MARSH 1 July 4, 2022 Achieving a successful outcome for a major Energy loss

MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

Embed Size (px)

Citation preview

Page 1: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 1April 21, 2023

Achieving a successful outcome for a major Energy loss

Page 2: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 2April 21, 2023

Claims Scenario

Introductions

Scene Setting

Page 3: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 3April 21, 2023 321 April 2023

Page 4: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 4April 21, 2023

Preparation & Prevention

Important to start on the right foot - set the tone

for the way the claim will proceed

Has the policy been triggered?

Plan of action

Communicate loss to insurers

Prove your claim!

Understand the clients business, client training,

wording analysis, claims protocol, provide claims data, case studies

Lessons learnt, feedback to placing team, training opportunity for colleagues

What is the desired outcome?

Collection of funds

Are the clients rights being protected?

Notification and Acknowledgement

Coverage

Claim Strategy

Insurer Contact

Information Gathering and Analysis

Negotiation

Settlement

Subrogation Management

Appointment of FACS?

Post Loss Analysis

Page 5: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 5April 21, 2023 521 April 2023

Fertilizer production plant with on site single train ammonia manufacturing plant

4.30 am 25th April 2012 - Fire occurring at the lubrication oil console for the Syngas compressor at the ammonia plant.

Initial indication of cause is an oil leak. Understand a Third Party Maintenance Contractor was working in the area earlier in the day.

Claims scenario: Fire Incident

Page 6: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 6April 21, 2023 621 April 2023

Fire Incident

Page 7: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 7April 21, 2023 721 April 2023

Insurance Claim Timeline Claim Closed

Date Of Loss - 25/04/2012

Page 8: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 8April 21, 2023

First Response

• The field operator immediately alerted the control room staff which then led to the first intervention team on site tackling the issue. The onsite fire fighting team responded immediately and successfully prevented the fire spreading to other critical items . Despite their efforts both the lube oil console and Syngas compressor were lost. This resulted in an emergency shutdown of the ammonia plant.

• All personnel accounted for and confirmed no injury or loss of life.

• Evaluation of site safety & loss mitigation

Fire Incident

Page 9: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 9April 21, 2023

Claims Scenario

Notification; requirements & significance

Page 10: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 10April 21, 2023 1021 April 2023

Claim proceduresIncident notification

Notification requirements under the policies:

• Energy Package Policy

Notice of every occurrence which may become a claim as soon as reasonably practicable on becoming aware of such an occurrence.

• Liability Policy

Details of any possible third party property damage or bodily injury / receipt of any notice (verbal or written) of any potential claim.

Page 11: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 11April 21, 2023

Claim proceduresIncident notification – Deductibles

• Plant Physical Damage Deductibles:

$250,000

$1,000,000

$5,000,000

• Plant Business Interruption Waiting Periods:

30 Days

45 Days

60 Days

Do you know your deductible?

Deductibles can be used as a guide whether or not to notify a loss incident.

IF IN DOUBT IT IS ALWAYS BEST TO NOTIFY!

Do you know your Waiting Period?

Page 12: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 12April 21, 2023 1221 April 2023

Loss Incident Report FormInsured: Name and Address

Loss location: Affiliate Fertilizer production plant with on site single train ammonia plant

Date and time of loss: 25th April 2012 at 4:30am

Details of incident: Fire occurring at the lubrication oil pump for the Syngas compressor at the ammonia plant

Damage: The lube oil pump and Syngas compressor were lost and this then resulted in an emergency shutdown of the ammonia plant

Estimated quantum: - Property Damage - ??- Expected Downtime – ??

Potential for recovery: Currently Unknown

General Remarks: Personnel Injury, 3rd party claim intimations

Contact Details: Insert details of who should be contacted for further information

Fire Incident

Page 13: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 13April 21, 2023 1321 April 2023

Insurance Claim Timeline Claim Closed

Date Of Loss - 25/04/2012

Loss Notification 25/05/2012

Current Loss Reserve

PD: TBA

Downtime: TBA

Page 14: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 14April 21, 2023

Hypothetical Claims Scenario

Insurance Notification Flow

Page 15: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 15April 21, 2023 1521 April 2023

Actions taken during the first hours and days following the occurrence of an incident are extremely important and a well prepared Insured, who execute best practice, will generally be able to optimize (in both speed & quantum) the recovery from their insurance program.

