = 7 MW (upward)
Uncertainty Up Settlement has increased in recent
months
Once normalized for capacity procured, FRP
settlements in the same range as in prior months
FRP Up Uncertainty Payment Amount – Nov 1, 2016
to February 2017
FRP Down Uncertainty Payment Amount – Nov 1,
2016 to February 28, 2017
Flex Ramp Up Payment following hourly ramp profile
Flex Ramp Down Payment – Hourly Distribution
Market Update
Page 59
Last updated: March 15, 2017
Page 60
Good price convergence between FMM and RTD in February.
Page 61
RT prices lower than DA prices for both NP15 and SP 15 in
January and February.
Page 62
Insufficient upward ramping capacity in ISO stayed at low
levels since last November.
Page 63
Insufficient downward ramping capacity increased in
January and February.
Page 64
Congestion revenue rights market revenue inadequacy
without auction revenues.
Page 65
Congestion revenue rights market revenue sufficiency
including auction revenues.
Page 66
Exceptional dispatch volume in the ISO area remained low in
January and February.
Page 67
Daily exceptional dispatches by reason
Page 68
Real-time Bid cost recovery increased slightly in January
and February
Page 69
Bid cost recovery (BCR) by Local Capacity Requirement area
Page 70
Minimum online commitment (MOC)
Page 71
Pmax of MOC Cleared Units
Page 72
Enforcement of minimum online commitments in
November and December
MOC NameNumber (frequency) of hours in
January and February
Humboldt 7110 1397
MOC East Nicolaus 1128
Orange County 7630 383
DEVERS SOUTH MOC 68
MOC Devers South 35
MOC Drum 30
MOC SAN ONOFRE BUS 25
MOC Wise 4611490 15
MOC Pease 10
MOC Moss 4513897 10
SCIT MOC 9
SDGE 7820 All In Service 4
Page 73
Renewable (VERS) schedules including net virtual supply
and aligns with VER forecast in January and February
http://www.caiso.com/Pages/documentsbygroup.aspx?GroupID=EFF75C
2E-F28E-4087-B88B-8DFFAED828F8
Page 74
Hourly distribution of maximum RTD renewable (VERS)
curtailment in February
Page 75
ISO area RTIEO increased in January and February.
2016 2017 (YTD)
RTCO $50,468,470 $3,434,789
RTIEO -$3,797,744 $9,402,400
Total Offset $46,670,726 $12,837,189
Page 76
CAISO Price correction events increased in February
0
1
2
3
4
5
6
7
8
9
10Ja
n-1
6
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Feb
-17
Co
un
t o
f Ev
ents
Process Events Software Events Data Error Events Tariff Inconsistency
Page 77
EIM-Related Price correction events increased in February
0
2
4
6
8
10
12
14
16
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
2016 2017
Co
un
t o
f Ev
ents
Process Events Software Events Data Error Events Tariff Inconsistency
EIM Interruption in NV Energy balancing area
• 3/6/17 17:35 to 3/10/17 18:00 EIM Interruption in NVE
BAA declared due to planned transmission outage
resulting in split of NVE system
• Interruption declared to mitigate potential abnormal
conditions resulting from split of imbalance conditions
• During interruption EIM transfer to/from NVE were
limited while NVE maintained balance
• Posted prices are being reviewed and subject to
administrative pricing or price corrections.
EIM Price trends
Page 79
EIM transfers between BAAs*
Page 80
PAC
W
PAC
E
NEV
P
AZP
S
PSE
I
(304MW, 1230MW)
(123MW, 917MW)
(88MW, 300MW)
(24
4M
W, 9
63
MW
)
(93
MW
, 7
66
MW
)
(0MW, 0MW)
*Notation: (average, maximum)
Page 81
EIM BCR declined in February
Page 82
EIM Manual Dispatch increased in February
Day-ahead load forecast
0.0%
0.5%
1.0%
1.5%
2.0%
2.5%
3.0%Jan
Feb
Ma
r
Ap
r
Ma
y
Jun
Jul
Au
g
Se
p
Oct
No
v
De
c
2015 2016 2017
MA
PE
Day-ahead peak to peak forecast accuracy
0.0%
0.5%
1.0%
1.5%
2.0%
2.5%
3.0%
3.5%Jan
Fe
b
Ma
r
Ap
r
Ma
y
Jun
Jul
Au
g
Se
p
Oct
No
v
De
c
2015 2016 2017
MA
PE
Day-ahead wind forecast
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
7.0%
8.0%
9.0%
10.0%Jan
Fe
b
Ma
r
Ap
r
Ma
y
Jun
Jul
Au
g
Se
p
Oct
No
v
De
c
2015 2016 2017
MA
E
**In 2015-2016, Economic dispatches are not added back in to the generation data.
**The 2017 generation data used for accuracy calculation contains the economically dispatched MW.
Day-ahead solar forecast
0.0%
1.0%
2.0%
3.0%
4.0%
5.0%
6.0%
7.0%
8.0%
9.0%
10.0%Jan
Fe
b
Ma
r
Ap
r
Ma
y
Jun
Jul
Au
g
Se
p
Oct
No
v
De
c
2015 2016 2017
MA
E
**In 2015-2016, Economic dispatches are not added back in to the generation data.
**The 2017 generation data used for accuracy calculation contains the economically dispatched MW.
Real-time wind forecast
0.0%
0.5%
1.0%
1.5%
2.0%
2.5%
3.0%
3.5%
4.0%Jan
Fe
b
Ma
r
Ap
r
Ma
y
Jun
Jul
Au
g
Se
p
Oct
No
v
De
c
2015 2016 2017
MA
E
**2015-2016 represent the accuracy of the forecast made each hour at xx:55 for the following hour, i.e. the 5-65
minute ahead forecast. Economic dispatches are not added back in to the generation data.
**2017 has been changed to track the RTD accuracy, i.e. the forecast made 7.5 minutes before the binding
interval. The 2017 generation data used for accuracy calculation contains the economically dispatched MW.
