72
Insightrix Research Inc. | 1-3223 Millar Ave | Saskatoon, SK S7K 5Y3 P: (306) 657-5640 | E: [email protected] | W: insightrix.com November, 2014 AGRICULTURAL DRAINAGE POLICY RESEARCH

Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

Insightrix Research Inc. | 1-3223 Millar Ave | Saskatoon, SK S7K 5Y3

P: (306) 657-5640 | E: [email protected] | W: insightrix.com

November, 2014

AGRICULTURAL DRAINAGE POLICY RESEARCH

Page 2: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

i

EXECUTIVE SUMMARY

STUDY BACKGROUND

The Water Security Agency (WSA) has been tasked with leading delivery of the 25-Year Saskatchewan

Water Security Plan. A key element of this plan relates to the drainage of water on agricultural lands. To

collect input from stakeholders within the agricultural community, the WSA undertook an extensive public

engagement process. The WSA hired Insightrix Research to manage the public engagement process as it

relates to the drainage of water on agricultural lands.

Three significant activities were undertaken as part of this public engagement process:

1) the development of an online community for stakeholders to contribute their thoughts on specific

issues surrounding agricultural drainage

2) an in-person meeting with select online community members and WSA representatives

3) a telephone and online survey of stakeholders to measure support of proposed policy principles

The target audiences for this engagement process included farmers, local government representatives

(elected officials), representatives from non-governmental organizations (NGOs), Conservation and

Development Area Authorities (CAAs), Watershed Associations, and interested parties from the general

public. The scope of this study included Saskatchewan residents only. A total of 491 individuals joined the

online community which was active from October 2013 to April 2014. A total of eight individuals attended

the in-person session which was held in Saskatoon on February 6th

, 2014 and 480 individuals participated

in the quantitative survey which was in field between April 7th

and April 21st, 2014. Unless otherwise

specified, any data presented using percentages originates from the quantitative research study.

CURRENT LANDSCAPE

The quantitative research shows that most respondents (87%) support the act of draining water off of

agricultural land. Most farmers (78%) are impacted by agricultural drainage in some way and four in ten

farmers (40%) self-report engaging in such draining activities themselves (as high as 68% among

members of the online panel). Three in ten of those surveyed (28%) have been involved in a drainage

complaint.

More than one half (55%) of survey respondents feel the current agricultural drainage policy is not

effective and nearly nine in ten (87%) believe it is important for a new policy to be developed. This

suggests that most stakeholders are open to and are ready for a change.

Page 3: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

ii

POLICY COMPONENTS

Through the research, many specific topics regarding a new policy were addressed. A draft policy outline

prepared by the WSA was used as a guide for much of the engagement process. A summary of

stakeholder sentiments with respect to each of these components is outlined below:

Drainage Rights

Stakeholders largely agree that drainage is not a landowner right and if specific impacts cannot

be mitigated then drainage activities should not be allowed.

Project Risk

Stakeholders universally support tying regulations to the risk involved in a drainage activity, with

the most risky projects requiring greater scrutiny and public input through an online engagement

process. However, stakeholders find it difficult to pinpoint the exact factors that determine project

risk. Broad-level criteria identified include reasons for water buildup, volume of water being

released, how the release of water will be controlled, anticipated negative consequences of

releasing the water, cumulative effects of releasing the water, and the reasons why water is being

released in the first place. It is likely that the WSA will need to develop its own detailed criteria to

determine risk and create categories of risk that stakeholders will need to follow.

Stakeholders agree that projects deemed to be of high risk should require approval, while mixed

opinions exist with respect to low-risk projects. Roughly equal proportions believe low-risk

projects should require approval, simply be registered with the WSA, or be allowed to proceed

without notifying the government at all. Farmers are more likely to support the latter option than

are non-farmers (33% vs. 13%, respectively).

Enforcement of policy principles and approaches regardless of project size is strongly encouraged

by stakeholders.

Project Cost Responsibilities

Stakeholders largely support the philosophy that those who benefit from drainage projects

should bear the costs for building and maintaining such projects. Opinions differ somewhat with

respect to division of costs among all parties involved – ranging from everyone having an equal

share to prorating fees based on benefits received.

Further, there is strong support for project owners bearing the costs of damages they cause,

particularly with projects that are not approved and/or registered with the WSA. Special

circumstances are advised in cases of significant weather-related events such as flooding.

Existing Activities

Page 4: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

iii

A majority of stakeholders believe that existing works that have not been approved by the

government should either require approval or registration consistent with new projects within a

reasonable timeframe or should simply be registered with the government through an online

process. Very few believe existing non-approved projects should be allowed to continue without

any approval or registration.

Stakeholder-recommended considerations when evaluating existing activities that have not

caused negative impacts include ensuring farmers are not penalized for past drainage activities,

allowing such projects to continue operating while they are being reviewed/approved, allowing

farmers a reasonable amount of time to address any deficiencies noted during the

review/approval process, and providing resources to assist the farmer with meeting the

requirements for their existing projects.

Approval Criteria

Stakeholders are supportive of requiring applicants to follow specific design and operation

standards and rules. Further, they largely support project organizers being required to repair any

damages they may cause. Fewer, however, are supportive of having private, qualified

professionals approve drainage works.

Specific criteria that stakeholders deemed important in allowing drainage to proceed include

consideration of upstream and downstream impacts, impact on flow rates within the system,

erosion potential, short-term and long-term impact, evidence of affected parties working

together, and the ease and ability for the project to be monitored by an independent body.

Wetlands Management

Wetlands management is a sensitive topic with stakeholders. While many support the notion of

maintaining some wetlands, others are opposed to the notion. Specifically, the effort to farm

around potholes and larger wetlands that could be converted to farmland strikes at the heart of

one’s philosophy regarding land use. Farmers are less likely to support the notion of retaining all

wetlands as compared to non-farmers (57% agree vs. 73% agree, respectively).

Some farmers indicate they choose to forego farming land that is considered wetlands while

others feel that they should receive some form of incentive or compensation to retain the

wetlands and offset the opportunity cost of using the land for producing crops. There is also

some opposition to imposing rules requiring that certain amounts of wetlands be maintained.

In light of the diverging opinions, it is likely that building consensus will be difficult.

Certification and Education

Stakeholders frequently mention that education is essential to ensuring that farmers follow the

proper procedures and are aware of the risks and liabilities with conducting drainage activities.

Page 5: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

iv

As a case in point, only 44% of survey respondents are aware that all drainage activities currently

require provincial government approval.

Stakeholders expect the government to provide relevant reference materials to guide them

through new policy requirements. Some also appear open to attending in-person orientation

sessions.

The notion of certifying or licensing individuals to be allowed to conduct drainage activities was

met with mixed reviews. While some endorse the idea, likening it to obtaining a driver’s licence

prior to operating a vehicle, others feel that landowner behaviour may not change regardless of

the implementation of a licensing system.

It is believed that a licensing system would be most effective if the WSA or another agency

actively enforce the system. Others also anticipate a licensing system could prove costly and yield

only a marginal benefit.

Despite the above opinions, modest support for fast-tracking approvals of low-risk projects for

those who are licensed is noted.

Local Water Boards

During the online and in-person discussions, it was suggested that local bodies, termed “water

boards” by these stakeholders, be created to deal with localized drainage issues. Several benefits

for this type of autonomous organization were cited including knowledge of local terrain and

watersheds, the ability to administer local policies (such as approval and compliance), and faster

decision-making.

However, several disadvantages were also noted including lack of knowledge about drainage, lack

of qualified representatives to sit on the board, local conflicts of interest, potential duplication

with existing organizations, and more red tape.

While many see merit in the local water board concept, further thought and investigation are

advised before pursuing the idea.

Management of Areas with Extensive Drainage

In areas with extensive drainage issues, there is broad-level support for government intervention

to require the formation of organized drainage authorities. However, there are also strong

advocates who oppose any form of forced government intervention. Specifically, farmers are less

likely to support the notion of preventing any new drainage in these areas until such an

organization is formed, regardless of whether it is formed voluntarily or through government

intervention than are non-farmers (52% vs. 64%, respectively).

As such, the forced formation of organized drainage authorities could become very contentious in

the area affected.

Page 6: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

v

Control Gates as a Requirement of Drainage

When presented with the notion of requiring project applicants to commit to installing control

gates as a requirement of approval for drainage activities, modest opposition was noted. The

primary concern is that control gates may not be the most effective control mechanism in every

region of the province.

Compliance and Enforcement

Calls for increased compliance and enforcement consistently arose throughout all phases of

research. Many stakeholders feel that increased efforts in this area can help reduce the frequency

of non-approved drainage and negative impacts. Commonly, individuals call for increased fines,

faster responses to complaints, such as closure of works, and faster resolution of disputes.

Stakeholders are divided on the use of a complaint-based system versus proactive enforcement

by the WSA. Farmers are more in favour of a complaint-based system (57%) while non-farmers

would prefer proactive enforcement (56%).

While opinions are divided in the compliance model used, most stakeholders support granting

the WSA powers to impose penalties, voluntary payments, notices of violation, stop work orders,

orders for closure of works, and orders for remedial action related to agricultural drainage.

With respect to a process for resolving disputes, stakeholders commonly recommend progressive

steps beginning with encouraging the affected parties to resolve the issue on their own,

mediation, and then arbitration by an independent third party.

Stakeholders are highly supportive of immediate closure of disputed works in cases where the

project has not received prior approval or registration. This was seen as a step to help motivate

farmers to register their existing works given that if a complaint is ever lodged, their project could

be shut down immediately.

Land Control Options

Stakeholders are divided with respect to land control options within a new policy regime. Many

support the notion of allowing the affected parties to strike a legal agreement regarding their

mutual drainage activities but a modest proportion feel the current registration of an easement

approach is best. The remaining minority feel it is appropriate to allow proponents to proceed

with their drainage activities without any formal agreement, as long as they are advised of the

risks in doing so.

Additional Resources

Repeatedly through the engagement process, stakeholders reported that there is an absence of

current and detailed mapping and topographical information to assist landowners, Conservation

Area Authorities (CAAs), the WSA, and other parties in planning and managing drainage.

Page 7: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

vi

Acknowledging there are costs, many stakeholders believe it is important for the province to

invest in these areas to provide more tools to manage drainage.

Some stakeholders advise the WSA to consult with neighbouring provinces regarding their water

management practices in addition to leading-edge European countries such as the Netherlands.

Finally, it is clear that stakeholders believe the WSA is currently understaffed to effectively

manage the current policy or the new policy when it is developed.

Page 8: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

vii

POLICY SUMMARY

The following table broadly summarizes policy concepts that were met with common agreement

(generally a majority supporting) and concepts without common agreement (either no agreement or

diverging opinions).

Policy concepts with common agreement Policy concepts without common agreement

Drainage is not a Right

If impacts can’t be mitigated, drainage should not be allowed

Proponents must be educated on best management practices around

drainage

Regulation should be tied to risk with high risk projects undergoing

more scrutiny

Specific definition of risk

Low risk projects – approval vs. registration only

Those who benefit from drainage should bear the costs of appropriate

design and management, including damage prevention and mitigation

Where drainage is allowed, drainage projects should align with

hydrological and environmental targets that reflect both local

circumstances and provincial objectives

Defining the specific targets

Approval criteria should be established Specific criteria that should be included

Existing drainage works should be addressed using the same criteria as

new projects Approval vs. registration for existing works

Wetlands should be addressed in the policy Strong opposing views on how it should be addressed

Inclusion of certification / licencing

The development of water boards

Forced compliance in areas of significant drainage issues Despite majority support, strong opposition may lead to

contention if implemented

Requiring control gates as a requirement of drainage approval

The regulatory process should remain distinct from any process related

to assessment of damages

Regulatory requirements should be put in place to minimize non-

compliance

Method of compliance administration (complaint-based vs.

proactive)

WSA having enforcement powers to address non-compliance

Parties claiming damages as a result of drainage should have adequate

access to resolution and compensation. Direct costs of the process

should be reasonably assessed to the party causing the impact

The responsibility for land control and civil liability for impacts rests

solely with project owners

Requiring the registration of an easement on title vs. legal

agreement vs. non-legal agreement

Public consultation before approval of high risk projects

Page 9: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

viii

CONCLUSIONS

There is broad agreement with the principles and approaches that it intends to incorporate into a new

agricultural drainage policy. However, there are several unique situations throughout Saskatchewan

which means the implementation of a broad policy will most likely result in cases where the overall rule

“may not apply” or apply well in every case. Further, there are a number of stakeholders who hold very

strong opinions about their land entitlement. In addition, poor neighbour relations and poor experiences

under the existing policy will likely result in not everyone being pleased with the outcomes of a new

policy. The key will be for the WSA to take a leadership role in determining what is in the best interest for

all stakeholders while at the same time applying some flexibility for the special cases that may arise. Once

a detailed draft policy is developed, there may be value in collecting feedback from this stakeholder

group, similar to the approach used during the in person session in February. In some areas there are

differences between farmers and non-farmers; however in most cases these differences are relatively

minor.

