Maturity for Opening PCC Pavements: Iowa Experience

John Smythe, Construction Engineer

Page 2: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Introduction

Maturity ConceptOpening SpecificationProceduresChallengesConclusions

Page 3: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

When Is It Okay to Drive On?What strength is needed?How do we measure?

Page 4: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Beams/Cylinders

Specimen – not actual structureDifferent curing than pavement

Direct measurement of pavement concreteActual temperature in pavement

vs. Maturity

Page 5: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Maturity Concept

Non-destructive testMeasures strength of in-place concreteEarly age testNot a 28-day strength test

Page 6: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Maturity ConceptTime Temperature Factor: TTF

Relationship between thermal history and strength of a concrete

ASTM C 1074Nurse•Saul Equation

M (°C•hrs) =Σ[(T – T0)Δt] where T0 = (-10 °C)

Time × Temperature = Maturity (TTF)

Page 7: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Time for Opening Standard Class C Concrete

5

7

500

500

>9

<9

Min. Time (Days)

Min. Flexural Strength,

(psi MOR-CPL)

PavementThickness

(in.)

Both strength and time conditions must be met.

At contractor’s option, maturity method to determine time for opening based on strength requirement only.

Page 8: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Typical Opening Times Utilizing Maturity

Summer (>80 °F) 24-48 hoursFall/Spring (>55 °F) 36-72 hoursLate Fall (<50 °F) 48-144 hours

Page 9: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Temperature Effect on Opening Time

40

50

60

70

80

90

100

5/1/01

5/8/01

5/22/0

15/2

9/01

6/4/01

6/12/0

16/1

9/01

6/25/0

16/2

7/01

7/10/0

17/1

6/01

7/23/0

1

8/1/01

8/6/01

8/14/0

1

Date

Tem

pera

ture

(deg

F)

30

35

40

45

50

55

60

65

70

75

Tim

e to

Ope

n (h

ours

)

HighLowHours

NHSX-218-2(57--3H-44

3 days

2 days

Seasonal Changes

Page 10: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Advantages - ContractorUse as haul roadExpedite sub-drain & shoulderingAccelerate staged construction Reduced construction time & Costs

Page 11: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Advantages – Public

Provide local access early

HomeownersBusinesses

Reduced Construction Time & Costs

Page 12: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Maturity Procedure

Contractor develops strength-maturity curve for mix used

Determine required opening TTFContractor takes pavement temperature readings and calculates TTF

Submit data to EngineerEngineer responsible for opening section

Contractor performs monthly curve validation

Agency monitors testing at all steps

Page 13: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Step 1- Develop Strength-Maturity Curve

Cast 12 beams

Thermocouple both ends of one beam

Test 3 beams at 4 different ages

Develop Strength vs. Maturity curve

Page 14: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Equipment for Opening TTF

Beam MoldsMaturity MeterThermocouple WireTesting MachineComputer

Page 15: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Maturity Meters

Page 16: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

MATURITY - STRENGTH DEVELOPMENTCOUNTY: PolkCURVE #: 1 MONITOR: INSPECTOR: PROJ. #: Im -35-5(109) REP/CONTRACTOR: C edar Valley DATE: 06/21/98

BEAM # LOAD AT TABLE BREAK W IDTH DEPTH FLEXURAL FLEXURAL AGE AT TTF TTF AVERAGE BEAMBREAK VALUE LOCATION COEFFICIENT STRENGTH BREAK CH 1 CH 2 TTF TEMP

(lbs) (lbs) (in) (in) (in) (psi) (days) (AVG)Enter Enter Enter Enter Enter Enter Enter Enter Enter

