MCOE Project Report

Embed Size (px)

Citation preview

  • 8/8/2019 MCOE Project Report

    1/37

    CHANGE MANAMGEMENTAT TOYOTA FINANCIAL

    SERVICESAn MCOE report submitted in partial fulfillment of the

    requirements

    For the award of the degree

    Of

    POST GRADUATE DIPLOMA IN MANAGEMENT

    Approved by AICTE

    2009-11

    (Equivalent to MBA)

    Submitted To: SubmittedBy:

    Prof. Anita Singh NISHI SHUKLA-9245

    Chairperson HR AVANEE TAYAGI-9054

    IMS (GZB) MOHSIN ALI-9111

    MADHUBALA SHARMA-9099

    PRASHANT PRIYADARSHI-9145

    INSTITUTE OF MANAGEMENT STUDIES

  • 8/8/2019 MCOE Project Report

    2/37

    GHAZIABAD

    DECLARATION

    I hereby certify that we has successfully completed our report on STUDY OFCHANGE MANAGEMNT IN TOYOTA FINANCIAL SERVICES, USA. This isalso to certify that this report is an original product and no unfair means like copyingetc have been used for its completion.

    NISHI SHUKLA -9245

    AVANEE TYAGI -9054

    MADHUBALA SHARMA -09099

    PRASHANT PRIYADARSHI -9145

    MOHSIN ALI -9111

    2

  • 8/8/2019 MCOE Project Report

    3/37

    ACKNOWLEDGEMENT

    For the preparation of this report and for all the personal insight into the study ofChange Management Systems and Processes of TOYOTA FINANCIALSERVICES, USA. I would like to take this opportunity to extend my sincerest noteof gratitude to PROF. ANITA SINGH (CHAIRPERSON HR) without which ourlearnings and insights would not have taken place.

    This report would have been incomplete without our acknowledging the immensecontribution and encouragement of my project guide, who has been instrumental at allimportant stages of knowledge-assimilation and report-preparation of this period.

    I would like to thank you for providing us with this wonderful opportunity andguidance.

    3

  • 8/8/2019 MCOE Project Report

    4/37

    TABLE OF CONTENT

    DECLARATION 2

    ACKNOWLEDGEMENT 3

    TABLE OF CONTENT 4

    EXECUTIVE SUMMARY 5

    OBJECTIVE 6

    COMPANY PROFILE 7

    INTRODUCTION 9

    TYPES OF PMO 11

    TFS PMO DESIGN 13

    HISTORY OF PMO 15

    ORGANIZATIONAL INFLUENCES 18

    CHANGE AND CULTURE 24

    CORE STRATEGY 27

    MAPPING THE WAY 28

    LESSON LEARNED APPROACH 31

    LIMITATION 32

    CONCLUSION 33

    REFERENCES 34

    ANNEXURE 35

    4

  • 8/8/2019 MCOE Project Report

    5/37

    EXECUTIVE SUMMARY

    The increased recognition of project management as an effective means of completinglarge and complex efforts has led to a proliferation of projects within a company. This

    has increased interest in developing Program Management Offices (PMOs) to

    coordinate projects across the organization. Developing and implementing a PMO

    within an organization can be difficult. While executives are ready to accept the

    benefits a PMO brings, some project managers have difficulty accepting a loss of

    control.

    In 2001 Toyota Financial Services made the decision to implement a PMO. There

    were three areas that provided particular challenges to the process: managing a

    complex process change, the high percentage of contractors in the workforce, and a

    collaborative Japanese culture populated by more individualistic Americans.

    Leadership In Action is an excellent value and an indispensable tool for improving

    your leadership and your organization. By uniting the insights of top scholars and the

    experience of working executives, each issue provides the best strategies for

    confronting such critical issues as leading a diverse workforce, maximizing the

    effectiveness of teamwork, stimulating creativity in the workforce, and more.

    5

  • 8/8/2019 MCOE Project Report

    6/37

    OBJECTIVE

    To study the impact of organizational change management in TOYOTA Financial

    Services, USA. More specifically to study the :

    Implementation of PMO (Program Management Office).

    Implementation of Leadership in action at TFS, USA

    6

  • 8/8/2019 MCOE Project Report

    7/37

    COMPANY PROFILE

    Since opening its doors in 1983, Toyota Financial Services has grown from a smallcompany with eight associates to one that currently employs approximately 3,300

    associates nationwide with managed assets in excess of $81 billion.

    The Toyota Financial Services brand identity was launched in December 1999. TFS is

    a service mark that acts as an umbrella brand name used to market the products of

    Toyota Motor Credit Corporation (TMCC) and Toyota Motor Insurance Services, Inc.

