2016 Louisiana Energy Conference June 1, 2016
McDermott Deepwater Overview
Brennan Roy Senior Business Development Manager
Forward‐Looking StatementsIn accordance with the Safe Harbor provisions of the Private Securities Litigation Reform Act of 1995, McDermott cautions thatstatements in this presentation which are forward‐looking, and provide other than historical information, involve risks, contingencies anduncertainties that may impact McDermott’s actual performance and results of operations. The forward‐looking statements in thispresentation include, but are not limited to, statements about backlog, bids outstanding and target projects, and the anticipatedbreakdown and timing of award of the associated contracts and expected backlog roll‐off, to the extent these may be viewed asindicators of future revenues or profitability, market trends and overall expected market size, expectations regarding McDermott’s globaland in‐market capabilities, expectations regarding opportunities provided by geographical diversity, the expected specifications of andoperations related to the DLV 2000, expected benefits from our joint ventures and alliances, the expected scope, execution, timing andvalue of projects discussed herein, expected benefits and savings resulting from our cost saving initiatives, including those resulting fromthe Additional Overhead Reduction (“AOR”) program, focus areas and priorities for McDermott’s business going forward andMcDermott’s earnings and other guidance for 2016. Although we believe that the expectations reflected in those forward‐lookingstatements are reasonable, we can give no assurance that those expectations will prove to have been correct. Those statements aremade by using various underlying assumptions and are subject to numerous risks, contingencies and uncertainties, including, amongothers: adverse changes in the markets in which we operate or credit markets, our inability to successfully execute on contracts inbacklog, changes in project design or schedules, the availability of qualified personnel, changes in the scope, terms or timing of contracts,contract cancellations, change orders and other modifications and actions by our customers and business partners, difficulties executingon the project, changes in industry norms and adverse outcomes in legal and other dispute resolution proceedings. If one or more ofthese risks materialize, or if underlying assumptions prove incorrect, actual results may vary materially from those expected. You shouldnot place undue reliance on forward‐looking statements. For a more complete discussion of these and other risk factors, please seeMcDermott’s annual and quarterly filings with the Securities and Exchange Commission, including its annual report on Form 10‐K for theyear ended December 31, 2015 and subsequent quarterly report on Form 10‐Q. This presentation reflects management’s views as of thedate hereof. Except to the extent required by applicable law, McDermott undertakes no obligation to update or revise any forward‐looking statement.
|2
A Look at McDermott
McDermott is a leading EPCI company Offshore upstream oil and gas projects
Experienced management team Worldwide presence with 11,600 employees Commitment to safety, quality and ethics NYSE listed : MDR since 1954 Pioneering Louisiana company founded in in
1923
|3
Offshore: Fixed Platforms, floating production systems, export pipelines
Subsea: Subsea hardware, umbilical, riser and flowline installation
EPCI: Full field development or single project delivery
McDermott’s Infrastructure and Solutions
• 1,100+ engineers globally• Offices in 10 locations
worldwide• FloaTEC, LLC 50:50 JV with
Keppel FELS• IO Oil & Gas Consultants
50:50 JV with GE
Capabilities / Services:• Studies & conceptual
designs• Front-End Engineering &
Design (FEED)• Detailed engineering &
design • Greenfield & Brownfield
engineering• Transportation &
installation engineering
EPCI . . . Unique Delivery Platform
Engineering• Dedicated Supply Chain
Management• 500+ dedicated
employees
Capabilities / Services:• Negotiating, purchasing,
transporting, inspecting, inventory control and quality assurance
• Global sourcing• Deep local knowledge• Strong supplier relations
ProcurementStrategically located facilities • Aggregate area: 600+
acres• Largest deck to date
23,000 tons• Largest jacket to date
38,000 tons
Capabilities / Services:• Topsides & onshore
modules• Jackets, piles & compliant
towers• TLPs, SPARs, FPSOs• Subsea production systems• Standardized fabrication
processes & procedures
ConstructionDedicated installation fleet• Global construction
fleet, multi-functional and subsea support vessels
Capabilities / Services: • Single & dual heavy-lift• Floatover install• Various diameter
pipeline install − S-Lay, J-Lay, Flex-Lay
and Reel-Lay• Dynamic positioning &
mooring systems• Subsea installation
support• De-commissioning
Installation
Fully Integrated, Single‐Source Solutions For Worldwide Offshore And Subsea Developments
5
Construction: Driving to a global standard of efficiency
|7
Jebel Ali / Dammam BatamAltamira
• Global, in‐market fabrication facilities with in‐house full control of cost, quality and schedule
• Instituted fabrication council to drive global process while streamlining supervision and structure
• Creating the ability to workshare
• Optimized processes and procedures
• JVs providing access to low cost and in‐market solutions
• A relentless culture of improvement
China
Malaysia
Control of Fabrication is an EPCI Sustainable Competitive Advantage
Installation: Shallow to deep throughout the lifecycle
|8
Dynamically Positioned Vessel
Anchored Vessel
Hook‐up & Commissioning
Versatile Fleet with Broad Capabilities is a Differentiator
• Class 3 dynamically positioned vessel with a 2,200‐ton crane and deepwater S‐lay pipelay system
• Fast transit speeds make the DLV2000 a global asset
• A full solution of shallow water fleet capabilities with versatile subsea fleet
• Supported by in‐market teams
• Expertise in complex brownfield installation, hook up and commissioning
Heavy Lift and High‐End Pipelay Vessel
DLV 2000:
9
Specialized Marine Fleet
Rigid Reel Lay Heavy Lift/Pipelay (S‐Lay/J‐Lay)Flex Lay
Launch Barges
Emerald Sea
NO 105
CSV 108
DB50
DB 27
DB101
Thebaud Sea
DB30
Agile
Intermac 650Intermac 600
Construction Support Vessels
DB32
NO 102 DLV2000
10
Gulfport, Gulf of Mexico (New 2016) Deepwater Pipelay Spoolbase ‐ Facility and storage 50 + acres
Derrick Lay Vessel (DLV) 2000 (Coming 2016)
11
Heavy lift pipe‐lay vessel
Deepwater S‐Lay capability:
4.5 to 60 inches
Derrick Lay Vessel (DLV) 2000 (New 2016)
12
DLV 2000 will add high‐end capabilities and versatility to our existing fleet. Heavy lift, rigid pipelay, subsea construction, accommodations and fast transit speeds for shallow and deepwater locations around the world.2000MT CraneS‐Lay w/ 450MT top tension
Scheduled to work in 2016 and 2017 on the INPEX Ichthys and Woodside Greater Western Flank Phase II Projects in Australia
|13
INVESTORCONTACT
Katherine MurrayVice President, Treasurer and Investor [email protected]
The information contained herein is provided for general information purposes only and is not intended or to be construed as a warranty, an offer, or any representation of contractual or other legal responsibility. McDermott has a policy of continuous improvement of its
products and services and reserves the right to change information including specifications and processes without notice.
Thank You