McMILLAN PAZDAN SMITH WCI GROUP LLC FIELD REPORT PROJECT: Leavelle McCampbell Middle FIELD REPORT NO.: Fifty (50) CONTRACT: Construction Management @ Risk HG Reynolds ARCHITECTS PROJECT NO.: Page 1 of 7 DISTRIBUTION: Owner: Dr. Shawn Foster, Aiken County Schools Mr. Kevin Chipman, Aiken County Schools Ms. Michelle Padgett, Aiken County Schools Ms. Beth Clark, Aiken County Schools Mr. Kip Gunter, Aiken County Schools Ms. Sandra Waddell, Aiken County Schools Mr. Jeremiah Jones, Aiken County Schools Architect: Mr. Donnie Love, McMillan Pazdan Smith Mr. Bill Williams,WCI Mr. Robert Wayne, WCI Consultant: Mr. Mayhar Angooraj, BGA Mr. William Wafer, BGA Mr. Dan Reider, BGA Mr. Tilden Hilderbrand, Hass & Hilderbrand Contractor: Mr. Jeffrey Reynolds, HG Reynolds Mr. Robert Lowe, HG Reynolds Mr. Graham Reynolds, HG Reynolds DATE: Aug. 16, 2016 WEATHER: Sunny / 99 / Humid TIME: 1:30 pm SCHEDULE COMMENTS: On Schedule PRESENT AT SITE: HJR General Contractor, HVAC, Plumbing, Electrical, Masonry, Roofing OBSERVATION: 1) Site conditions are dry as masonry veneer continues progress aggressively. The Contractor (Masonry) is continues @ approximately (99%) on 3 sides with moisture barrier and brick veneer install is continuous at front façade. Masonry contractors work is consistent. 2) Interior CMU walls in areas are damp due to previous weeks rain. Point work has slowed. 3) Slabs remain wet in partial areas throughout building both first and second floors. 4) Contractor install of additional temporary lights are inconsistent in several areas both first and second floors. This work is ongoing. 5) Roofing contractor work is aggressive and is consistent as flash of penetration for roof top curbs, devices and / or structures is ongoing. Roof install inspections are current. 6) First floor HVAC duct, gas, domestic water lines progress is continuous and consistent, as prime mastic seal and seismic fastener application are continuous and as specified in corridors, gym and cafeteria. 7) Scheduled HVAC 500lb and 700 lb. Air Handler Units have been delivered and received by contractor. 8) Fire sprinkler riser rooms and progressing as contractors nears (75%) install at riser rooms 9) CCI inspection are coordinated by CI Group as required by jobsite and consistent and documented. 10) The Electrical contractor has progressed to approximately (75%)complete roughed in on first floor as panel boxes and conduits are place to received required wire pull. Coordination is consistent. 11) Electrical scope of work maintains a critical status on second floor as rough in continues. 12) Temporary lights are required on second floor as coordination by contractor is ongoing. 13) Contractors stud framing work continues with specified details. As partial scheduled inspections have been provided and documented. 14) Contractor site maintenance and cleanup is continuous with current CMU debris and standing rain water is required.

McMILLAN PAZDAN SMITH WCI GROUP LLC FIELD REPORT

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

McMILLAN PAZDAN SMITH WCI GROUP LLC

FIELD REPORT

PROJECT: Leavelle McCampbell Middle

FIELD REPORT NO.: Fifty (50)

CONTRACT: Construction Management @ Risk

HG Reynolds ARCHITECTS

PROJECT NO.:

Page 1 of 7

DISTRIBUTION: Owner:

Dr. Shawn Foster, Aiken County Schools

Mr. Kevin Chipman, Aiken County Schools

Ms. Michelle Padgett, Aiken County Schools

Ms. Beth Clark, Aiken County Schools

Mr. Kip Gunter, Aiken County Schools

Ms. Sandra Waddell, Aiken County Schools

Mr. Jeremiah Jones, Aiken County Schools

Architect: Mr. Donnie Love, McMillan Pazdan Smith

Mr. Bill Williams,WCI

Mr. Robert Wayne, WCI

Consultant: Mr. Mayhar Angooraj, BGA

Mr. William Wafer, BGA

Mr. Dan Reider, BGA

Mr. Tilden Hilderbrand, Hass & Hilderbrand

Contractor: Mr. Jeffrey Reynolds, HG Reynolds

Mr. Robert Lowe, HG Reynolds

Mr. Graham Reynolds, HG Reynolds

DATE: Aug. 16, 2016

WEATHER: Sunny / 99 / Humid

TIME: 1:30 pm SCHEDULE

COMMENTS:

On Schedule

PRESENT AT SITE: HJR General Contractor, HVAC, Plumbing, Electrical, Masonry, Roofing

OBSERVATION:

1) Site conditions are dry as masonry veneer continues progress aggressively. The Contractor (Masonry) is

continues @ approximately (99%) on 3 sides with moisture barrier and brick veneer install is continuous at

front façade. Masonry contractors work is consistent.