**This forecast accuracy is pulled directly from the CAISO Forecasting System.
Real-time solar forecast
0%
1%
2%
3%
4%
5%
6%Jan
Fe
b
Ma
r
Ap
r
Ma
y
Jun
Jul
Au
g
Se
p
Oct
No
v
De
c
2015 2016 2017
MA
E
**2015-2016 represent the accuracy of the forecast made each hour at xx:55 for the following hour, i.e. the 5-65
minute ahead forecast. Economic dispatches are not added back in to the generation data.
**2017 has been changed to track the RTD accuracy, i.e. the forecast made 7.5 minutes before the binding
interval. The 2017 generation data used for accuracy calculation contains the economically dispatched MW.
**This forecast accuracy is pulled directly from the CAISO Forecasting System.
Policy Update
Brad Cooper
Manager, Market Design and Regulatory Policy
Page 89
Ongoing policy stakeholder initiatives
• Bid cost recovery enhancements
– Suspended due to FERC uplift allocation NOPR
• Stepped constraint parameters
– Closed initiative
– Will address changes to penalty prices appropriate for for increased
bid cap under FERC Order 831 separately
• Contingency modeling enhancements
- Fourth revised straw proposal including prototype results in late
March to early April
- July CAISO Board Meeting
Page 90
• Generator contingency and remedial action scheme
modeling
– Revised straw proposal posted March 15
– July EIM Governing Body and CAISO Board Meeting
• Energy storage and distributed energy resources (ESDER)
Phase 2
– Publish third revised straw proposal in April
– July CAISO Board meeting
– Publish ESDER Phase 3 issue paper in September
Page 91
Ongoing policy stakeholder initiatives (continued)
Ongoing policy stakeholder initiatives (continued)
• Commitment Costs and Default Energy Bid Enhancements
– Stakeholder workshops in late March and April
– Straw proposal in May
– September 2017 EIM Governing Board and CAISO Board
Meetings
• EIM Greenhouse Gas Enhancements
– Coordinating with ARB
– Developing approach to evaluate two-step model prior to
finalizing design
– Late 2017/early 2018 EIM Governing Board and CAISO Board
Meetings
Page 92
Ongoing policy stakeholder initiatives (continued)
• Flexible resource adequacy criteria and must-offer
obligation – phase 2
– Q1 2018 CAISO Board Meeting
– Q2 2018 FERC Filing
• Frequency response – phase 2
– Late March workshop
– 2018 CAISO Board Meeting
• Review Transmission Access Charge Structure
– Background white paper published in late March
– Publish issue paper first week of July
• Blackstart and system restoration phase 2
– Final draft proposal and stakeholder call in March
– May CAISO Board meeting with associated Tariff changes
Page 93
Policy stakeholder initiatives coming soon
• Planned to start in Q2 2017
– Resource adequacy enhancements
• Stakeholder engagement estimated in Q3
– Economic and maintenance outages
• Publish Issue paper in in April
– CRR auction efficiency
• Stakeholder working group on analysis in late March – early
April
– Management of EIM Imbalance Settlement for Bilateral
Schedule Changes
• Schedule TBD
– Risk-of-Retirement Process Enhancements
• Schedule TBD
Page 94
Renewable generation market impacts
Gabe Murtaugh
Senior Analyst, Monitoring and Reporting
Department of Market Monitoring
Page 95
Solar generation increased by almost 33
percent in 2016.
Page 96
0
5,000
10,000
15,000
20,000
25,000
Solar Wind Geothermal Biogas/Biomass
Ge
ne
rati
oin
(G
Wh
)
2013 2014 2015 2016
Prices mirrored net load patterns in 2016.
Page 97
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
$0
$10
$20
$30
$40
$50
$60
$70
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Ave
rag
e n
et
sys
tem
lo
ad
(M
W)
Pri
ce
($/M
Wh
)
Day-ahead 15-minute Average net load
As the ISO integrated more renewables,
prices have been negative more frequently.
Page 98
0%
1%
2%
3%
4%
5%
6%
2012 2013 2014 2015 2016
Pe
rce
nt
of
5-m
inu
te in
terv
als
Below -$145 -$145 to -$50 -$50 to $0
As more solar has been added, negative
price patterns have shifted.
Page 99
0%
2%
4%
6%
8%
10%
12%
14%
16%
18%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Pe
rce
nt
of
ne
ga
tive
5-m
inu
te i
nte
rva
ls
2012 2014 2016
Participants typically bid solar into the
market between -$25/MWh and $0/MWh.
Page 100
-1,500
-1,000
-500
0
500
1,000
1,500
2,000
2,500
3,000
below -$50 -$50 to -$25 -$25 to $0 $0 to $25 $25 to $50 above $50
Ave
rag
e h
ou
rly M
W
Natural Gas Hydro Geothermal Wind Solar Other
Despite more frequent negative prices,
curtailments decreased in 2016.
Page 101
0
500
1,000
1,500
2,000
2,500
3,000
3,500Ja
n
Fe
b
Ma
r
Apr
Ma
y
Ju
n
Ju
l
Aug
Sep
Oct
Nov
Dec
Ja
n
Fe
b
Ma
r
Apr
Ma
y
Ju
n
Ju
l
Aug
Sep
Oct
Nov
Dec
2015 2016
Se
lf s
ch
ed
ule
cu
rta
ilm
en
t M
Wh
Solar Wind Water Natural Gas Other Geothermal Nuclear
California exported energy to neighboring
EIM areas during midday hours in 2016.
