Max Assignment

Embed Size (px)

Citation preview

  • 8/6/2019 Max Assignment

    1/3

    FINANCE & COSTING ASSIGNMENT

    Name: Max William DCosta

    Roll No.: 4

    Course: PGDHR 09-

    11Trimester 1

    Topic: Risk Evaluation

    Problem

    Details of two Projects are given below:

    Project A Project B

    Cash Flow Probability Cash Flow Probability1000 0.2 1200 0.2800 0.6 800 0.6600 0.2 400 0.2

    Which project is more risky?

    Solution

    A) Let us calculate the Expected Cash Flow for Project A

    Expected Cash Flow for Project A = (1000 x 0.2) + (800 x 0.6) + (600 x 0.2)

    = 800

    B) Let us calculate the Expected Cash Flow for Project A

    Expected Cash Flow for Project B = (1200 x 0.2) + (800 x 0.6) + (400 x 0.2)= 800

    Here we can see that 800 is the mean.

    C) Let us calculate the Standard Deviation from the Mean for Project A

    Max DCosta Page 1

  • 8/6/2019 Max Assignment

    2/3

    Following are the steps for the calculation of Standard Deviation from the mean for

    Project A.

    Step 1: Calculate the Mean

    The mean has already been calculated above which is 800

    Step 2: Calculation of Deviation from Mean

    1000 800 = 200

    800 800 = 0

    600 800 = -200

    Step 3: Square each Deviation & Multiply by the corresponding Probabilities

    (200)2 x 0.2 = 8000

    (0)2 x 0.6 = 0

    (-200)

    2

    x 0.2 = 8000

    Step 4: Summation to find the Total Deviation (i.e.) Variance

    = (8000 + 0 + 8000)

    = 16000

    Step 5: Square Root of the Total Deviation (i.e. Variance) to get the Standard

    Deviation

    = 16000= 126.79

    D) Let us calculate the Standard Deviation from the Mean for Project B

    Following are the steps for the calculation of Standard Deviation from the mean for

    Project B.

    Step 1: Calculate the Mean

    The mean has already been calculated above which is 800

    Step 2: Calculation of Deviation from Mean

    1200 800 = 400

    800 800 = 0

    400 800 = -400

    Step 3: Square each Deviation & Multiply by the corresponding Probabilities

    Max DCosta Page 2

  • 8/6/2019 Max Assignment

    3/3

    (400)2 x 0.2 = 32000

    (0)2 x 0.6 = 0

    (-400)2 x 0.2 = 32000

    Step 4: Summation to find the Total Deviation (i.e.) Variance

    = (32000 + 0 + 32000)

    = 64000

    Step 5: Square Root of the Total Deviation (i.e. Variance) to get the Standard

    Deviation

    = 64000= 252.98

    Since the deviation (skewness) of Project B is more than that of Project A

    Project B is more Risky, and hence it may rejected.

    E) Also, which Project should I go for?

    Project A

    Variation of Project A is 126.49

    Co-efficient of Variation = Standard

    Deviation ()Mean

    = 126.49 800= 0.158

    Project B

    Variation of Project B is 252.98

    Co-efficient of Variation = Standard

    Deviation ()Mean

    = 252.98 800= 0.316

    Since the Co-efficient of Variation of Project A is lower.

    We will go in for Project A. Investment is recommended in Project A.

    Max DCosta Page 3