Upload
others
View
34
Download
10
Embed Size (px)
Citation preview
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
TWENTY FOURTH ANNUAL
WILLEM C. VIS INTERNATIONAL COMMERCIAL ARBITRATION MOOT
7 APRIL TO 13 APRIL 2017
MEMORANDUM FOR RESPONDENT
LUDWIG-MAXIMILIANS-UNIVERSITÄT MÜNCHEN
On Behalf of:
SantosD KG
77 Avenida O Rei
Cafucopa
Mediterraneo
RESPONDENT
Against:
Wright Ltd
232 Garrincha Street
Oceanside
Equatoriana
CLAIMANT
COUNSEL:
Antonio Aufiero ∙ Dina Kagan ∙ Katharina Lillich ∙
Mareike Neumayer ∙ Tobias Targosz ∙ Miriam Trotter
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
I
TABLE OF CONTENTS
INDEX OF AUTHORITIES ...................................................................................................... IV
INDEX OF CASES ............................................................................................................. XVII
INDEX OF ARBITRAL AWARDS ......................................................................................... XXII
INDEX OF LEGAL SOURCES .............................................................................................. XXV
LIST OF ABBREVIATIONS ................................................................................................ XXVI
STATEMENT OF FACTS ........................................................................................................... 1
SUMMARY OF ARGUMENTS ..................................................................................................... 3
ARGUMENT ............................................................................................................................ 4
I. THE TRIBUNAL SHOULD GRANT RESPONDENT SECURITY FOR ITS COSTS .................... 4
A. The Tribunal Has the Power to Order Security for Costs ...................................... 4
1. Neither the Terms of Reference nor the Rules restrict the Tribunal’s power to order
security for costs ........................................................................................................................... 4
(a) The Terms of Reference do not exclude the Tribunal’s power to order security
for costs ................................................................................................................................. 5
(b) A request for security for costs does not unlawfully amend the Terms of
Reference ............................................................................................................................... 5
(i) The restrictive effect of Art. 4.21 of the Rules does not extend to security
for costs ......................................................................................................................... 5
(ii) Even if the restrictive effect of Art. 4.21 of the Rules extended to security
for costs, the Tribunal would still have the power to order security for costs ... 6
2. Initiating a new arbitral proceeding to obtain security for costs would undermine
the latter’s nature .......................................................................................................................... 7
B. The Tribunal Should Exercise Its Power to Order Security for Costs ................... 7
1. RESPONDENT is in danger of suffering irreparable harm ............................................... 8
(a) CLAIMANT’s incapacity to comply with an award is evidenced by its balance
sheets ...................................................................................................................................... 8
(b) CLAIMANT’s non-compliance with a previous award further indicates that
RESPONDENT faces the risk of being deprived of its award .......................................... 9
(c) Seeking third party funding implies that CLAIMANT is impecunious ................. 10
2. RESPONDENT is not prevented from relying on CLAIMANT’s poor financial situation10
3. RESPONDENT’s request is urgent ..................................................................................... 11
4. RESPONDENT met its burden of proof ........................................................................... 11
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
II
5. An order for security for costs is just in the present circumstances ........................... 12
II. THE CLAIMS WERE SUBMITTED OUT OF TIME AND ARE THEREFORE INADMISSIBLE 13
A. CLAIMANT’s Email of April 1, 2016 Constituted the Failure of Negotiations ....... 13
B. CLAIMANT Failed to Meet the Sixty-Day Time Limit ........................................... 14
1. Initiation of arbitration requires the receipt of the request for arbitration by
RESPONDENT .............................................................................................................................. 15
2. Even if the receipt of the request for arbitration by the CAM-CCBC was decisive,
the arbitration was not commenced in time ........................................................................... 16
(a) The request of May 31, 2016 was incomplete and thus invalid .......................... 16
(i) The submitted power of attorney was defective ........................................... 16
(ii) The registration fee had not been paid in full ................................................ 17
(b) The defective request was not remedied ................................................................ 17
(i) The President does not have the power to extend the contractual deadline
for commencing arbitration by virtue of Art. 6.4 of the Rules ........................... 18
(ii) The amended power of attorney does not have a retroactive effect .......... 18
(iii) The payment of the remainder of the registration fee does not have a
retroactive effect ......................................................................................................... 19
C. The Delay is Not Justified by the Reasoning Brought Forward by CLAIMANT ... 19
1. The “pro-arbitration” rule does not extend to the question of CLAIMANT’s
compliance with the contractual deadline............................................................................... 20
2. CLAIMANT’s right to access to justice is not jeopardized ............................................. 20
3. Justification of the delay cannot be based on the cases cited by CLAIMANT ............ 21
4. CLAIMANT cannot justify its exceeding of the deadline by relying on the swift
transmission of the amended request to RESPONDENT by the CAM-CCBC .................... 22
III. CLAIMANT IS NOT ENTITLED TO THE ADDITIONAL PAYMENTS OF USD 2,285,240.00
AND USD 102,192.80 ............................................................................................................ 23
A. RESPONDENT Is Not Obliged to Pay Another USD 2,285,240.00 for the Fan
Blades ........................................................................................................................... 23
1. The fixed exchange rate of the Addendum applies to the entire Contract ............... 23
(a) The sale of the Parties made an agreement on a fixed exchange rate necessary24
(b) The Addendum’s wording supports the application of the fixed exchange rate25
(c) CLAIMANT’s subsequent behavior leads to the conclusion that the Parties
agreed on the fixed exchange rate .................................................................................... 25
(d) The contra proferentem rule does not apply ................................................................ 26
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
III
2. In any case, the exchange rate at the time of contract conclusion has to be applied26
(a) Fixing an exchange was necessary to comply with the Contract’s principles and
underlying circumstances .................................................................................................. 27
(i) Fixing an exchange rate corresponds with the Contract’s principle of risk-
sharing .......................................................................................................................... 27
(ii) The de-risking strategy calls for the fixation of an exchange rate ............... 28
(iii) The alleged principle of complete reimbursement is of no relevance ........ 28
(b) The Parties’ earlier conduct leads to the applicability of the exchange rate at the
time of contract conclusion .............................................................................................. 29
B. RESPONDENT Is Not Obliged to Pay the Levy ..................................................... 30
1. The Contract does not oblige RESPONDENT to bear the Levy ................................... 30
2. The CISG does not oblige RESPONDENT to bear the Levy ........................................ 30
(a) RESPONDENT is not obliged to pay the Levy under Art. 54 CISG ..................... 31
(i) Art. 80 CISG exempts RESPONDENT from its obligation to pay the Levy 31
(ii) The legal notion of Art. 35(2) CISG confirms that RESPONDENT is
exempt from its obligation to bear the Levy .......................................................... 32
(b) Art. 57 CISG does not oblige RESPONDENT to bear the Levy ........................... 33
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
IV
INDEX OF AUTHORITIES
Cambridge Business English Dictionary
Cambridge University Press, Cambridge 2011
Cited as: Cambridge Business English Dictionary
In § 165
ALTENKIRCH, Markus Die Sicherheitsleistung für die Prozesskosten, Ein
Vergleich des deutschen und englischen
Zivilprozessrechts und ein Vorschlag für das
Schiedsverfahrensrecht
Sellier. European Law Publishers, Munich 2013
Cited as: ALTENKIRCH
In §§ 21, 28, 59
BAMBERGER, Heinz G.
ROTH, Herbert
Beck’scher Online-Kommentar BGB
C. H. Beck, 40th ed., Munich 2016
Cited as: AUTHOR in: Bamberger/Roth
In § 123
BENEDICK, Gilles Die Informationspflichten im CISG und ihre
Verletzung, Unter Berücksichtigung des
Zusammenspiels mit dem nationalen schweizerischen
Recht
Sellier. European Law Publishers, Munich 2008
Cited as: BENEDICK
In § 170
BERG, Albert Jan van den International Arbitration: The Coming of a New Age?
ICCA Congress Series, Vol. 17
Kluwer Law International, Alphen aan den Rijn 2013
Cited as: AUTHOR in: van den Berg
In § 53
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
V
BERGER, Bernhard
Arbitration Practice – Security for Costs: Trends and
Developments in Swiss Arbitral Case Law
ASA Bulletin (2010/Vol. 28, Issue 1), pp. 7-81
Cited as: BERGER
In § 45
BERGER, Bernhard
KELLERHALS, Franz
International and Domestic Arbitration in Switzerland
Stämpfli Publications, 3rd ed., Berne 2015
Cited as: BERGER/KELLERHALS
In §§ 8, 57
BIANCA, Cesare M.
BONELL, Michael J.
Commentary on the International Sales Law
Giuffré, Milan 1987
Cited as: AUTHOR in: Bianca/Bonell
In § 170
BINDER, Peter International Commercial Arbitration and Conciliation
in UNCITRAL Model Law Jurisdiction
Sweet & Maxwell, 3rd ed., London 2010
Cited as: BINDER
In § 89
BISHOP, R. Doak
CRAWFORD, James
ET AL.
Foreign Investment Disputes: Cases, Materials and
Commentary
Kluwer Law International, 2nd ed., Alphen aan den
Rijn 2014
Cited as: BISHOP ET AL.
In § 54
BÖCKSTIEGEL, Karl-Heinz
KRÖLL, Stefan
ET AL.
Arbitration in Germany: The Model Law in Practice
Kluwer Law International, 2nd ed., Alphen aan den
Rijn 2015
Cited as: AUTHOR in: Böckstiegel et al.
In § 35
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
VI
BORN, Gary B.
International Commercial Arbitration Volume I-III
Kluwer Law International, 2nd ed., Alphen aan den
Rijn 2014
Cited as: BORN
In §§ 3, 49, 53, 101, 105, 108, 123
BRABANT, Alexander
LAPUNZINA VERONELLI, Andrea
ELLINGTON, Sarah
Et al.
Third Party Funding in International Arbitration,
Practical Consequences and Tactical Considerations
International Arbitration Law Review (2016/Vol. 19,
Issue 5), pp. 113-120
Cited as: BRABANT ET AL.
In § 59
BRUNNER, Christoph UN-Kaufrecht – CISG. Kommentar zum
Übereinkommen der Vereinten Nationen über
Verträge über den internationalen Warenkauf von 1980
Stämpfli Verlag AG, Bern 2004
Cited as: BRUNNER
In § 106
BUSCH, Danny
MACGREGOR, Laura (eds.)
The Unauthorised Agent, Perspectives from European
and Comparative Law
Cambridge University Press, Cambridge 2009
Cited as: AUTHOR in: The Unauthorised Agent
In § 93
CAM-CCBC Model Arbitration Clause
http://www.ccbc.org.br/Materia/1070/modelo-de-
clausula
Last visited: 16 January 2017
Cited as: Model Clause of the CAM-CCBC
In § 107
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
VII
CARON, David D.
CAPLAN, Lee M.
PELLONPÄÄ, Matti
The UNCITRAL Arbitration Rules: A Commentary
Oxford University Press, New York 2006
Cited as: CARON ET AL.
In § 90
CHUPRUNOV, Ivan The Arbitration Agreement and Arbitrability: Effects
of Contractual Assignment on an Arbitration Clause –
Substantive and Private International Law Perspectives
Repr. in: Austrian Yearbook on International
Arbitration (Vol. 2012), pp. 31-61
Cited as: CHUPRUNOV
In § 108
DARWAZEH, Nadia
LELEU, Adrien
Disclosure and Security for Costs or How to Address
Imbalances Created by Third-Party Funding
Journal of International Arbitration (2016/Volume 33,
Issue 2), pp. 125-150
Cited as: DARWAZEH/LELEU
In § 41
DRAETTA, Ugo
Short Practical Notes on Security for Costs in
Arbitration
The Paris Journal of International Arbitration
(2011/Issue 1), pp. 49-60
Cited as: DRAETTA
In §§ 41, 45, 57
FERRARI, Franco
KIENINGER, Eva-Maria
MANKOWSKI, Peter
Et al.
Internationales Vertragsrecht, Kommentar
C. H. Beck, 2nd ed., Munich 2012
Cited as AUTHOR in: Ferrari et al.
In §§ 123, 170, 176, 183
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
VIII
FERRARI, Franco
KRÖLL, Stefan
Conflict of Laws in International Arbitration
Sellier., Munich 2011
Cited as: AUTHOR in: Ferrari/Kröll
In § 89
FOUCHARD, Philippe
GAILLARD, Emmanuel
SAVAGE, John
Fouchard, Gaillard, Goldman on International
Commercial Arbitration
Kluwer Law International, The Hague 1999
Cited as: FOUCHARD/GAILLARD/SAVAGE
In § 108
GARNER, Bryan A. Black’s Law Dictionary
West Group, 5th ed., Eagan 1979
Cited as: BLACK
In § 74
GERBAY, Rémy
RICHMAN, Lisa
SCHERER, Maxi
Arbitrating under the 2014 LCIA Rules: A User’s
Guide
Kluwer Law International, Alphen aan den Rijn 2014
Cited as: GERBAY/RICHMAN/SCHERER
In § 28
GIRSBERGER, Daniel
VOSER, Nathalie
International Arbitration: Comparative and Swiss
Perspectives
Nomos/Schulthess, Zurich 2016
Cited as: GIRSBERGER/VOSER
In § 79
VON GOELER, Jonas Third Party Funding in International Arbitration and
its Impact on Procedure
Kluwer Law International, Alphen aan den Rijn 2016
Cited as: VON GOELER
In § 41
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
IX
GOLDSMITH, Aren;
MELCHIONDA, Lorenzo
Third party funding in international arbitration:
everything you ever wanted to know (but were afraid to
ask): Part 2
International Business Law Journal (2012/Vol. 2),
pp. 221-243
Cited as: GOLDSMITH/MELCHIONDA
In §§ 8, 57, 59
GU, Weixia
Security for Costs in International Commercial
Arbitration
Journal of International Arbitration (2005/Vol. 22,
Issue 3), pp. 167-206
Cited as: GU
In § 3
HUBER, Peter
MULLIS, Alastair
The CISG, A New Textbook for Students and
Practitioners
Sellier. European Law Publishers, Munich 2007
Cited as: AUTHOR in: Huber/Mullis
In § 176
ICC ICC International Court of Arbitration Bulletin
(2014/Vol. 25), p.29 (New Claims)
Cited as: ICC Bulletin (2014/Vol. 25, Supplement)
In § 17
KARRER, Pierre;
DESAX, Marcus
Security for Costs in International Arbitration, Why,
when, and what if…
In: Liber amicorum Karl-Heinz Böckstiegel,
pp. 339 et seqq.
Carl Heymanns, Cologne 2001
Cited as: KARRER/DESAX
In §§ 3, 21, 59
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
X
KOLLER, Christian Arbitration Agreement and Arbitrability –
Contemplations on Set-off and Counterclaim in
International Commercial Arbitration
Repr. in: Austrian Arbitration Yearbook 2008
Cited as: KOLLER in: Austrian Arbitration Yearbook 2008
In § 38
KRÖLL, Stefan
MISTELIS, Loukas
VISCASILLAS, Pilar P
UN Convention on Contracts for the International Sale
of Goods (CISG)
C. H. Beck, Munich 2011
Cited as: AUTHOR in: Kröll et al.