“”

Page 16: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 16April 21, 2023 1621 April 2023

Loss ScenarioInsurance Notification Flow

Risk Management

Affiliate Loss Location

Marsh

Loss Adjuster

(Local Insurer)Global Reinsurers

Complete ‘Incident Report Form’ (appendix A) and forward to Risk Management

Review ‘Incident Report Form’ and forward to Marsh as appropriate.

Acknowledge loss notification to RM & Affiliate and offer any preliminary advice/instructions.

Review ‘Incident Report Form’ and forward to local Insurer and Global Panel as appropriate.

Record notification and comment.

Select loss adjuster/lawyer (as applicable) via marsh.

Make contact with Affiliate to arrange site visit.

Issue reports via Marsh.

•Record notification and comment.•Select loss adjuster/lawyer (as applicable) via marsh.

Page 17: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 17April 21, 2023

Claims Scenario

Information Gathering & Post Incident Actions

Page 18: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 18April 21, 2023

Loss Adjuster Initial Meeting Agenda

• Presentation of involved personnel

• Role of Loss Adjuster & some basic working rules

• Brief description of the plant and company

• Details of equipment, drawing and main specifications

• Damage inspection

• Event description, causation, findings from investigations etc.

• Third party aspect.

• Production loss suffered so far and ahead

• Extra costs of working (over and above normal costs)

• Physical damage, inspection and testing

• List of main items to be repaired

• List of main items to be replaced

• Planned scope, time schedule and organization of damage rectification

• Details of potential modifications that may influence costs or time schedule

• On-site engineering resources

• Costs accounting and control• Review of loss estimate

Page 19: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 19April 21, 2023

Example of Detailed Information Request - Compressor failure• Who designed, manufactured, supplied, installed, commissioned operated and maintained the compressor ?

• Why was the compressor shut down and what were the operating variables that led to this decision?

• What was the operating regime of the compressor prior to shut down, eg start-up, normal duty, max duty, or was it actually running down at the time of any incident?

• What was the sequence and nature of alarms and trips that preceded the shut down and what were the alarm and trip levels applied?

• Had the compressor experienced a history of shut downs under similar circumstances?

• What was the history of alarms and trips for the compressor train as a whole, ie including the prime mover and power supply?

• What are the normal operating variables for the compressor?

• Have there been any unusual changes in the normal operating variables of the compressor train as a whole since it was commissioned?

• What were the balancing/alignment problems experienced during commissioning, if any?

• Are there other similar compressor trains in operation at the plant and have they experienced any problems or unusual trends in operation?

• What maintenance has been performed on the failed compressor train, including running maintenance and replenishment of lubricant?

• What is the specification of the lubricant, is it routinely sampled for analysis and if so what are the results?

• Was the compressor a cause of the failure or a consequence of a failure elsewhere?

• What components do we need to preserve for investigation purposes?

• What extent of oil pressure, oil flow and vibration monitoring was applied to the unit: where are the sensors located?

Page 20: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 20April 21, 2023 2021 April 2023

Claim proceduresPost incident actions

• Take all reasonable steps to prevent further damage. Acting at all times as a prudent uninsured.

• Prior to commencement of dismantling/repair work, take photographs of the incident scene and the damaged equipment/parts– use of video footage is becoming more common

• Preserve damaged equipment/parts for further inspection by the appointed Loss Adjuster / External Experts– protect from the elements– Designated ‘Lay Down Area’

• Notification to third parties holding them responsible for loss in order to preserve Insurer’s rights of recovery.

Page 21: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 21April 21, 2023 2121 April 2023

Claim proceduresPost incident actions

• Investigate the loss & identify cause(s)– Root cause analysis essential to the adjustment of the claim essential to prevent recurrence– secure documents, drawings, specifications etc.– obtain witness statements

• When a Loss Adjuster is appointed, agree expenditure and actions in advance with him

– need to establish a primary contact for communications with the Loss Adjuster

Page 22: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 22April 21, 2023

Post Incident ActionsThe importance of Cause and Origin

Underwriting– Statistics– Loss prevention

Subrogation Not employees Equipment vendors Contractors

World class experts in relevant specializations may be

employed to determine cause.