    (TMIS). TMCC was incorporated in California on October 4, 1982, and commenced

    operations in May 1983 by approving a finance contract for a used Toyota Corolla in

    Denver, Colorado. The company provides retail and wholesale financing, retail

    leasing, vehicle protection plans and certain other financial services to authorized

    Toyota, Lexus and Scion dealers, Toyota forklift and Hino dealers as well as Toyota

    Material Handling, U.S.A. dealers, affiliates, and their customers in the United States

    (excluding Hawaii).

    TFS is part of the worldwide financial services operations for Toyota Financial

    Services Corporation (TFSC), which is a wholly owned subsidiary of Toyota Motor

    Corporation (TMC) in Japan. TFS has three Regional offices, three Customer Service

    Centers, 30 Dealer Sales and Service Offices throughout the United States, and an

    affiliate financial services company in Puerto Rico.

    Toyota Motor Credit Corporation (TMCC) is one of the largest consumer finance

    companies in the U.S. and one of the highest-rated captive auto finance companies in

    the world with AA/Aa2 long-term credit ratings by Standard & Poor and Moody's,

    respectively.

    7

  • 8/8/2019 MCOE Project Report

    8/37

    Originally known as TMCC Equipment Finance, Toyota Financial Services

    Commercial Finance, a division of Toyota Motor Credit Corporation began operations

    in November 1984. We funded our first wholesale flooring (dealer) transaction in

    January 1985 and our first lease (customer) transaction in November 1985. Today,

    TFS Commercial Finance offers financial services to support Toyota Industrial

    Equipment and Hino Motor Sales dealers across the USA. Dedication to customers

    and dealers has earned Toyota Financial Services a reputation for service excellence

    in the commercial finance industry.

    8

  • 8/8/2019 MCOE Project Report

    9/37

    INTRODUCTION

    The Program Management Office

    Program offices trace their origins back to the Project Support Offices (PSOs)

    that cropped up in the 1960s to help large, complex aerospace and

    construction projects. As automated support tools such as the original Artemis

    scheduling application started to appear and become more widespread, the

    direction of program offices changed to include tools support to project

    managers. The emphasis changed again during the 1990s to include

    coordination among multiple projects to ensure consistency in PM practicesand quantitative portfolio management. While individual projects may have

    specific PSOs depending on the projects size and complexity, more often now

    the enterprises Program Management Office (PMO) provides support across a

    variety of projects that the organization is involved in. The Meta Group

    estimates that deploying a Project Office can reduce project failures by up to

    80% [STANDISH, 1995].

    While there is still confusion in the literature about whether such an office is a

    Project Office, a Program Office, a Project Support Office, or a Program

    Management Office, for the purposes of this article we will use the term

    Program Management Office to specify a project-centered organization which

    supports a variety of projects across the enterprise.

    Leadership In Action

    About five years ago, Toyota Financial Services (TFS) began an incremental process

    of establishing a leadership strategy that reflects both an orientation toward

    performance and a firm foundation for development.The strategic initiative

    started when the CEO, George Borst, and the organizations human resourcedepartment (HR) realized that TFS needed to change the way talent was being

    managed and developed. TFS also recognized that several things needed to occur to

    accomplish this.When TFS began its initiative, itwas already exceeding goals and

    9

  • 8/8/2019 MCOE Project Report

    10/37

    expanding into new markets. But theCEO wanted to create an organizationin which

    leaders maximized their results by developing and growing the capabilities of their

    people. Borstunderstood that this was a long-terminvestment that ultimately would

    Strengthen TFSs organizational capabilities. He also knew that key cultural andinfrastructure changes would beneeded to sustain lasting change. Theresult was that

    the CEO partneredwith HR, giving that department theopportunity and challenge to

    helplead TFS in this new directionbecoming a higher-performanceorganization.

    For TFS, a higher-performance organization is one that values performance,

    development of people, accountability for results, and strong leadershipand that is

    always ready for change. (The word higher in the term higher-performance

    organization was deliberately chosen to imply that even after the organization

    becomes better than it is today, there will always be room for more improvement.)

    Although TFS had many attributes that supported achievement of its objective,

    several key cultures are needed to be addressed.

    10

  • 8/8/2019 MCOE Project Report

    11/37

    TYPES OF PMOS

    Given that PMOs will oversee multiple projects, what types of things should a PMO

    do? The answer depends as much on the organizations needs as it does on anything

    else. There is not one right way to design a PMO. There are a variety of services and

    products that a PMO can offer an organization, and which ones the PMO will have

    when it is deployed depends on the specific needs of the organization.

    At the very least, a PMO can profitably serve to support a single function, such as a

    repository for historical project information or a location for project coordinatrs to

    live. As a historical repository it can gather the results of previous projects and of

    lessons learned and make them available for project managers to search through

    before they begin new projects. This becomes the corporate knowledge repository so

    that experience gained is not lost when people leave.

    At the high end, a PMO can change the PM culture [BLOCK 1999] and provide:

    Enterprise-wide project coordination and consistency.