Page 10: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

TABLE OF CONTENTS

EXECUTIVE SUMMARY _____________________________________________________________________________ i

STUDY BACKGROUND _____________________________________________________________________________ 1

INTRODUCTION_______________________________________________________________________________ 1

METHODOLOGY ______________________________________________________________________________ 1

STUDY FINDINGS __________________________________________________________________________________ 8

CURRENT LANDSCAPE _________________________________________________________________________ 8

PERCEIVED NEED FOR A NEW AGRICULTURAL DRAINAGE POLICY ________________________________ 13

NEW POLICY PRINCIPLES ____________________________________________________________________ 18

POLICY APPROACHES _______________________________________________________________________ 24

APPENDIX I – ONLINE DISCUSSION TOPICS _____________________________________________________ 46

APPENDIX II – IN-PERSON MEETING MATERIALS _______________________________________________ 49

APPENDIX III – QUESTIONNAIRE ________________________________________________________________ 52

Page 11: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

1

STUDY BACKGROUND

INTRODUCTION

The Water Security Agency (WSA) has been tasked with leading delivery of the 25-Year Saskatchewan

Water Security Plan. A key element of this plan relates to the drainage of water on agricultural lands. To

collect input from stakeholders within the agricultural community, the WSA undertook an extensive public

engagement process. The WSA hired Insightrix Research to manage the public engagement process as it

relates to the drainage of water on agricultural lands.

Three significant activities were undertaken as part of this public engagement process:

1) the development of an online community for stakeholders to contribute their thoughts on specific

issues surrounding agricultural drainage

2) an in-person meeting with select online community members and WSA representatives

3) a telephone and online survey of stakeholders to measure support of proposed policy principles

This report documents the findings of these three phases of research. Due to the interrelated nature of

the topics discussed within each phase of research, the findings from all three phases have been

combined and are reported together.

METHODOLOGY

The target audiences for this engagement process included farmers, local government representatives

(elected officials), representatives from non-governmental organizations (NGOs), Conservation and

Development Area Authorities (CAAs), Watershed Associations, and interested parties from the general

public. The scope of this study included Saskatchewan residents only. The following section outlines how

the three phases of research were conducted.

ONLINE COMMUNITY

Overview

Insightrix developed an online community to collect feedback from interested stakeholders. Insightrix has

developed a proprietary software program that supports an online community for research purposes.

Stakeholders were encouraged to join the online community and offer their comments on issues and

questions posted by Insightrix moderators regarding the topic of agricultural drainage. WSA

representatives had viewer access to the discussions, but they were not able post comments and they

were not visible to community members. Members of the community were able to choose a display name

that differed from their actual name to maintain anonymity. When recruited, members were asked to log

into the online community roughly two to three times per week, for an estimated total time of one hour

per week. The community was active from October 2013 to April 2014.

Page 12: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

2

Online Community Login Page

Recruitment

An extensive recruitment campaign was undertaken to ensure a broad mix of stakeholders was invited to

participate in the online community. The following recruitment steps were undertaken:

- mail drop to over 40,000 rural households

- print ads and online ads with farmer-related publications (Western Producer, Grainnews, etc.)

- promotion by WSA representatives and WSA Minister Ken Cheveldayoff at relevant events such as

SUMA and SARM meetings

- on-air promotion with radio interviewers/radio programs

- referrals from existing online community panel members

- telephone recruitment by Insightrix

The original goal for the online community size was 1,500 individuals. Despite the significant recruitment

efforts outlined above, there was less interest in joining the online community than anticipated. Feedback

from potential panel members during the telephone recruitment phase identified the following barriers to

participating in the community:

- lack of comfort with technology

- anticipated time commitment to be part of the panel

- Internet connectivity issues

- reluctance to join due to anonymity issues (despite being able to use a display name)

- lack of concern over agricultural drainage

Page 13: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

3

In the end, 491 individuals joined the online community. The distribution of these individuals by type is

outlined below.* Note that no representatives from the provincial or federal government were part of this

panel, nor did members of the WSA participate in the online discussions. Local government

representatives include elected officials within municipal government bodies.

* Note that the list was a “select all that apply” and as such, several individuals stated they were a member of the general public in addition to being a

member of another group. Therefore, these proportions add up to more than 100%.

Despite a smaller panel size than initially anticipated, the community was lively and had a great deal of

discussion on most topics. Overall, more than 2,000 posts were logged in the online community over the

seven months that it was active.

Process of Joining the Community

The process for joining the online community consisted of two steps. First, potential panel members were

directed to visit the website agdrainage.insightrix.com. This home page included both a log in section as

well as a “join’’ button. New users would click on the join button and be directed to enter their name and

email address. Once complete, an automated email message was sent to them from the online

community software. Potential members were required to open this email and click on an activation link

to confirm their membership in the community. Following this, new members were prompted to

complete a short profile survey prior to being able to view and participate in discussion forms.

Discussions

Insightrix worked closely with the WSA to develop a number of discussion topics to collect feedback from

panel members. Topics ranged from requesting broad-level input on agricultural drainage to specific

68%

13%

5%

7%

41%

Farmer / primary producer

Local government representative

Community organization or NGO

Conservation and Development Area Authority orWatershed Association

Member of the public

Page 14: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

4

feedback on potential policy items. A complete list of the discussion topics asked of members can be

found in Appendix I.

Example Discussion

The specific functionality available to members within the discussions included

- replying to others’ posts

- liking or disliking someone’s post

- sending a private message to the moderator or to another panel member

- reporting a comment as abusive

Further, panel members would receive an email message if

- a new discussion topic was posted to the online community

- someone replied to one of their posts

- someone sent them a private message

Interpretation of Findings

Findings from the online community should be considered qualitative in nature. Similar to reporting of

other qualitative research such as focus groups, common themes brought forward are highlighted

throughout this report. In addition any ideas or suggestions brought forward by members that were

openly embraced or discussed at length by other members is also included in the report. This means that

the findings from this phase of research may not be representative of opinions among all stakeholders.

Page 15: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

5

However, cases where sentiments identified within the online community align with the quantitative

research findings suggest that such beliefs are commonplace among stakeholders in general.

IN-PERSON MEETING

Given the complexity and interrelatedness of the issues surrounding agricultural drainage, the discussion

topics within the online community became broad and wide-ranging. While valuable information was still

being collected through the online community, the value of having an in-person meeting with a handful

of individuals was quickly identified, as it would enable more focused and detailed discussion of specific

issues and aspects of agricultural drainage.

To meet this need, Insightrix selected a mix of online community members who were most active in the

online discussions yet also represented differing viewpoints. Further, efforts were taken to ensure a mix of

individuals was recruited based on geographic regions and regional drainage-related challenges.

The in-person session was held in Saskatoon on February 6, 2014. There were eight participants from the

online community in attendance at the day-long session, as well as two representatives from the WSA.

The session was moderated by an Insightrix researcher. Several additional WSA, other government

officials and Insightrix staff members attended but did not participate in the discussion.

Topics covered in the session were based on the draft policy that the WSA had developed and included

- proposed policy principles

- proposed policy approaches

- proposed policy outcomes

- additional considerations from the panel

A copy of the materials that was distributed to in-person session participants in advance of the meeting is

included in Appendix II.

ONLINE AND TELEPHONE SURVEY

While the online community provided valuable qualitative feedback regarding agricultural drainage issues

and policy components, a quantitative assessment of support and opposition for proposed policy

elements was necessary. As such, the final step in the stakeholder engagement involved the

administration of a questionnaire. Originally, the plan was to conduct this survey with online panel

members. However, because fewer stakeholders joined the online community than planned, most

commonly due to a lack of comfort with technology, it was important to ensure feedback was collected

from the broader community through a traditional method. Therefore, a multimode approach was utilized

Page 16: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

6

where the online community received an online version of the questionnaire and at the same time, a

random selection of stakeholders was contacted by telephone to participate in the same survey.

The questionnaire was designed in partnership with the WSA and the content was based largely on the

discussions and findings from the online panel, the in-person meeting, and draft policy content that had

been prepared by the WSA. A copy of the questionnaire can be found in Appendix III.

Quotas were set to ensure a desired mix of stakeholders participated in the study (quotas are listed in the

questionnaire in Appendix III). In the end, 480 respondents participated in the survey and the final

distribution of respondents very closely matched the quotas initially set:

Method Sample Distribution

Telephone interviews 302

Online community 178

TOTAL 480

Respondent type Sample Distribution*

Farmer 337

Local government representative 142

NGO, CAA, WS Association 83

TOTAL 480

* Note that the list was a “select all that apply” and as such, several respondents stated that more than one category applies to them.

Data were collected from April 7th

to April 21st, 2014. The response rate from the online community was

36%. For the telephone interviews, the response rate was 28%. Because a portion of this research was

conducted online, the study is considered a non-probability proportional sampling study and therefore a

margin of error cannot be reported. However, this does not negatively reflect on the quality of the data

collected. Further, the results from this study can still be applied to the broader population of targeted

stakeholders, knowing that standard non-response research biases exist.

REPORTING NOTES

Unless otherwise specified, any data presented in this report using percentages originates from the

quantitative research study. Throughout the report, references are made with respect to feedback

collected from all research activities. For clarity, when speaking to results from each group, the findings

are identified as follows:

Online community: Members of the online community or online community members

In-person session: In-person session participants

Page 17: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

7

Telephone / online survey: Quantitative survey respondents.

The word ‘stakeholders’ refers to the broader audience of individuals who participated in any research

activity. Any quotes included in this report originate from the online community and/or the in person

session.

Page 18: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

8

STUDY FINDINGS

CURRENT LANDSCAPE

SHOULD DRAINAGE BE ALLOWED?

To begin, members of the online community were asked the broad

philosophical question about whether or not agricultural drainage should

be allowed. While differing opinions exist regarding the amount of

drainage that should be allowed and the specific criteria and rules that

should be put in place, most acknowledge that drainage is a necessary

fact in agricultural activity. Having said this, there are some who strongly

oppose all forms of agricultural drainage, commonly those who have

incurred damaged from others conducting such activities.

Despite wide-ranging opinions on the specifics of drainage, the

quantitative survey results illustrate that a large majority of respondents (70%) agree that drainage is

essential to agriculture but must be carefully designed and implemented to minimize downstream impact.

3. Broadly speaking which of the following three statements best reflects your opinion as it relates to drainage of water on agricultural

lands? Base: All respondents, n=480

12 % 17 %

70 %

1 %

Agricultural drainage poses a

serious risk to downstream

residents and landowners and

to water quality and should

not be allowed

Agricultural drainage is

essential to allow farmers to

manage their land and

maintain and improve the

viability of their operations

and should be allowed to

proceed with minimal

restrictions

Agricultural drainage is

essential to agriculture, but

must be carefully designed

and implemented to minimize

downstream impact

None of the above

“Upstream drainage, whether

controlled or not, will cause

damage to downstream

landowners by way of erosion,

siltation, ponding of

additional water, prolonged

wet areas, salinity, transfer of

weeds and diseases, etc., not

to mention negative

environmental impact.“

Page 19: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

9

CURRENT DRAINAGE ACTIVITIES

Claimed drainage of water on agricultural lands is commonplace but may still be understated given the

sensitivity of acknowledging such behaviour. Among farmers in the online community, 68% report that

they have conducted some form of drainage activity, most commonly the construction of permanent

channels and ditches, landscaping or leveling, and temporary v-ditching or scraping. This claimed

behaviour also lines up with comments made within the online community regarding drainage activities

that are undertaken.

Have you drained any of your farm land by means of the following? (select all that apply) n=334, farmers (Screener question)

Within the quantitative research study, generally consistent findings are noted (59% report they have

drained land).

6. Within the past 5 years, have you drained any of your farm land by means such as construction of permanent channels or ditches, landscaping, v-

ditches, scraping, tile drainage, etc.? Base: All respondents who are farmers, n=337

43%

42%

38%

18%

11%

6%

3%

32%

Construction of permanent channels / ditches

Landscaping / land levelling

Temporary v-ditches / scraping

Wetland consolidation

Wetland drainage

Tile drainage

Another means

Do not drain land

Have drained

farmland, 40 %

Have not drained

farmland, 59 %

68% at

least one

behaviour

Page 20: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

10

Several stakeholders are already involved in organized drainage activities through CAA’s or Watershed

Associations or have pursued various best practices methods of controlling drainage.