1 3000 3100 0.5 5.96 6.02 0.125004 388 1 650 650 650 24

2 3100 3250 0.5 6.00 6.01 0.124584 405 1 650 650 650 24

3 3050 3150 0.5 6.00 6.02 0.124171 391 1 650 650 650 24

4 3450 3400 0.5 5.98 6.00 0.125418 426 2 800 800 800 22

5 3550 3450 0.5 6.00 6.00 0.125000 431 2 800 800 800 22

6 3500 3425 0.5 6.00 6.00 0.125000 428 2 800 800 800 22

7 4000 4100 0.5 5.98 6.00 0.125418 514 3 1100 1100 1100 21

8 3990 4000 0.5 5.98 6.00 0.125418 502 3 1100 1100 1100 21

9 4000 4100 0.5 6.00 6.00 0.125000 513 3 1100 1100 1100 21

10 4600 4650 0.5 6.00 6.00 0.125000 581 4 1500 1500 1500 21

11 4700 4580 0.5 6.00 6.00 0.125000 573 4 1500 1500 1500 21

12 4750 4700 0.5 5.98 6.00 0.125418 589 4 1500 1500 1500 21

MIX INFORMATION EnterAIR: 7.8

SLUM P: 2 w /c: 0.42

M IX: C3W RC20FLY ASH SOURCE: Port Neal #4CEM ENT SOURCE: Ash G rov e

CO ARSE AGG REG ATE SOURCE: Duraham M ineFINE AGG REG ATE SOURCE: Vandalia

W ATER REDUCER BRAND: Daratard 17Add. Rate: 2 oz.

AIR ADM IXT URE BRAND: Darav air 1400Add. Rate: 6 oz.

M ETHOD O F DEVELO PM ENT: M aturity M eterDesired Flexural Strength (M O R): 500 psi

REQUIRED TTF: 1058

Certified M aturity Contractor Representative - Com ments:Signature

M aturity Curve Reviewed - Testing Engineer

M aturity Curveof A ll F lexural S trengths

300

400

500

600

700

2.000 3.000 4.000Log of TTF (C-hours)

Flex

ural

Stre

ngth

(psi

)

RegressionStrengths

Iowa DOT Spreadsheet

Page 17: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Step 2- Pavement Temperature Measurement

Insert thermocouple in pavement

18” from edgeMid depth

Minimum of 2 locations per day’s paving

Read morning and evening minimumCalculate pavement TTFWhen pavement TTF > required opening TTF OK to open

Page 18: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Equipment for Measuring Pavement TTF

Thermal Meter or dataloggerThermocouple wire

Page 19: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Maturity - Field Data

Project : Maturity Curve #: 1 Probe # : 1

County : Date Placed: 9/11/99

Contractor: Mix: C3W RC20

TTF Required to Open : 1058

Section of Pavement for Opening by MaturityFrom Location: 104+00 To Probe Location: 121+50

Age Temp TTF Sum Air TempDate Time (hours) (deg C) at age TTF (deg C)

(deg C-hr) (deg C-hr)

09/11/99 10:00 AM 0.00 28 003:00 PM 5.00 30 195 19507:00 PM 9.00 29 158 353

09/12/99 07:00 AM 21.00 21 420 77306:00 PM 32.00 20 335.5 1108.5

0 00 00 00 0

TTF: 1108.5Value in box should be equal to or greater thanrequired TTF.

Contractor Representativecc: RCE, Central Materials, Contractor

Field Data

Page 20: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Step 3- Monthly Curve Validation

Cast & Cure 3 BeamsMonitor Maturity until approximate required opening TTF is reachedTest all 3 beams and averageAverage Strength should be within ±50 psi of opening strength at TTF

>50 psi okay, more conservative<50 psi must develop new curve

Page 21: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Monthly Curve ValidationAssured same basic mix being placed

Weather conditions did not affect TTF, only time of opening

Page 22: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Factors Affecting TTFCementFly AshAdmixturesw/c ratioMix TypeAggregates

A curve validation can be used to allow some changes without establishing a new curve

Page 23: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Challenges to ImplementationContractor casting test specimens for acceptance based on strengthRequire new curve for minor mix changesRequire more expensive field maturity devices

Some cost $10 – 25 each

Page 24: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Keys to Implementation

Contractor flexibilityAllow minor mix changes – fly ash, etc.Allow curve validation instead of requiring new curve to be developed

Utilize thermocouple wire and thermometer or datalogger

Minor cost for few inches of thermocouple wireBuild in Factors of Safety

Page 25: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Factors of Safety

Iowa uses 500 psi opening Only 300 psi needed (Table previous slide)

Curve established on concrete with higher air content Require curve development at highest w/c ratio expected

Iowa allows w/c to change 0.02 higher Field maturity tested near edge

Temperature lower than at mid slab

Page 26: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

ConclusionsReliable method of opening PCC pavementsMany factors affect strength maturity relationshipMay use validations to allow mix changes Monthly curve validations give a measure of reliabilityContractor’s option since 1997 – zero instances of cracking from opening early

Page 27: Maturity for Opening PCC Pavements: Iowa Experiencesp.construction.transportation.org/Documents/Smyth...0)Δt] where T. 0 = (-10 °C) Time × Temperature = Maturity (TTF) Time for

Any Questions

About Maturity ?