    Set standards and methodologies for all projects in the enterprise

    Do quality audits of the projects.

    Help the management and executive teams select projects that support

    strategic goals.

    Help the executive team track the entire portfolio of projects in work by

    developing metrics and measuring all projects against those metrics.

    Identify the resources that are available to work on upcoming projects.

    Support the project managers and project teams with training mentoring, and

    career development.

    11

  • 8/8/2019 MCOE Project Report

    12/37

    Collect and archive the documents from completed projects and analyze them

    for trends.

    Provide a knowledge management system that gathers all project-relatedinformation.

    Makes it available in a readily accessible and useful format.

    The way the PMO is designed in any one-organization will usually lie somewhere

    between these two extremes, with the specific functions chosen according to the needs

    of the organization. At a major utility in California, the PMO in their Infrastructure

    Organization is referred to as the Nerve Center for the organization. Within Toyota

    Financial Services (TFS), the PMO has a strong emphasis on strategic project support

    and portfolio management.

    12

  • 8/8/2019 MCOE Project Report

    13/37

    TFS PMO DESIGN

    Toyota Financial Services is a relatively new company, having separated from Toyota

    Motor Sales (TMS) in 2000. At the time of the separation, TMS was assessing its

    project management capabilities. This assessment continued after the companies

    separated. The results of the analysis indicated that the best way to increase the

    abilities of TFS to deliver projects on time while meeting all of the business needs

    would be to institute a PMO. Experts were hired as contractors and the PMO

    organization structure shown in Figure 1 was developed based on TMSs needs.

    This is a true enterprise-wide PMO. It supports the executive branch, giving them an

    objective oversight into the current status of all projects as well as a project selectionprocess that is oriented towards the TFS strategic goals. It also supports the project

    managers, providing them best-practices methodologies and processes as well as

    administrative help in managing project schedules and, in the future, project costs.

    A major driver to the PMO design was that there were almost three dozen projects in

    work and more in the queue. The executive-level Governance committee managed

    this portfolio of projects, but they had very little factual data to base their decisions on

    when it came time to selecting and prioritizing projects or even understanding the

    current status of projects. Inputs were given them by the project managers who would

    sometimes gloss over problems on their projects and report that everything was going

    well even when it wasnt.

    There were several projects that were reported as being in work, even though no

    resources had been assigned to them beyond the project manager. There was one

    particularly important project that had a requirements analysis done, a project

    manager assigned, and no resources given it for almost two years after it had been

    started. This was the environment the PMO was designed in.

    13

  • 8/8/2019 MCOE Project Report

    14/37

  • 8/8/2019 MCOE Project Report

    15/37

    RECENT HISTORY OF PMOs AT TOYOTA

    THE TMS PMO

    This is not the first attempt at a PMO that has been developed. In discussions with

    employees at Toyota Motor Sales, it was revealed that a PMO was created several

    years ago to address the project management problems that were evident at that time.

    The development was done internally using existing project managers.

    With the advantage of historical hindsight, the developers did almost all of the right

    things to create a strong PMO. They developed methods and processes, they worked

    with the Human Resources department to create skill requirements for project

    managers, and they studied and examined best practices to design the PMO.

    The one thing they did not do as well as they could have been to understand the needs

    of the project managers themselves. If they had, they would have readily seen that

    there were a number of organizational issues, unrelated to project management

    practices that were making it difficult to manage projects. As a result of the PMO

    developers not gathering requirements, the PMs had no input into the effort.

    The first few processes that were implemented did not address the specific needs of

    the PMs and were therefore ignored. This created a climate where the remaining

    processes were also simply ignored by the PMs and never resulted in any long-lasting

    improvements. The PMO was killed during 2001.

    15

  • 8/8/2019 MCOE Project Report

    16/37

    THE TFS PMO

    The development relationship between Toyota Financial Services and Toyota Motor

    Sales was a complex one and is still in the process of evolving. Project managerscould come from either organization, but the development staff for software products

    was in the TMS IS group. The development problems affected both organizations.

    TMS already had a PMO at the time of the separation, so TFS determined that in

    order to ensure their projects got managed, as efficiently as possible they also needed

    a PMO.

    At one point each organization had a separate project manager assigned to the same

    projects, both of them being told they were in charge. When it became apparent that

    dual managers was not a workable solution the decision was jointly made that it

    should be the business that manages the overall effort and not the technical group.

    Currently the project manager comes from the part of the organization that origina ted

    the initial request, from the business side if its a business product being developed or

    a regulatory-mandated change and from the technical side for a technology upgrade.