KNOWLEDGE OF DRAINING RULES

Presently in Saskatchewan, most drainage activities require approval with the exception of slough

consolidations in certain situations. These special circumstances notwithstanding, lack of knowledge that

all drainage activities currently require provincial government approval is common. Although this question

was not directly asked in online community discussions or in the in-person session, the quantitative survey

results reveal that less than one half of respondents are aware of such a requirement (45%). In fact, 44%

believe the opposite: that at least some drainage activities do not require government approval.

Addressing this perception will be essential to ensuring that a new policy is successfully implemented.

11. To the best of your knowledge, do all drainage activities currently require provincial government approval, regardless of how big or small they are?

Base: All respondents, n=480

All drainage activities currently require

provincial government

approval, 45%

All drainage activities

currently do not require

provincial government

approval, 44%

Not sure, 11%

“In my area GPS autograde has

made believers out of pretty much

everyone. Now it takes a week in

spring for the water to run off

when it used to go in 2 days,

erosion is very minimal, and natural

environments are left because the

base of peoples land can produce

year after year.”

The extreme opposite is a person

draining every drop of water they

can. No drainage will cause

flooding. Extreme drainage will

eliminate ground water recharge.

.“

“In our area it is kind of an unwritten

rule that we never will or should

never make a grade steeper than

0.04 degrees.”

Page 21: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

11

CURRENT IMPACTS

Within the panel, comments about being negatively impacted by the

drainage activities of others are widespread. However, several on the panel

also note that they are benefiting from drainage activities.

The quantitative survey substantiates that most farmers (78%) are impacted

by repercussions of upstream drainage or insufficient drainage on their

land. This high level of impact likely explains the broad-level support for

drainage activities, as reported earlier.

4. Are any parts of your farm land… Base: Those respondents who are farmers, n=337

When specifically asked whether agricultural drainage positively or negatively impacts farmer’s operations,

the quantitative survey illustrates that there are those who benefit from such activities and those who do

not. This likely speaks to the divisive nature of agricultural drainage in general.

5. How much does agricultural drainage impact your farming operation in a positive/negative way? Base: All respondents who are farmers, n=337

23% 20%

35%

23%

Suffering frominsufficient

drainage only

Affected byupstream drainage

only

Suffering frominsufficient

drainage andaffected by

upstream drainage

Neither

22 %

28 %

29 %

28 %

51 %

56 %

Negatively

Positvely

A great deal Somewhat

78% impacted

“Drainage not allowed is

the extreme just like saying

everything should be

drained. Managed

drainage is common

practice. People normally

ensure that water does not

run into their home or

basement.”

The extreme opposite is a

person draining every drop

of water they can. No

drainage will cause

flooding. Extreme drainage

will eliminate ground water

recharge.

.“

Page 22: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

12

“Drainage must be carefully considered when livestock

producers’ drainage could provide contamination

issues for downstream landowners. These projects

require very close scrutiny before being allowed.”

“Farmers with very flat land will

require some form of drainage to

be able to use their land.”

COMPLAINTS

A little over one quarter of respondents claim they have been involved in a drainage dispute.

23. Have you ever been involved in a drainage complaint? Base: Those respondents who are farmers, n=337

TYPES OF DRAINAGE THAT SHOULD BE ALLOWED

Within the online community, members discussed the types of drainage that they believe should be

allowed to take place. Opinions among panel members are divided. While some believe that drainage

should not be allowed without a permit, others mention that if moving water into a ditch does not cause

any damage, it should be allowed without a permit. However, several also state that landowners should be

penalized for the downstream effects of their draining activities.

Situations where panel members suggest that drainage should be allowed include

- farmers with flat land

- drainage of small potholes and sloughs

- drainage that moves water from one piece of land to another piece

of land within the same farm

Broadly speaking, most panel members believe that drainage should be allowed in a controlled form.

They believe that the system should include gates which can control the flow of the water and stop

drainage if required. However, some concerns were raised with regards to drainage:

- Drainage from lands of livestock producers may cause contamination issues for downstream

landowners.

- Drainage should not be allowed if there is no means to slow water or if it floods downstream

land.

- Fertilizers and sprays may make their way into the water system which can contaminate the water.

Those who are against drainage in principle claim that all kinds of drainage have consequences. However,

many of them acknowledge that controlled and regulated drainage activity can lower the impact drainage

has on people downstream.

Have been involved in drainage

complaint, 28 %

Have not been involved in drainage

complaint, 73 %

Page 23: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

13

“With the hundreds of landowners that I have been involved with, 99% of them move their

water from one higher slough to a lower one to cut down on the inconvenience of not

getting into that area of the quarter of land until later in the spring (eliminating seeding

potholes). Some move their water into ditches and most cases the water just sits in the

ditch for a couple of weeks and is taken by nature. I believe they should have their right to

do what they feel is best for them but if there is a complaint or questions on the

consequences of that water, there should be an advisor or expert that will not only answer

their problem, but will come out and inspect the situation and advise the landowner.”

“We are told that ditching can be done with minimum downstream effect. We are told that

gates can be used to control water flow to prevent downstream flooding. So what we are to

believe is that during the springtime rush to get the crop in, farmers are going to keep the gates

closed because this is the also the peak time of downstream flooding? Does anybody think for a

moment that the individuals who currently are involved in unregulated ditching are going to

now install gates and manage them to prevent the flooding of their neighbour's land?”

“There is NO enforcement of

the rules. The WSA gives a few

recommendations and it

doesn't matter if there was

permission or not.”

PERCEIVED NEED FOR A NEW AGRICULTURAL DRAINAGE POLICY

Stakeholders were asked to discuss the need for a new agricultural drainage policy, including perceptions

of how effective the current policy is and important elements to include in a new policy.

EFFECTIVENESS OF THE CURRENT AGRICULTURAL DRAINAGE POLICY

More than one half of survey respondents (55%) believe the current policy is not effective at addressing

risks and impacts of drainage. This sentiment was also noted among the online community where several

members feel there is need for more compliance, management, and best practices with drainage.

7. In your opinion, how effective are current agricultural drainage policies at addressing risks and impacts of drainage? This includes prevention, education,

remediation and enforcement of compliance. Base: All respondents, n=480

7 %

31 %

28 %

27 %

7 %

Very effective

Somewhat effective

Not very effective

Not effective at all

Not sure

55% not

effective

38%

effective

Page 24: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

14

“Too many people are draining their land in total disregard

of any rules and recent provincial governments have not

done or wished to do anything about it.”

“Minister Cheveldayoff: We would like to see that you create a

pamphlet that states the rights of landowners, the obligations of

WSA, and the obligations of the person or group that want to drain.”

IMPORTANCE OF DEVELOPING A NEW POLICY

Discussions in the online community overwhelmingly point to the desire for a new policy to be developed.

The quantitative survey aligns with this, where nearly six in ten respondents (58%) feel it is very important

for a new policy to be developed and another 29% feeling that it is somewhat important.

8. In your opinion, how important is it for Saskatchewan to develop a new agricultural drainage policy? Base: All respondents, n=480

58 %

29 %

8 %

3 %

2 %

Very important

Somewhat important

Not very important

Not important at all

Not sure

87%

important

Page 25: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

15

At the philosophical level, respondents are highly supportive of overarching outcomes of a new policy

that makes efforts to prevent damage to downstream landowners and residents, downstream flooding,

and negative impacts on receiving water bodies.

% who say it is important to prevent…

9. How important is it that a new agricultural drainage policy address each of the following? Base: All respondents. n=480

The areas of prevention noted above were also frequently mentioned by members of the online drainage

panel and those who attended the in-person session.

60 %

65 %

73 %

76 %

30 %

28 %

22 %

20 %

90 %

93 %

95 %

96 %

Erosion that would impactreceiving lakes

Negative impacts on waterquality in receiving water

bodies

Downstream flooding

Damage to downstreamlandowners and residents

Very important Somewhat important

Page 26: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

16

“Once you have that and some kind of policy written up that will

include all of Saskatchewan, then you can add to it for your own area.

And that policy has to have people with open minds working on it.”

“A water security agency pops up and the

very real threat of yet another government

agency that is empowered to tell me what

I can and cannot do on my own land

appears to be coming into being….We

primary producers are getting very, very

nervous as to how things are going to

conclude.”

IMPORTANCE OF FORMAL & ORGANIZED DRAINAGE

Through the online community and the in-person session, a majority of stakeholders state that formal and

organized drainage is important and essential to prevent negative downstream impacts. While most are

supportive of formal organized drainage, there are some who are apprehensive about new rules that may

impose restrictions as to what they as landowners can do on or with their land.

“The idea of organized drainage is

a must in this province. Water is a

wasted resource; people have been

controlling water for centuries, for

use of the land for agriculture.”

“Drainage needs to be formal and organized to protect all those who are

affected by it. Those who only know their immediate area and imminent

‘needs’ will unintentionally harm the ecosystem and thereby themselves along

with others. Without someone looking out for the ecosystem it will be

damaged unintentionally by those who also need it because they do not

realize the far reaching effects of drainage.”

“The current system lacks a stable local

oversight capacity. Too often a problem is

solved upstream while even greater

problems are created downstream.”

“If there are emergencies, allow for quick

decisions but long term planning is

needed to address drainage going

forward.”

Page 27: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

17

LEARNINGS FROM OTHER JURISDICTIONS

During the in-person session, participants referenced drainage systems developed in Manitoba (super

highways) and Netherlands (meandering ditches). They also brought up the example of Alberta using

radar mapping to understand the topography. They suggest Saskatchewan do the same and let

municipalities use the information to build drainage systems. They suggest that the WSA consider

successful drainage system adopted elsewhere and adopt similar techniques to create regulations and

system in Saskatchewan.

“Saskatchewan has the

advantage of looking at other

jurisdictions neighbouring us

who have all tackled this.

Learning from other mistakes

we can learn something. “

“If you look at Manitoba look

at their structure – dams,

superhighways, it saved

Winnipeg, Brandon. “

Page 28: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

18

NEW POLICY PRINCIPLES

Throughout the online discussions, in-person session, and the quantitative survey, each of the policy

principles developed by the WSA was presented and discussed. This section summarizes the feedback on

each principle. Note that this section predominately deals with support for the principles. Refer to the

Policy Approaches section for details on how stakeholders feel such principles should be put into action.

PRINCIPLE 1: DRAINAGE RIGHTS, MITIGATION, AND EDUCATION

Principle 1: Drainage is not a right; if potential or existing hydrological or environmental impacts cannot be

adequately mitigated, the drainage should not be allowed. Proponents must be educated to best

management practices around drainage.

Drainage is not a Right

Among the online panel, there is clear support for the belief that drainage is not a right of landowners or

other entities. Rather, members see drainage as a privilege that should only be afforded when certain

criteria are met. Opinions on the specific criteria vary but at the philosophical level, people are unified that

drainage is not a right. Commonly, in-person session participants drew on the analogy of driving: citizens

do not have a right to drive but rather a licence to do so.

“Driving is not a right, it is a privilege. All drainage does not create a

problem. Some go into the creek, if the creek systems are

maintained properly, then it won’t be a problem. But I think we

should have licensed draining because illegal drainage pops up

regularly.”

Page 29: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

19

If Impacts Can’t Be Mitigated, Drainage Should Not Be Allowed

There is broad support for this component of Principle 1, both among

the panel and among those who completed the questionnaire (87%).

This aspect of the principle triggered a great deal of discussion regarding

what qualifies as an impact and what entails mitigation, but at the overall

level, respondents agree that if impacts cannot be controlled, then

drainage should be disallowed.

Proponents Must be Educated on Best Management Practices around Drainage

During the in-person sessions, a great deal of discussion took place

regarding educating landowners on the best practices of water

management. It was suggested that many “drainers” are simply

unaware of the impact their draining activities can have and through

some simple and straightforward education, the frequency of negative

activities could be reduced. The quantitative survey confirms support

for educating those who intend to drain water from their land. The

concept of certification as a requirement for draining was also brought

up at this point in the discussions. More on this subject is detailed in

the Policy Approaches section on page 32.

44 % 43 % 87 %

Strongly support

Somewhat support

Drainage should only be allowed if the negative

impacts of such drainage can be minimized

69 % 26 % 95 %

Strongly support

Somewhat support

Those who drain should be educated as to the best

management practices around drainage

Next I’m going to read out a number of potential things that could be considered part of a new

agricultural drainage policy and I’d like to know whether you would broadly support or oppose

each of these ideas? Base: All respondents, n=480

Next I’m going to read out a number of potential things that

could be considered part of a new agricultural drainage policy

and I’d like to know whether you would broadly support or

oppose each of these ideas? Base: All respondents, n=480 “That’s why education is important. It should be a privilege and not a

right until you are educated. With drainage it is difficult to keep

track of. Education is going to be quick.”

