Measure B Citizens’ Bond Oversight Committee
Meeting Agenda October 30, 2017, 4:30 – 6:00 p.m.
Indian Valley Campus ESCOM Center, Building 10
1800 Ignacio Blvd., Novato, CA 94949
1. Call to Order – Chair, Ross Millerick
2. Introduction of New Member Information
3. Approval of Agenda Action
4. Approval of the Meeting Minutes for August 22, 2017 Action
5. Public Comment Information
6. Communications Received by Committee Members Information
7. Annual Report Preparations ‐ Mike Chegini Information
8. Program/Project Update Report ‐ Casey Michaelis & Tim McBrian Information
9. Financial and Compliance Items ‐ Ann Kennedy a. Program Financial Reports for fiscal year ending 6/30/2017 Action b. Bond List Revision(s) Information c. District positions paid for by the Bond Information d. Questions sent to Bond Counsel since the last meeting Information
10. Confirmation of Next Meeting Date/Time: Tuesday, January 30, 2018 Information
11. Topics for next meeting: Information
Financial and Performance Audits Annual Report Draft for Committee Review/Approval Program/Project Update Report
Program Financial Reports for the period end 9/30/2017
12. Adjournment
2
Future Meeting Dates: Tuesday, January 30, 2018 4:30 – 6 p.m. Kentfield Campus, Academic Center, Room 217 Tuesday, March 27, 2018 4:30 – 6 p.m. Indian Valley Campus, Building 10, Room 140 Tuesday, June 26, 2018 4:30 – 6 p.m. Kentfield Campus, Academic Center, Room 217
Committee Membership: Requirement: Minimum 7 Member Committee*
*Required Representation (# ) Current Members
Board Approval Date
Term 1 End Date*
Community‐At‐Large (2) Margaret Pozzo DeSomma** 12/6/16 12/6/17
Jeff Gunderson 3/14/17 3/14/18
Senior Citizens’ Org. (1) Eric D. Sitzenstatter, Jr. 5/16/17 5/16/18
Tax Payers’ Association (1) Paul Premo 12/6/16 12/6/17
Business Community (1) Nancy McCarthy 4/18/17 4/18/18
Support Organization (1) Ross Millerick* 12/6/16 12/6/17
Student (1) Janelle LaChaux 10/17/17 10/17/18
* Elected as the Chair of the Committee, July 17, 2017
** Elected as the Vice Chair of the Committee, July 17, 2017
MARINCOMMUNITYCOLLEGEDISTRICTCITIZENS’BONDOVERSIGHTCOMMITTEEMEETING
AUGUST22,2017
LOCATION:KENTFIELDCAMPUS
ACADEMICCENTER,ROOM217835COLLEGEAVE.
KENTFIELD,CA94904
CITIZENS’BONDOVERSIGHTCOMMITTEE,MEMBERSPRESENTRossMillerick CBOCChairandRepresentative,Support
OrganizationJeffGunderson Representative,AtLargeNancyMcCarthy Representative,BusinessOrganizationPaulPremo Representative,TaxpayersAssociationEricD.Sitzenstatter,Jr. Representative,SeniorCitizenOrganization
CITIZENS’BONDOVERSIGHTCOMMITTEE,MEMBERSABSENTMargaretDeSomma Representative,AtLargeVACANT Representative,StudentOrganization
MARINCOMMUNITYCOLLEGEDISTRICT,STAFFPRESENTGregNelson VicePresidentofFinanceandCollege
OperationsKatyBauer ExecutiveAssistant
GUESTSAnnKennedy AKennedyGroup,FinancialManagerTimMcBrian GilbaneBuildingCompany,ProgramManagerCaseyMichaelis GilbaneBuildingCompany,PrincipalInChargeMaryRoss MemberofthePublic
I. CALLTOORDERTheCitizens’BondOversightCommittee(CBOC)meetingwascalledtoorderbyChair,RossMillerick,atapproximately4:32PM.CommitteeChair,RossMillerick,CommitteeMembers,JeffGundersonandPaulPremowerepresent.CommitteeMember,NancyMcCarthy,arrivedatapproximately4:42PMestablishingaquorum.CommitteeMember,EricD.Sitzenstatter,Jr.,arrivedatapproximately4:44PM.CommitteeMember,MargaretDeSomma,wasabsent.II. APPROVALOFAGENDACommitteeMember,PaulPremo,madeamotiontoapprovetheagendawithnochanges.CommitteeMember,JeffGunderson,secondedthemotion.ThemotionwasunanimouslycarriedbytheCommitteeMemberspresent.III. APPROVALOFMEETINGMINUTESFROMJULY17,2017MEETINGCommitteeMember,PaulPremo,madeamotiontoapprovetheJuly17,2017minuteswithnochanges.CommitteeMember,JeffGunderson,secondedthemotion.ThemotionwasunanimouslycarriedbytheCommitteeMemberspresent.VicePresident,GregNelson,proposedtosavetheaudiorecordingofthemeetingminutesasapublicrecord.ThemotionwasapprovedbyCommitteeMember,PaulPremo.ThemotionwassecondedbyCommitteeMember,JeffGunderson.ThemotionwasunanimouslycarriedbytheCommitteeMemberspresent.