    The PMO at TFS started out small. Because it was created at a relatively low level inthe organization, its primary effort was gathering project financial data and reporting

    it to a mid-level financial officer. As the need for a full PMO became apparent during

    the project management assessment, the decision was made to create a fully

    functional enterprise-level PMO and to move the office organizationally so that it

    reported directly to the CIO. Because a PMO will impose significant changes to the

    project management process, it gains authority by being positioned as high in the

    organization as possible [Miller, 1998]

    In consideration of the organizational issues surrounding the separation of the

    business side from the technology side of the company, the design of the PMO and

    development of the PM methodology very carefully separated project management

    from any specific product development methodology.

    Thus the project manager is responsible for the overall management of the project,

    while the technical lead is responsible for selecting the software development

    16

  • 8/8/2019 MCOE Project Report

    17/37

    approach. At TFS the development group is implementing the Rational Unified

    Process (RUP) for much of the work and kept a more traditional waterfall approach

    for mainframe development work. The project management methodology design was

    made flexible so that the PM could adapt to whatever approach was chosen by the

    development lead.

    17

  • 8/8/2019 MCOE Project Report

    18/37

    ORGANIZATIONAL INFLUENCES

    Depending on the level of project management maturity within the organization and

    the functionality desired from the PMO, implementing a PMO can be a highly

    complex and difficult undertaking, equivalent to implementing a full Enterprise

    Resource Planning (ERP) package. It involves significant change to how project

    managers, development staff, and project sponsors perform their work.

    While designing the PMO architecture can take only a few months, implementing it

    across the organization in a way that makes it both acceptable to employees and

    efficient in its processes takes a lot longer. It can take three years before everyone

    involved in project management buys into the changes and the product developmentprocess becomes consistent and efficient. It can take another two years before the

    efficiencies recover the initial costs and the PMO becomes cost effective. This is a

    long-term commitment that requires significant buy-in from the top of the

    organization.

    In many organizations where there are no standard processes that everyone accepts,

    there was a sense of doing whatever was necessary to do what you wanted to do.

    Within one particular group, the feeling was that many of the existing processes were

    cumbersome and not designed to support the type of work they did.

    They discovered that efforts of less than 100 man-hours were considered maintenance

    work and therefore were not expected to follow project management processes. As a

    result, this group designed virtually all of their projects to be less than 100 hours,

    thereby avoiding much of the formality associated with developing new products.

    At TFS, there were three issues that needed to be dealt with during the

    implementation planning phase:

    1. Organizational change management issues.

    2. The Minimal Employees approach.

    3. A Japanese-style consensus-building culture.

    18

  • 8/8/2019 MCOE Project Report

    19/37

    ORGANIZATIONAL CHANGE MANAGEMENT

    Because one of the primary emphases of the PMO was to develop a consistent set of

    methodologies (including processes, tools, and templates), it would significantlychange how the project managers would manage projects. Without a standardized

    approach the project managers were free to manage their projects in any way they

    wished, with no specific reporting requirements or controls. Because of the poor

    experience with previous attempts to implement a PMO, the project managers were

    not immediately ready to support this effort. In addition to the project managers,

    project sponsors were also not completely ready to support the changes because it

    would remove some of their authority over the project and make it obvious to

    everybody which projects were having problems.

    It is often said that when you introduce a change into an organization,

    20% of the people will support the change because they are either unhappy

    with the existing state or theyre so new they have no investment in the

    existing culture.

    20% of the people will resist the change no matter how beneficial you say it is

    to them. They have so much invested in the existing process that they see no

    reason to change.

    The remaining 60% are waiting to see how beneficial the change is and how

    serious upper management is about instituting the change. They will become

    unsupportive if they feel this is just another quick-hit so that someone can say

    we created this improvement. But they will become supportive if they see that

    the change is successful and to their benefit.

    When we developed the implementation plan for the PMO we were sensitive to these

    numbers. As we developed new processes, forms, and templates, we reviewed them

    with both the project managers and the project sponsors. During the review cycles itbecame obvious that many of the changes we were getting simply moved the changed

    19

  • 8/8/2019 MCOE Project Report

    20/37

    processes back to where the old processes were and de-scoped the new processes so

    that the net result was very little change. It required a great deal of consensus building

    in order to convince many of these people that the changes would be to their long-

    term benefit and much of the approval was given with a well wait and see

    mentality.

    Because the PMO has a variety of functions in different areas, the implementation

    was prioritized with the effort going into the most critical areas first. The first area to

    be developed was the creation of a set of consistent project management

    methodologies (including processes, templates, examples, and forms). Once this was

    completed the next area was to provide an infrastructure to support the project

    managers with help in project schedule tracking and project initiation. The last effort

    to be implemented will be the strategic support to the executives so that they have a

    consistent approach to managing the entire portfolio.

    20

  • 8/8/2019 MCOE Project Report

    21/37

    THE MINIMAL EMPLOYEES APPROACH

    Both TFS and TMS are required to keep down the quantity of full-time employees,

    presumably so that if the economic conditions deteriorate there will not be a need to

    lay people off. However, the amount of work that must be done grows as more

    products are sold. Without being able to hire employees the organizations turn to

    hiring contractors and consultants to fill the gap. Because the work is not necessarily

    simple, the contractors can be there for several years, a situation that is not

    uncommon in many companies.

