37
Materials Requirements Planning (Session 11) 1

Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

  • Upload
    doquynh

  • View
    230

  • Download
    7

Embed Size (px)

Citation preview

Page 1: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Materials Requirements Planning

(Session 11)

1

Page 2: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Outline

• Material Requirements Planning (MRP)• MRP Logic and Product Structure Trees• Time Fences• MRP Example• MRP II and Lot Sizing

2

Page 3: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Material Requirements Planning

• Materials requirements planning (MRP) is a means for determining the number of parts, components, and materials needed to produce a product

• MRP provides time scheduling information specifying when each of the materials, parts, and components should be ordered or produced

• Dependent demand drives MRP• MRP is a software system

3

Page 4: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Example of MRP Logic and Product Structure Tree

Given the product structure tree for “A” and the lead time and demand information below, provide a materials requirements plan that defines the number of units of each component and when they will be needed

Given the product structure tree for “A” and the lead time and demand information below, provide a materials requirements plan that defines the number of units of each component and when they will be needed

B(4)

E(1)D(2)

C(2)

F(2)D(3)

AProduct Structure Tree for Assembly A Lead Times

A 1 dayB 2 daysC 1 dayD 3 daysE 4 daysF 1 day

Total Unit DemandDay 10 50 ADay 8 20 B (Spares)Day 6 15 D (Spares)

4

Page 5: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

First, the number of units of “A” are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of “A” on the 9th day to receive them on day 10.

First, the number of units of “A” are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of “A” on the 9th day to receive them on day 10.

LT = 1 day

Day: 1 2 3 4 5 6 7 8 9 10A Required 50

Order Placement 50

5

Page 6: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Next, we need to start scheduling the components that make up “A”. In the case of component “B” we need 4 B’s for each A. Since we need 50 A’s, that means 200 B’s. And again, we back the schedule up for the necessary 2 days of lead time.

Next, we need to start scheduling the components that make up “A”. In the case of component “B” we need 4 B’s for each A. Since we need 50 A’s, that means 200 B’s. And again, we back the schedule up for the necessary 2 days of lead time.

D ay : 1 2 3 4 5 6 7 8 9 10A R equ ired 50

O rder P lac em ent 50B R equ ired 20 200

O rder P lac em ent 20 200

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A

SparesLT = 2

4x50=200

6

Page 7: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Finally, repeating the process for all components, we have the final materials requirements plan:Finally, repeating the process for all components, we have the final materials requirements plan:

7

Day: 1 2 3 4 5 6 7 8 9 10A Required 50

LT=1 Order Placement 50B Required 20 200

LT=2 Order Placement 20 200C Required 100

LT=1 Order Placement 100D Required 55 400 300

LT=3 Order Placement 55 400 300E Required 20 200

LT=4 Order Placement 20 200F Required 200

LT=1 Order Placement 200

B(4)

E(1)D(2)

C(2)

F(2)D(3)

A

40 + 15 spares

Part D: Day 6

7

Page 8: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Master Production Schedule (MPS)

• Time-phased plan specifying how many and when the firm plans to build each end item

Aggregate Plan(Product Groups)Aggregate Plan

(Product Groups)

MPS(Specific End Items)

8

Page 9: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Types of Time Fences• Frozen

– No schedule changes allowed within this window• Moderately Firm

– Specific changes allowed within product groups as long as parts are available

• Flexible– Significant variation allowed as long as overall

capacity requirements remain at the same levels

9

Page 10: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Example of Time Fences

8 15 26

Weeks

FrozenModerately

Firm Flexible

Firm Customer Orders

Forecast and availablecapacity

Capacity

10

Page 11: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Material Requirements Planning System

• Based on a master production schedule, a material requirements planning system:– Creates schedules identifying the specific parts

and materials required to produce end items

– Determines exact unit numbers needed

– Determines the dates when orders for those materials should be released, based on lead times