Page 102
-200
-150
-100
-50
0
50
100
150
200
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Imp
ort
s in
to N
V E
ne
rgy (
MW
)
California ISO to NV Energy
Release Plan Update
Janet Morris
Director, Program Office
Page 103
Release Plan 2017
Page 104
Independent 2017
• Settlements Release - Spring 2017
• MRI-S ACL Groups + CPG Enhancements (formerly OMAR Replacement)
• Reactive Power Requirements and Financial Compensation
• Administrative Pricing Policy Update
• RIMS Functional Enhancements
Spring 2017 (4/1/17)
• Acceptable Use Policy – CMRI
• RTD Local Market Power Mitigation (LMPM) Enhancements
• CRR Clawback Modifications
• Forecasting & Data Transparency Improvements ( PIRP System Decommissioning)
• Metering Rules Enhancement
Fall 2017 (11/1/17)
• EIM Portland General Electric (PGE) – 10/1/17
• Bidding Rules Enhancements – Part B
• Reliability Services Initiative Phase 1B
• Reliability Services Initiative Phase 2
• Commitment Cost Enhancement Phase 3
• RM & EIM 2017 Enhancements
• Gas Burn Report
Release Plan – 2018 and subject to further planning
Page 105
Spring 2018
• EIM 2018 Idaho Power Company
Fall 2018 – tentative, subject to impact assessment
• Bid Cost Recovery Enhancements
• Generation Contingency and Remedial Action Scheme
• Flexible Resource Adequacy Criteria and Must-offer Obligation Phase 2
• Frequency Response Phase 2
• Contingency Modeling Enhancements
• Commitment Costs and Default Energy Bid Enhancements
• ADS User Interface Replacement
Spring 2019
• EIM 2019 Seattle City Light
• EIM 2019 Balancing Authority of Northern California (BANC)
Subject to further release planning:
• ESDER Phase 2
• Stepped Transmission Constraints
• Regional Resource Adequacy
• Regional Integration and EIM Greenhouse Gas Compliance
• Transmission Access Charge Options
Page 106
Settlements Release – Spring 2017
ISSUE SUMMARY BPM IMPACTED
Update configuration guide to compare the Balancing Authority Area Meter Load Quantity to the Balancing Authority Area Base Load Schedule instead of comparing Balancing Authority Area Meter Demand Quantity to Balancing Authority Area Base Load Scheduling when assessing Over and Under Scheduling EIM Settlement.
PRR 969: (CC 6045)
Update Pre-calculation RTM Net Amount to resolve two issues that relate to (1) the application of the Persistent Deviation Metric (PDM) and (2) the determination of BCR bid cost for a net-settled MSS.
PRR 970: (RTM Net Amount PC)
Settlement BPM and Charge Code updates for T+33M Settlement Statement implementation (Documentation Only)
PRR TBD: (CC 7989, CC 7999, Settlement Main Body BPM)
RAAIM - Flex Categories 2 and 3 Assessment Hour Updates (Documentation Only)
PRR 968: (RA Availability Incentive Mechanism PC)
Page 107
Settlements Release – Spring 2017
Milestone Date Status
Configuration Guides Posted February 10, 2017
DRAFT Configuration Output File Posted March 10, 2017
SAMPLE statement for trade date 3/8/2017 Published March 14, 2017
Pre-Production DRAFT Configuration Output File Posted March 20, 2017
Production Deployment March 27, 2017
FINAL Configuration Output File Posted March 27, 2017
2017 - MRI-S ACL Groups+ CPG Enhancements
Project Info Details/Date
Application Software Changes
The MRI-S metering (MRI-S) application cannot currently support ACL (Access Control
List) groups functionality for defining a subset of resources belonging to an SCID.
Enhancements to the Application Identity Management (AIM) application will enable the
use of ACL groups for SCID-level read-only access for MRI-S.
There will be no market simulation of AIM ACL groups but this functionality will be live in
production to support the MRI-S Metering CPG enhancements market simulation.
A customer partnership group will be scheduled to address the upcoming market sim.
BPM Changes None
Business Process ChangesPotential Level-II business process changes under –
• Manage Market & Reliability Data & Modeling
• Manage Operations Support & Settlements
Page 108
Milestone Type Milestone Name Dates Status
Board Approval Board Approval N/A
BPMs Business Practice Manuals N/A
External BRS Post External BRS Nov 14, 2016
Tariff Pre-Tariff Filing QRB N/A
Config Guides Configuration Guide N/A
Tech Spec Publish Tech Specs Nov 02, 2016
Market Simulation MRI-S Metering Enhancements Mar 13, 2017 - Apr 07, 2017
Production Activation Phase 1 – ACL Groups Mar 10, 2017
Phase 2 - MRI-S Metering Enhancements Apr 05, 2017
OMAR Decommissioning OMAR System Decommissioning (+4 month transition) July 14
MRI-S ACL Groups + CPG Enhancements
Page 109
* ACL group creation to filter for a read only role at the resource level is not currently available
# System Summary Status Estimated Fix
Date
1 MRI-S CIDI 183777, 183993 - MRI-S for Metering Limitation of
100,000 records.
In process See previous slide
2 MRI-S Option to choose UOM is missing on the UI
3 MRI-S CIDI 184018 - Time zone is missing on the UI
4 MRI-S CIDI 183777, 183993 - Modification to AUP policy on data
retrieval to include querying by last updated time
5 MRI-S Option to request for data in various time interval in UI
6 MRI-S Ability to view log files within the same organization
7 MRI-S Ability to provide SC ID in the data retrieve request
MRI-S *ACL Group – filter read-only at the resource level In process See previous slide
Per last fall’s Customer Partnership Group discussions, the ISO will be not be performing any
user access migration, including the current third party access in OMAR to AIM because:
• The platform and business logic for third party access are completely different between
OMAR and AIM, so no automation is possible
• Any effort by the ISO would be manual, and would require heavy market participant
involvement due to data integrity questions around security and third-party access
concerns
• The data in OMAR is historical (aged) and therefore must be vetted by the Scheduling
Coordinators to ensure its validity
2017 – Reactive Power Requirements and Financial Compensation Project Info Details/Date
Application Software Changes None
BPM Changes None
Business Process Changes
Develop Infrastructure (DI) (80001)
• Level II - Manage Generator Interconnection Process (GIP) (Logical Group):
Requirement for non-synchronous resources providing dynamic reactive power pursuant to FERC Order No. 827 to
employ an automatic voltage regulator system.