    This use of contractor labor, in some parts of the organization 30% of the total labor

    force, has several effects. While many American companies have justified the use of

    contract labor as saying it gives them more flexibility because they can rapidly obtain

    the newest skill sets, the problems created by having a high percentage of contractors

    may outweigh that slight benefit.

    One major side effect is that much corporate knowledge resides with people who can

    leave at any time. While this is true of employees also, the turnover rate among

    contractors is higher because they are constantly aware of better opportunities outside

    the firm. Also, critical skills may be lost from the company. Operations of the

    mainframe computer system has been contracted to an outside firm. While the firm is

    well established and well-known, if they decide to cancel their contract Toyota no

    longer has the skills necessary to run their own mainframes. Additionally, there is an

    increasing gap between the skills needed to compete in todays environment and the

    skills of the employees. When skills can be hired on a temporary basis there is little

    incentive to invest in employees developing these skills.

    Within the PMO we were very sensitive to the fact that many of the project managers

    used by TFS were consultants. Our feeling was that project management should be

    considered a core competency of the organization and should be done by employees.

    Successful project managers have many soft skills that are necessary to consistently

    21

  • 8/8/2019 MCOE Project Report

    22/37

    deliver projects and that are specific to the organization they work in. If these people

    leave after a project is completed those skills leave with them and any new project

    managers brought in must relearn the same skill sets. Relearning how to be successful

    when those skills are already known is an unproductive way to spend time.

    Another side effect that we had to deal with in implementing the PMO was the fact

    that with so many contractors, much of the real power in the organization was

    concentrated in the hands of a relatively small number of middle managers. These are

    the people who own the business resources and they have the ability to slow down or

    kill any effort they choose not to assign resources to. Any change that occurred in the

    organization had to be filtered through them and approved by them.

    This was the group that provided the greatest amount of resistance to the PMO

    implementation. They saw themselves as giving up a significant amount of power to

    this new organization. When the PMO was elevated during the implementation

    process to reporting directly to the CIO some of this problem was mitigated because

    people saw that the PMO was being taken seriously. Prior to that a large amount of

    time was spent working with and coordinating with this management tier. As

    documents were routed for coordination many of the comments were designed to

    return the processes to the old way of doing things.

    22

  • 8/8/2019 MCOE Project Report

    23/37

    JAPANESE-STYLE CONSENSUS BUILDING CULTURE

    What was most challenging about working within the TFS culture was not the fact

    that it was originally modeled on the Japanese management approach of coordination

    and consensus building. What was most challenging was that we have a Japanese

    culture populated by Americans, many of whom came in with a typically American

    attitude that Im going to do whatever it takes to get this job done.

    The result was a set of clashes between people who had been with the organization for

    several years and were comfortable with the culture and people who were relatively

    new and were more at home with a style that recognized individual initiative rather

    than slow and careful consensus building.

    This provided challenges during the implementation of the PMO. Both the people

    who wanted rapid improvements and the middle-tier of managers who wanted to

    spend several weeks reviewing every change and assessing its impact had to be

    accommodated for the rollout.

    A two-fold approach was taken to ensure that buy-in was obtained from both groups.

    We worked with the project managers to identify where their biggest problems were

    and identified quick fixes to those problems. The quick fixes were designed to resolve

    the problem with as little impact to other areas as possible.

    For example, when the project managers complained that there were too many

    documents that they had to generate and that they were never aware of what all the

    documents were, the PMO team created a checklist showing which documents were

    required for the different phases of the project, who was responsible for those

    documents, and provided templates to assist in generating the documents.

    Once the project managers saw that what we were doing was actually helping them,

    they were more receptive to the other changes, like quality audits, that were also

    being rolled out. We found that many of the project managers had the can-do

    attitude that focused on completing the project.

    23

  • 8/8/2019 MCOE Project Report

    24/37

    At the same time we had to deal with a layer of middle management that did not want

    to see changes made to their organizations. We found we had to spend a lot of time

    building consensus among them in order to roll out many of the more far-reaching

    changes such as implementing a budget management process.

    A management review process was created where the changes were sent to the

    managers for review and approval. However, the changes were first coordinated with

    the project managers so that they could give a positive recommendation to their

    managers. This gave the managers an input into the process changes, but with the

    understanding that their employees were supportive of the changes.

    This did not completely resolve the problem of having managers make changes that

    would return the new processes to shadows of the existing processes, but the team felt

    it reduced the frequency and severity of the complaints from managers who wanted

    things to stay the way they were.