11

Page 12: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

©The McGraw-Hill Companies, Inc., 2004

Firm orders from knowncustomers

Forecastsof demand

from randomcustomers

Aggregateproduct

plan

Bill ofmaterial

file

Engineeringdesign

changes

Inventoryrecord file

Inventorytransactions

Master productionSchedule (MPS)

Primary reportsSecondary reports

Planned order schedule for inventory and production control

Exception reportsPlanning reportsReports for performance control

Materialplanning(MRP

computer program)

12

Page 13: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Bill of Materials (BOM) File

• Materials• Parts• Components• Production sequence • Modular BOM

– Subassemblies• Super BOM

– Fractional options13

Page 14: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Inventory Records File

• Each inventory item carried as a separate file– Status according to “time buckets”

• Pegging– Identify each parent item that created demand

14

Page 15: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Primary MRP Reports

• Planned orders to be released at a future time• Order release notices to execute the planned

orders• Changes in due dates of open orders due to

rescheduling • Cancellations or suspensions of open orders due

to cancellation or suspension of orders on the master production schedule

• Inventory status data15

Page 16: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Secondary MRP Reports

• Planning reports, for example, forecasting inventory requirements over a period of time

• Performance reports used to determine agreement between actual and programmed usage and costs

• Exception reports used to point out serious discrepancies, such as late or overdue orders

16

Page 17: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Additional MRP Scheduling Terminology

• Gross Requirements

• Scheduled receipts

• Projected available balance

• Net requirements

• Planned order receipt

• Planned order release17

Page 18: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

MRP Example

A(2) B(1)

D(5)C(2)

X

C(3)

Item On-Hand Lead Time (Weeks)X 50 2A 75 3B 25 1C 10 2D 20 2

Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10

Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10

18

Page 19: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

A(2)

XDay: 1 2 3 4 5 6 7 8 9 10

X Gross requirements 95LT=2 Scheduled receipts

Proj. avail. balance 50 50 50 50 50 50 50 50 50 50On- Net requirements 45hand Planned order receipt 4550 Planner order release 45A Gross requirements 90

LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 75

On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45

LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 25

On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40

LT=2 Scheduled receipts Proj. avail. balance 10 10 10 10 10

On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100

LT=2 Scheduled receipts Proj. avail. balance 20 20 20 20 20 20 20

On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80

19

It takes 2 A’s for each X

It takes 2 A’s for each X

Page 20: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95

LT=2 Scheduled receipts Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

On- Net requirements 45hand Planned order receipt 4550 Planner order release 45A Gross requirements 90

LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 75

On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45

LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 25

On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40

LT=2 Scheduled receipts Proj. avail. balance 10 10 10 10 10

On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100

LT=2 Scheduled receipts Proj. avail. balance 20 20 20 20 20 20 20

On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80

B(1)A(2)

X

It takes 1 B for each X

It takes 1 B for each X

20

Page 21: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95

LT=2 Scheduled receipts Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

On- Net requirements 45hand Planned order receipt 4550 Planner order release 45A Gross requirements 90

LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 75

On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45

LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 25

On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40

LT=2 Scheduled receipts Proj. avail. balance 10 10 10 10 10

On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100

LT=2 Scheduled receipts Proj. avail. balance 20 20 20 20 20 20 20

On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80

21

A(2) B(1)

X

C(3)

It takes 3 C’s for each A

It takes 3 C’s for each A

Page 22: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

A(2) B(1)

C(2)

X

C(3)

Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95

LT=2 Scheduled receipts Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

On- Net requirements 45hand Planned order receipt 4550 Planner order release 45A Gross requirements 90

LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 75

On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45

LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 25

On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40

LT=2 Scheduled receipts Proj. avail. balance 10 10 10 10 10

On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100

LT=2 Scheduled receipts Proj. avail. balance 20 20 20 20 20 20 20

On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80

It takes 2 C’s for each B

It takes 2 C’s for each B

22

Page 23: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

A(2) B(1)

D(5)C(2)

X

C(3)

Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95

LT=2 Scheduled receipts Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

On- Net requirements 45hand Planned order receipt 4550 Planner order release 45A Gross requirements 90

LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 75

On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45

LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 25

On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40

LT=2 Scheduled receipts Proj. avail. balance 10 10 10 10 10

On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100

LT=2 Scheduled receipts Proj. avail. balance 20 20 20 20 20 20 20

On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80

It takes 5 D’s for each B

It takes 5 D’s for each B

23

Page 24: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Closed Loop MRP

Production PlanningMaster Production SchedulingMaterial Requirements PlanningCapacity Requirements Planning

Realistic?No

Feedback

Execute:Capacity PlansMaterial Plans

Yes

Feedback

24

Page 25: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Manufacturing Resource Planning (MRP II)

• Goal: Plan and monitor all resources of a manufacturing firm (closed loop):– manufacturing– marketing– finance– engineering

• Simulate the manufacturing system

25

Page 26: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Lot Sizing in MRP Programs

• Lot-for-lot (L4L)• Economic order quantity (EOQ)• Least total cost (LTC)• Least unit cost (LUC)• Which one to use?

– The one that is least costly!

26

Page 27: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Numerical # 1:

Given the following product structure tree diagram, complete the MRP records for A, B, and C.

A

C B (2)

C

27

Page 28: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

28

Gross 5 15 18 8 12 22Scheduled Receipt

PAB (21) 21 16 1 3 15 3

P.O.Receipt 20 20 20

P.O. Release 20 20 20

Week 4 5 6 7 8 9

PART AQ=20; LT=1; SS=0

Gross 40 40 40Scheduled Receipt

32 32

PAB (20) 20 20 12 12 12

P.O.Receipt 40 40

P.O. Release 40 40

PART BQ=40; LT=2; SS=0

Gross 40 20 60 20

Scheduled Receipt

PAB (50) 50 10 10 10 10 10

P.O.Receipt 20 60 20

P.O. Release 20 60 20

PART CQ=L-4-L; LT=1; SS=10

Page 29: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Numerical # 2:Draw the time-phased product structure tree.

Parts L.T.A 1

B 2C 1D 1E 2F 3G 2

A

B(2) C (3)

F(2)D(2) E(2) E(2)

D(2)G(1)29

Page 30: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

1 2 3 4 5 6 7 830

G

D

A

B

E

F

D

E

C

Time-phased product structure of A

Time in week

Page 31: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Questions:

To ensure good master scheduling, a master scheduler must do which of the following?

• Never lose sight of the aggregate plan• Identify and communicate all problems• Be involved with customer order

promising• Be visible to all levels of management

31

Page 32: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

The purpose of a “time fence” is which of the following?

• Make sure the cows don’t get out of the barn

• Control flow through the production system

• Maximize sales to retailers• All of the above• None of the above

32

Page 33: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Which of the following is an objective under an MRP system?

• To improve customer service• Minimize inventory investment• Maximize production operating

efficiency• All of the above• None of the above

33

Page 34: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Which of the following is one of the three main inputs into an MRP system?

• BOM file• Exception report• Planning report• All of the above, None of the above

An MRP program accesses the status of a job according to specific time periods called which of the following?

a. Peg recordb. Time fencec. Time bucketd. Time clock, e. None of the above 34

Page 35: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

In MRP, workload per work center can be determined. When the work capacity is exceeded, which of the following options can be implemented to correct the imbalance of workload?

• Work overtime• Renegotiate the due date and reschedule• Subcontract to an outside shop• All of the above• None of the above

35

Page 36: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

Which of the following are reasons why a Lot-For-Lot (L4L) method of lot sizing can be used in an MRP application?

• Minimizes carrying costs• Sets planned orders to exactly match the

net requirements• Produces exactly what is needed• Does not carry any units over into future

periods• All of the above

36

Page 37: Materials Requirements Planning (Session 11) · Material Requirements Planning • Materials requirements planning (MRP) is a means for determining the number of parts, components,

End of Session

37