Nicole BonomoJake YatskoShannon RitterNoel RangelWilliam OsthoffJason Filer

MC6

MC6

Page 2: MC6 - University of Pittsburgh

4/17/2014

2

MC6

1900s: Dirt path intersecting West Liberty Ave. and Warrington Ave. 1914: Kaiser Ave. was replaced with Saw Mill Run Road 1920: Liberty Tunnel starts construction 1928: Saw Mill Run Blvd. was part of Allegheny county “City Beautiful”

bond 1930: Library Road extension 1947: Request Army COE Study 1951: Saw Mill Run extension (West End Bypass) 1960: First Congress Response 1961-1964: Army COE Study is performed 1964: Army COE suspends study due to PA involvement. (traffic) 1971: Resume Army COE study 1975: Channel Improvement Project recommended 1986: Federal Money is approved (However, another study is required) 1992: Study completed 2004: Plans in place for replacement 2007: Project restarted 2008: Traffic study done 2010: Redesigned plans are put in place 2013: Construction begins

MC6

Page 3: MC6 - University of Pittsburgh

4/17/2014

3

MC6

MC6

Page 4: MC6 - University of Pittsburgh

4/17/2014

4

MC6

MC6

Page 5: MC6 - University of Pittsburgh

4/17/2014

5

MC6

MC6

Page 6: MC6 - University of Pittsburgh

4/17/2014

6

MC6

MC6

Page 7: MC6 - University of Pittsburgh

4/17/2014

7

MC6

MC6

Page 8: MC6 - University of Pittsburgh

4/17/2014

8

MC6

MC6

Page 9: MC6 - University of Pittsburgh

4/17/2014

9

MC6

MC6

Page 10: MC6 - University of Pittsburgh

4/17/2014

10

MC6

MC6

Page 11: MC6 - University of Pittsburgh

4/17/2014

11

MC6

MC6

Page 12: MC6 - University of Pittsburgh

4/17/2014

12

MC6

PennDOT Phases 1-10

Page 13: MC6 - University of Pittsburgh

4/17/2014

13

MC6

MC6

Page 14: MC6 - University of Pittsburgh

4/17/2014

14

MC6

MC6

Page 15: MC6 - University of Pittsburgh

4/17/2014

15

MC6

MC6

Page 16: MC6 - University of Pittsburgh

4/17/2014

16

MC6

MC6

Page 17: MC6 - University of Pittsburgh

4/17/2014

17

MC6

MC6

Page 18: MC6 - University of Pittsburgh

4/17/2014

18

MC6

Page 19: MC6 - University of Pittsburgh

4/17/2014

19

MC6

MC6

Page 20: MC6 - University of Pittsburgh

4/17/2014

20

MC6

MC6

Page 21: MC6 - University of Pittsburgh

4/17/2014

21

MC6

MC6

Page 22: MC6 - University of Pittsburgh

4/17/2014

22

MC6

Page 23: MC6 - University of Pittsburgh

4/17/2014

23

MC6

Phasing

MC6

Page 24: MC6 - University of Pittsburgh

4/17/2014

24

Proposal◦ Bid Form

Takeoff Spreadsheet◦ Material◦ Labor ◦ Equipment◦ Subcontractor

Cost Curve Man Hour Curves

MC6

Page 25: MC6 - University of Pittsburgh

4/17/2014

25

MC6

MC6

Page 26: MC6 - University of Pittsburgh

4/17/2014

26

MC6

Examination of Specs and Drawings Bid Item Number Activities References Material Unit Prices

MC6

Page 27: MC6 - University of Pittsburgh

4/17/2014

27

Labor Costs Equipment Costs

MC6

Labor Estimate Crew Definition Identifying Durations

MC6

Page 28: MC6 - University of Pittsburgh

4/17/2014

28

Equipment Estimate RS Means Durations

MC6

Retaining Wall Example

MC6

Page 29: MC6 - University of Pittsburgh

4/17/2014

29

Sections MC6 MANAGEMENT POLICY STATEMENT RESPONSIBILITIES◦ CORPORATE SAFETY RESPONSIBILITIES ◦ SAFETY DIRECTOR RESPONSIBILITIES◦ SUPERINTENDENT/FOREMAN RESPONSIBILITIES◦ EMPLOYEE RESPONSIBILITIES

CONSEQUENCES AND DISCIPLINARY ACTIONS NEW EMPLOYEE TRAINING ACCIDENT INVESTIGATION RECORD KEEPING SUBCONTRACTOR COMPLIANCE TOOLBOX TALKS PROJECT SPECIFIC CONCERNS

MC6

Page 30: MC6 - University of Pittsburgh

4/17/2014

30

Communication Electrical Personal Protective Equipment Tools Trenching and Excavation Cranes Machinery Fire Protection Housekeeping Material Handling

MC6

AMBULANCE 911

POLICE 911

FIRE 911

MINOR INJURIES:MedExpress Brentwood (9am-9pm) (412) 884 - 03273516 Saw Mill Run Blvd, Pittsburgh PA

DirectionsSouth on SR-51(Saw Mill Run Blvd) go 1.2 miles MedExpress on RIGHT

HOSPITALSt Clair Hospital (412) 942 – 40001000 Brower Hill Rd, Pittsburgh, PA

DirectionsWest of SR-88 (Library Rd) go 0.2 milesTurn RIGHT onto Castle Shannon Rd go 1.1 milesContinue onto Scott Rd go 1.0 milesTurn LEFT onto Washington Rd go 0.1 milesTurn RIGHT onto Bower Hill Rd go 1.4 milesSt Clair Hospital on RIGHT

MC6

Page 31: MC6 - University of Pittsburgh

4/17/2014

31

Includes electric, telephone, cable TV, fiber optics, natural gas, water, sanitary and storm sewers.

