Last Mile Program UpdateMay 10, 2016
1
8/17/2019 Mass Broadband Iniative
2/15
• We have conducted and concluded an intensive program review in
collaboration with the MBI.• The MBI is shifting to a more flexible, responsive program framework
which prioritizes affordable and sustainable solutions and embraces arange of technology and operating options.
• The new course marks a change for MBI which up to now has been
constrained by irreconcilable expectations for speed, coverage,affordability, and a one-size fits all solution.
• We are prepared to move forward quickly and to partner with townsto discuss options and plans.
Goals:1. A strong collaborative partnership between the Administration, the
MBI, providers, and towns.
2. Rapid development and implementation of sustainable, reliable
broadband expansion projects 2
Program Update
8/17/2019 Mass Broadband Iniative
3/15
We have announced two new Advisors for the Last Mile program:
Peter Larkin: Special Advisor to the Secretary• Will advise the Administration on the go-forward plan for community
engagement and project implementation
• Will be Secretary Ash’s designee to Chair the MBI Board of Directors• MBI’s advocate for success, and will help ensure community interests are
heard and properly vetted
Bill Ennen: Last Mile Implementation Liaison• Working alongside the MBI staff to help troubleshoot and expedite to get the
best possible outcome in the shortest possible time
• Provides a consultative role to town leaders and MBI staff with regard toverifying each town’s path forward
• Will be based in Western Mass3
Advisors
8/17/2019 Mass Broadband Iniative
4/15
We are moving ahead with a fresh look.• Our shared goal is reliable, sustainable, affordable broadband
access for residents.
• We understand that there is no one-size-fits-all model for all towns.
• We will support projects that provide access to minimum speedrequirements, demonstrate viable funding and financing plans, andachieve operating sustainability.
• We are willing to support a range of technology, collaboration, and
operating choices.• The MBI, Special Advisor, and Implementation Liaison will engage
directly with Towns locally to propose and develop solutions.
• We want progress as quickly as possible.
4
Pathway Forward
8/17/2019 Mass Broadband Iniative
5/15
There is no one-size-fits-all solution.However, there are several different projectmodels and technology options that may work:
5
Several Viable Models
Models:• Expansion by Private
Provider • Extension of Existing
Cable Infrastructure• Multi-Municipal
Network• Independent
Municipal Network• Pilot Projects
Funding andFinancing:
• MBI/State GrantFunding
• Private PartnerInvestment
• Municipal Investment:
• USDA Loan Program• State House Notes• Qualified Bond
Program• Potential Federal
Funding (FCC CAF II)
TechnologyOptions:
• Fiber • Wireless• Cable• Hybrid Systems
8/17/2019 Mass Broadband Iniative
6/15
To receive state investment support, projects will need tomeet some minimum baseline requirements.
6
Baseline Requirements
Minimum ProjectRequirements:
• Project’s technology must provideaccess to broadband speeds asdefined by the FCC (25/3)
• Project must be capable ofdemonstrating long-term operatingsustainability without ongoing statesubsidy
• Project must be affordable
• Project should seek a minimum goal of96% residential coverage in its servicearea
• Endorsed by MBI professional staff • Financing Endorsed by DLS (as
needed)• Approved by MBI board
Technology andOperations:
• Preference for network operationsto be managed by experiencedprofessional partners whenpossible
• Many technology choices: fiber,wireless, cable, and/or hybridsolutions
• Preference for utilization ofMassBroadband 123 network whenappropriate
8/17/2019 Mass Broadband Iniative
7/15
7
Communities by Residential Broadband Provider
8/17/2019 Mass Broadband Iniative
8/15
We are reaching out to providers about
potential expansion:
8
Engaging with Providers
Company Comcast Verizon Charter Frontier FairpointMid
HudsonX5 Crocker
HilltownWireless
HolyokeG&E
WestfieldG&E
HQ Philadelphia,PANew York,
NYStamford,
CTNorwalk,
CTCharlotte,
NCCatskill,
NYSeattle,
WASpringfield,
MAAshfield,
MAHolyoke,
MAWestfield,
MA
CEOBrian
RobertsLowell
McAdamTom
RutledgeDaniel
McCarthyPaulSunu
JamesReynolds
GregForrest
MatthewCrocker
ChristopherGray
JamesLavelle,
GM
DanHoward,
GM
CY 2015Revenue
$75 billion$131
billion$10
billion$5.5
billion$900
million$25
million$70
million$66 million
Number ofEmployees
153,000 177,000 25,000 19,000 2,700 50 50Less than
30
SubscriptionsServed
27million
145million
6.7million
3.4 million 750,000 40,000
8/17/2019 Mass Broadband Iniative
9/15
8/17/2019 Mass Broadband Iniative
10/15
Using these models and available information, the MBI
will develop and start posting individual readiness statusreports for each town.
