Upload
phungtu
View
226
Download
3
Embed Size (px)
Citation preview
www.dot.state.pa.us
MASH Planning and Implementation for PennDOT
2016 TransportationEngineering and Safety Conference
Mark R. Burkhead, P.E.Bureau of Project Delivery
www.dot.state.pa.us
MASH differences
W-beam issues
Bridge barriers and approaches
DM-2 and other issues
Some content provided by John Durkos, Chair Task Force 13, RSI Inc.
www.dot.state.pa.us
Evolution of Crash Test Procedures
www.dot.state.pa.us
AASHTO-FHWA MASH 2016 Joint Implementation Agreement
January 7, 2016 FHWA Memo For contracts on the National Highway System with a letting
date after the dates below, only safety hardware evaluated using the 2016 edition of MASH criteria will be allowed for new permanent installations and full replacements: December 31, 2017: W-beam barriers and cast-in-place
concrete barriers June 30, 2018: all W-beam terminals December 31, 2018: cable barriers, cable terminals, and crash
cushions December 31, 2019: bridge rails, transitions, all other
longitudinal barriers (including portable barrier installed as permanent), all other terminals, sign supports, and all other breakaway hardware
www.dot.state.pa.us
Manual for Assessing Safety Hardware (MASH) - 2009
MASH09 Replaced Report 350
Changes to mass Impact angle changes for
certain terminal tests
www.dot.state.pa.us
MASH 09
Changes to mass from Report 350
www.dot.state.pa.us
MASH 09
Changes to impact conditions from Report 350
www.dot.state.pa.us
W-beam Issues
Height sensitivity 350 pickup 27 Top of Rail is right at the performance limit
MASH pickup 27 Top of Rail marginal 27 Top of Rail not so good
www.dot.state.pa.us
MASH at 27 Top of Rail
www.dot.state.pa.us
PA Weak Post System
Generally, barriers in RCs are 350 compliant 27 system very common among states
Weak post tested to 350 In 2000 it was tested It failed
Re-design moved splice to mid-span and height to 32
Current PennDOT weak post has been tested to MASH09 seriously it has
www.dot.state.pa.us
Old Weak Post
www.dot.state.pa.us
Re-design
www.dot.state.pa.us
Weak Post System
During development of MASH, Texas A&M Transportation Institute (TTI) did studies on differences between 350 and MASH
New 2-W system tested and passed! Some work for full eligibility remains
Small car test, etc.
www.dot.state.pa.us
MASH Test
www.dot.state.pa.us
Strong Post System
New 31 Strong Post System Type 31-S Modified MGS
8 blocks No new
component parts
www.dot.state.pa.us
Transition
2-S to 31-S transition
www.dot.state.pa.us
W-beam Transitions
W-beam transitions RC-54 Work in progress
www.dot.state.pa.us
More Implementation Issues
W-beam terminals sun-set by June 30, 2018 Manufacturers of End Treatments and Crash
Cushions are responsible for their hardware (testing, evaluations, FHWA Eligibility) Not gonna be cheap!!
Some old products may just fade away Currently no manufacturers have applied for
Bulletin 15 listing of any MASH end treatments
www.dot.state.pa.us
More Implementation Issues
All DOTs manage their new product review/approvals differently.
AASHTO has been contacted to attempt to establish consistency and continuity with product submittals across the US.
AASHTO reached out to a few of the DOTs identified as having a good system in place for reviewing vendor product approval submittals.
Will be topic at the next TCRS meeting.
www.dot.state.pa.us
Bridge Barriers
Bridge railings Changes to
load and impact height
MASH TL-4 with 32 concrete barrier
www.dot.state.pa.us
Bridge Barriers
NCHRP Project 20-07, Task 395 Initiative to evaluate all State DOT bridge barriers
(approx. 74) to sort of triage for possibility of submission without further work
Extensive survey to all State DOTs Results anticipated summer 2017 May not be definitive Still need full development and submission to FHWA
Where does that leave us? Pursue existing bridge barriers Look to other sources for similar barriers that serves the
same needs
www.dot.state.pa.us
PennDOT Bridge Approach Transition
Our Typical Bridge Approach Transition is Report 350 compliant at TL-4 RC-50, Sheets 1-3
www.dot.state.pa.us
PennDOT Bridge Approach Transition
Report 350 TL-4 test
www.dot.state.pa.us
Approach Transitions
Decisions decisions Pursue PennDOT transitions
Would require revisions and testing See what Task 395 produces in terms of bridge barriers
Results due June 2017 Look to other sources
Pooled Fund project stacked W-beam panels Initial crash test failed Work underway to resolve problems and retest Results not expected until last half of 2017
www.dot.state.pa.us
DM-2 Update Efforts
Update and reorganization of DM-2, Chapter 12 -Guide Rail, Median Barrier, and Roadside Safety Devices Updates for coordination with Pub 242 and Pavement
Preservation Guidelines Revisions for new Type 31-S Device listings being moved to Appendices Temporary barrier clarifications Other minor clarifications
www.dot.state.pa.us
Other Devices/Issues
Temp. work zone devices, including portable barriers, manufactured after Dec. 31, 2019 must meet MASH 2016. Devices manufactured on or before this date, and tested to Report 350 or MASH 2009 can be used through normal service life.
All 350 or MASH 2009 compliant permanent hardware may remain in place unless damaged beyond repair
www.dot.state.pa.us
Other Devices
How will MASH apply to all work zone devices Arrow boards/panels Trailer mounted temporary signals Self-certified devices Portable VMS WZ sign/sign stands
Number of variations to test may be prohibitive
Questions that AASHTO must answer
www.dot.state.pa.us
Coordination Tentacles
MASHDM-2
RCs
TCs
BDs/BCs
Pub 33
Maint. Manual
Pub408
DM-3
Pub652
www.dot.state.pa.us
Tentacles
Affects Majority of all construction contracts Maintenance Forces projects Maintenance repairs (internal and contract) Just about everything we do when on the roadways
www.dot.state.pa.us
Other Sources
Roadside Safety Research for MASH Implementation Pooled Fund Study, TPF-5(343) Formerly Roadside Safety Pooled Fund Study (now 17
states) Meeting October 25-26, 2016
All 2017 funded tasks related to MASH Implementation CIP barrier foundation for TL-4 MASH Thrie-beam bullnose MASH composite blockout retrofit Stacked W-beam transition
www.dot.state.pa.us
Next
Open End Consultant Agreement executed Work orders for defined scopes of work Accredited testing facility is included in team Schedule development underway
Continued coordination/communication with Pooled Fund group, FHWA, AFB20 (TRB), TCRS (AASHTO), Task Force 13, ATSSA
Weve got a long way to go and a short time to get there
www.dot.state.pa.us
Questions???
MASH Planning and Implementation for PennDOTSlide Number 2Evolution of Crash Test ProceduresAASHTO-FHWA MASH 2016 Joint Implementation AgreementManual for Assessing Safety Hardware (MASH) - 2009MASH 09MASH 09W-beam IssuesMASH at 27 Top of RailPA Weak Post SystemOld Weak PostRe-designWeak Post SystemMASH TestStrong Post SystemTransitionW-beam TransitionsMore Implementation IssuesMore Implementation IssuesBridge BarriersBridge BarriersPennDOT Bridge Approach TransitionPennDOT Bridge Approach TransitionApproach TransitionsDM-2 Update EffortsOther Devices/IssuesOther DevicesCoordination TentaclesTentaclesOther SourcesNextSlide Number 32