Page 110
Milestone Type Milestone Name Dates Status
Board Approval BOG Approval N/A
BPMs Post Draft BPM Changes N/A
External BRS Post External BRS N/A
Tariff File Tariff Dec 6, 2016
FERC Approval March 2, 2017
Configuration Guides Prepare Draft Configuration Guides N/A
Tech Spec Publish Tech Specs N/A
Market Sim Market Sim Window N/A
Production Activation Reactive Power Requirements and Financial Compensation
Mar 06, 2017
FERC approved filing subject to
refund and further FERC order
2017 – Administrative Pricing Policy Updates
Page 111
Project Info Details/Date
Application Software Changes
• MQS:
• Part 1 (used under normal market conditions): If there are less than 12 RTDs and 4
RTPDs missing – leverage existing process (last price used)
• Part 2 (used under normal market conditions): If RTD prices are available copy over
to RTPD; RTPD prices available copy over RTD. If neither RTPD or RTD prices are
available use DA prices
• Part 3 (used Market Suspension conditions): Use DA prices. If we don’t have DA
prices, revert to prior DA prices (awards and prices)
Business Process Change • Manage Markets and Grid
BPMs Market Instruments, Market Operations
Milestone Type Milestone Name Dates Status
Board Approval BOG Approval Dec 10, 2014
BPMs Post Draft BPM changes Mar 13, 2017
External BRS Post External BRS Mar 20, 2015
Tariff Tariff Approval Jan 30, 2017
Config Guides Prepare Draft Configuration Guides Dec 2, 2016
Tech Spec Publish Tech Specs N/A
Market Sim Market Sim Window N/A
Production Activation Administrative Pricing Policy Updates Apr 18, 2017 – no later than 5/16
2017 – RIMS Functional Enhancements
Project Info Details/Date Status
Application Software ChangesFunctional enhancements resulting from the Customer Partnership Group CPG.
More details to be provided in the future.
BPM Changes
Generator Interconnection and Deliverability Allocation Procedures
Generator Interconnection Procedures
Managing Full Network Model
Metering
Generator Management
Transmission Planning Process
Customer Partnership Group 10/16/15
Application and Study Webinar 3/31/16
Page 112
Milestone Type Milestone Name Dates Status
Board Approval Board approval not required N/A
BPMs Generator Interconnection and Delivery Allocation Apr 29, 2016
External BRS External BRS not Required N/A
Tariff No Tariff Required N/A
Tech Spec No Tech Specifications Required N/A
Production Activation Ph1 RIMS5 App & Study Mar 21, 2016
Production Activation Ph2 RIMS5 Queue Management, Transmission and Generation Dec 14, 2017
Spring 2017 Release – Overview
Page 113
Board Approval
BPMsExternal
BRSTariff
ConfigGuide
Tech Spec
Market Sim
Production Activation
Spring 2017 Release
Acceptable Use Policy - CMRI N/A N/A N/A N/A N/A N/A8/23/16 -9/23/16
4/1/17
RTD LMPM Enhancements 3/24/16 11/4/16 4/5/16FERC approved
effective date of4/1/17
N/A 4/14/162/7/17 -2/24/17 Target 4/18,
no later than 5/16
CRR Clawback Modifications 6/28/16 2/10/17 11/29/16FERC approved
effective date of4/1/17
N/A N/A N/A
Forecasting and Data Transparency Improvements (PIRP Decommissioning)
N/A 9/6/16 6/29/15 N/A N/A 4/15/163/21/17 -
4/4/174/5/17
Metering Rules Enhancement
12/14/16 2/2/17 N/AFiled with FERC
on 2/8/17N/A N/A N/A 4/10/17
COMPLETE
N/A
Spring 2017 – Acceptable Use Policy – CMRI
Project Info Details/Date
Application Software Changes
Scope includes enforcement of Acceptable Use Policy for CMRI
services to support the full implementation of 1 call per service per
identity (as designated by certificate) every 5 seconds. An error
code of 429 will be returned for any violation instance of the use
policy.
Page 114
Milestone Type Milestone Name Dates Status
Board Approval Board Approval N/A
BPMs BPMs N/A
External BRS External BRS N/A
Tariff Tariff N/A
Config Guides Config Guide N/A
Tech Spec Tech Spec N/A
Market Sim Market Sim Window Aug 23, 2016 - Sep 23, 2016
Production Activation Acceptable Use Policy - CMRI Apr 01, 2017
Spring 2017 - Real Time Dispatch Local Market Power Mitigation
Project Info Details/Date
Application Software Changes
• CMRI – Display mitigated bids from RTD process
• OASIS (Open Access Sametime Information System): Display RTD
reports for Market Clearing, the Pnode clearing, similar to current
RTPD reports
• RTM (Real Time Market)
• RTPD: Perform the LMPM run as an integral part of the binding
interval RTPD run
• RTD: Proposed mitigation in RTD run would work the same way
as the current RTPD run
BPM Changes
• Energy Imbalance Market (EIM): under the proposed RTD method,
bids are not necessarily mitigated for the whole hour
• RTD MPM will work the same way as the current RTPD MPM
Business Process Changes
• Manage Markets & Grid
• ATF – System Operations: Add MPM Application to Real Time and
annotate inputs and outputs
• ATF – System Operations, Real Time: Add MPM to diagram with inputs
and outputs
• Level II – Manage Real Time Operations – maintain balancing area
Page 115
Spring 2017 - Real Time Dispatch Local Market Power Mitigation
Page 116
Updated OASIS technical specifications 4.3.5
• http://www.caiso.com/Documents/OASIS-
InterfaceSpecification_v4_3_5Clean_Spring2017Release.pdf
• Updated the following MPM Services ( Spring 2017)
• Updated PRC_MPM_RTM_REF_BUS to add support for RTD LMPM.
• Updated PRC_MPM_RTM_NOMOGRAM_CMP to add support for RTD LMPM.
• Updated PRC_MPM_CNSTR_CMP to add support for RTD LMPM.