Minutes–MarinCommunityCollegeDistrictCitizens’BondOversightCommittee(CBOC)August22,2017Page2of2
IV. PUBLICCOMMENT
Nocommunicationfromthepublic.V. COMMUNICATIONSRECEIVEDBYCOMMITTEEMEMBERS
NocommunicationreceivedbyCommitteeMembers.VI. MEASUREB:PROGRAM/PROJECTUPDATE
VicePresident,GregNelson,gaveapresentationthatincludedFacilitiesMasterPlanCampusMaps,ExecutiveLevelSummaryslidesshowingprojectsummaryandstatusforeachprojectfundedbyMeasureB,aswellasmoredetailedslidesshowingthefollowingprojects:PomoClusterProgrammingReview(IndianValleyCampus),Maintenance&OperationsBuildingandDistrictWarehouseSchematicDesignReview(KentfieldCampus),LearningResourcesCenterandStudentServices(KentfieldCampus)ProjectInitiationaswellastheMasterProjectListReport.Severalquestionswereaskedincludingaboutthesolarproject(non‐bond),theIVCamphitheater,thePomoClusterrenovation,andDesignBuildvsDesignBidBuildwithregardtotheLearningResourcesCenterandStudentServicesbuildings.VicePresident,GregNelson,answeredthequestionsfromcommitteemembers.ThecommitteealsowantedtoknowhowtolookupthestudiesonlinefortheCorteMaderacreekwideningprojectandVicePresident,GregNelson,answeredthatMarinCountyFloodControlisleadingtheproject.
VII. FUTUREMEETINGSCHEDULE:SUGGESTEDDATES/TIMES
Theproposedmeetingdates/times/locationswasreviewed.CommitteeMembers,NancyMcCarthyandJeffGundersoncan’tattendthemeetingOctober3,2017.ItwasproposedtomovethemeetingtoMonday,October30,2017.ItwasdecidedtomovetheDecember11,2017meetingtoJanuary2018becausetheBoardofTrusteesDecembermeetingisthefirstweekofDecemberandtheauditwillnotbereadyfordiscussionbycommitteemembersuntilafteritisapprovedbytheBoard.Becausethe2018meetingsdatesaren’tfinalizeduntillate2017/early2018,Tuesday,January30,2018waschosen.TheCommitteeagreedtotentativelyapprovetheMarch27,2018andJune26,2018datesandwillreviseinafuturemeetingifnecessary.Themeetingtimeremains4:30‐6:00PMandthelocationswerenotchangedfromwhatwaspreviouslyagreedtowhichistorotatethemeetingsbetweenthetwocampuseswiththeOctober30,2017meetingtakingplaceatIndianValleyCampus.VIII. TOPICSFORNEXTMEETINGTheCommitteereviewedthetopicsforthenextmeeting.InadditiontothetopicsnotedontheAgenda,theCommitteewouldliketohaveahyperlinktooldMeasureCwebsiteaddedtotheMeasureBwebsite.CommitteeMember,PaulPremo,askedifthecommitteecouldgetmoredetailsabouttheAnnualReportpreparations.FinancialManager,AnnKennedyansweredthatCommunicationsManager,MikeChegini,wouldattendtheOctobermeetingandbringdraftsandsamples,includingaschedulewithdeadlinesforwhenitemsaredue.ThegoalwouldbetohaveeverythingfinalizedattheJanuary30,2018meetingandpresenttheReportattheFebruary2018BoardofTrusteesMeeting.IX. ADJOURNMENTThemeetingwasadjournedatapproximately5:45PM.
CBOC 2016-2017 Annual Report Schedule
10/30/17: Select volunteers for working group.