MC6

Page 32: MC6 - University of Pittsburgh

4/17/2014

32

Saw Mill Run Interceptor Relocation

394 LF 36-inch class IV sewer

4 manholes installed

Reconnect to existing 36-inch sewer

MC6

579 LF epoxy lined iron sewer 574 LF reinforced concrete pipe sewer 20 pre-cast manholes with cast-in-place

bases Fill abandoned sewers with 122 CY grout

MC6

Page 33: MC6 - University of Pittsburgh

4/17/2014

33

Communication is key. Invite each company to review the existing

utility plan set. Invite each utility company to a preliminary

Utility Coordination Meeting. Identify potential conflicts. Notify utility owner in writing at least 15 days

prior to starting operation.

MC6

Pennsylvania American Water Company 60 days are required after the contractor’s notice to proceed.

Columbia Gas 120 days are required after the contractor’s

notice to proceed.Seasonal shutdown restrictions will limit

construction April – September.

MC6

Page 34: MC6 - University of Pittsburgh

4/17/2014

34

Duquesne Light180 days are required after contractor’s notice to proceed.

Comcast60 days are required after D.L. completes their work.

Verizon397 days are required after Comcast completes their work.

MC6

Utility relocation conflicts are a major cause of delays to highway contractors.

PennDOT will compensate the contractor for utility delays where the delay occurred through no fault of the contractor.

Within 10 days of any utility relocation delay, contractor must notify PennDOT.

MC6

Page 35: MC6 - University of Pittsburgh

4/17/2014

35

Keep daily records of labor, material, equipment, and site overhead expenses for all operations affected.

Weekly- Prepare and submit a written report that indicates the number of days behind schedule, explain how utility relocation delayed operations.

MC6

Upon completion of the project, submit a report that contains itemization of all extra costs and a list of actions taken to minimize delay.

Submit dates when utility owner was contacted and copies of minutes from any meetings with the owner.

MC6

Page 36: MC6 - University of Pittsburgh

4/17/2014

36

Process◦ Identify◦ Analyze Probability/Impact Category Cost, Scope, Schedule, Quality

◦ Response Approach Avoid, Mitigate, Accept, Transfer, Defer

MC6

Page 37: MC6 - University of Pittsburgh

4/17/2014

37

MC6

MC6

Page 38: MC6 - University of Pittsburgh

4/17/2014

38

MC6

Page 39: MC6 - University of Pittsburgh

4/17/2014

39

Quality Assurance◦ Ensure work will be performed correctly

Quality Control◦ Verify work is being performed correctly

Process◦ Procedures◦ Inspections◦ Schedules

MC6

MC6

Page 40: MC6 - University of Pittsburgh

4/17/2014

40

MC6

MC6

Page 41: MC6 - University of Pittsburgh

4/17/2014

41

MC6

MC6

Page 42: MC6 - University of Pittsburgh

4/17/2014

42

Detailed real-time traffic modeling Any scenario can be modeled Test designs before implementation Before and after comparison

MC6

Page 43: MC6 - University of Pittsburgh

4/17/2014

43

MC6

MC6

Page 44: MC6 - University of Pittsburgh

4/17/2014

44

Furnish and Install Reinforcing Steel

MC6

Page 45: MC6 - University of Pittsburgh

4/17/2014

45

Storm Water Detention Tank

MC6

Page 46: MC6 - University of Pittsburgh

4/17/2014

46

MC6

MC6

Page 47: MC6 - University of Pittsburgh

4/17/2014

47

MC6

West Storm Water Detention Tank

Page 48: MC6 - University of Pittsburgh

4/17/2014

48

MC6

MC6

Page 49: MC6 - University of Pittsburgh

4/17/2014

49

MC6

MC6

Page 50: MC6 - University of Pittsburgh

4/17/2014

50

MC6

MC6

Page 51: MC6 - University of Pittsburgh

4/17/2014

51

MC6

MC6

Page 52: MC6 - University of Pittsburgh

4/17/2014

52

MC6

MC6

Page 53: MC6 - University of Pittsburgh

4/17/2014

53

MC6

East Storm Water Detention Tank

Page 54: MC6 - University of Pittsburgh

4/17/2014

54

MC6

MC6

Page 55: MC6 - University of Pittsburgh

4/17/2014

55

MC6

MC6

Page 56: MC6 - University of Pittsburgh

4/17/2014

56

MC6

MC6

Page 57: MC6 - University of Pittsburgh

4/17/2014

57

MC6

MC6

Page 58: MC6 - University of Pittsburgh

4/17/2014

58

MC6

West Tank

Page 59: MC6 - University of Pittsburgh

4/17/2014

59

MC6

MC6

Page 60: MC6 - University of Pittsburgh

4/17/2014

60

MC6

MC6

Page 61: MC6 - University of Pittsburgh

4/17/2014

61

MC6

MC6

Page 62: MC6 - University of Pittsburgh

4/17/2014

62

West Tank

MC6

Page 63: MC6 - University of Pittsburgh

4/17/2014

63

MC6

Questions?

MC6

Page 64: MC6 - University of Pittsburgh

4/17/2014

64

Thank You

MC6

A very special thank you to:Dr. OylerProf. BeckDr. MagalottiHeath Butler of PennDOTBrian Frye of JB Fay

Thank you to all Civil engineering faculty