Milestone Type Milestone Name Dates Status
Board Approval Board of Governors (BOG) approval Mar 24, 2016
BPMs Posted Market Operations BPM PRR 945 Nov 04, 2016
External BRS Post External BRS Apr 05, 2016
Tariff Received FERC approval Nov 08, 2016
Received FERC approval for 4/1 Jan 27, 2017
File updated APR 1 deployment date Jan 13, 2017
Tech Spec Publish Technical Specification - OASIS Apr 08, 2016
Publish Technical Specification - CMRI Apr 14, 2016
Market Sim Market Sim Window Feb 06, 2017 - Feb 24, 2017
Production Activation RTD - Local Market Power Mitigation Enhancement Apr 18, 2017 – no later than 5/16
Spring 2017 – Congestion Revenue Rights (CRR) Clawback
Project Info Details/Date
Application Software Changes
MQS/CRR Clawback:
If import bid <= day-ahead price, then the import is not considered a virtual award.
If export bid >= day-ahead price, then the export is not considered a virtual award.
If an import/export bid/self-schedule in real-time market is less than the day-ahead
schedule, then the difference shall be still subject to CRR Clawback rule.
CRR Clawback rule should include convergence bids cleared on trading hubs and
load aggregation points in the flow impact used to determine if the 10% threshold
is reached.
Inform Market Participants of CRR annual allocation/auction for 2017.
BPM Changes Market Operations Appendix F
Business Process Changes TBD
Page 117
Milestone Type Milestone Name Dates Status
Board Approval Board of Governors Approval Jun 28, 2016
BPMs Posted Market Operations BPM PRR 972 Feb 10, 2017
External BRS Post External BRS Nov 29, 2016
Tariff File Tariff Jan 25, 2017
Tariff Receive FERC order Mar 7, 2017
Production Activation CRR Clawback Modification Apr 18, 2017 – no later than 5/16
Spring 2017 – Forecasting and Data Transparency
Improvements (PIRP System Decommissioning)
Project Info Details/Date
Application Software Changes:
PIRP/CMRI
• Forecast Data Reporting (resource-level) that was performed in PIRP will be done in
CMRI. Rolling Hour Ahead, Locked Hour Ahead, and Rolling Day-Ahead forecasts.
• PIRP Decommissioning to occur in 2017
• CMRI to receive the Electricity Price Index for each resource and publish it to the
Market Participants.
• 60 Day PIRP / CMRI parallel production to start when AIM/ACL becomes available.
BPM Changes CMRI Technical Specification; New APIs will be described.
Data Transparency
• Independent changes, won’t
impact existing services
• Will be made available in
Production and cutover
schedule is discretionary
Atlas Reference:
1. Price Correction Messages (ATL_PRC_CORR_MSG)
2. Scheduling Point Definition (ATL_SP)
3. BAA and Tie Definition (ATL_BAA_TIE)
4. Scheduling Point and Tie Definition (ATL_SP_TIE)
5. Intertie Constraint and Scheduling Point Mapping (ATL_ITC_SP)
6. Intertie Scheduling Limit and Tie Mapping (ATL_ISL_TIE)
Energy
• EIM Transfer Limits By Tie (ENE_EIM_TRANSFER_LIMITS_TIE)
• Wind and Solar Summary (ENE_WIND_SOLAR_SUMMARY)
Prices
• MPM Default Competitive Path Assessment List (PRC_MPM_DEFAULT_CMP)
Business Process Changes MPs will receive the VER reports from CMRI rather than PIRP.
Page 118
Spring 2017 – Forecasting and Data Transparency
Improvements (PIRP System Decommissioning)
Project Info Details/Date
User-Provisioning process for
CMRI in preparation of Market
Simulation and subsequently for
production
• Client Services will reach out to the User Access Administrator (UAA)
• Updated AIM User Guide, detailing how to create new ACL groups, was posted on
February 21, 2017 - The market notice was posted on February 23, 2017
• If a user is at the SC level, there is no need to provision ACL access
• Exceptions - (Non-SC Level Users) – provisioning via AIM will be required
• Provisioning will be required to be done prior to Market Simulation
• Provisioning for PIRP via AARF will discontinue on Feb 16, 2017 for Map Stage and
Mar 20, 2017 for Production.
• Participants should begin to download their PIRP data (all reports) as soon as possible
as the data will not be available after June 1, 2017
• PIRP application including all the UI and API reports will be decommissioned June 6,
2017
• If you have any questions please contact your client services representative
Page 119
Spring 2017 – Forecasting and Data Transparency
Improvements (PIRP System Decommissioning)
Page 120
Milestone Type Milestone Name Dates Status
Board Approval Board Approval N/A
BPMsPublish Draft Business Practice Manuals (Market Instruments;
PRR 936)Sep 06, 2016
External BRS External Business Requirements Jun 29, 2015
Tariff Tariff Filing Activities N/A
Config Guides Settlements Configuration N/A
Tech Spec Publish Technical Specifications (CMRI; Wind and Solar) Apr 15, 2016
Publish Technical Specifications (CMRI: PIRP
Decommissioning)Feb 05, 2016
Market Sim CMRI Reports; VER Forecast & EPI (Fall 2016 Release) Aug 23, 2016 - Sep 23, 2016
New Renewables CMRI reports and APIs Market Simulation Mar 21, 2017 - Apr 04, 2017
Production Activation CMRI Reports; VER Forecast & EPI (Fall 2016 Release) Oct 01, 2016
OASIS API Enhancements; 9 Reports Dec 20, 2016
New Renewables CMRI reports and APIs Production
DeploymentApr 05, 2017
PIRP Decommission PIRP System Decommissioning Jun 06, 2017
Spring 2017 – Metering Rules Enhancements
Project Info Details/Date
Application Software Changes N/A
BPM Changes
Metering
• Metering BPM will be updated to reflect the ISO ME vs SC ME role
options, changes to the metering entity election process, and impacts
for metering data access via the metering data submission portal.
• EIM BPM will be updated to explain Metering data reporting access
based on transitions from ISOME to SCME (shall transition to
submission of SQMD meter data to Metering Data submission portal) or
SCME to ISOME (shall be able to review historical meter data in MRI-S
when resource was SCME).