11/21/17: 1st draft of annual report sent out.
12/1/17: Review & feedback due.
12/8/17: 2nd draft of annual report sent out.
12/15/17: Review & feedback due.
1/19/18: Final annual report draft sent out.
1/30/18: Annual report draft presentation at CBOC meeting.
2/2/18: Incorporate any edits from CBOC meeting, prepare for final publishing.
Feb-March 2018: Present annual report at Board meeting and publish online.
1
MEASURE BPROGRAM UPDAT E
CITIZENS’ BOND OVERSIGHT COMMITTEE: OCTOBER 30 , 2017
Projects in Design
I21-35617 Organic Farm/Garden Enhancements – Classroom, kitchen andrestrooms
I26-35610 Jonas Center and Building 18
I51-35620 New Miwok Center – Aquatic and Wellness Center
K07-35721 Maintenance & Operations Building and District Warehouse
K11-35715 Athletic Synthetic Turf Fields and Restroom/Storage Facilities –Phase 1: Baseball, restroom plaza
2
Projects under Construction
I25-35612 ADA Barrier Removal/Site Improvements – Organic Farm ParkingLot
K11-35715 Athletic Synthetic Turf Fields and Restroom/Storage Facilities –Phase 2: Soccer, volleyball and tennis courts
I50-35613 Admin Cluster – Generator
I26-35610 Jonas Center and Building 18 – Building 18 Roof replacement
Projects out or recently bid
I49-35618 Pomo Cluster – Phase 1: Exterior improvements
I50-35613 Admin Cluster – Building 11
4
K03-35718: Performing Arts
Project Summary:Small capital repairs.
Status: Floor replacement design complete Re-bid in January 2018, construction to begin
after Memorial Day 2018
K07-35721: Maintenance & Operations Building and District Warehouse
Project Summary:New facility for M&O to replace existing structures, from both campuses, that are in disrepair; Storage facility/metal structure for District storage for surplus property, program storage, etc.; The following programs are also included: Police, Reprographics, Graphic Design, Shipping & Receiving.
Status:
90% DD under review.
Soliciting comments and product information for M&Oequipment, police department lockers and storage,reprographics equipment layout and IT equipment.
Update project budget review current costs,design/constructability review to begin.
5
K11-35715: Athletic Synthetic Turf Fields and Restroom/Storage Facilities
Project Summary:Replace existing natural grass field with synthetic turf baseball field, restroom facility, modular equipment storage building, score board and perimeter fencing.
Status: Baseball field structures and ancillary buildings -
Plans and specifications submittal to DSA onSeptember 8, 2017.
I21-35617: Organic Farm/Garden Enhancements
Project Summary:New DSA pre-approved buildings for classroom and demonstrations for the organic farm & associated programs.
Status: Design with pre-engineered modular buildings Adjustment to farm lot line boundary is underway. New
fence project to follow. Site work includes ADA pathway access, irrigation and
drainage improvements
6
I26-35610: Jonas Center and Building 18
Project Summary:Multi-purpose facility to seat at least 275-300 for seated dinner, commercial kitchen, stage, and Jonas Center staging, etc.
Status:
Bridging Documents are under development
Anticipating RFQ for Design Build award 1stquarter 2018
Building 18 New Roof project began 10/23/17
I49-35618: Pomo Cluster
Project Summary:Buildings 1-7, Envelope improvements, windows replacement, mechanical repairs, flooring, painting, small capital repairs.
Status:
Phase I (Exterior & Windows) Bids open 11/2/17
Anticipate Phase II Construction Documents (InteriorRenovations) for review November 2017
7
CONSTRUCTION PROGRESS
K11-35715: Athletic Facilities Soccer, Volleyball, Futsal
Project Summary:Replace existing natural grass field with synthetic turf fields with associated markings for various sports, restroom facility, addition to existing gym complex for storage or equipment, score boards, tennis courts, multi-purpose turf in PE complex.
Status:
Soccer, futsal, volleyball and tennis courts areunder construction
BOT approved 10/17/17 a recommendation toaward base bid and Alternate #1 in the amount of$3,767,000- to BHM Construction Inc.
8
I57-35623: Demolition Project
Project Summary:Demolition of existing Corp Yard Facility and Buildings 11, 18, 19, 20, 22, 23, and other facilities as needed.