Page 30: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

20

PRINCIPLE 2: REGULATION TIED TO RISKS

Principle 2: The degree of regulation over the construction or operations

of drainage works should reflect hydrological or environmental risks.

Stakeholders are highly supportive of matching regulations for the

construction of works with the amount of risk involved. The key

challenge identified by panel members, however, will be objectively

defining risk levels. Further details on defining risk can be found on

page 24.

PRINCIPLE 3: THOSE WHO BENEFIT BEAR COSTS

Principle 3: Those who benefit from drainage should bear the costs of

appropriate drainage design and management, including damage

prevention and mitigation

Stakeholders largely support the WSA’s suggested approach of cost

responsibility for drainage works. This is confirmed through the

quantitative survey (84% support), the online community and the in-

person meeting that was held in February. However, it was noted that

there could be exceptions to liability such as in cases of extreme rainfall.

However, at the in-person session there were discussions about whether

costs should align with benefit received. Although these individuals

acknowledge that each landowner benefit varies, there can be

difficulty in quantifying this benefit. As such, it is felt that in cases of

organized drainage, all parties should share in the cost equally

(capital and operating).

52% 31% 84%

Strongly support

Somewhat support

44 % 43 % 87 %

Strongly support

Somewhat support

The degree of regulation of drainage works should be

based on the amount of risk involved

All parties who benefit from drainage should bear the

costs to design and manage such drainage activities,

including damage prevention

Next I’m going to read out a number of potential things that

could be considered part of a new agricultural drainage policy

and I’d like to know whether you would broadly support or

oppose each of these ideas? Base: All respondents, n=480

Next I’m going to read out a number of potential things that

could be considered part of a new agricultural drainage policy

and I’d like to know whether you would broadly support or

oppose each of these ideas? Base: All respondents, n=480

“We would like to see the risks in a tier

structure, where different risk levels are

categorized.”

“Most drainage is designed to protect private property,

to increase capital resale value, or to make the farming

operation easier. This becomes essentially a private

benefit and should not be a public cost.”

Page 31: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

21

.

PRINCIPLE 4: DRAINAGE ALIGNS WITH OBJECTIVES

Principle 4: Where drainage is allowed, drainage projects should align with hydrological and environmental

targets that reflect both local circumstances and provincial objectives.

Broadly speaking, members of the online community support the WSA’s suggestion of aligning projects

with hydrological and environmental targets. However, several note that it may be challenging to develop

targets that apply to all areas of the province given that each area of the province may be facing different

challenges. Others state that their support of such targets will depend on what specific targets are in fact

set. Further, some online community members express

concern over a loss of property rights based on the

WSA imposing hydrological and environmental targets.

This specific topic was not addressed in the

quantitative survey.

“Yes they should align with the hydrological and environmental targets. But, what are these

targets? There are very few standards actually available (as far as I can see) that I should target. There

are permitting requirements (usually looking to address a short term issue) but very few long-term

objectives.”

“The problem is the objectives are not the same

for the complete province. Different targets are

needed for different areas. In our area we need

controlled drainage. In other areas they may

need water storage and irrigation.”

“These projects need to be self-supporting. The

construction and maintenance should be

financed by the area it benefits. The complete

area benefits therefore the complete area

should share in the cost equally.”

“Everyone [impacted by the project] should pay

a buck an acre. Everybody has water and

everybody is involved in drainage.”

“You shouldn’t be 100% liable because you may

not be able to control for certain factors like

rain fall.”

“The drainage structure should belong to the

public following similar principles to roads and

bridges.”

Page 32: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

22

PRINCIPLE 5: LAND CONTROL RESPONSIBILITY

Principle 5: The responsibility for land control and civil liability for impacts rests solely with project owners.

Broadly speaking, stakeholders agree with this principle. However, at the in-person session, participants

suggested that all parties involved in a drainage activity should be deemed liable for project impacts

rather than solely the project owner. Further, the current approach of strict land control in the form of an

easement registered on title is met with opposition. However, they do agree that an agreement or

permission among the participating parties should be struck. At the same time, in-person session

participants believe that in cases where unregistered drainage activities take place, the owner should be

held liable for any negative impact his or her activities may cause.

PRINCIPLE 6: REGULATORY PROCESS SEPARATE FROM ASSESSMENT OF DAMAGES

Principle 6: The regulatory process should remain distinct from any process related to assessment of

damages.

During the in-person session, participants agreed that it is beneficial for regulatory process be separated

from assessments of damages. Specifically, they believe it is best for the WSA to not be responsible for

assessing damages but rather to allow parties who would like to claim damages to do so through an

established process to enable landowners to pursue others for such damages.

“What would happen if we looked at two separate parts of the WSA? A BUSINESS model to function as

an overseer, with the expertise and knowledge to assist landowners (all) with developing and problem-

solving drainage issues; I would suggest almost a consultant function? Provide the support to the

landowner, investigate damage claims from an expert (civil engineer, topographer, whom ever is

required) point of view; and then provide this information to the landowners who have a vested interest

in results, and to the adjudicator that would handle any claims following the implementation /

completion of the project. And allow a GOVERNMENT function of WSA to operate as the... not

'enforcer' so to speak but the Judge, Jury and Executioner.”

“Very plain and simple if you wish to drain YOU should find out exactly where your drained

water will go, who it will impact (rural or urban) and after they ALL are aware of your intentions

and give a SIGNED go ahead agreement should you then be allowed to proceed. If you

proceed before agreements then your drainage is closed and you are fined.”

Page 33: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

23

Processes should be put in place to ensure fair

resolution of individual drainage disputes

PRINCIPLE 7: ACCESS TO RESOLUTION & COMPENSATION

Principle 7: Parties claiming damages as a result of drainage should have adequate access to resolution and

compensation. Direct costs of the process should be reasonably assessed to the party causing the impact.

There is large-scale support for ensuring processes are put in place to ensure fair resolution of individual

drainage disputes. Further, there is also strong support for ensuring there is adequate access to

compensation and resolution for being negatively impacted by drainage activities.

50 % 35 % 86 %

Strongly support

Somewhat support

Those who feel they are being negatively impacted by

drainage should have adequate access to

compensation and resolution

69 % 26 % 95 %

Strongly support Somewhat support

Next I’m going to read out a number of potential things that could be considered part of a new

agricultural drainage policy and I’d like to know whether you would broadly support or oppose each

of these ideas? Base: All respondents, n=480

“The issue of compensation for downstream impact that is attributed to upstream water management

practices needs to be built in to the model. This needs to include a mechanism for oversight, for

complaints, for appeals, and also a mechanism for collection of penalties and distribution of

compensation.”

Page 34: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

24

POLICY APPROACHES

The WSA proposed a number of approaches to meet the new policy principles. These approaches were

further discussed with members of the panel and during the in-person discussion. Specific questions were

included with regards to certain approaches in the quantitative study. The following section outlines

stakeholder discussion and suggestions regarding the implementation of policy components.

DEFINING RISK

Members of the online community note that it will be difficult to define risk, even into broad categories of

low and high risk. However, the following guidelines were suggested in order to determine risk level:

- the length of time water has been present in the location of interest

- the reason why the water is being held back

- the volume of water that will be drained

- percentage of water being drained in comparison to the

area of the land it covers

- whether the drainage is being controlled and how it is

being controlled

- the potential and/or anticipated negative impact of the

drainage activity (hydrological, environmental, economic)

- cumulative effects based on other drainage activities taking place in the region/watershed

- the potential effect on nearby landowners, highways, and the RM should be considered.

Online panel members also state that a definitive set of criteria may not be possible to identify risk levels

given unique issues facing different parts of the province.

“Saskatchewan is a very big place –

one size regulation does not fit all.

Something that might work in the

north might not work in the south. We

would want to have all the facts in

front of us to categorize risk.”

“The idea of considering risk in drainage activities is seems pretty reasonable. The challenge in

my opinion is that most drainage projects start pretty small, with operators logically saying ‘my

project is just small, and there are already 400 other similar drains in my RM or watershed’ so it

should be OK to proceed or follow a code/guideline/standard. Drainage is a classic ‘cumulative

effects’ issue - add up 400 low risk small drainage projects, each of them low risk on their own,

and then have a look downstream where the sum of these projects come together, and there are

consequences, either environmental, or civil due to downstream damages.”

“My first concern is setting the bar too low for drainage plans that may at the outset appear to

be low risk. The risks are not only focused on the original drainage project but also relate to

downstream impacts.”

Page 35: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

25

During the in-person discussion, it was suggested that determining and managing risks should be

assigned to local boards or CAAs that are more familiar with the local terrain and conditions. They suggest

that the WSA should establish a code of conduct that local boards would follow when defining drainage

project risk, although there are mixed opinions on the benefits and drawbacks of such organizations. They

also suggest that landowners should be made aware of the various risk levels and code of conduct that

should be followed, as well as the repercussions of bad drainage.

Throughout the various discussions with stakeholders, the lack of availability of detailed information

related to watersheds was noted. Several stated that with this information, better decisions could be made

regarding the approval and denial of drainage activities and projects.

Finally, it was suggested that the WSA turn to other jurisdictions to see how water is managed and risk is

assessed. This included Alberta, Manitoba and Holland.

“I have studied most of the legislation from other provinces and this is the common approach.

Alberta's framework is very much along these lines and has very a reasonable, easy to understand

set of definitions to determine the risk level of any new works. All drainage works for any purpose

no matter how small require permitting under their system and it is the initial risk level

assessment which determines the conditions of approval, inspection if any and operating control

measures if any.”

“There needs to be a comprehensive survey of the watersheds in Saskatchewan. There is not a

reliable data base on which to make accurate plans.”

“Unfortunately no one has told me that the knowledge is out there in the form of geological /

drainage records.”

“The geological surveys were done a hundred plus years ago. I cannot help wondering if the fur

traders knew more about our water systems than we do today.”

Page 36: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

26

APPROVALS & REGISTRATION

A majority of stakeholders agree that high-risk projects should require approval or licensing prior to

proceeding. This was noted through both the online panel as well as through the quantitative study.

12. Moving forward how do you think the WSA should proceed with respect to high risk projects? Base: All respondents, n=480

Opinions regarding low-risk projects however are divided. While some suggest that people will comply

when a licence is required (30%), others state that requiring licensing on all projects will slow down the

system and simply registering a project with the WSA or another agency such as a CAA should suffice for

low-risk projects (36%). Further still, some believe low-risk projects should be allowed to proceed without

notifying the government at all (26%). Suggested examples of this latter approach would be in situations

where a landowner drains water from one part of their land to another (i.e., water does not leave their

property).

74 %

17 %

1 % 6 %

ALL high risk activitiesrequire approval

Require high riskactivities to simply be

registered with thegovernment through an

online process

Allow high risk activitiesto proceed without

notifying thegovernment at all

Something else

“It is important that even [the] smallest

project needs licensing. It notifies your

neighbours that you are doing a project

and there is paper work.”

“There must be approval of all landowners that

will be affected whether it be downstream or

upstream. The approvals need to be in writing.

The WSA should be involved in this process also.”

Page 37: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

27

13. And how do you think the WSA should proceed with respect to lower risk projects? Base: All respondents, n=480

Regardless of whether a low- or high-risk project is licensed or simply registered

with the WSA, stakeholders strongly believe that monitoring and enforcement of

such projects is essential. Further, if a project is not granted permission, is altered

from the original criteria, or is considered illegal, stakeholders agree that the

project holder should be subject to fines and project closures.

Farmers are more likely to support the ideal of

allowing low risk projects to proceed without

notifying the government at all while non-farmers are

more likely to support either of the alternative

approaches.

30 %

36 %

26 %

6 %

All low risk activitiesrequire approval

Require low riskactivities to simplybe registered withthe government

through an onlineprocess

Allow low riskactivities to proceed

without notifyingthe government at

all

Something else

“If any drainage is allowed, it should be completely

monitored, and only be done within set limits. People

should not be allowed to drain into creeks or water

ways as it always affects someone else downstream,

and that is unfair to them.”

“When a drainage permit is granted, the WSA need to be on

top of the situation at all times, before, during and after the

project is approved up to one year after the completion of

the project. If the project has been altered from the original

criteria the said project holder should be fined a hefty sum.”

“I don’t need police at every

point, I have speed limits

posted and I’m a trained driver.

So, I don’t think everything

should be licensed. It will slow

down the process.”

