    Last Mile Program UpdateMay 10, 2016

    1

  • 8/17/2019 Mass Broadband Iniative

    2/15

    • We have conducted and concluded an intensive program review in

    collaboration with the MBI.• The MBI is shifting to a more flexible, responsive program framework

    which prioritizes affordable and sustainable solutions and embraces arange of technology and operating options.

    • The new course marks a change for MBI which up to now has been

    constrained by irreconcilable expectations for speed, coverage,affordability, and a one-size fits all solution.

    • We are prepared to move forward quickly and to partner with townsto discuss options and plans.

    Goals:1. A strong collaborative partnership between the Administration, the

    MBI, providers, and towns.

    2. Rapid development and implementation of sustainable, reliable

    broadband expansion projects 2

    Program Update

  • 8/17/2019 Mass Broadband Iniative

    3/15

    We have announced two new Advisors for the Last Mile program:

    Peter Larkin: Special Advisor to the Secretary• Will advise the Administration on the go-forward plan for community

    engagement and project implementation

    • Will be Secretary Ash’s designee to Chair the MBI Board of Directors• MBI’s advocate for success, and will help ensure community interests are

    heard and properly vetted

    Bill Ennen: Last Mile Implementation Liaison• Working alongside the MBI staff to help troubleshoot and expedite to get the

    best possible outcome in the shortest possible time

    • Provides a consultative role to town leaders and MBI staff with regard toverifying each town’s path forward

    • Will be based in Western Mass3

    Advisors

  • 8/17/2019 Mass Broadband Iniative

    4/15

    We are moving ahead with a fresh look.• Our shared goal is reliable, sustainable, affordable broadband

    access for residents.

    • We understand that there is no one-size-fits-all model for all towns.

    • We will support projects that provide access to minimum speedrequirements, demonstrate viable funding and financing plans, andachieve operating sustainability.

    • We are willing to support a range of technology, collaboration, and

    operating choices.• The MBI, Special Advisor, and Implementation Liaison will engage

    directly with Towns locally to propose and develop solutions.

    • We want progress as quickly as possible.

    4

    Pathway Forward

  • 8/17/2019 Mass Broadband Iniative

    5/15

    There is no one-size-fits-all solution.However, there are several different projectmodels and technology options that may work:

    5

    Several Viable Models

    Models:• Expansion by Private

    Provider • Extension of Existing

    Cable Infrastructure• Multi-Municipal

    Network• Independent

    Municipal Network• Pilot Projects

    Funding andFinancing:

    • MBI/State GrantFunding

    • Private PartnerInvestment

    • Municipal Investment:

    • USDA Loan Program• State House Notes• Qualified Bond

    Program• Potential Federal

    Funding (FCC CAF II)

    TechnologyOptions:

    • Fiber • Wireless• Cable• Hybrid Systems

  • 8/17/2019 Mass Broadband Iniative

    6/15

    To receive state investment support, projects will need tomeet some minimum baseline requirements.

    6

    Baseline Requirements

    Minimum ProjectRequirements:

    • Project’s technology must provideaccess to broadband speeds asdefined by the FCC (25/3)

    • Project must be capable ofdemonstrating long-term operatingsustainability without ongoing statesubsidy

    • Project must be affordable

    • Project should seek a minimum goal of96% residential coverage in its servicearea

    • Endorsed by MBI professional staff • Financing Endorsed by DLS (as

    needed)• Approved by MBI board

    Technology andOperations:

    • Preference for network operationsto be managed by experiencedprofessional partners whenpossible

    • Many technology choices: fiber,wireless, cable, and/or hybridsolutions

    • Preference for utilization ofMassBroadband 123 network whenappropriate

  • 8/17/2019 Mass Broadband Iniative

    7/15

    7

    Communities by Residential Broadband Provider

  • 8/17/2019 Mass Broadband Iniative

    8/15

    We are reaching out to providers about

    potential expansion:

    8

    Engaging with Providers

    Company Comcast Verizon Charter Frontier FairpointMid

    HudsonX5 Crocker

    HilltownWireless

    HolyokeG&E

    WestfieldG&E

    HQ Philadelphia,PANew York,

    NYStamford,

    CTNorwalk,

    CTCharlotte,

    NCCatskill,

    NYSeattle,

    WASpringfield,

    MAAshfield,

    MAHolyoke,

    MAWestfield,

    MA

    CEOBrian

    RobertsLowell

    McAdamTom

    RutledgeDaniel

    McCarthyPaulSunu

    JamesReynolds

    GregForrest

    MatthewCrocker

    ChristopherGray

    JamesLavelle,

    GM

    DanHoward,

    GM

    CY 2015Revenue

    $75 billion$131

    billion$10

    billion$5.5

    billion$900

    million$25

    million$70

    million$66 million

    Number ofEmployees

    153,000 177,000 25,000 19,000 2,700 50 50Less than

    30

    SubscriptionsServed

    27million

    145million

    6.7million

    3.4 million 750,000 40,000

  • 8/17/2019 Mass Broadband Iniative

    9/15

  • 8/17/2019 Mass Broadband Iniative

    10/15

    Using these models and available information, the MBI

    will develop and start posting individual readiness statusreports for each town.