Page 23: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 23April 21, 2023

Claim proceduresPost incident actions - PD Assessment Protocol

• Inspection

• Determination of most economic repair options

• Options discussed with BI team for their approval

• Agreement on methodology of testing and interpretation of results

• Agreement with Insured on proposed repair-replacement

• Discussion with BI team on economics of expediting; overtime, air-freighting, domestic or import procurement

• Review all tender bids and appraise final choice

• Preparation of critical path schedule for repair stages

Page 24: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 24April 21, 2023 2421 April 2023

Claim proceduresPost incident actions

• Effect temporary / emergency repairs required to resume operations.

• Obtain witness statements as soon as possible while memories are clear.

• If applicable restore fire protection to site.

Page 25: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 25April 21, 2023 2521 April 2023

Claim proceduresPost incident actions

• Open a claim file Keep duplicates of all information given to other parties (loss adjusters,

brokers, contractors, licensors, suppliers, vendors, consultants etc.) Document everything.

• All expenses relating to the loss should be carefully recorded via allocated cost-center including:

– repair and replacement costs

– labor & supervision (time sheets)

– expenses incurred to mitigate the loss (labor, emergency response, equipment etc.)

Page 26: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 26April 21, 2023 2621 April 2023

Claim proceduresPost incident actions

• Third partly liability claims:– Do not admit to or assume responsibility / fault for the injury or

damage (even verbally)– Cooperate fully with legal authorities– Do not guarantee payment for any damages or injuries– Open a claim file in which duplicates of all relevant documentation

should be held– After initial contact, limit communications with any third party

claimants– Any communication received from a third party should be forwarded

without reply to Risk Management.

Page 27: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 27April 21, 2023 2721 April 2023

Claim proceduresPost incident actions

• Claims progress reporting

• Preservation of recovery opportunities – protect insurers rights of recovery against third parties – do not prejudice

possible subrogation actions– disposal of scrap and debris, salvage etc. to be agreed with Loss

Adjuster

Page 28: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 28April 21, 2023

2 months since incident…

• Loss adjuster has visited site and made an initial assessment

• Document request list has been submitted to Local Affiliate

• Preliminary report has been submitted to Insurers with an initial reserve

• Root Cause Analysis is being finalized

• Loss Location has now completed their reinstatement/repair plan and have decided to make some modifications from the original specification which will allow an increased throughput. Estimated lead time for procurement and commissioning of new units is 12 months

• Following adjuster visit, the site can now be cleared, with damaged units safely stored to preserve for any future analysis.

• Loss adjuster has requested financial information in order to calculate the potential business interruption exposure.

Fire Incident

Page 29: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 29April 21, 2023 2921 April 2023

Insurance Claim Timeline Claim Closed

Date Of Loss - 25/04/2012

Loss Notification

Loss Adjuster Visit

RCA?Adjusters Preliminary

Report is issued to Insurers

Current Loss Reserve

PD: $20m

BI: $200m

Page 30: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 30April 21, 2023

4 months since incident…

• 4 months since incident…

• Root Cause Analysis issued: cause was a failure of a ½“line at a connecting joint. The failure of the line is a result of inadequate torqueing/maintenance error. The failure of the line resulted in a spray of hot lube oil on a hot surface, providing a case for auto-ignition of the lube oil.

• Loss Adjuster has confirmed to Insurers that cause is accurate and that policy liability is engaged.

• Request for Advance Payment

• Due to the damage of the existing gantry crane it is necessary for Local Affiliate to hire a temporary crane in order to remove the damaged units. This cost will be given consideration under the ‘Extra Expenses’ provision in the policy as it will reduce total downtime.

• Local Affiliate has submitted financial data to loss adjuster, along with latest downtime estimates.

