17
Material Requirements Planning MRP

Material Requirements Planning - · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

  • Upload
    trannhu

  • View
    214

  • Download
    2

Embed Size (px)

Citation preview

Page 1: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

Material Requirements PlanningMRP

Page 2: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

MRP Scheduling Terminology

• Gross Requirements: needed during each period.

• Scheduled Receipts: Existing orders that arrive at beginning of period.

• On-hand or available balance:

• (depending on software convention, could be at the beginning of each period or end):

• Book: Inventory balance at end of each period.

• Net requirements: What is need to meet requirements and safety stock.

• Planned order receipt: arrives at beginning of period.

• Planned order release: Addresses lead time.

Page 3: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

MRP Table – determine the Project Available

Balance (Inventory)

1 2 3 4 5

Gross Requirements 10 40 10

Scheduled receipts (begin) 50

Projected Available

Balance (ending) 4

54

44

44

4

Net Requirements 6

Planned Order Receipts

Planned Order Releases

Page 4: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

MRP Table – determine the Project Available

Balance (Inventory)

1 2 3 4 5

Gross Requirements 10 40 10

Scheduled receipts (begin) 50

Projected Available

Balance (ending) 4

54

44

44

4

Net Requirements 6

Planned Order Receipts

Planned Order Releases

6 units short

Page 5: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

MRP Table – determine the Project Available

Balance (Inventory)

In week 5,

The project available balance (inventory) SMALLER THAN the

Gross Requirement.

Therefore,

Net requirement = the shortage quantity

= 4 (inventory) – 10 (Gross requirement)

= 6

Page 6: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

MRP Table – determine the Ending Inventory in

period 5.

If given a Standard Lot Size,

The Plan Order Receipts = the Standard Lot Size

(e.g. lot size = 50)

Thus in week 5,

The Ending Inventory = Plan Order Receipts – Net requirement

= 50 – 6

= 44

Page 7: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

MRP Table – determine the Ending Inventory in

period 5.

1 2 3 4 5

Gross Requirements 10 40 10

Scheduled receipts (begin) 50

Projected Available

Balance (ending) 4

54

44

44

4

44 Net Requirements 6

Planned Order Receipts 50

Planned Order Releases 50

Ending inventory

Page 8: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

MRP Table – determine the Plan Order

Receipts and Plan Order Release

REMARKS:

The quantity of Plan Order Receipts always equal to Net

Requirement if there is no restriction on Standard Lot Size.

The quantity of Plan Order Release always similar to Plan

Order Receipt. But, the allocation of the order has referred to

Lead Time (LT).

Page 9: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

MRP Table – determine the Plan Order

Receipts and Plan Order Release

Example:

Given a standard lot size = 50

Lead Time (LT) = 1 week

Therefore,

Plan Order Receipts for week 5 = 50

Plan Order Release = 50 that allocate at week 4

Page 10: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

MRP Table – determine the Plan Order Receipt

and Plan Order Release.

1 2 3 4 5

Gross Requirements 10 40 10

Scheduled receipts (begin) 50

Projected Available

Balance (ending) 4

54

44

44

4

44 Net Requirements 6

Planned Order Receipts 50

Planned Order Releases 50

Page 11: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

Example of MRP Logic and Product Structure Tree

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A

Product Structure Tree for Assembly ALead Times

A 1 day

B 2 days

C 1 day

D 3 days

E 4 days

F 1 day

Demand

Day 10 50 A

Day 8 20 B (Spares)

Day 6 15 D (Spares)

Given the product structure tree for “A” and the lead time and demand

information below, provide a materials requirements plan that defines

the number of units of each component and when they will be needed.

Page 12: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

LT = 1 day

Day: 1 2 3 4 5 6 7 8 9 10

A Required 50

Order Placement 50

First, the number of units of “A” are scheduled backwards to

allow for their lead time. So, in the materials requirement plan

below, we have to place an order for 50 units of “A” in the 9th

week to receive them in the 10th week.

Page 13: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

Next, we need to start scheduling the components that make up “A”. In

the case of component “B” we need 4 B’s for each A. Since we need 50

A’s, that means 200 B’s. And again, we back the schedule up for the

necessary 2 days of lead time.D a y : 1 2 3 4 5 6 7 8 9 1 0

A R e q u ire d 5 0

O rd e r P la c e m e n t 5 0

B R e q u ire d 2 0 2 0 0

O rd e r P la c e m e n t 2 0 2 0 0

SparesLT = 2

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A 4x50=200

Page 14: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

Day: 1 2 3 4 5 6 7 8 9 10

A Required 50

LT=1 Order Placement 50

B Required 20 200

LT=2 Order Placement 20 200

C Required 100

LT=1 Order Placement 100

D Required 55 400 300

LT=3 Order Placement 55 400 300

E Required 20 200

LT=4 Order Placement 20 200

F Required 200

LT=1 Order Placement 200

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A

40 + 15 spares

Part D: Day 6

Finally, repeating the process for all components, we have the

final materials requirements plan:

14

Page 15: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

MRP for Level 0- the BOM structure -

Page 16: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

Example of the MRP for Level 0

The Master Production Schedule shows we have to make 400

scissors (SC) during the 3rd week, in the 4th week 600, in the 6th

week 800, and in the 7th week 300 scissors.

This is called as Gross Requirements, GR to the demand of

fabrication of the products.

Page 17: Material Requirements Planning -   · PDF fileMRP Table –determine the Project Available Balance (Inventory) 1 2 3 4 5 Gross Requirements 10 40 10 Scheduled receipts (begin) 50

Example of MRP Explosion

. .

EPO is the Plan Order Release

150 0