In §§ 106, 157, 170, 176, 183
KÜHNER, Detlev The Impact of Party Impecuniosity on Arbitration
Agreements: The Example of France and Germany
Journal of International Arbitration (2014/Vol. 31,
Issue 6), pp. 807-818
Cited as: KÜHNER
In § 105
KUNZ, Catherine A. Enforcement of Arbitral Awards under the New York
Convention in Switzerland – An overview of the
current practice and case law of the Swiss Supreme
Court
ASA Bulletin (2016/Vol. 34, Issue 4), pp. 836-865
Cited as: KUNZ
In § 89
LEONARD, Sarah
DHARMANANDA, Kanaga
Peace Talks Before War: The Enforcement of Clauses
for Dispute Resolution Before Arbitration
Journal of International Arbitration (2006/Vol. 23),
pp. 301 et seqq.
Cited as: LEONARD/DHARMANANDA
In § 63
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XI
LEW, Julian D. M.
MISTELIS, Loukas A.
KRÖLL, Stefan M.
Comparative International Commercial Arbitration
Kluwer Law International, The Hague/London/New
York 2003
Cited as: LEW/MISTELIS/KRÖLL
In §§ 90, 94
MAGNUS, Ulrich
HABERMANN, Norbert
J. von Staudingers Kommentar zum Bürgerlichen
Gesetzbuch, Allgemeiner Teil 5
Sellier – de Gruyter, 1st ed., Berlin
Cited as: AUTHOR in: Staudinger BGB
In § 63
MARTINEK, Michael
MAGNUS, Ulrich
J. von Staudingers Kommentar zum Bürgerlichen
Gesetzbuch Band 2, (CISG)
Sellier – de Gruyter, lst ed. 2013
Cited as: AUTHOR in: Staudinger
In §§ 106, 124, 170
MAZZONI, Alberto
AONDOAKKA, Chief M.K.
UNIDROIT Principles of International Commercial
Contracts 2010
International Institute for the Unification of Private
Law (UNIDROIT), Rome 2010
Cited as: Official Commentary
In § 93
MOSES, Margaret L.
The Principles and Practice of International
Commercial Arbitration
Cambridge University Press, 2nd ed., New York 2012
Cited as: MOSES
In §§ 14, 21, 53
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XII
NEWMAN, Lawrence W.
DAVIDSON, Charles M.
Arbitrability of Timeliness Defense: Who decides?
Journal of International Arbitration (2004/Vol. 14),
pp. 137-144
Cited as: NEWMAN/DAVIDSON
In § 112
ÖHLBERGER, Veit Arbitration Agreement and Arbitrability – China-
Related Contracts: What to Consider When Agreeing
on CIETAC Arbitration
Repr. in: Austrian Yearbook of International
Arbitration 2009
Cited as: ÖHLBERGER in: Austrian Yearbook of
International Arbitration 2009
In § 34
PILTZ, Burghard Internationales Kaufrecht – Das UN-Kaufrecht in
praxisorientierter Darstellung
C.H. Beck, 2nd ed., Munich 2008
Cited as: PILTZ
In § 106
PÖRNBACHER, Karl
THIEL, Sophie
Kostensicherheit in Schiedsverfahren
German Arbitration Journal (SchiedsVZ) (2010/Vol. 8,
Issue 1), pp. 14-21
Cited as: PÖRNBACHER/THIEL
In §§ 3, 21, 45
REDFERN, Alan
HUNTER, Martin
BLACKABY, Nigel
PARTASIDES, Constantine
Law and Practice of International Commercial
Arbitration
Sweet & Maxwell, 4th ed., London 2014
Cited as: REDFERN ET AL.
In §§ 90, 94
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XIII
REDFERN, Alan;
HUNTER, Martin
BLACKABY, Nigel
PARTASIDES, Constantine
Redfern and Hunter on International Arbitration
Oxford University Press, 6th ed., Oxford 2015
Cited as: REDFERN/HUNTER
In §§ 21, 34, 53, 89, 123
REDFERN, Alan;
O’LEARY, Sam
Why It Is Time for International Arbitration to
Embrace Security for Costs
Arbitration International (2016/Vol. 32, Issue 3),
pp. 397-413
Cited as: REDFERN/O’LEARY
In §§ 3, 21, 28, 49, 57
ROSENGREN, Jonas Contract Interpretation in International Arbitration
Journal of International Arbitration (2013/Vol. 30,
Issue 1), pp. 1-16
Cited as: ROSENGREN
In § 137
RUBINS, Noah In God We Trust, All Others Pay Cash, Security for
Costs in International Commercial Arbitration
The American Review of International Arbitration
(2000/Vol. 11, Issue 3), pp. 307-378
Cited as: RUBINS
In §§ 57, 59
SÄCKER, Franz Jürgen
RIXECKER, Roland
OETKER, Hartmut
LIMPERG, Bettina
Münchener Kommentar zum Bürgerlichen
Gesetzbuch, Vol. 3
C. H. Beck, 7th ed., Munich 2016
Cited as: AUTHOR in: MüKo
In §§ 157, 170
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XIV
VON SCHLABRENDORFF, Fabian The Arbitral Tribunal’s Authority to Order Security for
Underlying Claims: Some Observations on How (Not)
to Exercise It
In: Liber amicorum Elsing, pp.493-507
Deutscher Fachverlag Gmbh, Frankfurt 2015
Cited as: VON SCHLABRENDORFF
In §§ 3, 28, 59
SCHMIDT, Karsten Münchener Kommentar zum Handelsgesetzbuch,
Vol. 5
C. H. Beck, 3rd ed., Munich 2013
Cited as: AUTHOR in: MüKo HGB
In § 157
SCHWENZER, Ingeborg Schlechtriem & Schwenzer, Commentary on the UN
Convention on the International Sale of Goods (CISG)
Oxford University Press, 4th ed., Oxford 2016
Cited as: AUTHOR in: Schlechtriem/Schwenzer
In §§ 106, 123, 124, 137, 157, 167, 170, 176, 183
SCHWENZER, Ingeborg Schlechtriem/Schwenzer, Kommentar zum
einheitlichen UN-Kaufrecht. Das Übereinkommen der
Vereinten Nationen über Verträge über den
internationalen Warenkauf, CISG
C.H. Beck, 6th ed., Munich 2013
Cited as: AUTHOR in: Schlechtriem/Schwenzer Ger. ed.
In § 170
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XV
SHAHDADPURI, Khushboo H. Third-Party Funding in International Arbitration:
Regulating the Treacherous Trajectory
Asian International Arbitration Journal (2016/Vol. 12,
Issue 2), pp. 77-106
Cited as: SHAHDADPURI
In § 41
STRAUBE, Frederico José
FINKELSTEIN, Claudio
CASADO FILHO, Napoleão (eds.)
The CAM-CCBC Arbitration Rules 2012, A
Commentary, Eleven International Publishing, The
Hague 2016
Cited as: AUTHOR in: Commentary of CAM-CCBC Rules
In §§ 14, 84, 90
SUN, Wei
WILLEMS, Melanie
Arbitration in China. A Practitioner’s Guide
Kluwer Law International, Alphen aan den Rijn 2015
Cited as: SUN/WILLEMS
In § 63
SUTTON, David St. John
GILL, Judith
GEARING, Matthew
Russel on Arbitration
Sweet & Maxwell, 23rd ed., London 2007
Cited as: SUTTON/GILL/GEARING
In § 14
TSANG, Alan Transnational rules on interim measures in
international courts and arbitrations
International Arbitration Law Review (2011/Vol. 14,
Issue 2), pp. 35-42
Cited as: TSANG
In § 14
VÖGELE, Alexander
BORSTELL, Thomas
ENGLER, Gerhard
Verrechnungspreise, Betriebswirtschaft, Steuerrecht
C. H. Beck, 4th ed., Munich 2015
Cited as: AUTHOR in: Vögele/Borstell/Engler
In § 127
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XVI
VOGENAUER, Stefan
KLEINHEISTERKAMP, Jan
Commentary on the UNIDROIT Principles of
International Commercial Contracts (PICC)
Oxford University Press, Oxford 2009
Cited as: AUTHOR in: Vogenauer/Kleinheisterkamp
In §§ 93, 94, 137
WAINCYMER, Jeff Procedure and Evidence in International Arbitration
Kluwer Law International, Alphen aan den Rijn 2012
Cited as: WAINCYMER
In §§ 28, 34, 53, 54
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XVII
INDEX OF CASES
Austria
Oberster Gerichtshof, 19 April 2007
No. 6 Ob 56/07i, CISG-online No. 1495
Cited as: OGH, 19 April 2007 (Austria)
In § 176
Germany
Bundesgerichtshof, 6 February 1986
III ZR 109/84
Neue Juristische Wochenzeitschrift (NJW) 1986, p. 2309
Cited as: BGH, 6 February 1986 (Germany)
In § 63
Bundesgerichtshof, 8 March 1995
VIII ZR 159/94, CISG-online No. 144
Neue Juristische Wochenzeitschrift (NJW) 1995, pp. 2099 et seqq.
Cited as: BGH, 8 March 1995 (Germany)
In § 176
Landgericht Frankenthal, 17 April 1997
No. 8 O 1995/95, CISG-online No. 479
Cited as: LG Frankenthal, 17 April 1997 (Germany)
In § 157
Oberlandesgericht München, 9 July 1997
No. 7 U 2070/97, CISG-online No. 282
Cited as: OLG Munich, 9 July 1997 (Germany)
In § 38
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XVIII
Oberlandesgericht Dresden, 27 December 1999
2 U 2723/99, CISG-online No. 511
International Commercial Law (Beilage zur Zeitschrift Transport) 2000, pp. 20 et seqq.
Cited as: OLG Dresden, 27 December 1999 (Germany)
In §§ 106, 124
Bundesgerichtshof, 31 October 2001
No. VIII ZR 60/01, CISG-online No. 617
Neue Juristische Wochenschrift 2002, pp. 370 et seqq.
Cited as: BGH, 31 October 2001 (Germany)
In § 170
Bundesgerichtshof, 2 March 2005
VIII ZR 67/04, Cisg Online No. 999
NJW-Rechts-Report (NJW-RR) 2005, pp. 1218 et seqq.
Cited as: BGH, 2 March 2005 (Germany)
In § 176
Oberlandesgericht Stuttgart, 15 May 2006
5 U 21/06, CISG-online No. 1414
Cited as: OLG Stuttgart, 15 May 2006 (Germany)
In § 106
Oberlandesgericht Düsseldorf, 23 March 2011
No. I-15 U 18/10, CISG-online No. 2218
International Commercial Law 2012, pp. 237 et seqq.
Cited as: OLG Düsseldorf, 23 March 2011 (Germany)
In § 106
VG Augsburg, 27 March 2012
No. Au 3 K 11.1298
Cited as: VG Augsburg, 27 March 2012 (Germany)
In § 35
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XIX
Oberlandesgericht Rostock, 18 October 2013
No. 1 Ss 9/13 (11/13)
Rechtspfleger 2015, pp. 160 et seqq.
Cited as: OLG Rostock, 18 October 2013 (Germany)
In § 35
Bundesgerichtshof, 28 May 2014
VIII ZR 410/12, CISG-online No. 2513
NJW-Rechtsprechungs-Report (NJW-RR) 2014, 1202
Cited as: BGH, 28 May 2014 (Germany)
In § 137
Landessozialgericht Baden-Württemberg, 29 January 2015
No. L 7 AS 1406/12
Cited as: LSG Baden-Württemberg, 29 January 2015 (Germany)
In § 35
New Zealand
RJ & AM Smallmon v Transport Sales Limited and Grant Alan Miller
Court of Appeal New Zealand, 22 July 2011
No. C A545/2010 [2011] NZ C A 340, CISG-online No. 2215
Cited as: RJ & AM Smallmon v Transport Sales and Grant Alan Miller (New Zealand)
In § 176
Switzerland
Bundesgericht, 17 August 1995
Transporten Handelsmaatschappij “Vekoma” BV v Maran Coal Corporation
ASA Bulletin 1996, pp. 673 et seqq.
Cited as: Vekoma v Maran Coal (Switzerland)
In § 63
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XX
Obergericht des Kantons Zug, 08 November 2011
No. OG 2010 8, CISG-online No. 2425
Cited as: OG Kanton Zug, 08 November 2011 (Switzerland)
In § 106
United Kingdom
Ust-Kamenogorsk Hydropower Plant JSC v AES Ust-Kamenogorsk Hydropower Plant LLP
No. UKSC 35
12 June 2013
Cited as: Ust-Kamenogorsk Hydropower Plant JSC v AES Ust-Kamenogorsk Hydropower Plant
LLP (United Kingdom)
In § 108
Sonatrach Petroleum Corporation (BVI) v Ferrell International Ltd
No. [2001] EWHC 481 (Comm)
Commercial Court, 04 October 2001
Arbitration Law Reports and Review 2001 pp. 693 et seqq.
Cited as: Sonatrach v Ferrell (United Kingdom)
In § 123
USA
Bechtel do Brasil Construcoes Ltda. v UEG Araucária Ltda., 638 F.3d 150 (2d Cir. 2011)
United States Court of Appeals for the Second Circuit
Cited as: Bechtel v UEG Araucária (USA)
In §§ 111, 112
Château des Charmes Wines Ltd v Sabaté USA, Sabaté SA
No. 02-15727, CISG-online No. 1139
U.S. Circuit Court of Appeals (9th Circuit), 05 May 2003
Cited as: Château des Charmes Wines v Sabaté (USA)
In § 106
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XXI
Medical Marketing International, Inc. v Internazionale Medico Scientifica S.r.l
No. 99-0380 Section “K” (1), CISG-online No. 387
United States District Court, E. D. of Louisiana, 17 May 1999
Cited as: Medical Marketing International, Inc. v Internazionale Medico Scientifica (USA)
In § 176
Mid-Ohio Sec. Corp. v. Estate of Burns
United States District Court, District of Nevada, 14 June 201, 790 F. Supp. 2d 1263
(D. Nev. 2011)
Cited as: Mid-Ohio Sec. Corp. v. E/O Burns (USA)
In §§ 111, 113
Princz v. Federal Republic of Germany, 813 F. Supp. 22 (D.D.C. 1992)
United States District Court for the District of Columbia, 23 December 1992
Cited as: Princz v Federal Republic of Germany (USA)
In § 105
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XXII
INDEX OF ARBITRAL AWARDS
International Commercial Arbitration Court [ICAC]
ICAC Russia Case No. 107/2002 of 2002
CISG-online No. 1181
Cited as: ICAC Case No. 107/2002
In § 123
International Chamber of Commerce [ICC]
ICC Case No. 2626 of 1977
Cited as: ICC Case No. 2626 (1977)
In § 123
ICC Case No. 8887 of 1997
Available at: ICC International Court of Arbitration Bulletin (Vol. 11/No. 1), p. 91
Cited as: ICC Case No. 8887 (1997)
In § 108
ICC Case No. 10032 of 1999
Cited as: ICC Case No. 10032 (1999)
In § 57
ICC Case No. 11869 of 2011
Assignee of buyer (Republic of Korea) Respondent: Seller (Australia) v Seller (Australia), Award
Cited as: ICC Case No. 11869 (2011)
In § 137
ICC Case No. 12732 of 2006
Procedural Order January 2006
Available at: ICC International Court of Arbitration Bulletin (Vol. 25/Supplement), p. 62
Cited as: ICC Case No. 12732 (2006)
In § 17
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XXIII
ICC Case No. 13620 of 2006
Cited as: ICC Case No. 13620 (2006)
In § 3
ICC Case No. 14433 of 2008
Cited as: ICC Case No. 14433 (2008)
In §§ 45, 57
ICC Case No. 15218 of 2008
Cited as: ICC Case No. 15218 (2008)
In § 57
ICC Case No. 19581 of 2014
Summarized in: ICC Bulletin (2014/Vol. 25, Supplement), pp. 35 et seq.