    24

  • 8/8/2019 MCOE Project Report

    25/37

    CHANGE AND CULTURE

    Merely acknowledging that an organization needs to change rarely leads to deep and

    fundamental change. Fundamental change requires a large amount of preparation and

    work. That is why TFSs approach has taken years, not months, to implement. For

    every two steps TFS took forward, it took one step backward. It is no exaggeration to

    say that without extensive efforts to prepare the organization for change, TFSs

    initiative could easily have failed. Organizational change begins with the

    organizations culture, whether that culture is approached directly or indirectly. Some

    attributes of TFSs culture are:

    A high respect for people and relationships (very associate focused).

    A focus on improving quality of life and supporting the communities in which we

    live.

    Zero tolerance when it comes to issues of integrity.

    The pursuit of kaizen, a philosophy of continuous improvement. TFS is always

    striving to be better. This translates into placing a high value on performance andresults.

    Changing the way management and associates thought about TFSs value of

    performance required a delicate balancehonoring the parts of TFSs culture that

    would serve as the foundation for change while redefining other aspects. In essence,

    what TFS needed to do was create a culture in which leaders could:

    Hold associates and managers accountable for performance, and align rewards and

    consequences accordingly.

    Differentiate based on performance, and develop associates differently based on

    their individual needs.

    Produce strong managers who value the development of people.

    Provide regular and honest feedback to associates to help them maximize their

    performance.

    These changes may seem simple. But they fundamentally affect every aspect of the

    work experience, including leadership expectations, hiring decisions, performance

    management, compensation, talent management, succession planning, and associate

    25

  • 8/8/2019 MCOE Project Report

    26/37

    development. They require much more than simply rolling out new HR tools or

    training programs, key drivers for career advancement.

    Changing the way management and associates thought about TFSs value of

    performance required a delicate balancehonoring the parts of TFSs culture that

    would serve as the foundation for change while redefining other aspects. In essence,

    what TFS needed to do was create a culture in which leaders could

    Hold associates and managers accountable for performance, and align rewards and

    consequences accordingly.

    Differentiate based on performance, and develop associates differently based on

    their individual needs.

    Produce strong managers who value the development of people.

    Provide regular and honest feedback to associates to help them maximize their

    performance.

    The focus was on leader- ship skills rather than technical skills. The senior managers

    needed to sup-

    port and lead these changes through their daily actions and decisions. HR redefined its

    own performance expectations and capabilities and how it held itself accountable for

    performance. The changes included:

    Acquiring and developing stronger analytical, strategic, and consultative capabilities

    Reshaping HR consulting teams, and locating them geographically with the

    departments business partners

    Creating an organizational development team to infuse stronger organizational

    design and development capabilities

    Enhancing the recruitment function to respond more effectively to the need for new

    talent.

    TFS also did the unprecedented and filled some executive leadership positions with

    outside candidates. This helped introduce new skills, knowledge, and ideas into the

    organization, illustrated that the changes touched every level of the organization, and

    sent a clear message that in the future, getting ahead at TFS would be more about the

    leadership skills and knowledge necessary to move TFS forward.

    26

  • 8/8/2019 MCOE Project Report

    27/37

    These efforts to prepare TFS for change were slow, deliberate, and often difficult

    but they were essential. They validated that things were changing and that the

    organization was moving in the right direction. Many organizations miss or quickly

    pass over the importance of readying an organization for change.

    Instead they focus on introducing new programs or tools, assuming that these will

    create the change. TFS believes that leaders must own and drive change, using the

    appropriate tools. At TFS, the initial steps set the stage for change and began to create

    experiences for managers to use as anchors as TFS continued to move forward.

    27

  • 8/8/2019 MCOE Project Report

    28/37

    CORE STRATEGY

    How do you get people to make required significant changes in behavior and mind-

    set? From some perspectives, the solution is fairly clear :

    Conduct a study of competencies as they relate to business goals.

    Design and roll out a performance management system, using the

    competencies as abase for performance measurement.

    Integrate the competencies into the recruitment and compensation systems.

    Create or align the compensation process.

    Conduct coaching workshops to support more effective communication during

    performance discussions.

    The steps TFS took were very similar to these. However, TFS wanted an organic

    process that would adapt to the organization as it grew. And it wanted a specific focuson transferring accountability and ownership to the business leaders. TFS believed

    that without such a shift, the tools would just be tools. TFS firmly believed that

    leaders, not tools, make leaders.

    TFSs core leadership strategy is built on two fundamental levers : accountability and

    differential investment. In a performance-based organization, managers and associates

    much hold themselves accountable and think of themselves as owners. TFS decided to

    differentiate how it invested in associates, based on performance. Rewards and

    consequences were more strongly linked to performance and results. TFS wanted to

    tailor how it developed and rewarded associates to maximize results.

    To implement its leadership strategy, TFS needed to integrate the concepts of

    accountability and differential investment into every existing and future HR program,

    including performance management, development and succession planning,

    compensation, and recruitment.