Status:
Abatement is completed in Buildings: 11, 18,19, 20, 22 and 23
Building 22 & 23 demolished as of 10/11/17
Building 18 has been demolished (interior)
Demolition of Buildings 19 & 20 began theweek of 10/11/17
I21-35617: Organic Farm/Garden Enhancements
Project Summary:New DSA pre-approved buildings for classroom and demonstrations for the organic farm & associated programs.
Status:
Building #22 Corp. Yard has been demolished inpreparation for work in parking lot improvements
Recommendation to BOT on 10/17/17 for award toWildcat Construction
Anticipated start date 10/30/17 on parking lotimprovements
A&E, DSA, Oversight & Other $3,119,658 $0 $0 $75,587,688$78,707,346Construction & Contingency $1,681,698 $0 $0 $161,755,656$163,437,354Furniture & Equipment $720,696 $0 $0 $27,134,604$27,855,300Unallocated Interest $0 $0 $0 $250,755$250,755
Totals: $270,250,755 $5,522,052 $0 $0 $264,728,703
Remaining Bond Funding (98%)Total Bond Expenses (2%)
A&E, DSA, Oversight & Other (27%)Construction & Contingency (62%)Furniture & Equipment (11%)
Budget vs Expenses (Bond Only) Budget Categories Chart
Whole Program Report
Funding Sources (Budget)
Marin Community College District
Measure B Bond ProgramReporting Period: Inception through 6/30/2017 Draft Pending Audit
Bond Authorization
Bond Allocated Interest Earned (Tax-exempt)
Unallocated Bond Interest Earned (Tax-exempt)
Total Bond:State
Other
Cost Status
Budget Group Total Budget
Actual Expenses To Date
Remaining BalanceBond State Other
$265,000,000
$0
$153,932
$0
$5,000,000
Total Bond + Other Funding: $270,250,755
$265,250,755
98.06 %
0.00 %
0.06 %
98.15 %
100.00 %
0.00 %
1.85 %
0.04 %
0.00 %
$96,823
$0
Unallocated Bond Interest Earned (Taxable)
Bond Allocated Interest Earned (Taxable)
Bond and Bond Authorization: Measure BInterest Earned: Interest Earnings Allocated to ProjectsTotal Interest Earnings (Investment Income): Interest Earned + Unallocated Interest EarnedUnallocated Interest Earned: Interest Earnings not yet allocated to specific projectsState: TBDOther: Contribution to Project from "other" source (non-State nor Bond)Expenses in the "Actual Expenses to Date" columns: Paid and Accrued expenses through the reporting period end date.Rounding factors may apply.
Page 1 of 110/20/2017 12:52:18 PM | COM-005
Notes:
Kentfield Campus Project ListBoard Approved
Child Study CenterK01-35717 $270,000 $0 $270,000 1/2/2020 5/14/2024$0
PE Complex/Pool RenovationsK02-35713 $2,427,000 $153,465 $2,273,535 1/3/2017 8/11/2020$153,465
Performing ArtsK03-35718 $520,000 $12,261 $507,739 5/1/2017 1/14/2020$12,261
Fine ArtsK04-35719 $670,000 $0 $670,000 1/2/2018 2/12/2020$0
Corte Madera Creek MitigationK05-35716 $1,000,000 $5,814 $994,186 3/1/2018 7/19/2022$5,814
Science Math & NursingK06-35720 $1,360,000 $1,854 $1,358,146 1/2/2020 5/14/2024$1,854
Village Square ReplacementK08-35722 $3,600,000 $970 $3,599,030 12/1/2021 4/14/2026$970
Site ImprovementsK09-35714 $4,700,000 $268,106 $4,431,894 8/1/2017 1/18/2022$116,017
Academic Center ExpansionK10-35723 $7,550,000 $0 $7,550,000 8/1/2018 12/6/2022$0
Parking StructureK12-35724 $9,000,000 $0 $9,000,000 1/4/2021 3/11/2026$0
Fusselman HallK14-35711 $6,550,000 $0 $6,550,000 8/1/2017 1/18/2022$0
Total Board Approved $37,647,000 $442,470 $37,204,530$290,382
ProcurementAthletic Synthetic Turf Fields andRestroom/Storage Facilities
K11-35715 $9,450,000 $236,514 $9,213,486 1/3/2017 7/20/2018$236,514
Procurement Total $9,450,000 $236,514 $9,213,486$236,514
DesignMaintenance & Operations Building andDistrict Warehouse
K07-35721 $8,430,000 $634,216 $7,795,784 1/3/2017 5/24/2019$634,216
