Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Initiating projects
Mergim Millaku
Ioannis Chalkias
Kevin Schörgnhofer
Content
- Project Life Cycle- Business Case- Project Governance Report- User requirements & solution design documents- Summary
Project Life Cycle
● Projects need clear start and end points● Also important: structure for the time between these points
→ Project Life Cycle is a recommended approach for this structure
● Covers Pre-Project, Project and Post-Project● Project initiation: Handover of the project ownership from the portfolio
management team to the project steering group
Project Life Cycle
Parts of Initiation-Phase
● Business case● Project governance report● User requirements document● Solution design document
Business Case
● Opportunity or problem● Strategic fit● Interdependencies● Success criteria● Options considered (should include “do-nothing” option)
Business Case
● Selected option:○ Risks
○ Benefits
○ Costs
○ Cost/benefit analysis
○ Deliverables and timescales
○ Planning assumptions
○ Benefits realisation plan
○ Management by objectives
Business Case
Opportunity or problem
● commercial gain: new market, new product or service● problem must be overcome to avoid risk
Strategic fit
● shows how the project will contribute to the strategic aims● opportunity to describe whether the contribution is direct, indirect, partial or
absent to each of the balanced scorecard quadrants● adds a dimension to the business case that is not purely commercial
Business Case
Interdependencies
● show the principal dependencies; helpful when the project is part of a wider portfolio or programme of work
● helps those who will have to manage those and in cases to justify it
Success criteria
● describes fully and clearly what success looks like -> decision to close the project is rel. easy
Business Case
Success criteria
● examples:● Does the new computer system process twice as many trades per day as the
previous one?● Have the new office operating procedures been made available to the Tokyo
office as a priority?● it is helpful for the project manager to ask each member to decide whether each
criterion is: essential, desirable, nice to have, low priority
Business Case
Option considered
● most problems or opportunities have a range of solutions● outline the most likely to satisfy the need● example:
○ An operational inefficiency may be overcome by introducing a new computer solution. As well as
living with the inefficiency, the business case could consider whether prepackaged software or a
system developed in house would provide the best answer.
● do-nothing option must feature● example for justified do-nothing option:
○ Year 2000 date change: there was real concern that some computers would fail to differentiate
between the year 2000 and the year 1900
Business Case
Option selected
● provides the most compelling argument in its favour● heart of the business case is formed from a balance of costs and benefits, but
the debate will be emotional during the early days● costs, risks and benefits subsections must be expressed robustly
Option selected: risks
● should identify the risks to a project as well as its benefits from the outset
Business Case
Option selected: risks
Business Case
Option selected: benefits
● should describe clearly each benefit in turn, including how they are to be measured and quantified in financial terms
Business Case
Option selected: costs
● every cost associated with the project should be identified so that it can be quantified
● should also include the operational, maintenance and support of the deliverable the project is producing (not only till the project closure)
● Budgets may be needed in:
company personnel, external contract staff, consultants, hardware, software, licences, property expenses (accommodation, travel, and so on), maintenance contracts environment and operations.
Business Case
Option selected: costs
Business Case
Option selected: cost/benefit analysis
● shows whether the project is forecast to deliver a successful outcome and when
Business Case
a summary
● business case is the single most important document in the project● it should be robust, clear and decisive in its recommendation● the organisation may not be much nearer knowing how the targets identified in
the business case are to be met -> purpose of the project governance report
Project Governance Report
Answered with detail serious questions and describe the future about the Project
Example:
● Why is this project necessary ?● Who will be involved in the management of the project ? ● What will the project deliver ? ● When will it deliver it ? ● How much will it cost ?
Project Governance Report
What is included in the Governance Report :
● Organisation
● Project Plan
Project Governance Report
Organisation
In this part are things like:
● Organisation chart
● Roles and responsibilities
● Communications plan
Project Governance Report
Organisation-Organisation Chart
● Identify the roles in the project and the reporting lines between them
● Persons with appropriate roles are listed there
Project Governance Report
Organisation Chart
Example:
Project Governance Report
Roles and Responsibilities:
● Describe all the roles of the Project
● Describe the respective responsibilities of each one
Project Governance Report
The communications plan will describe:
● what information must be communicated throughout the project and beyond? ● who needs to receive this information? ● what the communication format should be and who should develop or present
it?● when it is needed?
Project Governance Report
The communication plan is split in two parts
● a table, identifying the information needs and audiences
● a list of communication types, with dates or frequencies, by which those
audiences may obtain the information they need.
Project Governance Report
List of communication types:
Project Governance Report
Project plan contains
● Quality plan ● Planning assumptions ● Time schedule ● Resource plan ● Risks ● Project controls
Project Governance Report
Project plan contains is based on four components
● quality management and deliverables● costs (resources and budgets)● timescales● controls
Project Governance Report
Project plan-Quality plan
Describes how the end product will be developed and delivered to an acceptable standard, on time and to budget.