Cited as: ICC Case No. 19581 (2014)
In § 17
Iran-United States Claims Tribunal [IUSCT]
The Government of the Islamic Republic of Iran v The Government of the United States of
America
Cases No. A-4 and A-15, Award No. ITL 33-A/A-15(III)-2
1 February 1984
Cited as: Iran v United States (IUSCT)
In § 28
Sylvania Technical Systems Inc v The Government of the Islamic Republic of Iran
Award, Case No. 64 (180-64-1)
27 June 1985
Cited as: IUSCT Case No. 64 (1985)
In § 54
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XXIV
Nederlands Arbitrage Instituut [NAI]
Producer v Construction Company,
Interim Award, NAI Case No. 1694,
12 December 1996
Yearbook Commercial Arbitration 1998
Cited as: NAI Case No. 1694 (1996)
In § 57
Permanent Court of Arbitration [PCA]
Hulley Enterprises Limited (Cyprus) v The Russian Federation
Final Award, Case No. AA226
18 July 2014
Cited as: Hulley Enterprises Limited v The Russian Federation (PCA)
In § 34
South American Silver Limited (Bermuda) v The Plurinational State of Bolivia
Procedural Order No. 10 in: PCA Case No. 2013-15 of 2016
Cited as: South American Silver Ltd v Bolivia (PCA)
In § 3
Swiss Chambers’ Arbitration Institution [SCAI]
Claimants 1-2 v Respondents 1-16, Order No. 1
19 December 2008
ASA Bulletin 2010, pp. 47 et seqq.
Cited as: Claimants 1-2 v Respondents 1-16 (SCAI)
In § 57
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XXV
INDEX OF LEGAL SOURCES
Bürgerliches Gesetzbuch, 2016 (BGB)
CAM-CCBC Arbitration Rules, 2012 (Rules)
Convention on the Recognition and Enforcement of Foreign Arbitral Awards (= New
York Convention), 1958 (NYC)
DIAC Arbitration Rules 2007
DIS Arbitration Rules, 1998 (DIS Rules)
Handelsgesetzbuch, 2016 (HGB)
ICC Rules of Arbitration, 2012 (with Standard Clauses) (ICC Rules)
ICDR International Arbitration Rules 2014
ICSID Convention Arbitration Rules, 2006 (ICSID Rules)
International Arbitration Practice Guideline – Applications for Security for Costs, of the
Chartered Institute of Arbitrators, as revised on 29 November 2016 (Guideline for
Security for Costs)
KLRCA Arbitration Rules 2013
LCIA Arbitration Rules 2014
MKAS Rules
SIAC Rules 2016
Swiss Rules of International Arbitration, 2012 (Swiss Rules)
UNICTRAL Arbitration Rules, 2013 (UNCITRAL Rules)
UNCITRAL Model Law on International Commercial Arbitration, 1985 with
amendments as adopted in 2006 (Model Law)
UNIDROIT Principles of International Commercial Law, 2010 (UPICC)
United Nations Convention on the International Sale of Goods, 1980 (CISG)
Vienna Rules 2013
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XXVI
LIST OF ABBREVIATIONS
§(§) paragraph(s)
% per cent
Answ. Answer
Art(t). Article(s)
BGH Bundesgerichtshof
CAM-CCBC Center for Arbitration and Mediation of the
Chamber of Commerce Brazil-Canada
CEO Chief Executive Officer
cf. confer
Chapt. Chapter
Cl. Claimant
Corp. Corporation
DIAC Dubai International Arbitration Centre
DIS Deutsche Institution für Schiedsgerichtsbarkeit
E/O Estate of
ed. Edition
EQD Equatorianian Denars
et al. et alia/et aliae/et alii
et seq. et sequentia
et seqq. et sequentes
Exh. exhibit
GmbH Gesellschaft mit beschränkter Haftung
ibid. ibidem
ICAC International Commercial Arbitration Court
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XXVII
ICAC International Commercial Arbitration Court
ICC International Chamber of Commerce
ICDR International Centre for Dispute Resolution
ICSID International Centre for Settlement of
Investment Disputes
IUSICT Iran-United States Claims Tribunal
KG Kommanditgesellschaft
KLRCA Kuala Lumpur Regional Centre for Arbitration
LCIA London Court of International Arbitration
LG Landesgericht
Ltd Limited
Memo. Memorandum
MKAS Chamber of Commerce and Industry of the Russian
Federation
MüKo Münchener Kommentar
NAI Nederlands Arbitrage Intituut
No. Number
OG Obergericht
OLG Oberlandesgericht
p(p). Page(s)
PCA Permanent Court of Arbitration
Plc Public limited company
Proc. Procedural
R$ Brazilian Reais
Req. Request
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
XXVIII
Resp. Respondent
SA Sociedad Anónima
SCAI Swiss Chambers’ Arbitration Institution
SIAC Singapore International Arbitration Centre
SP Sociedad Participada
UN United Nations
UNCITRAL United Nations Commission on International
Trade Law
UNIDROIT International Institute for the Unification of
Private Law
USA United States of America
USD United States Dollar
v versus
Vol. Volume
ZG Zivilgericht
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
1
STATEMENT OF FACTS
The parties to this arbitration are Wright Ltd (hereinafter “CLAIMANT”) and
SantosD KG (hereinafter “RESPONDENT”, collectively “the Parties”).
CLAIMANT is a producer of fan blades, incorporated in Equatoriana. Its bank account is held in
Equatorianian Denars (EQD).
RESPONDENT is a manufacturer of jet engines, incorporated in Mediterraneo. Its bank account is
held in United States Dollars (USD).
Until 2010 CLAIMANT and RESPONDENT both were subsidiaries of the same
parent company, Engineering International SA. During this time, the
Parties had two cooperations.
27 July 2010 Engineering International SA sold CLAIMANT to its current parent
company Wright Holding Plc. Due to confidentiality, RESPONDENT
only learned about this sale shortly before it was executed.
01 August 2010 Three days after the sale of CLAIMANT, the Parties entered into a
“Development and Sales Agreement” (hereinafter “the Contract”), in
order to jointly develop the TRF 192-I, a new generation of fan blades.
03 August 2010 RESPONDENT was sold.
26 October 2010 The Parties attached an addendum to the Contract (hereinafter “the
Addendum”), agreeing on the purchase of 2,000 clamps for the fan
blades. The Parties further agreed on a fixed exchange rate of
USD 1.00 = EQD 2.01.
14 January 2015 RESPONDENT received the fan blades and the clamps. An invoice was
attached to the delivery. Its depicted purchase price was based on the
exchange rate of USD 1.00 = EQD 2.01.
15 January 2015 As soon as RESPONDENT effected payment of the invoiced amount
and informed CLAIMANT about the transaction, CLAIMANT declared
that a “wrong” exchange rate had been applied. It demanded an
additional payment of USD 2,285,240.00 for the fan blades.
29 January 2015 USD 20,336,367.20 were credited to CLAIMANT’s bank account. The
transferred sum had been investigated for money laundering. In order
to reimburse the investigation expenses, a 0.5 %
levy (USD 102,190.80) was deducted according to the Equatorianian
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
2
public law regulation ML/2010C.
09 February 2015 CLAIMANT demanded payment for this levy and repeated its allegation
that the invoice applied a “wrong” exchange rate.
10 February 2015 RESPONDENT declared to have complied with all its contractual
obligations. It pointed out the correctness of the invoice.
31 March 2016 A meeting between the Parties did not lead to an amicable solution, as
they insisted upon their respective positions.
01 April 2016 CLAIMANT declared that it had instructed its lawyer to initiate
arbitration proceedings.
31 May 2016 The CAM-CCBC received CLAIMANT’s request for arbitration.
01 June 2016 The President of the CAM-CCBC required CLAIMANT to supplement
its request for arbitration.
07 June 2016 CLAIMANT supplemented its request.
08 June 2016 The CAM-CCBC notified RESPONDENT about the commencement of
arbitration.
22 August 2016 The Terms of Reference were signed.
05 September 2016 Facts were disclosed which caused serious doubts as to CLAIMANT’s
compliance with an award rendered against it.
06 September 2016 Based on these facts, RESPONDENT submitted a request for security
for costs.
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
3
SUMMARY OF ARGUMENTS
CLAIMANT’s and RESPONDENT’s contractual relationship got off to a flying start when the Parties
agreed to jointly develop a new generation of fan blades. However, after the Contract had already
been performed, things took a wrong turn. CLAIMANT – in what now appears to be an attempt to
replenish its financial resources – decided to ask for more than it was entitled to by virtue of their
Contract. To this end, it dragged RESPONDENT into an arbitral proceeding and continues to give
alternative facts to support its claim.
Some of those facts were set straight by a diligent journalist, since CLAIMANT saw no need to
communicate with RESPONDENT itself. As soon as RESPONDENT found out about CLAIMANT’s
precarious financial situation, it took action and made a request for security for costs. To deprive
RESPONDENT of this appropriate means of defense, CLAIMANT argues that the request was
submitted too late. However, as RESPONDENT could not have made it any sooner, the request is
admissible. Furthermore, since CLAIMANT’s financial situation leaves little hope for recovery, it is
very likely that RESPONDENT will be left with its legal expenses. As a consequence, RESPONDENT
should be granted security for its legal costs (Issue I).
Funnily enough, CLAIMANT itself did not set a very good example at keeping deadlines. It has
proven itself incapable of observing the contractual time limit to commencing the arbitral
proceeding, and now intends to obliterate this failure by pointing to subsequent amendments to
its request for arbitration. As those amendments do not alter the fact that CLAIMANT initiated the
arbitration after the contractual time limit had expired, its request for arbitration should be
rejected as inadmissible (Issue II).
It is also not clear why RESPONDENT should top up CLAIMANT’s empty pockets after having
effected payment of the exact amount invoiced by CLAIMANT itself. It was afterwards that it
declared to be entitled to an additional USD 2,285,240.00 and, out of the blue, produced an
exchange rate favorable to its own interests. However, this not only goes against their contractual
agreement itself but also against the Contract’s inherent principle of risk-sharing. Moreover,
having failed to take into account the public law regulations of its own country, CLAIMANT now
wants to offload the costs for the observance thereof onto RESPONDENT. However, CLAIMANT is
not entitled to this additional payment neither by agreement nor by law. Therefore, RESPONDENT
is not obliged to pay either of the amounts demanded by CLAIMANT (Issue III).
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
4
ARGUMENT
I. THE TRIBUNAL SHOULD GRANT RESPONDENT SECURITY FOR ITS COSTS
1 On September 6, 2016, RESPONDENT submitted a request for security for costs in the
amount of USD 200,000.00. The Tribunal is respectfully requested to order CLAIMANT to
provide security for RESPONDENT’s costs. Contrary to CLAIMANT’s submission (Cl. Memo., § 11),
the Tribunal has the power to do so (A.). Since all prerequisites for such an order are met, the
Tribunal should exercise its power in favor of RESPONDENT (B.).
A. The Tribunal Has the Power to Order Security for Costs
2 Contrary to CLAIMANT’s submission (Cl. Memo., § 11), the Tribunal has the power to grant
RESPONDENT security for its costs.
3 CLAIMANT alleges that the Tribunal’s general power to grant interim measures under Art. 8
of the CAM-CCBC Rules and Art. 17 Model Law does not encompass the Tribunal’s power to
order security for costs (ibid.). It bases its reasoning on the fact that neither article explicitly
provides for this power (Cl. Memo., § 13). However, it is generally acknowledged that the power
to order interim measures does encompass the power to order security for costs, irrespective of
whether it is explicitly addressed (BORN, p. 2495; cf. KARRER/DESAX, p. 343; cf. GU, p. 182;
cf. PÖRNBACHER/THIEL, pp. 16 et seq.; cf. REDFERN/O’LEARY p. 402; cf. VON SCHLABRENDORFF,
pp. 494 et seq.; South American Silver Ltd v Bolivia (PCA); ICC Case No. 13620 (2006)). Since the
Parties agreed on the application of the Rules of the CAM-CCBC (Cl. Exh. C 2, Sec. 21), the
Tribunal has the power to order security for costs according to Art. 8 of the Rules.
4 Contrary to CLAIMANT’s submissions (Cl. Memo., §§ 7, 10), neither the Terms of Reference
nor the Rules restrict this power (1.). Further, contrary to what CLAIMANT alleges (Cl. Memo., §10)
initiating a new arbitral proceeding in order for RESPONDENT to obtain security for its legal costs
would be nonsensical (2.).
1. Neither the Terms of Reference nor the Rules restrict the Tribunal’s power to order
security for costs
5 The Tribunal has the power to order security for RESPONDENT’s costs as the Parties did not
conclude an agreement to the contrary. CLAIMANT’s submission that the power to order security
for costs is restricted by the Terms of Reference (Cl. Memo., § 7) is not persuasive.
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
5
6 In the Terms of Reference, the Parties did not agree to each bear their own costs. They did
therefore not exclude the right to request security for costs (a). Requesting security for costs does
not constitute an inadmissible modification of the Terms of Reference either (b).
(a) The Terms of Reference do not exclude the Tribunal’s power to order security for
costs
7 Contrary to CLAIMANT’s allegation (Cl. Memo., § 9), Art. 12.4 Terms of Reference does not
require the Parties to each bear their own legal costs. Therefore, the Terms of Reference do not
bar the Parties from seeking security for costs.
8 If, in the Terms of Reference, the parties agree to each bear their own costs, there is no
room for an order for security for costs (cf. BERGER/KELLERHALS, § 1595,
cf. GOLDSMITH/MELCHIONDA, p. 222). The Tribunal would then lack the power to order security
for costs in the present case.
9 However, Art. 12.4 Terms of Reference merely establishes that “[d]uring the course of the
arbitration proceedings, each party shall bear the fees of its respective attorneys”. The provision
does not preclude the Tribunal from allocating the costs to either one of the Parties at the end of
the proceeding. The Parties are only required to each bear their own legal costs during the
proceeding.
10 Instead, Art. 12.3 Terms of Reference expressly grants the Tribunal the authority to allocate
the costs of the proceeding.