“If the slough is under a certain

size (ex: 2 ac) then it would be

exempt from the process as

long as the water doesn't pass

on to another farmer’s land. If it

does then it should have to

have a permit, and to qualify,

the draining has to be done in

a responsible way(ex: tile)..”

28%

34%

33%

35%

43%

13%

ALL low risk activities requireapproval

Require low risk activities to simplybe registered with the government

through an online process

Allow low risk activities to proceedwithout notifying the government

at all

How do you think the WSA should proceed with respect to lower risk projects?

Farmer / primary producer Non-farmer

Page 38: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

28

EXISTING DRAINAGE WORKS

It was widely acknowledged among stakeholders that most existing drainage activities do not have

government approval. Stakeholders were asked their opinions on how these projects should be handled

in the context of adopting a new policy.

A wide range of opinions exist including recommending immediate closure of such works, requiring

approval of such works according to the new policy, continued operation of such works without any

review, or registration with the WSA through a grandfather clause. These opinions on how existing

drainage activities are handled tend to be impacted by the perceived risk and/or potential or actual

damage that existing activities have caused.

While opinions vary greatly when discussed in the online panel and at the in-person session, results from

the quantitative research illustrate that a majority of respondents (69%) feel some form of approval or

registration of existing works should take place. Specifically, nearly one half (46%) believe existing works

should require approval or registration consistent with the new policy within a reasonable time frame and

nearly one quarter (23%) suggest that all existing projects be simply registered through an online process,

presumably one that is more simplistic than a formal registration/approval process. Only 12% believe

existing works should remain unchecked.

46 %

23 %

14 %

12 %

1 %

4 %

Should require approval or registration consistent withthe new policy within a reasonable time frame such as

5 or 10 years

Should be simply registered with the provincialgovernment through an online process

Something else

Should be allowed to continue without any approvalor registration

No opinion on the matter

Not sure

14. Thinking about existing drainage works that have not received provincial government approval, do you feel that such works.

Base: All respondents, n=480.

Page 39: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

29

During the online and in-person sessions, stakeholders discussed the willingness and incentives for

landowners to register their existing works that are currently not approved by the WSA. Specifically, it is

believed that landowners will be reluctant to register or seek approval for existing works in cases where

there have been no complaints or damages from their project because the project may be denied by the

WSA once an application is made. To address this, stakeholders suggest that the WSA

- ensure farmers are not penalized for past drainage activities related to their project provided

there are no outstanding damages or grievances

- ensure that existing projects that have not caused damages or grievances be allowed to

operate until the WSA has issued an approval or denial decision for the project

- allow farmers a reasonable amount of time to comply with any change order requirements

set upon them based on the registration/approval of existing works

- make resources available, such as project managers, who can help landowners meet the

guidelines and regulations set by WSA for drainage activities

However, members state that current illegal draining which negatively impacts others should not be

allowed to continue.

“If the drainage activity has not been

approved, ditches should be filled in

immediately and the party or parties

(including R.M.'s) responsible for the

unapproved draining should be

financially responsible for both the cost

of filling in the ditches and for any

damage the drainage may have caused

downstream.”

“The priority has to be to protect the people downstream, not

protecting the people that are gaining by draining their land. These

control gates have to be monitored by an independent body. (NOT

THE WATER SECURITY AGENCY). The way the system is now, it is

always in favor of the people that are draining their land. This has to

stop. The mindset of the old Saskatchewan Watershed Authority and

the new WSA has to change.”

“If the activity is deemed to have too many negative effects vs.

the positive benefits the drainage activity should be immediately

reversed at the cost of those who initiated it. The reversal

process should happen by a third party though.”

Page 40: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

30

APPROVAL CRITERIA

Stakeholders were asked to comment on the

approval criteria for drainage works. A majority of

survey respondents agree that applicants should

follow specific design and operation standards and

a similar proportion agree that project organizers

should be required to repair any damages they may

cause. Agreement with having private, qualified

professionals approve drainage work is mixed.

During the in-person session, it was mentioned that

hiring a private, qualified professional to approve

drainage can become expensive for landowners.

However, others note that there is value in having

an expert fully assess the risks and potential

damages of a drainage project.

Specific criteria deemed important to allow drainage to proceed according to online panel members and

in-person participants include

- consideration of upstream and downstream impacts for farm land, streams, ditches,

roadways, towns, and other infrastructure

- watershed contamination including wetlands

- impact on flow rates and the ability for the system to handle additional potential water flows

- erosion potential

- short-term and long-term impacts

- evidence of affected parties working together on the project

- ease and ability for the project to be monitored by an independent body (the WSA, CAA, etc.)

after the works have been approved (i.e. staff nearby or regularly visit the area to monitor the

project)

15. For new and or existing projects that will require an approval, do you

agree or disagree with each of the following? Base: All respondents, n=480

“If you start with where the water ends up and work your way

back to the end of the catch basin and have a plan that will

allow everyone in the catch basin to drain into the ditch then

and only then will we have a controlled drainage system and

protect downstream farmers.”

30 %

49 %

50 %

24 %

25 %

28 %

55 %

74 %

77 %

Private, qualifiedprofessionals will berequired to approve

drainage work

Project organizers willbe required to repairany damages caused

The applicants willneed to follow specificdesign and operationstandards and rules

Strongly Agree

Somewhat agree

Page 41: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

31

16. Thinking about wetlands, please rate your agreement with each of the

following statements. Base: All respondents. n=480

WETLANDS MANAGEMENT

Stakeholder feedback illustrates that there are divided opinions regarding wetlands management as it

relates to agricultural drainage. The first debate is with respect to the definition of

wetlands. Members of the online community and participants at the in-person

session commonly believe the definition of a wetland can be based on size of the

water body and/or the length of time the water has been present. Specifically, some

believe that if water persists in a location throughout the entire year, it should be

considered a wetland. Others believe that water being present for two to three years

would classify the body as a wetland. Further, some believe that “potholes” should

not be classified as wetlands due to their small size. In the end, the definition of a

wetland was secondary to opinions on wetlands management from an agricultural perspective.

Within the quantitative study, more than three quarters (78%) of respondents agree that a new drainage

policy should ensure that some larger, more permanent wetlands be retained. However, equal

proportions agree that all wetlands should be retained (63%) and that drainage of small wetlands is

acceptable (62%). The apparent contradiction in support for these three opposing viewpoints confirms

that opinions vary among respondents and addressing the issue of wetland management may prove

challenging. This is further substantiated by the fact that the topic of wetlands resulted in more than 100

posts in the online community. This is more active than many of the other discussion topics with the

online panel.

Farmers are less likely to support the notion of retaining all

wetlands:

- Farmers: 57% agree

- Non-farmers: 73% agree

29%

24%

43%

33%

39%

36%

62%

63%

78%

Drainage of wetlands is an acceptablepart of agriculture because it is unrealisticto expect farmers to give up the potential

production or to drive large machineryaround many small wetlands

Wetlands are very important and whiledrainage activities that remove

floodwater from fields are fine, allWetlands should be retained

Drainage of wetlands is acceptable, butthe policy should ensure that some larger,

more permanent wetlands are retained

Strongly agree

Somewhat disagree

“We do need to define the

meaning of a wetland. In my

books a wetland never goes

dry in a normal year. A

slough that holds water for 3

to 8 weeks in the spring then

dries up is not a wetland.”

Page 42: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

32

A common theme noted throughout the online discussion included the opportunity and real costs of

retaining wetlands and who bears this cost. Some farmers note that they make a personal decision to

retain some wetlands at their own opportunity cost while others feel that

incentives such as tax breaks or fees paid by interest groups would encourage

farmers to maintain wetlands. Others feel that a broader habitat plan needs to

be put in place with the purchase of wetlands and investment by other bodies

such as governments or interest groups to maintain such water bodies for

wildlife.

It was suggested that the WSA list its objectives as related to wetlands management as well as

communicate the importance of and benefits of retaining wetlands. Other factors suggested by

stakeholders that the WSA could consider include

- set a goal of the amount wetlands that should be retained as a measurement of success

- wetland location (wetlands in a corner of land is more desirable to maintain than in the

middle of a field)

- wildlife preservation benefits

- access to the wetlands during dry years/storage of water for dry years

- the necessity of wetlands to maintain proper filtering effects for

future years

- providing tax incentives or other tangible benefits for farmers to

retain wetlands or alternatively, tax penalties for draining such

wetlands

- require farmers to retain a certain amount of wetlands as a condition of drainage of water

from other parts of their farm land (divided support/opposition noted)

“As farmers we look at

wetland like nonproductive

area. But that’s not true.”

“Though I agree with the idea of more wetlands, I doubt many farmers would buy into this. If the

wetlands happen to occur on a corner of a parcel of land, then most owners wouldn't have a

problem leaving it as is. If the wetlands happen to be in the middle of the field, I believe owners

wouldn’t be so keen on keeping it around… I think making it mandatory to keep some wetlands

on farm land would cause a lot of headache because of those who would object it. The way I see

it right now, creating wetlands seems to be only achievable through incentives, not forcefulness.”

“I believe wetlands could be left, but show me the money!!!!!!!! The USA pays

there farmers set aside fees and so should we here. If Ducks Unlimited wants

wetlands, pay me the money otherwise I’ll produce grain in them.”

“Should we, the farmers retain wetlands as part of

the condition for drainage? My answer would be

yes, yet who would decide which wetland should be

left, the farmer or the one authorizing the permit.”

“If I could drain 150 acres

for crop production [and

be required to leave] 10

for retaining water [as a

condition of drainage],

my farm would be more

productive and add to

the wealth of

agriculture!!”

“Maybe it would be better if we

had a large purchased area in

the public trust that would hold

water instead of a lot of small,

unconnected potholes.”

“Lake Diefenbaker is on verge of becoming Lake Winnipeg due to

phosphate loading. If we are going to be responsible stewards of

this province, which is what the government is responsible for,

then we need to get in know of everyone issue's.”

Page 43: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

33

CERTIFICATION, EDUCATION & INCENTIVES

Throughout the online discussion and the in-person session, educating stakeholders on the best

management practices related to drainage was repeatedly mentioned. Specifically, most believe that

education is the key to ensure that landowners understand the best practices for drainage, understand the

repercussion of poor drainage projects, and implement it in their projects. Suggestions included written

materials, workshops and seminars. The quantitative study verifies that there is interest in having the

government provide educational materials on best management practices on agricultural drainage (95%

agree).

Among in-person session participants, most state that they would be willing to pursue drainage education

if such courses were made available. It is noted though that actual participation in such courses may be

notably lower than stated, as in research studies respondents tend to overstate their future behaviours.

Interest in enrolling in an education course was not measured within the quantitative survey.

In the in-person session, it was suggested that incentives be provided to those who take a formal course

or obtain certification on drainage to encourage education among those involved in drainage. Such

incentives could include a faster approval process for future drainage works. The quantitative research

suggests there is moderate support for this notion (59% agree with the concept) and a similar proportion

(54%) agree that a licence be required as a condition of drainage. While many online panel members like

these concepts, many express concern that educating people or issuing licences may not alter behaviours.

Again, enforcement was brought up as essential ensure a licensing system is effective.

17. With respect to education, there are some options being considered. Do you agree or

disagree with each of the following? Base: All respondents. n=480

23 %

20 %

57 %

31 %

38 %

38 %

54 %

59 %

95 %

The government should require those who undertake drainage to acquire

certification before draining, similar to obtaining a Driver’s Licence before

being able to operate a vehicle

The government should provide anincentive to those who acquire

certification in the form of fast-trackedapproval

The government should provide accessto useful educational materials on

drainage best management practice

Strongly agree

Somewhat agree

Page 44: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

34

Additional considerations brought forward by stakeholders regarding education and licensing include

- a licence should not allow high risk projects to be fast tracked

- there could be significant costs and resource requirements to administer a licensing system

- provide incentives to obtain education rather than force it on people

- provide a reasonable timeframe for farmers to become educated

- forcing education on landowners can be seen as further government intervention

.

“I do feel that there should be a significant

time spent in the classroom to learn the

good, bad and ugly. Also, get information on

using technology, deeper vs. wider ditches.”

“I think people need to be educated on the

damage that draining water does, and how a

person can do it in a way that will not affect other

people.”

“Great idea [licensing drainers]. I would

suggest that there be a manual or book one

could use as reference when filling out an

application for drainage and between the

application and approval process problem

areas could be flagged and granting of license

would be conditional.”

“Education and good communication simply

cannot hurt. Hopefully this would be an

opportunity to inform participants about the

bigger picture and the downstream

implications of draining. Perhaps some

people would come up with alternatives and

in those cases there would be a bit less

draining.”

“I'm not particularly fond of this idea for the

reason being a simple license doesn't ensure

that "bad" drainage won't take place.”