Fire Incident

Page 31: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 31April 21, 2023

Property Damage Claim Submission:

Compressor & Lube Oil Pump USD 22,500,000

Instrumentation USD 350,000

Compressor House USD 420,000

Facility Rack USD 1,100,000

Gantry Crane USD 130,000

Others USD 72,000

Total USD 24,572,000

Application for PD Advance USD 2,000,000

Fire Incident

Page 32: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 32April 21, 2023

Business Interruption Estimation:

Estimated Total Downtime 450 days

Gross Profit per Day $525,000

Temporary Crane Hire $98,000

Waiting Period 60 days

Total Loss of Profit 450 x $525,000 = $236,250,000

Less Waiting Period 60 x $525,000 = $31,500,000

Crane Hire = $98,000

Net Claim $204,652,000

Application for BI Advance $?????????

Fire Incident

Page 33: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 33April 21, 2023 3321 April 2023

Insurance Claim Timeline Claim Closed

Date Of Loss - 25/04/2012

Loss Notification

Loss Adjuster Visit

RCA

Adjusters Preliminary Report is issued to

(Re)Insurers

Current Loss Reserve

PD: $20m less $2m POA

Downtime: $200m less ?? POA

Initial Coverage Analysis

Interim Report issued recommending POAPartial Claim Submission

Page 34: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 34April 21, 2023

August 2013

• All reinstatement and commissioning works were completed by 14th July 2013

• Plant resumed full operation as of 19th July 2013 (450 days since loss incident).

• Final claim submission has now been submitted to loss adjuster. Loss adjuster has now completed his final report which includes a recommendation for full and final settlement of the claim.

Fire Incident

Page 35: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 35April 21, 2023

Property Damage Claim Submission:

Fire Incident

Claimed (USD) Adjusted Amount (USD)

1. Compressor 22,500,000 18,000,000

2. Instrumentation 350,000 350,000

3. Compressor House 420,000 420,000

4. Facility Rack 1,100,000 1,100,000

5. Gantry Crane 130,000 130,000

6. Others 72,000 57,000

Less Deductible -1,000,000 -1,000,000

23,572,000 19,057,000

Page 36: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 36April 21, 2023

Final Business Interruption Claim:

Total Downtime 450 days

Less Waiting Period 60 days

Less Re-design Period 60 days

Less Planned Turnaround 50 days

Indemnifiable downtime 280 days

Total Loss of Gross Profit 280 days x $525,000 = $147,000,000

Crane Hire = $98,000

Net Claim = $147,098,000

Fire Incident

Page 37: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 37April 21, 2023

Final Settlement

Net Property damage $19,057,000

Net Business Interruption $147,098,000

Total Net Loss $166,155,000

Less First Advance $32,000,000

Less Quarterly Advance Payments $100,000,000

Final Payment USD = $34,155,000

Fire Incident

Page 38: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 38April 21, 2023 3821 April 2023

Insurance Claim Timeline Claim Closed

Date Of Loss - 25/04/2012

Loss Notification

Loss Adjuster Visit

RCA

Adjusters Preliminary Report is issued to

(Re)InsurersInitial Coverage Analysis

Interim Report issued recommending Advance

Partial Claim Submission

Settlement Negotiations Final Report

Final Claim Submission Final Coverage Analysis

Sign Proof of Loss

Collect and transfer funds

Insurers Agreement

Page 39: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 39April 21, 2023

HOW DID IT WORK OUT ?

Did the process start off correctly ?

Was there early acknowledgment that policy been triggered?

Was there a clear plan of action

Was the Communication with insurers effective ?

Did you prove your claim!

Were Lessons learnt recorded and acted on ? Were the training opportunity for colleagues

achieved ?

Did you achieve the desired outcome?

Were all funds collected timely ?

Were all the rights protected?

Notification and Acknowledgement

Coverage

Claim Strategy

Insurer Contact

Information Gathering and Analysis

Negotiation

Settlement

Subrogation Management

Post Loss Analysis

Page 40: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 40April 21, 2023

Key requirements for Successful Outcomes

• Leadership

• Team Approach

• World Class Experts and Adjusters

• Regular Reviews and Updates

• Communication – No Surprises for either party

• Timely and reliable information is critical

Page 41: MARSH 0 May 15, 2015 Achieving a successful outcome for a major Energy loss

MARSH 41April 21, 2023

Questions?