11 To conclude, the Terms of Reference do not restrict the Tribunal’s power to order security
for costs.
(b) A request for security for costs does not unlawfully amend the Terms of Reference
12 Contrary to CLAIMANT’s allegations (Cl. Memo., § 10), requesting security for costs does not
result in an unlawful amendment of the Terms of Reference. Art. 4.21 of the Rules does not
apply to security for costs (i). Even if it applied, the Tribunal would still have the power to order
security for costs (ii).
(i) The restrictive effect of Art. 4.21 of the Rules does not extend to security for costs
13 Contrary to CLAIMANT’s submission (Cl. Memo., § 10), an order for security for costs would
not unlawfully amend the Terms of Reference as Art. 4.21 of the Rules does not apply to security
for costs.
14 According to Art. 4.21 of the Rules, the claims and causes of action may no longer be
amended after the Terms of Reference were signed. This only pertains to new claims or other
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
6
causes of action concerning the subject matter (WALD ET AL. in: Commentary of CAM-CCBC Rules,
Art. 4.21 p. 111). However, interim measures, such as security for costs, are neither new claims
nor causes of action regarding the subject matter. They rather serve to protect the parties’ rights
in the course of the proceeding (TSANG, p. 35; SUTTON/GILL/GEARING, § 5-074; cf. MOSES,
p. 105).
15 Thus, the Rules do not impose a ban on requesting security for costs after the signing of the
Terms of Reference. It follows that RESPONDENT’s request does not constitute an unlawful
amendment of the Terms of Reference.
(ii) Even if the restrictive effect of Art. 4.21 of the Rules extended to security for costs, the Tribunal would still
have the power to order security for costs
16 Contrary to CLAIMANT’s submission (Cl. Memo., § 32), RESPONDENT could not have made its
request any sooner. Therefore, the Tribunal would still have the power to order security for costs
after the signing of the Terms of Reference even if Art. 4.21 of the Rules applied to security for
costs.
17 A request for security for costs is admissible even after the signing of the Terms of
Reference if the relevant causes of action were not known at that time (ICC Case No. 12732
(2006); cf. ICC Case No. 19581 (2014); cf. ICC Bulletin (2014/Vol. 25, Supplement), p. 29).
18 RESPONDENT submitted the request as soon as the facts on which it is based came to light.
The revealed information had not been publicly available before and RESPONDENT was therefore
dependent on CLAIMANT’s cooperation (Req. for Security). However, CLAIMANT did not inform
RESPONDENT about its refusal to comply with an award rendered against it (ibid.). Nor did it let
RESPONDENT know that it sought third party funding to pursue its claims in this arbitration (ibid.).
These facts are substantial to evaluating CLAIMANT’s financial situation as they give rise to
legitimate concerns about the latter’s solvency. The relevant information could not have been
deduced from the balance sheets of 2015 (cf. Proc. Order No. 2, § 28), rather it was only revealed
after signing the Terms of Reference (Resp. Exh. R 6). RESPONDENT therefore submitted its
request as soon as possible.
19 Hence, the request is admissible and the Tribunal has the power to order security for
RESPONDENT’s costs.
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
7
2. Initiating a new arbitral proceeding to obtain security for costs would undermine the
latter’s nature
20 According to CLAIMANT, “RESPONDENT’s only other option in this situation is to initiate a
new arbitration proceeding” (Cl. Memo., § 10). However, initiating a new proceeding for obtaining
security for costs would in fact contradict the latter’s nature. This is because security for costs is
inseparably linked to the pending arbitral proceeding.
21 An order for security for costs necessarily precedes the rendering of the arbitral
award (REDFERN/O’LEARY, p. 399; MOSES, p. 105; REDFERN/HUNTER, § 7.14). Proceedings
may be paused or even terminated if the order is not adhered to (PÖRNBACHER/THIEL, p. 20;
ALTENKIRCH, p. 273; KARRER/DESAX, pp. 351 et seq.). Thus, it has a direct impact on the
proceeding (ibid.). It is only once the Tribunal renders the award that it decides whether the
requesting party actually receives the secured sum (cf. Art. 12.3 Terms of Reference). If the request
for security for costs were to be dealt with in a separate proceeding, it would be void of meaning.
22 Thus, initiating a new proceeding in order to obtain security for RESPONDENT’s costs would
be nonsensical.
23 According to Art. 8 of the Rules, the Tribunal has the power to order security for costs. This
power is neither restricted by the Terms of Reference nor by the relevant.
B. The Tribunal Should Exercise Its Power to Order Security for Costs
24 The Tribunal should order security for costs in the present case. Contrary to CLAIMANT’s
allegations (Cl. Memo., §§ 9, 14, 17, 25), the prerequisites for such an order are met.
25 CLAIMANT establishes that the following prerequisites need to be adhered to in order to
grant security for costs: First, RESPONDENT must be in danger of suffering irreparable
harm (Cl. Memo., §§ 14, 21 et seq.). Second, this must be due to a fundamental change in
CLAIMANT’s financial situation after contract conclusion (Cl. Memo., §§ 27 et seq.). Third,
RESPONDENT’s request has to be urgent (Cl. Memo., § 14). Fourth, RESPONDENT must meet its
burden of proof for the abovementioned requirements (Cl. Memo., §§ 11, 16 et seqq.). Finally,
granting security for costs has to be just under the present circumstances (Cl. Memo., §§ 24 et seq.,
32).
26 Insofar, RESPONDENT has no objections. However, contrary to CLAIMANT’s submission, the
abovementioned prerequisites are met: RESPONDENT runs the risk of suffering irreparable
harm (1.). RESPONDENT is not prevented from relying on CLAIMANT’s poor financial situation as
it deteriorated substantially since contract conclusion (2.). The submitted request for security for
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
8
costs is urgent (3.) RESPONDENT also met its burden of proof (4.). An evaluation of the
exceptional circumstances of this case shows that ordering security for costs is just (5.).
1. RESPONDENT is in danger of suffering irreparable harm
27 Contrary to CLAIMANT’s allegations (Cl. Memo., §§ 14, 21), RESPONDENT faces the danger of
suffering irreparable harm.
28 CLAIMANT submits that “an injury that can be ‘made whole’ by monetary relief does not
constitute irreparable harm” (Cl. Memo., § 21). Thereby, it relies on a single award from 1984 (ibid.;
cf. Iran v United States (IUSCT)). The case refers to ‘irreparable harm’ as harm which cannot be
compensated by an award of damages. By relying on this case, CLAIMANT neglects that an award
of damages will in fact be futile if CLAIMANT is financially unable to comply with it. Therefore,
the more recent consensus is that for an order for security for costs it suffices to establish the
danger of “incurring substantial expense in defending a claim only to find that any costs order
made in its favor goes unfulfilled” (REDFERN/O’LEARY, p. 410). This very standard is the bar for
ordering security for costs (ALTENKIRCH, p. 214; cf. VON SCHLABRENDORFF, p. 504;
GERBAY/RICHMAN/SCHERER, p. 267, WAINCYMER, p. 646).
29 Correspondingly, RESPONDENT is merely obliged to establish that it is in danger of being
deprived of an award rendered against CLAIMANT.
30 As CLAIMANT would not be able to comply with an award in RESPONDENT’s favor,
RESPONDENT faces the risk of being deprived of this award. This becomes apparent from
CLAIMANT’s balance sheets (a) and its previous conduct (b). Further, seeking third party funding
implies that CLAIMANT is impecunious (c).
(a) CLAIMANT’s incapacity to comply with an award is evidenced by its balance sheets
31 Contrary to CLAIMANT’s allegation (Cl. Memo., § 19), the balance sheets show its incapacity to
comply with a future award.
32 CLAIMANT’s overall financial situation prevents it from complying with a future award.
CLAIMANT asserts that its largely depleted liquidity is usually built up again as soon as the newly
developed products are sold (Cl. Memo., § 28; Cl. Exh. C 9). However this is merely an uncertain
expectation. Since 2009, CLAIMANT did not build up any liquid means but suffered a loss of more
than USD 800,000.00 (Proc. Order No. 2, § 28), despite selling fan blades (cf. Cl. Exh. C 9). This
raises legitimate doubts as to whether liquid means will indeed be built up again. What is more,
CLAIMANT could be developing a new product by the time the award is rendered, leaving it with
depleted liquidity once again.
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
9
33 In addition, enforcing an award into CLAIMANT’s assets also runs the risk of being fruitless.
34 The execution into a company’s assets entails liquidating its property, plant and intangible
assets (REDFERN/HUNTER, § 11.13; Hulley Enterprises Limited v The Russian Federation (PCA)). If
there are not enough assets, the enforcement of the award is endangered (cf. WAINCYMER, p. 600;
ÖHLBERGER in: Austrian Yearbook of International Arbitration 2009, p. 142).
35 In case the award needs to be enforced, it is not guaranteed that RESPONDENT’s interest in
receiving the amount it is entitled to will be satisfied. According to the balance sheets,
CLAIMANT’s assets equal USD 42,757,950.00, whereas all its liabilities amount to
US 40,532,950.00 (Proc. Order No. 2, § 28). However, the liquidated amount of the assets will not
necessarily equal the worth ascribed to them in the balance sheets (cf. RÜTZEL/KRAPFL in:
Böckstiegel et al., p. 1070; cf. LSG Baden-Württemberg, 29 January 2015 (Germany); cf. OLG Rostock, 18
October 2013 (Germany); cf. VG Augsburg, 27 March 2012 (Germany)). In fact, if less than 95 % of the
assets’ value listed in the balance sheets were obtained through liquidation, not all of CLAIMANT’s
creditors including RESPONDENT could be fully satisfied. Thus, the enforcement of an award
runs the risk of being fruitless.
36 To conclude, the balance sheets show that RESPONDENT faces the risk of being deprived of
its award due to CLAIMANT’s precarious financial situation.
(b) CLAIMANT’s non-compliance with a previous award further indicates that
RESPONDENT faces the risk of being deprived of its award
37 Contrary to CLAIMANT’s allegations (Cl. Memo., § 23), its non-compliance with an award
rendered against it in a different arbitral proceeding gives reason to doubt its future compliance.
38 In a proceeding between CLAIMANT and one of its suppliers in January 2016, CLAIMANT was
ordered to pay USD 2,500,000 (Req. for Security, § 2; Resp. Exh. R 6). To the present day,
CLAIMANT has not complied with this payment obligation (Proc. Order No. 2, § 30). In an attempt
to justify this, CLAIMANT points to an alleged set-off with a pending claim of its parent
company (Cl. Memo., § 23; Answ. to Req. for Security; Proc. Order No. 2, § 30). However, this is not
persuasive: set-off is only possible where the parties have two certainly existing mutual claims
against each other (KOLLER in: Austrian Arbitration Yearbook 2008, p. 62; OLG Munich, 9 July 1997
(Germany)). Meanwhile, CLAIMANT’s parent company has not yet transferred its claim to
CLAIMANT (cf. Answ. to Req. for Security). Further, the existence of the claim is uncertain as long as
it has not been decided by the courts of Ruritania (ibid.). Therefore, CLAIMANT cannot justify its
non-compliance with the award of the proceeding against its supplier. It must also be considered
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
10
that an amount of USD 2,500,000.00 might soon have to be paid by CLAIMANT. This sum will
then no longer be available for the satisfaction of RESPONDENT’s future costs award.
39 To conclude, RESPONDENT has good reason to fear non-compliance with an award rendered
in its favor.
(c) Seeking third party funding implies that CLAIMANT is impecunious
40 Contrary to CLAIMANT’s allegation (Cl. Memo., § 29), CLAIMANT’s efforts to obtain third
party funding confirm RESPONDENT’s doubts as to CLAIMANT’s liquidity.
41 It is usually impecunious parties who make use of third party funding in order to pursue
their claims (SHAHDADPURI, p. 81; cf. DARWAZEH/LELEU, p. 125; VON GOELER, p. 333). Thus,
the fact that CLAIMANT made efforts to obtain third party funding (Proc. Order No. 2, § 29), gives
reason to believe that it is unable to bear the costs of the arbitration (cf. DRAETTA, p. 55).
Consequently, it becomes doubtful whether CLAIMANT will comply with an award rendered
against it. This is all the more true, given that it was only able to pursue its claim by misusing a
loan from its parent company, originally provided for product development (Proc. Order No. 2,
§ 29). All of this affirms the conclusions already drawn by RESPONDENT regarding CLAIMANT’s
precarious financial situation (see supra §§ 31 et seqq.).
42 CLAIMANT’s search for third party funding therefore shows that RESPONDENT runs the risk
of being deprived of a future award.
43 In conclusion, RESPONDENT runs the risk of being deprived of an award rendered in its
favor. CLAIMANT’s poor financial standing is evidenced by its balance sheets, its previous non-
compliance and its efforts to receive third party funding.
2. RESPONDENT is not prevented from relying on CLAIMANT’s poor financial situation
44 RESPONDENT can rely on CLAIMANT’s poor financial situation as it deteriorated substantially
after contract conclusion.
45 An order for security for costs requires a serious deterioration in the relevant party’s financial
situation since the conclusion of the arbitration agreement (DRAETTA, pp. 53 et seq.; BERGER,
p. 10; PÖRNBACHER/THIEL, p. 18; ICC Case No. 14433 (2008)).
46 The balance sheet of 2009, which was the most recent one at the time of contract conclusion,
shows that CLAIMANT’s total assets amounted to USD 57,775,000.00 (Proc. Order No. 2, § 28). By
2015, they have deteriorated by about USD 15,000,000.00 (ibid.). Further, CLAIMANT’s liquidity
diminished from USD 875,000.00 in 2009 to USD 199,950.00 in 2015 (ibid.). This amounts to a
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
11
decrease of more than 75 %. Moreover, the annual profit decreased from about
USD 2,500,000.00 in 2009 to USD 657,000.00 in 2015 (ibid.), which equals a decrease of 73 %.
47 This development is bound to be qualified as a serious deterioration. Thus, RESPONDENT is
not prevented from relying on CLAIMANT’s poor financial situation.
3. RESPONDENT’s request is urgent
48 Contrary to CLAIMANT’s lines of argument (Cl. Memo., § 14), the matter of security for
RESPONDENT’s legal costs is urgent.
49 Interim measures, such as security for costs, are urgent if the decision cannot await the final
award (BORN, p. 2474; REDFERN/O’LEARY, p. 410). Security for costs serves its purpose best if it
is granted as soon as possible (cf. REDFERN/O’LEARY, p. 399). If the opposing party does not
adhere to the order for security for costs, the proceeding is stopped and the applicant is left with
all the costs it incurred. The longer the tribunal waits with its decision, the more costs the
applicant accumulates.
50 RESPONDENT’s costs for this proceeding are increasing from day to day. It cannot be sure
whether it will be able to recover these costs from CLAIMANT, unless RESPONDENT is granted
security for its costs.
51 Thus, the request is urgent.
4. RESPONDENT met its burden of proof
52 Contrary to CLAIMANT’s allegations (Cl. Memo., § 17), RESPONDENT met its burden of proof
by submitting the newspaper article.