    28

  • 8/8/2019 MCOE Project Report

    29/37

    MAPPING THE WAY

    TFS began with performance management. This decision was based on the belief that

    a performance-based organization needs to have a practical and credible assessment

    and measurement system so associates can be accurately differentiated and held

    accountable. At TFS, this program is called Maximizing Associate Performance, or

    MAP.

    It provides the foundation for all current and future HR programs. TFS also needed acommon language for describing its expectations for associates and their work. In

    2005, TFS defined core competencies by band or grade level across the organization.

    Evaluation on these competencies constitutes half of a persons overall performance

    assessment; assessment of results makes up the other half. The competencies

    described how TFS wanted managers to act. It then was necessary to create the

    conditions that would encourage them to act in the desired ways to engaged in

    coaching and development.

    The two important competencies- performance accountability and coaching and

    development were shifted to the resultssection of the managersperformance

    appraisal. This sent the message that meeting or exceeding traditional results was not

    enough and that focusing solely on these results created a short-term view for the

    organizationwhich also was not enough. In the past, managers had felt conflicted

    about which was most importantimmediate business results or development. They

    tended to focus more on these results because more weight tended to be placed there.

    Now managers were being told that developing associates was as important as results

    and that they were accountable for current performance and for investing in

    expanding capabilities to achieve long-term profit growth. Another change came in

    the way performance was managed. The focus shifted away from documenting

    performance only at the end of the performance period. This meant

    29

  • 8/8/2019 MCOE Project Report

    30/37

    Accepting that performance management is an ongoing process that occursthroughout the performance period, not just at the end

    Establishing clear expectations at the start of the performance period

    Providing honest feedback frequently and with an emphasis, when needed, on

    performance changes that could be made

    Tailoring feedback to each per- son, and providing developmental direction based

    on that persons current performance level.

    The conceptual shifts were from managing performance to maximizing performance,

    from assessment to action, from annual appraisals to ongoing feedback, and from

    compliance to commitment. The data that emerge from performance management are

    essential to how associates are rewarded and developed. There are many opportunities

    in this modal to build effective leadership development processes.

    Concurrent with the establishment of MAP, some changes were made to thecompensation programs. This wasto reinforce differentiation based onperformance.

    More focus was placedon rewarding higher-performing associates, to ensure they felt

    valued and recognized. MAP performance ratings were also used as the primary

    driver of compensation programs, to further reinforce the link between pay and

    performance. Additionally, TFS expanded its talent review process, using the new

    competencies and focusing developmental and promotional conversations on

    leadership capabilities. The CEO also initiated leadership strategy conferences atwhich the elements of strong leadership were reinforced. Borst led many of the

    discussions andused these conferences as an opportunity to broaden the perspective

    ofmembers of his leadership team andto clarify his expectations of them asleaders.

    These additional steps served to drive home the fact that TFS was following up its

    words with actions communication was developed to keep associates up to date on

    MAP activities and to ensure that MAP stays at the forefront of managers minds. TheCEO played a significant role, using oral and written channels to reinforce his support

    30

  • 8/8/2019 MCOE Project Report

    31/37

    by communicating that MAP is a top priority. Managers incorporated messages about

    MAP at the departmental level via meetings, town halls, and other forums.

    As a result of TFSs efforts, performance management and leadership development

    planning are now an integral part of the organizations annual planning calendar. But

    the work is not yet done. Measurement and accountability systems continue to be

    built, the reward system is being modified, and the leadership development strategy is

    extending downward into the organization as the succession process develops. Talent

    reviews are being used to identify those who exhibit leadership abilities as well as

    those with high potential to do so. Some people at TFS are adapting to performance

    management and MAP more easily than others.

    In keeping with the Toyota culture, the HR team will ensure that the performance

    management process is accomplishing what it was intended to do. HR will

    incorporate changes that make sense for the business and ensure that the new system

    remains practical for facilitating good coaching and development discussion. Its too

    soon to tell whether TFSs leadership strategy will be successful. Success will largely

    depend on how well these concepts continue to be embraced and owned by the

    business leaders.

    31

  • 8/8/2019 MCOE Project Report

    32/37

    LEASON LEARNED APPROACH

    TFSs leadership effort began slowly and progressed incrementally, using a lessons-

    learned approach. The focus was on building understanding and creating a shift in

    mind-set. Three primary elements figured in the design and implementation of the

    effort: strategy (where the organization is going), culture(what the organization

    values and how it behaves), and readiness(leaders willingness to embrace and leadthese changes). Working to create an accountable organization means rethinking how

    business decisions are made to ensure that the elements of TFSs organizational

    design are aligned to support an accountable culture. Specifically, accountability

    levels should be consistent with levels of control and influence. Leaders will resist

    being held accountable for areas over which they have little or no control. This will be

    an important area for TFS to focus on if it is to sustain an account- able culture.