Also contains:
● Deliverables● Responsibilities● Standards
Project Governance Report
Project plan-Quality plan-Deliverables
● Specified the end product● All other deliverables that must be produced● The scope of the project● Describe each one Deliverables● Deliverable needed
Project Governance Report
Project plan-Quality plan-Deliverables
Project Governance Report
Project plan-Quality plan-Deliverables
Project Governance Report
Project plan-Quality plan- Responsibilities
● Describes who will be responsible for which aspects● Not a regurgitation of the roles and responsibilities section● Specifically identifies the things that named individuals must do● Quality management
Project Governance Report
Project plan-Quality plan- Responsibilities
How to ensure quality;
● specified● planned● built● tested● accepted
Project Governance Report
Project plan-Quality plan- Responsibilities:
Contains statements like:
● The project steering group will agree a set of success criteria from which all expressions of quality will be derived.
● The sponsor will approve time, cost and benefit expectations throughout the project.
● The customer representative will approve the user requirements document on behalf of all end users of the key deliverable.
Project Governance Report
Project plan-Quality plan- Standards
● Prescribed standards that must be met● Include documentary or procedural standards for:
○ specifying the outcome
○ designing the outcome
○ building the outcome
○ testing the outcome
○ operating the outcome
○ managing the project
Project Governance Report
Project plan-Planning assumptions
Project Governance Report
Project plan-Time schedule
● Is not a project plan
● Does not show how cost or quality expectations will be met
Project Governance Report
Project plan-Time schedule
Illustration as Gnatt: as flow diagram:
Project Governance Report
Project plan-Resource plan
● How and when the project is likely to incur its costs
Project Governance Report
Project plan-Risk
● Risks identified in the:○ project outline and
○ business case
● Present as risk register
Project Governance Report
Risk register:
Project Governance Report - Project Controls
Used to describe how the project will be kept on track
● Control Cycle● Escalation Management● Change Control● Configuration Control● Quality Control● Risk and issue management
Project Governance Report - Project Controls
Control Cycle - meetings and reporting
● various control mechanisms to ensure the information/communication flow● ensures that corrective actions can be taken if necessary● usually a table is used as a representation
Project Governance Report - Project Controls
Escalation Management
● describes what constitutes a significant issue● how to handle this issues● represented as “escalation conditions”● usually escalation conditions are described for time, cost and benefit margins
Project Governance Report - Project Controls
Escalation Management - Example
Project Governance Report - Project Controls
Escalation Management - Example
Project Governance Report - Project Controls
Escalation Management - Example
Project Governance Report - Project Controls
Change Control
● how are changes defined● how will be dealt with them● divided into
○ Baseline
○ Contingency
○ Process
○ Responsibilities - facilitated by the project manager
Project Governance Report - Project Controls
Change Control - Baseline
● Business case v1.0● Project governance report v1.0● User requirements document v1.0● Solution design document v1.0
Project Governance Report - Project Controls
Change Control - Contingency - Example
● Risk mitigation: 23,300● Change management: 1,000● Approved changes: 52,000
Total: 76,300
Project Governance Report - Project Controls
Change Control - Process
Change requests (as well as arisen problems) consist of four steps
● Change request identification● Change request analysis● Change request impact assessment● Conclusion and decision
Change requests have to be checked against the escalation conditions
Project Governance Report - Project Controls
Configuration Control
How will the project maintain the products it creates?
● Which products are to be subject to control?
● Who owns them?
● Where will the products be held?
● How will back-ups be taken?
● How will security be ensured?
● How will the products be distributed and redistributed?
● How will versions be controlled?
● Which version will constitute the baseline?
● How will checks be made to make sure that all products are where they should be?
Project Governance Report - Project Controls
Quality Control
● Product quality tests○ describes any tests on products
○ should contain a detailed description of the particular test
● Project quality tests○ mostly only on large projects
Project Governance Report - Project Controls
Risk and Issue Management
● how risks and issues will be identified and prioritised● the criteria for assigning ownership● how mitigating actions will be planned● how progress will be monitored and controlled● the process by which contingency funds may be drawn
User Requirements Document
● the customers view of the project● describes the customer needs which the projects outcome must satisfy● Implementation depends on the type of project
○ “If the project has to deliver a computer system, it may contain a list of functional and
non-functional requirements”
○ For a new office building, a graphical depiction can be used
● important basis of the whole project and its products
Solution Design Document
● describes how the customer needs will be fulfilled● Implementation again depends on the type of project
○ Description of the design of a computer system
○ For a new office building, the architects blueprint can be used
Summary
● Initiation stage sets the fundament for a successful project● Unknowns should get resolved● At the end the success criteria should be established● Detailed answers for the questions
○ Why
○ Who
○ What
○ When
○ How