53 It lies within the tribunal’s discretion to weigh the evidentiary value of submitted
documents (WAINCYMER, p. 793, BORN, pp. 2309 et seq.; MOSES, p. 172). Thereby, it should
consider whether the submitted evidence was the most suitable at this point in
time (REDFERN/HUNTER, § 6.90; HOFFMANN/SHETTY in: van den Berg, pp. 198 et seq.;
cf. WAINCYMER, p. 794; cf. BORN, p. 2310).
54 RESPONDENT submitted its request as soon as the necessity became apparent; namely on the
day following the publication of the article in the Carioca Business News (cf. Req. for Security;
cf. Resp. Exh. R 6). By including the newspaper article, it immediately provided the best piece of
evidence available at the time. After all, further proof can be submitted at a later stage of the
proceeding if needed. For the time being, a newspaper article can be considered sufficient
evidence (cf. IUSCT Case No. 64 (1985); cf. BISHOP ET AL., § 12.07; WAINCYMER, p. 794).
CLAIMANT has not contested any of the facts in the article on which RESPONDENT relied. Instead,
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
12
CLAIMANT even confirmed them by explaining its motivation (Answ. to Req. for Security; Cl. Memo.,
§§ 23, 29).
55 To conclude, the newspaper article constitutes sufficient proof for RESPONDENT’s
statements.
5. An order for security for costs is just in the present circumstances
56 Ordering security for RESPONDENT’s costs is just under the present circumstances.
57 RESPONDENT agrees with CLAIMANT’s lines of argument (Cl. Memo., § 24) that the Tribunal
ought to weigh the Parties’ opposing interests under the given circumstances (cf. ICC
Case No. 15218 (2008); cf. ICC Case No. 14433 (2008); cf. ICC Case No. 10032 (1999); cf. Claimants
1-2 v Respondents 1-16 (SCAI); cf. NAI Case No. 1694; cf. REDFERN/O’LEARY, p. 411; cf. DRAETTA,
p. 55; cf. RUBINS, pp. 374 et seq.). Thereby, it should take into account whether the applicant has a
prima facie chance of prevailing in the arbitration (RUBINS, p. 371; BERGER/KELLERHALS, § 1595;
DRAETTA, p. 53). A party has such a prima facie chance of succeeding if its case does not seem
completely unsubstantiated at first sight (cf. GOLDSMITH/MELCHIONDA, p. 222; cf. REDFERN/
O’LEARY, p. 410).
58 Contrary to CLAIMANT’s allegations (Cl. Memo., § 25), RESPONDENT has a prima facie chance
of succeeding. It has brought forward a well-argued case including proof regarding its defense. As
RESPONDENT’s case is thus not completely unsubstantiated at first sight, there is no necessity to
pre-judge the merits of the case. Therefore, the Tribunal’s “impartiality” – as alleged by
CLAIMANT (Cl. Memo., § 26) – cannot be doubted. Hence, CLAIMANT’s concerns about the
enforceability of the award (ibid.) are unfounded.
59 Further, RESPONDENT’s legitimate concerns as to whether it will be able to recover its
arbitral costs by far outweigh CLAIMANT’s interest to pursue its claim. CLAIMANT could provide
security for costs with the help of a bank guarantee (cf. ALTENKIRCH, p. 270; cf. VON
SCHLABRENDORFF, p. 499; cf. KARRER/DESAX, p. 349; cf. RUBINS, p. 320). Further, its parent
company could also accommodate with a letter of comfort or another loan, should it find
CLAIMANT’s claims worth pursuing. This would enable CLAIMANT to safeguard its right to
present its claim. By contrast, RESPONDENT faces the risk of not being reimbursed for its legal
costs. In case RESPONDENT is awarded its costs, it is limited to executing into CLAIMANT’s assets.
It cannot draw on the assets of CLAIMANT’s parent company, as the latter is not a party to this
arbitration (cf. BRABANT ET AL., p. 117; cf. GOLDSMITH/MELCHIODA, p. 223). Thus, the risk
RESPONDENT has to face is much more imminent.
60 To conclude, an order for security for costs would be just under the present circumstances.
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
13
Conclusion to the First Issue
The Tribunal has the power to grant security for costs. It should also exercise this power in favor
of RESPONDENT as all prerequisites for such an order are met. Consequently, CLAIMANT should
be ordered to provide security for RESPONDENT’s costs in the amount of USD 200,000.00.
II. THE CLAIMS WERE SUBMITTED OUT OF TIME AND ARE THEREFORE
INADMISSIBLE
61 The arbitration clause in the Contract provides that “each party has the right to initiate
arbitration proceedings within sixty days after the failure of the negotiation” (Cl. Exh. C 2,
Sec. 21). The failure of negotiations between the Parties occurred on April 1, 2016, thereby
triggering the sixty-day time limit (A.). Contrary to what CLAIMANT submits (Cl. Memo., §§ 42
et seqq.), it failed to comply with this time limit, which renders its request inadmissible (B.). This
delay cannot be justified by the reasoning brought forward by CLAIMANT (C.).
A. CLAIMANT’s Email of April 1, 2016 Constituted the Failure of Negotiations
62 Contrary to CLAIMANT’s allegations (Cl. Memo., §§ 34 et seqq.), its email of April 1, 2016
marked the failure of the Parties’ negotiations. Consequently, the time limit began to run on the
following day and expired on May 31, 2016.
63 The time limit is triggered by the failure of negotiations (Cl. Exh. C 2, Sec. 21). Whether
negotiations are still ongoing or have already come to a standstill is to be determined from an
objective point of view (cf. SUN/WILLEMS, p. 141; LEONARD/DHARMANANDA, p. 315; Vekoma v
Maran Coal (Switzerland)). A party’s assertion that it is, in principle, ready to negotiate does not
necessarily affirm the existence of negotiations between the parties (BGH, 6 February
1986 (Germany)). Rather, negotiations only continue as long as the parties hold an actual exchange
of views on a particular dispute (PETERS/JACOBY in: Staudinger BGB, Art. 203 § 7).
64 The present dispute had already been a matter of disagreement between the Parties for over
a year when they held a meeting on this subject on March 31, 2016 (Resp. Exh. R 3). The meeting,
however, did not help to resolve the fundamental differences between the Parties (ibid.; Proc.
Order No. 2, § 23). Rather, it reinforced those differences as neither of them was willing to move
away from its respective position (ibid.). In fact, already during that meeting, CLAIMANT refused
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
14
to even discuss some of the key points, such as the fixed exchange rate, unless RESPONDENT
agreed to place further orders (ibid.). Therefore, the negotiations had already come to a standstill
at that meeting.
65 On the following day, RESPONDENT received the abovementioned email. CLAIMANT
reiterated its position and at the same time announced that it had already “instructed [its] lawyer
to take the necessary steps to initiate arbitration proceedings” (Resp. Exh. R 3). It is true that
CLAIMANT further on declared that it would “remain open to any meaningful negotiations” (ibid.).
However, this needs to be seen in context with the disillusioning outcome of the meeting held
only a day earlier. Except for the fact that CLAIMANT decided to initiate legal proceedings, the
email did not contain any information which had not already been communicated in the
meeting (cf. ibid.; Proc. Order No. 2, § 23). After all, CLAIMANT’s insistence upon receiving
additional payment was already known to RESPONDENT. Thus, from an objective point of view,
the email served as a written documentation of the failure of the negotiation.
66 Therefore, CLAIMANT’s assertion that “the email clearly evidences CLAIMANT’s intent to
continue negotiations” (Cl. Memo., § 33) is not convincing. Such negotiations would only take
place should RESPONDENT “reconsider [its] view” (Resp. Exh. R 3). Thus, the phrase “open to
any meaningful negotiations” must be understood as a mere courtesy, allowing CLAIMANT to save
face.
67 By objective standards, the recipient of the email could only understand its content as
follows: Unless RESPONDENT concedes to CLAIMANT’s demands, the latter will proceed with
taking legal actions against the former. The fact that on the very next day, CLAIMANT’s parent
company attempted to authorize their lawyer (cf. Power of Attorney by Wright Holding Plc) also shows
that it did not actually expect any further negotiations to take place.
68 The email therefore cannot be qualified as a continuation of an exchange of views.
Consequently, the negotiation failed on April 1, 2016, thereby triggering the sixty-day time limit
stipulated in the Contract.
B. CLAIMANT Failed to Meet the Sixty-Day Time Limit
69 Contrary to CLAIMANT’s submission (Cl. Memo., §§ 42 et seqq.), CLAIMANT failed to submit its
request for arbitration within the period of sixty days. The request is therefore inadmissible.
70 In order to comply with the sixty-day time limit, CLAIMANT was obliged to initiate
arbitration by May 31, 2016 at the latest. It is therefore necessary to define at which point in time
arbitration was initiated. Since the Rules do not provide such a definition, recourse must be had
to Art. 21 Model Law. Accordingly, arbitration was only initiated on June 8, 2016, when
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
15
RESPONDENT received a copy of the request for arbitration (1.). Even if the receipt of the request
by the CAM-CCBC was decisive, proceedings were not validly commenced on May 31, 2016.
CLAIMANT’s request of that date was incomplete (2.).
1. Initiation of arbitration requires the receipt of the request for arbitration by
RESPONDENT
71 Contrary to CLAIMANT’s submission (Cl. Memo., §§ 42 et seqq.), the arbitration proceeding is
initiated when the request of arbitration is received by RESPONDENT. As correctly pointed out by
CLAIMANT (Cl. Memo., § 43), Art. 21 Model Law requires the receipt of the request by the
respondent for the arbitration to commence, unless the parties agreed otherwise.
72 The Parties did not reach such an agreement in the present case. They agreed upon the
application of the institutional rules of the CAM-CCBC (Cl. Exh. C 2, Sec. 21). However, contrary
to CLAIMANT’s submission (Cl. Memo., § 44), these Rules, in particular Art. 4, do not define when
arbitral proceedings are deemed to be commenced.
73 Art. 4.1 of the Rules enumerates a number of documents which must be enclosed with a
request for arbitration filed with the CAM-CCBC. This misled CLAIMANT to assuming that “once
these documents are submitted to the President of the CAM-CCBC, arbitration is considered to
have commenced” (Cl. Memo., § 44). However, Art. 4.1 of the Rules merely sets forth that “a
party desiring to commence arbitration will notify the CAM-CCBC” (emphasis added). There are
numerous important arbitral institutions which, in turn, do include provisions such as: “arbitral
proceedings shall be deemed to commence on the date on which […]” (Art. 2(2) ICDR-IAR
cf. Art. 4(2) ICC Rules; cf. Art. 2(2) KLRCA Rules,; cf. Art. 3(2) Swiss Rules; cf. Art. 3(2) UNICTRAL
Rules), “arbitration shall be deemed to commence […]” (Art. 7(1) Vienna Rules), “arbitral
proceedings shall commence when […]” (Art. 8(1) MKAS Rules) or “the date […] shall be treated
as the date on which the arbitration has commenced for all purposes” (Art. 1.4.1.4 LCIA Rules;
cf. Art. 3 SIAC Rules; cf. Art. 4.6 DIAC Rules). Those institutional rules provide definitions of the
commencement of arbitration. No comparable wording can be found in the Rules of the CAM-
CCBC. Consequently, they do not contain a definition of a point in time at which the arbitration
is deemed to have commenced.
74 This makes it necessary to have recourse to Art. 21 Model Law, which applies as the lex loci
arbitri (Proc. Order No. 1, § 5(4)). CLAIMANT objects (Cl. Memo., § 37) to the application of the
Model Law on the grounds of an alleged difference in the meaning of the words
“initiate” (Cl. Exh. C 2, Sec. 21) and “commence” (Art. 21 Model Law). However, “initiate” is
simply a synonym for “commence” (BLACK, “initiate”) and CLAIMANT’s argument does not hold.
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
16
75 For a timely commencement of the arbitration, RESPONDENT must have received the request
by May 31, 2016. However, this was only the case on June 8, 2016 (CAM-CCBC’s letter to the
Respondent, June 8, 2016). CLAIMANT therefore did not comply with the contractual time limit.
2. Even if the receipt of the request for arbitration by the CAM-CCBC was decisive, the
arbitration was not commenced in time
76 Even if the Tribunal were to consider the receipt of the request by the CAM-CCBC to be
decisive, the proceeding was not commenced in time. The request received by the CAM-CCBC
on May 31, 2016 was incomplete and therefore invalid (a). Further, the contractual time limit was
not extended by the President (b).
(a) The request of May 31, 2016 was incomplete and thus invalid
77 The requirements for a valid request for arbitration are enumerated in Art. 4(1), (2) of the
Rules. Meanwhile, CLAIMANT’s request of May 31, 2016 is defective in two respects. First, the
power of attorney enclosed with the request does not comply with Art. 4.1(b) of the Rules (i).
Second, CLAIMANT did not pay the registration fee pursuant to Art. 4.2 of the Rules (ii).
(i) The submitted power of attorney was defective
78 The power of attorney submitted to the CAM-CCBC on May 31, 2016 was not in line with
Art. 4.1(b) of the Rules. First, it indicates the wrong client, namely CLAIMANT’s parent company,
Wright Holding Plc. Second, it was the CEO of that parent company who signed the power of
attorney, rather than CLAIMANT.
79 According to Art. 4.1(b) of the Rules, the party wishing to commence arbitration must attach
to its request a power of attorney for any lawyer providing for adequate representation. As an
initiating document, the power of attorney needs to be “clear and unambiguous”, irrespective of
the applicable law or rules (cf. GIRSBERGER/VOSER, p. 212).
80 The submitted power of attorney failed to satisfy Art. 4.1(b) of the Rules, as shown by the
reaction of the President of the CAM-CCBC: On June 1, 2016, the President ordered CLAIMANT
to amend its request (CAM-CCBC’s letter to the Claimant of June 1, 2016). Thereby, he explicitly
rebuked CLAIMANT for submitting a power of attorney referring to the wrong claimant.
81 CLAIMANT itself does not contest that its power of attorney was defective (Cl. Memo., §§ 47
et seqq.). Instead, it relies on the fact that it provided an amended power of attorney upon the
President’s request to do so (Cl. Memo., § 47). It is true that the President gave CLAIMANT ten
days to implement the necessary amendments (CAM-CCBC’s letter to the Claimant of June 1, 2016)
and that CLAIMANT complied with this order (Fasttrack to CAM-CCBC, June 7, 2016). However,
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
17
CLAIMANT’s observance of the deadline set by the President does not change the fact that it
failed to abide by the contractual time limit in the first place. The correct power of attorney was
submitted a week after expiration of this time limit.
82 CLAIMANT did not provide a valid power of attorney within the deadline. As it thus failed to
comply with Art. 4.1(b) of the Rules, its request for arbitration was incomplete.
(ii) The registration fee had not been paid in full
83 The insufficient payment of the registration fee further hinders the commencement of the
proceeding on May 31, 2016. Of the R$ 4,000.00 due, CLAIMANT had only paid R$ 400.00 by
May 31, 2016 (CAM-CCBC’s letter to the Claimant of June 1, 2016).
