MEANS OFFICE BUILDINGPRE-CONSTRUCTION & CONTRACTING SERVICES PROPOSAL
Eddie Aquino, Jimmy Fu, Alvin Sarmiento
Spring 2011
Civil Engineering 239
PROJECT TEAM
Eddie AQUINO PROJECT MANAGER/3D MODELLER
Jimmy FU PROJECT ENGINEER/
CONSTRUCTION SITE LOGISTICS
Alvin SARMIENTO PROJECT ESTIMATOR/SCHEDULER
2
PROJECT REQUIREMENTS Three-story office building w/ underground
garage Concrete waffle slab Spread footings Structural Steel framing with steel deck Penthouse structure CMU Steel joist roof Construction budget 10.5 million – 12 million
PROJECT LOCATION
COMPONENT StreetLooking Southeast
COMPONENT StreetLooking Southwest
PROJECT LOCATION
2.60 Acres IP (PD) URBAN Freeways
3D MODEL
PDF Simulation
Cost Estimates
Timberline Sage Ranked most used estimating software by
ENR
AutoCAD Timberline
Primavera
MS Project
Cost Estimates
Features CSI MasterFormat Provides detailed labor, material, and
equipment cost estimates Provides total cost/unit and total amount
per item
Cost Estimates
Problems Encountered Can not access Division 10-16
Mechanical and Electrical Systems
Cost Estimates
Problems Encountered Final cost estimates from Timberline does
not match cost estimates given in excel sheet
Schedule
MS Project Timeline: January 27, 2011 – January 6,
2012 RS Means 2002 and Golden Bear
Construction Inc. RS Means Office Building Schedule
Superstructure
GarageMeasurement
Daily Output based on RS Means production
Approximate Completion
Structural Steel Columns/Beams 114 Tons 14.4 Tons 8 days
1st FloorMeasurement
Daily Output based on RS Means production
Approximate Completion
Structural Steel Columns/Beams 114 Tons 14.4 Tons 8 days
Metal Deck 18,900 SF 3,500 SF 6 daysConcrete Fill Over Metal Deck 18,900 SF 8,640 SF 3 daysWaffle Slab 18,900 SF 2,380 SF 8 daysFire Proofing 18,900 SF 3,000 SF 7 days
Schedule
Schedule Accuracy of schedule and duration of project
Each activity has a predecessor At any time during schedule, one or more
activities can occur Advantages
Simple to use Disadvantages
Activities may not have any predecessor or successor
CONSTRUCTION SITE
CONSTRUCTION EQUIPMENT
ACTION MOBILE INDUSTRYMODEL 1250 (46’x12’)
LINDEN COMANSALC 500 Series