Definitions & Acronyms BPM Changes
• New Tariff and Business Process/System acronyms.
Business Process Changes
• Manage Transmission & Resource Implementation
• Manage Market & Reliability Data & Modeling (MMR) (80004)
• ISO Meter Certification (MMR LII)
• Metering Systems Access (Production) (MMR LII)
• Metering System Configuration for Market Resources (MMR
LII)
• Station Power Implementation (MMR LIII)
• Application Flow - Billing & Settlements
• Analyze Missing Measurement Report (MOS LIII)
• Manage Market Billing & Settlements (MOS LII)
• Manage Market Quality System (MOS LII)
• Manage Rules of Conduct (MOS LII)
• Meter Data Acquisition & Processing (MOS LII)
• SCME Self Audit (MOS LII)
Page 121
Spring 2017 – Metering Rules Enhancements
Page 122
Milestone Type Milestone Name Dates Status
Board Approval Board of Governors (BOG) approval Dec 14, 2016
BPMs Metering BPM Feb 02, 2017
Energy Imbalance Market BPM Feb 02, 2017
External BRS External Business Requirements N/A
Tariff Tariff Filing at FERC Feb 08, 2017
Config Guides N/A N/A
Tech Spec N/A N/A
Production Activation Metering Rules EnhancementsApr 10, 2017 upon FERC
approval
Fall 2017 Release – Overview
Page 123
Board Approval
BPMs External BRS Tariff Config Guide Tech Spec Market SimProduction Activation
Fall 2017 Release
EIM Portland General Electric N/A N/A N/A 8/31/17 N/A N/A6/6/17 -7/6/17
10/1/17
Bidding Rules Enhancements - Part B 3/25/16
6/15/17
1/13/17
6/1/17
6/27/17
4/3/17
8/8/17 -9/8/17
11/1/17
Reliability Services Initiative Phase 1B 5/12/15 12/23/16
Reliability Services Initiative Phase 2 10/27/16 1/31/17
Commitment Cost Enhancement Phase 3 3/25/16 1/6/17 TBD
RM & EIM 2017 Enhancements TBD TBD2/17/17
(Updates)7/31/17
Gas Burn Reports N/A N/A 7/29/16 N/A N/A N/A
COMPLETE
N/A
Fall 2017 – EIM Portland General Electric
Project Info Details/Date
Application Software Changes Implementation of Portland General Electric as an EIM Entity.
BPM ChangesEIM BPM will be updated to reflect new modeling scenarios identified
during PGE implementation and feedback from PGE.
Market Simulation
ISO promoted market network model including PGE area to non-
production system and allow PGE exchange data in advance of Market
Simulation.
Parallel Operations August 1 – September 30, 2017
Page 124
Milestone Type Milestone Name Dates Status
Tariff File Readiness Certification Aug 31, 2017
Market Sim Market Sim Window Jun 6, 2017 – Jul 6, 2017
Parallel Operations Parallel Operations Window Aug 1, 2017 – Sep 30, 2017
Production Activation EIM - Portland General Electric Oct 01, 2017
Fall 2017 - Bidding Rules Enhancements – Part B
Page 125
Project Info Details/Date
Application Software Changes
• MasterFile:
• Electric Region added to GRDT as non-modifiable
• OASIS:
• Publish fuel regions (public information)
Business Process Change• Manage Transmission & Resource Implementation
• Manage Entity & Resource Maintenance Updates
• Manage Full Network Model Maintenance
BPMs Market Instruments, Reliability Requirements
Milestone Type Milestone Name Dates Status
Board Approval BOG Approval Mar 25, 2016
BPMs Post Draft BPM changes Jun 15, 2017
External BRS Post External BRS Jan 13, 2017
Tariff File Tariff Jun 01, 2017
Config Guides Prepare Draft Configuration Guides June 27, 2017
Tech Spec Publish CMRI Tech Specs Apr 03, 2017
Market Sim Market Sim Window Aug 08, 2017 - Sep 08, 2017
Production Activation Bidding Rules Part B Nov 01, 2017
Fall 2017 - Reliability Services Initiative Phase 1BProject Info Details/Date Status
Application Software Changes
Developments under consideration include:
Scope:
• Redesign of Replacement Rule for System RA and Monthly RA Process.
• RA Process and Outage Rules for implementation for 2017 RA year.
• Scope not delivered in RSI Phase 1A (OASIS reporting),
Impacted Systems:
• CIRA
• OASIS
• Settlements
Business Process Changes Manage Market & Reliability Data & Modeling
Page 126
Milestone Type Milestone Name Dates Status
Board Approval Board Approval May 12, 2015
BPMs Post Draft BPM changes Jun 15, 2017
External BRS Post Updated External BRS v1.3 Mar 03, 2017
Tariff File Tariff Jun 01, 2017
Config Guides Config Guide June 27, 2017
Tech Spec Publish Technical Specifications Apr 03, 2017
Market Sim Market Sim Window Aug 08, 2017 - Sep 08, 2017
Production Activation Reliability Services Initiative Phase 1B Nov 01, 2017
Fall 2017 – Reliability Services Initiative Phase 2
Project Info Details/Date
Application Software Changes
CIRA:• Modifications to the RA and Supply Plan to show breakdown of local and system. Validation
rules need to be updated.
• Update planned/forced outage substitution rules
• Allow market participants to select how much system/local MWs to substitute.
• Modification of UI screens to accommodate system/local MW split.
• Enhance system to allow exemption from submission of RA Plans for LSE that have a RA
obligation < 1 MW for a given capacity product.
Settlements:• Splitting local from system in upstream RA system could potentially impact the RAAIM
calculation.