84 Art. 4.2 of the Rules sets forth that the claimant “must” pay a registration fee (WALD ET AL.
in: Commentary of CAM-CCBC Rules, Art. 4.2, p. 67). The registration fee serves the critical purpose
of deterring parties from submitting an evidently unsubstantiated request for arbitration (WALD
ET AL. in: Commentary of CAM-CCBC Rules, Art. 4.2, pp. 66 et seq.).
85 CLAIMANT appears to be of the opinion (Cl. Memo., § 49) that the registration fee does not
have to be paid when submitting the request. This is not, however, the view of the President: He
regards the fulfillment of Art. 4.2 of the Rules as an indispensable element to a complete request
for arbitration (CAM-CCBC’s letter to the Claimant of June 1, 2016). This is why he waited for
CLAIMANT to comply with his orders before transmitting a copy of the request to
RESPONDENT (ibid.). After all, the CAM-CCBC has a legitimate interest in knowing whether the
claimant has a serious and unambiguous intent to arbitrate. This can only be reliably determined
by demanding the claimant to pay a registration fee, which CLAIMANT did not do in the present
case.
86 Thus, the lacking payment of the registration fee was such a significant deficiency of the
request that the proceeding could not be commenced before complete payment was effectuated.
As a consequence, CLAIMANT’s request for arbitration of May 31, 2016 was incomplete.
(b) The defective request was not remedied
87 Contrary to CLAIMANT’s allegations (Cl. Memo., §§ 45 et seqq.), the defects of the request of
May 31, 2016 were not remedied. The President does not have the power to extend contractual
time limits by virtue of Art. 6.4 of the Rules (i.). Nor does the amended power of attorney have a
retroactive effect (ii.). The subsequent payment of the complete registration fee does not have a
retroactive effect either (iii.).
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
18
(i) The President does not have the power to extend the contractual deadline for commencing arbitration by virtue
of Art. 6.4 of the Rules
88 Contrary to CLAIMANT’s submission (Cl. Memo., §§ 45 et seq.), Art. 6.4 of the Rules does not
authorize the President to extend the contractual deadline for commencing arbitration.
89 Art. 6.4 of the Rules only applies to time periods “provided in these Rules”. It was in the
Parties’ Contract that they agreed that an arbitration proceeding needs to be commenced within
sixty days after failure of negotiations (Cl. Exh. C 2, Sec. 21). Therefore, granting the CAM-CCBC
the power to extend contractual time limits would undermine the principle of party autonomy,
which is the central pillar of commercial arbitration (REDFERN/HUNTER, § 6.07; BINDER, §§ 5-
014, 5-017; BOOG in: Ferrari/Kröll, p. 416; cf. KUNZ, p. 850).
90 Moreover, Art. 6 of the Rules applies to time limits in the course of the arbitral
proceeding (cf. VERÇOSA in: Commentary of CAM-CCBC Rules, Art. 6, p. 125). In the case at hand,
CLAIMANT failed to meet the deadline to initiate arbitration proceedings. Those distinct types of
time limits are not comparable to one another: Time limits for submissions in the ongoing
arbitration proceeding serve the need for speedy proceedings (CARON ET AL., p. 618). However,
as compliance with rigid time limits cannot always be guaranteed in practice, there must be an
option to extend such time limits (ibid.). By contrast, time bars for the commencement of
arbitration are included in the contract for the sake of legal certainty (LEW/MISTELIS/KRÖLL,
p. 507; cf. REDFERN ET AL., § 4-04). Parties have a legitimate expectation that upon expiry of the
deadline, they will not be confronted with any legal claims (ibid.). The possibility of a
discretionary extension of such a time limit would thus completely defeat the purpose of legal
certainty.
91 Hence, the contractual time limit could not have been extended by the President of the
CAM-CCBC.
(ii) The amended power of attorney does not have a retroactive effect
92 Contrary to CLAIMANT’s submission (cf. Cl. Memo., §§ 45 et seq.), the second power of
attorney did not amend the request retroactively.
93 The only way to achieve such an effect is to retroactively amend the provided power of
attorney by virtue of Art. 2.2.9 UPICC. This article provides for the retroactive authorization of
an agent’s acts (Official Commentary, Art. 2.2.9 p. 90; KREBS in: Vogenauer/Kleinheisterkamp, Art. 2.2.9
§ 1; BUSCH in: The Unauthorised Agent, p. 372).
94 However, such a retroactive authorization is only possible where it does not contradict the
parties’ agreement (cf. KREBS in: Vogenauer/Kleinheisterkamp, Art. 2.2.9 § 18). The Parties’
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
19
contractual time limit precludes the possibility to retroactively remedy a request after its expiry.
The purpose of this time limit is to provide legal certainty (cf. LEW/MISTELIS/KRÖLL, p. 507;
cf. REDFERN ET AL., § 4-04). The Parties have a legitimate expectation not to be confronted with
any legal claims upon the expiry of the sixty days (cf. ibid.). If the amendment provided a week
after expiry of the deadline were to retroactively remedy the invalid request, CLAIMANT would be
able to open a loophole in the contractual time limit. This would render the agreement upon a
time limit to commencing arbitration void of meaning.
95 CLAIMANT did not retroactively remedy its request by submitting a second power of attorney.
(iii) The payment of the remainder of the registration fee does not have a retroactive effect
96 As correctly described by CLAIMANT (Cl. Memo., § 49), the President of the CAM-CCBC
requested payment of the additional amount, which CLAIMANT effected (CAM-CCBC’s letter to the
Claimant of June 1, 2016). However, CLAIMANT does not establish why the proceeding should
commence when only 10 % of the required amount has been paid.
97 CLAIMANT merely mentions Art. 4(4) of the ICC Rules (Cl. Memo., § 48). This rule stipulates
that a claimant who failed to make payment of the registration fee may be granted a further time
limit to do so by the Secretariat of the ICC. However, the rules governing this arbitration are
those of the CAM-CCBC (Cl. Exh. C 2, Sec. 21), which do not include a corresponding nor even
a similar regulation. This aligns with the fact that CLAIMANT found itself compelled to resort to
the ICC Rules rather than the set of rules applicable to this arbitration.
98 Therefore, the payment of the remainder of the registration fee does not retroactively amend
the failure to effect payment in time.
C. The Delay is Not Justified by the Reasoning Brought Forward by CLAIMANT
99 CLAIMANT introduces a number of reasons why its request should not be deemed
inadmissible (Cl. Memo., §§ 50 et seqq.). However, its attempts to justify exceeding the contractual
time limit are not convincing. First, the cited “pro-arbitration” rule only governs the
interpretation of the scope of arbitration clauses and does not apply to time bars (1.). Second, the
Tribunal should consider that the expiry of the contractual time limit does not preclude
CLAIMANT from pursuing its right before a state court (2.). Third, the cases invoked by
CLAIMANT are not persuasive authorities for this arbitration (3.). Fourth, CLAIMANT cannot
justify its exceeding of the deadline by relying on the swift transmission of the amended request
to RESPONDENT by the CAM-CCBC (4.).
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
20
1. The “pro-arbitration” rule does not extend to the question of CLAIMANT’s
compliance with the contractual deadline
100 CLAIMANT invokes “a ‘pro arbitration rule’ in interpreting arbitration clauses” (Cl. Memo.,
§ 51). However, the pro-arbitration rule does not alter the fact that its request was submitted out
of time and that it is therefore inadmissible.
101 CLAIMANT cites an author who indeed argues for a presumption in favor of
arbitration (BORN, pp. 1326 et seqq.). However, the quoted passage deals with “‘Pro-Arbitration’
presumptions regarding [the] scope of international arbitration agreement[s]” (BORN, p. 1326).
The presumption thus concerns the question whether or not a particular dispute was intended to
be submitted to arbitration instead of state courts (ibid.). The rationale behind such an extensive
interpretation of the scope of arbitration agreements is the interest of commercially reasonable
parties to resolve all of their disputes in a single, centralized proceeding (BORN, p. 1319).
102 The scope of the arbitration clause is not contested in the case at hand. Sec. 21 of the
Contract encompasses “all disputes arising out of or in connection with” the Contract (Cl. Exh.
C 2). Instead, the issue is whether CLAIMANT submitted its request for arbitration in time. Since
the “pro-arbitration” rule does not give any support in solving this question, there is no room for
its application.
103 The “pro-arbitration” rule does not make CLAIMANT’s belated request admissible.
2. CLAIMANT’s right to access to justice is not jeopardized
104 The inadmissibility of CLAIMANT’s request for arbitration does not result in an infringement
of its right to access to justice.
105 CLAIMANT submits that declaring the belated request inadmissible would infringe
“established international arbitral practice” (Cl. Memo., § 56). It thereby appears to be referring to
the right of each party to have access to justice, which is indeed a fundamental and internationally
recognized principle (Princz v Federal Republic of Germany (USA); cf BORN, p. 1083; cf. KÜHNER,
p. 806). However, CLAIMANT is not prevented from bringing its case before a state court upon
the expiry of the sixty-day time limit. This follows from an interpretation of the arbitration
agreement in accordance with Art. 8 CISG.
106 It is acknowledged that Art. 8 CISG governs the interpretation of arbitration
clauses (SCHMIDT-KESSEL in: Schlechtriem/Schwenzer, Art. 8 § 5; Château des Charmes Wines v
Sabaté (USA); OLG Stuttgart, 15 May 2006 (Germany)). As the common intent of the Parties
(Art. 8(1) CISG) cannot be determined (cf. Proc. Order No. 2, § 23), the understanding of a
reasonable business person within the meaning of Art. 8(2) CISG is decisive (cf. PILTZ, § 2-189;
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
21
cf. ZUPPI in: Kröll et al., Art. 8 § 21; cf. OG Kanton Zug, 8 November 2011 (Switzerland); OLG Düsseldorf,
23 March 2011 (Germany)). A reasonable business person would analyze the wording of the
clause (BRUNNER, Art. 8 § 13; MAGNUS in: Staudinger, Art. 8 § 24; OLG Dresden, 27 December 1999
(Germany)).
107 Sec. 21 of the Contract provides that “if no agreement can be reached each party has the right
to initiate arbitration proceedings within sixty days after the failure of the negotiation to have the
dispute decided by an arbitrator” (Cl. Exh. C 2, Sec. 21; emphasis added). By contrast, the standard
arbitration clause recommended by the CAM-CCBC reads: “Any dispute arising out of the
present contract, including its interpretation or performance, shall be finally settled by
arbitration […]” (Model Clause of the CAM-CCBC; emphasis added). The Parties did not adopt this
model clause. Sec. 21 of the Contract deviates from this wording in two respects. First, it does
not provide for the dispute to be “finally” decided by an arbitrator. Second, the Parties are given
the “right” to have recourse to arbitration, without being imposed the obligation to do so.
108 The negative effect of an arbitration clause is a “mirror-image” of its positive effect (BORN,
p. 1270). It is recognized that the stipulation of a strict positive obligation to solve disputes
through arbitration leads to a strict negative obligation to refrain from state court
proceedings (BORN, p. 1272; cf. Ust-Kamenogorsk Hydropower Plant JSC v AES Ust-Kamenogorsk
Hydropower Plant LLP (United Kingdom); cf. CHUPRUNOV, p. 38; cf. FOUCHARD/GAILLARD/
SAVAGE, p. 380; ICC Case No. 8887 (1997)).
109 As Sec. 21 of the Contract is comparably ‘soft’, a reasonable business person would not
understand it as excluding the Parties’ right to initiate state court proceedings upon the expiration
time limit.
110 In conclusion, the time bar in Sec. 21 of the Contract does not deprive CLAIMANT of this
right, but merely sets forth a time limit in which the right to refer to arbitration may be exercised.
The inadmissibility of the request does not infringe CLAIMANT’s right to access to justice.
3. Justification of the delay cannot be based on the cases cited by CLAIMANT
111 Contrary to CLAIMANT’s allegations (Cl. Memo., § 55), neither the ruling of Bechtel v UEG
Araucária (USA) nor of Mid-Ohio Sec. Corp v E/O Burns (USA) should be considered persuasive
authority for the admissibility of its request.
112 Bechtel v UEG Araucária (USA) is concerned with the arbitrability of the timeliness defense,
i.e. the question of whether it is the courts or the arbitrators who may decide whether a claim was
timely submitted (cf. NEWMAN/DAVIDSON, p. 137). The dispute arose due to a choice-of-law
provision which was in conflict with the arbitration agreement. It was ultimately a question of the
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
22
scope of the arbitrator’s power. This is not a matter of disagreement in the present case. Nor is
there a conflicting choice-of-law provision. Therefore, the reasoning cannot be transferred.
113 Nor is Mid-Ohio Sec. Corp. v. E/O Burns (USA) comparable to the present case. In that case, it
was unclear whether the claim was filed within the timeframe of a particular institutional rule.
This rule did not define what event triggers the time limit. By contrast, the arbitration clause in
the present case sets forth that it is the failure of the negotiation which triggers the time limit.
114 To conclude, neither of the cases are persuasive authority when determining the
inadmissibility of CLAIMANT’s request.
4. CLAIMANT cannot justify its exceeding of the deadline by relying on the swift
transmission of the amended request to RESPONDENT by the CAM-CCBC
115 The fact that the CAM-CCBC transmitted the request as soon as on June 8, 2016 does not
justify CLAIMANT’s non-compliance with the contractual deadline.
116 CLAIMANT argues (Cl. Memo., § 58) that if arbitration had been initiated on May 31, 2016,
RESPONDENT would have been notified by June 15, 2016 at the latest (Art. 4.3 of the Rules). As it
received a copy of the request on June 8, 2016, CLAIMANT alleges that RESPONDENT cannot rely
on the delay (ibid.).
117 However, the fast transmission of the request was only due to the efficiency of the CAM-
CCBC, which processed the amendments immediately upon their receipt. CLAIMANT should not
be able to benefit from a circumstance which evidently lies within the sphere of responsibility of
the CAM-CCBC (Art. 4.3 of the Rules). The fact that the CAM-CCBC did not exhaust the fifteen-
day time limit under Art. 4.3 of the Rules to forward the request happened to play into
CLAIMANT’s hands but was a mere coincidence.
118 As a conclusion, CLAIMANT cannot rely on the CAM-CCBC’s quick reaction to CLAIMANT’s
belated request.
Conclusion to the Second Issue
The contractual sixty-day time limit was triggered by the failure of negotiation on April 1, 2016.
CLAIMANT failed to abide by this time limit. Its submitted request for arbitration was deficient
and not remedied. As CLAIMANT was unable to justify this exceeding of the deadline, its request
for arbitration should be dismissed.