2) Interior CMU walls in areas are damp due to previous weeks rain. Point work has slowed.

3) Slabs remain wet in partial areas throughout building both first and second floors.

4) Contractor install of additional temporary lights are inconsistent in several areas both first and second

floors. This work is ongoing.

5) Roofing contractor work is aggressive and is consistent as flash of penetration for roof top curbs, devices

and / or structures is ongoing. Roof install inspections are current.

6) First floor HVAC duct, gas, domestic water lines progress is continuous and consistent, as prime mastic

seal and seismic fastener application are continuous and as specified in corridors, gym and cafeteria.

7) Scheduled HVAC 500lb and 700 lb. Air Handler Units have been delivered and received by contractor.

8) Fire sprinkler riser rooms and progressing as contractors nears (75%) install at riser rooms

9) CCI inspection are coordinated by CI Group as required by jobsite and consistent and documented.

10) The Electrical contractor has progressed to approximately (75%)complete roughed in on first floor as panel

boxes and conduits are place to received required wire pull. Coordination is consistent.

11) Electrical scope of work maintains a critical status on second floor as rough in continues.

12) Temporary lights are required on second floor as coordination by contractor is ongoing.

13) Contractors stud framing work continues with specified details. As partial scheduled inspections have been

provided and documented.

14) Contractor site maintenance and cleanup is continuous with current CMU debris and standing rain water is

required.

McMILLAN PAZDAN SMITH WCI GROUP LLC

FIELD REPORT

PROJECT: Leavelle McCampbell Middle

FIELD REPORT NO.: Fifty (50)

CONTRACT: Construction Management @ Risk

HG Reynolds ARCHITECTS

PROJECT NO.:

Page 2 of 7

SUBMITTALS: 1) Submission is in progress.

COORDINATION: 1) Bi-weekly meeting Tuesday 10:00 am, August 23 ,2016.

INSPECTIONS: 1) Coordination by WCI Group

DEFICEINT WORK:

1) Temporary Light Fixtures

PHOTOS: Attached

View of East and North facades

McMILLAN PAZDAN SMITH WCI GROUP LLC

FIELD REPORT

PROJECT: Leavelle McCampbell Middle

FIELD REPORT NO.: Fifty (50)

CONTRACT: Construction Management @ Risk

HG Reynolds ARCHITECTS

PROJECT NO.:

Page 3 of 7

Masonry façade @ Gymnasium

Interior Framing typical @ Cafeteria

McMILLAN PAZDAN SMITH WCI GROUP LLC

FIELD REPORT

PROJECT: Leavelle McCampbell Middle

FIELD REPORT NO.: Fifty (50)

CONTRACT: Construction Management @ Risk

HG Reynolds ARCHITECTS

PROJECT NO.:

Page 4 of 7

Framing furring, studs for soffitts and headers (Typical) Administration area.

View of Electrical Panel Room as conduits have installed to panels boxes (Typ)

McMILLAN PAZDAN SMITH WCI GROUP LLC

FIELD REPORT

PROJECT: Leavelle McCampbell Middle

FIELD REPORT NO.: Fifty (50)

CONTRACT: Construction Management @ Risk

HG Reynolds ARCHITECTS

PROJECT NO.:

Page 5 of 7

View of indoor AHU placed on pads

View of 500lbs and 700lbs AHU

McMILLAN PAZDAN SMITH WCI GROUP LLC

FIELD REPORT

PROJECT: Leavelle McCampbell Middle

FIELD REPORT NO.: Fifty (50)

CONTRACT: Construction Management @ Risk

HG Reynolds ARCHITECTS

PROJECT NO.:

Page 6 of 7

Fire Sprinkler Riser Rooms nearing 75% complete (Typ)

McMILLAN PAZDAN SMITH WCI GROUP LLC

FIELD REPORT

PROJECT: Leavelle McCampbell Middle

FIELD REPORT NO.: Fifty (50)

CONTRACT: Construction Management @ Risk

HG Reynolds ARCHITECTS

PROJECT NO.:

Page 7 of 7

Gymnasium View as masonry walls continue to dry

Masonry Veneer view has progressed to approximately 80% overall to completions

Reported by: Wayne Jr. -WCI Group