    As a result of TFSs efforts, performance management and leadership development

    planning are now an integral part of the organizations annual planning calendar. But

    the work is not yet done. Measurement and accountability systems continue to be

    built, the reward system is being modified, and the leadership development strategy is

    extending downward into the organization as the succession process develops. Talent

    reviews are being used to identify those who exhibit leadership abilities as well as

    those with high potential to do so.

    32

  • 8/8/2019 MCOE Project Report

    33/37

    LIMITATION

    Limitation of our project are as follows :

    Study is based on secondary data, since TFS Change Mangaement that we

    have studied are based on TFS situated in USA.

    There is no use of statistical data, hence conclusion is more subjective (which

    is not generally more reliable and accurate).

    Many changes have occurred time to time in TFS but we have only studied

    two changes.

    33

  • 8/8/2019 MCOE Project Report

    34/37

    CONCLUSION

    Once the need to have a PMO became obvious, the most difficult task of doing it was

    to implement it into an organization where many of the employees were not initially

    supportive of the large changes that were being made. They had seen PMOs

    developed before and cancelled. While the implementation effort is still in its early

    stages, the initial successes, while small, have changed many peoples minds about

    how beneficial the PMO can be.

    The stakeholders were coordinated with during the design effort and the PMO was

    designed to satisfy the organizations major project management issues. By

    identifying where the most pain was and quickly fixing some of those, we obtained

    support from the project managers who began to see that this could be highly

    beneficial to themselves and not just another set of changes.

    The full implementation is expected to be a three-year effort that began in late

    summer of 2001. At the present time it appears to be on track. It has been a somewhatfrustrating experience for the development team who expected to being implementing

    the PMO as soon as it was designed and approved by upper management. Instead they

    had to learn how to deal with a recalcitrant organization who changed very slowly and

    only with a great deal of coordination and consensus building. Some people at TFS

    are adapting to performance management and MAP more easily than others. In

    keeping with the Toyota culture, the HR team will use the kaizenphilosophy to ensure

    that the performance management process is accomplishing what it was intended to

    do. HR will incorporate changes that make sense for the business and ensure that the

    new system remains practical for facilitating good coaching and development

    discussions.

    Its too soon to tell whether TFSs leadership strategy will be successful. Success will

    largely depend on how well these concepts continue to be embraced and owned by the

    business leaders. Its too soon to tell whether TFSs leadership strategy will be

    successful. Success will largely depend on how well these concepts continue to be

    34

  • 8/8/2019 MCOE Project Report

    35/37

    embraced and owned by the business leaders.

    REFERENCES

    Block, T.R., 1999, The Seven Secrets of a Successful Project Office. PM

    Network, April, 1999: 43-48.

    Miller, J., 1998, Project Office One of the Fastest Growing Segments in

    Information Systems, Proceedings of the 29th Annual Project Management

    Institute 1998 Seminars and Symposium, published by The ProjectManagement Institut.e

    STANDISH, 1995, The CHAOS Project Management Research Study,

    published by The Standish Group.

    35

  • 8/8/2019 MCOE Project Report

    36/37

    ANNEXURE

    SUBSCRIBE TOLEADERSHIP IN ACTIONNOW!

    This is an article that was featured in Leadership in Action, a periodical from theCenter for Creative Leadership, published in association with Jossey-Bass.

    We are confident that you will findLeadership in Action to be an excellent value andan indispensable tool for improving your leadership and your organization. By unitingthe insights of top scholars and the experience of working executives, each issue

    provides the best strategies for confronting such critical issues as leading a diverseworkforce, maximizing the effectiveness of teamwork, stimulating creativity in the

    workforce, and more.

    You can subscribe by printing and mailing this form to Jossey-Bass, 989 MarketStreet, San Francisco, CA 94103-1741. For fastest service, call 888/378-2537 (toll-free) or 415/433-1767; fax to 888/481-2665 (toll-free) or 415/951-8553; or e-mail to

    [email protected].

    Thank you!

    Yes! I want to subscribe toLeadership in Action now.

    For a one-year (six issues) subscription:INDIVIDUAL: U.S./Canada/Mexico $189 Outside N. America $225INSTITUTION: U.S. $325 Canada/Mexico $385 Outside N. America $436

    36

  • 8/8/2019 MCOE Project Report

    37/37

    Payment enclosed (New York and Canadian residents, please add sales tax). Makecheck payable to Jossey-Bass.

    Bill my organization (purchase order and phone number required)

    Purchase Order # ______________________________________________________Phone _______________________________________________________________

    Charge my credit card. Visa MasterCard American Express Discover (circle one)

    Card # _______________________________________________________________

    Exp. Date ____________________________________________________________

    Signature _____________________________________________________________

    Phone _______________________________________________________________

    Name________________________________________________________________

    Address______________________________________________________________

    City/State/ZIP_________________________________________________________