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
23
III. CLAIMANT IS NOT ENTITLED TO THE ADDITIONAL PAYMENTS OF
USD 2,285,240.00 AND USD 102,192.80
119 When the Parties signed their Contract, they did not expressly determine the exchange rate
applicable to the purchase price calculation of the fan blades (Cl. Exh. C 2). Upon
RESPONDENT’s initiative, the Parties concluded the Addendum providing for a fixed exchange
rate of USD 1.00 = EQD 2.01 (hereinafter “fixed exchange rate”) (Cl. Exh. C 2; Answ. to Req.,
§ 10). Immediately upon the receipt of the fan blades, RESPONDENT effected payment of the
purchase price of USD 20,438,560.00 (Cl. Exh. C 3). Afterwards, CLAIMANT alleged that the
Parties had agreed on a different exchange rate, namely that at the time of
delivery (USD 1.00 = EQD 1.79) (Cl. Exh. C 5). On the basis of this allegation, CLAIMANT
demands an additional payment of USD 2,285,240.00 (ibid.). Further, after RESPONDENT had
effected payment, the Equatoriana Central Bank deducted a levy of USD 102,192.80 (hereinafter
“the Levy”) by virtue of the Equatorianian public law regulation ML/2010C (hereinafter “the
Regulation”) (Cl. Exh. C 8). CLAIMANT argues that this sum must be borne by RESPONDENT as
well (Cl. Exh. C 6).
120 Contrary to CLAIMANT’s submission (Cl. Memo., §§ 60 et seqq.), it is not entitled to the
additional payment of USD 2,285,240.00 for the fan blades (A.). Nor is RESPONDENT obliged to
bear the Levy in the amount of USD 102,192.80 (B.).
A. RESPONDENT Is Not Obliged to Pay Another USD 2,285,240.00 for the
Fan Blades
121 Contrary to CLAIMANT’s submission (Cl. Memo., §§ 60 et seqq.), it is not entitled to the
payment of USD 2,285,240.00. This is because the fixed exchange rate of the
Addendum (USD 1.00 = EQD 2.01) is applicable to the calculation of the purchase price (1.).
Even if the Tribunal were to disagree, CLAIMANT is still not entitled to this additional payment.
Rather, it would merely be entitled to the payment of USD 97,440.00 as the exchange rate at the
time of contract conclusion (USD 1.00 = EQD 2.00) would have to be applied (2.).
1. The fixed exchange rate of the Addendum applies to the entire Contract
122 Contrary to CLAIMANT’s allegations (Cl. Memo., §§ 75 et seqq.), the Addendum amended the
Contract. Consequently, the Contract is governed by the fixed exchange rate of the Addendum.
Therefore, the purchase price due under the Contract amounts to USD 20,438,560.00, the
payment of which was effected by RESPONDENT (Cl. Exh. C 3).
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
24
123 According to Art. 29(1) CISG, a mere agreement between the contracting parties is sufficient
to amend a contract (cf. SCHROETER in: Schlechtriem/Schwenzer, Art. 29 §§ 6 et seq.; cf. SAENGER in:
Bamberger/Roth, Art. 9 § 1; cf. FERRARI in: Ferrari et al., Art. 29 § 7; cf. ICAC Case No 107/2002).
Whether the parties agreed to amend a contract is a matter of interpretation, which is to be
conducted pursuant to the law governing the contract (REDFERN/HUNTER, § 3.93; BORN, pp. 505,
515, Sonatrach v Ferrell (United Kingdom); ICC Case No. 2626 (1977)). As the Parties agreed that the
CISG applies to the Addendum (Cl. Exh. C 2, Addendum, Sec. 20), it must be interpreted in
accordance with Art. 8 CISG.
124 RESPONDENT agrees with CLAIMANT that there has been no common intent (Art. 8(1) CISG)
regarding the Addendum’s effect on the Contract (Cl. Memo., §§ 62 et seqq.). Therefore, the
understanding of a reasonable business person is decisive (Art. 8(2) CISG). When interpreting a
contract under Art. 8(2) CISG, the wording and all relevant circumstances shall be taken into
account, such as the parties’ negotiations, practices and subsequent conduct (Art. 8(3) CISG;
SCHMIDT-KESSEL in: Schlechtriem/Schwenzer, Art. 8 § 21; MAGNUS in: Staudinger, Art. 8 § 24;
cf. OLG Dresden, 27 December 1999 (Germany)).
125 Contrary to CLAIMANT’s allegations (Cl. Memo., §§ 75 et seqq.), an interpretation pursuant to
Art. 8(2) CISG leads to the conclusion that the fixed exchange rate stipulated in the Addendum
was to govern the whole Contract. This is due to several reasons: The sale of the Parties made it
necessary to agree on a fixed exchange rate for the Contract (a). Thus, as evidenced by the
Addendum’s wording, the fixed exchange rate is to be applied to the Contract (b). This also
corresponds with the Parties’ subsequent conduct (c). Lastly, contrary to CLAIMANT’s
submission, the contra proferentem rule does not apply (d).
(a) The sale of the Parties made an agreement on a fixed exchange rate necessary
126 Since the Parties were no longer subsidiaries of Engineering International SA (cf. Proc. Order
No. 2, § 1), they needed to provide for an exchange rate. Therefore, a reasonable business person
would find that the fixed exchange rate of the Addendum applies to the Contract.
127 One of the Contract’s underlying principles is the equal distribution of risks (Req. for Arb.,
§ 6; cf. Cl. Exh. C 1; cf. Resp. Exh. R 5). The exchange rate has a major impact on the currency risk
associated with the Contract (Resp. Exh. R 5; cf. BORSTELL/HÜLSTER in: Vögele/Borstell/Engler,
Chapt. M §§ 129 et seqq.).
128 When the Parties were subsidiaries of Engineering International SA, their parent company
used to determine the applicable exchange rate (Proc. Order No. 2, § 5). Thus, during the
negotiations, the Parties did not agree upon an applicable exchange rate (cf. Cl. Exh. C 1;
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
25
Resp. Exh. R 5). However, CLAIMANT was sold four days before contract conclusion and
RESPONDENT shortly after (Proc. Order No. 2, § 1). The established way to determine an applicable
exchange rate could thus not be followed anymore. In light of the Contract’s underlying principle
of the distribution of risks, the necessity to fix an exchange rate arose (Resp. Exh. R 5). To this
end, RESPONDENT suggested on October 22, 2010 to fix the exchange rate to
USD 1.00 = EQD 2.01 when adding the Addendum to the Contract (cf. Resp. Exh. R 2, 5). This
was the exchange rate of that day (cf. Proc. Order No. 2, § 12). A reasonable business person would
have realized this need of a new approach to determine the applicable exchange rate. It would
have regarded the fixed exchange rate of the Addendum as such.
129 Therefore, a reasonable business person would come the conclusion that the fixed exchange
rate also governs the Contract.
(b) The Addendum’s wording supports the application of the fixed exchange rate
130 When analyzing the wording of the Addendum (Cl. Memo., §§ 77 et seq.), CLAIMANT drew the
wrong conclusions. The wording, in fact, supports the applicability of the fixed exchange rate to
the entire Contract.
131 The decisive sentence of the Addendum states “The exchange rate for the agreement is fixed
to US$ 1 = EQD 2.01” (Cl. Exh. C 2, Addendum, emphasis added). Its heading reads “Addendum”,
whereas the Contract is referred to as the “main Agreement” in the Addendum’s body (ibid.).
Therefore, the term ‘agreement’ must stand for something other than either of the two – namely
the Contract and the Addendum taken together. A reasonable business person would recognize
that the Parties would have chosen a different term than ‘agreement’ if they had wanted to restrict
the effect of the fixed exchange rate to the Addendum only.
132 To conclude, a reasonable business person would find the fixed exchange rate of the
Addendum to govern the Contract.
(c) CLAIMANT’s subsequent behavior leads to the conclusion that the Parties agreed on
the fixed exchange rate
133 CLAIMANT issued an invoice based on the fixed exchange rate (Req. for Arb. § 10; Cl. Exh.
C 4). This subsequent behavior evidences that CLAIMANT itself was of the opinion that the
purchase price must be calculated based on the fixed exchange. Only after RESPONDENT effected
payment of the invoiced amount, CLAIMANT contested the applicability of the fixed exchange
rate to the Contract (Cl. Exh. C 3, 5).
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
26
134 CLAIMANT attempts to diminish the legal relevance of the invoice by relying on its
employee’s lack of knowledge regarding the details of the Contract (Cl. Memo., §§ 84 et seq.).
However, the fact that an impartial employee understood the fixed exchange rate as pertaining
the purchase of the fan blades (Cl. Exh. C 4) contradicts CLAIMANT’s submission. The employee
itself admits to “not realizing that the main contract […] did not contain a fixed exchange
rate” (ibid.) even after consulting “all correspondence” (ibid.). This indicates that a reasonable
business person would also come to the conclusion that the correct exchange rate is
USD 1.00 = EQD 2.01.
135 To conclude, CLAIMANT’s subsequent conduct leads to the applicability of the fixed
exchange rate to the calculation of the purchase price.
(d) The contra proferentem rule does not apply
136 CLAIMANT invokes the contra proferentem rule to establish that the Addendum must be
interpreted in its favor (Cl. Memo., §§ 79 et seqq.). CLAIMANT derives this from Art. 4.6
UPICC (ibid.). However the contra proferentem rule does not apply.
137 Art. 4.6 UPICC and Art. 8 CISG both include the contra proferentem rule (VOGENAUER in:
Vogenauer/Kleinheisterkamp, Art. 4.6 § 5; SCHMIDT-KESSEL in: Schlechtriem/Schwenzer, Art. 8, § 49;
BGH, 28 May 2014 (Germany)). This rule states that where a clause is ambiguous even after
interpretation, the wording will be construed against the party who drafted it (ICC Case
No. 11869 (2011); ROSENGREN, p. 11; VOGENAUER in: Vogenauer/Kleinheisterkamp, Art. 4.6 § 5).
138 As Sec. 20 of the Contract provides that the UPICC is only applicable for issues not dealt
with in the CISG (Cl. Exh. C 2), Art. 4.6 UPICC shall not apply. In any case, the interpretation of
the Addendum leads to an unambiguous result: The fixed exchange rate governs the Contract (see
supra §§ 122 et seqq.).
139 To conclude, the contra proferentem rule does not apply.
2. In any case, the exchange rate at the time of contract conclusion has to be applied
140 If the Tribunal were to find that the Addendum did not amend the Contract in regard to the
exchange rate, recourse must be had to the Contract. In this case, an interpretation of the original
Contract would provide for the application of the exchange rate at the time of contract
conclusion (USD 1.00 = 2.00 EQD). Thus, CLAIMANT would still not be entitled to the
additional payment of USD 2,285,240.00 as the exchange rate at the time of delivery is not
applicable (contrary to Cl. Memo., §§ 60 et seqq.). Rather only USD 97,440.00 would be due.
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
27
141 There is no common intent (Art. 8(1) CISG) of the Parties regarding the application of a
certain exchange rate (Proc. Order No. 2, § 15). Therefore, the understanding of a reasonable
business person (Art. 8(2) CISG) is the relevant standard in interpretation. Thereby, pursuant to
Art. 8(3) CISG, any relevant circumstances of the case shall be taken into account.
142 Such interpretation leads to the following conclusions: In order to comply with the
principles and circumstances underlying the Contract, it was necessary to fix an exchange rate (a).
This should be the one at the time of contract conclusion (b).
(a) Fixing an exchange was necessary to comply with the Contract’s principles and
underlying circumstances
143 The Contract’s underlying principle of risk-sharing calls for a fixed exchange rate (i).This is
further supported by the de-risking strategy (ii). The cost-plus basis for the price calculation does
not alter this result (iii).
(i) Fixing an exchange rate corresponds with the Contract’s principle of risk-sharing
144 Fixing an exchange rate is the only means to achieve the Contract’s principle of risk-sharing.
145 The Parties agreed that the Contract shall be based on risk-sharing (Cl. Memo., § 68; Cl. Exh.
C 1, 2; Req. for Arb., § 6). Applying a floating exchange rate, as suggested by
CLAIMANT (Cl. Memo., §§ 60 et seqq.), would in fact contradict this principle.
146 CLAIMANT recognized that RESPONDENT bore the risk that the price of the components of
the jet engine exceeded the price offered to Earhart SP (Cl. Memo. §§ 68 et seqq.). This is because
the purchase price of some of those components was indeterminable when RESPONDENT had to
offer a fixed price to Earhart SP (cf. Resp. Exh. R 5). CLAIMANT on the other hand bore the risk
that its production costs were to exceed the agreed maximum price of USD 13,125.00 (Req. for
Arb., § 7; Cl. Exh. C 2, Sec. 4). Both Parties were aware of the fact that the two risks were
“minor” (Req. for Arb., § 7; Cl. Memo., § 69; Resp. Exh. R 5).
147 What remains is the currency risk. In order to comply with the principle of risk-sharing, this
risk has to be equally divided between the Parties. Fixing an exchange rate is ideal to share the
currency risk associated with the Contract: Both Parties bear the risk that the exchange rate may
develop to their disadvantage.
148 A reasonable business person would thus conclude that in order to adhere with the
Contract’s underlying principle of risk sharing, it was necessary to fix an exchange rate.
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
28
(ii) The de-risking strategy calls for the fixation of an exchange rate
149 The strategy to de-risk RESPONDENT necessitates the fixation of an exchange rate.
150 In a meeting held on November 10, 2009, Engineering International SA announced that
RESPONDENT had to be de-risked (Resp. Exh. R 1). For this purpose, all other subsidiaries were
ordered to reduce the risks in existing contracts with RESPONDENT. Also, the risks in future
contracts were to be kept to a minimum (ibid.). One of the objectives explicitly mentioned by
Engineering International SA was to reduce any currency risks involved (ibid.). In particular, it
suggested using fixed exchange rates (ibid.). The CEOs of both Parties passed these orders on to
the negotiators of the Contract (Proc. Order No. 2, § 18).
151 When the Parties entered into negotiations, they were still affiliates (cf. Proc. Order No. 2, § 1).
As negotiations continued, the situation remained unchanged (ibid.). Just shortly before the
Contract was supposed to be signed, the signing had to be postponed due to CLAIMANT’s
sale (ibid.). Since the negotiations about CLAIMANT’s sale had been kept confidential,
RESPONDENT only found out about the sale when the signing date had to be postponed (ibid.).
Therefore, the main part of the Contract was drafted under the assumption that CLAIMANT
would contribute to RESPONDENT’s de-risking (cf. ibid.). All this time, CLAIMANT did not give
RESPONDENT any reason to doubt the former’s compliance with the de-risking strategy.
152 Therefore, a reasonable business person would conclude that an exchange rate had to be
fixed due to the de-risking strategy.
(iii) The alleged principle of complete reimbursement is of no relevance
153 Contrary to CLAIMANT’s submission (Cl. Memo., §§ 60, 67), the alleged principle of complete
reimbursement (Cl. Exh. C 2, Sec. 4(1)) does not lead to the application of a floating exchange rate.
154 In order for CLAIMANT to be fully reimbursed for its costs, a floating exchange rate has to be
applied (Cl. Memo., § 60). With such a floating exchange rate, RESPONDENT would bear the entire
currency risk – CLAIMANT would bear none of it. However, CLAIMANT itself noted that in respect
of the conversion from EQD to USD “no major risk [was] involved” (Cl. Exh. C 1). It therefore
thought that it does bear a certain risk. Had they agreed on a floating exchange rate, CLAIMANT
would not have faced any risk at all regarding the conversion (see supra § 146). CLAIMANT
contradicts itself: On the one hand, it wants to be reimbursed for its entire costs. On the other
hand, it acknowledges that the Contract provides for a fixed exchange rate. A reasonable business
person would conclude that the principle both Parties ascribed to the Contract, is the prevailing
one.