Student ServicesK13-35710 $51,380,000 $112,608 $51,267,392 9/1/2017 9/7/2023$17,920
Learning Resources CenterK15-35712 $32,300,000 $271,940 $32,028,060 9/1/2017 9/7/2023$189,560
Total Design $92,110,000 $1,018,764 $91,091,236$841,696
ConstructionDemolition of Kent Avenue MaintenanceFacilities
K18-35725 $700,000 $0 $700,000 1/3/2017 12/31/2018$0
Total Construction $700,000 $0 $700,000$0
Campus Contingency - Kentfield CampusK99-35799 $6,150,000 $0 $6,150,000 1/3/2023 12/31/2027$0
Total Kentfield Campus Budget $146,057,000 $1,697,749 $144,359,251$1,368,592
Campus Contingency / (Estimate at Completion - Expenses to Date) 3.91%
Indian Valley Campus Project ListBoard Approved
Building 27 (Dental, EMT, Court Reporting,Library)
I47-35619 $1,350,000 $0 $1,350,000 1/2/2019 5/16/2023$0
Building 12I56-35622 $1,500,000 $0 $1,500,000 10/2/2017 12/31/2020$0
Building 17I58-35624 $1,250,000 $6,839 $1,243,161 1/2/2018 5/17/2022$6,839
Total Board Approved $4,100,000 $6,839 $4,093,161$6,839
DesignOrganic Farm/Garden EnhancementsI21-35617 $3,030,000 $136,427 $2,893,573 1/3/2017 8/28/2019$125,327
Jonas Center and Building 18I26-35610 $11,400,000 $240,111 $11,159,889 1/3/2017 6/24/2021$191,074
Pomo ClusterI49-35618 $10,559,000 $163,410 $10,395,590 1/3/2017 11/30/2019$163,410
New Miwok CenterI51-35620 $24,157,000 $127,361 $24,029,639 4/25/2017 2/9/2022$127,361
Outdoor AmphitheaterI55-35616 $1,000,000 $66,081 $933,919 1/3/2017 11/5/2019$66,081
Total Design $50,146,000 $733,390 $49,412,610$673,253
Project Summary Report
ProjectNumber
Marin Community College District
Measure B Bond ProgramReporting Period: Inception through 6/30/2017 Draft Pending Audit
BudgetRemaining
Start Date
End Date
Bond Exp.To Date
BondBudget
Cost Status
Sched Status
Qtr Bond ExpenseProject Name
Page 1 of 3
See last page for definitions and notes
10/20/2017 12:54:08 PM | COM-001
Indian Valley Campus Project ListConstruction
ADA Barrier Removal/Site ImprovementsI25-35612 $8,837,500 $941,930 $7,895,570 1/2/2018 2/15/2022$592,539
Admin ClusterI50-35613 $5,662,000 $303,481 $5,358,519 1/3/2017 7/6/2020$172,882
Demolition ProjectI57-35623 $800,000 $577,995 $222,005 1/3/2017 12/31/2018$577,995
Total Construction $15,299,500 $1,823,405 $13,476,095$1,343,416
ConsolidatedMaintenance & Operations BuildingI22-35614 $0 $0 $0 1/1/1900 1/1/1900($105,846)
StorageI23-35615 $0 $0 $0 1/1/1900 1/1/1900$0
New Aquatics CenterI24-35611 $0 $0 $0 1/1/1900 1/1/1900($28,235)
Building 18 (Ohlone Cluster)I53 $0 $0 $0 1/1/1900 1/1/1900$0
Building 21 (Old Pool Building)I54 $0 $0 $0 1/1/1900 1/1/1900$0
Total Consolidated $0 $0 $0($134,081)
CancelledIVC Tree Study and Removal ProjectI52 $0 $0 $0 1/1/1900 1/1/1900$0
Total Cancelled $0 $0 $0$0
Campus Contingency - Indian ValleyCampus
I99-35699 $2,627,500 $0 $2,627,500 1/3/2023 12/31/2027$0
Total Indian Valley Campus Budget $72,173,000 $2,563,634 $69,609,366$1,889,427
Campus Contingency / (Estimate at Completion - Expenses to Date) 3.64%
District and District-Wide Project ListBoard Approved
Environmental Impact ReportD53-35111 $895,000 $23,803 $871,197 1/1/2017 12/31/2024$23,803
Information TechnologyD54-35112 $10,725,000 $104,782 $10,620,218 1/3/2017 12/31/2027$104,782
Instructional EquipmentD55-35113 $17,875,000 $39,458 $17,835,542 8/1/2017 8/1/2028$39,458
Campus SecurityD59-35110 $1,975,000 $286,084 $1,688,916 1/3/2017 5/11/2021$97,201
Total Board Approved $31,470,000 $454,127 $31,015,873$265,245
District Wide/Program ContingencyD99-35599 $8,000,000 $0 $8,000,000 1/3/2023 12/31/2027$0
Total District and District-wide Budget $39,470,000 $454,127 $39,015,873$265,245
District Wide/Program Contingency / (Estimate at Completion - Expenses to Date) 16.73%