“Licencing drainage reminds me of the long

gun registration fiasco. The idea of creating a

knowledge base with a licence based system

may have its merits.”

Page 45: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

35

LOCAL WATER BOARDS

During the online and in-person discussions, it was suggested that

local bodies be created to deal with localized drainage issues.

Called “water boards” by online panel members and in-person

session participants, they state that through a board of this kind,

farmers can communicate their drainage problems and work

together to find solutions. A mix of benefits and drawbacks were

noted with this concept, as outlined below. Given the range of

opinions, it is anticipated that this would be a contentious topic if

pursued further by the WSA.

Key points brought forward by stakeholders include the following:

- Local organizations could work with the government to

administer the policies and guidelines because they will

have a better understanding of the local terrain.

- Local organizations could work with a water expert

where needed.

- Local water boards could include representation from

RMs and town councils involved as well as a diverse group of people to

bring in different interests (agriculture and environmental).

- Most believe that all officials for the water board should be elected, not

appointed.

- The water board could be the primary contact with the WSA, and

therefore, local problems would be handled locally.

- The water board could handle some of the responsibilities currently held

by the WSA such as mediating water complaints, managing control

gates, and assisting with technical knowledge of elevations and drainage

projects being proposed; however, there would be a close relationship

between the WSA and the local board.

- Local organizations could play a role in enforcement and compliance.

Identified perceived benefits of such boards could include

- greater knowledge of the local terrain

- better representation of local interest

- more responsive decision-making

- more effective enforcement of the policy

“We can’t have a regulation

for every water base. If we

had this managed through

more local boards, they

would be able to help better

and WSA can just leave a list

of do’s and don’ts and is left

up for negotiation with the

WSA.”

“They could handle

responsibilities currently

held by WSA as such as

mediating water complaints,

managing control gates &

assisting in technical

knowledge of elevations &

drainage projects being

proposed.”

“It would help correct problems created by

individuals and or municipalities in water

drainage by taking the local politics out of

it.”

“I propose a from the bottom up, local

organization - grassroots if you will - but

technically supported by the government and

with financial incentives. The government

should set up a legal framework in which

water boards would be created and operate.

If disputes within a basin arise, binding

mediation should be the norm. RM's with

their arbitrary, historical borders are, as a

rule, not equipped to deal with water issues.

These follow natural borders which normally

transcends RM borders. But RM's could

perhaps be called upon to assist in a practical

manner by providing heavy-duty equipment

in certain cases (like during the spring

runoff), something they do already. The key

is that the local people know the terrain and

have already an idea about possible

solutions.”

Page 46: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

36

Despite a detailed discussion the concept of a local water board, some concern and opposition is noted.

Specific concerns noted include the following:

- lack of drainage knowledge among board members who are authorized to make decisions for

their region

- finding capable individuals willing to sit on the board given the contentious issues and

potential time commitments

- difficulty coordinating with neighbouring water boards/jurisdictions

- the potential for feuding among board members and/or RMs within the water board

- the potential for unfair treatment of landowners based on local

political dynamics

- potential duplication/overlap with existing CAAs, watershed

authorities, watershed stewardship groups and RMs in some

capacities

- lack of an independent body to make objective decisions for the

local area

“The problem comes with the

fact that you have people who

know nothing about natural

water flow, ground saturation,

ground make up [making

decisions].”

“This could become a very slippery slope in a

hurry. Say the governing body says 'Ok the

limit has been reached. No further drainage

allowed'. Now two neighboring farmers may

not have a level playing field. One has drained,

the other is not allowed to.”

“If we form boards it is people like this that will be

the first to sit on them so that they can continue

with their actions. It will pit farmer against farmer if

we have local boards. We have already seen the

RCMP called in where some of this draining has

brought neighbours to blows. It will take an

independent body to oversee and take action. They

must have set rules to work with and enforce and

penalties that will make people comply.”

“The province has already created Watershed

Stewardship Groups for most of the provinces

watersheds. They receive technical assistance /

support from WSA and other qualified agencies /

departments. Is there a need to add yet another

entity like a water board to the mix or should we

improve on what's already in place?”

“I sit on a local board SCRWA and a CND. I have

for 20 years we have mediated drainage

complaints and had very good success.”

“It is my experience that doing things in a group

is far better than a piece meal approach.”

Page 47: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

37

MANAGEMENT OF AREAS WITH EXTENSIVE DRAINAGE

Next, stakeholders were asked about options the WSA could pursue in areas of the province where there

are extensive drainage issues. The quantitative study shows that there is agreement that landowners in

these areas should continue to be encouraged to come together voluntarily to form legal entities to

facilitate organized drainage (80%). However, the same proportion (79%) also believes that if landowners

in such areas are unable to form a drainage entity on their own, the province should be able to require

the formation of such organizations.

Interestingly, only 56% support the notion of preventing any new drainage in these areas until such an

organization is formed, regardless of whether it is formed voluntarily or through government intervention.

Farmers are less likely to support this idea (52%) than are non-farmers (64%).

Within the online community some note that with WSA involvement, decisions like expropriation would

be made by those without a personal profit interest, which would be an advantage in stalemate situations.

Despite strong positive support for provincial intervention if needed in these regions, there is strong

opposition noted among some online discussion members. Specifically, there are concerns over a

government agency having the power to force drainage works on a farmer’s land as well as the

anticipated effectiveness of such a government body given the existing dissatisfaction with the current

process of administering agricultural drainage. Again, these people believe that greater enforcement will

encourage increased compliance with drainage policies.

25 %

32 %

33 %

31 %

47 %

47 %

56 %

79 %

80 %

The provincial government should simplydisallow any new drainage in these areas

until the formation of an organized drainageauthority is created, regardless of whether

such organizations form on their own orthrough government intervention

The province should be able to require theformation of organized drainage authorities

in these areas

Landowners in these areas should continueto voluntarily come together to form legal

entities to facilitate organized drainage as iscurrently the case

Strongly agree

Somewhat agree

18. In areas where there is extensive drainage activity, the provincial government is considering options related to

the formation of organized drainage authorities. Please rate your agreement with each of the following

statements. Base: All respondents. n=480

Page 48: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

38

CONTROL GATES AS A REQUIREMENT OF DRAINAGE

Within the online community, members were asked if the installation of a control gate(s) should be

considered necessary for the approval of a drainage project. This topic was not discussed in the

quantitative survey or at length in the in-person session. While

there does not appear to be strong opposition to the use of

control gates, a variety of issues are noted that members believe

will make it complex for the WSA to implement a policy of

requiring the use of control gates as a condition of drainage, as

summarized below:

- There is a need to consider the broader watershed

rather than make this a condition at the individual

farm level.

- Depending on the unique nature of each region, control gates may or may not be the best

solution to effectively control water.

- For control gates to be effective, one needs to know the region well to in order to administer

the gates.

- Administering control gates needs to be done in a coordinated manner to ensure the system

can handle the flow.

- There is need for details on elevations within the region to make proper decisions on when

and how much water flow to allow.

- Given the size and geographic sparseness of some regions, it is suggested that water be

controlled by culverts rather than relying on humans to control several gates in the system.

“In the condition of gates controlling the

water flow, you will need someone that has

been involved since the beginning of this

project and knows the area very, very well.

That person will be responsible [to] all of the

landowners and the board with data of

timing, dates, and gates opened, and how

much water flow and controlled.”

“So now we're talking about changing the role of

the WSA from its current responsibility of

preventing illegal drainage (a role it is presently

failing miserably at) to one where it will be asked

to enforce organized drainage? Not a chance!”

“Water security agency should never hold the

right to force a landowner to participate in a c

and d project that they do not which to

participate in. Nor should they hold the right to

force any water works to be done on farmer

owned land ever!”

“Should WSA have the power to force

landowners to work together in areas with many

problems? I think yes. If I'm standing in water

and all around me is water for miles and I'm not

cooperating with anyone to fix this or try to

make it better then I should be forced.”

Page 49: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

39

“Water control should be on a watershed basis

to be effective as well as the placement of

gates. Gates would be opened and closed by a

water management committee for the

watershed using the local landowners to

physically open or close the gates. This way

there would be immediate feedback on any

screw ups.”

“Control gates are a good idea but impossible to

manage on a watershed wide scale. Most watersheds

are too large with too few inhabitants with too little

knowledge of the bigger picture. In my area water

would quickly build up and spill over roads causing

damage. The best way to manage flow is to undertake a

comprehensive plan to limit flow by installing culverts

through roads of the proper size to limit peak flow out

of the watershed.”

“I don't think it should be a requirement across

the board because each watershed differs

immensely.”

Page 50: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

40

COMPLIANCE & ENFORCEMENT

Compliance and enforcement is an area that was commonly

referenced throughout the engagement process with stakeholders.

There is a strong belief that greater emphasis should be placed on

ensuring that those who drain water follow a policy that is set forth.

Among those surveyed, 86% support the government putting

regulatory requirements in place to minimize non-compliance with

drainage activities. This level of support is echoed in the online panel

and in-person discussions. Stakeholders suggest that the WSA establish

provincial objectives for drainage and communicate them with residents

so that all parties who are or may become involved in drainage

activities are aware of them and can keep them in perspective when

initiating a drainage project. Stakeholders also stated that the WSA

rules and regulations should be uniform and applicable throughout

the province. Through its compliance efforts, stakeholders recommend that the WSA should focus on

water management, including agricultural drainage activities, education regarding drainage, water

conservation, and other applicable elements.

The quantitative study also indicates that opinions are divided with respect to the compliance and

enforcement method that the WSA should undertake. Specifically, one half (51%) state that the

government should rely on a complaint-based enforcement system from landowners while nearly the

same proportion (45%) believes the government should proactively enforce compliance. Farmers are

more likely to prefer a complaint-based approach (57%) while non-farmers are more likely to prefer

proactive enforcement (56%).

The government proactively enforces

compliance with regulations such as

fines, penalties, stop work orders, etc., 45 %

The government relies on a complaint-based enforcement system from landowners and then investigates the

situation, 51 %

Don't know, 4 %

20. Turning to compliance and enforcement, which of the following two options would you prefer? Base: All respodents. n=480

57 % 29 % 86 %

Strongly support Somewhat support

Regulatory requirements should be put in place to

minimize non-compliance

Next I’m going to read out a number of potential things that

could be considered part of a new agricultural drainage policy

and I’d like to know whether you would broadly support or

oppose each of these ideas? Base: All respondents, n=480

“Let's use an analogy of a boxer…random drug

testing for athletes has been shown to be a

more effective means of discouraging PEDs

use than scheduled testing, so too could

random compliance checking be better at

discouraging bad drainage.”

Page 51: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

41

Regardless of which method is used (complaint-based or

government enforcement), the quantitative study shows

that there is strong support (78%) for the WSA having

the power to enforce administrative penalties, voluntary

payments, notices of violation, stop work orders, orders

for closure of works, and orders for remedial action

related to agricultural drainage. While a majority of

farmers agree with this point, support is lower than that

among non-farmers (73% vs. 88%). However, strong

support for the concept is further substantiated through

the online discussions.

Commonly, increased fines are cited as an additional

deterrent to non-compliance, complemented with greater

enforcement (either proactive or via a complaint-based

system). However, stakeholders are quick to point out that

the WSA should have adequate resources to manage complaints to prevent false complaints from

delaying decisions on valid claims.

41 % 37 % 78 %

Strongly support

Somewhatsupport

Regardless of which method is used, do you support or oppose the

WSA having enforcement powers to impose things like

administrative penalties, voluntary payments, notices of violation,

stop work orders, orders for closure of works, and orders for

remedial action related to agricultural drainage? Base: All

respondents, n=480

“You need a fine of $10,000 and up, not $200. Put some

teeth into it or forget it you are just wasting everyone’s

time with these small fines and not doing it the way it is

supposed to be done.”

“The [current] drainage complaint system is a

complete failure because it pits neighbor

against neighbor, friend against friend, and in

most cases the government agency sits back

and does nothing.” “We know where the problem is, where it

starts, and also the solution, but to achieve the

solution will take years because of all the red

tape. We need an agency that will take

responsibility and do their job.”

Page 52: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

42

RESOLVING DISPUTES

When asked about what an effective process to resolving drainage

disputes between neighbours might look, the following points were

noted:

- educate farmers about the policies surrounding agricultural

drainage (i.e., provide advice, not just penalties)

- encourage both parties to resolve the issue on their own first

- ensure there is no conflicts of interest among the disputing parties and the agency tasked

with resolving or laying judgment

- employ a process that enables an independent body to review disputes, force closure of

works, enforce penalties, etc.