BPM Changes• Reliability Requirements: Changes to the monthly RA process
• Settlements and Billing
Business Process ChangesManage Market & Reliability Data & Modeling- Manage Monthly & Intra-Monthly Reliability Requirements
- Manage Yearly Reliability Requirements
Page 127
Fall 2017 – Reliability Services Initiative Phase 2
Page 128
Milestone Type Milestone Name Dates Status
Board Approval Board of Governor's Approval Oct 27, 2016
BPMs Post Draft BPM changes Jun 15, 2017
External BRS Post External BRS Jan 31, 2017
Tariff File Tariff Jun 01, 2017
Config Guides Config Guide June 27, 2017
Tech Spec Publish Technical Specifications Apr 03, 2017
Market Sim Market Sim Window Aug 08, 2017 - Sep 08, 2017
Production Activation Reliability Services Initiative Phase 2 Nov 01, 2017
Project Info Details/Date
Application Software Changes
Scope:
1. Clarify use-limited registration process and documentation to determine opportunity
costs
2. Each submission evaluated on a case-by-case basis to determine if the ISO can
calculate opportunity costs
• ISO calculated; Modeled limitation
• Market Participant calculated; Negotiated limitation
3. Enhanced definition of “use-limited” in response to FERC’s rejection of the proposed
definition in Cost Commitment Enhancements Phase 2
4. Change Nature of Work attributes (Outage cards)
1. Modify use-limited reached for RAAIM Treatment
2. Add new demand response nature of work attribute for RDRR and PDR
5. Market Characteristics
1. Maximum Daily Starts
2. Maximum MSG transitions
3. Ramp rates
Impacted Systems:
1. CIRA
2. CMRI
3. IFM/RTN
4. SIBR
5. MasterFile
6. OASIS
7. OMS
8. Settlements
BPM ChangesMarket Instruments, Outage Management, Reliability Requirement, Market Operations,
Settlements & Billing
Business Process ChangesLevel II – Manage Reliability Requirements
Level II – Manage Day Ahead Market
Page 129
Fall 2017 - Commitment Cost Enhancements Phase 3
Page 130
Fall 2017 - Commitment Cost Enhancements Phase 3 (cont.)
Milestone Type Milestone Name Dates Status
Board Approval Board of Governors (BOG) Approval Mar 25, 2016
BPMs Post Draft BPM changes Jun 15, 2017
Publish Final Business Practice Manuals TBD
External BRS Post External BRS Jan 06, 2016
Tariff File Tariff TBD
Receive FERC order TBD
Config Guides Config Guide June 27, 2017
Tech Spec Create ISO Interface Spec (Tech spec) Apr 03, 2017
Market Sim Market Sim Window Aug 08, 2017 – Sep 8, 2017
Production Activation Commitment Costs Phase 3 Nov 01, 2017
Fall 2017 – RM & EIM Enhancements 2017
Project Info Details/Date
Application Software Changes
Address enhancements identified by policy, operations, technology,
business and market participants.
The following requirements are being evaluated:
• EIM Entity access reports
• BAAOP provisioning in AIM
• EIM data report enhancements to support market participant and EIM
entity shadow settlements
• Shared BAA Resource Modeling
• Change to ETSR formulation to separate base energy transfer to
distinct non-optimizable ETSRs.
BPM Changes TBD
Business Process Changes TBD
Page 131
Page 132
Fall 2017 – RM & EIM Enhancements 2017 (cont.)
Milestone Type Milestone Name Dates Status
BPMs Draft BPM changes TBD
Post Draft BPM changes TBD
Publish Final Business Practice Manuals TBD
External BRS Post Updated External BRS to public site Feb 17, 2017
Tariff File Tariff Jul 31, 2017
Receive FERC order Nov 01, 2017
Config Guides Design review - BPM and Tariff SMEs TBD
Configuration Guides due June 27, 2017
Tech Spec Technical Specifications due Apr 03, 2017
Market Sim Market Sim Window Aug 08, 2017 - Sep 08, 2017
Production Activation EIM Enhancements 2017 Nov 01, 2017
Fall 2017 – Gas Burn Reports
Page 133
Project Info Details/Date
Application Software ChangesCMRI - implement ISO Market software functionality to calculate and present gas burn
estimates to gas companies serving electric generation located within the CAISO BAA
Business Process Change• Develop Infrastructure
• Manage Market & Reliability Data & Modeling
Milestone Type Milestone Name Dates Status
Board Approval BOG Approval N/A
BPMs Post Draft BPM changes N/A
External BRS External Business Requirements Jul 29, 2016
Tariff Receive FERC order N/A
Config Guides Prepare Draft Config Guide N/A
Tech Spec Publish Technical Specifications - CMRI Apr 03, 2017
Market Sim Market Sim Window N/A
Production Activation GenDB MF Consol and Gas Burn Report Nov 01, 2017
Spring 2018 – EIM Idaho Power Company
Project Info Details/Date
Application Software Changes Implementation of Idaho Power Company as an EIM Entity.
BPM Changes
EIM BPM will be updated if needed to reflect new modeling scenarios
identified during Idaho Power implementation and feedback from Idaho
Power.
Market Simulation
The ISO approved the Idaho Power network model and continues to make
progress integrating the Idaho model into the ISO non-production
environment in preparation for integration testing.
