44
METHOD STATEMENT 1.INTRODUCTIO N This Method Statement describes the specific safe

Method Statement

Embed Size (px)

Citation preview

Page 1: Method Statement

METHOD STATEMENT1.INTRODUCTIONThis Method Statement describes the specific safe working methods which will be

Page 2: Method Statement

used by ------------------ to carry out the construction new storage facilities.2.SCOPEThis document covers the scope of work required for the

Page 3: Method Statement

execution of the tank construction. The method statement is in the following sequence as the work will becarried out.

Page 4: Method Statement

Tank specific design and drawings

Construction of new tank foundation

Plate, structural steel and tank component procurement

Page 5: Method Statement

Floor, shell and roof plate fabrication

Installation of new floor plate and double deck roof 

Fire protection system

Page 6: Method Statement

Instrumentation and electrical works

Demolition of tank foundation, floor and roof 

Tank decommissioning

Tank isolation

Page 7: Method Statement

Tank cleaning

Tank conditional inspection survey

Blasting and painting works

Hydro-testing

Calibration

Hook up to existing process

Page 8: Method Statement

line, commissioning and demobilisation

3.REFERENCES

API 650: Welded steel storage tanks for Oil Storage

Page 9: Method Statement

API MPMS 3.1B: Manual of Petroleum Measurement Standards Chapter 3 – Tank Gauging (Section 1B: Standard Practice for

Page 10: Method Statement

Level measurement of LiquidHydrocarbons in Stationery Tanks by Automatic Tank Gauging)Method Statement1 of 17

Page 11: Method Statement
Page 12: Method Statement

 

Recommended Practice 14FZ: Recommended practice for Design and Installation of Electrical Systems for Fixed and Floating

Page 13: Method Statement

Offshore Petroleum Facilities for Unclassified and Class1, Zone 0, Zone 1 and Zone 2 Locations

 NFPA 30: Flammable and Combustible

Page 14: Method Statement

Liquid Code-2000 Edition

BS 8110: Structural use of Concrete in Building4.LIST OF EQUIPMENT

30 ton mobile crane

Page 15: Method Statement

Flat deck/low bed trailer 

Semi automatic welding machine

DC welding machines (400A)

Air compressor 

Sand blasting set

Page 16: Method Statement

Spray painting set

Wheel loader 

Tipper truck 

Mini dumper truck 

Fuel tanker 

Power generating set (30kVA,

Page 17: Method Statement

50kVA, 60kVA, 100kVA)

 NDT Equipment

Man Lifting Equipment (25m Boom height)

Dewatering pumps

Page 18: Method Statement

Pneumatic power winch

Pneumatic air winch5.SITE PERSONNELC o n s t r u c t i on M a n a g e r1 S i t e

Page 19: Method Statement

E n g i n e er 2 H S E O f f i c e r1 Q A / Q C O f f i c e r1 Q A E n g i n ee r 2 Q C I n s p e c to r 2 S i t e

Page 20: Method Statement

S u p e r v i so r 1 P i p e / P la t e W e l d e r s 6Method Statement2 of 17

Page 21: Method Statement

G r i t B l a s t e rs 4 O p e ra t o r s8

Page 22: Method Statement

6.WORK SEQUENCE AND METHOD6.1.Tank Specific Design And DrawingsThe following elements design shall be considered for adequacy in

Page 23: Method Statement

accordance with therelevant codes and standards as may be applicable and any findings communicated to theCOMPANY for review and approval before

Page 24: Method Statement

changes will be effected.

The tank foundation shall be verified in accordance with appendix B of API650:2005 and BS 8110

Page 25: Method Statement

The floor and annular plates shall be verified in accordance with the requirements of clauses 4.4 and 4.5 of API 650:2005

Page 26: Method Statement

The shell plates shall be verified in accordance with the requirements of clauses 4.6of API 650:2005

Roof and other roof accessories shall be verified

Page 27: Method Statement

to meet the requirement of Clause4.10 of API 650:2005

 Nozzles shall be verified to meet the requirement of clauses 4.7.6 for shell and

Page 28: Method Statement

4.8.5for roof of API 650:2005

The piping system shall be verified to meet the requirement of ASME B31.36.2.Plates, Structural Steel And Diesel

Page 29: Method Statement

Storage Tank Components Procurement

Steel plate and sections procured shall be accompanied with their mill certificates

Page 30: Method Statement

Samples shall be taken from the procured materials to confirm that the chemical andmechanical materials conform with the requirement of

Page 31: Method Statement

clause 4 of API 650: 20056.3.Cutting, Forming and FabricationPlate material shall be straight and/or flattened by pressing or rolling audtties

Page 32: Method Statement

 shall bedone before the material is processed in any way.

MarkingTo enable the various

Page 33: Method Statement

fabricated components to be assembled together correctly on site, each part shall be marked with unique numbering system asshowed

Page 34: Method Statement

on the “Approved for Construction” drawings.Method Statement3 of 17

Page 35: Method Statement