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
29
155 Therefore, the alleged principle of complete reimbursement does not alter the conclusion
that an exchange rate has to be fixed.
(b) The Parties’ earlier conduct leads to the applicability of the exchange rate at the time
of contract conclusion3
156 Contrary to CLAIMANT’s submission (Cl. Memo., §§ 71 et seq.), the Parties’ previous business
practice calls for the application of the exchange rate at the time of contract conclusion.
157 When discerning the understanding of a reasonable business person, the practices
established between the contracting parties are to be taken into account (Art. 8(3) CISG;
SCHMIDT-KESSEL in: Schlechtriem/Schwenzer, Art. 8 § 46; GRUBER in: MüKo, Art. 8 § 20; ZUPPI in:
Kröll et al., Art. 8 § 25). The key element to establishing a business practice between two parties is
the creation of a justified expectation that they will proceed correspondingly (SCHMIDT-KESSEL in:
Schlechtriem/ Schwenzer, Art. 9 § 8; FERRARI in: MüKo HGB, Art. 9 § 8; LG Frankenthal, 17 April
1997 (Germany)).
158 CLAIMANT and RESPONDENT have been business partners since 2003 (Proc. Order No. 2, § 5).
During this time, they entered into two contracts: The first was concluded in March 2003 and
performed in January 2006, the second was concluded in January 2005 and performed in May
2008 (ibid.). In both contracts, the exchange rate at the time of contract conclusion had been
applied when calculating the purchase price (ibid.). RESPONDENT could legitimately expect that
the exchange rate at the time of contract conclusion would also be applied to this Contract, as
CLAIMANT did not raise any doubts as to the continuation of the practice. The fact that
CLAIMANT did not simply forget about the issue of the exchange rate is evidenced by its own
documentations of the negotiations (Cl. Exh. C 1).
159 A reasonable business person would conclude that, in light of the Parties’ previous business
practice, the exchange rate at the contract conclusion has to be applied.
160 To conclude, RESPONDENT does not have to pay an additional USD 2,285,240.00. It paid
the full amount of the purchase price due under the Contract, calculated on the basis of the fixed
exchange rate provided for in the Addendum. Even if the fixed exchange rate of the Addendum
did not extend to the Contract, the exchange rate at the time of contract conclusion would have
to be applied. CLAIMANT would then merely be entitled to USD 97,440.00
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
30
B. RESPONDENT Is Not Obliged to Pay the Levy
161 RESPONDENT is under no duty to pay the Levy in the amount of USD 102,192.80. First, the
Contract does not put an obligation on RESPONDENT to pay the Levy (1.). Second, the CISG
does not impose such an obligation on RESPONDENT either (2.).
1. The Contract does not oblige RESPONDENT to bear the Levy
162 Contrary to CLAIMANT’s allegations (Cl. Memo., §§ 86 et seqq.), RESPONDENT is not obliged to
pay the Levy by virtue of the Parties’ agreement.
163 Sec. 4(3) of the Contract provides that the buyer shall transfer the purchase price to the seller
and that “the bank charges for the transfer of the amount are to be borne by the
BUYER” (Cl. Exh. C 2).
164 As the drafters of the Contract were not aware of the existence of the Regulation (Proc. Order
No. 2, § 6), there was no common intent (Art. 8(1) CISG) as to whether the Levy should be
excluded. Insofar, CLAIMANT comes to the same result (cf. Cl. Memo., §§ 90 et seq.). Thus, the
understanding of a reasonable business person is decisive (Art. 8(2) CISG).
165 A reasonable business person would understand the term ‘bank charges’ to refer to
“amounts of money paid by a customer for a bank’s services” (CAMBRIDGE BUSINESS ENGLISH
DICTIONARY, “bank charges”). In view of this definition, it would expect a ‘bank charge’ to be used
for a service either CLAIMANT or RESPONDENT asked for. Further, it would assume that this
service is provided by CLAIMANT’s bank, the Equatoriana National Bank (Cl. Exh. C 2, Sec. 4(3)).
However, the Levy is deducted by the Equatoriana Central Bank in the course of an examination
for money laundering (Proc. Order No. 2, § 7). This procedure was introduced by the
Equatorianian government by virtue of the Regulation ML/2010C (ibid.). The profit derived from
the investigations is eventually brought to the Equatorianian Ministry of Finance (ibid.). Therefore,
a reasonable business person would not consider the Levy to be a bank charge paid by a
customer for a bank’s service. The investigation serves the state’s interests only.
166 In conclusion, the Levy is not encompassed by Sec. 4(3) of the Contract, wherefore
RESPONDENT is not contractually obliged to bear it.
2. The CISG does not oblige RESPONDENT to bear the Levy
167 RESPONDENT does not have to bear the Levy by virtue of the CISG. That is because,
contrary to CLAIMANT’s lines of argument (Cl. Memo., § 133), Art. 62 CISG does not impose the
obligation to bear the Levy. Art. 62 CISG corresponds with the obligation to pay the purchase
price set forth in Art. 53 CISG (MOHS in: Schlechtriem/Schwenzer, Art. 62 § 1), which is further
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
31
specified by Artt. 54, 57 CISG (MOHS in: Schlechtriem/Schwenzer, Art. 53 § 1). However, neither
Art. 54 CISG (a) nor Art. 57 CISG (b) impose such an obligation on RESPONDENT.
(a) RESPONDENT is not obliged to pay the Levy under Art. 54 CISG
168 RESPONDENT is not obliged to pay the Levy. CLAIMANT correctly points out that the
obligation to bear the Levy is theoretically encompassed by Art. 54 CISG (Cl. Memo., §§ 96
et seqq.). Art. 54 CISG sets forth the buyer’s obligation to take all steps necessary in order to
enable payment to be made. Yet, CLAIMANT disregards that RESPONDENT is exempt from the
obligation to pay the Levy by virtue of Art. 80 CISG (i). This result is also in line with the legal
notion of Art. 35(2) CISG (ii).
(i) Art. 80 CISG exempts RESPONDENT from its obligation to pay the Levy
169 Contrary to what CLAIMANT submits (Cl. Memo., §§ 95 et seqq.), RESPONDENT is not required
to pay the Levy under Art. 54 CISG. As CLAIMANT did not fulfill its duty to inform
RESPONDENT about the Regulation, the latter is exempt from the obligation to pay the Levy by
virtue of Art. 80 CISG.
170 If a party causes another party’s failure to perform by act or omission, the former party
cannot rely on this failure (Art. 80 CISG; ATAMER in: Kröll et al., Art. 80 § 4; SAENGER in: Ferrari
et al., Art. 80 § 1; HUBER in: MüKo, Art. 80, § 1). Such omission may be a violation of one’s duty
to cooperate, which also encompasses a duty to inform (Art. 7(1) CISG; FERRARI in:
Schlechtriem/Schwenzer Ger. ed., Art. 7 § 54; MAGNUS in: Staudinger, Art. 7 § 41; ATAMER in: Kröll
et al., Art. 80 § 7; BGH, 31 October 2001 (Germany)). Artt. 54, 7(1) CISG impose the duty upon the
seller to inform the buyer about the former’s domestic public law regulations (cf. HUBER in: MüKo,
Art. 54 § 3; cf. MOHS, in: Schlechtriem/Schwenzer, Art. 54 § 4; cf. MASKOW in: Bianca/Bonell, Art. 54
§ 2.7). In order for the seller to be under such a duty to inform, the public law regulations must
first be unknown to the buyer (cf. BENEDICK, §§ 1021 et seqq.). Second, the seller must have reason
to believe that the buyer is unaware of the regulation (cf. BENEDICK, §§ 1032 et seqq.). Third, the
knowledge of the regulation has to be of relevance for the contract conclusion (cf. BENEDICK,
§§ 1038 et seqq.).
171 First, RESPONDENT did not know about the Regulation when the Parties concluded their
contract (Cl. Exh. C 7; Proc. Order No. 2, § 8). RESPONDENT can further not be expected to know
about the Regulation. This follows from the fact that it is a quite extraordinary regulation which
only came into force recently (Proc. Order No. 2, § 7). There are only five other states with a
comparable rule in force (ibid.). No such rule exists in RESPONDENT’s country
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
32
Mediterraneo (Proc. Order No. 2, § 8.). What is more, none of RESPONDENT’s domestic
newspapers published information regarding the Levy when the Regulation entered into
force (cf. Proc. Order No. 2, § 7). Furthermore, RESPONDENT’s only business partner in
Equatoriana is CLAIMANT (ibid.). Therefore, RESPONDENT cannot be expected to know about the
Regulation.
172 Second, CLAIMANT had reason to believe that RESPONDENT was not aware of the
Regulation. CLAIMANT knew about Equatoriana’s intention to fight money laundering due to
press reports before the Contract was concluded (Proc Order No. 2, § 8). However, it only found
out about the Regulation when a levy was actually deducted from another payment in June
2010 (ibid.). Therefore, as CLAIMANT was not aware of the Regulation, in spite of the press
reports, it cannot reasonably expect RESPONDENT, seated in another country (Req. for Arb., § 2),
to know it.
173 Third, knowledge of the Regulation was of relevance for the contract conclusion. Had
RESPONDENT been aware of a levy being charged, the Parties would have discussed this issue
during their negotiations and would have met an agreement regarding the Levy (Answ. to Req.,
§ 18). Therefore, it was essential for RESPONDENT to know about the Regulation.
174 Thus, all prerequisites for a duty to inform on behalf of CLAIMANT according to Artt. 54, 7(1)
CISG are fulfilled. However, CLAIMANT did not comply with this duty. It did not inform
RESPONDENT about the Regulation. Therefore, RESPONDENT is exempt from bearing the Levy
by virtue of Art. 80 CISG.
(ii) The legal notion of Art. 35(2) CISG confirms that RESPONDENT is exempt from its obligation to bear the
Levy
175 Contrary to CLAIMANT’s allegations (Cl. Memo., §§ 107 et seqq.), Art. 35(2) CISG confirms
that RESPONDENT is not obliged to bear the Levy.
176 Art. 35(2) CISG sets out objective standards to determine the conformity of delivered
goods (KRÖLL in: Kröll et al., Art. 35 § 60; MULLIS in: Huber/Mullis, p. 135; SCHWENZER in:
Schlechtriem/Schwenzer, Art. 35 § 13). For assessing this conformity, the domestic standard of the
seller’s country is decisive, unless he knew or ought to have known about the buyer’s domestic
regulations (cf. FERRARI in: Ferrari et al., Art. 35 § 14; KRÖLL in: Kröll et al., Art. 35 § 96; MULLIS in:
Huber/Mullis, pp. 136 et seq.; Medical Marketing International, Inc. v Internazionale Medico Scientifica
(USA); RJ & AM Smallmon v Transport Sales and Grant Alan Miller (New Zealand); OGH, 19 April
2007 (Austria); BGH, 2 March 2005 (Germany); BGH, 8 March 1995 (Germany)). The reason is that a
foreign seller cannot be expected to “know the not easily determinable public law provisions […]
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
33
of the country to which he exports” (BGH, 8 March 1995 (Germany)). The buyer, however, “can
be expected to have such expert knowledge” (ibid.). He therefore cannot rely on a non-
compliance with the domestic regulations of his country unless he informed the seller (ibid.).
177 In other words, the recipient of a delivery cannot invoke a non-compliance with its domestic
public law provisions if the foreign deliverer was unaware of them and did not have to be aware.
In the case at hand, CLAIMANT was the recipient of the purchase price, whereas RESPONDENT
was the one who ‘delivered’ the purchase price.
178 Therefore, the legal notion of Art. 35(2) CISG can be transferred onto the present case.
179 RESPONDENT does not have to comply with the Regulation since RESPONDENT neither
knew nor ought to have known about it (see supra § 171). Contrary to CLAIMANT’s
allegations (Cl. Memo., § 132), it cannot be expected of RESPONDENT to know the Regulation.
CLAIMANT wrongfully alleges (ibid.) that RESPONDENT would necessarily have come across the
Levy when inquiring about the ‘bank charges’ for the transfer. However, the Levy was not
charged for the purpose of transfer but was to pay for an investigation for money laundering (see
supra § 165). In fact, it is an extraordinary regulation (see supra § 171). Therefore, RESPONDENT
could not have been expected to inform itself about the Equatorianian legal development.
180 To conclude, RESPONDENT does not have to bear the Levy due to the legal notion of
Art. 35(2) CISG.
(b) Art. 57 CISG does not oblige RESPONDENT to bear the Levy
181 CLAIMANT invokes Art. 57 CISG which regulates the place of payment (Cl. Memo., § 103) to
establish that RESPONDENT has to bear the Levy.
182 However, the default rule of Art. 57(1) CISG only applies if the parties have not agreed on a
place of payment (Art. 57(1) CISG). As the Parties included Sec. 4(3) into their Contract, recourse
cannot be had to Art. 57 CISG. Sec. 4(3) of the Contract determines that the purchase price is to
be deposited into CLAIMANT’s bank account. Place of payment is therefore CLAIMANT’s place of
business, Equatoriana. Further, Sec. 4(3) of the Contract shifts the responsibility to bear bank
charges onto RESPONDENT (Cl. Exh. C 2). However, since the Levy is not a bank charge for
transfer (see supra § 165) it is carved out from RESPONDENT’s obligations (contrary Cl. Memo.,
§ 106).
183 Even if Art. 57 CISG were applicable, the result would be the same. Both, Artt. 54, 57 CISG
define the scope of the obligation to pay the purchase price under the CISG and thereby
complement each other (MOHS in: Schlechtriem/Schwenzer, Art. 57 § 20; MANKOWSKI in: Ferrari et al.,
Art. 53 § 5; BUTLER/HARINDRANATH in: Kröll et al., Art. 53 § 1). As RESPONDENT is exempt
LUDWIG -MAXIMILIANS-UNIVERSITÄT MÜNCHEN
_____________________________________________________
34
from the obligation to bear the Levy under Art. 54 CISG (see supra §§ 168 et seqq.), Art. 57 CISG
cannot not reinstate this duty.
184 Therefore, the obligation to bear the Levy on RESPONDENT’s part cannot be derived from
Art. 57 CISG.
Conclusion to the Third Issue
CLAIMANT is not entitled to the additional payment of USD 2,285,240.00. RESPONDENT does not
have to bear the Levy in the amount of USD 102,192.80.
REQUEST FOR RELIEF
In light of the submissions made above, RESPONDENT respectfully requests the Tribunal to find
that:
I. RESPONDENT’s request for security for costs should be granted.
II. The claims brought forward by CLAIMANT are inadmissible.
III. CLAIMANT is neither entitled to USD 2,285,240.00 for the fan blades nor to
USD 102,192.80 for the Levy