Example Readiness Elements Include:
10
Project Readiness
Town Preferences and Actions
• Establish a Local ProjectModel Preference
• Take Local Actions: Bond Authorization and DebtExclusion (if necessary)
• Establish MLP(if necessary)
• Establish Inter-Municipal Agreements (if necessary)
Financing and Funding
• Review MBI Cost andSustainability Analyses
• Understand and ConfirmTotal Project Costs
• Examine and PursueFunding Options
• Confirm and Review
Financing Options withFinancial Advisor and BondCounsel
• Develop Financing Plan withFinancial Advisor and BondCounsel
• Local Borrowing PlanEndorsed by either DLS orUSDA
Project Details
• Review and SelectTechnology Options
• Review and Select RegionalCollaboration Options
• Review and SelectOperator/ISP
• Develop and Confirm a
Sustainable Business Plan
8/17/2019 Mass Broadband Iniative
11/15
We are prepared to engage directly witheach town individually or as collaboratives tosupport and review projects.
11
How We Work Together
ReviewMaterials
Town
Decision-Making
Project Approval
andFunding
MBI/
StateReview
MBI TracksStatus via
ReadinessReport
Meetingsand Support
Project Models
Funding and
Financing
Technology &Operations
Project
Submissionto MBI
Process will be iterative and collaborative, butalso time-bound with deadlines!
8/17/2019 Mass Broadband Iniative
12/15
Appendix
12
8/17/2019 Mass Broadband Iniative
13/15
13
List of Program Towns
Town CountyMONTGOMERY HAMPDENMOUNT WASHINGTON BERKSHIRENEW ASHFORD BERKSHIRENEW BRAINTREE WORCESTERNEW MARLBOROUGH BERKSHIRENEW SALEM FRANKLINNORTHFIELD FRANKLINOTIS BERKSHIREPELHAM HAMPSHIRE
PERU BERKSHIREPETERSHAM WORCESTERPLAINFIELD HAMPSHIREPRINCETON WORCESTERROWE FRANKLINROYALSTON WORCESTERSANDISFIELD BERKSHIRESAVOY BERKSHIRE
SHELBURNE FRANKLINSHUTESBURY FRANKLINTOLLAND HAMPDENTYRINGHAM BERKSHIREWARWICK FRANKLINWASHINGTON BERKSHIREWENDELL FRANKLINWEST STOCKBRIDGE BERKSHIREWINDSOR BERKSHIREWORTHINGTON HAMPSHIRE
Town County
ALFORD BERKSHIRE ASHFIELD FRANKLINBECKET BERKSHIREBLANDFORD HAMPDENBUCKLAND FRANKLINCHARLEMONT FRANKLINCHESTER HAMPDENCHESTERFIELD HAMPSHIRECOLRAIN FRANKLIN
CONWAY FRANKLINCUMMINGTON HAMPSHIREEGREMONT BERKSHIREFLORIDA BERKSHIREGOSHEN HAMPSHIREHANCOCK BERKSHIREHARDWICK WORCESTERHAWLEY FRANKLIN
HEATH FRANKLINHINSDALE BERKSHIREHUNTINGTON HAMPSHIRELANESBOROUGH BERKSHIRELEVERETT FRANKLINLEYDEN FRANKLINMIDDLEFIELD HAMPSHIREMONROE FRANKLINMONTAGUE FRANKLINMONTEREY BERKSHIRE
8/17/2019 Mass Broadband Iniative
14/15
14
Model Examples
Town A:Expansion by
Private Provider •Ownership: Theprivate party wouldown the network
•Operations: Theprivate party wouldoperate the network
•Financing: Likely acombination of stateand private fundingwith a possibility forCAF II funding
•Technology: Fiber,Coax, or Wirelessdepending onprovider
•OperatingConsiderations:Sustainabilityconcerns would beminimized
•Challenges:Effectively incentingthe private sector toinvest with modestpublic investment
Town B: Extensionof Existi ng Cable
Infrastructure•Ownership:Incumbent cableprovider
•Operations:Incumbent cableprovider underexisting franchiseagreement
•Financing: Likely acombination of stateand private fundingwith a possibility forCAF II funding
•Technology: Likelythe same as existingtechnology providerdeploys in that town
•Operating
Considerations:Minimal
•Challenges:Effectively incentingthe private sector toinvest with modestpublic investment
Town C: Multi-Municipal Network
•Ownership: Municipal
•Operations:Outsourced andbased on consortiummodel
•Financing:Combination ofstate/MBI funds andmunicipal borrowing;unlikely availability forCAF II funds
•Technology: Fiber,wireless, or hybrid
•OperatingConsiderations:Emphasis onattaining broadbandspeeds withmaximum coverageat affordable priceswhile focusing onlong termsustainability
•Challenges:Fostering a flexiblestructure that willallow a town to exitwith its assets
Town D:Independent
Municipal Network•Ownership:Municipality
•Operations:Outsourced
•Financing:Combination ofstate/MBI funds andmunicipal borrowing;unlikely availability forCAF II funds
•Technology: f iber orwireless
•OperatingConsiderations:emphasis onattaining broadbandspeeds withmaximum coverageat affordable priceswhile focusing onlong termsustainability
•Challenges: Achieving asustainable network
Town E: PilotProjects
•Ownership: Variable,but likely the applyingmunicipality
•Operations: Variable,but preferablyoutsourced
•Financing: Variabledepending on project
•Technology:Dependent on pilotprogram (wireless,fiber, hybrid, etc.)
•OperatingConsiderations:Ensuring that the pilotmodel will foster longterm sustainability
•Challenges:
Balancing the need toinvest in newprograms with adesire to beresponsible stewards
8/17/2019 Mass Broadband Iniative
15/15
15
Town Profile Example