Uncategorized ProjectsProgram Management, District StaffD98-35510 $7,300,000 $806,542 $6,493,458 10/2/2017 12/31/2027$23,946
Total Uncategorized Projects $7,300,000 $806,542 $6,493,458$23,946
Unallocated Interest Earnings $250,755 $0 $250,755 1/1/1900 1/1/1900$0
Measure B Project List Subtotal $265,250,755 $5,522,052 $259,728,703$3,547,211
Project Summary Report
ProjectNumber
Marin Community College District
Measure B Bond ProgramReporting Period: Inception through 6/30/2017
BudgetRemaining
Start Date
End Date
Bond Exp.To Date
BondBudget
Cost Status
Sched Status
Qtr Bond ExpenseProject Name
Page 2 of 3
See last page for definitions and notes
10/20/2017 12:54:08 PM | COM-001
Draft Pending Audit
Measure B Bond Program Total: $265,250,755 $5,522,052 $259,728,703$3,547,211
Projects consist of District wide project administration and other operating expenses.Represents paid and accrued expenses through the reporting period end date.Bond Expenses To Date:
When project is available for intended use.End Date:Start Date:
Report Notes & Definitions
Scheduled start date or first expenditure, whichever comes first.
* Uncategorized:
Project Status Guidelines
Ok: Project has normal range of issues.Cost (Contingency):Schedule Large Capital Projects (Required Occupancy Date - Forecast Completion Date):Schedule Other Projects (Required Occupancy Date - Forecast Completion Date):
Contingency > 5% of Budget Remaining> 2 Months Schedule Contingency
> 1 Months Schedule Contingency
1
2
2
2
2
1
~ 1 Month Schedule Contingency> 1 and < 2 Months Schedule Contingency
Contingency < 5% and > 3% Budget Remaining
Schedule Other Projects (Required Occupancy Date - Forecast Completion Date):Schedule Large Capital Projects (Required Occupancy Date - Forecast Completion Date):Cost (Contingency):
Project has significant issue(s), however, project team has a solution and/or options.Caution:
Problem: Project has significant issue(s), however, project team has a solution and/or options.
Cost (Contingency):Schedule Large Capital Projects (Required Occupancy Date - Forecast Completion Date):Schedule Other Projects (Required Occupancy Date - Forecast Completion Date):
Contingency < 2% of Budget Remaining
< 1 Month Schedule Contingency
< 2 Weeks Schedule Contingency
1
2
2
Budget Remaining =1 Total Budget – Cost to Date – Encumbered
Forecast Completion Date =2 Project is ready to be occupied for its intended purpose (Work is usably complete including equipment installation and outfitting. Some punch list items may remain and financial closeout may still be pending).
Problem Project Details
X
N/A
Projects will not be listed in the "Complete" phase until they are financially complete.
Rounding factors may apply.
Project Summary Report Marin Community College District
Measure B Bond ProgramReporting Period: Inception through 6/30/2017
Page 3 of 3
See last page for definitions and notes
10/20/2017 12:54:08 PM | COM-001
Draft Pending Audit
Superintendent / President
VP Finance / College Operations
Capital Projects & Operations (Vacant)
Director of Facilities Planning, Operations &
Maintenance
Asst. Director of Maintenance &
Operations
Administrative Assistant
Director of Fiscal Services
Bond Accountant(Vacant)
Purchasing Buyer (Bond)
Accounts Specialist (Bond)
Keygent LLCAnn Kennedy –
A Kennedy Group
David Casnocha – Stradling Law
FirmPiper Jaffrey
Executive Asst I
Bond Compliance & Finance Team
PM/CM Company
Bond Outreach
/ PR
Daily Bond Operations
District positions currently funded by the bond
Positions currently existing
Consultants/Experts for selling bonds on market and compliance expertise
Contract vendor for Bond Management