- impose a nominal fee such as $100 for filing a complaint to minimize those filing false

complaints (fee would be refundable if the claim is valid)

Several suggest that the water boards previously

discussed could take on the role of mediator in these

types of disputes, conflicts of interest

notwithstanding. However, the need for quick

resolution of disputes is also frequently referenced.

“Teach, teach, teach, and a willingness to

learn what others have learned before

you. As farmers we are our own worst

enemy, sometimes getting angry before

we understand and know the facts.”

“Communication is the key. Many

arrogant R.M. councilors have to read

the rules and regulations and have to be

educated so as to not just stick up for

friends and for their own agendas”

“A government process that solves all

disputes with a mediator is essential” “Water security must act more quickly than it

does to resolve issues. They need to be able to

fine offenders with heavy penalties to deter

unauthorized drainage. Once they have photos

and proof, their own water board should have

authority to fine people and fix the problem areas

so that drainage is stopped. Any appeals from

the offender should be considered after the fines

because it just leaves the door open to prolonged

abuse as we currently see now.”

Page 53: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

43

NON-COMPLIANT COMPLAINT PROCESS

Members of the online panel and in-person session participants were asked to comment on the following

possible non-compliant complaint process: (this topic was not discussed in the survey)

In cases of complaints, the WSA will immediately order closure of a non-compliant drain, and then

consider a licensing request. A licensed project will stay open, but WSA will review the claim of

damage to determine if the drainage approval needs to be altered if a report by a qualified person

supports the allegation of damage

The majority of stakeholders support the above policy suggestion. However, it is recommended that the

WSA provide sufficient time for landowners to register or seek approval of their existing projects before

implementing this policy. For licensed works that result in a complaint, stakeholders advise that a review

of the project be expedited to ensure that any ongoing damage is minimized.

As noted earlier, concerns with the WSA’s ability to manage the process are voiced with respect to this

policy suggestion, especially in regards to turnaround times.

LAND CONTROL

During the in-person session and in the quantitative study, stakeholders were asked to comment on

future land control requirements that they would be comfortable with when a new policy is adopted.

Presently, an easement registered on a land title is deemed required for a drainage project to proceed

where one farmer is draining land across another farmer’s land. Feedback from participants at the in-

person session illustrate that this requirement is undesirable for the following reasons:

“Yes I support this. The most important thing to accomplish in such a case of unlicensed drainage

having negative impacts downstream is to reduce or stop the cause of those impacts ASAP (i.e. close

the ditch), so as not to cause further hardship to those affected. Regarding the licensed work causing

negative downstream impacts, obviously if such a situation is occurring then there is clearly some sort

of non-compliance with the conditions of the approval (if deemed to cause impacts, it wouldn't have

been licensed in the first case), and there would need to be expedited mitigation measures

implemented in order to not prolong the negative impacts by dragging out the process for an

extended period of time.”

“The time to consider a licensing request,

process it, and perhaps then remove the

closure could take months or years.”

Page 54: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

44

- an easement is permanent/extremely difficult to remove and if drainage conditions change,

the farmer who has water draining across his or her land cannot prevent the drainage from

continuing, especially if the upstream farmer begins to allow water onto his or her land from

someone else upstream

- an easement makes a parcel of land less attractive when being sold

Rather, stakeholders indicate that they historically have preferred more of a “hand-shake” approach where

there remains flexibility for both parties to reassess the agreement on an as needed basis. Various

alternatives were discussed at the in-person session and presented to respondents in the survey. Based on

these results, opinions are somewhat divided. The greatest proportion (44%) support a new approach

where a legal contract be signed between the two parties indicating that they are aware of and accept the

impacts of the drainage activity they are entering, as a means to avoid registration of an easement.

Three in ten (30%) suggest keeping things as they are now and 17% recommend simply advising

proponents of the legal risks of not choosing to proceed with registered land control.

5 %

17 %

30 %

44 %

Another option

Simply make proponents aware of the legal risks andthat they will bear liability if they choose to proceed

with drainage without registered land control

Keep things as they are now

Require an agreement or contract from the partiesinvolved indicating that they are aware of and accept

the impacts of the drainage activity

22. Presently, a licensed drainage project requires the registration of an easement

on land titles if water is crossing over someone’s land. Going forward, there are

three options the government is considering. Which approach would you support?

Base: All respondents, n=480

“I have seen where projects have been altered

after easements have been signed. There was no

consulting with the people who signed and these

were the people most affected.”

Page 55: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

45

ONLINE APPROVAL

During the in-person session, participants were asked if they would support or oppose a process whereby

new high risk drainage licence requests be posted on the WSA website for public consultation prior to

approval. Online community members strongly supported this approach. This support is further validated

through the quantitative survey whereby three quarters of respondents (75%) stating that they support

the idea. While a majority of farmers are supportive of this idea, their support is lower than that of non-

farmers (69% vs. 84%).

42 % 33 % 75 % Strongly support

Somewhat support

Q19. Do you support or oppose having high risk drainage licence requests posted on the

WSA website for public consultation before approval. Base: All respondents, n=480

Public consultation before approval of high risk projects

Page 56: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

46

APPENDIX I – ONLINE DISCUSSION TOPICS

Drainage: When, How, Organized and Illegal:

- When drainage is allowed to proceed, what conditions should be required, if any?

- Formal organized drainage refers to landowners working together, perhaps through a

conservation area authority, to develop drainage works. How important is formal, organized

drainage and where is it most critical?

- What actions should be taken to address existing drainage activity that has not been approved

but should require approval?

- In what situations should drainage be allowed? In what situations should it not be allowed?

Suggested Ideas from the Panel:

- A suggestion has been made that local water boards be created to manage drainage. If such

boards were created, what role should they have? How would such a board function? How would

the Board members be selected?

- Several comments have referred to needing to control the release of water. Should having a

control gate, so water is released only after the peak flows have gone by, be a condition of

approval of drainage? If so, in what situations?

- A suggestion made in one of the previous sessions is that a farmer be required to retain at least

some wetlands on their land as a condition of approval for drainage. What are your thoughts on

this?

- What would an effective process to resolve drainage disputes between neighbours look like?

Please be as specific as possible.

Hydrological and Environmental Aspects:

- The degree of regulation over the construction/operations of drainage works should reflect

hydrological or environmental risks. Should low risk projects follow a general code of practice

while greater risk projects require more review and possible approval through a permit process?

What kinds of things would make a project low risk versus high risk? Would this make things

easier or harder for stakeholders?

- Drainage produces many benefits but can also create problems. If potential or existing

hydrological or environmental impacts cannot be adequately mitigated, should the drainage be

disallowed?

- Should drainage projects be required to align with hydrological and environmental targets that

reflect both local circumstances and provincial objectives? What types of things should be

considered?

Page 57: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

47

Drainage Benefits, Costs and Damages:

- Previously this online community discussed whether or not drainage should be designed and built

to avoid downstream impacts such as flooding or environmental degradation. If such works are

developed, who should pay the cost, including design, construction, land control and

maintenance, of doing it right? Should the costs to build and maintain be the same for everyone

affected or should those who benefit more from the drainage system pay a different amount?

Why? How would this look?

Risk Management:

- How important is it that existing works be regulated in the same manner as new works, so as to

mitigate risks? Would this be an appropriate approach and what should be considered if such an

approach were taken? PLEASE REFER TO THE INITIAL POST BY PANEL MANAGER FOR THE FULL

DESCRIPTION.

- Risk level was a topic of an earlier discussion in this forum and a few determining factors of risk

level were suggested by the group. The WSA is presenting their definition of RISK, RISK

ASSESSMENT and RISK MANAGEMENT, along with the FACTORS to assess impacts of drainage.

Please read the full description on the initial post by Panel Manager and let us know if the factors

presented are appropriate or if there is anything missing.

- WSA proposes an approach to regulation and compliance based upon risk levels. Please read the

full description on the initial post by Panel Manager and tell us the concerns and/or benefits you

see with the proposed approach.

- At times unauthorized drainage will have caused property or environmental damage. The

question is who should be responsible for repairing the damage? Should new drainage

regulations require that the drainer repair or compensate for such damage?

- Organized drainage often leads to better drainage projects with fewer problems between

neighbours. In areas with many problems where a organized drainage system could resolve many

of the problems, should Water Security Agency have the power to force landowners to work

together, possibly through creation of a conservation and development authority, to develop

organized drainage?

Licenses:

- An important step to good drainage is to ensure people who are doing drainage understand best

practices. There are several ways government could do this. One option is to create a license to

construct drainage works, like having a driver’s license. To do drainage, one would need to

demonstrate an understanding of good practices.

- This license could be set up as a requirement for those involved in drainage. Alternatively,

obtaining the license could be optional but incentives would be provided to those who have a

Page 58: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

48

license such as less review and a faster approval process for drainage works. Would some type of

license to drain be a useful component of the drainage regulation process?

Complaints:

- Would you support or oppose the following if it was put in place as part of the new agricultural

drainage policy: In cases of complaints, the WSA will immediately order closure of a noncompliant

drain, and then consider a licensing request. A licensed project will stay open, but WSA will review

the claim of damage to determine if the drainage approval needs to be altered if a report by a

qualified person supports the allegation of damage.

Closing Thoughts:

- Please provide any final thoughts you have before we close this forum and thank you for your

participation!

Page 59: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

49

APPENDIX II – IN-PERSON MEETING MATERIALS

Agricultural Drainage Consultation

Travelodge Hotel Saskatoon

Room: Concorde 1

February 6th

, 2014

9:00am – 4:30pm

Agenda

8:30 - 9:00 – Breakfast/Registration

9:00 – 9:10 –Introductions, opening remarks, housekeeping – Insightrix

9:10 – 9:30 – WSA presentation

9:30 – 10:30 – Discuss policy principles

10:30 – 10:40 – Break

10:40 – 12:00 – Discuss policy approaches

12:00 – 12:45 – Lunch

12:45 – 1:00 – Summarize discussion points regarding principles and approaches

1:00 – 1:45 – Discuss policy outcomes

1:45 – 2:30 – Discuss additional considerations

2:30 – 2:45 – Coffee Break

2:45 – 3:30 – Continue discussion on additional considerations

3:30 – 4:00 – Additional thoughts from participants

4:00 – 4:30 – Summary of items discussed & wrap up

Materials for Review:

The following ideas are presented for the group’s consideration. They reflect some of the ideas that have

arisen in discussions on the online forum and in past consultations on drainage.

Policy Principles – For consideration and discussion

1. Drainage is not a right; if potential or existing hydrological or environmental impacts cannot be

adequately mitigated, the drainage should not be allowed. Proponents must be educated to best

management practices around drainage.

2. The degree of regulation over the construction or operations of drainage works should reflect

hydrological and environmental risks.

3. Those who benefit from drainage should bear the costs of appropriate drainage design and

management, including damage prevention and mitigation.

Page 60: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

50

4. Where drainage is allowed, drainage projects should align with hydrological and environmental

objectives / targets that reflect both local circumstances and provincial objectives.

5. The responsibility for land control and civil liability for impacts rests solely with project owners.

6. The regulatory process should remain distinct from any process related to assessment of damages.

7. Parties claiming damages as a result of drainage should have adequate access to resolution and

compensation. Direct costs of the process should be reasonably assessed to the party causing the

impact.

Policy Goals – For consideration and discussion

1. Effective prevention, remediation and compliance tools to address risks and impacts of drainage.

2. Direction of resources and regulatory controls toward high risk activities and areas and away from

lower risk activities and areas.

3. Increased implementation of drainage best management practices and reduced hydrological and

environmental risks related to drainage.

4. Integration of the management of hydrological and environmental impacts and risks associated with

drainage.

5. Reduction of non-compliance with regulatory requirements to a reasonable and acceptable level.

6. Satisfactory and fair resolution of individual drainage disputes and costs borne by the offending

party.

Policy Approaches – For consideration and discussion

1. Classify and regulate drainage activities according to potential risks.

a. Require a registration, rather than an approval, to document the existence of drainage activity

where no approval to construct or operate is required.

b. Require best management practices and minimization and/or mitigation of risks as part of

standards and approval conditions.

c. Require approvals for those drainage activities that are in a high risk category or in areas with

high ecological/hydrological value or risk (e.g., closed basins/wetland impact).

2. Make existing drainage works subject to the approval/registration requirements.

a. Allow a period of time for owners of existing drainage projects to apply/register.

b. In some cases, owners may be required to close, alter, or remediate damages caused by existing

works.

3. In some cases, require specific design and operating conditions on approvals in order to mitigate

negative impacts on downstream water quality, aquatic habitat/wetlands, flooding, and natural flow

regimes.

Page 61: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

51

4. Consider both environmental and hydrological impacts and associated risks in the regulation of

drainage.