Parallel Operations February 1, 2018 – March 30, 2018
Page 134
Milestone Type Milestone Name Dates Status
Tariff File Readiness Certification Feb 28, 2018
Market Sim Market Sim Window Dec 01, 2017 - Jan 31, 2018
Parallel Operations Parallel Operations Window Feb 01, 2018 - Mar 30, 2018
Production Activation EIM - Idaho Power Apr 04, 2018
Short-Term Plan OASIS
OASIS API New Versions - Transition Schedule :
Market Simulation Testing : Available from 1/3/2017
Production Deployment – 2/2/2017
Production Transition Period : 2/02/2017 – 3/31/2017
Page 135
XML Report Name Market Run ID Group Name VersionTransition Period in
Production
After Transition Period(4/1/2017
onwards)
PRC_INTVL_LMP RTM RTM_LMP_GRP 1 Supported Not Supported/ Invalid Request
PRC_INTVL_LMP RTM RTM_LMP_GRP 2 Supported Not Supported/ Invalid Request
PRC_INTVL_LMP RTM RTM_LMP_GRP 3 Supported Supported
PRC_HASP_LMP HASP HASP_LMP_GRP 1 Supported Not Supported/ Invalid Request
PRC_HASP_LMP HASP HASP_LMP_GRP 2 Supported Not Supported/ Invalid Request
PRC_HASP_LMP HASP HASP_LMP_GRP 3 Supported Supported
PRC_RTPD_LMP RTPD RTPD_LMP_GRP 1 Supported Not Supported/ Invalid Request
PRC_RTPD_LMP RTPD RTPD_LMP_GRP 2 Supported Not Supported/ Invalid Request
PRC_RTPD_LMP RTPD RTPD_LMP_GRP 3 Supported Supported
PRC_SPTIE_LMP DAM,RTD,RTPD
DAM_SPTIE_LMP_GRP,
RTD_SPTIE_LMP_GRP,
RTPD_SPTIE_LMP_GRP 3 Supported Not Supported/ Invalid Request
PRC_SPTIE_LMP DAM,RTD,RTPD
DAM_SPTIE_LMP_GRP,
RTD_SPTIE_LMP_GRP,
RTPD_SPTIE_LMP_GRP 4 Supported Not Supported/ Invalid Request
PRC_SPTIE_LMP DAM,RTD,RTPD
DAM_SPTIE_LMP_GRP,
RTD_SPTIE_LMP_GRP,
RTPD_SPTIE_LMP_GRP 5 Supported Supported
Short-Term Plan OASIS
The updated OASIS Technical Specifications v4.3.3 include changes
noted below:
Page 136
API Report Name Existing Proposed Changes
PRC_INTVL_LMP- Changes apply
to Group Zip Only
One file with all price components within
the same zip file- LMP, Congestion ,
Energy, Loss and GHG
New Version -Separate file for each price
component within the same zip file - LMP,
Congestion , Energy, Loss and GHG
PRC_RTPD_LMP - Changes apply
to Group Zip Only
One file with all price components within
the same zip file- LMP, Congestion ,
Energy, Loss and GHG
New Version -Separate file for each price
component within the same zip file - LMP,
Congestion , Energy, Loss and GHG
PRC_HASP_LMP - Changes apply
to Group Zip Only
One file with all price components within
the same zip file- LMP, Congestion ,
Energy and Loss
New Version -Separate file for each price
component within the same zip file - LMP,
Congestion , Energy and Loss
PRC_SPTIE_LMP(DAM,RTD,RTPD)-
Changes apply to Group Zip only
One file with all price components within
the same zip file- LMP, Congestion ,
Energy, Loss and GHG
New Version - Separate file for each price
component within the same zip file - LMP,
Congestion , Energy, Loss and GHG
TRNS_CURR_USAGE
Request allows for past , current and
future trade dates
Existing Version - No change to current and future
trade dates . System will throw - "Invalid Request
Error" for requests with past trade dates.
TRNS_CURR_USAGE &
TRNS_USAGE
No restriction on number of transmission
id's requested in single zip.
Existing Version - System will throw error 1017
which is “Please select a maximum of 10 nodes or
use the ALL option.” when you are requesting data
for more than 10 transmission id's for single zip.
Short-Term Plan OASIS
OASIS API changes based on query type:
XML Report Name Market Run ID Version Query Type Response file
PRC_INTVL_LMP RTM 3 Single node
One file with all price components within the same zip file- LMP,
Congestion , Energy, Loss and GHG
PRC_INTVL_LMP RTM 3 ALL_APNODES
One file with all price components within the same zip file- LMP,
Congestion , Energy, Loss and GHG
PRC_INTVL_LMP RTM 3 ALL
Separate file for each price component within the same zip file -
LMP, Congestion , Energy, Loss and GHG
PRC_HASP_LMP HASP 3 Single node
One file with all price components within the same zip file- LMP,
Congestion , Energy, Loss and GHG
PRC_HASP_LMP HASP 3 ALL_APNODES
One file with all price components within the same zip file- LMP,
Congestion , Energy, Loss and GHG
PRC_HASP_LMP HASP 3 ALL
Separate file for each price component within the same zip file -
LMP, Congestion , Energy, Loss and GHG
PRC_RTPD_LMP RTPD 3 Single node
One file with all price components within the same zip file- LMP,
Congestion , Energy, Loss and GHG
PRC_RTPD_LMP RTPD 3 ALL_APNODES
One file with all price components within the same zip file- LMP,
Congestion , Energy, Loss and GHG
PRC_RTPD_LMP RTPD 3 ALL
Separate file for each price component within the same zip file -
LMP, Congestion , Energy, Loss and GHG
PRC_SPTIE_LMP DAM,RTD,RTPD 5 Single node
One file with all price components within the same zip file- LMP,
Congestion , Energy, Loss and GHG
PRC_SPTIE_LMP DAM,RTD,RTPD 5 ALL_APNODES
One file with all price components within the same zip file- LMP,
Congestion , Energy, Loss and GHG
PRC_SPTIE_LMP DAM,RTD,RTPD 5 ALL
Separate file for each price component within the same zip file -
LMP, Congestion , Energy, Loss and GHG
Page 137
ISO Daily Briefing
• A digest version of ISO market notices
• Distributed daily, Mon-Fri around 1:30 p.m. (PST)
• NEW: Upcoming Events - Every Thursday the briefing
will include stakeholder activities for the following week
• To subscribe to the Daily Briefing:
Go to www.caiso.com
Under “Stay Informed” tab
Select “Notifications”
Click under Market notices heading
Select Daily Briefing from the list of categories
Note: If you currently receive ISO market notices and you re-subscribe, the system will override your previous
category selections. If you still want to receive market notices in other categories, you’ll need to reselect those
categories of interest.
Page 138
Market Performance and Planning Forum
2017 Schedule
• May 16
• July 18
• September 19
• November 14
Questions or meeting topic suggestions:
Submit through CIDI - select the “Market Performance and
Planning Forum” category
Page 139