    Example Readiness Elements Include:

    10

    Project Readiness

    Town Preferences and Actions

    • Establish a Local ProjectModel Preference

    • Take Local Actions: Bond Authorization and DebtExclusion (if necessary)

    • Establish MLP(if necessary)

    • Establish Inter-Municipal Agreements (if necessary)

    Financing and Funding

    • Review MBI Cost andSustainability Analyses

    • Understand and ConfirmTotal Project Costs

    • Examine and PursueFunding Options

    • Confirm and Review

    Financing Options withFinancial Advisor and BondCounsel

    • Develop Financing Plan withFinancial Advisor and BondCounsel

    • Local Borrowing PlanEndorsed by either DLS orUSDA

    Project Details

    • Review and SelectTechnology Options

    • Review and Select RegionalCollaboration Options

    • Review and SelectOperator/ISP

    • Develop and Confirm a

    Sustainable Business Plan

  • 8/17/2019 Mass Broadband Iniative

    11/15

    We are prepared to engage directly witheach town individually or as collaboratives tosupport and review projects.

    11

    How We Work Together

    ReviewMaterials

    Town

    Decision-Making

    Project Approval

    andFunding

    MBI/

    StateReview

    MBI TracksStatus via

    ReadinessReport

    Meetingsand Support

    Project Models

    Funding and

    Financing

    Technology &Operations

    Project

    Submissionto MBI

    Process will be iterative and collaborative, butalso time-bound with deadlines!

  • 8/17/2019 Mass Broadband Iniative

    12/15

    Appendix

    12

  • 8/17/2019 Mass Broadband Iniative

    13/15

    13

    List of Program Towns

    Town CountyMONTGOMERY HAMPDENMOUNT WASHINGTON BERKSHIRENEW ASHFORD BERKSHIRENEW BRAINTREE WORCESTERNEW MARLBOROUGH BERKSHIRENEW SALEM FRANKLINNORTHFIELD FRANKLINOTIS BERKSHIREPELHAM HAMPSHIRE

    PERU BERKSHIREPETERSHAM WORCESTERPLAINFIELD HAMPSHIREPRINCETON WORCESTERROWE FRANKLINROYALSTON WORCESTERSANDISFIELD BERKSHIRESAVOY BERKSHIRE

    SHELBURNE FRANKLINSHUTESBURY FRANKLINTOLLAND HAMPDENTYRINGHAM BERKSHIREWARWICK FRANKLINWASHINGTON BERKSHIREWENDELL FRANKLINWEST STOCKBRIDGE BERKSHIREWINDSOR BERKSHIREWORTHINGTON HAMPSHIRE

    Town County

    ALFORD BERKSHIRE ASHFIELD FRANKLINBECKET BERKSHIREBLANDFORD HAMPDENBUCKLAND FRANKLINCHARLEMONT FRANKLINCHESTER HAMPDENCHESTERFIELD HAMPSHIRECOLRAIN FRANKLIN

    CONWAY FRANKLINCUMMINGTON HAMPSHIREEGREMONT BERKSHIREFLORIDA BERKSHIREGOSHEN HAMPSHIREHANCOCK BERKSHIREHARDWICK WORCESTERHAWLEY FRANKLIN

    HEATH FRANKLINHINSDALE BERKSHIREHUNTINGTON HAMPSHIRELANESBOROUGH BERKSHIRELEVERETT FRANKLINLEYDEN FRANKLINMIDDLEFIELD HAMPSHIREMONROE FRANKLINMONTAGUE FRANKLINMONTEREY BERKSHIRE

  • 8/17/2019 Mass Broadband Iniative

    14/15

    14

    Model Examples

    Town A:Expansion by

    Private Provider •Ownership: Theprivate party wouldown the network

    •Operations: Theprivate party wouldoperate the network

    •Financing: Likely acombination of stateand private fundingwith a possibility forCAF II funding

    •Technology: Fiber,Coax, or Wirelessdepending onprovider

    •OperatingConsiderations:Sustainabilityconcerns would beminimized

    •Challenges:Effectively incentingthe private sector toinvest with modestpublic investment

    Town B: Extensionof Existi ng Cable

    Infrastructure•Ownership:Incumbent cableprovider

    •Operations:Incumbent cableprovider underexisting franchiseagreement

    •Financing: Likely acombination of stateand private fundingwith a possibility forCAF II funding

    •Technology: Likelythe same as existingtechnology providerdeploys in that town

    •Operating

    Considerations:Minimal

    •Challenges:Effectively incentingthe private sector toinvest with modestpublic investment

    Town C: Multi-Municipal Network

    •Ownership: Municipal

    •Operations:Outsourced andbased on consortiummodel

    •Financing:Combination ofstate/MBI funds andmunicipal borrowing;unlikely availability forCAF II funds

    •Technology: Fiber,wireless, or hybrid

    •OperatingConsiderations:Emphasis onattaining broadbandspeeds withmaximum coverageat affordable priceswhile focusing onlong termsustainability

    •Challenges:Fostering a flexiblestructure that willallow a town to exitwith its assets

    Town D:Independent

    Municipal Network•Ownership:Municipality

    •Operations:Outsourced

    •Financing:Combination ofstate/MBI funds andmunicipal borrowing;unlikely availability forCAF II funds

    •Technology: f iber orwireless

    •OperatingConsiderations:emphasis onattaining broadbandspeeds withmaximum coverageat affordable priceswhile focusing onlong termsustainability

    •Challenges: Achieving asustainable network

    Town E: PilotProjects

    •Ownership: Variable,but likely the applyingmunicipality

    •Operations: Variable,but preferablyoutsourced

    •Financing: Variabledepending on project

    •Technology:Dependent on pilotprogram (wireless,fiber, hybrid, etc.)

    •OperatingConsiderations:Ensuring that the pilotmodel will foster longterm sustainability

    •Challenges:

    Balancing the need toinvest in newprograms with adesire to beresponsible stewards

  • 8/17/2019 Mass Broadband Iniative

    15/15

    15

    Town Profile Example