5. In areas of extensive drainage, enable the province to require organized drainage in order to

appropriately manage drainage activities and mitigate cumulative effects.

6. Put in place an effective compliance strategy that includes education and appropriate enforcement

powers, such as the ability to impose administrative penalties, voluntary payments, notices of

violation, stop work orders, orders for closure of works, orders requiring third party investigation and

orders for remedial action.

7. Enable the WSA to require remedial action where it determines that drainage activity has led to or

may pose a risk of significant environmental or hydrological damages, including damages related to

cumulative effects of multiple activities (e.g., flooding, erosion, sediment or nutrient increases in water

bodies/impacts on wetlands).

8. No longer require proof that land control has been registered against title as a condition of drainage

authorization. Make proponents aware of the legal risk and that they will bear liability if they choose

to proceed with drainage without registered land control.

9. Direct damages claims to a mediated or an arbitrated resolution or through the courts or a specific

tribunal.

Additional Considerations:

1. Risk-based regulation – considerations for registration, review and permits

2. Mitigating negative impacts of drainage – considerations for drainage limits and education

3. Encouraging organized drainage

4. Drainage & interest registration on land title (land control) – considerations & WSA’s role

5. Drainage complaint process – considerations for the following

a. WSA’s role

b. WSA’s authority & enforcement

c. Cost allocations for damages

6. Education on compliance – key messages

Page 62: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

52

APPENDIX III – QUESTIONNAIRE

WSA TELEPHONE / ONLINE SURVEY

Ver 3.1 (April 1, 2014)

Quotas

Method (based on sample) Sample size

Telephone interviews 300

Online panel

(estimated 50% response rate) 150

TOTAL 450

Respondent type (flexible –

do not terminate) Sample size

Farmer 350

Local government

representative 50

NGO, CAA, WS Association 30

General public 20

TOTAL 450

Introduction

[Online panel]

Dear Ag Drainage Online Citizen Panel member. Thank you for your continued participation in the online

community. Please take a few minutes to complete the following online survey. The results will be used

to help the WSA finalize components of the new agricultural drainage policy.

[Telephone] Hello! My name is ____________ and I am calling from Insightrix Research in Saskatoon. We

are conducting a survey on behalf of the Saskatchewan Water Security Agency with respect to issues

related to agricultural drainage. The survey will take approximately 12 minutes of your time. All the

information you provide will be kept strictly confidential and reported in an aggregate form only and the

results will be used to help the WSA finalize components of the new agricultural drainage policy.

Page 63: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

53

Background & Top of Mind Impressions

1. To begin are you a… (read list, select all that apply)

Farmer / primary producer (growing crops, raising livestock, etc.)

A representative of local government such as an RM, community, Reserve, or Metis Local

A representative of a community organization or NGO related to agricultural drainage

A representative of a Conservation and Development Area Authority or Watershed Association

None of the above

2. What first comes to mind when you think of agricultural drainage in Saskatchewan? (probe fully)

Record verbatim

3. Broadly speaking which of the following three statements best reflects your opinion as it relates to

drainage of water on agricultural lands? (read items)

[randomize order]

Agricultural drainage is essential to allow farmers to manage their land and maintain and improve the

viability of their operations and should be allowed to proceed with minimal restrictions.

Agricultural drainage poses a serious risk to downstream residents and landowners and to water

quality and should not be allowed.

Agricultural drainage is essential to agriculture, but must be carefully designed and implemented to

minimize downstream impacts [always last]

None of the above (do not read)

Prefer not to say (do not read)

[skip to next section if farmer NOT selected in Q1]

4. Are any parts of your farm land...

Suffering from insufficient drainage

Affected by upstream drainage

Neither (do not read)

Page 64: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

54

5. How much does agricultural drainage impact your farming operation in…(read list)

A positive way

A negative way

A great deal

Somewhat

Not very much

Not at all

Prefer not to say (do not read)

6. Within the past 5 years, have you drained any of your farm land by means such as construction of

permanent channels or ditches, landscaping, v-ditches, scraping, tile drainage, etc.?

Yes

No

Not at all

Prefer not to say (do not read)

Policy Opinions

7. In your opinion, how effective are current agricultural drainage policies at addressing risks and

impacts of drainage? This includes prevention, education, remediation and enforcement of

compliance. (telephone: would you say the current policy is…)

Very effective

Somewhat effective

Not very effective

Not effective at all

Not sure (do not read)

8. In your opinion, how important is it for Saskatchewan to develop a new agricultural drainage policy?

(read scale)

Very important

Somewhat important

Not very important

Not important at all

Not sure (do not read)

Prefer not to say (do not read)

Page 65: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

55

How important is it that a new agricultural drainage policy address each of the following? (read item and

scale)

[randomize order]

Preventing damage to downstream landowners and residents

Preventing erosion that would impact receiving lakes

Preventing negative impacts on water quality in receiving water bodies

Preventing downstream flooding

Very important

Somewhat important

Not very important

Not important at all

Not sure (do not read)

Prefer not to say (do not read)

9. Next I’m going to read out a number of potential things that could be considered part of a new

agricultural drainage policy and I’d like to know whether you would broadly support or oppose each

of these ideas? Please be assured there are no right or wrong answers. It’s just your opinion that

counts. (Telephone: The first one is… (read item SLOWLY then read the scale))

[randomize order]

Drainage should only be allowed if the negative impacts of such drainage can be minimized. [always

first]

All parties who benefit from drainage should bear the costs to design and manage such drainage

activities, including damage prevention.

Those who drain should be educated as to the best management practices around drainage.

The degree of regulation of drainage works should be based on the amount of risk involved (assume

that risk levels would be defined).

Regulatory requirements should be put in place to minimize non-compliance.

Processes should be put in place to ensure fair resolution of individual drainage disputes

Those who feel they are being negatively impacted by drainage should have adequate access to

compensation and resolution

Strongly support

Somewhat support

Somewhat oppose

Strongly oppose

Don’t know (do not read)

Prefer not to say (do not read)

Page 66: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

56

10. To the best of your knowledge, do all drainage activities currently require provincial government

approval, regardless of how big or small they are?

Yes

No

Not sure (do not read)

11. Moving forward how do you think the WSA should proceed with respect to high risk projects?

Should… (read options SLOWLY) (if necessary / display online: “Please base your answer on what you

deem to be a high risk project.”)

ALL high risk activities require approval

Require high risk activities to simply be registered with the government through an online process

Allow high risk activities to proceed without notifying the government at all

Something else: __________________

Not sure (do not read)

12. And moving forward, how do you think the WSA should proceed with respect to lower risk

projects? Should… (read options SLOWLY) (if necessary / display online: “Please base your answer on

what you deem to be a low risk project.”)

ALL low risk activities require approval

Require low risk activities to simply be registered with the government through an online process

Allow low risk activities to proceed without notifying the government at all

Something else: __________________

Not sure (do not read)

13. Thinking about existing drainage works that have not received provincial government approval, do

you feel that such works…

Should be allowed to continue without any approval or registration

Should be simply registered with the provincial government through an online process

Should require approval or registration consistent with the new policy within a reasonable time frame

such as 5 or 10 years

Something else: __________________

No opinion on the matter (do not read)

Not sure (do not read)

Page 67: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

57

14. For new and or existing projects that will require an approval, do you agree or disagree with each of

the following? (read item, scale)

[randomize order]

The applicants will need to follow specific design and operation standards and rules

Private, qualified professionals will be required to approve drainage works.

Project organizers will be required to repair any damages caused

Strongly agree

Somewhat agree

Somewhat disagree

Strongly disagree

Depends on the situation

No opinion on the matter (do not read)

Not sure (do not read)

15. Thinking about wetlands, please rate your agreement with each of the following statements: (read

item, scale)

[randomize order]

Wetlands are very important and while drainage activities that remove floodwater from fields are fine,

all wetlands should be retained.

Drainage of wetlands is an acceptable part of agriculture because it is unrealistic to expect farmers to

give up the potential production or to drive large machinery around many small wetlands.

Drainage of wetlands is acceptable, but the policy should ensure that some larger, more permanent

wetlands are retained.

Strongly agree

Somewhat agree

Somewhat disagree

Strongly disagree

No opinion on the matter (do not read)

Not sure (do not read)

Page 68: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

58

16. With respect to education, there are some options being considered. Do you agree or disagree with

each of the following? (read item, scale)

The government should provide access to useful educational materials on drainage best

management practices.

The government should require those who undertake drainage to acquire certification before

draining, similar to obtaining a Driver’s Licence before being able to operate a vehicle. (such

certification would be developed by the government)

The government should provide an incentive to those who acquire certification in the form of fast-

tracked approvals.

Strongly agree

Somewhat agree

Somewhat disagree

Strongly disagree

No opinion on the matter (do not read)

Not sure (do not read)

[put the next two questions on the same page]

17. In areas where there is extensive drainage activity, the provincial government is considering options

related to the formation of organized drainage authorities. Please rate your agreement with each of

the following statements. (read item, scale)

Landowners in these areas should continue to voluntarily come together to form legal entities to

facilitate organized drainage as is currently the case.

The province should be able to require the formation of organized drainage authorities in these

areas.

The provincial government simply disallowing any new drainage in these areas until the formation of

an organized drainage authority is created, regardless of whether such organizations form on their

own or through government intervention.

Strongly support

Somewhat support

Somewhat oppose

Strongly oppose

No opinion on the matter (do not read)

Not sure (do not read)

Page 69: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

59

18. Do you support or oppose having high risk drainage license requests posted on the WSA website for

public consultation before approval? (read scale)

Strongly support

Somewhat support

Somewhat oppose

Strongly oppose

Not sure (do not read)

19. Turning to compliance and enforcement, which of the following two options would you prefer? (read

items)

[randomize order of statements]

The government proactively enforces compliance with regulations such as fines, penalties, stop

work orders, etc.

OR

The government relies on a complaint-based enforcement system from landowners and then

investigates the situation

Don’t know (do not read)

20. Regardless of which method is used, do you support or oppose the WSA having enforcement

powers to impose things like administrative penalties, voluntary payments, notices of violation, stop

work orders, orders for closure of works, and orders for remedial action related to agricultural

drainage? (read scale)

Strongly support

Somewhat support

Somewhat oppose

Strongly oppose

Not sure (do not read)

Prefer not to say (do not read)

Page 70: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

60

21. Presently, a licensed drainage project requires the registration of an easement on land titles if water is

crossing over someone’s land. Going forward, there are three options the government is considering.

Which approach would you support? (read items)

Keep things as they are now (i.e. require that the WSA see a registration on land title before

approving licensed drainage)

Require an agreement or contract from the parties involved indicating that they are aware of and

accept the impacts of the drainage activity.

Simply make proponents aware of the legal risks and that they will bear liability if they choose to

proceed with drainage without registered land control.

Another option: ______________

Not sure (do not read)

Demographics

Finally, we have a few more questions to help us profile your answers. Please be assured that your

answers will be kept strictly confidential.

22. Have you ever been involved in a drainage complaint?

Yes

No

23. What is your main farm activity? (read list if necessary)

Grains and other crops

Livestock and cropping (i.e. mixed farm)

Livestock only [skip next question]

Horticulture, Vegetables or Fruits

Other: Please specify__________

24. How many cultivated acres will your farming operation be this coming season, including land you may

rent?

(Notes for interviewers:

640 acres are in a section and 1 section = 4 quarters

160 acres are in a quarter

80 acres = .5 of a quarter

40 acres = .25 of a quarter)

Page 71: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

61

____ cultivated acres [0 decimals, copy response over to new variable]

OR

_____ quarters [allow for 2 decimals; calculate acres and put in new variable][programming – use

question from Ag Land Lease study]

Not sure/Prefer not to say

25. Record gender / Please indicate your gender

Male

Female

26. Into which of the following age ranges do you fall? (read list)

18 to 34

35 to 44

45 to 54

55 to 64

65+

Prefer not to say (do not read)

27. What is the highest level of education you have achieved? (read list if necessary)

Some high school

Completed high school

Some technical school or college

Completed technical or college diploma

Some university

Completed university degree (Undergrad, Masters or PhD)

Prefer not to say (do not read)

28. This concludes our study. Do you have any other comments to add? [not required]

Textbox

Page 72: Market Research Proposal for SaskTel WSA/News Releases/Agricultural... · A key element of this plan relates to the drainage of water on agricultural lands. To collect input from

62

29. In this study, we are attempting to reach as many farmers and other stakeholders as possible. Would

you be willing to give me the name and telephone number of anyone else that you believe would

want to provide input on what we discussed this evening?

Name: ____________

Phone number: ___________

Once again thank you very much for your participation…it is greatly appreciated. Have a great day!!